1999 PI SYSTEM USERS’ CONFERENCE
1999 PI System Users’ ConferenceMonterey, California
POLIMERI EUROPAAN ENICHEM | UNION CARBIDE VENTURE
SYNAPSIS
![Page 2: 1999 PI System Users’ Conference Monterey, California](https://reader035.fdocuments.us/reader035/viewer/2022062310/5681603f550346895dcf63c0/html5/thumbnails/2.jpg)
arO
1999 PI SYSTEM USERS’ CONFERENCE
Taking SAP to the Factory FloorTaking SAP to the Factory Floor an an
Italian ExperienceItalian Experience
Ing. Carlo Volpones, POLIMERI EUROPA Sig. Roberto Spoladore, SYNAPSIS
![Page 3: 1999 PI System Users’ Conference Monterey, California](https://reader035.fdocuments.us/reader035/viewer/2022062310/5681603f550346895dcf63c0/html5/thumbnails/3.jpg)
arO
1999 PI SYSTEM USERS’ CONFERENCE
Agenda• Company Profile
• Program Opera
• Management and Technology Challenge
• Company Key Decisions
• Implementation Partners
• Manufacturing Implementation
• Implementation Design
• Conclusion
![Page 4: 1999 PI System Users’ Conference Monterey, California](https://reader035.fdocuments.us/reader035/viewer/2022062310/5681603f550346895dcf63c0/html5/thumbnails/4.jpg)
arO
1999 PI SYSTEM USERS’ CONFERENCE
Company Profile
![Page 5: 1999 PI System Users’ Conference Monterey, California](https://reader035.fdocuments.us/reader035/viewer/2022062310/5681603f550346895dcf63c0/html5/thumbnails/5.jpg)
arO
1999 PI SYSTEM USERS’ CONFERENCE
Polimeri Europa s.r.l.
• Formed in April, 1995, Polimeri Europa is a 50:50 Enichem/Union Carbide venture for the development, production, marketing, and sale of polyethylene and olefins in the European market.
Year 1998
• Sales Revenue 1.6 Billion USD
• Total Capacity 1,600 Polyethylene kty 700 Ethylene kty
• Employees 1,571
![Page 6: 1999 PI System Users’ Conference Monterey, California](https://reader035.fdocuments.us/reader035/viewer/2022062310/5681603f550346895dcf63c0/html5/thumbnails/6.jpg)
arO
1999 PI SYSTEM USERS’ CONFERENCE
Polimeri Europa Principal Manufacturing Facilities
Brindisi
Ferrara
Priolo
Dunkerque
Oberhausen
Gela
Ragusa
Eschborn
Milan
![Page 7: 1999 PI System Users’ Conference Monterey, California](https://reader035.fdocuments.us/reader035/viewer/2022062310/5681603f550346895dcf63c0/html5/thumbnails/7.jpg)
arO
1999 PI SYSTEM USERS’ CONFERENCE
Key Investments for the Polimeri Europa Joint-Venture
• Brindisi UNIPOL Project– to take maximum advantage of the product and process
capabilities of UNIPOL technology
• Program Opera– to achieve a substantial business performance improvement
through investment in:• IT architecture and application• Organization / work process redesign• People (skills and training)
![Page 8: 1999 PI System Users’ Conference Monterey, California](https://reader035.fdocuments.us/reader035/viewer/2022062310/5681603f550346895dcf63c0/html5/thumbnails/8.jpg)
arO
1999 PI SYSTEM USERS’ CONFERENCE
Brindisi Project
• Start date 1st January 1995• Completion date 1st September 1997• Technology UCC Gas Phase• Total capacity 400 Polyethylene kty• Production lines 2 lines• Type of products LLDPE-HDPE• Customer satisfaction High Level of Acceptance
• First company implementation of OSI PI3 RTDB systemFirst company implementation of OSI PI3 RTDB system
![Page 9: 1999 PI System Users’ Conference Monterey, California](https://reader035.fdocuments.us/reader035/viewer/2022062310/5681603f550346895dcf63c0/html5/thumbnails/9.jpg)
arO
1999 PI SYSTEM USERS’ CONFERENCE
arO
![Page 10: 1999 PI System Users’ Conference Monterey, California](https://reader035.fdocuments.us/reader035/viewer/2022062310/5681603f550346895dcf63c0/html5/thumbnails/10.jpg)
arO
1999 PI SYSTEM USERS’ CONFERENCE
Why The Word “OPERA”?
• Opera It’s an Italian word known in all the world.
• Opera It belongs to the musical language and reminds “harmony”.
• Opera This word expresses the idea of “working group”.
• Each Opera is one and only.
![Page 11: 1999 PI System Users’ Conference Monterey, California](https://reader035.fdocuments.us/reader035/viewer/2022062310/5681603f550346895dcf63c0/html5/thumbnails/11.jpg)
arO
1999 PI SYSTEM USERS’ CONFERENCE
Program Opera Objectives
• Create Business Value by:• improve customer service• improve efficiency and effectiveness of company operations• improve flexibility and response time to satisfy emerging
business needs
• Using a Program Approach that incorporates:• business process redesign• implementation of a core information system (SAP) and
integrated scientific systems (RTDB)• training and personnel development
![Page 12: 1999 PI System Users’ Conference Monterey, California](https://reader035.fdocuments.us/reader035/viewer/2022062310/5681603f550346895dcf63c0/html5/thumbnails/12.jpg)
arO
1999 PI SYSTEM USERS’ CONFERENCE
Program Scope
Geography
ItalyFrance
Germany
Process Application SolutionSAP R/3 Standard vers. 3.1
FI EISQM CO/CCAPS PMTR HRWM AASD SD SHPIM MMPP-PI LC
Scientific Systems and Niche ApplicationsRTDBLIMSSCMTransportation
Executive
Business Infrastructure
FulfillDemand
BalanceSupply &Demand
CreateDemand
ServiceCustomer
![Page 13: 1999 PI System Users’ Conference Monterey, California](https://reader035.fdocuments.us/reader035/viewer/2022062310/5681603f550346895dcf63c0/html5/thumbnails/13.jpg)
arO
1999 PI SYSTEM USERS’ CONFERENCE
Management and Technology Challenge
![Page 14: 1999 PI System Users’ Conference Monterey, California](https://reader035.fdocuments.us/reader035/viewer/2022062310/5681603f550346895dcf63c0/html5/thumbnails/14.jpg)
arO
1999 PI SYSTEM USERS’ CONFERENCE
Management Challenge Assessment of Current Situation (Starting Point Fall 1996)
• Work Processes
– Complex, Not Well Integrated Across Functions Or Locations.
– Real Time Information Not Available For Rapid Decision Making.
– Require High Levels Of Personal Experience.
– Require Significant Duplication Of Effort And Reentry Of Data.
![Page 15: 1999 PI System Users’ Conference Monterey, California](https://reader035.fdocuments.us/reader035/viewer/2022062310/5681603f550346895dcf63c0/html5/thumbnails/15.jpg)
arO
1999 PI SYSTEM USERS’ CONFERENCE
• Systems
– Slow Response Time and Some Information Not Accurate or Up to Date.
– Little Integration of Applications Between Plant Sites and French and German Affiliates.
– Very Difficult to Modify Applications to Meet Emerging New Needs.
– Limited Access and Experience with Process Control and Data Collection Applications.
Technology Challenge Assessment of Current Situation (Starting Point Fall 1996)
![Page 16: 1999 PI System Users’ Conference Monterey, California](https://reader035.fdocuments.us/reader035/viewer/2022062310/5681603f550346895dcf63c0/html5/thumbnails/16.jpg)
arO
1999 PI SYSTEM USERS’ CONFERENCE
Company Key Decisions
![Page 17: 1999 PI System Users’ Conference Monterey, California](https://reader035.fdocuments.us/reader035/viewer/2022062310/5681603f550346895dcf63c0/html5/thumbnails/17.jpg)
arO
1999 PI SYSTEM USERS’ CONFERENCE
Company Key Decisions
• Implement common work processes throughout Polimeri Europa.
• Utilize integrated business software (SAP) installed without modifications (standard).
• Use of a Managing General Contractor (Ernst & Young) to deliver project results.
• Implement the project as rapidly as possible to minimize business risk.
• Use standard scientific applications at all sites with certified SAP interfaces.
![Page 18: 1999 PI System Users’ Conference Monterey, California](https://reader035.fdocuments.us/reader035/viewer/2022062310/5681603f550346895dcf63c0/html5/thumbnails/18.jpg)
arO
1999 PI SYSTEM USERS’ CONFERENCE
Polimeri WAN
Brindisi
Ferrara
Priolo
Gela
RagusaDunkerque
Eschborn
IT Company Infrastructure
Milan Head Office
Public Network
Router
![Page 19: 1999 PI System Users’ Conference Monterey, California](https://reader035.fdocuments.us/reader035/viewer/2022062310/5681603f550346895dcf63c0/html5/thumbnails/19.jpg)
arO
1999 PI SYSTEM USERS’ CONFERENCE
Business Integration Using New Applications
Distribution centers
Company code
Head office
Customer
Transportorder
Productionorder
Factories
Stock
Local offices
ProfitCenter
Material
WarehousesMessage/EventHandler
Distribution Centers
![Page 20: 1999 PI System Users’ Conference Monterey, California](https://reader035.fdocuments.us/reader035/viewer/2022062310/5681603f550346895dcf63c0/html5/thumbnails/20.jpg)
arO
1999 PI SYSTEM USERS’ CONFERENCE
Definition of Operations Work Processes
HS&EHS&EMaintenanceMaintenance Manufacturing Manufacturing
Sub Processes
• Plant line schedules
• Production
• Quality Control
Sub Processes
• Plan & ScheduleMaintenanceActivities
• Execute MaintenanceActivites
• MaintenanceEngineering
Sub Processes
• EnvironmentalCompliance
• Process Safety
•
Product Safety•
Personnel Safety
• Process Engineering
• Technology Development
• Engineering
Sub Processes
ManufacturingProcess Technology and Engineering
![Page 21: 1999 PI System Users’ Conference Monterey, California](https://reader035.fdocuments.us/reader035/viewer/2022062310/5681603f550346895dcf63c0/html5/thumbnails/21.jpg)
arO
1999 PI SYSTEM USERS’ CONFERENCE
Implementation Partners
![Page 22: 1999 PI System Users’ Conference Monterey, California](https://reader035.fdocuments.us/reader035/viewer/2022062310/5681603f550346895dcf63c0/html5/thumbnails/22.jpg)
arO
1999 PI SYSTEM USERS’ CONFERENCE
Implementation Partners
(MGC)(MGC)
Hewlett PackardHardware and system software
OSI SOFTWARE(Synapsis )
RTDB
Ernst & YoungManaging General Contractor
Polimeri Europa• Head office• 7 plants• many warehouses
(Synapsis)
![Page 23: 1999 PI System Users’ Conference Monterey, California](https://reader035.fdocuments.us/reader035/viewer/2022062310/5681603f550346895dcf63c0/html5/thumbnails/23.jpg)
arO
1999 PI SYSTEM USERS’ CONFERENCE
Manufacturing
Implementation
![Page 24: 1999 PI System Users’ Conference Monterey, California](https://reader035.fdocuments.us/reader035/viewer/2022062310/5681603f550346895dcf63c0/html5/thumbnails/24.jpg)
arO
1999 PI SYSTEM USERS’ CONFERENCE
Polimeri Europa Plant Overview
• Fully integrated plant facilities located at Brindisi and Dunkerque that manufacture both ethylene and polyethylene.
• Other PE sites (Ferrara, Gela, Ragusa, and Priolo) manufacture only polyethylene from purchased raw materials.
• Plants are generally round the clock continuous and batch operations.
• Finished product is packaged and sold to customers in batches.
![Page 25: 1999 PI System Users’ Conference Monterey, California](https://reader035.fdocuments.us/reader035/viewer/2022062310/5681603f550346895dcf63c0/html5/thumbnails/25.jpg)
arO
1999 PI SYSTEM USERS’ CONFERENCE
Overall Considerations for the Implementation
• No duplication of SAP - scientific system data input activities in the Control Room during normal shift operations.
• Warehouse inventory data must be available real time and updated automatically.
• Production Planning is compiled at headquarters with detail execution at the plants.
• Plant operators have one and only one interface for data input.
• Standard solution through the different DCS vendors.
![Page 26: 1999 PI System Users’ Conference Monterey, California](https://reader035.fdocuments.us/reader035/viewer/2022062310/5681603f550346895dcf63c0/html5/thumbnails/26.jpg)
arO
1999 PI SYSTEM USERS’ CONFERENCE
SAP Modules Utilized for theIntegrated Manufacturing Solution• Controlling and financial modules for business decision making.• Manufacturing quality and material management modules for plant operations.
› SAP MM and WM for plant material acquisition and movements
› SAP PP-PI for production planning and production order tracking
› SAP QM for quality management of rawmaterial, packaging, and finished product
› SAP CO and FI for product cost and campaign control
![Page 27: 1999 PI System Users’ Conference Monterey, California](https://reader035.fdocuments.us/reader035/viewer/2022062310/5681603f550346895dcf63c0/html5/thumbnails/27.jpg)
arO
1999 PI SYSTEM USERS’ CONFERENCE
SAP Configuration Design Parameters
• In SAP plants are modeled as batch units.• For costing purposes, batches of finished product are
aggregated into production campaigns.• A plant production campaign is represented in SAP as a
Production Order.• Plants are represented in a simplified form in SAP as
macro operations.• A plant production cycle is divided in logical SAP Phases.
![Page 28: 1999 PI System Users’ Conference Monterey, California](https://reader035.fdocuments.us/reader035/viewer/2022062310/5681603f550346895dcf63c0/html5/thumbnails/28.jpg)
arO
1999 PI SYSTEM USERS’ CONFERENCE
Framework Used in Developing the Integrated Manufacturing Solution Model
• Production managed as campaigns: production quantities calculated of materials consumed and resources utilized for each finished product.
• Economic analysis (cost summaries, and efficiency analysis versus plan) by single campaign and by unit line (on a monthly basis).
• Verification of material and resource availability relative to production orders.
![Page 29: 1999 PI System Users’ Conference Monterey, California](https://reader035.fdocuments.us/reader035/viewer/2022062310/5681603f550346895dcf63c0/html5/thumbnails/29.jpg)
arO
1999 PI SYSTEM USERS’ CONFERENCE
Framework Used in Developing the Integrated Manufacturing Solution Model (cont.)
• Advancement of production interfaced with RTDB.
• Available to Promise (ATP) updated in real time with planned transfers relative to production orders.
• Raw material to finished product lot testing traceability.
• Finished product lot to lot test traceability.
![Page 30: 1999 PI System Users’ Conference Monterey, California](https://reader035.fdocuments.us/reader035/viewer/2022062310/5681603f550346895dcf63c0/html5/thumbnails/30.jpg)
arO
1999 PI SYSTEM USERS’ CONFERENCE
Tracking Production Advancement Using RTDB - SAP Integrated Application Solution
RTDB SAP PP-PI
SAP FISAP MM
Production CampaignLot Traceability Reports
Production Campaign Cost Reports
Finished Product lot to test transfersConsumption (actual and std.) raw material (by lot and non)
Phase Closure
Information from RTDB :.) Finished lot Product to test..) Quantity of Finished product transferred to Silos.) Quantity of Raw materials by lot consumed.) Quantity of Raw materials non lot consumed
WM
QM
![Page 31: 1999 PI System Users’ Conference Monterey, California](https://reader035.fdocuments.us/reader035/viewer/2022062310/5681603f550346895dcf63c0/html5/thumbnails/31.jpg)
arO
1999 PI SYSTEM USERS’ CONFERENCE
Implementation
Design
![Page 32: 1999 PI System Users’ Conference Monterey, California](https://reader035.fdocuments.us/reader035/viewer/2022062310/5681603f550346895dcf63c0/html5/thumbnails/32.jpg)
arO
1999 PI SYSTEM USERS’ CONFERENCE
Implementation Design - Components
SYNAPSIS
• PI 3.2 Real time data historian, Batch Monitor and totalizations
• PS-RLINK PI system gateway to SAP R/3 PP-PI module
• PI-ProcessBook 2.0 Graphical representations and PIBatchView management of:
- Process data (PI) - Process Order (SAP Recipe)
![Page 33: 1999 PI System Users’ Conference Monterey, California](https://reader035.fdocuments.us/reader035/viewer/2022062310/5681603f550346895dcf63c0/html5/thumbnails/33.jpg)
arO
1999 PI SYSTEM USERS’ CONFERENCE
Implementation Design - Infrastructure
Polimeri WAN
Milan Head Office
Public Network
PI ProcessBookPI ProcessBook
PI ProcessBook
PI Home nodePLANT SUITERLINK
DCS
SITE
SAP
SYNAPSIS
![Page 34: 1999 PI System Users’ Conference Monterey, California](https://reader035.fdocuments.us/reader035/viewer/2022062310/5681603f550346895dcf63c0/html5/thumbnails/34.jpg)
arO
1999 PI SYSTEM USERS’ CONFERENCE
Implementation Design - Model
SYNAPSIS
• Process Order Stored in Plant Suite Managed as a PI Batch Unitwith its own PI Tags
• Phase Each phase is a PI Batch Unit with its own PI Tags
• Material(s) Each material is a PI Tag
![Page 35: 1999 PI System Users’ Conference Monterey, California](https://reader035.fdocuments.us/reader035/viewer/2022062310/5681603f550346895dcf63c0/html5/thumbnails/35.jpg)
arO
1999 PI SYSTEM USERS’ CONFERENCE
Implementation Design - Data Sources
SYNAPSIS
Different data sources had to be used:
• DCS Input Real time data collected by standard PI interfaces.
• Manual entry Manul data to be entered by operator
• Unmeasured (Standard) Data to be computed on
the base of recipe standard
![Page 36: 1999 PI System Users’ Conference Monterey, California](https://reader035.fdocuments.us/reader035/viewer/2022062310/5681603f550346895dcf63c0/html5/thumbnails/36.jpg)
arO
1999 PI SYSTEM USERS’ CONFERENCE
Implementation Design - Data Sources solution
SYNAPSIS
Different solutions have been implemented:
• DCS Input Standard PI features such as : - Performance Equation
- Totalizer
• Manual entry A specific ProcessBook display has been
developed using VBA
• Unmeasured (Standard) A specific program has
been developed and integrated using PS-RLINK standard features AS A RESULT: ALL IS IN PI SYSTEM
![Page 37: 1999 PI System Users’ Conference Monterey, California](https://reader035.fdocuments.us/reader035/viewer/2022062310/5681603f550346895dcf63c0/html5/thumbnails/37.jpg)
arO
1999 PI SYSTEM USERS’ CONFERENCE
-> Start and End Phase -> Material Quantity Consumed/ Produced -> Phase ID -> Recipe ID-> Phase confirmation Type (Partial/Finished)
PRIOLO PLANT DETAIL
Reactor
BlenderB
BlenderC
BlenderD
BlenderA
Silos
Priolo PlantReactor -> Duration Phase: ~ 4 hours -> By-product is moved to one Blender every phase confirmationBlender -> 4 Blenders -> Duration Phase: ~ 13 hours -> By-product is moved to ‘Silos’Silos -> Not a real phase: Material transferred to Silos
Priolo Units
Unit Information
SYNAPSIS
![Page 38: 1999 PI System Users’ Conference Monterey, California](https://reader035.fdocuments.us/reader035/viewer/2022062310/5681603f550346895dcf63c0/html5/thumbnails/38.jpg)
arO
1999 PI SYSTEM USERS’ CONFERENCE
RESOURCE AND PHASE - ONE PROCESS ORDER MANY PHASES CONFIRMATIONS
TIME
ORDER
order_pi_statusorder_sap_recipe
0
1
CRID1
PHASE
phase_lot_numberL1 L2 L3 L4
phase_sap_statusStart Partial EndPartial Partial
phase_pi_statusStart EndEnd/Start End/Start End/Start
SYNAPSIS
phase_sap_recipeCRID1 CRID1 CRID1 CRID1 CRID1
![Page 39: 1999 PI System Users’ Conference Monterey, California](https://reader035.fdocuments.us/reader035/viewer/2022062310/5681603f550346895dcf63c0/html5/thumbnails/39.jpg)
arO
1999 PI SYSTEM USERS’ CONFERENCE
SYNAPSIS
PB Display - Overall view
Blenders Details
Reactor Details
![Page 40: 1999 PI System Users’ Conference Monterey, California](https://reader035.fdocuments.us/reader035/viewer/2022062310/5681603f550346895dcf63c0/html5/thumbnails/40.jpg)
arO
1999 PI SYSTEM USERS’ CONFERENCE
SYNAPSIS
PB Display - Reactor
Viewing Lots in Reactor
SAP Process Order Information
PLANT_SUITE
Process InformationP I
![Page 41: 1999 PI System Users’ Conference Monterey, California](https://reader035.fdocuments.us/reader035/viewer/2022062310/5681603f550346895dcf63c0/html5/thumbnails/41.jpg)
arO
1999 PI SYSTEM USERS’ CONFERENCE
SYNAPSIS
PB Display - Reactor
New Campaign Selection Window
Lot Details Window
![Page 42: 1999 PI System Users’ Conference Monterey, California](https://reader035.fdocuments.us/reader035/viewer/2022062310/5681603f550346895dcf63c0/html5/thumbnails/42.jpg)
arO
1999 PI SYSTEM USERS’ CONFERENCE
SYNAPSIS
PB Display - Blender
Process InformationP I
Moving Lot across Blender and Silo
![Page 43: 1999 PI System Users’ Conference Monterey, California](https://reader035.fdocuments.us/reader035/viewer/2022062310/5681603f550346895dcf63c0/html5/thumbnails/43.jpg)
arO
1999 PI SYSTEM USERS’ CONFERENCE
SYNAPSIS
PB Display - Silos
Viewing lots in Silo (Selected Process Order)
P I
SAP Process Order Selection
PLANT_SUITE
![Page 44: 1999 PI System Users’ Conference Monterey, California](https://reader035.fdocuments.us/reader035/viewer/2022062310/5681603f550346895dcf63c0/html5/thumbnails/44.jpg)
arO
1999 PI SYSTEM USERS’ CONFERENCE
Conclusion
![Page 45: 1999 PI System Users’ Conference Monterey, California](https://reader035.fdocuments.us/reader035/viewer/2022062310/5681603f550346895dcf63c0/html5/thumbnails/45.jpg)
arO
1999 PI SYSTEM USERS’ CONFERENCE
PE Project Opera “First’s”
• SAP electronic connection to Italian banks.
• Use of SAP HR and TR modules.
• Third party facility management of client server environment.
• Integration of information systems from DCS through PI3 to SAP business reporting systems.
![Page 46: 1999 PI System Users’ Conference Monterey, California](https://reader035.fdocuments.us/reader035/viewer/2022062310/5681603f550346895dcf63c0/html5/thumbnails/46.jpg)
arO
1999 PI SYSTEM USERS’ CONFERENCE
Closing Observations
• SAP and PI3 are technology tools that provide significant productivity improvement opportunities on their own but are not the complete solution.
• The real breakthrough was the integration that came from committed and creative process sponsors and technologists who insisted on a seamless flow of information from the process unit to business management.
• The result of direct hands on end-user involvment made certain that an integrated solution eliminated duplication of data input and aimed at reduced overall operating costs.