1876 Drainage Study - Lee & Associates
Transcript of 1876 Drainage Study - Lee & Associates
PRELIMINARY
DRAINAGE STUDY For
34th & J Residences
3402 J St.
San Diego, CA 92102 A.P.N 545-250-08
Prepared By:
Kenneth J. Discenza, P.E.
Site Design Associates, Inc.
1016 Broadway, Suite A
El Cajon, CA 92021
619-442-8467
September 12, 2011
J-1876
TABLE OF CONTENTS
1. INTRODUCTION............................................................................................................... 1
2. VICINITY MAP.................................................................................................................. 3
3. RATIONAL METHOD ...................................................................................................... 4
4. HYDROLOGIC RESULTS................................................................................................ 9
5. DETENTION REQUIREMENTS ................................................................................... 11
6. CONCLUSION.................................................................................................................. 12
7. DECLARATION OF RESPONSIBLE CHARGE......................................................... 13
FIGURES
FIGURE 1 - OVERLAY OF THE SOIL RUNOFF POTENTIAL MAP ON THE PROJECT SITE...................... 6
FIGURE 2 - SIX-HOUR PRECIPITATION FOR 100-YEAR STORM FREQUENCY ................................... 7
FIGURE 3 - 24-HOUR PRECIPITATION FOR 100-YEAR STORM FREQUENCY ..................................... 8
TABLES
TABLE 1 - RUNOFF COEFFICIENTS, MAXIMUM OVERLAND FLOW LENGTHS & INITIAL TC ............. 5
TABLE 2: SUMMARY OF PRE-PROJECT PEAK DISCHARGE RATES.............................................. 9
TABLE 3: IMPERVIOUS AREA PERCENTAGES............................................................................. 10
TABLE 4: SUMMARY OF POST-PROJECT PEAK DISCHARGE RATES.......................................... 10
APPENDICES
Appendix A: Pre-Project Drainage Map
Appendix B: Post-Project Drainage Map
Site Design Associates, Inc.
34th & J Residences Page 1 J-1876 July 25, 2011
1. INTRODUCTION
This drainage report presents the pre and post-project condition hydrologic analyses for the
proposed 34th & J Residences project (hereafter referred to as project). The project is located at
3402 J St., in the City of San Diego, County of San Diego. The drainage area associated with the
proposed project and adjacent off-site slopes is approximately 0.91 acres. See the Vicinity Map,
located in Section 2 of this report, for the approximate location of the project.
Currently, there is one home constructed on the western portion of the lot, a large asphalt driveway,
and a separate asphalt area on the northern boundary of the site. The remainder of the lot is
covered with annual grasses and a few large trees. Stormwater runoff sheet drains in a westerly
direction and eventually flows west down J St. From there it enters a curb inlet which empties
directly into Chollas Creek, a concrete-lined channel.
The land use of the site is currently designated as residential. The proposed project includes the
construction of 12 2-story condominium homes, a concrete driveway, 27 parking spaces (including
2 per garage and 3 guest spaces), and associated walks and landscaping. The storm drain
improvements for the post-project condition consist of inlets and pipes throughout the site to collect
runoff from roofs and landscaped areas. The inlets within the driveway will include filtration
devices to treat the water before it gets discharged to the street and then to Chollas Creek. Off-site
run-on from the 0.11 acres to the east of the site will be collected in a concrete brow ditch and
discharged along with the on-site runoff. Run-on is expected to be minimal as the drainage area is
quite small and is heavily vegetated with ice plant.
The majority of run-off will flow to an underground detention basin and then be released at the pre-
project flow rate to a bioretention area for further treatment. Inlets in the northwest and southwest
corners of the site discharge directly to the bioretention area (see the Post-Project Drainage Map in
Appendix B for details). All runoff will overflow from the bioretention area through a curb outlet
onto 34th street, and will flow down J St to an existing inlet and then to Chollas Creek as it
currently does.
Site Design Associates, Inc.
34th & J Residences Page 2 J-1876 July 25, 2011
The western portion of the driveway slopes steeply to 34th St. The runoff from this portion will be
collected by a trench drain at the end of the driveway. The trench drain will slope north and
drainage will flow into the bioretention area for treatment before being released through the curb
outlet.
The City of San Diego Stormwater Standards, dated January 14, 2011 conforms to the County of
San Diego Standard Urban Storm Water Mitigation Plan (herein referred to as SUSMP), which
requires that all Priority Development Projects must be designed so that runoff rates and durations
are controlled to maintain or reduce pre-project downstream erosion conditions and protect stream
habitat. All post-project flows will be treated and managed per the SUSMP.
Final inlet sizing and hydraulic calculations for the proposed storm drain system will take place
during final engineering of this project, and are not included in this report.
Site Design Associates, Inc.
34th & J Residences Page 3 J-1876 July 25, 2011
2. VICINITY MAP
Site Design Associates, Inc.
34th & J Residences Page 4 J-1876 July 25, 2011
3. RATIONAL METHOD
The watershed is relatively small; therefore the rational method (RM) is selected to calculate
runoff.
Q = CIA
Where,
Q = Peak Rate of Flow (cfs)
C = Runoff Coefficient
I = Average rainfall intensity (in/hr)
A = Drainage Area (acres)
The soil runoff potential for this site is determined by overlaying the site on the Soil Runoff
Potential Map, published by the County of San Diego, DPW. The Soil Runoff Potential Overlay
Map is shown in Figure 1. Soil Group ‘D’ and undetermined soils are present near this site. Soil
group ‘D’ is conservatively chosen for the purpose of calculations in this report as the map shows
the soil type to be unknown.
The storm frequency chosen for design purposes this study has a 100-year recurrence interval. The
six-hour anticipated precipitation for the project site subject to the design storm frequency, 6P , is
shown in Figure 2. The twenty-four hour anticipated precipitation for the project site subjected to
the design storm frequency; 24P is shown in Figure 3.
6P = 2.5 inches
24P = 4.0 inches
6P is in the range of 45% to 65% (62.5%) of 24P and therefore needs no adjustment.
The time of concentration for on-site basin, cT , is determined from the following formula [1].
3
)1.1(8.1S
DCTc−
=
Where,
cT = Time of Concentration in hours ( cT ≥ 5 min.)
D = Watercourse Distance (ft.)
Site Design Associates, Inc.
34th & J Residences Page 5 J-1876 July 25, 2011
S = Slope (%)
C = Runoff Coefficient
The average rainfall intensity is calculated from the following equation (San Diego County
Hydrology Manual, June 2003). 645.0
644.7 −××= DPI
Where,
I = Rainfall Intensity (in/hr)
6P = Six hour precipitation (inches)
D = Duration (min.)
Time of concentration ( cT ) is composed of two components: The initial time of concentration ( iT ),
and the travel time ( tT ).
The maximum overland flow length ( ML ) is used from Table 1 in calculating the initial time of
concentration.
Table 1 Runoff Coefficients, Maximum Overland Flow Lengths & Initial Tc
Site Design Associates, Inc.
34th & J Residences Page 6 J-1876 July 25, 2011
Figure 1 - Overlay of the Soil Runoff Potential Map on the Project Site
PROJECT SITE
SOIL GROUP
Site Design Associates, Inc.
34th & J Residences Page 7 J-1876 July 25, 2011
Figure 2 - Six-Hour Precipitation for 100-Year Storm Frequency
PROJECT SITE
P6 = 2.5 INCHES
Site Design Associates, Inc.
34th & J Residences Page 8 J-1876 July 25, 2011
Figure 3 - 24-Hour Precipitation for 100-Year Storm Frequency
PROJECT SITE
P24 = 4.0 INCHES
Site Design Associates, Inc.
34th & J Residences Page 9 J-1876 July 25, 2011
4. HYDROLOGIC RESULTS
The 100-year, 6-hour peak flow rates for the pre-project can be found in Table 2. Watershed
boundaries and drainage areas can be found on the, “Pre-Project Drainage Map,” located in
Appendix A. Area A represents all on-site runoff while Area B represents the small area of off-site
run-on. The C-values and initial times of concentration for both areas were taken from Table 1
based on impervious percentage.
Area B is entirely pervious and is therefore given a C-value of 0.35. But due to its steep slope and
short travel distance of 38 ft., the Tc is shown as the minimum of 5 minutes.
Area A has approximately 10,000 sf of impervious area of the total 34,970 sf. This gives an overall
impervious percentage of 28.7%, so the values in Table 2 were interpolated from the Table 1 values
listed under the 25% and 30% impervious.
There is no existing stormwater conveyance system on site, and therefore all existing drainage is
sheet flow. So the given Tc’s are comprised only of Ti as Tt = 0
Table 2: Summary of Pre-Project Peak Discharge Rates
The 100-year, 6-hour peak flow rates for the post-project can be found in Table 4. The outline of
Area B remains the same as do its hydraulic characteristics. The overall outline of Area A remains
the same but it is broken into three subareas A1, A2, and A3 as shown on the Post-Project Drainage
Map in Appendix B. Area A1 represents the majority of the site which will drain to the proposed
detention structure before draining to the bioretention area for treatment. Area A2 represents the
area draining directly to the bioretention area. And Area A3 represents the areas that will drain
directly to 34th St., the majority of which is part of the expanded right-of-way.
The C-values for all three subareas were again interpolated from Table 1 based on impervious
Site Design Associates, Inc.
34th & J Residences Page 10 J-1876 July 25, 2011
percentage. The breakdown of impervious percentages of each subarea is shown in Table 3.
Table 3: Impervious Area Percentages
In this case, Table 1 does not apply for the initial times of concentration as all of the initial travel
distances are shorter then the maximum (LM) given by the table. Therefore, Formula 1 (given in
section 3) was used to calculate Ti. In each case the Ti was less then the minimum of 5 min. and
therefore 5 min. was used in the calculation of the intensity (I) as described in section 3.3 of the San
Diego County Hydrology Manual. The Tt for area A1 was calculated from the travel time through
250 ft of pipe length, upstream of the detention structure, at a velocity of 2.5 ft/s. This gives a total
travel time off 100 sec. or 1.67 min.
Table 4: Summary of Post-Project Peak Discharge Rates
Site Design Associates, Inc.
34th & J Residences Page 11 J-1876 July 25, 2011
5. DETENTION REQUIREMENTS
The on-site 100-year pre-project peak flow rate is 2.01 cfs. The on-site 100-year post-project peak
flow rate totals approximately 3.31 cfs. Therefore, detention will be required for this storm event.
The project proposes an on-site, underground detention facility plus storage within the bioretention
area which will detain the post-project flows back to pre-project flow rates. The preliminary
storage volume needed to meet this requirement is approximately 1600 sq-ft. Details for the
detention basin will be completed with the final design.
Site Design Associates, Inc.
34th & J Residences Page 12 J-1876 July 25, 2011
6. CONCLUSION
This drainage report presents the 100-year, 6-hour pre and post-project hydrologic analyses for the
34th & J Residences project. Off-site flows are conveyed through the project site and are
discharged in the same location as they were in the pre-project condition. On-site runoff from the
proposed project will be detained, treated as necessary, discharged to the street and ultimately
drains into Chollas Creek.
The pre-project condition 100-year, 6-hour peak runoff rate on-site is 2.01 cfs. The post-project
condition 100-year, 6-hour peak runoff rate on-site is 3.31 cfs. Therefore, detention is required for
this storm event. The preliminary storage volume required to detain this event is 1,600 sq-ft.
Details for the detention basin will be included with the final grading plan design.
Inlet sizing and hydraulic calculations for the proposed storm drain system will take place during
final engineering of this project.
All post-project flows will be treated per the SUSMP, and will be addressed in a separate report.
Site Design Associates, Inc.
34th & J Residences Page 13 J-1876 July 25, 2011
7. DECLARATION OF RESPONSIBLE CHARGE
I, hereby declare that I am the engineer of work for this Drainage Report, that I have exercised
responsible charge over the design of the project with respect to this study as defined in section
6703 of the Business and Professions Code, and that the design is consistent with current standards.
I understand that the check of project drawings specifications, studies and reports by the City of
San Diego is confined to a review only and does not relieve me, as engineer in responsible charge,
of my responsibilities for project design.
Kenneth J. Discenza RCE 29930 Expires 06/30/13 Date
Site Design Associates, Inc.
34th & J Residences Page 14 J-1876 July 25, 2011
APPENDIX A
Pre-Project Drainage Map
Site Design Associates, Inc.
34th & J Residences Page 15 J-1876 July 25, 2011
APPENDIX B
Post-Project Drainage Map