Transcript of 165th St. Improvement Project Hugo City Council Meeting March 17, 2014.
Pavement rehabilitation projectPavement rehabilitation project
Neighborhood Meeting held November 14, 2013Neighborhood Meeting held November 14, 2013
Public Hearing held February 3, 2014Public Hearing held February 3, 2014
Neighborhood Meeting held February 24, 2014Neighborhood Meeting held February 24, 2014
BackgroundBackground
Mill/overlay existing pavement Mill/overlay existing pavement – Approximately 7-inches of pavementApproximately 7-inches of pavement– Mill top 2-3 inches and place new pavementMill top 2-3 inches and place new pavement
Culvert replacement – IngersollCulvert replacement – Ingersoll
Minor drainage improvementsMinor drainage improvements
Review roadway striping (no-passing zones)Review roadway striping (no-passing zones)
Proposed ImprovementsProposed Improvements
Speed limitsSpeed limits– City Council authorized speed study (MnDot) Mar 3, 2014City Council authorized speed study (MnDot) Mar 3, 2014– Review 165Review 165thth/Ingersoll curve advisory speed /Ingersoll curve advisory speed
165165thth/Ingersoll intersection realignment/Ingersoll intersection realignment– Traffic data/resident feedback not supportive Traffic data/resident feedback not supportive – Not recommended with projectNot recommended with project
Roadway wideningRoadway widening– Costs/impacts reviewed and discussedCosts/impacts reviewed and discussed– Not recommended with projectNot recommended with project
Other Project ComponentsOther Project Components
Mill/overlay cost estimate:Mill/overlay cost estimate: $1,200,000$1,200,000
– AssessmentsAssessments $99,000$99,000– City state-aid road fundsCity state-aid road funds $1,101,000$1,101,000
Assessments - $1,800 per unitAssessments - $1,800 per unit
Crack fill/seal coat in 2-4 yearsCrack fill/seal coat in 2-4 years
Project Costs/Financing Project Costs/Financing
Project ScheduleProject Schedule
Neighborhood meetingNeighborhood meeting Nov 14, 2013Nov 14, 2013
City Council updateCity Council update Nov 18, 2013Nov 18, 2013
Public Hearing (held and closed)Public Hearing (held and closed) Feb 3, 2014Feb 3, 2014
Neighborhood meetingNeighborhood meeting Feb 24, 2014Feb 24, 2014
Council consider Ordering ProjectCouncil consider Ordering Project March 17, March 17, 20142014
Plan/Specification PreparationPlan/Specification Preparation Mar-Apr, 2014Mar-Apr, 2014
Neighborhood Open House plansNeighborhood Open House plans April 2014April 2014
Project BiddingProject Bidding May 2014May 2014
Award Construction ContractAward Construction Contract May-June 2014May-June 2014
Construction Construction June-Sept 2014June-Sept 2014
Assessment HearingAssessment Hearing Sept 2014Sept 2014
Next Steps Next Steps
City Council consider Resolution Ordering ProjectCity Council consider Resolution Ordering Project– Mill/overlay projectMill/overlay project– Do not include 165Do not include 165thth/Ingersoll realignment/Ingersoll realignment– Do not include roadway wideningDo not include roadway widening
City Assessment Policy City Assessment Policy
Rural Res. mill/overlayRural Res. mill/overlay $1,800/unit$1,800/unit– Direct frontageDirect frontage
– AccessAccess
Corner lots proratedCorner lots prorated
Subdividable lotsSubdividable lots– Multiple unit assessmentMultiple unit assessment
– Zoning classificationZoning classification
– Wetlands/existing buildingsWetlands/existing buildings
0.5 unit0.5 unit
0.5 unit0.5 unit
165165thth Street Street
Har
row
Ave
.H
arro
w A
ve.
No improvementsNo improvements– Leave the roadway as-isLeave the roadway as-is– No culvert replacementNo culvert replacement– Review 165Review 165thth/Ingersoll curve (signage/speed limit)/Ingersoll curve (signage/speed limit)
Mill/OverlayMill/Overlay
Full ReconstructionFull Reconstruction
Project OptionsProject Options
Mill existing pavement Mill existing pavement – Approximately 7-inches of pavementApproximately 7-inches of pavement– Mill top 2-3 inches and place new pavementMill top 2-3 inches and place new pavement– Remove pavement within 165Remove pavement within 165thth/Ingersoll curve/Ingersoll curve
Culvert replacement – IngersollCulvert replacement – IngersollMinor drainage improvementsMinor drainage improvements
Expect 15 years of pavement lifeExpect 15 years of pavement life
Mill and Overlay Mill and Overlay