165440914-35331506-Pnms-Engineering-Manual

73
ROI-S04188-053E 030808 P ASOLINK N ETWORK M ANAGEMENT S YSTEM Engineering M anua l (PASOLINK Version) NEC Corporation Copyright © 2003

Transcript of 165440914-35331506-Pnms-Engineering-Manual

  • ROI-S04188-053E 030808

    P ASOLINK N ETWORK M ANAGEMENT S YSTEM

    Engineering Manual(PASOLINK Version)

    NEC CorporationCopyright 2003

  • ROI-S04188

    Restricted Right Legends. All rights are reserved. No part of this document may be copied, reproduced, or translated to another language without the prior written consent of NEC Corporation. The information contained in this material is subject to change without notice.

    Copyright Notices. Copyright 2003 NEC Corporation, all right reserved.

    Reproduction, adaptation, or translation of this material without prior written permission is prohibited, expected as allowed under the copyright laws.

  • ROI-S04188

    - i -

    CONTENTS 1. INTRODUCTION .......................................................................................................................1

    2. SYSTEM OVERVIEW ...............................................................................................................2

    3. SYSTEM COMPONENTS .........................................................................................................3 3.1 PNMS-CENTRAL SITE COMPUTER SYSTEM .............................................................................3 3.2 PNMT - PASOLINK NETWORK MANAGEMENT TERMINAL ........................................................3 3.3 PMC- PASOLINK MANAGEMENT CARD..................................................................................3

    4. PHYSICAL INTERFACE............................................................................................................8 4.1 PNMS ..................................................................................................................................8 4.2 PNMT...................................................................................................................................8 4.3 PM CARD..............................................................................................................................9

    5. PNMS COMMUNICATION INTERAFCE.................................................................................11

    6. NETWORK SIZING RULE .....................................................................................................12

    7. PNMS IP ADDRESSING.........................................................................................................14 7.1 SIMPLE TRUNK LINE NETWORK (SERIAL INTERFACE) ..............................................................14 7.2 SIMPLE TRUNK LINE NETWORK (LAN INTERFACE)..................................................................16 7.3 SIMPLE TRUNK LINE NETWORK (THROUGH IP NETWORK) ........................................................19 7.4 MULTI SUB-BRANCH NETWORK .............................................................................................20 7.5 PNMS IP ADDRESSING SUMMARY .......................................................................................23 7.6 IP ADDRESS REQUIREMENT FOR CUSTOMER .........................................................................23

    8. INTEROPERABILITY WITH OTHER NETWORK....................................................................24 8.1 CONNECTION AVAILABILITY ...................................................................................................24

    9.TYPICAL CONFIGURATION....................................................................................................25 9.1 POINT TO POINT CONNECTION...............................................................................................25 9.2 POINT TO MULTI-POINT CONNECTION ....................................................................................27 9.3 MULTI-CLUSTER NETWORK (1) -DEDICATED LEASED LINE (SERIAL INTERFACE)-......................27 9.4 MULTI-CLUSTER NETWORK (2) DEDICATED LEASED LINE (LAN INTERFACE)- .......................28 9.5 MULTI-CLUSTER NETWORK (3) PSTN (SERIAL INTERFACE)-.................................................28 9.6 MULTI-CLUSTER NETWORK (4) PSTN (LAN INTERFACE)- ....................................................29 9.7 MULTI-CLUSTER NETWORK (5) IP NETWORK (LAN INTERFACE)- .........................................29 9.8 CPM REDUCTION SOLUTION.................................................................................................30

    10. PNMS CONFIGURATION.....................................................................................................33 10.1 COLD STAND-BY PNMS PRINCIPLE .....................................................................................33 10.2. BACK UP PNMS DATA (UNIX VERSION ONLY) ....................................................................33 10.3 PARALLEL PNMS ...............................................................................................................33 10.4 HIERARCHICAL PNMS CONFIGURATION ...............................................................................35

    11. NETWORK CONFIGURATION WORK..................................................................................37 11.1 PNMS FOR WINDOWS ........................................................................................................37 11.2 PNMS FOR UNIX...............................................................................................................45

    12. RELATED EQUIPMENT FOR PNMS ..................................................................................53 12.1 HYB CONVERTER...............................................................................................................53 12.2. MANAGEMENT INTERFACE UNIT (MIU) ................................................................................54 12.3 PNMS CABLE...................................................................................................................55

  • ROI-S04188

    - ii -

    -Abbreviations-

    DCN Digital Communication Network DEM Demodulator CONV Converter CPM Central PM Card DSC Digital Service Channel HDLC High Level Data Link Control HYB Hybrid IDU Indoor Unit

    INTFC Interface I/O Input/Output IP Internet Protocol LAN Local Area Network LCT Local Craft Terminal MIB Management Information Base MIU Management Interface Unit MSC Mobile Switching Center MUX Multiplexer NE Network Element NRM Normal Response Mode ODU Outdoor Unit PMC PASOLINK Management Card PNMS PASOLINK Network Management System PNMT PASOLINK Network Management Terminal PPP Point to Point Protocol PS Power Supply PSTN Public Switched Telephone Network RPM Remote PM Card TX Receive SCPM Sub-Central PM Card SNMP Simple Network Management Protocol SV Supervisory TFTP Trivial File Transfer Protocol TX Transmit SC Service Channel SV Supervisory SW Switch UDP User Datagram Protocol

  • ROI-S04188

    - 1 -

    1. INTRODUCTION This document is developed as a guideline to help to ensure a high degree of accuracy, completeness and uniformity in the system design of a PNMS (PASOLINK Network Management System).

    NECs PASOLINK system can be remotely monitored and controlled by the optional PNMT (PASOLINK Network Management Terminal) and the PNMS*.

    In order to use these systems, each IDU needs to be equipped with the optional PMC (PASOLINK Management Card). The PNMT software is installed in the Windows 98/NT/2000/XP based portable PC and connected to SV (marked as LA) port at 19.2kbps asynchronous mode. PNMT can login to a PMC and monitor and control any PASOLINK remotely in the network. Therefore the PNMT is used mainly for maintenance purpose. For continuous network monitoring, PNMS is required. All PASOLINKs under the PNMS are always accessible.

    To facilitate the system design, this guide describes the PNMS and its components, with emphasis on the capability of each component and the connections that makes the communication of network management system possible. It is also includes the procedure for PASOLINK network system design, the architecture, the interpretation of a radio network to the system, determination of the communication paths, and consideration of system expansion. In addition, this guide gives some examples of System design, the drawings for cabling of components and the PMC (PASOLINK Management Card) naming and addressing scheme are the topics of relating to the detailed PNMS system configuration.

    *PNMS and PNMT is not mandatory requirement s for the operation of PASOLINK network.

  • ROI-S04188

    - 2 -

    2. SYSTEM OVERVIEW NEC designed PASOLINK Network Management System (PNMS), which enables remote monitoring and control of a radio network. The NEC PNMS is a sophisticated supervisory tool for transmission equipment and allows operator to perform remote system monitor alarms, control NE configuration parameters and display event logging and performance data in either UNIX or Microsoft Windows platform.

    Figure 2.1 shows a typical PNMS application. The system consists of a central computer (PNMS Computer) and a number of remote data processing nodes called PM card. It supervises and controls PASOLINK transmission equipments.

    In the following sections the functions and the usage of each component are described in more detail.

    PNMSPNMT

    IDU

    RS-232C/V.11, 19.2kbpsorLAN(10Base-T)

    RS-232C,19.2kbps

    Digital Service Channel, 9.6kbps

    PM CARD

    Operation Center

    Concept of NMS for PASOLINKConcept of NMS for PASOLINK

    Figure 2-1 Typical PNMS Application

  • ROI-S04188

    - 3 -

    3. SYSTEM COMPONENTS

    3.1 PNMS-Central Site Computer System

    The Central Site Computer is the central operator interface and database, from which system operators manage the PASOLINK network. It receives data from the network via PM Card, stores it, and displays it to the operator in a variety of formats. It accepts command request from the operators and sends them to the on-site equipment for execution. Two types of PNMS can be proposed in accordance with Customers Network size. One is PNMS on Windows NT/2000/XP (supporting up to 500/1,000NEs) and the other is PNMS on UNIX OS (supporting up to 10,000NEs).

    3.2 PNMT - PASOLINK Network Management Terminal

    The PNMT (PASOLINK Network Management Terminal) is a portable computer fitted with NEC's PMNT software, which is used, as an on-site maintenance tool by technicians. It connects directly to the LA port of PASOLINK to upgrade the configuration and software. It is also used to provide local/remote data display and control capabilities similar to those of PNMS.

    The PNMT function can also be run on the PNMS to provide configuration and application software upgrade for PM Card from a central point.

    The PNMT runs in the Windows 95/98/NT/2000/XP environment and makes extensive use of the user friendly Windows Graphical User Interface (GUI). It cannot only interrogate individual PMCs but also monitors the network (subnetwork). It means that the PNMT user can make connections to remote PMC from any node within a PASOLINK subnetwork. A PASOLINK subnetwork is defined as a collection of PMC nodes headed by Central PM CARD. Sub PM Card and Remote PM Card nodes are other node types, which can be part of a PASOLINK subnetwork. This PASOLINK subnetwork is called PASOLINK CPM Cluster in later section. Note that the PNMT is an optional component of the PNMS system.

    3.3 PMC- PASOLINK Management Card

    PM Cards are located at each site in the monitored network to collect alarm and status information from PASOLINK and to control that equipment in response to commands from the central site operator. The PMC primary tasks are to control and acquire data from PASOLINK at remote location and transfer this data back to the central site. The PM card is designed as plug-in modules.

    3.3.1 SNMP Agent Function - PM Cards is functioned as a SNMP agent, which detects alarm and status changes in

    monitored equipment, and sends of change notifications to PNMS

    - PM Card retains the MIB data and transmit a response to SNMP GET commands from PNMS and PNMT.

    - Execution of SNMP SET message commands received from PNMS/PNMT and transmit a control command to the alarm control portion (ALM CONT) in the IDU.

  • ROI-S04188

    - 4 -

    3.3.2 Collecting Performance Monitor Data - Performance measurement is equivalent to ITU-T G.826 standard.*

    * The measurement is by the total value of performance monitoring data of RF portion, not the performance monitoring data of every 2MB traffic as stated in ITU-T G.826.

    - The following performance parameters are measured.

    - Erred Second Ratio (ESR) - Severely Erred Second Ratio (SESR) - Unavailable Seconds Ratio (UASR) - Background Block Error Ratio (BBER)

    - Stored period in PM Card

    There are two types of performance data files, one is every 15 minutes data file and the other is every day data file.

    PASOLINK : per 15 minutes data : 7 days per day data : 7 days

    - Performance Monitor file format

    Performance monitor file is Binary format in PM Card (This file is stored in PNMS/PNMT as ASCII format.). It can be converted to the desirable format by the customer.

    3.3.3 Collecting Event Log Data - Hold event log of changed MIB data. The following events are logged.

    - Status change - Alarm occurrence - Alarm recovery - Control initiation - Parameter change

    - Up to 300 event logs are stored. (The old event logs will be erased as the new event is logged.)

    - Event log file format

    Events log file is ASCII format. It can be converted to the desirable format by the customer.

  • ROI-S04188

    - 5 -

    3.3.4 Configuration File - Hold information of PASOLINK logical network. There are three kinds of file as follows.

    (1) ME Configuration file : Common file

    - Setting Auxiliary input and output

    - Threshold value of Performance Monitor data

    (2) System Configuration file : As per PM card

    - NE name and PM Card type

    - IP address of each port of PM card, Communication speed

    - Opposite IP address

    (3) Network Configuration file : As per PM card

    - Sub network name

    - IP address and PM Card type in the Sub network

    3.3.5 PMC Operating Modes Depending on the size, a network can normally be divided into a number of sub-networks. To distribute the traffic load we normally define one of the PMC as master and the rest as slaves through discrete design. As introduced in above, we also call a master a Central PMC (CPM), a sub-master a Sub-Central PMC (SCPM) and similarly, a slave a Remote PMC (RPM) as described in Figure 3.1.

    CPM CPM

    SCPM SCPM

    SCPM SCPM

    SCPM

    RPM RPM

    RPMRPM

    RPM

    RPM

    RPMSCPM

    SCPM

    RPM

    Figure 3.1 PNMS NETWORK IMAGE

    PNMS-CPM subnetwork

    CPM clusterSubnetwork

    PNMS network

    CPM

    RPM

    RPM

    The Roles of CPM, SCPM and RPM and their rule are explained, 1. Basic function of PMC, 2. Sizing rule of PMC, 3. Adoption Criteria of SCPM, and 4. Positioning of SCPM

  • ROI-S04188

    - 6 -

    1. Basic function of PMC

    The PM Cards (PMC) operational mode is based on Master/Slave polling concept. The network consists of a Central site PM Card (CPM), a possibly Sub-central site PMC (SCPM) and a Remote Site PMC (RPM) installed with an individual software functioning as CPM, SCPM and RPM.

    Even though there is no difference in the hardware design, the PMC will be playing different roles according to the installed software in a network management system as follows;

    (1) Master mode (CPM, the head of CPM Cluster):

    Master function of SCPMs/RPMs under it Gateway function between PNMS and SCPMs/RPMs and routing the messages from

    PNMS to SCPMs/RPMs and back.

    The CPM is a data acquisition and control unit, which processes and then transfers all the physical information of equipment. which is directly connected to the CPM. In addition, CPM is connected to PNMS via a dedicated serial communications link or LAN interface, and passes messages received from SCPM/RPMs to the PNMS for display.

    (2) Sub-Master mode (Sub-Central PMC, SCPM): the head of Subnetwork

    Master function of RPMs under it Gateway function between CPM and RPM and routing the messages from CPM to

    RPM and back.

    SCPM is a data acquisition and control unit which processes and then transfers all the physical information of equipment which is directly connected to the SCPM. This function is the same as that of RPM.(Slave Mode).

    (3) Slave Mode (RPM):

    RPM is a data acquisition and control unit. It monitors and controls equipment at some remote location. Its prime task is to monitor and control and transfer data back to the central site.

    2. Sizing Rule of PMC

    The sizing restriction of PMC is specified as follows:

    (1) CPM-RPM Configuration:

    In the case of CPM-RPM configuration, one CPM can handle up to13 RPM(s). To increase the number of RPM to more than 14, another CPM is required.

    One PNMS can handle up to 32 CPMs. (The detailed network sizing rule is described in SECTION 6.)

    Therefore in case of regional PNMS-CPM-RPM configuration, one PNMS can handle max. 416 RPM(s) (32CPMsX13RPMs=416).

    (2) CPM-SCPM-RPM Configuration:

    In case more than 416 RPM(s) are required to be handled by one PNMS, SCPM is used.

    One SCPM can handle up to 13RPM (S)

    One CPM can handle up to 31 or 30 SCPM(s). (Refer section 6)

  • ROI-S04188

    - 7 -

    Therefore, if SCPM is used, the number of RPM which can be handled by one PNMS is increased more than 416 RPMs.

    As a rule of thumb, SCPM is used in order to increase the network size that can be supervised by PNMS.

    By using the SCPM, one CPM associated with 31 SCPMs can handle up to 416 NEs (SCPMs and RPMs). This can result in a network configuration with the optimal number of CPM(s) within one PNMS coverage.

    (3) Adoption Criteria SCPM

    As basic rule, if the number of RPM becomes 10, a SCPM is assigned on the head of the group of RPM(s) then connected to CPM. As mentioned before, additional 3 RPM(S) may be connected in the maximum case . However this possibility is reserved for future expansion. (Of course, if no future expansion is sure, up to 13 RPM(S) may be connected from initial stage.)

    (4) Rule of SCPM

    SCPM is considered as a kind of RPM with enhanced function such as Sub-master in order to expand the network size. Therefore, depends on the network configuration, there is a case that RPM may be applicable and there is a case that SCPM should be applied. In other word, SCPM NE is NE which may be selected as RPM or SCPM depends on the actual network configuration.

    3.3.6 CPM/SCPM/RPM Role Change Function When the PM card founds an interruption of polling signal from the upper PM card, this PM card can function as CPM. Several PM cards do the role change. The PM card cease role change when receiving a polling signal from its upper PM card. During role change, an alarm is indicated but role change status cannot be viewed on the PNMS.

    Example 1

    If there is a link fault between RPM3 and 4, RPM4 will role change to CPM.

    Example 2

    If there is an equipment fault in RPM4, RPM5 will role change to CPM.

    CPM1 RPM2 RPM3 RPM4 RPM5 RPM6 RPM7

  • ROI-S04188

    - 8 -

    4. PHYSICAL INTERFACE Summary of physical interface of each equipment is described below.

    Figure 4-1 Available Physical Interface

    PNMS

    CPM

    PNMT

    SCPM RPMRS-232C

    19.2kbps Async.(For Windows NT)

    10Base T(For Windows NT and Unix)

    RS-232C/V.11 19.2kbpsAsync.orLAN(10Base-T)(NMS port)

    RS-485 or RS232C9.6kbpsAsync.(NMS port)

    RS-232C(COM port)

    RS-232C (LA port) RS-232C (LA port)

    DSC (9.6kbps) internal connection10 Base-TFor upper management system

    RS-485orRS232C9.6kbpsAsync.(NMS port)

    4.1 PNMS

    4.1.1 Serial Interface Functional : RS232C

    Electrical : V.24

    Mechanical : DB 9 PIN

    Communication rate : 19.2 kbps (Asynchronous)

    4.1.2 LAN Interface Interface : Ethernet (100/10 BaseT)

    Connector type : RJ-45

    4.2 PNMT

    Functional : RS232C

    Electrical : V.24

    Mechanical : DB 9 PIN

    Communication rate : 19.2 kbps (Asynchronous)

  • ROI-S04188

    - 9 -

    4.3 PM Card

    4.3.1 LA Port Functional : RS232C

    Electrical : V.24

    Mechanical : DB 15 PIN

    Communication rate : 19.2 kbps (Asynchronous)

    4.3.2 NMS Port

    4.3.2.1 PASOLINK (V3) Functional

    for PNMS connection : RS232C/RS422/LAN(10Base-T)

    for Back to Back connection : RS232C/RS485

    Electrical : V.24/V.11(for RS232C/RS422/RS485)

    Mechanical :DB 15 PIN

    Communication rate

    for PNMS connection : 19.2 kbps (Asynchronous) (for RS232C/RS422)

    for Back to Back connection : 9.6kbps (Asynchronous)

    4.3.2.1 PASOLINK (V4) Functional

    for PNMS connection : RS232C/RS422/LAN(10Base-T) for Back to Back connection : RS232C/RS485

    Electrical : V.24/V.11(for RS232C/RS422/RS485)

    Mechanical : DB 15 PIN RJ-45 (for PNMS(LAN) connection)

    Communication rate

    for PNMS connection : 9.2 kbps (Asynchronous) (for RS232C/RS422) for Back to Back connection : 9.6kbps (Asynchronous)

  • ROI-S04188

    - 10 -

    (PASOLINK (V3))

    (PASOLINK (V4))

    LA portNMS port

    NMS port(LAN)

    NMS port (Serial)LA port

  • ROI-S04188

    - 11 -

    5. PNMS COMMUNICATION INTERAFCE The interface condition between PNMS and NEs (CPM,SCPM,RPM) is summarized in Figure 5.1 (Serial interface) and Figure5.2 (LAN interface). The physical interface at PNMS Hardware is RS232C or 10baseT interface. The physical interface at CPM for PNMS connection is Serial (RS-232C/V.11,19.2kbps, Async.) or LAN(10 Base-T). The choice of the physical (Serial or LAN) interface at CPM should be done by the hardware replacement of PM Card. The choice of the serial interface (RS232C or V.11) should be done by the PNMS software.

    The physical interface at CPM, SCPM and RPM for back to back connection is RS-232C or RS-485 (9.6kbps, Async.). The choice of the physical interface (RS232C or RS485) at CPM,SCPM and RPM should be done by the PNMS software.

    Serial Interface between PNMS (Windows) and CPM

    Figure5-1 PNMS Communication Architecture (Serial Interface)

    RPM-1

    SCPM

    SNMP/TFTPSNMP/TFTPSNMP/TFTPAP

    RS-232C/485 9.6kbps Async.

    RS-232C/4859.6kbps Async.

    RS-232C19.2kbps Async.

    Physical*

    HDLC/NRMHDLC/NRMPPPData Link

    IPIPIPNetwork

    UDPUDPUDPTransport

    SCPM-RPMCPM-SCPMPNMS-CPM

    CPM

    *The converter willbe required for other interfaces.

    RPM-2

    RPM-3

    RPM-4

    LAN Interface between PNMS (Windows and UNIX) and CPM

    Figure 5-2 PNMS Communication Architecture

    SCPM

    SNMP/TFTPSNMP/TFTPSNMP/TFTPAP

    RS-232C/485 9.6kbps Async.

    RS-232C/4859.6kbps Async.

    10baseTPhysical*

    HDLC/NRMHDLC/NRMEthernetData Link

    IPIPIPNetwork

    UDPUDPUDPTransport

    SCPM-RPMCPM-SCPMPNMS-CPM

    CPMRPM

    -1

    RPM-2

    RPM-3

    RPM-4

    LAN

  • ROI-S04188

    - 12 -

    6. NETWORK SIZING RULE The following network sizing restriction is applied when NEC PASOLINK supervisory network hierarchy is configured.

    13*(8)Maximum number of branch(multi-drop) per site

    13,5,1*(7)Maximum number of NEs per subnetwork

    32 subnetwork *(6)Maximum number of subnetwork per CPM cluster

    416NEs*(5)Maximum number of NEs per CPM cluster

    32 ea*(3)Maximum number of CPM per PNMS

    500/1000 NEs*(1)Maximum number of NE per PNMS

    Table 6-1: Network Sizing Rule (Theoretical, Number of NE)

    PNMS for Windows

    PNMS for UNIX

    1000-10,000NEs*(2)

    320 ea*(4)

    (1) Maximum number of NEs(500 or 1,000) is depends on PC Hardware specification.

    (2) Software type for1,000/2,000/3,000/4,000/5,000/6,000/7,000/8,000/9,000/10,000 NEs are available.

    (3) Through LAN interface

    (4) PNMS for UNIX has region level window(up to 10 regions can be supported per PNMS. 1 region includes up to 32CPMs. Therefore up to 320(10 regions X 32CPMs) CPMs can be included per PNMS.

    (5) This number is calculated by following formula.

    Maximum number of NEs per CPM cluster

    = [Maximum Number of subnetwork per CPM cluster] X [Maximum number of NE per subnetwork ]

    (6) This value has relation with maximum number of SCPM because the head NE of each subnetwork is SCPM.

    Maximum number of SCPMs : 31 (Single Master, Refer Figure 6.1) 30 (Dual Master, Refer Figure 6.2)

  • ROI-S04188

    - 13 -

    PNMS

    Subnet1

    SCPM1 SCPM2

    Subnet2 Subnet3

    Subnet32

    SCPM31

    Subnet N

    SCPM N-1

    Subnet N+1

    SCPM N

    Figure 6.1(Single Master)

    Maximum number of subnetwork are 32 under a CPM. Therefore maximum number of SCPM is 31.

    : RPM

    : CPM

    : SCPM

    PNMS

    SCPM3

    Subnet4

    Subnet32

    SCPM30

    Subnet N+1

    SCPM N-1

    Subnet N+2

    SCPM N

    Subnet 3

    Figure 6.2 CPM (Dual Master)

    Maximum number of subnetwork are 32. In case of dual CPM configuration,maximum number of SCPM is 30.

    Dual Master

    SCPM2

    Subnet2 Subnet1

    SCPM N+1

    Radio SectionBack to back connection

    : RPM

    : CPM

    : SCPM

    (7) Maximum number of NE(SCPM and RPM)s in one subnetwork is depends on subnetmask of its subnetmask setting by Operator. The relation between the subnetmask and number of NE is described below.

    Subnetmask Assigned IP address Available IP address Number of NE 255.255.255.252 4 2 1 255.255.255.248 8 6 5 255.255.255.240 16 14 13

    (8) This is applied for star configuration.

  • ROI-S04188

    - 14 -

    7. PNMS IP ADDRESSING PNMS identifies each NE with IP address (IP v4). IP addressing scheme and requirement is described with typical network.

    7.1 Simple Trunk Line Network (Serial Interface)

    To explain IP addressing of PNMS, Typical network example (simple Trunk line) is shown (Figure 7.1.1). Serial interface is assumed for the interface between PNMS (Windows) and CPM in this figure.

    PNMS (Windows)

    PNMS

    1

    3

    Remote Site-A

    4 5

    Remote Site-B

    6 7

    Remote Site-C

    8

    Remote Site-D

    2

    : RPM

    RS232C19.2/9.6kbps, Async

    2

    Figure7.1.1 Typical Network Example (Simple trunk line [Physical Model])

    1 : CPM

    Figure 7.1.2 shows a logical network of Figure7.1.1 and IP address assignment example. To demonstrate connection of each NE with PNMS, 2 sub-networks, PNMS and CPM sub-network (A) and PASOLINK CPM cluster network (B) are defined.

    1CPM

    2RPM

    4RPM

    5RPM

    6RPM

    7RPM

    8RPM

    3RPM

    PNMS

    Central Site

    192.168.1.254

    192.168.1.253

    172.20.101.2

    172.20.101.3172.20.101.6

    172.20.101.4172.20.101.5 172.20.101.7

    172.20.101.8

    172.20.101.1

    Subnet-B (PASOLINK CPM cluster)

    Subnet-A (PNMS-CPM Subnetwork)

    Figure7.1.2 Typical Network Example (Simple trunk line [Logical Model])

  • ROI-S04188

    - 15 -

    7.1.1 IP Addressing Scheme for PNMS-CPM Subnetwork CPM NMS port and PC PNMS serial port must be located in the same sub network as shown Figure7.1.2. In this figure, the CPM is connected to PNMS through RS-232C interface and PPP encapsulation. The CPM NMS port IP address acts as the gateway to its PASOLINK cluster. For example, CPM passes an IP packet from PNMS with 172.20.101.3 to the destination NE.

    For this PNMS and CPM sub-network (A), PNMS uses a subnet mask of 255.255.255.252. (fixed). One PNMSCPM sub network includes 4 IP addresses accordingly. However 2 IP addresses are not available because one is assigned for network address, the other is reserved for broadcast address.

    7.1.2 IP Addressing Scheme for PASOLINK CPM Cluster This section shows the IP addressing scheme in PASOLINK CPM cluster (B). PNMS uses a Subnet mask of 255.255.255.240 for this sub-network in this case. Therefore one sub-network in CPM cluster has 16 IP addresses. However available IP addresses for Remote PM Card (RPM) are 13 as shown in section 6 Network sizing rule. It is because one is assigned for network address, the other is reserved for broadcast address, in addition one IP address is assigned for CPM.

    In addition, Operator can set subnetmask in accordance with the number of NE in each sub-network in case the number of NE in a subnetwork is small. The relation between the subnetmask and the number of NE in the subnetwork is described below.

    Subnetmask Assigned IP address

    Available IP address

    Number of NE

    255.255.255.252 4 2 1 255.255.255.248 8 6 5

    255.255.255.240 16 14 13 Table 7.1.1 Relation between the subnetmask and number of NE

    For reference assigned IP address and available IP address of each sub-network are shown in following table.

    Subnet-B(Number of NEs : 7NEs ->Subnetmask : 255.255.255.240 172.20.101. 015 (Assigned IP Address) 172.20.101. 114 (Available IP Address)

    Table7.1.2 Example for IP address planing in each Subnet

    Subnet-A (Subnetmask : 255.255.255.252(Fixed))192.168.1. 252 255 (Assigned IP Address(Fixed))192.168.1. 253254 (Available IP Address(Fixed))

  • ROI-S04188

    - 16 -

    7.2 Simple Trunk Line Network (LAN Interface)

    To explain IP addressing of PNMS, Typical network example (simple Trunk line) is shown (Figure 7.2.1). Serial interface is assumed for the interface between PNMS and CPM in this figure.

    PNMS

    PNMS

    1

    3

    Remote Site-A

    4 5

    Remote Site-B

    6 7

    Remote Site-C

    8

    Remote Site-D

    2

    : RPM

    LAN(10base-T)

    2

    Figure7.2.1 Typical Network Example (Simple trunk line [Physical Model])

    1 : CPM

    Figure 7.2.2 shows a logical network of Figure7.2.1 and IP address assignment example. To demonstrate connection of each NE with PNMS, 2 sub-networks, PNMS and CPM sub-network (A) and PASOLINK CPM cluster network (B) are defined.

    1CPM

    2RPM

    4RPM

    5RPM

    6RPM

    7RPM

    8RPM

    3RPM

    PNMS

    Central Site

    172.20.100.1172.20.100.2

    172.20.101.2172.20.101.3

    172.20.101.6

    172.20.101.4172.20.101.5 172.20.101.7

    172.20.101.8

    172.20.101.1

    Subnet-B (PASOLINK CPM cluster)

    Subnet-A (PNMS-CPM Subnetwork)

    Figure7.2.2 Typical Network Example (Simple trunk line [Logical Model])

  • ROI-S04188

    - 17 -

    7.2.1 IP Addressing Scheme for PNMS-CPM Subnetwork CPM NMS port and PC PNMS LAN port must be located in the same sub network as shown Figure7.2.2. In this figure, the CPM is connected to PNMS through LAN(10 Base-T) interface. The CPM NMS port IP address acts as the gateway to its PASOLINK cluster. For example, CPM passes an IP packet from PNMS with 172.20.101.3 to the destination NE.

    For this PNMS and CPM sub-network (A), Operator can set subnetmask in accordance with the number of NE in this subnetwork. In case of network example described in Figure 7.4, PNMS uses a subnet mask of 255.255.255.252 because this subnetwork has one CPM (Refer to Table7.1.1)

    7.2.2 IP Addressing Scheme for PASOLINK CPM Cluster Refer to section 7.1.2.

    For reference assigned IP address and available IP address of each sub-network are shown in following table.

    Subnet-B (Number of NEs : 7NEs -> Subnetmask : 255.255.255.240172.20.101. 015 (Assigned IP Address) 172.20.101. 114 (Available IP Address)

    Table7.2.1 Example for IP address planing in each Subnet

    Subnet-A (Number of NEs : 1NEs ->Subnetwask : 255.255.255.252 172.20.100. 0 3 (Assigned IP Address)172.20.100. 12 (Available IP Address)

    7.2.3 Plural CPM Configuration Figure 7.2.3 shows plural CPM configuration. Figure 7.2.4 is logical Model of this configuration. In this case, Subnetmask of PNMS-CPM subnetwrok is assigned to 255.255.255.248 as shown Table 7.2.2.

  • ROI-S04188

    - 18 -

    PNMS

    1

    12

    Remote Site-B

    Remote Site-C

    11

    13 14

    Figure7.2.3 Typical Network Example (Simple trunk line with plural CPM [Physical Model])

    2

    22

    Remote Site-H

    Remote Site-F

    21

    23 24Remote Site-E

    3

    32

    Remote Site-I

    31

    33 34

    1CPM

    12RPM

    PNMS

    Subnet-B (PASOLINK CPM cluster)

    Figure7.2.4 Typical Network Example (Multi-branch network [Logical Model])

    13RPM

    18RPM

    3CPM

    32RPM

    38RPM

    33RPM

    22RPM

    28RPM

    23RPM

    2CPM

    Subnet-A (PNMS-CPM subnetwork)

    Subnet-C

    Subnet-D

    Table7.2.2 Example for IP address planing in each Subnet

    Subnet-A (Number of NEs : 3 NEs -> Subnetmask : 255.255.255.248)172.20.100. 0 7 (Assigned IP Address)172.20.100. 1 6 (Available IP Address)

    Subnet-B (Number of NEs : 10 NEs -> Subnetmask : 255.255.255.240)172.20.101. 015 (Assigned IP Address) 172.20.101. 114 (Available IP Address) Subnet-C (Number of NEs : 10NEs -> Subnetmask : 255.25.255.240)172.20.102. 0 15 (Assigned IP Address) 172.20.102. 1 14 (Available IP Address)Subnet-D (Number of NEs : 10NEs -> Subnetmask : 255.255.255.240)172.20.103. 015 (Assigned IP Address) 172.20.103.1 14 (Available IP Address)

  • ROI-S04188

    - 19 -

    7.3 Simple Trunk Line Network (through IP network)

    Figure7.3 .1shows typical network example (simple Trunk line) with LAN interface through IP network between PNMS and CPM.

    PNMS1

    3

    Remote Site-A

    4 5

    Remote Site-B

    6 7

    Remote Site-C

    8

    Remote Site-D

    2

    : RPM

    RS232C or V.1119.2/9.6kbps, AsyncorLAN(10 base-T)

    2

    1 : CPM

    : Router

    Figure 7.3.1 Typical Network Example (Simple trunk line [Physical Model])

    IP network

    Figure 7.3.2 shows a logical network of Figure7.3.1 and IP address assignment example. To demonstrate connection of each NE with PNMS, 2 sub-networks, Router and CPM sub-network and PASOLINK CPM cluster network are defined.

    1CPM

    2RPM

    4RPM

    5RPM

    6RPM

    7RPM

    8RPM

    3RPM

    PNMS

    Central Site

    172.20.100.1

    172.20.100.2

    172.20.101.2

    172.20.101.3172.20.101.6

    172.20.101.4172.20.101.5 172.20.101.7

    172.20.101.8

    172.20.101.1

    Subnet-B (PASOLINK CPM cluster)

    Subnet-A (Router-CPM Subnetwork)

    Figure7.3.2 Typical Network Example (Simple trunk line [Logical Model])

    IP network

  • ROI-S04188

    - 20 -

    7.3.1 IP Addressing Scheme for Router-CPM Subnetwork CPM NMS port and the Router Serial or LAN port must be located in the same sub network as shown Figure 7.3.2. In this figure, the CPM is connected to the router and must be added to the IP routing table of the subnetwork in the CPM Cluster into the router and acts as the gateway to the PASOLINK CPM cluster. For example, an IP packet with 172.20.101.3 is sent to the IP network, the router passes this to the CPM NMS port and then the CPM passes it to the destination NE, which is the recipient of the packet as shown in Figure 7.3.2.

    For this Router and CPM sub-network, PNMS uses a subnet mask of 255.255.255.252 (fixed) for serial interface. For LAN interface Operator can set subnetmask in accordance with the number of NE in this network.

    7.3.2 IP Addressing Scheme for PASOLINK CPM Cluster Refer to section 7.1.2.

    7.4 Multi Sub-Branch Network

    Figure7.4.1 shows typical network example (Multi sub-branch network). In this figure serial interface between PNMS and CPM is assumed.

    Central Site

    PNMS (Windows)

    1

    4

    Remote Site-A

    5 6

    Remote Site-B

    Remote Site-C

    14

    Remote Site-D

    3

    10 9

    12 1113

    Remote Site-E

    Remote Site-F

    Remote Site-G7

    82

    RS232C19.2/9.6kbps, Async

    RS4859.6kbps, Async

    Figure 7.4.1 Typical Network Example (Multi sub-branches network[Physical Model])

    : RPM3

    1 : CPM2 : SCPM

    Figure 7.4.2 shows a logical model of Figure7.4.1 and IP address assignment example. To demonstrate connection of each NE with PNMS, 3 sub-networks, PNMS and CPM sub-network (A) and PASOLINK CPM cluster network (B and C) are defined.

    1CPM

    2SCPM

    4RPM

    5RPM

    6RPM

    7RPM

    8RPM

    3RPM

    PNMS

    Central Site 14RPM

    11RPM

    10RPM

    9RPM

    12RPM

    13RPM

    172.20.100.1172.20.100.2

    172.20.101.2

    172.20.101.3

    172. 20.101.6

    172.20.101.4172.20.101.5

    172.20.101.7

    172. 20.101.8

    172.20.101.9

    Subnet-B(PASOLINK CPM cluster)

    Subnet-C

    172.20.101.17172.20.101.18172.20.101. 19

    172.20.101. 20172.120.101. 21

    172.20.101. 22Subnet-A(Router-CPM Subnetwork)

    172.20.101.1

    Figure 7.4.2 Typical Network Example (Multi sub-branches network[Logical Model])

  • ROI-S04188

    - 21 -

    7.4.1 IP Addressing Scheme for PNMS-CPM Subnetwork Refer to section 7.1.1.

    7.4.2 IP Addressing Scheme for PASOLINK CPM Cluster PNMS uses a Subnet mask of 255.255.255.240 for subnet-B. Therefore one sub-network in CPM cluster has 16 IP addresses. Each sub network can accommodate 16 IP addresses. Available IP addresses for Remote PM Card (RPM) are 13. Subnet-B is assigned from 172.20.101.0 to 172.20.101.15. (16 IP Addresses) However 172.20.101.0 and 172.20.101.15 is not available because 172.20.101.0. is sub network address and 172.20.101.15 is reserved for broadcast address. In addition one IP address is assigned on Central PM Card. Therefore 13 IP addresses (for 13 RPMs) are available in Subnet-B (same as for all other sub network).

    In addition IP address for next sub-network (Subnet-C) shall be assigned from 172.20.101.16. (172.20.101.17 to172.20.101.30 is available), even if Subnet-B has less than 13 NEs (for example only one NE), Subnet-C is started to assign from 172.20.101.17. As explained section 7.1.2, operator can set subnetmask for each subnetwork. For example, 255.255.255.248 can be assigned for Subnet-C in case there is no additional NE in Subnert-C in the future.

    One CPM cluster can include maximum 32 sub-networks as explained in Section 6. Therefore one CPM cluster can accommodate maximum 512 IP addresses(16 IP address x 32 sub-networks) . This maximum 512 consecutive IP addresses are reserved in PNMS. Two (2) class C sub-networks (for example, 172.20.101.** and 172.20.102.**) are required to assure the 512 IP Addresses.

    For reference assigned IP address and available IP address of each sub-network are shown in Table 7.4.1

    Subnet-B : 172.20.101. 015 (Assigned IP Address) : 172.20.101. 114 (Available IP Address)

    Subnet-C : 172.20.101.1631 (Assigned IP Address) 172.20.101. 1730 (Available IP Address)

    Table 7.4.1 Example for IP address planing in each Subnet

    Subnet-A : 172.20.100. 03 (Assigned IP Address)172.20.100. 12 (Available IP Address)

  • ROI-S04188

    - 22 -

    7.4.3 Example of IP Addressing for Multi Sub-Branch Network Figure7.4.3 show the example of IP address assignment for CPM cluster with 8

    sub-network. (In this example, all subnetmask is assigned to 255.255.255.240.)

    RPM SCPM

    CPMSCPMRPMRPMRPM

    RPM SCPMRPM

    RPM SCPM 172.18. 0.1

    RPM SCPMRPMRPM

    RPM SCPM

    172.18.0.18

    172.18.0.2

    172.18.0.33

    172.18.0.34

    172.18.0.65

    172.18. 0. 36

    172.18.0. 35

    172.18.0.78

    172.18. 0.66

    172.18.0. 49172.18.0. 50172.18. 0.51172.18.0.62

    172.18.0.81172.18.0.83

    172.18.0. 94

    172.18.0.82

    172.18.0. 97

    172.18. 0. 113

    171.18.0. 110

    172.18.0.126

    B

    CD

    E

    F

    G

    H

    172.18.0. 37

    172.18. 0.67

    PNMS

    Figure 7.4.3 Network Example (IP address Scheme)

    172.18.2.2

    172.18.2.1

    172.18.0.17

    A

    I

    Router and CPM subnetwork

    R

    Table 7.4.2 shows assigned IP addresses and available IP addresses of each sub network of this multi sub-branch network.

    Subnet-C : 172.18.0. 1631 (Assigned IP Address) : 172.18.0. 17 30 (Available IP Address)

    Subnet-D : 172.18.0. 3247 (Assigned IP Address) : 172.18.0. 33 46 (Available IP Address)

    Subnet-E : 172.18.0. 4863 (Assigned IP Address) : 172.18.0. 4962 (Available IP Address)

    Subnet-F : 172.18.0. 6479 (Assigned IP Address) : 172. 18.0. 6578 (Available IP Address)

    Subnet-G : 172.18.0.8095 (Assigned IP Address) : 172.18.0.8194 (Available IP Address)

    Subnet-H : 172.18.0.96111 (Assigned IP Address): 172.18.0.97110 (Available IP Address)

    Table 7.4.2 : Example for IP address planning in each Subnet

    Subnet-A : 172.18.2. 1 (Router Serial IP Address): 172.18.2. 2 (CPM NMS port IP Address)

    Subnet-B : 172.18.0. 015 (Assigned IP Address) : 172.18.0. 1 14 (Available IP Address)

    Subnet-I : 172.18.0.112127 (Assigned IP Address): 172.18.0.113126 (Available IP Address)

  • ROI-S04188

    - 23 -

    7.5 PNMS IP Addressing Summary

    Figure 7.5.1 (Serial Interface) and Figure 7.5.2 (LAN interface) describe the summary of PNMS IP addressing scheme.

    Figure 7.5.1 IP address Scheme for PNMS (Serial interface between PNMS and CPM)

    Subnet Mask is selectable by Operator.

    255.255.255.252(11111111.11111111.11111111.11111100)255.255.255.248(11111111.11111111.11111111.11111000)255.255.255.240(11111111.11111111.11111111.11110000)

    Subnet Mask is 255.255.255.252(11111111.11111111.11111111.11111100)Assigned address is 4.All 1s and 0s are reserved.Therefore 2 address are available.

    CPM

    SCPMSCPM

    RPMRPM

    PNMS (Windows)Serial Interface

    SCPM

    RPM

    Subnet Mask is selectable by Operator according to the number of CPM.

    Figure7.5.2 IP address Scheme for PNMS (LAN interface between PNMS and CPM)

    Subnet Mask is selectable by Operator.

    255.255.255.252(11111111.11111111.11111111.11111100)255.255.255.248(11111111.11111111.11111111.11111000)255.255.255.240(11111111.11111111.11111111.11110000)

    CPM

    SCPMSCPM

    RPMRPM

    SCPM

    RPM

    LAN

    7.6 IP Address Requirement for Customer

    During the Network Design phase, following IP address must be required in order for each NEs to connect to the PNMS.

    1) PNMS(Router)CPM sub-network

    IP address for Router Serial port or PNMS (PC or WS) port IP address for CPM NMS

    2) PASOLINK CPM cluster network

    CPM cluster sub-network Address for each NE (Two class C sub networks are required for maximum 512 IP addresses)

  • ROI-S04188

    - 24 -

    8. INTEROPERABILITY WITH OTHER NETWORK If the network is composed of only PASOLINK, the integration of PNMS will be simple. However in case of the existing customers transmission network, interconnectivities and interoperability among different manufacturers will have to be confirmed. The purpose of this section is to allow the PASOLINK supervisory network to managed each heterogeneously located PASOLINK hop through customers existing transmission network and IP network.

    For example, the interconnected equipments could be:

    Other transport equipments from manufacturers Routers such as Cisco

    8.1 Connection Availability

    Following table is the connection availability between PASOLINK and Other equipment (other manufacture equipment and NEC equipment other than PASOLINK) of RS485 interface.

    Table 8.1 Connection Availability

    Point to point Connection Point to multi-point (daisy chain) connection

    Other equipment (RS485)

    Other equipment (RS422)

    Other equipment (RS485)

    Other equipment (RS422)

    PASOLINK RS485

    PASOLINK (RS485)

    Not Available (Note 1)

    (Note 2) Not Available (Note 1)

    Not Available Available

    Proposed Solution

    Convert RS422 by using HYB CONV

    Convert RS422 by using HYB CONV

    -

    Note.1) Because the method of connecting data signal lines in plural connections in point to multi-point line is not determined, it is not possible to connect equipment from different manufacturers unless connection test between PASOLINK and other equipment is required.

    Note.2) Terminal impedance of other manufacture equipment is not clear. Therefore output logical condition of other manufacture equipment is not clear in high impedance condition. In this case it is impossible to connect each other. (Connection test is required between PASOLINK and other equipment.)

  • ROI-S04188

    - 25 -

    9. TYPICAL CONFIGURATION The PNMS supports a variety of radio topologies. That is, there are many ways in which the connections can be made between PNMS, CPM, SCPM and RPM. The system design is to analyse the network and customer requirement, to decide the PASOLINK network configuration, to estimate the cost and provide customer with some optimised solutions.

    Based on the radio network information a PASOLINK network management system can be formed by following steps specified below:

    Select PNMS Architecture and decide on the number of PNMS hardware. Decide that the PASOLINK network configuration based on given radio topology.

    Divide the monitored network into sub-networks, which is geographically and functionally manageable for monitoring and controlling in accordance with section 6.Network Sizing rule.

    Decide on the PMC operation modes (such as CPM, SCPM, and RPM) and the PMC

    Determine the data communication path. 9.1 Point to Point Connection

    Figure 9.1 shows the PASOLINK supervisory interface with existing network (dedicated line such as DSC) between PNMS and CPM.

    PASOLINK CLUSTER

    DSC 19.2kbps, ASYNC

    Figure 9.1 Interoperability with other manufacture equipment

    PNMS(Windows )

    Existing Network (Dedicated line)

    RS-232C 19.2kbpsASYNC

    RS-232C/V.11 19.2kbpsASYNC

    DSC 19.2kbps, ASYNC

    LAN

    RS-232C/V.11 19.2kbpsASYNC

    Existing Network (Dedicated line)

    PNMS(UNIX or

    Windows )

    PASOLINK CLUSTER

    R

    RS-232C 19.2kbpsASYNC

  • ROI-S04188

    - 26 -

    Figure 9.2 show the PASOLINK supervisory interface with existing network (PSTN or IP network) between PNMS and CPM.

    MD MD

    Figure 9.2 Interoperability with other network

    LAN

    RS-232C 9.6kbpsASYNC

    RS-232C/V.11 9.6kbpsASYNC

    RS-232C/V.11 19.2kbpsASYNC

    PSTN

    Continuous connection is needed

    PNMS(UNIX or

    Windows)

    PNMS(Windows )

    PASOLINK CLUSTER

    RR

    PASOLINK CLUSTER

    LAN

    RR

    PASOLINK CLUSTER

    IPNetwork

    IPNetwork

    R :Router

    : RPM

    : CPM

    MD :Modem

    Figure 9.3 show the PASOLINK supervisory interface with existing network between PASOLINKs.

    Figure 9.3 Interoperability with other network (point to point connection)

    LANRS-232C or RS-485

    9.6kbpsASYNC

    RS-232C, RS-485 9.6kbpsASYNC

    RS-232C 19.2kbpsASYNC

    PASOLINK CLUSTER

    Existing Network (Dedicated line)19.2/9.6 kbps, ASYNC PNMS

    (UNIX orWindows)

    LANRS-232C or RS-485

    9.6kbpsASYNC

    RS-232C or RS-485 9.6kbpsASYNC

    RS-232C 19.2kbpsASYNC

    PASOLINK CLUSTER

    PNMS(UNIX or

    Windows)

    MD MDPSTN

    Continuous connection is needed

    R

    R

    PASOLINK CLUSTER

    PASOLINK CLUSTER

  • ROI-S04188

    - 27 -

    9.2 Point to Multi-Point Connection

    Figure 9.4 show the PASOLINK supervisory interface with existing network between PASOLINKs (point to multi-point connection). Because of the reason described section 8.1, HYB converter (Refer to section 12.1) is required to combine and divide the supervision signal.

    Figure 9.4 Interoperability with other network

    LANRS232C, RS-485 9.6kbpsASYNC

    RS-232C, RS-485 9.6kbpsASYNC

    RS-232C 19.2kbpsASYNC

    Existing Network(Dedicated line)19.2/9.6 kbps, Async PNMS(UNIX or

    Windows)

    HYB

    CONV

    HYB

    CONV

    R

    R :Router

    : Existing Network (Dedicated line): RPM: CPM

    PASOLINK CLUSTER

    9.3 Multi-Cluster Network (1) - Dedicated Leased Line (Serial Interface) -

    Figure 9.5 shows a multi-cluster network, monitored and controlled by PNMS through serial interface and dedicated line such as DSC. Multiple connections on central computer are realized by RS232C extension port installed in the PC. 19.2kbps (RS232C interface) are required for dedicated leased line or Digital Service Channel.

    ???

    Figure 9.5 Multi-branch network through Digital Service Channel with PNMS Serial interface

    PNMS(Windows)

    Multi-serial board (inserted into PCI SLOT)

    ????

    RS-232C/V.11 19.2kbpsASYNC

    RS-232C 19.2kbpsASYNC

    PASOLINK CLUSTER

    Existing Network (Dedicated line)

    19.2kbps, ASYNC

    PASOLINK CLUSTER

  • ROI-S04188

    - 28 -

    9.4 Multi-Cluster Network (2) - Dedicated Leased Line (LAN Interface) -

    Figure 9.6 shows a multi-cluster network, monitored and controlled by PNMS through LAN interface and dedicated line such as DSC. 19.2kbps (RS232C interface) are required for Router port.

    ????

    ????

    RS-232C/V.11 19.2kbpsASYNC

    PASOLINK CLUSTER

    PASOLINK CLUSTER

    R

    PNMS(UNIX or

    Windows )

    Existing Network (Dedicated line)

    19.2kbps, ASYNC

    Figure 9.6 Multi-branch network through Digital Service Channel with PNMS Serial interface

    RS-232C 19.2kbpsASYNC

    9.5 Multi-Cluster Network (3) - PSTN (Serial Interface) -

    Figure9.7 shows a multi-cluster network, monitored and controlled by PNMS through serial interface and PSTN. RS232C interface (19.2kbps) are required for Modem.

    PNMS(Windows)

    MD

    MD

    MD

    MD

    MD

    MD

    MD

    MD

    ????

    RS-232C 19.2kbpsASYNC

    RS-232C 19.2kbpsASYNC

    ????

    PASOLINK CLUSTER

    PSTN

    Continuous connection is needed

    Figure 9.7 Multi-branch network through PSTN with PNMS Serial interface

    PASOLINK CLUSTER

    Multi-serial board (inserted into PCI SLOT)

  • ROI-S04188

    - 29 -

    9.6 Multi-Cluster Network (4) - PSTN (LAN Interface) -

    Figure 9.8 shows a multi-cluster network, monitored and controlled by PNMS through LAN interface and PSTN. RS232C interface (19.2kbps) are required for Modem.

    MD

    MD

    MD

    MD

    MD

    MD

    MD

    MD

    ????

    RS-232C 19.2kbpsASYNC

    RS-232C 19.2kbpsASYNC

    ????

    PASOLINK CLUSTER

    PSTN

    Continuous connection is needed

    Figure 9.8 Multi-branch network through PSTN with PNMS LAN interface

    R

    PASOLINK CLUSTER

    PNMS(UNIX or

    Windows )

    9.7 Multi-Cluster Network (5) - IP Network (LAN Interface) -

    Figure 9.9 and Figure 9.10 shows a multi-cluster network, monitored and controlled by PNMS through LAN interface and IP network. Figure 9.9 shows serial interface is assumed between Router port and CPM. Figure 9.10 shows LAN interface is assumed between Router and CPM.

    IP NETWORK

    LAN

    RS-232C/V.11 19.2kbpsASYNC

    ????

    PASOLINK CLUSTER

    PASOLINK CLUSTER

    Figure 9.9 Multi-branch network through IP network

    R

    R

    R

    R

    R

    PNMS(UNIX or

    Windows )

  • ROI-S04188

    - 30 -

    IP NETWORK

    LAN

    LAN

    ????

    PASOLINK CLUSTER

    PASOLINK CLUSTER

    Figure 9.10 Multi-branch network through IP network

    R

    R

    R

    R

    R

    PNMS(UNIX or

    Windows )

    9.8 CPM Reduction Solution

    In accordance with customers network such that many CPM clusters scattered in all over the region, plural CPMs are required to be monitored and controlled by PNMS as shown in Figure9.11 and Figure 9.12. In such cases the number of the required Router serial ports increases according to the number of CPMs. To reduce CPMs and reduce the number of Routers serial ports, following solution is proposed.

    ????

    ????

    RS-232C/V.11 19.2kbpsASYNC

    RS-232C 19.2kbpsASYNC

    PASOLINK CLUSTER

    PASOLINK CLUSTER

    RPNMS

    (UNIX orWindows)

    Existing Network (Dedicated line)

    19.2kbps, ASYNC

    Figure 9.11 Multi cluster network through Digital Service Channel

    : RPM

    : CPM

    : SCPM

    Up to 416 NEs

    Up to 416 NEs

    Up to 416 NEs

    Up to 416 NEs

  • ROI-S04188

    - 31 -

    PASOLINK CLUSTERs

    PNMS

    PASOLINK CLUSTERs

    PASOLINK CLUSTERs

    : Existing Network (Dedicated line) : CPM

    R

    R

    R

    R

    Customer IP Network

    Figure 9.12 Basic connection through existing radio line and IP network(point to multi-point)

    RS-232C 19.2kbpsASYNC

    RS-232C 19.2kbpsASYNC

    The concept for reducing CPM is shown Figure 9.13. The CPM function is located at PNMS site. The SV signal from PASOLINK clusters scattered all over the region are concentrated (combined) by mediation device called HYB CONV (Hybrid Converter) at PNMS site. Then the concentrated signal is connected to CPM function. (The detailed function of HYB CONV is described in Section 12.1.)

    ????

    ????

    RS-232C or RS485 9.6kbpsASYNC

    RS-232C 19.2kbpsASYNC

    PASOLINK CLUSTER

    PASOLINK CLUSTER

    R

    PNMS(UNIX or

    Windows)

    Existing Network (Dedicated line)

    9.6 kbps, ASYNC

    Figure 9.13 Multi cluster network through Digital Service Channel

    CPM Function

    HYB

    CONV

    : RPM

    : CPM

    : SCPM

    Up to 416 NEs

    SV signal Concentrated Function

    This CPM function is realized by usage of mediation device, called MIU (Management Interface Unit), locating at PNMS site as shown Figure 9.14 and Figure 9.15.(The detailed function of MIU is described in Section 12.2.)

    By using HYB CONV and MIU, the SV signal from many PASOLINK cluster is combined into one signal and send to a serial port of Router.

  • ROI-S04188

    - 32 -

    ????

    ????

    RS-232C/V.11 19.2kbpsASYNC

    orLAN(10BASE-T)

    PASOLINK CLUSTER

    PASOLINK CLUSTER

    R

    PNMS

    Existing radio line

    HYB

    CONV

    MIU

    Figure 9.14 CPM reduction solution-1for basic connection through existing radio line (point to multi-point)

    RS-232C 19.2/9.6kbps

    ASYNC

    5 port

    HYB

    CONV

    Up to 13 SCPM5 port : RPM

    : CPM

    : SCPM

    RS-232C or RS485 port 9.6kbps, ASYNC

    RS-4859.6kbpsASYNC

    Up to 416 NEs

    R

    PASOLINK CLUSTER

    PNMS

    HYBCONVPASOLINK CLUSTER

    HYBCONV

    PASOLINK CLUSTER

    HYBCONV

    MIU

    MIU

    MIU

    : Existing Network (Dedicated line): RPM: CPM : SCPM

    RS-232C or RS485 port 19.2/9.6kbps

    ASYNC

    RS-232C or RS485 port 19.2/9.6kbps

    ASYNC

    R

    R

    R

    Customer IP Network

    Figure 9.15 CPM reduction solution-2 for basic connection through existing radio line and IP network (point to multi-point)

  • ROI-S04188

    - 33 -

    10. PNMS CONFIGURATION Basically cold stand-by configuration is proposed for PNMS redundancy. In addition Parallel PNMS can be proposed.

    10.1 Cold Stand-by PNMS Principle

    Basically cold stand-by PNMS is pre- installed PNMS software. However network configuration file, event log data and performance monitor data is not included in cold stand-by PNMS. Cold stand-by PNMS should be assigned the same IP addresses as on-line PNMS and not connected with PNMS network.

    Therefore in case that on-line PNMS is down, one of following two procedures could be taken.

    (1) Remake the network configuration file in the cold stand-by PNMS same as that of on- line PNMS to monitor and control the same network. (Event log and Performance monitor data of on-line PNMS can not be retrieved in cold stand-by PNMS.

    (2) Operator takes a back up data of network configuration file to cold stand-by PNMS disk when network configuration is changed. In addition (if desired), Operator is recommended to perform regular back up of event log data and performance monitor data to cold stand-by disk daily, for instance.

    When on-line PNMS is down, Operator should connect the stand-by PNMS with PNMS network. (The data between the timing of last back up and timing of on-line PNMS clash cannot be retrieved.)

    10.2. Back Up PNMS Data (UNIX version only)

    PNMS (UNIX) provides GUI-based backup tool for making backups of the following PNMS data to another disk. There are two types of PNMS backups method, scheduled backup (every day or every week) and Manual backup (unscheduled).

    -Network configuration data -User security data -Performance monitor data -Logging data

    10.3 Parallel PNMS

    Two PNMS can monitor and control PASOLINK network simultaneously and independently. These are connected to CPM through Router, as shown Figure 10.1. This configuration is called Parallel PNMS. Parallel" means that status change (ex. Alarm and event occurrence) of each NE is recognized in both PNMS. Even if the one PNMS is down, the other PNMS can monitor and control NEs in the network. However, there is case that logging data and performance monitor data are not synchronized between the PNMS-1 and PNMS-2, i.e., such data is not stored into both PNMSs.

  • ROI-S04188

    - 34 -

    For example, assuming that PNMS-1 is in operation and PNMS-2 is down:

    a) Logging data

    If alarms occur in PASOLINK network, the alarm log is registered in PNMS-1. However these logs are not registered in PNMS-2. After PNMS-2 is re-started, the logging data is not synchronized between PNMS-1 and PNMS-2. In this case Operator is required to download the logging data from PNMS-1and to upload it to PNMS-2 desired directory and re-start PNMS-2, if Operator want to synchronize the logging data of both PNMS.

    b) Performance monitor data

    PNMS collects performance data stored in each PM Cards in the network once a day. (Collecting time can be set by Operator.) If PNMS-1 collects performance data of NEs in the network, PNMS-1 stores performance data of the day. However PNMS-2 does not store the performance data. Therefore, after PNMS-2 is re-started, the performance data is not synchronized between PNMS-1 and PNMS-2. In this case Operator is required to download the performance data from PNMS-1 and upload it to PNMS-2 desired directory and re-start PNMS-2, if Operator want to synchronize the performance data of both PNMSs.

    c) Network configuration data

    In addition, the network configuration data can be created from either Network Configuration tool (PNMS) and is not automatically transferred to another PNMS regardless whether PNMS is in operation or down. Therefore, in order to synchronize such data between PNMSs, whenever such data is created or changed from one PNMS, Operator shall remake such data in another PNMS to be identical to those in one PNMS accordingly.

    Network Operation Center-1

    PNMS-1

    PNMS-2

    Customer IP network

    Regional Network Operation Center-2 : ROUTER

    : PASOLINK

    Alarm or Event Trap

    Alarm or Event Trap

    Figure 10.1Parallel PNMS

    LAN

    LAN

  • ROI-S04188

    - 35 -

    10.4 Hierarchical PNMS configuration

    Central and Regional PNMS can be configured as shown in the Figure 10.2. Regional PNMS monitors and controls PASOLINKs in its region. Central PNMS monitors and controls all PASOLINKs in all regions (up to 10 regions).

    Regional PNMS supports up to 500/1,000 NEs (PNMS for Windows) or 1,000 NEs (PNMS for UNIX). Central PNMS supports up to 2,000 NEs (PNMS for Windows) or 10,000 NEs (PNMS for UNIX).

    Each NE is monitored and controlled by both Central and Regional PNMS. It means that even if Central PNMS is down, each Regional PNMS can monitor and control NEs in its region.

    In a similar way, if a regional PNMS is down, the Central PNMS can monitor and control NEs under the region where the Regional PNMS is down.

    Central and Regional PNMS work independently. In case one of them is down following situation occurs for logging data and performance monitor data.

    For example, assuming that Central PNMS is in operation and a Regional PNMS is down:

    a) Logging data

    If alarms occur in the PASOLINK network, the alarm logs are registered in only Central PNMS. However these logs are not registered in Regional PNMS. Even if Regional PNMS is re-started, the logging data is not recorded in the Regional PNMS.

    b) Performance monitor data

    PNMS collects performance data stored in each NE in the network once a day. Operator can set time to collect and what NEs to collect. In case Central PNMS collects performance data of NEs in the network when regional PNMS is down, only Central PNMS stores performance data of the day and Regional PNMS does not store them. Even if Regional PNMS is re-started, the performance data is not stored in the Regional PNMS.

    Network configuration work The network configuration file for Regional PNMS and each NE is created by Network Configuration tool in Regional PNMS site and imported to Regional PNMS by Update network configuration window. Operator should send network configuration file for each Regional PNMS to Central PNMS (for example by E-mail). In Central PNMS, Operator imports each regional PNMS configuration file to Central PNMS by Update network configuration window in order to monitor and control all regions.

    If network configuration is modified in a region, Operator modifies network configuration file in each Regional PNMS site and import it to Regional PNMS by Update network configuration window. The modified network configuration file is sent to Central PNMS, for example by E-mail, and imported to it by Update network configuration window.

  • ROI-S04188

    - 36 -

    Central PNMS

    Regional Operation Center-1

    Regional PNMS

    Network Operation Center

    Customer IP Network

    Regional Operation Center-2

    Regional Operation Center-3

    Regional Operation Center-4

    Regional Operation Center-5

    Regional Operation Center-6

    Regional PNMS

    Figure 10.2 Central/Regional PNMS Configuration

    Note) Following function is not supported for Central PNMS. These functions are done by Regional PNMS.

    1. Link performance history (collection of link performance monitor data stored in each NE per day) function to avoid traffic congestion

    2. Automatically Set date and time function

    3. Dialup connection function (only for PNMS for Windows, This function is not used because IP connection is used.)

    4. Upper SNMP interface function (only for PNMS for Windows)

  • ROI-S04188

    - 37 -

    11. NETWORK CONFIGURATION WORK

    11.1 PNMS for Windows

    11.1.1 Install PNMS 1. Install PASOLINK hardware.

    If the PASOLINK system exists with configuration file, skip Step 2 through Step 6.

    Figure11.1 Network Example

    : RPM

    : CPM

    : Radio Connection

    : Cable Connection

    PNMS Site

    2. Decide each PM Card mode (for example Figure 11.2).

    Figure11.2 Network Example

    : RPM

    : CPM

    : Radio Connection

    : Cable Connection

    PNMS Site

    : SCPM

    3. Create configuration file on PNMS for each PM Card and PNMS by Network Configuration tool.

    4. Export configuration file of each PM Card and PNMS to the directory set up in the Network Configuration tool.

  • ROI-S04188

    - 38 -

    5. Copy the configuration files of each PM Card from PNMS PC to PNMT and download them to each PM Card on site using PNMT.

    6. Import configuration file for PNMS using Update Network Configuration window function on PNMS.

    Figure11.3 Network Example

    : RPM

    : CPM

    : Radio Connection

    : Cable Connection

    PNMS Site

    7. Connect PNMS to CPM and confirm the connection. After that it is possible to monitor and control each NE.

    Figure11.4Network Example

    : RPM

    : CPM

    : SCPM

    R

    R : Router

    Subnet-1

    Subnet-2

    Subnet-3

    Subnet-4

    Subnet-5

    : Radio Connection

    : Cable Connection

  • ROI-S04188

    - 39 -

    11.1.2 Modify Network Configuration

    11.1.2.1 Example 1 : Add New HOP in Subnet-4 1. Plan to add new HOP in Subnet-4.

    Figure 11.5 Network Example

    : RPM

    : CPM

    : SCPM

    R

    R : Router

    Subnet-1

    Subnet-2

    Subnet-3

    Subnet-4

    Subnet-5

    New Hop

    : Radio Connection

    : Cable Connection

    2. Decide the new PM Card mode(CPM, SCPM or RPM) (for example Figure 11.7).

    3. Create configuration file for new PM card and PNMS by Network Configuration tool.

    4. Export configuration file of each PM Card and PNMS to the directory set up in Network Configuration tool.

    5. Copy the configuration files of new PM Card from PNMS PC to PNMT and download them to new PM Card by PNMT and install new NE(ODU and IDU) on site.

    6. Download the modified configuration files to the existing PM Cards, Master PM Cards (SCPM of new NEs subnetwork and CPM which such SCPM is belonging) and a PM Card which is connecting new HOP physically) from PNMS. Refer to Figure 11.6. (Downloading from PNMT is also available. In this case copy the configuration files for each NE from PNMS PC to PNMT is required.)

    - Master PM Card (Sub-CPM in Subnet-4): Modify Network Configuration file to recognize the added new HOP. (System Configuration file is not necessary to be modified.)

    - Existing PM card connecting with new HOP physically : Modify System Configuration file to recognize connecting with new HOP. (Although Network Configuration file is also necessary to be modified, the network configuration file is automatically modified and downloaded from Master PM CARD (CPM or SCPM) to the RPM under it.)

    -Other PM Cards in this CPM cluster: Although Network Configuration file is necessary to be modified, the network configuration file is automatically modified and downloaded from Master PM CARD (CPM or SCPM) to each PM Cards under it. (System Configuration file is not necessary to be modified.)

  • ROI-S04188

    - 40 -

    Figure 11.6Network Example

    R

    Subnet-1

    Subnet-2

    Subnet-3

    Subnet-4

    Subnet-5

    New Hop

    : RPM

    : CPM

    : SCPM

    R : Router: Radio Connection

    : Cable Connection

    7. Update Network configuration file for PNMS using Update Network Configuration window function PNMS. After that it is possible to monitor and control added NE.

    Figure 11.7Network Example

    R

    Subnet-1

    Subnet-2

    Subnet-3

    Subnet-4

    Subnet-5

    : RPM

    : CPM

    : SCPM

    R : Router: Radio Connection

    : Cable Connection

  • ROI-S04188

    - 41 -

    11.1.2.2 Example 2 : Add New Subnetwork 1. Plan to add new subnetwork.

    Figure 11.8 Network Example

    R

    Subnet-1

    Subnet-2

    Subnet-3

    Subnet-4

    Subnet-5New Subnet

    : RPM

    : CPM

    : SCPM

    R : Router: Radio Connection

    : Cable Connection

    2. Decide the new PM Card mode (CPM, SCPM or RPM) (for example Figure 11.10).

    3. Create configuration file for new subnetwork and PNMS by Network Configuration tool.

    4. Export configuration file of each PM Card and PNMS to the directory set up in the to Network Configuration tool.

    5. Copy the configuration files of new PM Card from PNMS PC to PNMT and download the configuration file for new PM Card by PNMT and install new NE (ODU and IDU) on site.

    6. Download the modified configuration file, to the existing PM Card (Master PM Card (CPM which new subnetwork is belonging and all SCPMs in the CPM cluster.) and a PM Card which connecting with new HOP physically from PNMS. Refer to Figure 11.9. (Downloading from PNMT is also available. In this case copy the configuration files for each NE from PNMS PC to PNMT is required.)

    - Master PM CARD (CPM and all SCPMs in the CPM cluster): Modify Network Configuration file to recognized the added new subnetwork. (System Configuration file is not necessary to be modified.)

    - Existing PM Card connecting with new subnet physically: Modify System Configuration file to be recognized connecting new HOP. (Although Network Configuration file is also necessary to be modified, the network configuration file is automatically modified and downloaded from Master PM CARD (CPM or SCPM) to the RPM under it.)

    - Other PM Card in this CPM Cluster: Although Network Configuration file is necessary to be modified, the network configuration file is automatically modified and downloaded from Master PM CARD (CPM or SCPM) to the PM Card under it. (System Configuration file is not necessary to be modified.)

  • ROI-S04188

    - 42 -

    Figure 11.9Network Example

    R

    Subnet-1

    Subnet-2

    Subnet-3

    Subnet-4

    Subnet-5New Subnet

    : RPM

    : CPM

    : SCPM

    R : Router: Radio Connection

    : Cable Connection

    7. Update Network configuration file for PNMS by Update Network Configuration window function on PNMS. After that it is possible to monitor and control added subnetwork.

    Figure 11.10 Network Example

    R

    Subnet-1

    Subnet-2

    Subnet-3

    Subnet-4

    Subnet-5Subnet-6

    : RPM

    : CPM

    : SCPM

    R : Router: Radio Connection

    : Cable Connection

  • ROI-S04188

    - 43 -

    11.1.2.3 Example 3 : Modify Sub-Network Configuration 1. It is planed to be divided Subnet-2 into two subnetworks to consider future expansion.

    Figure11.11Network Example

    R

    Subnet-1

    Subnet-2

    Subnet-3

    Subnet-4

    Subnet-5

    New Subnet

    : RPM

    : CPM

    : SCPM

    R : Router: Radio Connection

    : Cable Connection

    2. Decide each PM Card mode according to new network configuration as shown

    Figure11.13.

    3. Create configuration file for PM Cards in modified subnetwork and for PNMS by Network Configuration tool.

    4. Export configuration file for each PM Card and for PNMS to the director set up in the Network Configuration tool.

    5. Download modified configuration file to associated all NEs in new subnetwork and the Master NE (CPM which new subnetwork is belonging and all SCPMs in the CPM cluster.) from PNMS. Refer to Figure 11.12. (Downloading from PNMT is also available. In this case copy the configuration files for each NE from PNMS PC to PNMT is required.)

    - Master PM CARD (CPM) and all SCPM in the CPM cluster : Modify Network Configuration file to be recognized to modification of sub-network configuration

    - All NEs in new subnetwork : Modify network configuration file and system configuration file

    - Other PM Card in this CPM Cluster: Although Network Configuration file is necessary to be modified, the network configuration file is automatically modified and downloaded from Master PM CARD (CPM or SCPM) to the PM Card under it. (System Configuration file is not necessary to be modified.)

  • ROI-S04188

    - 44 -

    Figure11.12Network Example

    R

    Subnet-1

    Subnet-2

    Subnet-3

    Subnet-4

    Subnet-5

    New Subnet

    : RPM

    : CPM

    : SCPM

    R : Router: Radio Connection

    : Cable Connection

    6. Update Network configuration file for PNMS by Update Network Configuration window function on PNMS. After that it is possible to monitor and control modified sub network.

    Figure11.13Network Example

    R

    Subnet-1

    Subnet-2

    Subnet-3

    Subnet-4

    Subnet-5

    New Subnet

    : RPM

    : CPM

    : SCPM

    R : Router: Radio Connection

    : Cable Connection

  • ROI-S04188

    - 45 -

    11.2 PNMS for UNIX

    11.2.1 Install PNMS 1. Install PASOLINK hardware.

    If the PASOLINK system exists with configuration file, skip Step 2 through Step 6.

    Figure11.14 Network Example

    : RPM

    : CPM

    : Radio Connection

    : Cable Connection

    PNMS Site

    : PC for Network configuration tool

    2. Decide each PM Card mode (for example Figure 11.15).

    Figure11.15 Network Example

    : RPM

    : CPM

    : Radio Connection

    : Cable Connection

    : SCPM

    PNMS Site

    : PC for Network configuration tool

    3. Create configuration file for each PM Card and for PNMS by Network Configuration tool on PC.

    4. Export configuration file of each PM Card and for PNMS to the directory set up in the Network Configuration tool.

    5. Copy the configuration files of each PM Card form PC (Network Configuration tool) to PNMT and download them to each PM Card on site using PNMT.

  • ROI-S04188

    - 46 -

    6. Upload the configuration file from PC (Network Configuration tool) to PNMS Work Station by FTP and import it into PNMS.

    Figure11.16 Network Example

    : RPM

    : CPM

    : Radio Connection

    : Cable Connection

    Upload Map file

    : PC for Network configuration tool

    7. Connect PNMS to CPM and confirm the connection. After that it is possible to monitor

    and control each NE.

    Figure11.17Network Example

    : RPM

    : CPM

    : SCPM

    R

    R : Router

    Subnet-1

    Subnet-2

    Subnet-3

    Subnet-4

    Subnet-5

    : PC for Network configuration tool

    : Radio Connection

    : Cable Connection

  • ROI-S04188

    - 47 -

    11.2.2 Modify Network Configuration

    11.2.2.1 Example 1 : Add New HOP in Subnet-4 1. Plan to add new HOP in Subnet-4.

    Figure 11.18 Network Example

    : RPM

    : CPM

    : SCPM

    R

    R : Router

    Subnet-1

    Subnet-2

    Subnet-3

    Subnet-4

    Subnet-5

    New Hop

    : PC for Network configuration tool

    2. Decide the new PM Card mode (CPM, SCPM or RPM) (for example Figure 11.20).

    3. Create configuration file for new PM card and PNMS by Network Configuration tool.

    4. Export configuration file of each PM Card and PNMS to the directory set up in the Network Configuration tool.

    5. Upload the configuration file of each PM Card and PNMS from PC (Network configuration tool) to PNMS Work Station by FTP and import it into PNMS.

    6. Copy the configuration files of new PM Card from PC (Network Configuration tool) to PNMT and download them to new PM Card by PNMT and install new NE (ODU and IDU) on site.

    7. Download the modified configuration files to the existing PM Cards, Master PM Cards (SCPM of new NEs subnetwork and CPM which such SCPM is belonging.) and a PM Card, which is connecting new HOP physically from PNMS. Refer to Figure 11.19. (Downloading from PNMT is also available. In this case copy the configuration files for each NE from PNMS PC to PNMT is required.)

    - Master PM Card (Sub-CPM in Subnet-4): Modify Network Configuration file to recognize the added new HOP (System Configuration file is not necessary to be modified.

    - Existing PM card connecting with new HOP physically : Modify System Configuration file to recognize connecting with new HOP (Although Network Configuration file is also necessary to be modified, the network configuration file is automatically modified and downloaded from Master PM CARD (CPM or SCPM) to the RPM under it.)

    - Other PM Cards in this CPM cluster: Although Network Configuration file is necessary to be modified, the network configuration file is automatically modified and downloaded from Master PM CARD (CPM or SCPM) to each PM Cards under it. (System Configuration file is not necessary to be modified.)

  • ROI-S04188

    - 48 -

    Figure 11.19Network Example

    : RPM

    : CPM

    : SCPM

    R

    R : Router

    Subnet-1

    Subnet-2

    Subnet-3

    Subnet-4

    Subnet-5

    New Hop

    : PC for Network configuration tool

    8. After that it is possible to monitor and control added NE.

    Figure 11.20Network Example

    : RPM

    : CPM

    : SCPM

    R

    R : Router

    Subnet-1

    Subnet-2

    Subnet-3

    Subnet-4

    Subnet-5

    : PC for Network configuration tool

  • ROI-S04188

    - 49 -

    11.2.2.2 Example 2 : Add New Subnetwork 1. Plan to add new subnetwork

    Figure 11.21 Network Example

    : RPM

    : CPM

    : SCPM

    R

    R : Router

    Subnet-1

    Subnet-2

    Subnet-3

    Subnet-4

    Subnet-5New Subnet

    : PC for Network configuration tool

    2. Decide the new PM Card mode (CPM, SCPM or RPM) (for example Figure 11.23).

    3. Create configuration file for new subnetwork and PNMS by Network Configuration tool.

    4. Export configuration file of each PM Card and PNMS to the directory set up in the Network Configuration tool.

    5. Upload the configuration file of each PM Card and PNMS from PC (Network Configuration tool) to PNMS Work Station by FTP and import it into PNMS.

    6. Copy the configuration files of new PM Card from PC (Network Configuration tool) to PNMT and download the configuration file for new PM Card by PNMT and install new NE (ODU and IDU)I on site.

    7. Download the modified configuration file, to the existing PM Card (Master PM Card (CPM which new subnetwork is belonging and all SCPMs in the CPM cluster.) and a PM Card which connecting with new HOP physically from PNMS Refer to Figure 11.22. (Downloading from PNMT is also available. In this case copy the configuration files for each NE from PNMS PC to PNMT is required.)

    -Master PM CARD (CPM and all SCPMs in the CPM cluster): Modify Network Configuration file to recognized the added new subnetwork. (System Configuration file is not necessary to be modified.)

    - Existing PM Card connecting with new subnet physically: Modify System Configuration file to be recognized connecting new HOP (Although Network Configuration file is also necessary to be modified, the network configuration file is automatically modified and downloaded from Master PM CARD (CPM or SCPM) to the RPM under it.)

    - Other PM Card in this CPM Cluster: Although Network Configuration file is necessary to be modified, the network configuration file is automatically modified and downloaded from Master PM CARD(CPM or SCPM) to the PM Card under it.) (System Configuration file is not necessary to be modified.)

  • ROI-S04188

    - 50 -

    Figure 11.22 Network Example

    : RPM

    : CPM

    : SCPM

    R

    R : Router

    Subnet-1

    Subnet-2

    Subnet-3

    Subnet-4

    Subnet-5New Subnet

    : PC for Network configuration tool

    8. After that it is possible to monitor and control added subnetwork.

    Figure 11.23 Network Example

    : RPM

    : CPM

    : SCPM

    R

    R : Router

    Subnet-1

    Subnet-2

    Subnet-3

    Subnet-4

    Subnet-5Subnet-6

    : PC for Network configuration tool

  • ROI-S04188

    - 51 -

    11.2.2.3 Example 3 : Modify Sub-Network Configuration 1. It is planed to be divided Subnet-2 into two subnetworks to consider future expansion.

    Figure11.24Network Example

    : RPM

    : CPM: SCPM

    R

    R : Router

    Subnet-1

    Subnet-2

    Subnet-3

    Subnet-4

    Subnet-5

    New Subnet

    : PC for Network configuration tool

    2. Decide each PM Card mode according to new network configuration as shown Figure11.26.

    3. Create configuration file for PM Cards in modified subnetwork and for PNMS by Network Configuration tool.

    4. Export configuration file for each PM Card and PNMS to the directory set up in the Network Configuration tool.

    5. Upload the configuration file for each PM Card and PNMS from PC(Network Configuration tool) to PNMS Work Station by FTP and import it into PNMS.

    6. Download modified configuration file to associated all NEs in new subnetwork and the Master NE (CPM which new subnetwork is belonging and all SCPMs in the CPM cluster) from PNMS. Refer to Figure 11.25. (Downloading from PNMT is also available. In this case copy the configuration files for each NE from PNMS PC to PNMT is required.)

    - Master PM CARD (CPM) and all SCPM in the CPM cluster : Modify Network Configuration file to be recognized to modification of sub-network configuration

    - All NEs in new subnetwork : Modify network configuration file and system configuration file

    - Other PM Card in this CPM Cluster: Although Network Configuration file is necessary to be modified, the network configuration file is automatically modified and downloaded from Master PM CARD(CPM or SCPM) to the PM Card under it. (System Configuration file is not necessary to be modified.)

  • ROI-S04188

    - 52 -

    Figure11.25Network Example

    : RPM

    : CPM: SCPM

    R

    R : Router

    Subnet-1

    Subnet-2

    Subnet-3

    Subnet-4

    Subnet-5

    New Subnet

    : PC for Network configuration tool

    7. After that it is possible to monitor and control modified sub network.

    Figure11.26Network Example

    : RPM

    : CPM: SCPM

    R

    R : Router

    Subnet-1

    Subnet-2

    Subnet-3

    Subnet-4

    Subnet-5

    New Subnet

    : PC for Network configuration tool

  • ROI-S04188

    - 53 -

    12. RELATED EQUIPMENT FOR PNMS

    12.1 HYB Converter

    The Hybrid converter is designed to convert serial interface, RS232C, RS422 and RS485 and to combine/divide communication signal simultaneously all in one unit. It is used for transmitting SV signal of PNMS through third party equipment.

    It is especially useful for PASOLINK multi-cluster network monitored and controlled by PNMS through third party equipment to convert interface and to combine or divide supervisory signal.

    Followings are the features of HYB Converter:

    Easy setting Interface, function and transmission speed. -> Selection of interface (RS232C/RS422/RS485), function (interface conversion or Combine/Divide) and transmission speed (9.6kbps/19.2kbps) is executed by front switch

    Interface Conversion function -> For each port, three physical interfaces may be selected: RS232C, RS422 and RS485. Following conversions are available. (1) RS232C form/to RS422 (2) RS232C from/to RS485 (3) RS422 from/to RS485

    Combine/Divide function -> Provide 7 communication ports, up to 1:6 (Maximum) combine/divide function is available

    Flexible function Setting -> In accordance with network configuration, flexible function setting is available at port level. (1) Interface conversion function only (2) Combine/Divide function only (3) Both Conversion and Combine/Divide function

    Figure 12.1 shows a example of using HYB converter in PNMS network.

    Central Site

    PNMS

    Remote Cluster-A

    3 41 2

    Remote Cluster-B

    7 8

    Remote Cluster-E

    5 6

    Remote Cluster-C

    MM

    M

    MM

    M

    M M

    M : MODEM / Other Microwave Radio Equipment2 : PASOLINK

    M M : Dedicated leased line / Digital Service Channel

    RS232C19.2/9.6kbps,Async

    RS232C, 9.6kbps, Async

    Provide 1:4 Divide/Combine function

    : Hybrid Converter

    5 6

    Remote Cluster-D

    M

    M

    RS232C, 9.6kbps, Async

    Figure 12.1 Network example using HYB CONV

  • ROI-S04188

    - 54 -

    12.2 Management Interface Unit (MIU)

    12.2.1 Main Feature MIU provides CPM function and together with HYB Converter it works to concentrate Supervisory signal from each PASOLINK (PM Card), which is scattered in different places as shown Figure 12.2. The detail is also described in section 9.8.

    ????

    ????

    RS-232 or RS485 9.6kbpsASYNC

    RS-232C/V.11 19.2kbpsASYNC

    orLAN(10BASE-T)

    PASOLINK CLUSTER

    PASOLINK CLUSTER

    R

    PNMS(UNIX or

    Windows NT)

    Existing Network (Dedicated line) 9.6 kbps, ASYNC

    RS232 port (In case of other than RS232C or RS485 port, additional converter is required in accordance with the physical interface)

    Figure 12.2 Multi cluster network through Digital Service Channel

    HYB

    CONV

    MIU

    RS-485 9.6kbpsASYNC

    12.2.2 Interface: (1) For PNMS: PNMS port

    Physical interface : RS232C (V.24) or RS422 (V.11) or LAN(10Base-T)

    Connector : DB 15pin (for RS23C/RS422) : RJ-45 (for LAN(10Base-T))

    Communication rate : 19.2 kbps (PPP, Asynchronous) (for RS23C/RS422)

    (2) For PNMT : PNMT port

    Physical interface : RS232C (V.24)

    Connector : DB 15pin

    Communication rate : 19.2 kbps (PPP, Asynchronous)

    (3) For Back to Back : EXP port

    Physical interface : RS485 (V.11)

    Connector : RJ 45

    Communication rate : 9.6 kbps (Asynchronous)

  • ROI-S04188

    - 55 -

    12.3 PNMS CABLE

    Following table shows cables for PNMS connection. In accordance with customers network configuration, the selection of suitable cable is required.

    Table 13.1 Cable List Cable Name How to use Pin Assignment LCT Figure 12.4 Figure 12.5 PNMT Figure 12.6 Figure 12.7 PNMT+LCT Figure 12.8 Figure 12.9 PNMS (serial connection) Figure 12.10,12.11 Figure 12.12 PNMS (LAN connection through Ethernet HUB)*1 Figure 12.13 Figure 12.14 PNMS (LAN connection through Router)*1 Figure 12.15 Figure 12.16 Back to Back (Point to point)

    -RS232C Figure 12.17 Figure 12.18 -RS485 Figure 12.17 Figure 12.19

    Back to Back (Point to multi-point) (1) Cascade connection Cable Figure 12.20 Figure 12.21 (2) Cascade connection Cable Figure 12.20 Figure 12.22 (3) Terminal connector Figure 12.20 Figure 12.23

    PNMS (Serial connection) + Back to Back (Point to multi-point)

    (1) Cascade connection Cable Figure 12.24 Figure 12.25 (2) Cascade connection Cable Figure 12.24 Figure 12