16. Rehabilitation and Mine Closure - · PDF fileArmour rock is required for erosion...
-
Upload
truongcong -
Category
Documents
-
view
212 -
download
0
Transcript of 16. Rehabilitation and Mine Closure - · PDF fileArmour rock is required for erosion...
Chapter 16
Mount Peake ProjectDraft Environmental Impact Statement
16.
16.1 The Project is expected to disturb a total area of approximately 1,060 habreakdown of area according to individual mine feature. In the context of rehabilitation and closure, these mine features can be broadly separated into two categories:
m
mbe rehabilitated.
The first category comprises the major earthwork mine componentsCombined, these three be approximately 77 ha in area, will remain as an open void and not be rehabilitated.
This leaves a total of approximately 98
Rehabilitation can be separated into two broad phases:
m
mconclusion of oper
Progressive rehabilitation is defined as rehabilitation that can be undertaken through the life of mine.However, arehabilitation of these features is not possible.rehabilitated during the life of mine, however the nature ofprogressive rehabilitation is not feasible. Justification for this position is as follows:
TSF
long term stockpiles
infrastructure
TNG has prepared a Conceptual Mine Closure Plan been prepared consistent with the Western Australian Environmenreleased in 2011.
Chapter 16 – Rehabilitation and Mine Closure
Mount Peake ProjectDraft Environmental Impact Statement
16. Rehabilitation and Mine Closure
BackgroundThe Project is expected to disturb a total area of approximately 1,060 habreakdown of area according to individual mine feature. In the context of rehabilitation and closure, these mine features can be broadly separated into two categories:
mine features that remain on site after closure, essentially in
mine features that are demolished and removed from site at closure, leaving a bare land surface to be rehabilitated.
The first category comprises the major earthwork mine componentsCombined, these three be approximately 77 ha in area, will remain as an open void and not be rehabilitated.
This leaves a total of approximately 98
Rehabilitation can be separated into two broad phases:
mine features where progressive rehabilitation methods can be applied; and
mine features that are fully operational until closureconclusion of oper
Progressive rehabilitation is defined as rehabilitation that can be undertaken through the life of mine.However, a number of mine features remain in operation until the very end of mine life, so progressive rehabilitation of these features is not possible.rehabilitated during the life of mine, however the nature ofprogressive rehabilitation is not feasible. Justification for this position is as follows:
TSF
ong term stockpiles
nfrastructure
TNG has prepared a Conceptual Mine Closure Plan been prepared consistent with the Western Australian Environmental Protection Authority (EPA) released in 2011.
Rehabilitation and Mine Closure
Mount Peake Project Draft Environmental Impact Statement
Rehabilitation and Mine Closure
Background The Project is expected to disturb a total area of approximately 1,060 habreakdown of area according to individual mine feature. In the context of rehabilitation and closure, these mine features can be broadly separated into two categories:
ine features that remain on site after closure, essentially in
ine features that are demolished and removed from site at closure, leaving a bare land surface to be rehabilitated.
The first category comprises the major earthwork mine componentsCombined, these three features comprise 642 ha or 60% of the total be approximately 77 ha in area, will remain as an open void and not be rehabilitated.
This leaves a total of approximately 98
Rehabilitation can be separated into two broad phases:
ine features where progressive rehabilitation methods can be applied; and
ine features that are fully operational until closureconclusion of operation.
Progressive rehabilitation is defined as rehabilitation that can be undertaken through the life of mine.number of mine features remain in operation until the very end of mine life, so progressive
rehabilitation of these features is not possible.rehabilitated during the life of mine, however the nature ofprogressive rehabilitation is not feasible. Justification for this position is as follows:
Tailings drequired for the tailings surfac
These ore stockpiles will be constructed according to grade and will largely function as an extension to the ROM. These stockpiles will allow blending of ore into the processing plant. that will be reclaimed towards the end of the mine life. At mine closure, all stockpiles will have been removed and the base pad arearehabilitation
nfrastructure This comprises primary mine infrastructure (process plant, power station, process water damborefield, access roads). closure. There is almost no ability to progressively rehabilitate parts of this infrastructure.
TNG has prepared a Conceptual Mine Closure Plan been prepared consistent with the Western Australian
tal Protection Authority (EPA) released in 2011. The DMP /
Rehabilitation and Mine Closure
Draft Environmental Impact Statement
Rehabilitation and Mine Closure
The Project is expected to disturb a total area of approximately 1,060 habreakdown of area according to individual mine feature. In the context of rehabilitation and closure, these mine features can be broadly separated into two categories:
ine features that remain on site after closure, essentially in
ine features that are demolished and removed from site at closure, leaving a bare land surface to
The first category comprises the major earthwork mine componentsfeatures comprise 642 ha or 60% of the total
be approximately 77 ha in area, will remain as an open void and not be rehabilitated.
This leaves a total of approximately 983 ha of land that requires rehabilitation
Rehabilitation can be separated into two broad phases:
ine features where progressive rehabilitation methods can be applied; and
ine features that are fully operational until closure
Progressive rehabilitation is defined as rehabilitation that can be undertaken through the life of mine.number of mine features remain in operation until the very end of mine life, so progressive
rehabilitation of these features is not possible.rehabilitated during the life of mine, however the nature ofprogressive rehabilitation is not feasible. Justification for this position is as follows:
Tailings deposition will continue until the site closes. A period of time is then required for the tailings surfac
These ore stockpiles will be constructed according to grade and will largely function as an extension to the ROM. These stockpiles will allow blending of ore into the processing plant. that will be reclaimed towards the end of the mine life. At mine closure, all stockpiles will have been removed and the base pad arearehabilitation.
comprises primary mine infrastructure (process plant, power station, process water dam, rail siding) as well as ancillary infrastructure (accommodation village, borefield, access roads).
There is almost no ability to progressively rehabilitate parts of this infrastructure.
TNG has prepared a Conceptual Mine Closure Plan been prepared consistent with the Western Australian
tal Protection Authority (EPA) / EPA released a revised version of this Guideline in May 2015.
Rehabilitation and Mine Closure
The Project is expected to disturb a total area of approximately 1,060 habreakdown of area according to individual mine feature. In the context of rehabilitation and closure, these mine features can be broadly separated into two categories:
ine features that remain on site after closure, essentially in
ine features that are demolished and removed from site at closure, leaving a bare land surface to
The first category comprises the major earthwork mine componentsfeatures comprise 642 ha or 60% of the total
be approximately 77 ha in area, will remain as an open void and not be rehabilitated.
ha of land that requires rehabilitation
Rehabilitation can be separated into two broad phases:
ine features where progressive rehabilitation methods can be applied; and
ine features that are fully operational until closure
Progressive rehabilitation is defined as rehabilitation that can be undertaken through the life of mine.number of mine features remain in operation until the very end of mine life, so progressive
rehabilitation of these features is not possible. Portions of the WRD can potentially be progressively rehabilitated during the life of mine, however the nature ofprogressive rehabilitation is not feasible. Justification for this position is as follows:
eposition will continue until the site closes. A period of time is then required for the tailings surface to dry sufficiently to allow vehicle movement.
These ore stockpiles will be constructed according to grade and will largely function as an extension to the ROM. These stockpiles will allow blending of ore into the processing plant. They will also provide a storage area for low grade ore that will be reclaimed towards the end of the mine life. At mine closure, all stockpiles will have been removed and the base pad area
comprises primary mine infrastructure (process plant, power station, process ) as well as ancillary infrastructure (accommodation village,
borefield, access roads). This infrastructure is required to be operational until mine There is almost no ability to progressively rehabilitate parts of this
TNG has prepared a Conceptual Mine Closure Plan (MCP) been prepared consistent with the Western Australian
tal Protection Authority (EPA) Guidelines for preparing mine closure plansEPA released a revised version of this Guideline in May 2015.
Rehabilitation and Mine Closure
The Project is expected to disturb a total area of approximately 1,060 habreakdown of area according to individual mine feature. In the context of rehabilitation and closure, these mine features can be broadly separated into two categories:
ine features that remain on site after closure, essentially in perpetuity; and
ine features that are demolished and removed from site at closure, leaving a bare land surface to
The first category comprises the major earthwork mine componentsfeatures comprise 642 ha or 60% of the total
be approximately 77 ha in area, will remain as an open void and not be rehabilitated.
ha of land that requires rehabilitation
Rehabilitation can be separated into two broad phases:
ine features where progressive rehabilitation methods can be applied; and
ine features that are fully operational until closure, so rehabilitation can only commence at the
Progressive rehabilitation is defined as rehabilitation that can be undertaken through the life of mine.number of mine features remain in operation until the very end of mine life, so progressive
Portions of the WRD can potentially be progressively rehabilitated during the life of mine, however the nature of most of the other mine features are such that progressive rehabilitation is not feasible. Justification for this position is as follows:
eposition will continue until the site closes. A period of time is then e to dry sufficiently to allow vehicle movement.
These ore stockpiles will be constructed according to grade and will largely function as an extension to the ROM. These stockpiles will allow blending of ore
They will also provide a storage area for low grade ore that will be reclaimed towards the end of the mine life. At mine closure, all stockpiles will have been removed and the base pad area
comprises primary mine infrastructure (process plant, power station, process ) as well as ancillary infrastructure (accommodation village,
his infrastructure is required to be operational until mine There is almost no ability to progressively rehabilitate parts of this
(MCP) for the projectbeen prepared consistent with the Western Australian Department of Mi
Guidelines for preparing mine closure plansEPA released a revised version of this Guideline in May 2015.
Rehabilitation and Mine Closure
The Project is expected to disturb a total area of approximately 1,060 ha. Table 2breakdown of area according to individual mine feature. In the context of rehabilitation and closure, these
perpetuity; and
ine features that are demolished and removed from site at closure, leaving a bare land surface to
The first category comprises the major earthwork mine components; the open pit, the WRD and the TSFfeatures comprise 642 ha or 60% of the total Project envelope. The pit, which will
be approximately 77 ha in area, will remain as an open void and not be rehabilitated.
ha of land that requires rehabilitation at
ine features where progressive rehabilitation methods can be applied; and
, so rehabilitation can only commence at the
Progressive rehabilitation is defined as rehabilitation that can be undertaken through the life of mine.number of mine features remain in operation until the very end of mine life, so progressive
Portions of the WRD can potentially be progressively most of the other mine features are such that
progressive rehabilitation is not feasible. Justification for this position is as follows:
eposition will continue until the site closes. A period of time is then e to dry sufficiently to allow vehicle movement.
These ore stockpiles will be constructed according to grade and will largely function as an extension to the ROM. These stockpiles will allow blending of ore
They will also provide a storage area for low grade ore that will be reclaimed towards the end of the mine life. At mine closure, all stockpiles will have been removed and the base pad area will be
comprises primary mine infrastructure (process plant, power station, process ) as well as ancillary infrastructure (accommodation village,
his infrastructure is required to be operational until mine There is almost no ability to progressively rehabilitate parts of this
for the project (Appendix MDepartment of Mines and Petroleum (DMP) and
Guidelines for preparing mine closure plansEPA released a revised version of this Guideline in May 2015.
. Table 2-2 provides a breakdown of area according to individual mine feature. In the context of rehabilitation and closure, these
perpetuity; and
ine features that are demolished and removed from site at closure, leaving a bare land surface to
the open pit, the WRD and the TSFoject envelope. The pit, which will
be approximately 77 ha in area, will remain as an open void and not be rehabilitated.
at closure.
ine features where progressive rehabilitation methods can be applied; and
, so rehabilitation can only commence at the
Progressive rehabilitation is defined as rehabilitation that can be undertaken through the life of mine.number of mine features remain in operation until the very end of mine life, so progressive
Portions of the WRD can potentially be progressively most of the other mine features are such that
progressive rehabilitation is not feasible. Justification for this position is as follows:
eposition will continue until the site closes. A period of time is then e to dry sufficiently to allow vehicle movement.
These ore stockpiles will be constructed according to grade and will largely function as an extension to the ROM. These stockpiles will allow blending of ore
They will also provide a storage area for low grade ore that will be reclaimed towards the end of the mine life. At mine closure, all
will be available for
comprises primary mine infrastructure (process plant, power station, process ) as well as ancillary infrastructure (accommodation village,
his infrastructure is required to be operational until mine There is almost no ability to progressively rehabilitate parts of this
ppendix M). This MCP has nes and Petroleum (DMP) and
Guidelines for preparing mine closure plans, originally EPA released a revised version of this Guideline in May 2015.
16
2 provides a breakdown of area according to individual mine feature. In the context of rehabilitation and closure, these
ine features that are demolished and removed from site at closure, leaving a bare land surface to
the open pit, the WRD and the TSFoject envelope. The pit, which will
, so rehabilitation can only commence at the
Progressive rehabilitation is defined as rehabilitation that can be undertaken through the life of mine. number of mine features remain in operation until the very end of mine life, so progressive
Portions of the WRD can potentially be progressively most of the other mine features are such that
eposition will continue until the site closes. A period of time is then e to dry sufficiently to allow vehicle movement.
These ore stockpiles will be constructed according to grade and will largely function as an extension to the ROM. These stockpiles will allow blending of ore
They will also provide a storage area for low grade ore that will be reclaimed towards the end of the mine life. At mine closure, all
available for
comprises primary mine infrastructure (process plant, power station, process ) as well as ancillary infrastructure (accommodation village,
his infrastructure is required to be operational until mine There is almost no ability to progressively rehabilitate parts of this
This MCP has nes and Petroleum (DMP) and
, originally EPA released a revised version of this Guideline in May 2015.
16-1
breakdown of area according to individual mine feature. In the context of rehabilitation and closure, these
ine features that are demolished and removed from site at closure, leaving a bare land surface to
the open pit, the WRD and the TSF. oject envelope. The pit, which will
number of mine features remain in operation until the very end of mine life, so progressive
most of the other mine features are such that
his infrastructure is required to be operational until mine
This MCP has nes and Petroleum (DMP) and
Chapter 16
Mount Peake ProjectDraft Environmental Impact Statement
16.2 The key rehabilitation objectives for the
aw
p
16.3
16.3.1
Rehabilitation and closure can be
Progressive
Closure
Post closure
As described in Section remain active until closure. However, progressive rehabilitation can occur in places suborrow pits, embankments of the WRD and TSF and disused access tracks.
At closure, decommissioning, demolition and removal of the bulk of the process plant infrastructure, power station and the majority of the accommodation village can landforms (WRD and open pit) can also occur.
The size and scale of demolition and rehabilitation works, the weather (wet and dry seasons) and the TSF, that needs to dry sufficiently before rehabilitation works can beclosure and rehabilitation works often need to be scheduled over a number of years.
This extended closure period also requires maintaining some essential infrastructure at the site post closure, to support successive campaiworks
a
pfacilities; and
a
16.3.2
ClearingVegetation clearing in advance of mine activities needs to be managed to ensure clearing is confined tthe appropriate area and any specific locations to be avoided are identified and protected. Clearing be managed through an internal clearing procedure contained in the site
A key aspect to consider for cleared and stockpiled vegetrehabilitation. The primary role of reinstated vegetation debris is to provide a seed store (if directly reapplied) and also as fauna habitat. Storage for longer than a few days or weeks at most, means that any attached seed pods will usually have dried out and dropped their seed, negating this benefit.
Chapter 16 – Rehabilitation and Mine Closure
Mount Peake ProjectDraft Environmental Impact Statement
ObjectivesThe key rehabilitation objectives for the
as far as practicable, rehabilitation achieves a stable and functioning landform which is comparable with the surrounding landscape and other environmental values; and
prevent and mitigat
Rehabilitation and
16.3.1 Closure Planning Phases
Rehabilitation and closure can be
Progressive
Closure
Post closure
As described in Section remain active until closure. However, progressive rehabilitation can occur in places suborrow pits, embankments of the WRD and TSF and disused access tracks.
At closure, decommissioning, demolition and removal of the bulk of the process plant infrastructure, power station and the majority of the accommodation village can landforms (WRD and open pit) can also occur.
The size and scale of demolition and rehabilitation works, the weather (wet and dry seasons) and the TSF, that needs to dry sufficiently before rehabilitation works can beclosure and rehabilitation works often need to be scheduled over a number of years.
This extended closure period also requires maintaining some essential infrastructure at the site post closure, to support successive campai
s. At a minimum, this infrastructure is likely to include:
a portion of the accommodation village that remains connected to the WWTP;
power generation to power the accommodation village, comfacilities; and
a water supply bore that allows a potable water supply to be produced.
16.3.2 Rehabilitation Techniques
Clearing Vegetation clearing in advance of mine activities needs to be managed to ensure clearing is confined tthe appropriate area and any specific locations to be avoided are identified and protected. Clearing
managed through an internal clearing procedure contained in the site
A key aspect to consider for cleared and stockpiled vegetrehabilitation. The primary role of reinstated vegetation debris is to provide a seed store (if directly reapplied) and also as fauna habitat. Storage for longer than a few days or weeks at most, means that
ny attached seed pods will usually have dried out and dropped their seed, negating this benefit.
Rehabilitation and Mine Closure
Mount Peake Project Draft Environmental Impact Statement
Objectives The key rehabilitation objectives for the
s far as practicable, rehabilitation achieves a stable and functioning landform which is comparable ith the surrounding landscape and other environmental values; and
and mitigate risks assoc
Rehabilitation and
Closure Planning Phases
Rehabilitation and closure can be
During the operational (life of mine) phase.
At or immediately after the mine ceases to operate.
For a number of number of years rather than being undertaken as a single, uninterrupted exercise.
As described in Section 16.1, the Mt Peake mine configuration is such that most of the mine features remain active until closure. However, progressive rehabilitation can occur in places suborrow pits, embankments of the WRD and TSF and disused access tracks.
At closure, decommissioning, demolition and removal of the bulk of the process plant infrastructure, power station and the majority of the accommodation village can landforms (WRD and open pit) can also occur.
The size and scale of demolition and rehabilitation works, the weather (wet and dry seasons) and the TSF, that needs to dry sufficiently before rehabilitation works can beclosure and rehabilitation works often need to be scheduled over a number of years.
This extended closure period also requires maintaining some essential infrastructure at the site post closure, to support successive campai
. At a minimum, this infrastructure is likely to include:
portion of the accommodation village that remains connected to the WWTP;
ower generation to power the accommodation village, com
water supply bore that allows a potable water supply to be produced.
Rehabilitation Techniques
Vegetation clearing in advance of mine activities needs to be managed to ensure clearing is confined tthe appropriate area and any specific locations to be avoided are identified and protected. Clearing
managed through an internal clearing procedure contained in the site
A key aspect to consider for cleared and stockpiled vegetrehabilitation. The primary role of reinstated vegetation debris is to provide a seed store (if directly reapplied) and also as fauna habitat. Storage for longer than a few days or weeks at most, means that
ny attached seed pods will usually have dried out and dropped their seed, negating this benefit.
Rehabilitation and Mine Closure
Draft Environmental Impact Statement
The key rehabilitation objectives for the Project are:
s far as practicable, rehabilitation achieves a stable and functioning landform which is comparable ith the surrounding landscape and other environmental values; and
risks associated with closure and rehabilitation of the Project.
Rehabilitation and Closure
Closure Planning Phases
Rehabilitation and closure can be broken into the following key mine phases:
During the operational (life of mine) phase.
At or immediately after the mine ceases to operate.
For a number of reasons, mine closure works number of years rather than being undertaken as a single, uninterrupted exercise.
, the Mt Peake mine configuration is such that most of the mine features remain active until closure. However, progressive rehabilitation can occur in places suborrow pits, embankments of the WRD and TSF and disused access tracks.
At closure, decommissioning, demolition and removal of the bulk of the process plant infrastructure, power station and the majority of the accommodation village can landforms (WRD and open pit) can also occur.
The size and scale of demolition and rehabilitation works, the weather (wet and dry seasons) and the TSF, that needs to dry sufficiently before rehabilitation works can beclosure and rehabilitation works often need to be scheduled over a number of years.
This extended closure period also requires maintaining some essential infrastructure at the site post closure, to support successive campaigns of contractors mobilising to site to conduct a program of
. At a minimum, this infrastructure is likely to include:
portion of the accommodation village that remains connected to the WWTP;
ower generation to power the accommodation village, com
water supply bore that allows a potable water supply to be produced.
Rehabilitation Techniques
Vegetation clearing in advance of mine activities needs to be managed to ensure clearing is confined tthe appropriate area and any specific locations to be avoided are identified and protected. Clearing
managed through an internal clearing procedure contained in the site
A key aspect to consider for cleared and stockpiled vegetrehabilitation. The primary role of reinstated vegetation debris is to provide a seed store (if directly reapplied) and also as fauna habitat. Storage for longer than a few days or weeks at most, means that
ny attached seed pods will usually have dried out and dropped their seed, negating this benefit.
roject are:
s far as practicable, rehabilitation achieves a stable and functioning landform which is comparable ith the surrounding landscape and other environmental values; and
iated with closure and rehabilitation of the Project.
losure Planning
broken into the following key mine phases:
During the operational (life of mine) phase.
At or immediately after the mine ceases to operate.
reasons, mine closure works number of years rather than being undertaken as a single, uninterrupted exercise.
, the Mt Peake mine configuration is such that most of the mine features remain active until closure. However, progressive rehabilitation can occur in places suborrow pits, embankments of the WRD and TSF and disused access tracks.
At closure, decommissioning, demolition and removal of the bulk of the process plant infrastructure, power station and the majority of the accommodation village can landforms (WRD and open pit) can also occur.
The size and scale of demolition and rehabilitation works, the weather (wet and dry seasons) and the TSF, that needs to dry sufficiently before rehabilitation works can beclosure and rehabilitation works often need to be scheduled over a number of years.
This extended closure period also requires maintaining some essential infrastructure at the site post gns of contractors mobilising to site to conduct a program of
. At a minimum, this infrastructure is likely to include:
portion of the accommodation village that remains connected to the WWTP;
ower generation to power the accommodation village, com
water supply bore that allows a potable water supply to be produced.
Vegetation clearing in advance of mine activities needs to be managed to ensure clearing is confined tthe appropriate area and any specific locations to be avoided are identified and protected. Clearing
managed through an internal clearing procedure contained in the site
A key aspect to consider for cleared and stockpiled vegetrehabilitation. The primary role of reinstated vegetation debris is to provide a seed store (if directly reapplied) and also as fauna habitat. Storage for longer than a few days or weeks at most, means that
ny attached seed pods will usually have dried out and dropped their seed, negating this benefit.
s far as practicable, rehabilitation achieves a stable and functioning landform which is comparable ith the surrounding landscape and other environmental values; and
iated with closure and rehabilitation of the Project.
lanning
broken into the following key mine phases:
During the operational (life of mine) phase.
At or immediately after the mine ceases to operate.
reasons, mine closure works often number of years rather than being undertaken as a single, uninterrupted exercise.
, the Mt Peake mine configuration is such that most of the mine features remain active until closure. However, progressive rehabilitation can occur in places suborrow pits, embankments of the WRD and TSF and disused access tracks.
At closure, decommissioning, demolition and removal of the bulk of the process plant infrastructure, power station and the majority of the accommodation village can occur. Rehabilitation of completed mine
The size and scale of demolition and rehabilitation works, the weather (wet and dry seasons) and the TSF, that needs to dry sufficiently before rehabilitation works can beclosure and rehabilitation works often need to be scheduled over a number of years.
This extended closure period also requires maintaining some essential infrastructure at the site post gns of contractors mobilising to site to conduct a program of
. At a minimum, this infrastructure is likely to include:
portion of the accommodation village that remains connected to the WWTP;
ower generation to power the accommodation village, communications and water treatment
water supply bore that allows a potable water supply to be produced.
Vegetation clearing in advance of mine activities needs to be managed to ensure clearing is confined tthe appropriate area and any specific locations to be avoided are identified and protected. Clearing
managed through an internal clearing procedure contained in the site
A key aspect to consider for cleared and stockpiled vegetation is the storage time before its rerehabilitation. The primary role of reinstated vegetation debris is to provide a seed store (if directly reapplied) and also as fauna habitat. Storage for longer than a few days or weeks at most, means that
ny attached seed pods will usually have dried out and dropped their seed, negating this benefit.
s far as practicable, rehabilitation achieves a stable and functioning landform which is comparable ith the surrounding landscape and other environmental values; and
iated with closure and rehabilitation of the Project.
broken into the following key mine phases:
At or immediately after the mine ceases to operate.
often need to be scheduled over a number of years rather than being undertaken as a single, uninterrupted exercise.
, the Mt Peake mine configuration is such that most of the mine features remain active until closure. However, progressive rehabilitation can occur in places suborrow pits, embankments of the WRD and TSF and disused access tracks.
At closure, decommissioning, demolition and removal of the bulk of the process plant infrastructure, occur. Rehabilitation of completed mine
The size and scale of demolition and rehabilitation works, the weather (wet and dry seasons) and the TSF, that needs to dry sufficiently before rehabilitation works can be undertaken, are all reasons why closure and rehabilitation works often need to be scheduled over a number of years.
This extended closure period also requires maintaining some essential infrastructure at the site post gns of contractors mobilising to site to conduct a program of
portion of the accommodation village that remains connected to the WWTP;
munications and water treatment
water supply bore that allows a potable water supply to be produced.
Vegetation clearing in advance of mine activities needs to be managed to ensure clearing is confined tthe appropriate area and any specific locations to be avoided are identified and protected. Clearing
managed through an internal clearing procedure contained in the site Construction EMP.
ation is the storage time before its rerehabilitation. The primary role of reinstated vegetation debris is to provide a seed store (if directly reapplied) and also as fauna habitat. Storage for longer than a few days or weeks at most, means that
ny attached seed pods will usually have dried out and dropped their seed, negating this benefit.
s far as practicable, rehabilitation achieves a stable and functioning landform which is comparable
iated with closure and rehabilitation of the Project.
need to be scheduled over a number of years rather than being undertaken as a single, uninterrupted exercise.
, the Mt Peake mine configuration is such that most of the mine features remain active until closure. However, progressive rehabilitation can occur in places such as completed
At closure, decommissioning, demolition and removal of the bulk of the process plant infrastructure, occur. Rehabilitation of completed mine
The size and scale of demolition and rehabilitation works, the weather (wet and dry seasons) and the undertaken, are all reasons why
closure and rehabilitation works often need to be scheduled over a number of years.
This extended closure period also requires maintaining some essential infrastructure at the site post gns of contractors mobilising to site to conduct a program of
portion of the accommodation village that remains connected to the WWTP;
munications and water treatment
Vegetation clearing in advance of mine activities needs to be managed to ensure clearing is confined tthe appropriate area and any specific locations to be avoided are identified and protected. Clearing
Construction EMP.
ation is the storage time before its rerehabilitation. The primary role of reinstated vegetation debris is to provide a seed store (if directly reapplied) and also as fauna habitat. Storage for longer than a few days or weeks at most, means that
ny attached seed pods will usually have dried out and dropped their seed, negating this benefit.
16
s far as practicable, rehabilitation achieves a stable and functioning landform which is comparable
need to be scheduled over a number of years rather than being undertaken as a single, uninterrupted exercise.
, the Mt Peake mine configuration is such that most of the mine features ch as completed
At closure, decommissioning, demolition and removal of the bulk of the process plant infrastructure, occur. Rehabilitation of completed mine
The size and scale of demolition and rehabilitation works, the weather (wet and dry seasons) and the undertaken, are all reasons why
This extended closure period also requires maintaining some essential infrastructure at the site post gns of contractors mobilising to site to conduct a program of
munications and water treatment
Vegetation clearing in advance of mine activities needs to be managed to ensure clearing is confined to the appropriate area and any specific locations to be avoided are identified and protected. Clearing will
Construction EMP.
ation is the storage time before its re-use in rehabilitation. The primary role of reinstated vegetation debris is to provide a seed store (if directly reapplied) and also as fauna habitat. Storage for longer than a few days or weeks at most, means that
ny attached seed pods will usually have dried out and dropped their seed, negating this benefit.
16-2
s far as practicable, rehabilitation achieves a stable and functioning landform which is comparable
ch as completed
occur. Rehabilitation of completed mine
o will
reapplied) and also as fauna habitat. Storage for longer than a few days or weeks at most, means that
Chapter 16
Mount Peake ProjectDraft Environmental Impact Statement
TopsoilFor the purpose of this document, topsoil is defined as the soil profile that contains the majority of the seed store, organic matter and biological (the depth of topsoil layer. In a mining context, the practical depth to which earthmoving equipment is able to remove a layer generally determines the topsoil 100 –
Topsoil storage methods topsoil stockpiles of approximately 2 m high minimise the potential of composting and anaerobic conditions formi
Storage time is another key factor. It is generally recognised the storage time is inversely proportional to topsoil viability (activity).
Materials for In addition to topsoil, which is required for all mine features, some mine features require a supply of specific material. Competent rock is required for the following purposes:
adischarges and to protect sections of the base of elevated landforms and abandonment bunds that are subject to erosion from surface floodwaters. Armour rock used for these purposes is usually in th
athe pit void to prevent vehicular access. To reduce the potential of erosion of these features over time that then allows vehicle entry, these features are required to be construct(rocky) material.
RippingA number or ripping methods and types of bulldozer rippers (tines) are used in mine rehabilitation. All ripping should be done on contour, to maximise resistance to surface water flow.
Break soil compaction
Depencreated from earthmoving equipment, ripping to depths of 1.0 plant roots and water to penetrate the soil profile to depth. lateral wings used to break compaction on floors of bauxite mine pits. A single or multiple tines without wings can also be successfully used to break soil compaction in dry soil conditions.
Chapter 16 – Rehabilitation and Mine Closure
Mount Peake ProjectDraft Environmental Impact Statement
Topsoil For the purpose of this document, topsoil is defined as the soil profile that contains the majority of the seed store, organic matter and biological (the depth of topsoil layer. In a mining context, the practical depth to which earthmoving equipment is able to remove a layer generally determines the topsoil
– 200 mm.
Topsoil storage methods topsoil stockpiles of approximately 2 m high minimise the potential of composting and anaerobic conditions forming at depth.
Storage time is another key factor. It is generally recognised the storage time is inversely proportional to topsoil viability (i.e.activity).
Materials for RehabilitationIn addition to topsoil, which is required for all mine features, some mine features require a supply of specific material. Competent rock is required for the following purposes:
armour rock. Armour rock is required for erosion protection on discharges and to protect sections of the base of elevated landforms and abandonment bunds that are subject to erosion from surface floodwaters. Armour rock used for these purposes is usually in the order of 300
abandonment bundsthe pit void to prevent vehicular access. To reduce the potential of erosion of these features over time that then allows vehicle entry, these features are required to be construct(rocky) material.
Ripping A number or ripping methods and types of bulldozer rippers (tines) are used in mine rehabilitation. All ripping should be done on contour, to maximise resistance to surface water flow.
Break soil compaction
Depending on the extent of soil compaction created from earthmoving equipment, ripping to depths of 1.0 – 1.5plant roots and water to penetrate the soil profile to depth. Figure 16lateral wings used to break compaction on floors of bauxite mine pits. A single or multiple tines without wings can also be successfully used to break soil compaction in dry soil conditions.
Rehabilitation and Mine Closure
Mount Peake Project Draft Environmental Impact Statement
For the purpose of this document, topsoil is defined as the soil profile that contains the majority of the seed store, organic matter and biological (the depth of topsoil layer. In a mining context, the practical depth to which earthmoving equipment is able to remove a layer generally determines the topsoil
Topsoil storage methods are atopsoil stockpiles of approximately 2 m high minimise the potential of composting and anaerobic
ng at depth.
Storage time is another key factor. It is generally recognised the storage time is inversely proportional to i.e. the longer the storage time, the greater the loss of seed viability and biological
Rehabilitation In addition to topsoil, which is required for all mine features, some mine features require a supply of specific material. Competent rock is required for the following purposes:
. Armour rock is required for erosion protection on discharges and to protect sections of the base of elevated landforms and abandonment bunds that are subject to erosion from surface floodwaters. Armour rock used for these purposes is usually in
e order of 300 – 500 mm diameter; and
bandonment bunds. An abandonment bund is required to be constructed around the perimeter of the pit void to prevent vehicular access. To reduce the potential of erosion of these features over time that then allows vehicle entry, these features are required to be construct(rocky) material.
A number or ripping methods and types of bulldozer rippers (tines) are used in mine rehabilitation. All ripping should be done on contour, to maximise resistance to surface water
Break soil compaction
ding on the extent of soil compaction created from earthmoving equipment, ripping to
1.5 m will occurplant roots and water to penetrate the soil profile
16-1 shows a single tine with lateral wings used to break compaction on floors of bauxite mine pits. A single or multiple tines without wings can also be successfully used to break soil compaction in dry soil conditions.
Rehabilitation and Mine Closure
Draft Environmental Impact Statement
For the purpose of this document, topsoil is defined as the soil profile that contains the majority of the seed store, organic matter and biological (the depth of topsoil layer. In a mining context, the practical depth to which earthmoving equipment is able to remove a layer generally determines the topsoil
a key factor in maximising topsoil viability. It is generally recognised that topsoil stockpiles of approximately 2 m high minimise the potential of composting and anaerobic
Storage time is another key factor. It is generally recognised the storage time is inversely proportional to the longer the storage time, the greater the loss of seed viability and biological
In addition to topsoil, which is required for all mine features, some mine features require a supply of specific material. Competent rock is required for the following purposes:
. Armour rock is required for erosion protection on discharges and to protect sections of the base of elevated landforms and abandonment bunds that are subject to erosion from surface floodwaters. Armour rock used for these purposes is usually in
mm diameter; and
. An abandonment bund is required to be constructed around the perimeter of the pit void to prevent vehicular access. To reduce the potential of erosion of these features over time that then allows vehicle entry, these features are required to be construct
A number or ripping methods and types of bulldozer rippers (tines) are used in mine rehabilitation. All ripping should be done on contour, to maximise resistance to surface water
ding on the extent of soil compaction created from earthmoving equipment, ripping to
will occur. This allows plant roots and water to penetrate the soil profile
shows a single tine with lateral wings used to break compaction on floors of bauxite mine pits. A single or multiple tines without wings can also be successfully used to break soil compaction in dry soil conditions.
For the purpose of this document, topsoil is defined as the soil profile that contains the majority of the seed store, organic matter and biological (bacterial and fungthe depth of topsoil layer. In a mining context, the practical depth to which earthmoving equipment is able to remove a layer generally determines the topsoil depth
key factor in maximising topsoil viability. It is generally recognised that topsoil stockpiles of approximately 2 m high minimise the potential of composting and anaerobic
Storage time is another key factor. It is generally recognised the storage time is inversely proportional to the longer the storage time, the greater the loss of seed viability and biological
In addition to topsoil, which is required for all mine features, some mine features require a supply of specific material. Competent rock is required for the following purposes:
. Armour rock is required for erosion protection on discharges and to protect sections of the base of elevated landforms and abandonment bunds that are subject to erosion from surface floodwaters. Armour rock used for these purposes is usually in
mm diameter; and
. An abandonment bund is required to be constructed around the perimeter of the pit void to prevent vehicular access. To reduce the potential of erosion of these features over time that then allows vehicle entry, these features are required to be construct
A number or ripping methods and types of bulldozer rippers (tines) are used in mine rehabilitation. All ripping should be done on contour, to maximise resistance to surface water
ding on the extent of soil compaction created from earthmoving equipment, ripping to
. This allows plant roots and water to penetrate the soil profile
shows a single tine with lateral wings used to break compaction on floors of bauxite mine pits. A single or multiple tines without wings can also be successfully used to break soil
Figure
For the purpose of this document, topsoil is defined as the soil profile that contains the majority of the bacterial and fungal) activity. There is no universal definition of
the depth of topsoil layer. In a mining context, the practical depth to which earthmoving equipment is able depth. In most mining operati
key factor in maximising topsoil viability. It is generally recognised that topsoil stockpiles of approximately 2 m high minimise the potential of composting and anaerobic
Storage time is another key factor. It is generally recognised the storage time is inversely proportional to the longer the storage time, the greater the loss of seed viability and biological
In addition to topsoil, which is required for all mine features, some mine features require a supply of specific material. Competent rock is required for the following purposes:
. Armour rock is required for erosion protection on discharges and to protect sections of the base of elevated landforms and abandonment bunds that are subject to erosion from surface floodwaters. Armour rock used for these purposes is usually in
. An abandonment bund is required to be constructed around the perimeter of the pit void to prevent vehicular access. To reduce the potential of erosion of these features over time that then allows vehicle entry, these features are required to be construct
of bauxite mine pits. A single or multiple tines without wings can also be successfully used to break soil
Figure 16-1
For the purpose of this document, topsoil is defined as the soil profile that contains the majority of the ) activity. There is no universal definition of
the depth of topsoil layer. In a mining context, the practical depth to which earthmoving equipment is able most mining operati
key factor in maximising topsoil viability. It is generally recognised that topsoil stockpiles of approximately 2 m high minimise the potential of composting and anaerobic
Storage time is another key factor. It is generally recognised the storage time is inversely proportional to the longer the storage time, the greater the loss of seed viability and biological
In addition to topsoil, which is required for all mine features, some mine features require a supply of specific material. Competent rock is required for the following purposes:
. Armour rock is required for erosion protection on drainage diversion structures, spillway discharges and to protect sections of the base of elevated landforms and abandonment bunds that are subject to erosion from surface floodwaters. Armour rock used for these purposes is usually in
. An abandonment bund is required to be constructed around the perimeter of the pit void to prevent vehicular access. To reduce the potential of erosion of these features over time that then allows vehicle entry, these features are required to be construct
of bauxite mine pits. A single or multiple tines without wings can also be successfully used to break soil
Single lateral winged tine
For the purpose of this document, topsoil is defined as the soil profile that contains the majority of the ) activity. There is no universal definition of
the depth of topsoil layer. In a mining context, the practical depth to which earthmoving equipment is able most mining operations this is accepted at
key factor in maximising topsoil viability. It is generally recognised that topsoil stockpiles of approximately 2 m high minimise the potential of composting and anaerobic
Storage time is another key factor. It is generally recognised the storage time is inversely proportional to the longer the storage time, the greater the loss of seed viability and biological
In addition to topsoil, which is required for all mine features, some mine features require a supply of
drainage diversion structures, spillway discharges and to protect sections of the base of elevated landforms and abandonment bunds that are subject to erosion from surface floodwaters. Armour rock used for these purposes is usually in
. An abandonment bund is required to be constructed around the perimeter of the pit void to prevent vehicular access. To reduce the potential of erosion of these features over time that then allows vehicle entry, these features are required to be constructed of competent
of bauxite mine pits. A single or multiple tines without wings can also be successfully used to break soil
ingle lateral winged tine
16
For the purpose of this document, topsoil is defined as the soil profile that contains the majority of the ) activity. There is no universal definition of
the depth of topsoil layer. In a mining context, the practical depth to which earthmoving equipment is able ons this is accepted at
key factor in maximising topsoil viability. It is generally recognised that topsoil stockpiles of approximately 2 m high minimise the potential of composting and anaerobic
Storage time is another key factor. It is generally recognised the storage time is inversely proportional to the longer the storage time, the greater the loss of seed viability and biological
In addition to topsoil, which is required for all mine features, some mine features require a supply of
drainage diversion structures, spillway discharges and to protect sections of the base of elevated landforms and abandonment bunds that are subject to erosion from surface floodwaters. Armour rock used for these purposes is usually in
. An abandonment bund is required to be constructed around the perimeter of the pit void to prevent vehicular access. To reduce the potential of erosion of these features over
ed of competent
of bauxite mine pits. A single or multiple tines without wings can also be successfully used to break soil
ingle lateral winged tine
16-3
) activity. There is no universal definition of the depth of topsoil layer. In a mining context, the practical depth to which earthmoving equipment is able
ons this is accepted at
Storage time is another key factor. It is generally recognised the storage time is inversely proportional to
drainage diversion structures, spillway discharges and to protect sections of the base of elevated landforms and abandonment bunds that are subject to erosion from surface floodwaters. Armour rock used for these purposes is usually in
. An abandonment bund is required to be constructed around the perimeter of
of bauxite mine pits. A single or multiple tines without wings can also be successfully used to break soil
Chapter 16
Mount Peake ProjectDraft Environmental Impact Statement
Water and seed containment on slopes
At Mountpushed down during rehabilitation using a bulldozer to the final batter angle of situation is different tocompacted. Soil compaction on the embankments of these landforms is not likely to achieve the same compaction as pit floor
Retaining rainfall and applvegetation establishment and reducerip to depths of approximately 0.6 and applied seed on slopes. Furrows from this tine are shown in
Figure
Figure
Chapter 16 – Rehabilitation and Mine Closure
Mount Peake ProjectDraft Environmental Impact Statement
Water and seed containment on slopes
ount Peake, the pushed down during rehabilitation using a bulldozer to the final batter angle of situation is different tocompacted. Soil compaction on the embankments of these landforms is not likely to achieve the same compaction as pit floor
Retaining rainfall and applvegetation establishment and reduce
to depths of approximately 0.6 and applied seed on slopes. Furrows from this tine are shown in
Figure 16-2 Single vertical winged tine
Figure 16-4 Three tine
Rehabilitation and Mine Closure
Mount Peake Project Draft Environmental Impact Statement
Water and seed containment on slopes
Peake, the WRD and ROMpushed down during rehabilitation using a bulldozer to the final batter angle of situation is different to pit floors that have been traversed repeatedly by mine equipment and are highly compacted. Soil compaction on the embankments of these landforms is not likely to achieve the same compaction as pit floors.
Retaining rainfall and applyingvegetation establishment and reduce
to depths of approximately 0.6 and applied seed on slopes. Furrows from this tine are shown in
Single vertical winged tine
Three tine ripper
Rehabilitation and Mine Closure
Draft Environmental Impact Statement
Water and seed containment on slopes
WRD and ROM pad will bepushed down during rehabilitation using a bulldozer to the final batter angle of
pit floors that have been traversed repeatedly by mine equipment and are highly compacted. Soil compaction on the embankments of these landforms is not likely to achieve the same
ying seed and fertilisevegetation establishment and reduced erosion.
to depths of approximately 0.6 – 0.8m but to produce a wide open furrow capable of holding water and applied seed on slopes. Furrows from this tine are shown in
Single vertical winged tine
ripper
pad will be constructed from tipped mine waste which is then pushed down during rehabilitation using a bulldozer to the final batter angle of
pit floors that have been traversed repeatedly by mine equipment and are highly compacted. Soil compaction on the embankments of these landforms is not likely to achieve the same
seed and fertiliser on these slopes erosion. Figure
0.8m but to produce a wide open furrow capable of holding water and applied seed on slopes. Furrows from this tine are shown in
Single vertical winged tine
constructed from tipped mine waste which is then pushed down during rehabilitation using a bulldozer to the final batter angle of
pit floors that have been traversed repeatedly by mine equipment and are highly compacted. Soil compaction on the embankments of these landforms is not likely to achieve the same
r on these slopes Figure 16-2 shows a tine with vertical wings designed to
0.8m but to produce a wide open furrow capable of holding water and applied seed on slopes. Furrows from this tine are shown in Figure
Figure 16-3
Figure 16-5
constructed from tipped mine waste which is then pushed down during rehabilitation using a bulldozer to the final batter angle of
pit floors that have been traversed repeatedly by mine equipment and are highly compacted. Soil compaction on the embankments of these landforms is not likely to achieve the same
r on these slopes are key criteria in achieving successful shows a tine with vertical wings designed to
0.8m but to produce a wide open furrow capable of holding water Figure 16-3.
3 Winged tine furrows
5 Rip spacing
constructed from tipped mine waste which is then pushed down during rehabilitation using a bulldozer to the final batter angle of less than 20
pit floors that have been traversed repeatedly by mine equipment and are highly compacted. Soil compaction on the embankments of these landforms is not likely to achieve the same
key criteria in achieving successful shows a tine with vertical wings designed to
0.8m but to produce a wide open furrow capable of holding water
Winged tine furrows
Rip spacing
16
constructed from tipped mine waste which is then 20o. This
pit floors that have been traversed repeatedly by mine equipment and are highly compacted. Soil compaction on the embankments of these landforms is not likely to achieve the same
key criteria in achieving successful shows a tine with vertical wings designed to
0.8m but to produce a wide open furrow capable of holding water
Winged tine furrows
16-4
pit floors that have been traversed repeatedly by mine equipment and are highly compacted. Soil compaction on the embankments of these landforms is not likely to achieve the same
key criteria in achieving successful shows a tine with vertical wings designed to
Chapter 16
Mount Peake ProjectDraft Environmental Impact Statement
Using a single tine on a ‘trackbetween rip furrows is flattened by the bulldozer trackswhere landforms can include large rocks. In these situations, ripping can bring these rocks to the surface. Multiple tines hook these rocks and the dozer drags them, creating a deep this risk as the rock is usually turned by the tine with minimal earth displacement.
On WRD’s that do not consist of minimum of two winged tines behind each track. This would eliminate the embankment. Use of a third tine improved water holding and spacing using double tines (solid lines) and triple tines (dotted line). The dozer passes arthe previous pass so not to drive over previous rip lines.
Seed and FertiliserWhere seeding is specified, the following criteria apply:
swhich
s
fertiliser may be applied to maximise the success of plant growth. Seed and fertiliser application will be preferably done in oappropriate.
16.3.3
As the site is yet to commence operations, no defined list of trials and studies has yet been determined. There is a clear need to implement some rehabilitation programmes early in the project’s life, in order to establish a monitoring life of mine with a successful track record.
16.3.4
Completion criteria are necessary to provide the basis on which successful rehabilitation and mine closure, and achievements of cldeveloped from the closure objectives, in order to provide distinct and measurable criteria for successful rehabilitation of the Mount Peake operation.
Completion criteria allow for verificatifeatures final design and rehabilitation. Verification methods include monitoring results, management audits, design signselected to allow quantitative assessment of rehabilitation performance.
At the current early stage of the mine’s life, it is unrealistic to establish final completion criteria. Results of progressive rehabilitation and monitoring of other mine feathat the stated criteria can be achieved. Therefore, interim completion criteria have been proposed. Target (final) completion criteria have also been documented. Future versions of the MCP will review these cr
The MCP includes a table that identifies closure objectives, completion criteria and measurement tools for each mine feature. An abbreviated version of this table
Chapter 16 – Rehabilitation and Mine Closure
Mount Peake ProjectDraft Environmental Impact Statement
Using a single tine on a ‘trackbetween rip furrows is flattened by the bulldozer trackswhere landforms can include large rocks. In these situations, ripping can bring these rocks to the surface. Multiple tines hook these rocks and the dozer drags them, creating a deep
s risk as the rock is usually turned by the tine with minimal earth displacement.
On WRD’s that do not consist of minimum of two winged tines behind each track. This would eliminate the embankment. Use of a third tine improved water holding and spacing using double tines (solid lines) and triple tines (dotted line). The dozer passes arthe previous pass so not to drive over previous rip lines.
Seed and FertiliserWhere seeding is specified, the following criteria apply:
surfaces that have been covered with topsoil and ripped will be seeded with local native species which are compatible with other species in the area;
seeding will be carried out prior to the onset of the main rainfall period; and
ertiliser may be applied to maximise the success of plant growth. Seed and fertiliser application will be preferably done in oappropriate.
16.3.3 Future Trials and Studies
As the site is yet to commence operations, no defined list of trials and studies has yet been determined. There is a clear need to implement some rehabilitation programmes early in the project’s life, in order to establish a monitoring life of mine with a successful track record.
16.3.4 Completion Criteria
Completion criteria are necessary to provide the basis on which successful rehabilitation and mine closure, and achievements of cldeveloped from the closure objectives, in order to provide distinct and measurable criteria for successful rehabilitation of the Mount Peake operation.
Completion criteria allow for verificatifeatures final design and rehabilitation. Verification methods include monitoring results, management audits, design signselected to allow quantitative assessment of rehabilitation performance.
At the current early stage of the mine’s life, it is unrealistic to establish final completion criteria. Results of progressive rehabilitation and monitoring of other mine feathat the stated criteria can be achieved. Therefore, interim completion criteria have been proposed. Target (final) completion criteria have also been documented. Future versions of the MCP will review these criteria against the developing body of closure knowledge and revise the criteria if necessary.
The MCP includes a table that identifies closure objectives, completion criteria and measurement tools for each mine feature. An abbreviated version of this table
Rehabilitation and Mine Closure
Mount Peake Project Draft Environmental Impact Statement
Using a single tine on a ‘trackbetween rip furrows is flattened by the bulldozer trackswhere landforms can include large rocks. In these situations, ripping can bring these rocks to the surface. Multiple tines hook these rocks and the dozer drags them, creating a deep
s risk as the rock is usually turned by the tine with minimal earth displacement.
On WRD’s that do not consist of minimum of two winged tines behind each track. This would eliminate the embankment. Use of a third tine improved water holding and seed retention surface thaspacing using double tines (solid lines) and triple tines (dotted line). The dozer passes arthe previous pass so not to drive over previous rip lines.
Seed and Fertiliser Where seeding is specified, the following criteria apply:
urfaces that have been covered with topsoil and ripped will be seeded with local native species are compatible with other species in the area;
eeding will be carried out prior to the onset of the main rainfall period; and
ertiliser may be applied to maximise the success of plant growth. Seed and fertiliser application will be preferably done in one pass with ripping to reduce soil compaction if hand seeding is not
Future Trials and Studies
As the site is yet to commence operations, no defined list of trials and studies has yet been determined. There is a clear need to implement some rehabilitation programmes early in the project’s life, in order to establish a monitoring – feedback life of mine with a successful track record.
Completion Criteria
Completion criteria are necessary to provide the basis on which successful rehabilitation and mine closure, and achievements of cldeveloped from the closure objectives, in order to provide distinct and measurable criteria for successful rehabilitation of the Mount Peake operation.
Completion criteria allow for verificatifeatures final design and rehabilitation. Verification methods include monitoring results, management audits, design sign-off and comparison against reference documents. selected to allow quantitative assessment of rehabilitation performance.
At the current early stage of the mine’s life, it is unrealistic to establish final completion criteria. Results of progressive rehabilitation and monitoring of other mine feathat the stated criteria can be achieved. Therefore, interim completion criteria have been proposed. Target (final) completion criteria have also been documented. Future versions of the MCP will review
iteria against the developing body of closure knowledge and revise the criteria if necessary.
The MCP includes a table that identifies closure objectives, completion criteria and measurement tools for each mine feature. An abbreviated version of this table
Rehabilitation and Mine Closure
Draft Environmental Impact Statement
Using a single tine on a ‘track-to-track’ ripping method has a disadvantage in that the intervening space between rip furrows is flattened by the bulldozer trackswhere landforms can include large rocks. In these situations, ripping can bring these rocks to the surface. Multiple tines hook these rocks and the dozer drags them, creating a deep
s risk as the rock is usually turned by the tine with minimal earth displacement.
On WRD’s that do not consist of large rockyminimum of two winged tines behind each track. This would eliminate the embankment. Use of a third tine (Figure 16
seed retention surface thaspacing using double tines (solid lines) and triple tines (dotted line). The dozer passes arthe previous pass so not to drive over previous rip lines.
Where seeding is specified, the following criteria apply:
urfaces that have been covered with topsoil and ripped will be seeded with local native species are compatible with other species in the area;
eeding will be carried out prior to the onset of the main rainfall period; and
ertiliser may be applied to maximise the success of plant growth. Seed and fertiliser application will ne pass with ripping to reduce soil compaction if hand seeding is not
Future Trials and Studies
As the site is yet to commence operations, no defined list of trials and studies has yet been determined. There is a clear need to implement some rehabilitation programmes early in the project’s life, in order to
feedback – improvelife of mine with a successful track record.
Completion Criteria
Completion criteria are necessary to provide the basis on which successful rehabilitation and mine closure, and achievements of closure objectives are determined. Completion criteria have been developed from the closure objectives, in order to provide distinct and measurable criteria for successful rehabilitation of the Mount Peake operation.
Completion criteria allow for verification of environmental outcomes for the features final design and rehabilitation. Verification methods include monitoring results, management
off and comparison against reference documents. selected to allow quantitative assessment of rehabilitation performance.
At the current early stage of the mine’s life, it is unrealistic to establish final completion criteria. Results of progressive rehabilitation and monitoring of other mine feathat the stated criteria can be achieved. Therefore, interim completion criteria have been proposed. Target (final) completion criteria have also been documented. Future versions of the MCP will review
iteria against the developing body of closure knowledge and revise the criteria if necessary.
The MCP includes a table that identifies closure objectives, completion criteria and measurement tools for each mine feature. An abbreviated version of this table
track’ ripping method has a disadvantage in that the intervening space between rip furrows is flattened by the bulldozer trackswhere landforms can include large rocks. In these situations, ripping can bring these rocks to the surface. Multiple tines hook these rocks and the dozer drags them, creating a deep
s risk as the rock is usually turned by the tine with minimal earth displacement.
large rocky mine waste, minimum of two winged tines behind each track. This would eliminate the
16-4) may be trialled, to determine if the final profile provides an seed retention surface tha
spacing using double tines (solid lines) and triple tines (dotted line). The dozer passes arthe previous pass so not to drive over previous rip lines.
Where seeding is specified, the following criteria apply:
urfaces that have been covered with topsoil and ripped will be seeded with local native species are compatible with other species in the area;
eeding will be carried out prior to the onset of the main rainfall period; and
ertiliser may be applied to maximise the success of plant growth. Seed and fertiliser application will ne pass with ripping to reduce soil compaction if hand seeding is not
As the site is yet to commence operations, no defined list of trials and studies has yet been determined. There is a clear need to implement some rehabilitation programmes early in the project’s life, in order to
improvement cycle to life of mine with a successful track record.
Completion criteria are necessary to provide the basis on which successful rehabilitation and mine osure objectives are determined. Completion criteria have been
developed from the closure objectives, in order to provide distinct and measurable criteria for successful rehabilitation of the Mount Peake operation.
on of environmental outcomes for the features final design and rehabilitation. Verification methods include monitoring results, management
off and comparison against reference documents. selected to allow quantitative assessment of rehabilitation performance.
At the current early stage of the mine’s life, it is unrealistic to establish final completion criteria. Results of progressive rehabilitation and monitoring of other mine feathat the stated criteria can be achieved. Therefore, interim completion criteria have been proposed. Target (final) completion criteria have also been documented. Future versions of the MCP will review
iteria against the developing body of closure knowledge and revise the criteria if necessary.
The MCP includes a table that identifies closure objectives, completion criteria and measurement tools for each mine feature. An abbreviated version of this table
track’ ripping method has a disadvantage in that the intervening space between rip furrows is flattened by the bulldozer tracks. However, where landforms can include large rocks. In these situations, ripping can bring these rocks to the surface. Multiple tines hook these rocks and the dozer drags them, creating a deep
s risk as the rock is usually turned by the tine with minimal earth displacement.
mine waste, multiple winged tines are recommended, with a minimum of two winged tines behind each track. This would eliminate the
ay be trialled, to determine if the final profile provides an seed retention surface than two tines.
spacing using double tines (solid lines) and triple tines (dotted line). The dozer passes arthe previous pass so not to drive over previous rip lines.
Where seeding is specified, the following criteria apply:
urfaces that have been covered with topsoil and ripped will be seeded with local native species are compatible with other species in the area;
eeding will be carried out prior to the onset of the main rainfall period; and
ertiliser may be applied to maximise the success of plant growth. Seed and fertiliser application will ne pass with ripping to reduce soil compaction if hand seeding is not
As the site is yet to commence operations, no defined list of trials and studies has yet been determined. There is a clear need to implement some rehabilitation programmes early in the project’s life, in order to
ment cycle to develop rehabilitation prescriptions over the
Completion criteria are necessary to provide the basis on which successful rehabilitation and mine osure objectives are determined. Completion criteria have been
developed from the closure objectives, in order to provide distinct and measurable criteria for successful
on of environmental outcomes for the features final design and rehabilitation. Verification methods include monitoring results, management
off and comparison against reference documents. selected to allow quantitative assessment of rehabilitation performance.
At the current early stage of the mine’s life, it is unrealistic to establish final completion criteria. Results of progressive rehabilitation and monitoring of other mine features is required before that the stated criteria can be achieved. Therefore, interim completion criteria have been proposed. Target (final) completion criteria have also been documented. Future versions of the MCP will review
iteria against the developing body of closure knowledge and revise the criteria if necessary.
The MCP includes a table that identifies closure objectives, completion criteria and measurement tools for each mine feature. An abbreviated version of this table is provided
track’ ripping method has a disadvantage in that the intervening space However, this single tine technique is preferred
where landforms can include large rocks. In these situations, ripping can bring these rocks to the surface. Multiple tines hook these rocks and the dozer drags them, creating a deep gully.
s risk as the rock is usually turned by the tine with minimal earth displacement.
multiple winged tines are recommended, with a minimum of two winged tines behind each track. This would eliminate the track print on the landform
ay be trialled, to determine if the final profile provides an two tines. Figure 16-5
spacing using double tines (solid lines) and triple tines (dotted line). The dozer passes ar
urfaces that have been covered with topsoil and ripped will be seeded with local native species
eeding will be carried out prior to the onset of the main rainfall period; and
ertiliser may be applied to maximise the success of plant growth. Seed and fertiliser application will ne pass with ripping to reduce soil compaction if hand seeding is not
As the site is yet to commence operations, no defined list of trials and studies has yet been determined. There is a clear need to implement some rehabilitation programmes early in the project’s life, in order to
develop rehabilitation prescriptions over the
Completion criteria are necessary to provide the basis on which successful rehabilitation and mine osure objectives are determined. Completion criteria have been
developed from the closure objectives, in order to provide distinct and measurable criteria for successful
on of environmental outcomes for the Project area as well as each features final design and rehabilitation. Verification methods include monitoring results, management
off and comparison against reference documents. Measurement tools haselected to allow quantitative assessment of rehabilitation performance.
At the current early stage of the mine’s life, it is unrealistic to establish final completion criteria. Results of tures is required before
that the stated criteria can be achieved. Therefore, interim completion criteria have been proposed. Target (final) completion criteria have also been documented. Future versions of the MCP will review
iteria against the developing body of closure knowledge and revise the criteria if necessary.
The MCP includes a table that identifies closure objectives, completion criteria and measurement tools is provided Table 16
track’ ripping method has a disadvantage in that the intervening space this single tine technique is preferred
where landforms can include large rocks. In these situations, ripping can bring these rocks to the surface. gully. The single tine reduces
s risk as the rock is usually turned by the tine with minimal earth displacement.
multiple winged tines are recommended, with a track print on the landform
ay be trialled, to determine if the final profile provides an 5 shows a conceptual rip
spacing using double tines (solid lines) and triple tines (dotted line). The dozer passes are off
urfaces that have been covered with topsoil and ripped will be seeded with local native species
eeding will be carried out prior to the onset of the main rainfall period; and
ertiliser may be applied to maximise the success of plant growth. Seed and fertiliser application will ne pass with ripping to reduce soil compaction if hand seeding is not
As the site is yet to commence operations, no defined list of trials and studies has yet been determined. There is a clear need to implement some rehabilitation programmes early in the project’s life, in order to
develop rehabilitation prescriptions over the
Completion criteria are necessary to provide the basis on which successful rehabilitation and mine osure objectives are determined. Completion criteria have been
developed from the closure objectives, in order to provide distinct and measurable criteria for successful
roject area as well as each features final design and rehabilitation. Verification methods include monitoring results, management
Measurement tools ha
At the current early stage of the mine’s life, it is unrealistic to establish final completion criteria. Results of tures is required before TNG can be confident
that the stated criteria can be achieved. Therefore, interim completion criteria have been proposed. Target (final) completion criteria have also been documented. Future versions of the MCP will review
iteria against the developing body of closure knowledge and revise the criteria if necessary.
The MCP includes a table that identifies closure objectives, completion criteria and measurement tools 16-1.
16
track’ ripping method has a disadvantage in that the intervening space this single tine technique is preferred
where landforms can include large rocks. In these situations, ripping can bring these rocks to the surface. The single tine reduces
multiple winged tines are recommended, with a track print on the landform
ay be trialled, to determine if the final profile provides an shows a conceptual rip
e off-set from
urfaces that have been covered with topsoil and ripped will be seeded with local native species
ertiliser may be applied to maximise the success of plant growth. Seed and fertiliser application will ne pass with ripping to reduce soil compaction if hand seeding is not
As the site is yet to commence operations, no defined list of trials and studies has yet been determined. There is a clear need to implement some rehabilitation programmes early in the project’s life, in order to
develop rehabilitation prescriptions over the
Completion criteria are necessary to provide the basis on which successful rehabilitation and mine osure objectives are determined. Completion criteria have been
developed from the closure objectives, in order to provide distinct and measurable criteria for successful
roject area as well as each features final design and rehabilitation. Verification methods include monitoring results, management
Measurement tools have been
At the current early stage of the mine’s life, it is unrealistic to establish final completion criteria. Results of can be confident
that the stated criteria can be achieved. Therefore, interim completion criteria have been proposed. Target (final) completion criteria have also been documented. Future versions of the MCP will review
iteria against the developing body of closure knowledge and revise the criteria if necessary.
The MCP includes a table that identifies closure objectives, completion criteria and measurement tools
16-5
track’ ripping method has a disadvantage in that the intervening space this single tine technique is preferred
where landforms can include large rocks. In these situations, ripping can bring these rocks to the surface. The single tine reduces
multiple winged tines are recommended, with a
ay be trialled, to determine if the final profile provides an shows a conceptual rip
set from
ertiliser may be applied to maximise the success of plant growth. Seed and fertiliser application will
As the site is yet to commence operations, no defined list of trials and studies has yet been determined. There is a clear need to implement some rehabilitation programmes early in the project’s life, in order to
develop rehabilitation prescriptions over the
developed from the closure objectives, in order to provide distinct and measurable criteria for successful
roject area as well as each
At the current early stage of the mine’s life, it is unrealistic to establish final completion criteria. Results of can be confident
The MCP includes a table that identifies closure objectives, completion criteria and measurement tools
Mount Peake ProjectDraft Environmental Impact Statement
Table
Chapter 16 – Rehabilitation and Mine Closure
Mount Peake ProjectDraft Environmental Impact Statement
Table 16-1 Closure objectives and criteria
Domain Mine feature
All General / site wide
1 Open pit
2 WRD and ROM pad
3 TSF
4 Process plant and power station
5 Rail siding
Rehabilitation and Mine Closure
Mount Peake Project Draft Environmental Impact Statement
Closure objectives and criteria
eature Interim c
General / site Hazardous environmental impact.Infrastructure removed.Disturbed areas rehabilitated.
Open pit Abandonment bund effectively restricts access to open pit. Abandonment bund is constructed in accordance with the Safety Bund Walls Mines Guidelines (DoI
WRD and ROM pad
The landform is stable and safe.There areor salt in the vicinity of the landform.
The landform is stable and safe.Erosion of any waste rock cap does not liberate tailings material.Stability assessment defined procedures or standards.Water quality parameters in groundwater monitoring bores do not exceed values representative of analogue sites andThere are no mass vegetation deaths in the vicinity of the landform.
Process plant and power station
Hazardous materials confined to prevent off site environmental impact.Infrastructure removed.Disturbed areas rehabilitated.
Rail siding All infrastructure not subject to a sequential use agreement is removed.Disturbed areas rehabilitated.
Rehabilitation and Mine Closure
Draft Environmental Impact Statement
Closure objectives and criteria
completion criteria
Hazardous materials confined to prevent off site environmental impact. Infrastructure removed. Disturbed areas rehabilitated.Abandonment bund effectively restricts access to open pit. Abandonment bund is constructed in accordance with the Safety Bund Walls Around Mines Guidelines (DoIR 1997).The landform is stable and safe.There are no mass vegetation deaths caused by AMD or salt in the vicinity of the landform.
The landform is stable and safe.Erosion of any waste rock cap does not liberate tailings material. Stability assessment undertaken in accordance with defined procedures or standards.Water quality parameters in groundwater monitoring bores do not exceed values representative of analogue sites and / or baseline data.There are no mass vegetation deaths in the vicinity of
landform. Hazardous materials confined to prevent off site environmental impact. Infrastructure removed. Disturbed areas rehabilitated.All infrastructure not subject to a sequential use agreement is removed. Disturbed areas rehabilitated.
materials confined to prevent off site
Disturbed areas rehabilitated. Abandonment bund effectively restricts access to
Abandonment bund is constructed in accordance with round Abandoned Open Pit
R 1997). The landform is stable and safe.
no mass vegetation deaths caused by AMD or salt in the vicinity of the landform.
The landform is stable and safe. Erosion of any waste rock cap does not liberate
undertaken in accordance with defined procedures or standards. Water quality parameters in groundwater monitoring bores do not exceed values representative of
or baseline data. There are no mass vegetation deaths in the vicinity of
Hazardous materials confined to prevent off site
Disturbed areas rehabilitated. All infrastructure not subject to a sequential use
Disturbed areas rehabilitated.
Measurement
materials confined to prevent off site Contaminated sites audit. Decommissioning audit to confirm initial rehabilitation works have been constructed according to design. Rehabilitation monitoring results.
Abandonment bund effectively restricts access to
Abandonment bund is constructed in accordance with Open Pit
Visual inspections and completed checklist.Decommissioning audit to confirm initial rehabilitation works have been constructed according to design.
no mass vegetation deaths caused by AMD Stability assessment undertaken in accordance with defined procedures.Visual inspections and completed checklist.Decommissioning audit to confirm initial rehabilitation worconstructed according to design. Rehabilitation monitoring results
Erosion of any waste rock cap does not liberate
undertaken in accordance with
Water quality parameters in groundwater monitoring
There are no mass vegetation deaths in the vicinity of
Stability assessment undertaken in accordance with defined procedures or standards. TSF monitoring register to be maintainedVisual inspections and completed checklist.Water quality monitoring results. Water quality records of local surface Rehabilitation monitoring results
Hazardous materials confined to prevent off site Contaminated sites audit. Decommissioningconstructed according to design. Rehabilitation monitoring results.
All infrastructure not subject to a sequential use Decommissioning auditconstructed according to design. Rehabilitation monitoring results.
Measurement tools / performance indicators
Contaminated sites audit. Decommissioning audit to confirm initial rehabilitation works have been constructed according to design. Rehabilitation monitoring results.Visual inspections and completed checklist.Decommissioning audit to confirm initial rehabilitation works have been constructed according to design.
Stability assessment undertaken in accordance with defined procedures.Visual inspections and completed checklist.Decommissioning audit to confirm initial rehabilitation worconstructed according to design. Rehabilitation monitoring resultsStability assessment undertaken in accordance with defined procedures or standards. TSF monitoring register to be maintainedVisual inspections and completed checklist.Water quality monitoring results. Water quality records of local surface Rehabilitation monitoring results
Contaminated sites audit. Decommissioning audit to confirm initial rehabilitation works have been constructed according to design. Rehabilitation monitoring results.Decommissioning audit to confirm initial rehabilitation works have been constructed according to design. Rehabilitation monitoring results.
erformance indicators
Decommissioning audit to confirm initial rehabilitation works have been constructed according to design. Complete audit inspection checklist.Rehabilitation monitoring results. Visual inspections and completed checklist. Decommissioning audit to confirm initial rehabilitation works have been constructed according to design. Complete audit inspection checklist.
Stability assessment undertaken in accordance with defined procedures.Visual inspections and completed checklist. Decommissioning audit to confirm initial rehabilitation worconstructed according to design. Complete audit inspection checklist.Rehabilitation monitoring results. Stability assessment undertaken in accordance with defined procedures or
TSF monitoring register to be maintained. Visual inspections and completed checklist. Water quality monitoring results. Water quality records of local surface and ground water.Rehabilitation monitoring results
to confirm initial rehabilitation works have been constructed according to design. Complete audit inspection checklist.Rehabilitation monitoring results.
to confirm initial rehabilitation works have been constructed according to design. Complete audit inspection checklist.Rehabilitation monitoring results.
Decommissioning audit to confirm initial rehabilitation works have been audit inspection checklist.
Decommissioning audit to confirm initial rehabilitation works have been Complete audit inspection checklist.
Stability assessment undertaken in accordance with defined procedures.
Decommissioning audit to confirm initial rehabilitation works have been Complete audit inspection checklist.
Stability assessment undertaken in accordance with defined procedures or
and ground water.
to confirm initial rehabilitation works have been Complete audit inspection checklist.
to confirm initial rehabilitation works have been Complete audit inspection checklist.
16-6
Decommissioning audit to confirm initial rehabilitation works have been audit inspection checklist.
Decommissioning audit to confirm initial rehabilitation works have been Complete audit inspection checklist.
Stability assessment undertaken in accordance with defined procedures.
ks have been Complete audit inspection checklist.
Stability assessment undertaken in accordance with defined procedures or
to confirm initial rehabilitation works have been Complete audit inspection checklist.
to confirm initial rehabilitation works have been Complete audit inspection checklist.
Mount Peake ProjectDraft Environmental Impact Statement
Chapter 16 – Rehabilitation and Mine Closure
Mount Peake ProjectDraft Environmental Impact Statement
Domain Mine feature
6 Access road
7 Bore field
8 Pipelines and power lines
9 Ancillary infrastructure areas
Rehabilitation and Mine Closure
Mount Peake Project Draft Environmental Impact Statement
eature Interim c
Access road Roads are reshaped in order to redrainage lines and waters are not impounded.Roads required for monitoring and maintenance are in useable condition.Rehabilitated road areas are stable and non
Bore field All infrastructure removed.Rehabilitated areas are stable and non
Pipelines and power lines
Above ground pipelines, pumping and power infrastructure are removed.Buried pipelines are flushed, emptied, grouted at either end and buried at least 600 mm below the surface.
Ancillary infrastructure
All infrastructure, mobile plant, transportable structures and consumables are removed. Concrete is buried to a depth of at least 1 m below ground level.
Rehabilitation and Mine Closure
Draft Environmental Impact Statement
completion criteria
Roads are reshaped in order to redrainage lines and waters are not impounded.Roads required for monitoring and maintenance are in useable condition. Rehabilitated road areas are stable and nonAll infrastructure removed. Rehabilitated areas are stable and non
Above ground pipelines, pumping and power tructure are removed.
Buried pipelines are flushed, emptied, grouted at either end and buried at least 600 mm below the surface. All infrastructure, mobile plant, transportable structures and consumables are removed. Concrete is buried to a depth of at least 1 m below ground level.
Roads are reshaped in order to re-instate natural drainage lines and waters are not impounded. Roads required for monitoring and maintenance are in
Rehabilitated road areas are stable and non-eroding.
Rehabilitated areas are stable and non-eroding.
Above ground pipelines, pumping and power tructure are removed.
Buried pipelines are flushed, emptied, grouted at either end and buried at least 600 mm below the
All infrastructure, mobile plant, transportable structures and consumables are removed. Concrete is buried to a depth of at least 1 m below
Measurement
instate natural
Roads required for monitoring and maintenance are in
eroding.
Visual inspections and completed checklist.Decommissioning audit toconstructed according to design. Rehabilitation monitoring results
eroding. Visual inspections and completed checklist.Decommissioning audit to confirm initial rehabilitation works have been constructed according to design.
Buried pipelines are flushed, emptied, grouted at either end and buried at least 600 mm below the
Decommissioning audit to confirm initial rehabilitation works have been constructed according to design.
Concrete is buried to a depth of at least 1 m below
Decommissioning audit to confirm initial rehabilitatconstructed according to design. Complet
Measurement tools / performance indicators
Visual inspections and completed checklist.Decommissioning audit to confirm initial rehabilitation works have been constructed according to design. Rehabilitation monitoring results
inspections and completed checklist.Decommissioning audit to confirm initial rehabilitation works have been constructed according to design. Decommissioning audit to confirm initial rehabilitation works have been constructed according to design.
Decommissioning audit to confirm initial rehabilitatconstructed according to design. Complet
erformance indicators
Visual inspections and completed checklist. confirm initial rehabilitation works have been
constructed according to design. Complete audit inspection checklist.Rehabilitation monitoring results
inspections and completed checklist. Decommissioning audit to confirm initial rehabilitation works have been constructed according to design. Complete audit inspection checklist.Decommissioning audit to confirm initial rehabilitation works have been constructed according to design. Complete audit inspect
Decommissioning audit to confirm initial rehabilitatconstructed according to design. Complete audit inspection c
confirm initial rehabilitation works have been Complete audit inspection checklist.
Decommissioning audit to confirm initial rehabilitation works have been Complete audit inspection checklist.
Decommissioning audit to confirm initial rehabilitation works have been Complete audit inspection checklist.
Decommissioning audit to confirm initial rehabilitation works have been audit inspection checklist
16-7
confirm initial rehabilitation works have been Complete audit inspection checklist.
Decommissioning audit to confirm initial rehabilitation works have been Complete audit inspection checklist.
Decommissioning audit to confirm initial rehabilitation works have been ion checklist.
ion works have been hecklist.
Chapter 16
Mount Peake ProjectDraft Environmental Impact Statement
16.3.5
Should visual inspections or monitoring results indicate the need for maintenance works or remedial action to be undertaken, TNG will mobilise contractors to site to undemaintenance works may include:
vmay be required. Also, weed w
erehabilitation is not progressing towards a selfmay be considered:
o
o
aaccess.
16.3.6
Maintaining an effective data management system is essential to ensure rehabilitation and closure related information is stored and maintained during the life of mine.
TNG will establish and maintain a document management system to store all relevant rehabilitation and closure information for the Mount Peake
16.3.7
Ultimately, the goal of all mine closure and rehabilitation works is to leave a final landfstakeholder objectives and achieves the completion criteria. The mine operator can then apply for relinquishment of the mining tenement and return of environmental securities.
16.4
16.4.1
The oand / or reshallow
aAround geotechnical studies conducted to
sthe
Chapter 16 – Rehabilitation and Mine Closure
Mount Peake ProjectDraft Environmental Impact Statement
16.3.5 Post Closure Maintenance
Should visual inspections or monitoring results indicate the need for maintenance works or remedial action to be undertaken, TNG will mobilise contractors to site to undemaintenance works may include:
vegetation - if rehabilitation is failing, additional application of fertiliser, additional seeding or planting may be required. Also, weed w
erosion - if significant rehabilitation is not progressing towards a selfmay be considered:
o construct, improve, or repair drainage control measures to reduce water slopes of the landform; and
o areas of deep erosion and
access - remedial works will be required if access prevention measures fail to restrict unauthorised access.
16.3.6 Data Management
Maintaining an effective data management system is essential to ensure rehabilitation and closure related information is stored and maintained during the life of mine.
TNG will establish and maintain a document management system to store all relevant rehabilitation and closure information for the Mount Peake
16.3.7 Relinquishment
Ultimately, the goal of all mine closure and rehabilitation works is to leave a final landfstakeholder objectives and achieves the completion criteria. The mine operator can then apply for relinquishment of the mining tenement and return of environmental securities.
Rehabilitation Design
16.4.1 Open Pit
The open pit will be left safeand / or re-profiled mine landforms. shallow pit lake. Rehabilitation actions include:
abandonment bunds will be constructed around the pit in accordance with the Safety Bund Walls Around Abandoned geotechnical studies conducted to
surfaces outside the abandonment bund the rehabilitation
Rehabilitation and Mine Closure
Mount Peake Project Draft Environmental Impact Statement
Post Closure Maintenance
Should visual inspections or monitoring results indicate the need for maintenance works or remedial action to be undertaken, TNG will mobilise contractors to site to undemaintenance works may include:
f rehabilitation is failing, additional application of fertiliser, additional seeding or planting may be required. Also, weed w
f significant embankment erosion on the TSF, WRD or ROM pad is identified or rehabilitation is not progressing towards a selfmay be considered:
construct, improve, or repair drainage control measures to reduce water slopes of the landform; and
areas of deep erosion and
emedial works will be required if access prevention measures fail to restrict unauthorised
a Management
Maintaining an effective data management system is essential to ensure rehabilitation and closure related information is stored and maintained during the life of mine.
TNG will establish and maintain a document management system to store all relevant rehabilitation and closure information for the Mount Peake
Relinquishment
Ultimately, the goal of all mine closure and rehabilitation works is to leave a final landfstakeholder objectives and achieves the completion criteria. The mine operator can then apply for relinquishment of the mining tenement and return of environmental securities.
Rehabilitation Design
Open Pit
pen pit will be left safe, restricting unauthorised public access by utilising abandonment bunding profiled mine landforms.
pit lake. Rehabilitation actions include:
bandonment bunds will be constructed around the pit in accordance with the Safety Bund Walls Abandoned Open Pit Mines Guidelines (DoIR 1997)
geotechnical studies conducted to
outside the abandonment bund rehabilitation strategies de
Rehabilitation and Mine Closure
Draft Environmental Impact Statement
Post Closure Maintenance
Should visual inspections or monitoring results indicate the need for maintenance works or remedial action to be undertaken, TNG will mobilise contractors to site to undemaintenance works may include:
f rehabilitation is failing, additional application of fertiliser, additional seeding or planting may be required. Also, weed will be implemented if required;
embankment erosion on the TSF, WRD or ROM pad is identified or rehabilitation is not progressing towards a self
construct, improve, or repair drainage control measures to reduce water slopes of the landform; and
areas of deep erosion and / or instability may need to be remediated with appropriate material.
emedial works will be required if access prevention measures fail to restrict unauthorised
Maintaining an effective data management system is essential to ensure rehabilitation and closure related information is stored and maintained during the life of mine.
TNG will establish and maintain a document management system to store all relevant rehabilitation and closure information for the Mount Peake P
Ultimately, the goal of all mine closure and rehabilitation works is to leave a final landfstakeholder objectives and achieves the completion criteria. The mine operator can then apply for relinquishment of the mining tenement and return of environmental securities.
Rehabilitation Design
, restricting unauthorised public access by utilising abandonment bunding profiled mine landforms. Groundwater recovery post closure will result in the formation of a
pit lake. Rehabilitation actions include:
bandonment bunds will be constructed around the pit in accordance with the Safety Bund Walls Open Pit Mines Guidelines (DoIR 1997)
geotechnical studies conducted to determine
outside the abandonment bund strategies detailed in Section
Should visual inspections or monitoring results indicate the need for maintenance works or remedial action to be undertaken, TNG will mobilise contractors to site to unde
f rehabilitation is failing, additional application of fertiliser, additional seeding or planting ill be implemented if required;
embankment erosion on the TSF, WRD or ROM pad is identified or rehabilitation is not progressing towards a self-sustaining community, the following remedial actions
construct, improve, or repair drainage control measures to reduce water
or instability may need to be remediated with appropriate material.
emedial works will be required if access prevention measures fail to restrict unauthorised
Maintaining an effective data management system is essential to ensure rehabilitation and closure related information is stored and maintained during the life of mine.
TNG will establish and maintain a document management system to store all relevant rehabilitation and Project.
Ultimately, the goal of all mine closure and rehabilitation works is to leave a final landfstakeholder objectives and achieves the completion criteria. The mine operator can then apply for relinquishment of the mining tenement and return of environmental securities.
, restricting unauthorised public access by utilising abandonment bunding roundwater recovery post closure will result in the formation of a
pit lake. Rehabilitation actions include:
bandonment bunds will be constructed around the pit in accordance with the Safety Bund Walls Open Pit Mines Guidelines (DoIR 1997)
determine the extent of bunding to be constructed; and
outside the abandonment bund will be covered with topsoil, ripped and seeded according to tailed in Section 16.3.2
Should visual inspections or monitoring results indicate the need for maintenance works or remedial action to be undertaken, TNG will mobilise contractors to site to unde
f rehabilitation is failing, additional application of fertiliser, additional seeding or planting ill be implemented if required;
embankment erosion on the TSF, WRD or ROM pad is identified or sustaining community, the following remedial actions
construct, improve, or repair drainage control measures to reduce water
or instability may need to be remediated with appropriate material.
emedial works will be required if access prevention measures fail to restrict unauthorised
Maintaining an effective data management system is essential to ensure rehabilitation and closure related information is stored and maintained during the life of mine.
TNG will establish and maintain a document management system to store all relevant rehabilitation and
Ultimately, the goal of all mine closure and rehabilitation works is to leave a final landfstakeholder objectives and achieves the completion criteria. The mine operator can then apply for relinquishment of the mining tenement and return of environmental securities.
, restricting unauthorised public access by utilising abandonment bunding roundwater recovery post closure will result in the formation of a
bandonment bunds will be constructed around the pit in accordance with the Safety Bund Walls Open Pit Mines Guidelines (DoIR 1997) (Figure
the extent of bunding to be constructed; and
will be covered with topsoil, ripped and seeded according to 16.3.2.
Should visual inspections or monitoring results indicate the need for maintenance works or remedial action to be undertaken, TNG will mobilise contractors to site to undertake these works. Such
f rehabilitation is failing, additional application of fertiliser, additional seeding or planting
embankment erosion on the TSF, WRD or ROM pad is identified or sustaining community, the following remedial actions
construct, improve, or repair drainage control measures to reduce water
or instability may need to be remediated with appropriate material.
emedial works will be required if access prevention measures fail to restrict unauthorised
Maintaining an effective data management system is essential to ensure rehabilitation and closure related information is stored and maintained during the life of mine.
TNG will establish and maintain a document management system to store all relevant rehabilitation and
Ultimately, the goal of all mine closure and rehabilitation works is to leave a final landfstakeholder objectives and achieves the completion criteria. The mine operator can then apply for relinquishment of the mining tenement and return of environmental securities.
, restricting unauthorised public access by utilising abandonment bunding roundwater recovery post closure will result in the formation of a
bandonment bunds will be constructed around the pit in accordance with the Safety Bund Walls Figure 16-6),
the extent of bunding to be constructed; and
will be covered with topsoil, ripped and seeded according to
Should visual inspections or monitoring results indicate the need for maintenance works or remedial rtake these works. Such
f rehabilitation is failing, additional application of fertiliser, additional seeding or planting
embankment erosion on the TSF, WRD or ROM pad is identified or sustaining community, the following remedial actions
construct, improve, or repair drainage control measures to reduce water movement down outer
or instability may need to be remediated with appropriate material.
emedial works will be required if access prevention measures fail to restrict unauthorised
Maintaining an effective data management system is essential to ensure rehabilitation and closure
TNG will establish and maintain a document management system to store all relevant rehabilitation and
Ultimately, the goal of all mine closure and rehabilitation works is to leave a final landform that meets all stakeholder objectives and achieves the completion criteria. The mine operator can then apply for
, restricting unauthorised public access by utilising abandonment bunding roundwater recovery post closure will result in the formation of a
bandonment bunds will be constructed around the pit in accordance with the Safety Bund Walls , or in accordance with
the extent of bunding to be constructed; and
will be covered with topsoil, ripped and seeded according to
16
Should visual inspections or monitoring results indicate the need for maintenance works or remedial rtake these works. Such
f rehabilitation is failing, additional application of fertiliser, additional seeding or planting
embankment erosion on the TSF, WRD or ROM pad is identified or sustaining community, the following remedial actions
movement down outer
or instability may need to be remediated with appropriate material.
emedial works will be required if access prevention measures fail to restrict unauthorised
Maintaining an effective data management system is essential to ensure rehabilitation and closure
TNG will establish and maintain a document management system to store all relevant rehabilitation and
orm that meets all stakeholder objectives and achieves the completion criteria. The mine operator can then apply for
, restricting unauthorised public access by utilising abandonment bunding roundwater recovery post closure will result in the formation of a
bandonment bunds will be constructed around the pit in accordance with the Safety Bund Walls or in accordance with
the extent of bunding to be constructed; and
will be covered with topsoil, ripped and seeded according to
16-8
f rehabilitation is failing, additional application of fertiliser, additional seeding or planting
sustaining community, the following remedial actions
movement down outer
or instability may need to be remediated with appropriate material.
emedial works will be required if access prevention measures fail to restrict unauthorised
TNG will establish and maintain a document management system to store all relevant rehabilitation and
orm that meets all
will be covered with topsoil, ripped and seeded according to
Chapter 16
Mount Peake ProjectDraft Environmental Impact Statement
Figure
16.4.2
Given the nature of embankment. Capping of the TSF surface will occur after closure when it has dried sufficiently to allow machine access.
Figure
A ‘store and release’ cover design is considered a valid rehabilitation option for the store and release cover design uses select materials as a monolithic storage layer able to absorb precipitation into the soilevapotranspiration, to manage the water with minimal or no runoff.
Chapter 16 – Rehabilitation and Mine Closure
Mount Peake ProjectDraft Environmental Impact Statement
Figure 16-6 Conceptual pit abandonment bund design
16.4.2 TSF
Given the nature of embankment. Capping of the TSF surface will occur after closure when it has dried sufficiently to allow machine access.
Figure 16-7 TSF design
A ‘store and release’ cover design is considered a valid rehabilitation option for the store and release cover design uses select materials as a monolithic storage layer able to absorb precipitation into the soilevapotranspiration, to manage the water with minimal or no runoff.
Rehabilitation and Mine Closure
Mount Peake Project Draft Environmental Impact Statement
Conceptual pit abandonment bund design
Given the nature of the operating TSF, progressive rehabilitation will be limited to the perimeter embankment. Capping of the TSF surface will occur after closure when it has dried sufficiently to allow machine access. Figure 16-7
TSF design
A ‘store and release’ cover design is considered a valid rehabilitation option for the store and release cover design uses select materials as a monolithic storage layer able to absorb precipitation into the soil / rock mass rather than pondievapotranspiration, to manage the water with minimal or no runoff.
Rehabilitation and Mine Closure
Draft Environmental Impact Statement
Conceptual pit abandonment bund design
operating TSF, progressive rehabilitation will be limited to the perimeter embankment. Capping of the TSF surface will occur after closure when it has dried sufficiently to allow
shows the TSF design.
A ‘store and release’ cover design is considered a valid rehabilitation option for the store and release cover design uses select materials as a monolithic storage layer able to absorb
rock mass rather than pondievapotranspiration, to manage the water with minimal or no runoff.
Conceptual pit abandonment bund design
operating TSF, progressive rehabilitation will be limited to the perimeter embankment. Capping of the TSF surface will occur after closure when it has dried sufficiently to allow
shows the TSF design.
A ‘store and release’ cover design is considered a valid rehabilitation option for the store and release cover design uses select materials as a monolithic storage layer able to absorb
rock mass rather than pondievapotranspiration, to manage the water with minimal or no runoff.
Conceptual pit abandonment bund design
operating TSF, progressive rehabilitation will be limited to the perimeter embankment. Capping of the TSF surface will occur after closure when it has dried sufficiently to allow
A ‘store and release’ cover design is considered a valid rehabilitation option for the store and release cover design uses select materials as a monolithic storage layer able to absorb
rock mass rather than ponding on top, then either allowing infiltration or evapotranspiration, to manage the water with minimal or no runoff.
operating TSF, progressive rehabilitation will be limited to the perimeter embankment. Capping of the TSF surface will occur after closure when it has dried sufficiently to allow
A ‘store and release’ cover design is considered a valid rehabilitation option for the store and release cover design uses select materials as a monolithic storage layer able to absorb
ng on top, then either allowing infiltration or evapotranspiration, to manage the water with minimal or no runoff. The intention
operating TSF, progressive rehabilitation will be limited to the perimeter embankment. Capping of the TSF surface will occur after closure when it has dried sufficiently to allow
A ‘store and release’ cover design is considered a valid rehabilitation option for the TSF (Figure store and release cover design uses select materials as a monolithic storage layer able to absorb
ng on top, then either allowing infiltration or he intention will be to limit infiltration.
16
operating TSF, progressive rehabilitation will be limited to the perimeter embankment. Capping of the TSF surface will occur after closure when it has dried sufficiently to allow
Figure 16-8). A store and release cover design uses select materials as a monolithic storage layer able to absorb
ng on top, then either allowing infiltration or to limit infiltration.
16-9
embankment. Capping of the TSF surface will occur after closure when it has dried sufficiently to allow
. A
to limit infiltration.
Chapter 16
Mount Peake ProjectDraft Environmental Impact Statement
Figure Source: Zornberg
The following general rehabilitation tasks will be applied to
acommissioned prior to rehabilitation works commencing;
a
the (Figure
aconstruct a waste
the TSF capped surface will be covered with topsoil, ripped and seeded according to the actionsdetailed in Section
16.4.3
The following general actions will be applied to close and rehabilitate the WRD:
a
oalternative design approved by a suitably
wdirected to a sump
sdetai
Chapter 16 – Rehabilitation and Mine Closure
Mount Peake ProjectDraft Environmental Impact Statement
Figure 16-8 Conceptual TSF closure designSource: Zornberg et al.
The following general rehabilitation tasks will be applied to
a review of the TSF by a suitably qualified geotechnical or engineering specialist will be commissioned prior to rehabilitation works commencing;
all process pipe work and general refuse will be removed;
he closed TSF will Figure 16-8);
a materials balance assessment will be undertaken to identify the inert waste rock to be used to construct a waste
he TSF capped surface will be covered with topsoil, ripped and seeded according to the actionsdetailed in Section
16.4.3 WRD
The following general actions will be applied to close and rehabilitate the WRD:
all refuse and remaining infrastructure will be removed;
outer slopes of the facility will be battered alternative design approved by a suitably
water runoff from the odirected to a sump
surfaces will be covered with topsoil, ripped and seeded according to the detailed in Section
Rehabilitation and Mine Closure
Mount Peake Project Draft Environmental Impact Statement
Conceptual TSF closure designet al. (2010)
The following general rehabilitation tasks will be applied to
review of the TSF by a suitably qualified geotechnical or engineering specialist will be commissioned prior to rehabilitation works commencing;
ocess pipe work and general refuse will be removed;
TSF will have an);
materials balance assessment will be undertaken to identify the inert waste rock to be used to construct a waste rock cap (Zornberg
he TSF capped surface will be covered with topsoil, ripped and seeded according to the actionsdetailed in Section 16.3.2
The following general actions will be applied to close and rehabilitate the WRD:
ll refuse and remaining infrastructure will be removed;
uter slopes of the facility will be battered alternative design approved by a suitably
ater runoff from the outer slopes of directed to a sump(s) prior to release into natural drainage systems;
urfaces will be covered with topsoil, ripped and seeded according to the led in Section 16.3.2
Rehabilitation and Mine Closure
Draft Environmental Impact Statement
Conceptual TSF closure design
The following general rehabilitation tasks will be applied to
review of the TSF by a suitably qualified geotechnical or engineering specialist will be commissioned prior to rehabilitation works commencing;
ocess pipe work and general refuse will be removed;
have an inert waste rock cap designed as a ‘store and release’ cover system
materials balance assessment will be undertaken to identify the inert waste rock to be used to rock cap (Zornberg
he TSF capped surface will be covered with topsoil, ripped and seeded according to the actions16.3.2.
The following general actions will be applied to close and rehabilitate the WRD:
ll refuse and remaining infrastructure will be removed;
uter slopes of the facility will be battered alternative design approved by a suitably
uter slopes of the prior to release into natural drainage systems;
urfaces will be covered with topsoil, ripped and seeded according to the 16.3.2.
Conceptual TSF closure design
The following general rehabilitation tasks will be applied to
review of the TSF by a suitably qualified geotechnical or engineering specialist will be commissioned prior to rehabilitation works commencing;
ocess pipe work and general refuse will be removed;
inert waste rock cap designed as a ‘store and release’ cover system
materials balance assessment will be undertaken to identify the inert waste rock to be used to rock cap (Zornberg et al. 2010);
he TSF capped surface will be covered with topsoil, ripped and seeded according to the actions
The following general actions will be applied to close and rehabilitate the WRD:
ll refuse and remaining infrastructure will be removed;
uter slopes of the facility will be battered to the conceptual design shown in alternative design approved by a suitably qualified geotechnical
the landform will be contained by a toe drain / bund wall and prior to release into natural drainage systems;
urfaces will be covered with topsoil, ripped and seeded according to the
The following general rehabilitation tasks will be applied to the TSF:
review of the TSF by a suitably qualified geotechnical or engineering specialist will be commissioned prior to rehabilitation works commencing;
ocess pipe work and general refuse will be removed;
inert waste rock cap designed as a ‘store and release’ cover system
materials balance assessment will be undertaken to identify the inert waste rock to be used to 2010); and
he TSF capped surface will be covered with topsoil, ripped and seeded according to the actions
The following general actions will be applied to close and rehabilitate the WRD:
ll refuse and remaining infrastructure will be removed;
to the conceptual design shown in qualified geotechnical
landform will be contained by a toe drain / bund wall and prior to release into natural drainage systems;
urfaces will be covered with topsoil, ripped and seeded according to the
TSF:
review of the TSF by a suitably qualified geotechnical or engineering specialist will be
inert waste rock cap designed as a ‘store and release’ cover system
materials balance assessment will be undertaken to identify the inert waste rock to be used to
he TSF capped surface will be covered with topsoil, ripped and seeded according to the actions
The following general actions will be applied to close and rehabilitate the WRD:
to the conceptual design shown in qualified geotechnical engineer;
landform will be contained by a toe drain / bund wall and prior to release into natural drainage systems; and
urfaces will be covered with topsoil, ripped and seeded according to the rehabilitation
review of the TSF by a suitably qualified geotechnical or engineering specialist will be
inert waste rock cap designed as a ‘store and release’ cover system
materials balance assessment will be undertaken to identify the inert waste rock to be used to
he TSF capped surface will be covered with topsoil, ripped and seeded according to the actions
The following general actions will be applied to close and rehabilitate the WRD:
to the conceptual design shown in Figure 16
landform will be contained by a toe drain / bund wall and
rehabilitation
16
review of the TSF by a suitably qualified geotechnical or engineering specialist will be
inert waste rock cap designed as a ‘store and release’ cover system
materials balance assessment will be undertaken to identify the inert waste rock to be used to
he TSF capped surface will be covered with topsoil, ripped and seeded according to the actions
16-9, or an
landform will be contained by a toe drain / bund wall and
rehabilitation strategies
16-10
Chapter 16
Mount Peake ProjectDraft Environmental Impact Statement
Figure
16.4.4
General actions for rehabilitation of infrastructure areas are as follows:
ademolition works;
sdemolition plan;
s
cA
s
b
n
aretained;
a
16.4.5
The following actions wi
s
w
wdrainage paths;
s16.3.2
Chapter 16 – Rehabilitation and Mine Closure
Mount Peake ProjectDraft Environmental Impact Statement
Figure 16-9 Conceptual WRD design
16.4.4 Infrastructure
General actions for rehabilitation of infrastructure areas are as follows:
all structures will be decontaminated (if necessary) and washed down prior to the commencement of demolition works;
structural engineers will determine a safe and efficient dismandemolition plan;
structures will be pulled to the ground and dismantled;
concrete slabs and footings will be broken down to a depth of 1 m below the finished ground surfaceAlternatively concrete could be covered to provide
services will be removed or buried at a depth at least 1 m below the final ground surface;
buried pipes left
non-recyclable and inert waste will be disposed of in
access roads required to be left for post closure monitoring purposes need to be defined and retained; and
all areas will be ripped
16.4.5 Site Roads
The following actions wi
sumps, bunding and bitumen will be removed (where applicable);
windrows respread over the road surface and road crown reshaped (where applicable);
where haul roads disrupt surface drainage, excavatidrainage paths;
surfaces will be covered with topsoil, ripped and seeded according to the action detailed in Section 16.3.2.
Rehabilitation and Mine Closure
Mount Peake Project Draft Environmental Impact Statement
Conceptual WRD design
Infrastructure
General actions for rehabilitation of infrastructure areas are as follows:
ll structures will be decontaminated (if necessary) and washed down prior to the commencement of demolition works;
tructural engineers will determine a safe and efficient dismandemolition plan;
tructures will be pulled to the ground and dismantled;
oncrete slabs and footings will be broken down to a depth of 1 m below the finished ground surfacelternatively concrete could be covered to provide
ervices will be removed or buried at a depth at least 1 m below the final ground surface;
uried pipes left in situ will be flushed and sealed at each end;
recyclable and inert waste will be disposed of in
ccess roads required to be left for post closure monitoring purposes need to be defined and and
ll areas will be ripped to break compaction
Roads
The following actions will be taken to rehabilitate roads and hardstand areas:
umps, bunding and bitumen will be removed (where applicable);
indrows respread over the road surface and road crown reshaped (where applicable);
here haul roads disrupt surface drainage, excavatidrainage paths; and
urfaces will be covered with topsoil, ripped and seeded according to the action detailed in Section
Rehabilitation and Mine Closure
Draft Environmental Impact Statement
Conceptual WRD design
General actions for rehabilitation of infrastructure areas are as follows:
ll structures will be decontaminated (if necessary) and washed down prior to the commencement of
tructural engineers will determine a safe and efficient disman
tructures will be pulled to the ground and dismantled;
oncrete slabs and footings will be broken down to a depth of 1 m below the finished ground surfacelternatively concrete could be covered to provide
ervices will be removed or buried at a depth at least 1 m below the final ground surface;
will be flushed and sealed at each end;
recyclable and inert waste will be disposed of in
ccess roads required to be left for post closure monitoring purposes need to be defined and
to break compaction
ll be taken to rehabilitate roads and hardstand areas:
umps, bunding and bitumen will be removed (where applicable);
indrows respread over the road surface and road crown reshaped (where applicable);
here haul roads disrupt surface drainage, excavati
urfaces will be covered with topsoil, ripped and seeded according to the action detailed in Section
Conceptual WRD design
General actions for rehabilitation of infrastructure areas are as follows:
ll structures will be decontaminated (if necessary) and washed down prior to the commencement of
tructural engineers will determine a safe and efficient disman
tructures will be pulled to the ground and dismantled;
oncrete slabs and footings will be broken down to a depth of 1 m below the finished ground surfacelternatively concrete could be covered to provide
ervices will be removed or buried at a depth at least 1 m below the final ground surface;
will be flushed and sealed at each end;
recyclable and inert waste will be disposed of in
ccess roads required to be left for post closure monitoring purposes need to be defined and
to break compaction prior to overburden and
ll be taken to rehabilitate roads and hardstand areas:
umps, bunding and bitumen will be removed (where applicable);
indrows respread over the road surface and road crown reshaped (where applicable);
here haul roads disrupt surface drainage, excavati
urfaces will be covered with topsoil, ripped and seeded according to the action detailed in Section
General actions for rehabilitation of infrastructure areas are as follows:
ll structures will be decontaminated (if necessary) and washed down prior to the commencement of
tructural engineers will determine a safe and efficient disman
tructures will be pulled to the ground and dismantled;
oncrete slabs and footings will be broken down to a depth of 1 m below the finished ground surfacelternatively concrete could be covered to provide the necessary cover depth;
ervices will be removed or buried at a depth at least 1 m below the final ground surface;
will be flushed and sealed at each end;
recyclable and inert waste will be disposed of in an onsite lan
ccess roads required to be left for post closure monitoring purposes need to be defined and
prior to overburden and
ll be taken to rehabilitate roads and hardstand areas:
umps, bunding and bitumen will be removed (where applicable);
indrows respread over the road surface and road crown reshaped (where applicable);
here haul roads disrupt surface drainage, excavation will occur at low points to re
urfaces will be covered with topsoil, ripped and seeded according to the action detailed in Section
General actions for rehabilitation of infrastructure areas are as follows:
ll structures will be decontaminated (if necessary) and washed down prior to the commencement of
tructural engineers will determine a safe and efficient dismantling procedure and prepare a
oncrete slabs and footings will be broken down to a depth of 1 m below the finished ground surfacethe necessary cover depth;
ervices will be removed or buried at a depth at least 1 m below the final ground surface;
will be flushed and sealed at each end;
onsite landfill or similar;
ccess roads required to be left for post closure monitoring purposes need to be defined and
prior to overburden and / or topsoil application.
ll be taken to rehabilitate roads and hardstand areas:
umps, bunding and bitumen will be removed (where applicable);
indrows respread over the road surface and road crown reshaped (where applicable);
on will occur at low points to re
urfaces will be covered with topsoil, ripped and seeded according to the action detailed in Section
ll structures will be decontaminated (if necessary) and washed down prior to the commencement of
tling procedure and prepare a
oncrete slabs and footings will be broken down to a depth of 1 m below the finished ground surfacethe necessary cover depth;
ervices will be removed or buried at a depth at least 1 m below the final ground surface;
dfill or similar;
ccess roads required to be left for post closure monitoring purposes need to be defined and
or topsoil application.
indrows respread over the road surface and road crown reshaped (where applicable);
on will occur at low points to re-establish natural
urfaces will be covered with topsoil, ripped and seeded according to the action detailed in Section
16
ll structures will be decontaminated (if necessary) and washed down prior to the commencement of
tling procedure and prepare a
oncrete slabs and footings will be broken down to a depth of 1 m below the finished ground surface
ervices will be removed or buried at a depth at least 1 m below the final ground surface;
ccess roads required to be left for post closure monitoring purposes need to be defined and
or topsoil application.
indrows respread over the road surface and road crown reshaped (where applicable);
establish natural
urfaces will be covered with topsoil, ripped and seeded according to the action detailed in Section
16-11
ll structures will be decontaminated (if necessary) and washed down prior to the commencement of
oncrete slabs and footings will be broken down to a depth of 1 m below the finished ground surface.
establish natural
urfaces will be covered with topsoil, ripped and seeded according to the action detailed in Section
Chapter 16
Mount Peake ProjectDraft Environmental Impact Statement
16.5 Stakeholder engagement is a key component of mine closure planning. Mines developed in remote regions often require construction of a range of infand should be retained after mine closure. Retention of any infrastructure must be on the basis of a formal sequential use agreement, where the details of retained infrastructure are described and matof tenure,
At this point in the infrastructure is listed as items most likely to be retained by
the rail siding may be required to remain as a passing bay or parking lo
w
a
Chapter 16 – Rehabilitation and Mine Closure
Mount Peake ProjectDraft Environmental Impact Statement
Infrastructure to be Retained after ClosureStakeholder engagement is a key component of mine closure planning. Mines developed in remote regions often require construction of a range of infand should be retained after mine closure. Retention of any infrastructure must be on the basis of a formal sequential use agreement, where the details of retained infrastructure are described and mat
tenure, ongoing maintenance liability and legal liability are clearly
At this point in the infrastructure is listed as items most likely to be retained by
he rail siding may be required to remain as a passing bay or parking lo
water bores, storage dams and water tanks m
access roads may be retained for pastoral use, fire brea
Rehabilitation and Mine Closure
Mount Peake Project Draft Environmental Impact Statement
Infrastructure to be Retained after ClosureStakeholder engagement is a key component of mine closure planning. Mines developed in remote regions often require construction of a range of infand should be retained after mine closure. Retention of any infrastructure must be on the basis of a formal sequential use agreement, where the details of retained infrastructure are described and mat
ongoing maintenance liability and legal liability are clearly
At this point in the Project’s development, no sequential use agreements are in place. The following infrastructure is listed as items most likely to be retained by
he rail siding may be required to remain as a passing bay or parking lo
ater bores, storage dams and water tanks m
ccess roads may be retained for pastoral use, fire brea
Rehabilitation and Mine Closure
Draft Environmental Impact Statement
Infrastructure to be Retained after ClosureStakeholder engagement is a key component of mine closure planning. Mines developed in remote regions often require construction of a range of infand should be retained after mine closure. Retention of any infrastructure must be on the basis of a formal sequential use agreement, where the details of retained infrastructure are described and mat
ongoing maintenance liability and legal liability are clearly
roject’s development, no sequential use agreements are in place. The following infrastructure is listed as items most likely to be retained by
he rail siding may be required to remain as a passing bay or parking lo
ater bores, storage dams and water tanks m
ccess roads may be retained for pastoral use, fire brea
Infrastructure to be Retained after ClosureStakeholder engagement is a key component of mine closure planning. Mines developed in remote regions often require construction of a range of infrastructure that other stakeholders consider have value and should be retained after mine closure. Retention of any infrastructure must be on the basis of a formal sequential use agreement, where the details of retained infrastructure are described and mat
ongoing maintenance liability and legal liability are clearly
roject’s development, no sequential use agreements are in place. The following infrastructure is listed as items most likely to be retained by
he rail siding may be required to remain as a passing bay or parking lo
ater bores, storage dams and water tanks may be retained for pastoral use; and
ccess roads may be retained for pastoral use, fire brea
Infrastructure to be Retained after Closure Stakeholder engagement is a key component of mine closure planning. Mines developed in remote
rastructure that other stakeholders consider have value and should be retained after mine closure. Retention of any infrastructure must be on the basis of a formal sequential use agreement, where the details of retained infrastructure are described and mat
ongoing maintenance liability and legal liability are clearly
roject’s development, no sequential use agreements are in place. The following infrastructure is listed as items most likely to be retained by other parties:
he rail siding may be required to remain as a passing bay or parking lo
ay be retained for pastoral use; and
ccess roads may be retained for pastoral use, fire breaks and general access.
Stakeholder engagement is a key component of mine closure planning. Mines developed in remote rastructure that other stakeholders consider have value
and should be retained after mine closure. Retention of any infrastructure must be on the basis of a formal sequential use agreement, where the details of retained infrastructure are described and mat
ongoing maintenance liability and legal liability are clearly established.
roject’s development, no sequential use agreements are in place. The following other parties:
he rail siding may be required to remain as a passing bay or parking location for general rail traffic;
ay be retained for pastoral use; and
ks and general access.
Stakeholder engagement is a key component of mine closure planning. Mines developed in remote rastructure that other stakeholders consider have value
and should be retained after mine closure. Retention of any infrastructure must be on the basis of a formal sequential use agreement, where the details of retained infrastructure are described and mat
established.
roject’s development, no sequential use agreements are in place. The following
cation for general rail traffic;
ay be retained for pastoral use; and
ks and general access.
16
Stakeholder engagement is a key component of mine closure planning. Mines developed in remote rastructure that other stakeholders consider have value
and should be retained after mine closure. Retention of any infrastructure must be on the basis of a formal sequential use agreement, where the details of retained infrastructure are described and matters
roject’s development, no sequential use agreements are in place. The following
cation for general rail traffic;
16-12
rastructure that other stakeholders consider have value
ters
cation for general rail traffic;