_______________________________________________________________________________________________________ESD 1.6-121 r0 Check the LCLS Project website to verify 2 of 13 that this is the correct version prior to use.
SLAC National Accelerator Laboratory
Table of Contents Table of Contents ..............................................................................................................................................2 1. Overview.........................................................................................................................................................2 2. Hutch 1 Specific Requirements ...................................................................................................................2 3. Hutch 2 Specific Requirements ...................................................................................................................3
1. Overview NEH Hutch 1 and Hutch 2 have been turned over to LCLS project for beneficial occupancy. Plans for science instrument installation are being finalized. To support the science instruments, additional mechanical and electrical support utilities are needed in the hutch. Mechanical systems include: Vacuum pump exhaust lines, process chilled water distribution manifold, compressed air accumulator and distribution manifold, and additional support for the laser safety system including AC power at specific points and a sliding laser operations door. Electrical systems include cable tray installation, instrumentation rack installation, electrical power distribution to instrumentation racks, convenience outlets along instrument beam lines, and support to the laser safety system and Hutch Protection System.
2. Hutch 1 Specific Requirements
2.1. Electrical • Instrumentation Racks. Racks B950S-10, B950S-11, B950S-12, B950S-13, B950S-14,
B950S-15, and B950S-16 are being installed by a separate SLAC Cable Shop contract. o For each rack, run two 3 phase 208VAC 20A service from Power Panels
2CBP02-950 and 2DBP02-950 (on north-east wall), terminate in Furman power distribution center in each rack. Update panel schedule. Notes: Rack B950S-10 has been connected to AC under a previous contract and is not included in this scope; routing for power to racks B950S-11, B950S-12, and B950S-13 has already been installed under the previous contract to power rack B950S-10.
• Beam line Instrument convenience outlets o Install 120VAC 20A service in quad boxes and 208 three phase outlets at 25
locations marked BEAMLINE ELECTRICAL. Circuits are specified in the AC Power table. Electrical service to be run from panels 2CBP02-950 and 2DBP02-950 inside the hutch. Note, three 208 single phase circuits at location #28 come from panel 2DBP05-950 outside hutch.
• Pump Power o Install three 208VAC 20A service on east wall at south side. Separate circuits for
each 208VAC outlet. Route conduit along east wall just above cable trays and drop to outlet locations. Route from panel 2DBP05-950 located outside hutch.
• Laser Table
_______________________________________________________________________________________________________ESD 1.6-121 r0 Check the LCLS Project website to verify 3 of 13 that this is the correct version prior to use.
SLAC National Accelerator Laboratory
o Install two 120VAC 20A circuits to laser table. Circuits will later be attached to molded plug strips on laser table enclosure under a separate contract. Route from panels 2CBP02-950 and 2DBP02-950.
• Hutch Protection System o Install one 120VAC 20A circuit with Hubble receptacle at Hutch entry panel.
Panel for service to be approved by PPS group.
2.2. Mechanical • Process Cooling Water (PCW)
o Install PCW supply and return manifolds with 20 connections each on east wall between AMO and SXR beamlines, see PCW and Compressed Air Drawing. Remove PCW piping to south wall. Install “ball valve type” mechanical valves for controlling water flow to individual devices.
o Install PCW piping from Racks B950S-10, through B950S-16 to PCW manifold. • Compressed Air
o Install 5 gal. Compressed Air accumulator on east wall as shown in drawing PCW and Compressed Air. Remove piping and service location at south wall. Install compressed air line to XTOD accumulator location on west wall
• Exhaust Ducting o Install exhaust ducting, nominal 6 inch diameter, from exhaust pump location in
south east corner to exhaust vent in north west corner of room. Provide port locations along exhaust duct as shown in the drawing and provide support for exhaust from three roughing pumps at south east corner as shown in Exhaust drawing.
• Concrete Drilling o Installation of stands and will require special mounting holes to be drilled into
the floor and anchors installed. Approximately 80 holes. Hole template to be provided by SLAC. Holes will be an approx. 50/50 mix of 3/8 inch and ½ inch flush mount Hilti HIS-N drop-in steel anchors with Hilti HIT-RE 500-SD epoxy adhesive capsules.
• Hoist/Crane o REMOVED FROM SCOPE OF THIS WORK
• Laser Safety Door o Install rolling laser safety door on inside of Hutch 1 Access door. Use Chase
Doors Saino Service Door with pass door. See figure 1 below. Door system supplied by SLAC.
3. Hutch 2 Specific Requirements
3.1. Electrical • Instrumentation Racks. Racks B950S-20, B950S-21, B950S-22, B950S-23, B950S-24,
and B950S-25 are being installed by a separate SLAC Cable Shop contract.
_______________________________________________________________________________________________________ESD 1.6-121 r0 Check the LCLS Project website to verify 4 of 13 that this is the correct version prior to use.
SLAC National Accelerator Laboratory
o For each rack, run two 3 phase 208VAC 20A service from Power Panels 2CBP03-950 and 2DBP03-950 (on north-east wall), terminate in Furman power distribution center in each rack. Update panel schedule.
• Beam line Instrument convenience outlets o Clean power: Install 120VAC 20A service in quad boxes at 24 locations marked
in drawing BEAMLINE ELECTRICAL. Circuit definitions are listed in the AC Power Table. Routing is indicated in the drawing, some routing sections are to be flex-conduit type to allow for terminal quad box to be relocated as needed. Route from Panels 2CBP03-950 and 2DBP03-950.
• Laser Safety System Displays o Install 120VAC 20A service to Laser Safety System Display locations (two inside
hutch and one outside above hutch access door) and at Laser System Control Panel location. Locations to be field marked. Route from Panels 2CBP03-950 and 2DBP03-950.
• Laser Table o Install two 120VAC 20A circuits to laser table. Circuits will later be attached to
molded plug strips on laser table enclosure under a separate contract. Route from Panels 2CBP03-950 and 2DBP03-950.
• Hutch Protection System o Install one 120VAC 20A circuit with Hubble receptacle at Hutch entry panel.
Panel for service to be approved by PPS group.
3.2. Mechanical • Process Cooling Water (PCW)
o Install PCW supply and return manifolds with 20 connections each on south wall in southeast corner of the hutch as shown in drawing PCW and Compressed Air. Remove PCW piping to south wall. Install “ball valve type” mechanical valves for controlling water flow to individual devices.
o Install PCW piping from Racks B950S-20, through B950S-25 to PCW manifold location.
• Compressed Air o Install 5 gal. Compressed Air accumulator on south wall as shown in drawing
PCW and Compressed Air. Remove piping and service location at south wall. • Exhaust Ducting
o Install exhaust ducting, nominal 6 inch diameter from exhaust vent in north west corner of room. Provide port locations as shown in Exhaust drawing.
• Concrete Drilling o Installation of stands and laser tables will require special mounting holes to be
drilled into the floor and anchors installed. Approximately 80 holes. Hole template to be provided by SLAC. Holes will be an approx. 50/50 mix of 3/8 inch and ½ inch flush mount Hilti HIS-N drop-in steel anchors with Hilti HIT-RE 500-SD epoxy adhesive capsules, specified in template.
o Core drill approx. 6 inch hole in west wall at field marked location. Note, scope includes relocation of near by ground wires to accommodate location of hole.
_______________________________________________________________________________________________________ESD 1.6-121 r0 Check the LCLS Project website to verify 5 of 13 that this is the correct version prior to use.
SLAC National Accelerator Laboratory
• Laser Safety Door o Install rolling laser safety door on inside of Hutch 2 Access door. Use Chase
Doors Saino Service Door with pass door. See figure 1 below. Door system supplied by SLAC.
4. Figures
Figure 1: Example of Chase Door System
_______________________________________________________________________________________________________ESD 1.6-121 r0 Check the LCLS Project website to verify 6 of 13 that this is the correct version prior to use.
SLAC National Accelerator Laboratory
Figure 2: Beamline Electrical
Figure 3: PCW and Compressed Air
_______________________________________________________________________________________________________ESD 1.6-121 r0 Check the LCLS Project website to verify 7 of 13 that this is the correct version prior to use.
SLAC National Accelerator Laboratory
Figure 4: Exhaust
5. Tables
5.1. AC Power Table
Electrical Modifications - 1st Hutch:
Instrument Hutch Location Voltage Circuit Outlets Reference Routing Feed from
Panels
SXR Hutch 1
Single pulse shutter 110 1 1 Quad #1
conduit on floor
2CBP02-950 2DBP02-950
SXR Hutch 1
Transmission chamber 110 2 2 Quad #2 & #3
conduit on cable tray supports
2CBP02-950 2DBP02-950
SXR Hutch 1
Transmission chamber 208 3-4-5
1 Outlet #4
conduit on cable tray supports
2CBP02-950 2DBP02-950
SXR Hutch 1
Monochromator tank - D.S. end 110 6 2 Quad #5 & #6
flex line floor/conduit floor
2CBP02-950 2DBP02-950
SXR Hutch 1
Monochromator tank - D.S. end 208 7-8-9
1 Outlet #7
flex line floor/conduit floor
2CBP02-950 2DBP02-950
_______________________________________________________________________________________________________ESD 1.6-121 r0 Check the LCLS Project website to verify 8 of 13 that this is the correct version prior to use.
SLAC National Accelerator Laboratory
AMO Hutch 1
Single Pulse Shutter 110 10 1 Quad #11
conduit on floor
2CBP02-950 2DBP02-950
AMO Hutch 1
KB mirror tank - U.S. end 110 11 2 Quad
#12 & #13
flex line floor/conduit floor
2CBP02-950 2DBP02-950
AMO Hutch 1
KB mirror tank - U.S. end 208
12-13-14
1 Outlet #14
flex line floor/conduit floor
2CBP02-950 2DBP02-950
AMO Hutch 1
HFP U.S. and D.S sides 110 15 2 quad
#15 & #17
flex line floor/conduit floor
2CBP02-950 2DBP02-950
AMO Hutch 1
HFP north end 110 16 1 Quad #16
flex line floor/conduit floor (extend from #15 location)
2CBP02-950 2DBP02-950
AMO Hutch 1
Diag. Cham. U.S. end 110 17 2 Quad
#18 & #19
flex line floor/conduit floor
2CBP02-950 2DBP02-950
AMO Hutch 1
Diag. Cham. D.S. end 110 18 2 Quad
# 20 & #21
flex line floor/conduit floor
2CBP02-950 2DBP02-950
AMO Hutch 1 East wall 208
19, 20, 21
1 Outlet #22 outlet on wall
2CBP02-950 2DBP02-950
AMO Hutch 1 East wall 110 22 1 quad #23
flex line off wall
2CBP02-950 2DBP02-950
AMO Hutch 1
East Wall, S. corner 208
23, 24,25
1 Outlet #24 outlet on wall 2DBP05-950
AMO Hutch 1
East Wall, S. corner 208
26, 27, 28
1 Outlet #25 outlet on wall 2DBP05-950
AMO Hutch 1
East Wall, S. corner 208
29, 30, 31
1 Outlet #26 outlet on wall 2DBP05-950
AMO Hutch 1 Laser table 110 32, 33
2 power strips #27
power strips on table
2CBP02-950 2DBP02-950
AMO Hutch 1
Between HFC and Diag. Cham. 208
76, 77, 78, 79,
80, 81
3 separate 208 single phase outlets #28
208 single phase for pump controllers 2DBP05-950
AMO Hutch 1
Laser Safety System 110 NA various NA
from outside panel, installed in separate contract
2CBP02-950 2DBP02-950
AMO addtl. Rack
Hutch 1
NW hutch floor 208
34, 35, 36, 37,
38, 39
2 furman distribu
tion NA
conduit, note, routing installed in separate contract
2CBP02-950 2DBP02-950
_______________________________________________________________________________________________________ESD 1.6-121 r0 Check the LCLS Project website to verify 9 of 13 that this is the correct version prior to use.
SLAC National Accelerator Laboratory
AMO Laser Rack
Hutch 1
NW Hutch floor 208
40, 41, 42, 43,
44, 45
2 furman distribu
tion NA
conduit, note, routing installed in separate contract
2CBP02-950 2DBP02-950
SXR Rack
Hutch 1
NW hutch floor 208
46, 47, 48, 49,
50, 51
2 furman distribu
tion NA
conduit, note, routing installed in separate contract
2CBP02-950 2DBP02-950
XTOD/MPS Rack
Hutch 1
NW Hutch floor 208
52, 53, 54, 55,
56, 57
2 furman distribu
tion NA
conduit, note fully installed in separate contract
2CBP02-950 2DBP02-950
AMO Rack
Hutch 1
South Wall West End 208
58, 59, 60, 61,
62, 63
2 furman distribu
tion NA conduit 2CBP02-950 2DBP02-950
AMO Rack
Hutch 1
South Wall West End 208
64, 65, 66, 67,
68, 69
2 furman distribu
tion NA conduit 2CBP02-950 2DBP02-950
AMO Rack
Hutch 1
Sout Wall Middle 208
70, 71, 72, 73,
74, 75
2 furman distribu
tion NA conduit 2CBP02-950 2DBP02-950
Electrical Modifications - 2nd Hutch:
SXR Hutch 2
Exit slit - on wall 110 1 2 Quad #1 & #2 conduit wall
2CBP03-950 2DBP03-950
SXR Hutch 2
K-B mirrors - U.S. end 110 2 2 Quad #3 & #4
flex line from end tray/conduit floor
2CBP03-950 2DBP03-950
SXR Hutch 2
Diff. Pump/laser mirror 110 3 2 Quad #5 & #6
flex line from end tray/conduit floor
2CBP03-950 2DBP03-950
SXR Hutch 2
Diff. Pump/laser mirror 208 4-5-6
1 Outlet #7
flex line from end tray/conduit floor
2CBP03-950 2DBP03-950
SXR Hutch 2
U.S. End station between SXR & XTOD 110 7 2 Quad #8 & #9
flex line from end tray/conduit floor
2CBP03-950 2DBP03-950
_______________________________________________________________________________________________________ESD 1.6-121 r0 Check the LCLS Project website to verify 10 of 13 that this is the correct version prior to use.
SLAC National Accelerator Laboratory
SXR Hutch 2
U.S. End station between SXR & XTOD 208 8-9-10
1 Outlet #10
flex line from end tray/conduit floor
2CBP03-950 2DBP03-950
SXR Hutch 2
D.S. End station, edge walkway or on wall 110 11 2 Quad
#11 & #12
flex line from wall
2CBP03-950 2DBP03-950
SXR Hutch 2
D.S. End station, edge walkway or on wall 208
12-13-14
1 Outlet #13
flex line from wall
2CBP03-950 2DBP03-950
SXR Hutch 2
User racks - north end station 110
15, 16, 17 3 Quad
#14, 15 & 16
conduit on support over walkway
2CBP03-950 2DBP03-950
SXR Hutch 2
User racks - north end station 208
18-19-20
1 Outlet #17
conduit on support over walkway
2CBP03-950 2DBP03-950
SXR/Laser
Hutch 2
Laser table - terminate end cable tray 110 21 1 box #18
conduit on cable tray supports
2CBP03-950 2DBP03-950
SXR/Laser
Hutch 2
Laser table - terminate end cable tray 110 22 1 box #19
conduit on cable tray supports
2CBP03-950 2DBP03-950
SXR/Laser
Hutch 2
Laser safety- various locations in room 110 23
1 Quad? #20
conduit wall/tbd
2CBP03-950 2DBP03-950
AMO Hutch 2
Future end station - on wall 110 24 2 Quad
#21 & #22 conduit wall
2CBP03-950 2DBP03-950
AMO Hutch 2
Future end station - on wall 208
25-26-27
1 Outlet #23 conduit wall
2CBP03-950 2DBP03-950
XPP Hutch 2 XPP Slits 110 28 1 Quad #24
flex line from end tray/conduit floor
2CBP03-950 2DBP03-950
SXR Laser Rack
Hutch 2
NW Hutch floor 208
29, 30, 31, 32,
33, 34
2 furman distribu
tion NA conduit 2CBP03-950 2DBP03-950
Future AMO Rack
Hutch 2
NW hutch floor 208
35, 36, 37, 38,
39, 40
2 furman distribu
tion NA conduit 2CBP03-950 2DBP03-950
XTOD/MPS Rack
Hutch 2
South Wall West side 208
41, 42, 43, 44,
2 furman distribu
tion NA conduit 2CBP03-950 2DBP03-950
_______________________________________________________________________________________________________ESD 1.6-121 r0 Check the LCLS Project website to verify 11 of 13 that this is the correct version prior to use.
SLAC National Accelerator Laboratory
45, 46
SXR Rack
Hutch 2
South Wall Middle 208
47, 48, 49, 50,
51, 52
2 furman distribu
tion NA conduit 2CBP03-950 2DBP03-950
SXR Rack
Hutch 2
South Wall Middle 208
53, 54, 55, 56,
57, 58
2 furman distribu
tion NA conduit 2CBP03-950 2DBP03-950
SXR Rack
Hutch 2
South Wall East Side 208
59, 60, 61, 62,
63, 64
2 furman distribu
tion NA conduit 2CBP03-950 2DBP03-950
5.2. PCW Expected Usage Table
Location Total PCW Available
(gpm) Area Budgetd
PCW Device Heat Load (KW)
PCW Needed (gpm)
NEH 73 Hutch 1 10 B950S-10 XTOD/MPS Rack 0.5 0.34
B950S-11 SXR Rack 0.5 0.34
B950S-12 AMO Laser Controls 1.5 1
B950S-13 AMO Rack 0.5 0.34
B950S-14 AMO Rack 1 0.68
B950S-15 AMO Rack 1 0.68
B950S-16 AMO Rack 1.5 1
9ea. 80L/s turbos in series
1.17
2000 L/s turbo 1.54
2ea. 1300 L/s turbos in parallel
1.06
400 L/s turbo 0.26 300 L/s turbo 0.26
_______________________________________________________________________________________________________ESD 1.6-121 r0 Check the LCLS Project website to verify 12 of 13 that this is the correct version prior to use.
SLAC National Accelerator Laboratory
2ea. spectometer turbos in series
0.68
Primary Pump 1 0.26 Primary Pump 2 0.26 Primary Pump 3 0.26
Hutch 1
Total Expecte
d 10.13
Hutch 2 10 B950S-20 AMO Rack (future) 0 0
B950S-21 SXR Laser Controls 1.5 1
B950S-22
XTOD/MPS/XPP Rack
0.5 0.34
B950S-23 SXR Rack 0.5 0.34
B950S-24 SXR Rack 1 0.68
B950S-25 AMO Rack 1 0.68
Turbo Pump circuit 1 0.68
Turbo Pump circuit 2 0.68
Turbo Pump circuit 3 0.68
Primary Pump 1 0.34 Primary Pump 2 0.34 Primary Pump 3 0.34
Hutch 2
Total Expecte
d 6.1
Hutch 3 10 B950S-30 XPP 0.5 0.34 B950S-31 XPP 0.5 0.34 B950S-32 XPP 1 0.68 B950S-33 XPP 1 0.68 P950S-34 XPP 0.5 0.34
_______________________________________________________________________________________________________ESD 1.6-121 r0 Check the LCLS Project website to verify 13 of 13 that this is the correct version prior to use.
SLAC National Accelerator Laboratory
Hutch 3
Total Expecte
d 2.38
Laser Room 15 Laser Chiller 3
Laser Room Total
Expected
3 Will
increase to 15
Laser Room 2 0 Laser Chiller 6.8
Laser Room 2
Total Expecte
d
6.8
Server Racks 0 B950S-40 Switch 0.5 0.34
B950S-41 Patch 0 0 B950S-42 Server 1.5 1.02 B950S-43 Server 1.5 1.02
Server Racks Total
Expected
2.38 Will
increase to 24
NEH Total
Expected
27.79 NEH to
supply FEE as well
FEE 0 0 5 FEE Total
Expected
5 Take from NEH Source