15638-e1-1500-CA-pro-203 Ms&Ra - Dome Roof Installation Rev 2

download 15638-e1-1500-CA-pro-203 Ms&Ra - Dome Roof Installation Rev 2

of 18

Transcript of 15638-e1-1500-CA-pro-203 Ms&Ra - Dome Roof Installation Rev 2

  • 7/25/2019 15638-e1-1500-CA-pro-203 Ms&Ra - Dome Roof Installation Rev 2

    1/18

    EPC WORKSFORCONSTRUCTION

    OF OIL TERMINAL AT HFZ

    AGREEMENT NO. 10-5638-E-1

    ABU DHABI

    OIL REFINING COMPANY PROJECT PROCEDURE

    METHOD STATEMENT FOR DOMEFRAME INSTALLATION

    DOC. NO.: 5638-E1-1500-CA-PRO-203Page1 /17

    Rev.

    2

  • 7/25/2019 15638-e1-1500-CA-pro-203 Ms&Ra - Dome Roof Installation Rev 2

    2/18

    EPC WORKSFORCONSTRUCTION

    OF OIL TERMINAL AT HFZ

    AGREEMENT NO. 10-5638-E-1

    ABU DHABI

    OIL REFINING COMPANY PROJECT PROCEDURE

    METHOD STATEMENT FOR DOMEFRAME INSTALLATION

    DOC. NO.: 5638-E1-1500-CA-PRO-203Page2 /17

    Rev.

    2

    This page is a record of all revision of this document. All previous issues are hereby supersededand are to be destroyed.

    REV DATE DESCRIPTION PRPD CHKD REVD APPRD COMPANY

    2 17/06/13Issue for

    constructionYB Dinesh ZZP WLY

    1 20/05/13 Issue forconstruction

    YB Dinesh ZZP WLY

    0 03/04/13Issure forcomments

    YB Dinesh ZZP WLY

    B 01/04/13Issure forcomments

    YB Dinesh ZZP WLY

  • 7/25/2019 15638-e1-1500-CA-pro-203 Ms&Ra - Dome Roof Installation Rev 2

    3/18

    EPC WORKSFORCONSTRUCTION

    OF OIL TERMINAL AT HFZ

    AGREEMENT NO. 10-5638-E-1

    ABU DHABI

    OIL REFINING COMPANY PROJECT PROCEDURE

    METHOD STATEMENT FOR DOMEFRAME INSTALLATION

    DOC. NO.: 5638-E1-1500-CA-PRO-203Page3 /17

    Rev.

    2

    PARAGRAPHS REVISED IN THIS ISSUE

    Para. No. Para. No. Para. No. Para. No.

    5.1.13 Attachment 1

    5.3.1

    5.3.2

    5.3.3

    5.3.4

    5.3.5

  • 7/25/2019 15638-e1-1500-CA-pro-203 Ms&Ra - Dome Roof Installation Rev 2

    4/18

    EPC WORKSFORCONSTRUCTION

    OF OIL TERMINAL AT HFZ

    AGREEMENT NO. 10-5638-E-1

    ABU DHABI

    OIL REFINING COMPANY PROJECT PROCEDURE

    METHOD STATEMENT FOR DOMEFRAME INSTALLATION

    DOC. NO.: 5638-E1-1500-CA-PRO-203Page4 /17

    Rev.

    2

    TABLE OF CONTENTS

    No. DESCRIPTION PAGE

    1 PURPOSE....................................................................................................................... 5

    2 DEFINITIONS AND ABBREVIATIONS................................................................... 5

    2.1 Definitions............................................................................................................. 5

    2.2 Abbreviations....................................................................................................... 5

    3 CODES AND STANDARDS............................................................................................ 5

    4 RESOURCES................................................................................................................ 6

    4 1 M 6

  • 7/25/2019 15638-e1-1500-CA-pro-203 Ms&Ra - Dome Roof Installation Rev 2

    5/18

    EPC WORKSFORCONSTRUCTION

    OF OIL TERMINAL AT HFZ

    AGREEMENT NO. 10-5638-E-1

    ABU DHABI

    OIL REFINING COMPANY PROJECT PROCEDURE

    METHOD STATEMENT FOR DOMEFRAME INSTALLATION

    DOC. NO.: 5638-E1-1500-CA-PRO-203Page5 /17

    Rev.

    2

    1 PURPOSE

    The method statement is applicable to the lattice dome frame Installation in Jet A-1 Tanks

    T-501, T-502, T-503, T-504.

    2 DEFINITIONS AND ABBREVIATIONS

    2.1 Definitions

    COMPANY ABU DHABI OIL REFINING COMPANY (TAKREER)

    CONTRACTOR Sinopec international Petroleum Service Corporation

    May One possible course of action

    PMC WS ATKINS & OVERSEAS PARTNERS

    Shall/must/is to be A mandatory requirement

    Should A non-mandatory requirement

    2 2 Abb i ti

  • 7/25/2019 15638-e1-1500-CA-pro-203 Ms&Ra - Dome Roof Installation Rev 2

    6/18

    EPC WORKSFORCONSTRUCTION

    OF OIL TERMINAL AT HFZ

    AGREEMENT NO. 10-5638-E-1

    ABU DHABI

    OIL REFINING COMPANY PROJECT PROCEDURE

    METHOD STATEMENT FOR DOMEFRAME INSTALLATION

    DOC. NO.: 5638-E1-1500-CA-PRO-203Page6 /17

    Rev.

    2

    5638-E1-1500-CA-PRO-201 Construction procedure for Tank fabrication and erection

    5638-E1-1500-QA-ITP-MEQ-001 Inspection And Test Plan For Storage Tank

    5638-E1-1500-QA-PRO-001 Project Quality Plan

    AFC drawings

    5638-E1-1500- MEQ -DWG-506 DOME COVER PLATE DETAILS JET A-1 TANK

    STD-MF-0024 Method of Tank Erection

    4 RESOURCES

    4.1 Manpower

    Tank Engineer 1

    QA/QC 1

    HSE officer 1

    welder 8

    Ri i i 1

  • 7/25/2019 15638-e1-1500-CA-pro-203 Ms&Ra - Dome Roof Installation Rev 2

    7/18

    EPC WORKSFORCONSTRUCTION

    OF OIL TERMINAL AT HFZ

    AGREEMENT NO. 10-5638-E-1

    ABU DHABI

    OIL REFINING COMPANY PROJECT PROCEDURE

    METHOD STATEMENT FOR DOMEFRAME INSTALLATION

    DOC. NO.: 5638-E1-1500-CA-PRO-203Page7 /17

    Rev.

    2

    3 nos. movable aluminium scaffolding with a maximum height of 7metre with three planks

    Minimum distance between planks not more than 2 metre, connected by ladder

    Stay pole at the four corners of the scaffold

    Dedicated labours to move scaffolding .

  • 7/25/2019 15638-e1-1500-CA-pro-203 Ms&Ra - Dome Roof Installation Rev 2

    8/18

    CONSTRUCTION OF OILTERMINAL AT HFZ(EPC-1)

    AGREEMENT NO. 10-5638-E-1

    ABU DHABI

    OIL REFINING COMPANY PROJECT PROCEDURE

    METHOD STATEMENT FOR DOME

    ROOF INSTALLATION

    DOC. NO.: 5638-E1-1500-CA-PRO-203Page8/17

    Rev.

    2

  • 7/25/2019 15638-e1-1500-CA-pro-203 Ms&Ra - Dome Roof Installation Rev 2

    9/18

    CONSTRUCTION OF OILTERMINAL AT HFZ(EPC-1)

    AGREEMENT NO. 10-5638-E-1

    ABU DHABI

    OIL REFINING COMPANY PROJECT PROCEDURE

    METHOD STATEMENT FOR DOME

    ROOF INSTALLATION

    DOC. NO.: 5638-E1-1500-CA-PRO-203Page9/17

    Rev.

    2

    5.1.5 Identical slots (48 nos.)at equal intervals are provided on the ring beam allowing

    lateral movement of the dome frame along the slot to adjust the dome to required

    profile during erection.5.1.6 The Dome roof is a spherical structure with rounded bottom, reinforcement pates

    are to be bolted on the ring beam (rounded bottom) and ensured to be in position as

    per drawings.

    5.1.7 Dome frame members shall be identified and marked clearly before installation, to

    prevent frame members(primary and secondary) and other accessories misused.

    Twoinstallation personnel with movable Aluminum Alloy Scaffoldingshall be

    engaged in the erection of Dome frame member.

    5.1.8 After installating upto 5 layers, the reinforcement plates shall be welded and the the

    slots on the ring beam can be plug welded, start full welding of the support plates

    B(96 nos ) and the ring beam to the shell.

  • 7/25/2019 15638-e1-1500-CA-pro-203 Ms&Ra - Dome Roof Installation Rev 2

    10/18

    CONSTRUCTION OF OILTERMINAL AT HFZ(EPC-1)

    AGREEMENT NO. 10-5638-E-1

    ABU DHABI

    OIL REFINING COMPANY PROJECT PROCEDURE

    METHOD STATEMENT FOR DOME

    ROOF INSTALLATION

    DOC. NO.: 5638-E1-1500-CA-PRO-203Page10/17

    Rev.

    2

  • 7/25/2019 15638-e1-1500-CA-pro-203 Ms&Ra - Dome Roof Installation Rev 2

    11/18

    CONSTRUCTION OF OILTERMINAL AT HFZ(EPC-1)

    AGREEMENT NO. 10-5638-E-1

    ABU DHABI

    OIL REFINING COMPANY PROJECT PROCEDURE

    METHOD STATEMENT FOR DOME

    ROOF INSTALLATION

    DOC. NO.: 5638-E1-1500-CA-PRO-203Page11/17

    Rev.

    2

    5.1.12 The spherical shape of the dome is achieved by inter-connecting different members

    in their respective nodes.Each members are connected to the node plates by bolts.

    5 1 13 Aft ll th d f b bl i li h d th i t ith

  • 7/25/2019 15638-e1-1500-CA-pro-203 Ms&Ra - Dome Roof Installation Rev 2

    12/18

    CONSTRUCTION OF OILTERMINAL AT HFZ(EPC-1)

    AGREEMENT NO. 10-5638-E-1

    ABU DHABI

    OIL REFINING COMPANY PROJECT PROCEDURE

    METHOD STATEMENT FOR DOME

    ROOF INSTALLATION

    DOC. NO.: 5638-E1-1500-CA-PRO-203Page12/17

    Rev.

    2

    5.2.2 Prefabricate 10 curve ladders (3000650mm) to avoid welder to slip from the dome

    structure during assembly and welding.

    5.2.3 According to the drawings(5638-E1-1500-MEQ-DWG-506),lifting by crane and

    laying the first dome roof plate in the center.2 mobile scaffoldings will be set under

    two sides of plates .The erector will stand in the scaffolding to assist laying the

    center dome roof plate and then tack weld the plate. the positioning plate

  • 7/25/2019 15638-e1-1500-CA-pro-203 Ms&Ra - Dome Roof Installation Rev 2

    13/18

    CONSTRUCTION OF OILTERMINAL AT HFZ(EPC-1)

    AGREEMENT NO. 10-5638-E-1

    ABU DHABI

    OIL REFINING COMPANY PROJECT PROCEDURE

    METHOD STATEMENT FOR DOME

    ROOF INSTALLATION

    DOC. NO.: 5638-E1-1500-CA-PRO-203Page13/17

    Rev.

    2

    stand in the curve ladder which top side is fixed to the pipe by belt and the down

    side is fixed with handrail.

  • 7/25/2019 15638-e1-1500-CA-pro-203 Ms&Ra - Dome Roof Installation Rev 2

    14/18

    CONSTRUCTION OF OILTERMINAL AT HFZ(EPC-1)

    AGREEMENT NO. 10-5638-E-1

    ABU DHABI

    OIL REFINING COMPANY PROJECT PROCEDURE

    METHOD STATEMENT FOR DOME

    ROOF INSTALLATION

    DOC. NO.: 5638-E1-1500-CA-PRO-203Page14/17

    Rev.

    2

    5.3 Roof Cover plate Welding

    5.3.1 First, al l the welding in the dome roof plates shal l be carried out by

    intermittent weld from dom e center to bound ary . The top surface of dome

    cover sh al l be welded equal ly as per drawings b y 12 welders. Bottom surface

    of dome cov er shal l be welded simultaneously in al l the four quarters of the

  • 7/25/2019 15638-e1-1500-CA-pro-203 Ms&Ra - Dome Roof Installation Rev 2

    15/18

    CONSTRUCTION OF OILTERMINAL AT HFZ(EPC-1)

    AGREEMENT NO. 10-5638-E-1

    ABU DHABI

    OIL REFINING COMPANY PROJECT PROCEDURE

    METHOD STATEMENT FOR DOME

    ROOF INSTALLATION

    DOC. NO.: 5638-E1-1500-CA-PRO-203Page15/17

    Rev.

    2

    5.3.6 Temporary angle- steel supports shall be welded to the dome centre cover plates

    to secure the welders during welding.the temporary attachments shall be removed

    after all the welding has been performed and subjected to NDE as per DGSrequirements.

    5.3.7 Bo ttom surface of dome cover shal l be welded in intermittent way as per

    Drawings 5638-E1-1500-MEQ-DWG-506. Non-welded area shall be sealed

    with B elzona materials as per manufacture recomm endations. In absence of

    Belzona seal ing. Proceeding seal ing w elding.

    6 QA/ QC

    Please refer to following documents:

    a) Project Quality Plan 5638-E1-1500-QA-PRO-001.

    b) Inspection And Test Plan For Storage Tank 5638-E1-1500-QA-ITP MEQ-001.

    c) Approved construction drawing requirement shall be ensured.

  • 7/25/2019 15638-e1-1500-CA-pro-203 Ms&Ra - Dome Roof Installation Rev 2

    16/18

    CONSTRUCTION OF OILTERMINAL AT HFZ(EPC-1)

    AGREEMENT NO. 10-5638-E-1

    ABU DHABI

    OIL REFINING COMPANY PROJECT PROCEDURE

    METHOD STATEMENT FOR DOME

    ROOF INSTALLATION

    DOC. NO.: 5638-E1-1500-CA-PRO-203Page16/17

    Rev.

    2

    7.9 During roof plate laying. All the workers working at height be adoned FBH duly

    anchored chest straps with the carabiner of a rope grabber at very next to climbing

    on the roof and check and confirm the robustness of the tie up points, rope grabbergrip and tightness of nuts of carabiners as formost activity. A rope grabber be

    provided for each worker at roof. In no circumstance a rope grabber shall be used

    for more than one worker.

    7.10 During roof plate welding. All the workers working at height be adoned FBH duly

    anchored chest straps with the carabiner of a Retractable Life Line at very next to

    climbing on the roof and check and confirm the robustness of the tie up points,

    retractable life line grip and tightness of nuts of carabiners as formost activity. A

    rectractable life line be provided for each worker at roof. In no circumstance a rope

    grabber shall be used for more than one worker.

    7.11 All the welders shall cover the welding spot with fire blanket for minimum 10

  • 7/25/2019 15638-e1-1500-CA-pro-203 Ms&Ra - Dome Roof Installation Rev 2

    17/18

    CONSTRUCTION OF OILTERMINAL AT HFZ(EPC-1)

    AGREEMENT NO. 10-5638-E-1

    ABU DHABI

    OIL REFINING COMPANY PROJECT PROCEDURE

    METHOD STATEMENT FOR DOME

    ROOF INSTALLATION

    DOC. NO.: 5638-E1-1500-CA-PRO-203Page17/17

    Rev.

    2

    3 minutes) incase of suspension of worker from height. A mobile scaffolding shall

    be made available as a spare for rescue during emergency; and a knife with

    scabbard and 18mm rope with a carbiner shall be kept on the rescue mobilescaffolding. A mobile scaffolding shall be moved to hold suspended victim

    immediately. All the personnel working inside the tank will be trained on the rescue

    methods.

    7.16 3rdparty trained rescue team shall be made available at site and they will be act as

    per the orders of ERTL (Emergency Response Team Leader) according to the

    emergency situation.

    7.17 Suspended persons shall not be laid down for 40 minutes and water shall not be

    given to the victim immediately, depends upon the situations.

    7.18 Heat Stress. Heat stress measures like water arrangement, job rotations, Flag

    notifications shall be complied as per project procedures.

  • 7/25/2019 15638-e1-1500-CA-pro-203 Ms&Ra - Dome Roof Installation Rev 2

    18/18

    Attachment 1 Welding Sequence Drawing