14 Ric Parker

download 14 Ric Parker

of 15

Transcript of 14 Ric Parker

  • 8/6/2019 14 Ric Parker

    1/15

    2010 Rolls-Royce plcThe information in this document is the property of Rolls-Royce plc and may not be copied or communicated to a third party, or used for anypurpose other than that for which it is supplied without the express written consent of Rolls-Royce plc.This information is given in good faith based upon the latest information available to Rolls-Royce plc, no warranty or representation is givenconcerning such information, which must not be taken as establishing any contractual or other commitment binding upon Rolls-Royce plc orany of its subsidiary or associated companies.

    National Ambitions for Power Generationin the UK

    Nuclear TechnologiesRic Parker17th March 2010

  • 8/6/2019 14 Ric Parker

    2/15

    Role of Nuclear in UK Generating Mix

    Significance for Timing of Nuclear New-build

    UK Focus in Technology Development

    Next Generation of Nuclear Power Plants

    Opportunities for UK Industry

    UK R&D Programme to Support New Build Beyond UK New-build

    Civil Nuclear and Rolls-Royce

    Beyond Gen III Summary

    Outline

  • 8/6/2019 14 Ric Parker

    3/15

    Role of Nuclear in UK Generating Mix

    The CBI Decision Time Report July 2009

    Business as Usual Scenario

    Almost all of the UKs ageing

    coal-fired and nuclear powerstations will be retired by 2020

    CBI assumes delays in

    licensing /authorisation of newnuclear stations will meanthese may not be

    commissioned until post 2020

    Balanced Pathway Scenario

    FGD and NOx-abated

    plants capable ofcomplying with the revisedLCPD run until after 2020

    Greater encouragement ofCCS throughdemonstrator programmes

    Scaling back the 2020

    target for renewables,reducing the quantity ofwind

    note 1:This level of plant retirement significantly exceeds most previous projections.

  • 8/6/2019 14 Ric Parker

    4/15

    Significance for composition UK generating mix (2030)

    Gas fired capacityrises to 36 %

    Nuclear capacityconstrained to 20 %

    Nuclear capacityincreased to 34 %

    Power Prices lower andvolatility reduced

    Delivers further CO2abatementover medium term compared toBAU

    Gas imports in 2030 rise to100 BCM with greater gasinfrastructure needs

    CO2emissions from UK powergen 45%lower in 2030 compared with BAUnote 1

    note 1 CBI projects that CO2emissions from Balanced Pathway will amount to 35 MT as compared with 60 MT for BAU

  • 8/6/2019 14 Ric Parker

    5/15

    UK Historical Technology Development

    UK currently has 19 nuclear reactors, totalling11 GWe of capacity This fleet is characterised by unique reactor

    designs:

    15 Advanced Gas-cooled Reactors(AGRs)

    2 Magnox stations Only a single UK nuclear power plant (Sizewell

    B, Pressurised Water Reactor) completed in

    1995 can be considered of modern design By 2020, electricity from these stations reduced

    to 7 % of UK capacity from current 15-20% (allexcept Sizewell B closed by 2023)

    Only Sizewell B offers scope for significant lifeextension

    UK nuclear R&D has been dominated by clean-up and de-commissioning of existing plant.

  • 8/6/2019 14 Ric Parker

    6/15

    Next Generation of Nuclear Plants

    Next generation of UK nuclear stations:

    HMG approval for 10 sites in England and Wales (first by2017)

    UKs proposed new build programme will use existing GenerationIII or III+ reactor designs

    The most likely designs for early plants in the next generationinclude:

    Westinghouse 1,150 MWe AP1000TM Pressurised WaterReactor (PWR)

    AREVA 1,600 MWe European Pressurised water Reactor

    (EPR) design

    Assessment of non-site-specific issues associated with theabove designs is expected to be completed in Q2 2011.

  • 8/6/2019 14 Ric Parker

    7/15

    Candidate Reactor Designs

    Both of the most likely designsare held by non-UK OEMs

    The AREVA EPRTM design iscurrently being utilised for the

    following new nuclear plantsunder construction:

    - Flamanville 3, France

    - Olkiluoto Unit 3, Finland

    China has officially adopted the WestinghouseAP1000 as a standard for inland nuclear

    projects- Sanmen 6 x 1,150 MW units, Zhejang

    - Haiyan 6 x 1, 150 MW, Shandong AREVA

    Westinghouse

  • 8/6/2019 14 Ric Parker

    8/15

    Opportunities for UK Industry

    A report1 (February 2009) examined the capability and capacity of thesupply chain for a UK new civil nuclear build programme

    this concluded that there will be significant opportunities for UK-based companies:

    Pre-Build (Design) including reactor plantsystem module andproduct definition, instrumentation and control, electrical systems,etc.

    Project Management

    Civil Construction

    Manufacturing, including large forgings, other forgings and

    castings, valves, pumps, cables, etc.

    Operation and Decommissioning

    Nuclear engineering skills gaps were identified as a weakness for theUKs new-build, nuclear supply chain.

    Note 1: Supply Chain for a UK Nuclear New Build Programme, Dr Stephen A Court, National Metals TechnologyCentre (NAMTEC) submitted to Department for Business Enterprise and Regulatory Reform (BERR)

  • 8/6/2019 14 Ric Parker

    9/15

  • 8/6/2019 14 Ric Parker

    10/15

    Potential Work-Streams for UK Nuclear

    R&D Programme To reduce costs and risks involved in new build and licensing.

    - modelling of plant transient behaviour

    - external hazard assessment e.g. seismic design

    - control and instrumentation

    To ensure that plants operate at the maximum safety andcapacity

    - Equipment Health Management (EHM), novel sensors,knowledge management techniques, use of virtual plantmodels to assist in maintenance

    To ensure long term safety and availability of plants- development of improved materials and lifing To ensure a sustainable waste management

  • 8/6/2019 14 Ric Parker

    11/15

    Today nuclear power accounts for 16% of the worldselectricity production

    Operational reactors(2009)Total number 441

    New Build(2010-2030)Total number 389

    NorthAmerica(167)

    SouthAmerica(14)

    Europe(170)

    South Africa(9)

    Rest of Asia(57)

    India(52)

    China(124)

    Russia(74)

    CentralEasternEurope(82)

    Japan(66)

    Region (TotalNo.)

  • 8/6/2019 14 Ric Parker

    12/15

    The world, new-build market is worth ~850Bn to 2030 withthe support market contributing a further ~950Bn

    New Build

    Current fleet

    support

    New Buildsupport

    Nuclear Power Plantmarket 2010-2030 (Bn)

    Source: Rolls-Royce

    WEO, WNA

    M

    New Build

    Support

    Bn

  • 8/6/2019 14 Ric Parker

    13/15

    Civil Nuclear and Rolls-Royce Rolls-Royce is well-positioned with skills,

    capabilities and facilities for participationin UK civil nuclear new build

    Over 50 years of nuclear engineering

    experience Rolls-Royce has considerable capability

    UK submarines: water reactor

    engineering, instrumentation andcontrol systems.

    Data Systems and Solutions: nuclear

    services in USA and mainlandEurope

    Structuring high value-added supply

    chains ~2000 nuclear engineers/specialists

  • 8/6/2019 14 Ric Parker

    14/15

    Gen IV GOFastR Gas-cOoled Fast Reactors

    6m 3-year EU FP7 funded programme with 21partners.

    Breeder reactor technology using U-238 and Pu-239as fuel.

    High temperature operation (up to 950 C reactoroutlet temperature).

    > 45% thermal efficiency.

    Single phase, inert primary coolant.

    Potential to burn long-lived minor actinides. Rolls-Royce areas of interest:

    Power conversion systems systemdesign, component selection andperformance.

    High temperature primary circuit heat exchangertechnology.

  • 8/6/2019 14 Ric Parker

    15/15

    New nuclear build has a significant potential for meeting UKGHG and energy security targets

    Delivery of technology/systems in time to match retirements iskey

    Recent nuclear R&D focus on clean-up and decommissioning ofexisting unique reactor designs

    Timing of new UK nuclear stations makes selection of pre-

    existing Gen III or III+ designs essential Candidate reactor designs already exist from overseas

    suppliers, but considerable opportunities exist for UK industryacross design, construction, operation and decommissioning

    A targeted UK R&D programme to support new build will beessential if UK companies are to benefit

    This will not stop at Gen III; we need to be match-fit for Gen IV

    Summary