Improving Vector Shift Relaying for Islanding Detection S. Martinez de Lafuente 1 , F. Uriondo 1 , J. Tavallo 2 and J.M. García 2 1 Department of Electrical Engineering ESI Bilbao, University of the Basque Country Alameda Urquijo s/n 48013 Bilbao (Spain) Phone/Fax number:+0034 946 012 000, e-mail: [email protected] , [email protected] 2 INGETEAM POWER TECHNOLOGY Parque Tecnológico de Vizcaya Edificio 108 48170 Zamudio (Spain) Phone/Fax number:+0034 946 018 900, e-mail: [email protected] , [email protected] Abstract The two main dedicated passive methods for detecting distributed generation islanding are the rate-of- change-of-frequency (ROCOF) and vector-surge (VS) relays. The paper presents an enhanced new algorithm for VS relaying. The new algorithm takes into account that the real voltage shift can happen in a wave zero-crossing or that it can be split into two different half cycles. It also measures the true vector shift magnitude in the three phases, allowing for future changes of settings in order to adequate them to the real relay working situation. Keywords: Distributed generation, islanding detection, vector-surge (VS) relays, vector-shift (VS) relays, synchronous generators. 1. Introduction The problem of islanding happens when a part of the distribution network is disconnected from the rest of the system but the distributed generators keep feeding the islanded part of the network. This situation involves several problems, for the equipment and for the personnel safety also, so, it is common practice to disconnect all distributed generators to minimize the risks associated to the islanding situation. The methods to detect the islanding situation can be classified into active and passive [1]. The paper deals with one of the most popular passive methods used to determinate that the islanding has happened, the so called vector shift, vector jump or vector surge relay. The principle of operation of the vector shift relay is quite simple [2]. During normal operation, the terminal voltage of an embedded synchronous generator lags the synchronous electromotive force by an angle “δ”. If the grid supply is suddenly disconnected from the section of the network partially supplied by the embedded generator, the load on the generator increases or decreases and this causes a shift in the rotor displacement angle. The terminal voltage jumps to a new value and the phase position changes as shown in figure 1. Vector Shift T T’ T U(t) t Fig 1- Vector Shift and variation in the wave period The vector shift in angle and in time are related by the following expression: T T T ' 2 (1) Where T is the wave period (typically 20ms) and T' is the period during the vector shift. Usually relays measure the period calculating the time difference between two consecutive rising/falling zero edges of the voltage wave. The calculation is done by the relays [3], [4] every half cycle and the relay setting threshold must be exceeded twice consecutively to issue a trip command. 2. Problems in the measure of the vector shift. The vector shift presented in figure 1 is purely theoretical, if we simulate with certain degree of detail the vector shift using the models (to be explained and referenced in detail in the full paper) presented by Freitas

Transcript of 127-martinez.pdf

  • Improving Vector Shift Relaying for Islanding Detection

    S. Martinez de Lafuente

    1, F. Uriondo

    1, J. Tavallo

    2 and J.M. Garca

    2

    1Department of Electrical Engineering

    ESI Bilbao, University of the Basque Country

    Alameda Urquijo s/n 48013 Bilbao (Spain) Phone/Fax number:+0034 946 012 000, e-mail: [email protected], [email protected]

    2INGETEAM POWER TECHNOLOGY

    Parque Tecnolgico de Vizcaya

    Edificio 108 48170 Zamudio (Spain) Phone/Fax number:+0034 946 018 900, e-mail: [email protected] , [email protected]

    Abstract The two main dedicated passive methods for detecting distributed generation islanding are the rate-of-

    change-of-frequency (ROCOF) and vector-surge (VS)

    relays. The paper presents an enhanced new algorithm for

    VS relaying. The new algorithm takes into account that the

    real voltage shift can happen in a wave zero-crossing or that

    it can be split into two different half cycles. It also measures

    the true vector shift magnitude in the three phases, allowing

    for future changes of settings in order to adequate them to

    the real relay working situation.

    Keywords: Distributed generation, islanding detection,

    vector-surge (VS) relays, vector-shift (VS) relays,

    synchronous generators.

    1. Introduction The problem of islanding happens when a part of the

    distribution network is disconnected from the rest of the

    system but the distributed generators keep feeding the

    islanded part of the network. This situation involves

    several problems, for the equipment and for the personnel

    safety also, so, it is common practice to disconnect all

    distributed generators to minimize the risks associated to

    the islanding situation.

    The methods to detect the islanding situation can be

    classified into active and passive [1]. The paper deals

    with one of the most popular passive methods used to

    determinate that the islanding has happened, the so called

    vector shift, vector jump or vector surge relay.

    The principle of operation of the vector shift relay is

    quite simple [2]. During normal operation, the terminal

    voltage of an embedded synchronous generator lags the

    synchronous electromotive force by an angle . If the grid supply is suddenly disconnected from the section of

    the network partially supplied by the embedded

    generator, the load on the generator increases or

    decreases and this causes a shift in the rotor displacement

    angle. The terminal voltage jumps to a new value and the

    phase position changes as shown in figure 1.

    Vector

    Shift

    T T T

    U(t)

    t

    Fig 1- Vector Shift and variation in the wave period

    The vector shift in angle and in time are related by the

    following expression:

    T

    TT

    '2 (1)

    Where T is the wave period (typically 20ms) and T' is the

    period during the vector shift. Usually relays measure the

    period calculating the time difference between two

    consecutive rising/falling zero edges of the voltage wave.

    The calculation is done by the relays [3], [4] every half

    cycle and the relay setting threshold must be exceeded

    twice consecutively to issue a trip command.

    2. Problems in the measure of the vector shift.

    The vector shift presented in figure 1 is purely

    theoretical, if we simulate with certain degree of detail

    the vector shift using the models (to be explained and

    referenced in detail in the full paper) presented by Freitas

  • and other authors we see that the result is the one

    presented in figure 2.

    1

    U(t)

    t

    VS1 VS2

    R S T

    T

    T Fig 2- Simulated three-phase vector shift

    The problems when trying to measure the vector shift are

    the following:

    The vector shift in two phases (R & T) is divided in two instants of time (VS1 and VS2) in

    different half cycles.

    The vector shift in phase S (VS2) happens in a zero crossing, so it is also divided in two half

    cycles.

    A manufacturer [4] solves the problem using a 5 out of 6

    tripping method, this is, a measurement of each phase

    voltage angle is performed every half-cycle and the

    decision as to whether a trip condition exists is made

    every full cycle. The angle difference between the

    present and previous measurement is calculated. This

    process yields six results at the end of each power system

    cycle (2 half-cycles x 3 phase voltages). If 5 of those 6

    results are above the setting threshold, a trip signal is

    initiated.

    3. Summary of the new algorithm.

    3.1. Basis

    The key of the new algorithm is that its decision criteria

    is based on three measurements in each phase, this is, on

    a total of nine measurements to decide if there has been a

    breaker opening or not.

    The algorithm measures the period every half cycle but

    takes into account that only in one of the measures the

    vector shift is exactly measured. This is due to the fact

    that the vector shift can be divided in two different half

    cycles so only the measure that includes both half cycles

    measures the vector shift in its real value.

    In order to see it more clearly, in figure 3, we have

    isolated the vector shift in one phase for an opening of

    the breaker at full load. As illustrated in the figure the

    total (and real) vector shift is divided in two parts, the so

    called Vector Shift 1 and Vector Shift 2, that happen in

    two different half cycles. If we calculate the period for

    each zero crossing, we see that T1 does not include the

    total vector shift and neither does T3, only T2 measures it.

    Vector

    Shift 1

    Vector

    Shift 2

    T1

    T2

    T3

    t

    U(t)

    Fig 3- Simulated Vector Shift

    The algorithm proceeds as follows: every half cycle it is

    checked whether the measured vector shift exceeds the

    set threshold or not. If the setting is exceeded this vector

    shift is compared to the ones in the previous and the

    following half cycles and it searches for the biggest one.

    The biggest value and the half cycle when it has taken

    place are memorized. Then, the values of the vector shifts

    in the previous and the following half cycles to the

    recorded one are added (this must be a similar value to

    the recorded one). If both values are higher than the set

    threshold, it is accepted that a vector shift has happened

    in that phase.

    The same process is repeated in the other two phases and

    if the setting is exceeded in the three phases a three pole

    trip is provoked.

    Another important aspect to point out, that the new

    algorithm also takes advantage of, is that the addition of

    the vector shifts of the periods T1 and T3 is equal to the

    measured vector shift in the period T2.

    3.2. Ancillary elements

    The vector shift is calculated with the following formula

    in each phase:

    average

    average

    T

    TT

    '360

    Where the average period is calculated based on the

    periods measured in the previous cycles.

    Not to distort the measure, the following measures are

    taken:

    In the calculus of the average period, the periods where the vector shift has a higher value than

    the established one are not included. For

    example, if we take a value of 2 degrees/cycle,

    that fits with a ROCOF of 0.278 Hz/s, if the

  • ROCOF has a higher value than this, the queue

    is not refreshed and the unit ends up operating

    after a certain time. This avoids the distortion of

    the average period due to faults and serves as a

    backup of the ROCOFs unit.

    Neither are included in the average period the values of the period when voltages are below

    75% of the rated value because it is assumed

    that these values are polluted by the effect of a

    fault or the connection of the source.

    The value of the voltage is calculated using a half cycle Fourier transform, in that way when

    the decision of including or not a cycle in the

    calculus of the average is taken, you already

    know the effective value of the voltage with

    precision, something that would not happen with

    a full cycle Fourier transform.

    In order to provoke the trip order in the three phases, the voltages have to exceed the 75% of

    the rated value, to avoid the three pole trip in

    three phase faults.

    4. Simulated model.

    The system selected to make all the simulations is

    the one used in most of the articles dedicated to the

    topic of the vector shift[5][6].

    GS2MVA0.69kV

    VSRelay

    Yg/0.69/13,8kV

    Line

    Yg/13,8/230kV

    230kV100MVA

    Fig 4- Model used in the simulations

    The implemented MATLAB model is shown in the

    next picture.

    Fig5- MATLAB model used in the simulations

    Due to the size of the picture, the details of the simulated

    model cant be appreciated in the best way. It has been included a voltage regulator and it also has been

    simulated the turbine with its control. This last point

    could seem unnecessary for the study of the vector shift

    but is interesting to study the algorithms stability in large simulations.

    The model also gives the chance of connecting and

    disconnecting different loads, provoking faults in order to

    analyse the stability and provoking islands with different

    unbalances between the load and the generation.

    5. The algorithms sensitivity.

    As it has been mentioned before, one of the advantages

    of the algorithm is the capacity of measuring the vector

    shift precisely. This advantage has been used to analyse

    the algorithms sensitivity. Starting with a situation of full load in the source, we form islandings with different

    levels of instability between generation and consumption

    in the islanding and we save the data of the measured

    vector shift getting the curve shown in the picture below.

    In the picture, for example, it can be seen that for a

    setting of 4 of the vector shift, it is needed a instability

    of 20% between the generation and the consumption to

    make the unit act. For the typical setting of 8 it is needed

    an instability of 40% between generation and

    consumption to make the unit act. In the same way, the

    rest of the points of the curve can be read.

    0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1 1.1 1.2 1.3 1.4 1.5 1.6 1.7 1.8 1.9 20

    2

    4

    6

    8

    10

    12

    14

    16

    18

    20

    22V

    ecto

    r S

    hif

    t (d

    egre

    es)

    Consumption (p.u)i

    Island with lack of

    generation

    Island with excess of

    generation

    Perfect Island

    Fig 6- Sensitivity of the algorithm of the vector shift

    6. Security of the algorithm.

    As important as the sensitivity is the security of the

    algorithm. It has been proved that for a setting of 4, the

    simulated system does not act against:

    Single phase-faults.

    Double phase faults.

    Three phase faults: It depends on the duration of the faults, because the longer it lasts, the

    measured vector shift is higher. For example, for

    a setting of 4, doesnt act for faults with a duration shorter than 100ms.

    Another important aspect is the capacity of detecting the

    opening of the breaker just when the fault occurs (if we

    want to be more precise, when it finishes due to the

    opening of the breaker). As different mechanisms are

    used to numb the unit against faults, it is important to

    detect the opening of the breaker just before the fault, in

    this sense we can affirm that in all the cases, when the

    breaker opens during a fault, the unit acts properly with

    almost every setting between 4 and 12 for one-phase,

    double-phase and three-phase faults.

    Finally, we have to highlight the influence of the

    connection and disconnection of the loads and, in it the

    relative strength of the system and the point of

    1

    Discrete,

    Ts = 2.083e-006 s.

    1

    A B CA B C

    A B C

    a b c

    A

    B

    C

    a

    b

    c

    VabcA

    B

    C

    a

    b

    c

    A

    B

    C

    a

    b

    c

    A

    B

    C

    a

    b

    c

    Vf _

    m

    A

    B

    C

    Pm

    Synchronous Machine

    2 MVA 0.69 kV

    1

    wref

    Pref

    we

    Pe0

    dw

    Pm

    gate

    HTG

    v ref

    v d

    v q

    v stab

    Vf

    Excitation

    System

    A

    B

    C

    100MVA, 230 kV

    source

    A B C

    A B C

    Vabc (pu)

    Iabc (pu)

  • connection with the load is fundamental, and the

    algorithm does not run away from those influences. The

    connections and disconnections of high power loads

    make the unit act in a wrong way.

    In the simulated system, we can calculate the vector shift

    provoked by the connection and disconnection of

    different power loads in the exit of the generator or in the

    terminals of the generator in low voltage. If we simulate

    the connection and disconnection of loads in the exit of

    the source, in which changing P2 (power connected en the

    AT side of the transformer) we get a table like the

    following:

    Table 1 Vector shift provoked by the connection and disconnection of

    loads

    Potencia

    (MW/Scc)

    Potencia(pu Scc

    PCC)

    Salto Vector

    -20/28 -20% 22.69

    -10/28 -10% 14.45

    -5/28 -5% 7.77

    -2/28 -2% 3.20

    +2/28 +2% 3.22

    +5/28 +5% 7.81

    +10/28 +10% 14.54

    +20/28 +20% 23.91

    7. Conclusions.

    The designed algorithm for vector shift, measures with

    precision the pure vector shifts and the zero crossing

    ones. Also measures the value of the vector shift to

    enable changes in the settings if needed, with criteria of

    the vector shift measured by the unit. In the other hand,

    the unit is relaying as it does not act against faults and

    trips properly in the openings of the breakers caused by

    faults. The effect of the connection and disconnection of

    the loads and the inaccurate tripping in the abrupt

    changes in the loads in weak systems and for loads that

    are next to the source is not sorted out, but this is a

    problem inherent to the philosophy of operation of the

    vector shift.

    8. Acknowledgements

    This study has been done as a part of the PROINVER

    project which is financed by Spanish Ministry of Science

    and Innovation (INNPACTO program).

    9. References.

    [1] "The Impact of Renewable Energy Sources and

    Distributed Generation on Substation Protection

    and Automation". CIGRE WG B5.34. August

    2010.

    [2] N. Jenkins, R. Allan, P. Crossley, D. Kirschen, and

    G. Strbac, "Embedded Generation", 1st ed.

    London, U.K.: Inst. Elect. Eng., 2000.

    [3] Crompton Instruments, "Vector Shift and ROCOF

    Relay Instruction Manual".

    [4] AREVA, "MICOM P341 Relay Instruction Manual

    P341"

    [5] John Mulhausen, Joe Schaefer, Mangapathirao

    Mynam, Armando Guzmn, and Marcos

    Donolo, "Anti-Islanding Today,Successful

    Islanding in the Future", 2010 Texas A&M

    Conference for Protective Relay Engineer.

    [6] Walmir Freitas, Wilsun Xu, Carolina M.

    Affonso, and Zhenyu Huang,"Comparative

    Analysis Between ROCOF and Vector

    Surge Relays for Distributed Generation

    Applications". IEEE Transactions On

    Power Delivery, VOL. 20, NO. 2, APRIL 2005

    10. Other references.

    [7] Jyh-Cherng Gu, and Cheng-Chun Wang and

    Kuo-Chen Hsu, "Islanding Detection and Protection of a Utility connected Wind Turbines

    via a novel FPGA-based Relay", APAP2009,

    October 18~21, 2009 Jeju, Korea.

    [8] F. Katiraei, C. Abbey, I. Da Cunha and Y. Brisette,

    "Performance Assessment of Commercial

    Relays for Anti-Islanding Protection of Rotating

    Machine Based Distributed Generation".

    CIGRE CANADA, Conference On Power

    Systems, Winnipeg 2008.

    [9] Walmir Freitas, Wilsun Xu, and Zhenyu Huang," A Practical Method for Assessing the

    Effectiveness of vector Surge Relays for

    Distributed Generation Applications". IEEE

    TRANSACTIONS ON POWER DELIVERY,

    VOL. 20, NO. 1, JANUARY 2005