1201 PARC ELISE Supplemental Instruction No. 055 R2 202 – 2425 Quebec Street Vancouver, BC V5T 4L6 FOUGERE ARCHITECTURE INC. Page 1 of 1 Phone: 604.873.2907 [email protected] Date of Issue: March 30, 2017 Distribution: Nelson Chung David Chung Dava Developments Ltd. Dava Developments Ltd. Steve O’Neill Peter Gee Daniel Kravcak Mark Golder Jack Orr Thomas Leung Mathew Mok Mike Dixon Charlie Yao Mary Chan Bill Wong Joe Wong Matt Kokan Brenda Shaw Laurence Kao Kai Mikkelsen Wayne Fougere Jurgen Schlote Joe Larano Dava Developments Ltd. Dava Developments Ltd. Performance Construction Ltd. Performance Construction Ltd. Performance Construction Ltd. Thomas Leung Structural Engineers Ltd. Thomas Leung Structural Engineers Ltd. Williams Engineering Canada Ltd. Williams Engineering Canada Ltd. PMG Landscape Architects Ltd Matson Peck & Topliss Core Concept Consulting Geo Pacific Consultants Ltd. Level 5 Consulting Ltd. CES Group Gage-Babcock & Associates Ltd. Fougere Architecture Inc. Fougere Architecture Inc. Fougere Architecture Inc. Subject: Revision to details on A511 -A106 South building Unit 108 A2 – wall along gridline 32 – studs revised to 6” -HSS’s moved in ½” -Steel studs revised to 6” Prepared by: John Hula Fougere Architecture Inc.

Transcript of 1201 PARC ELISE Supplemental Instruction No. 055 R2€¦ ·  · 2017-04-07-A106 South building...

1201 PARC ELISE Supplemental Instruction No. 055 R2

202 – 2425 Quebec Street Vancouver, BC V5T 4L6

FOUGERE ARCHITECTURE INC.Page 1 of 1

Phone: 604.873.2907 [email protected]

Date of Issue: March 30, 2017 Distribution: Nelson Chung

David Chung Dava Developments Ltd. Dava Developments Ltd.

Steve O’Neill Peter Gee Daniel Kravcak Mark Golder Jack Orr Thomas Leung Mathew Mok Mike Dixon Charlie Yao Mary Chan Bill Wong Joe Wong Matt Kokan Brenda Shaw Laurence Kao Kai Mikkelsen Wayne Fougere Jurgen Schlote Joe Larano

Dava Developments Ltd. Dava Developments Ltd. Performance Construction Ltd. Performance Construction Ltd. Performance Construction Ltd. Thomas Leung Structural Engineers Ltd. Thomas Leung Structural Engineers Ltd. Williams Engineering Canada Ltd. Williams Engineering Canada Ltd. PMG Landscape Architects Ltd Matson Peck & Topliss Core Concept Consulting Geo Pacific Consultants Ltd. Level 5 Consulting Ltd. CES Group Gage-Babcock & Associates Ltd. Fougere Architecture Inc. Fougere Architecture Inc. Fougere Architecture Inc.

Subject: Revision to details on A511

-A106 South building Unit 108 A2 – wall along gridline 32 – studs revised to 6” -HSS’s moved in ½” -Steel studs revised to 6”

Prepared by: John Hula Fougere Architecture Inc.

LEGAL DESCRIPTION:LOT A BLOCK 741 DISTRICT LOT 526 GROUP 1NEW WESTMINSTER DISTRICT PLAN EPP39006

LEGAL DESCRIPTION:LOT A BLOCK 741 DISTRICT LOT 526 GROUP 1NEW WESTMINSTER DISTRICT PLAN EPP39006