115kV Sub-Station - Usual Transm & Distr 1

download 115kV Sub-Station - Usual Transm & Distr 1

of 13

Transcript of 115kV Sub-Station - Usual Transm & Distr 1

  • 7/31/2019 115kV Sub-Station - Usual Transm & Distr 1

    1/13

    Power System Planning Tehran 2008

    2.6 Usual Transmission & Distribution Systems (115 kV & 22/11 kV)

    Characteristics for 115 kV & 22/11 kV systems

    OHL: UGC:

    - rural areas, suburbs - urban and industrialised areas,

    suburbs

    - usually 2 or 4 circuits on one system;

    often together with higher or lower

    voltage levels

    - security distance between cables in

    the trench

    - earthing conductor on top of the tower

    (lightning protection)

    - cable sheath grounded

    - fibre optic or copper conductors,

    integrated in earthing conductor as

    telecommunication cable or separate

    - telecommunication cable beside the

    energy cable

    - transmission of information on OHL

    (Power Line Carrier)

    - transmission on the cable sheath is

    checked

    - aluminium / steel 2A/mm2

    560/50; 250/50

    - copper, aluminium

    - 1,2 conductors/phase - three-phase

    - three single phase cables

    - porcelain insulator - oil, gas pressure, XLPE

    - conductor sag, depending on ice charge

    or maximum temperature

    - cable must have the chance to

    move in the trench

    - surge arrester at the end - surge arrester at the common point

    OHL/ cable

    - backward flash over, disturbing several

    systems

    - digging machines destroy cables

    - conductor oscillations

    - 100 km maximum length - 10...20 km maximum length

    - Z = 380 Ohm (240/40 Al/St)

    PN = 35 MW

    St h= 125 MW

    - Z = 40 Ohm (500 mm2 Al)

    PN = 400 MW

    Sth = 100 MVA

    - fault localisation easy,

    repairing time short

    - electric-acoustical,

    repairing time long

    - short circuit current relative small

    x' ~ 0,2 Ohm/km

    - relative high,

    x' ~ 0,14 Ohm/km

    2. Network Planning - 2.6 Usual Transmission & Distribution Networks page1 / 13

  • 7/31/2019 115kV Sub-Station - Usual Transm & Distr 1

    2/13

  • 7/31/2019 115kV Sub-Station - Usual Transm & Distr 1

    3/13

    Power System Planning Tehran 2008

    - transformer

    harmonised with the capacity of the feeding network

    long life time

    losses as cost factor

    long repair time

    well protected and supervised (oil, tap changer, partly discharges,.. )

    surge arrester

    voltage oscillations (!)

    overload cooling system

    dimensioning of X, (uK)

    transportability

    spare parts

    protection

    two ore more transformers in each node substation 230/115 kV or 115/22 kV.

    2. Network Planning - 2.6 Usual Transmission & Distribution Networks page3 / 13

  • 7/31/2019 115kV Sub-Station - Usual Transm & Distr 1

    4/13

    Power System Planning Tehran 2008

    - network configuration of subtransmission and distribution lines

    meshed, ring, ring with connections, radial, T-connection

    double busbar in important node substations

    redundant, limited redundant or non redundant looping of substations in a line redundant connections by the lower voltage level lines in case of a failure

    110 kV XLPE cable

    2. Network Planning - 2.6 Usual Transmission & Distribution Networks page4 / 13

  • 7/31/2019 115kV Sub-Station - Usual Transm & Distr 1

    5/13

    Power System Planning Tehran 2008

    (115 kV)

    110 kV double busbar air-insulated &

    110 kV double busbar SF6 insulated

    2. Network Planning - 2.6 Usual Transmission & Distribution Networks page5 / 13

  • 7/31/2019 115kV Sub-Station - Usual Transm & Distr 1

    6/13

    Power System Planning Tehran 2008

    - protection system

    distance protection

    overcurrent

    short interruption (OHL)

    differential protection (depends of network structure )

    selectivity

    - supervisory control / operation

    switching telecontrolled

    occupied substations (rare)

    telephone (LV networks)

    customers information

    - maintenance

    organisation and availability of staff and material maintenance data acquisition

    preventive or event orientated

    The electricity transmission + distribution is a SYSTEM

    optimum, if all technical components of one supply level indicate a comparable

    availability

    operation and maintenance is done in an acceptable time

    the feeding substations are harmonised by power capacity and protection with

    the over-layed and underlayed networks

    2. Network Planning - 2.6 Usual Transmission & Distribution Networks page6 / 13

  • 7/31/2019 115kV Sub-Station - Usual Transm & Distr 1

    7/13

  • 7/31/2019 115kV Sub-Station - Usual Transm & Distr 1

    8/13

    Power System Planning Tehran 2008

    - voltage dependent claims

    only little increase of the voltage of the healthy conductors

    use of surge arrester with low-rated voltage

    avoidance of sequence faults avoidance of displacement potentials during the failure free operation

    avoidance of overvoltages as consequence of ignition and extinguishing of

    the arc

    avoidance of ferro-resonance after clearing the earth fault and switching

    measures

    - operation and customer dependent claims

    practically uninterrupted supply of all customers

    economical solution, for later network extension too

    automatic and selective fault localisation compatible with the industrial installation of the customers

    It is not possible to fulfil all requirements; some of them are inconsistent with

    others.

    Network with insulated SP and compensated earth current

    - during faults, the healthy conductors have an increased potential

    - calculating the currents and the displacement potential with symmetrical

    components,

    - aggravation of repeating arc ignition by tuning the resonance circuit near to thenormal frequency (compensated system)

    - repeating ignitions of arcs in insulated SP networks on from 10 A; transients!

    arc currents of 50 A are normally stable; localisation

    2. Network Planning - 2.6 Usual Transmission & Distribution Networks page8 / 13

  • 7/31/2019 115kV Sub-Station - Usual Transm & Distr 1

    9/13

    Power System Planning Tehran 2008

    Znyn5

    11

    Imax = 1.500 A

    2. Network Planning - 2.6 Usual Transmission & Distribution Networks page9 / 13

  • 7/31/2019 115kV Sub-Station - Usual Transm & Distr 1

    10/13

    Power System Planning Tehran 2008

    Networks with low-impedance SP grounding

    - calculating the operational frequency processes by symmetrical components:

    one, two and zero system

    - earth fault factor, the highest operational frequency conductor-to-earth voltageof a healthy phase during a fault with earth contact

    is a scale for the insulation stress during the fault.

    International Practice

    - ideal

    compensation to reduce the earth currents; arcs in air are extinguished

    without switching measures; operating the meshed OHL or single conductor

    cables during a longer time

    over-voltage protection by surge arrester to avoid sequence faults

    short low-impedance earthing to localise the fault by earth fault protection selective short circuit protection with short interruption to switch-off short

    circuits with practically uninterrupting the customers

    - reality

    110 kV rather low-impedance grounding; earthing installations, earth ropes

    and short circuit protection are dimensioned for the highest short circuit

    current. (The earth rest current increases with network extensions,

    especially by cables; the displacement potentials increase in OHL systems

    with multiple circuits on one tower)

    recommendation

    * radial cable networks up to 22 kV : low-impedance 500 A...1000 A

    * earth rest current up to 22 kV : maximum 60 A (comp. SP)

    for 115 kV : maximum 130 A (comp. SP)

    * OHL and UGC: short time SP grounding by resistances dimensioned

    for 300 A

    * 110 kV with insulated SP not allowed; ferro resonances

    * insulated SP: only for networks with limited extension, economical reasons

    2. Network Planning - 2.6 Usual Transmission & Distribution Networks page10 / 13

  • 7/31/2019 115kV Sub-Station - Usual Transm & Distr 1

    11/13

    Power System Planning Tehran 2008

    * earth current compensation

    - reducing the damage proportions

    - transformers Dy

    * low-impedance grounding- reducing damage risk by quick and selective switching off

    Both ways can be successful, as the technical risk can simplified described as

    Risk the damage proportion x frequency

    Consequences of faults

    - low-impedance SP grounding

    limited short circuit current in MV systems because of the reactance upto 1..2 kA; in 115 kV systems to...15 kA

    self healing by short interruption in OHL networks in case of a

    lightning stroke; customers without interruption of supply (only some

    100 ms)

    risk of damaged equipment is very small; short interruption time

    - earth fault in compensated and insulated networks

    capacitive current as fault current; 10 A...100 A

    arc extinguishes by thermal prolongation of the arc

    neglectable damage at the point of earth current risk of transient earth current because of slowly back coming voltage

    self healing insulation, depends of energy at the failure point

    not self healing; duration of accidental arc to ground; insulation stress

    special behaviour of mixed OHL/UGC networks (statistics)

    - double earth fault in compensated and insulated networks

    two faulty points in a longer distance

    double earth fault via ground: contact and influencing potential

    relatively rare, grounding devices normally not dimensioned for this

    - grounding system

    thermal dimensioning

    contact potential

    earth current 10 A...hours; 10 kA...< 1 sec

    minimum 50 mm2 iron (compensated SP grounding)

    maximum 65 V contact voltage; 60 A rest current -> 4 Ohm

    (meshed grounding system, 1-m-ring, 25% contact voltage)

    low-impedance SP grounded

    2. Network Planning - 2.6 Usual Transmission & Distribution Networks page11 / 13

  • 7/31/2019 115kV Sub-Station - Usual Transm & Distr 1

    12/13

    Power System Planning Tehran 2008

    - maximum short circuit current; grounding wires

    100 mm2 iron

    35 mm2 copper

    influence to telecommunication lines

    Basic grounding of a substation

    - changing from compensated to low-impedance grounded SP

    grounding system

    ct

    protection

    surge arrester

    - localisation of earth faults

    insulated SP

    active and reactive power flow of the 50 Hz oscillation to determine the

    fault direction;

    localisation relays; ct in Holmgreen position, cable encircling ct

    compensated networks

    power direction in the zero-system; high precision necessary, watt rest

    current; increase by bypass switching (resistance parallel with

    compensating inductivity; ohmic component; less compensation))

    harmonics

    5th harmonic; compensation not effective; minimum 0,5% Un

    2. Network Planning - 2.6 Usual Transmission & Distribution Networks page12 / 13

  • 7/31/2019 115kV Sub-Station - Usual Transm & Distr 1

    13/13

    Power System Planning Tehran 2008

    transient earth relay (reactive power)

    short time switching-off and on

    short time SP grounding

    short time phase grounding earth fault distance protection relay

    central evaluation with computer support

    2. Network Planning - 2.6 Usual Transmission & Distribution Networks page 13 / 13