115kV Sub-Station - Usual Transm & Distr 1
-
Upload
venkat-suresh -
Category
Documents
-
view
228 -
download
1
Transcript of 115kV Sub-Station - Usual Transm & Distr 1
-
7/31/2019 115kV Sub-Station - Usual Transm & Distr 1
1/13
Power System Planning Tehran 2008
2.6 Usual Transmission & Distribution Systems (115 kV & 22/11 kV)
Characteristics for 115 kV & 22/11 kV systems
OHL: UGC:
- rural areas, suburbs - urban and industrialised areas,
suburbs
- usually 2 or 4 circuits on one system;
often together with higher or lower
voltage levels
- security distance between cables in
the trench
- earthing conductor on top of the tower
(lightning protection)
- cable sheath grounded
- fibre optic or copper conductors,
integrated in earthing conductor as
telecommunication cable or separate
- telecommunication cable beside the
energy cable
- transmission of information on OHL
(Power Line Carrier)
- transmission on the cable sheath is
checked
- aluminium / steel 2A/mm2
560/50; 250/50
- copper, aluminium
- 1,2 conductors/phase - three-phase
- three single phase cables
- porcelain insulator - oil, gas pressure, XLPE
- conductor sag, depending on ice charge
or maximum temperature
- cable must have the chance to
move in the trench
- surge arrester at the end - surge arrester at the common point
OHL/ cable
- backward flash over, disturbing several
systems
- digging machines destroy cables
- conductor oscillations
- 100 km maximum length - 10...20 km maximum length
- Z = 380 Ohm (240/40 Al/St)
PN = 35 MW
St h= 125 MW
- Z = 40 Ohm (500 mm2 Al)
PN = 400 MW
Sth = 100 MVA
- fault localisation easy,
repairing time short
- electric-acoustical,
repairing time long
- short circuit current relative small
x' ~ 0,2 Ohm/km
- relative high,
x' ~ 0,14 Ohm/km
2. Network Planning - 2.6 Usual Transmission & Distribution Networks page1 / 13
-
7/31/2019 115kV Sub-Station - Usual Transm & Distr 1
2/13
-
7/31/2019 115kV Sub-Station - Usual Transm & Distr 1
3/13
Power System Planning Tehran 2008
- transformer
harmonised with the capacity of the feeding network
long life time
losses as cost factor
long repair time
well protected and supervised (oil, tap changer, partly discharges,.. )
surge arrester
voltage oscillations (!)
overload cooling system
dimensioning of X, (uK)
transportability
spare parts
protection
two ore more transformers in each node substation 230/115 kV or 115/22 kV.
2. Network Planning - 2.6 Usual Transmission & Distribution Networks page3 / 13
-
7/31/2019 115kV Sub-Station - Usual Transm & Distr 1
4/13
Power System Planning Tehran 2008
- network configuration of subtransmission and distribution lines
meshed, ring, ring with connections, radial, T-connection
double busbar in important node substations
redundant, limited redundant or non redundant looping of substations in a line redundant connections by the lower voltage level lines in case of a failure
110 kV XLPE cable
2. Network Planning - 2.6 Usual Transmission & Distribution Networks page4 / 13
-
7/31/2019 115kV Sub-Station - Usual Transm & Distr 1
5/13
Power System Planning Tehran 2008
(115 kV)
110 kV double busbar air-insulated &
110 kV double busbar SF6 insulated
2. Network Planning - 2.6 Usual Transmission & Distribution Networks page5 / 13
-
7/31/2019 115kV Sub-Station - Usual Transm & Distr 1
6/13
Power System Planning Tehran 2008
- protection system
distance protection
overcurrent
short interruption (OHL)
differential protection (depends of network structure )
selectivity
- supervisory control / operation
switching telecontrolled
occupied substations (rare)
telephone (LV networks)
customers information
- maintenance
organisation and availability of staff and material maintenance data acquisition
preventive or event orientated
The electricity transmission + distribution is a SYSTEM
optimum, if all technical components of one supply level indicate a comparable
availability
operation and maintenance is done in an acceptable time
the feeding substations are harmonised by power capacity and protection with
the over-layed and underlayed networks
2. Network Planning - 2.6 Usual Transmission & Distribution Networks page6 / 13
-
7/31/2019 115kV Sub-Station - Usual Transm & Distr 1
7/13
-
7/31/2019 115kV Sub-Station - Usual Transm & Distr 1
8/13
Power System Planning Tehran 2008
- voltage dependent claims
only little increase of the voltage of the healthy conductors
use of surge arrester with low-rated voltage
avoidance of sequence faults avoidance of displacement potentials during the failure free operation
avoidance of overvoltages as consequence of ignition and extinguishing of
the arc
avoidance of ferro-resonance after clearing the earth fault and switching
measures
- operation and customer dependent claims
practically uninterrupted supply of all customers
economical solution, for later network extension too
automatic and selective fault localisation compatible with the industrial installation of the customers
It is not possible to fulfil all requirements; some of them are inconsistent with
others.
Network with insulated SP and compensated earth current
- during faults, the healthy conductors have an increased potential
- calculating the currents and the displacement potential with symmetrical
components,
- aggravation of repeating arc ignition by tuning the resonance circuit near to thenormal frequency (compensated system)
- repeating ignitions of arcs in insulated SP networks on from 10 A; transients!
arc currents of 50 A are normally stable; localisation
2. Network Planning - 2.6 Usual Transmission & Distribution Networks page8 / 13
-
7/31/2019 115kV Sub-Station - Usual Transm & Distr 1
9/13
Power System Planning Tehran 2008
Znyn5
11
Imax = 1.500 A
2. Network Planning - 2.6 Usual Transmission & Distribution Networks page9 / 13
-
7/31/2019 115kV Sub-Station - Usual Transm & Distr 1
10/13
Power System Planning Tehran 2008
Networks with low-impedance SP grounding
- calculating the operational frequency processes by symmetrical components:
one, two and zero system
- earth fault factor, the highest operational frequency conductor-to-earth voltageof a healthy phase during a fault with earth contact
is a scale for the insulation stress during the fault.
International Practice
- ideal
compensation to reduce the earth currents; arcs in air are extinguished
without switching measures; operating the meshed OHL or single conductor
cables during a longer time
over-voltage protection by surge arrester to avoid sequence faults
short low-impedance earthing to localise the fault by earth fault protection selective short circuit protection with short interruption to switch-off short
circuits with practically uninterrupting the customers
- reality
110 kV rather low-impedance grounding; earthing installations, earth ropes
and short circuit protection are dimensioned for the highest short circuit
current. (The earth rest current increases with network extensions,
especially by cables; the displacement potentials increase in OHL systems
with multiple circuits on one tower)
recommendation
* radial cable networks up to 22 kV : low-impedance 500 A...1000 A
* earth rest current up to 22 kV : maximum 60 A (comp. SP)
for 115 kV : maximum 130 A (comp. SP)
* OHL and UGC: short time SP grounding by resistances dimensioned
for 300 A
* 110 kV with insulated SP not allowed; ferro resonances
* insulated SP: only for networks with limited extension, economical reasons
2. Network Planning - 2.6 Usual Transmission & Distribution Networks page10 / 13
-
7/31/2019 115kV Sub-Station - Usual Transm & Distr 1
11/13
Power System Planning Tehran 2008
* earth current compensation
- reducing the damage proportions
- transformers Dy
* low-impedance grounding- reducing damage risk by quick and selective switching off
Both ways can be successful, as the technical risk can simplified described as
Risk the damage proportion x frequency
Consequences of faults
- low-impedance SP grounding
limited short circuit current in MV systems because of the reactance upto 1..2 kA; in 115 kV systems to...15 kA
self healing by short interruption in OHL networks in case of a
lightning stroke; customers without interruption of supply (only some
100 ms)
risk of damaged equipment is very small; short interruption time
- earth fault in compensated and insulated networks
capacitive current as fault current; 10 A...100 A
arc extinguishes by thermal prolongation of the arc
neglectable damage at the point of earth current risk of transient earth current because of slowly back coming voltage
self healing insulation, depends of energy at the failure point
not self healing; duration of accidental arc to ground; insulation stress
special behaviour of mixed OHL/UGC networks (statistics)
- double earth fault in compensated and insulated networks
two faulty points in a longer distance
double earth fault via ground: contact and influencing potential
relatively rare, grounding devices normally not dimensioned for this
- grounding system
thermal dimensioning
contact potential
earth current 10 A...hours; 10 kA...< 1 sec
minimum 50 mm2 iron (compensated SP grounding)
maximum 65 V contact voltage; 60 A rest current -> 4 Ohm
(meshed grounding system, 1-m-ring, 25% contact voltage)
low-impedance SP grounded
2. Network Planning - 2.6 Usual Transmission & Distribution Networks page11 / 13
-
7/31/2019 115kV Sub-Station - Usual Transm & Distr 1
12/13
Power System Planning Tehran 2008
- maximum short circuit current; grounding wires
100 mm2 iron
35 mm2 copper
influence to telecommunication lines
Basic grounding of a substation
- changing from compensated to low-impedance grounded SP
grounding system
ct
protection
surge arrester
- localisation of earth faults
insulated SP
active and reactive power flow of the 50 Hz oscillation to determine the
fault direction;
localisation relays; ct in Holmgreen position, cable encircling ct
compensated networks
power direction in the zero-system; high precision necessary, watt rest
current; increase by bypass switching (resistance parallel with
compensating inductivity; ohmic component; less compensation))
harmonics
5th harmonic; compensation not effective; minimum 0,5% Un
2. Network Planning - 2.6 Usual Transmission & Distribution Networks page12 / 13
-
7/31/2019 115kV Sub-Station - Usual Transm & Distr 1
13/13
Power System Planning Tehran 2008
transient earth relay (reactive power)
short time switching-off and on
short time SP grounding
short time phase grounding earth fault distance protection relay
central evaluation with computer support
2. Network Planning - 2.6 Usual Transmission & Distribution Networks page 13 / 13