112/06/2012. Summary Network infrastructure consolidation & upgrade 66 kV et 18 kV UPS SILCON...

35
LS1 DAY F. Duval / EN-EL on behalf of EN/EL Activités EN-E 1 12/06/2012

Transcript of 112/06/2012. Summary Network infrastructure consolidation & upgrade 66 kV et 18 kV UPS SILCON...

Page 1: 112/06/2012. Summary  Network infrastructure consolidation & upgrade 66 kV et 18 kV  UPS SILCON replacement project  Projects and maintenance work.

LS1 DAY

F. Duval / EN-EL on behalf of EN/EL group

Activités EN-EL

1 12/06/2012

Page 2: 112/06/2012. Summary  Network infrastructure consolidation & upgrade 66 kV et 18 kV  UPS SILCON replacement project  Projects and maintenance work.

Summary

Network infrastructure consolidation & upgrade 66 kV et 18 kV UPS SILCON replacement project Projects and maintenance work on substation 400 kV & 66 kV Maintenance works on 18 kV, 3.3 kV and LV networks Yearly tests Other EN/EL consolidation & upgrade projects Projects for other groups R2E Cables & fibres projects Schedule Workloads Increase of manpower

EN/EL activities during LS1

2 12/06/2012LS1 Day - François Duval EN-EL

Page 3: 112/06/2012. Summary  Network infrastructure consolidation & upgrade 66 kV et 18 kV  UPS SILCON replacement project  Projects and maintenance work.

3 LS1 Day - François Duval EN-EL

66 et 18 kV Networks Consolidation & Upgrade

power cables replacement18 kV SPS New substation BE91in Prévessin (Safe feeding of CCC safety network

for SPS) Repowering CCC 66 kV Protection system consolidation (Prévessin and LHC 1-2-4-6-8) Extension of the 66 kV substation Prevessin New 66 kV feeder on Meyrin site + upgrade of the18 kV substation in

the west area ME59 New power link18 kV ME9 –ME59 in Meyrin and Autotransfert

modification accordingly Upgrade main18 kV substation in Prévessin du BE Consolidation of fire protection systems for power transformers and

for the 400 kV substation Consolidation of the18 kV substations BA4 et BA5

requirements depending mainly on the injector schedule (2013 !) Total budget = 20 MCHF

12 Juin 2012

Page 4: 112/06/2012. Summary  Network infrastructure consolidation & upgrade 66 kV et 18 kV  UPS SILCON replacement project  Projects and maintenance work.

4 LS1 Day - François Duval EN-EL

66 et 18 kV Networks Consolidation & Upgrade

12 Juin 2012

2013Upgrade sous

station BE

2012-2013Réseau secours Prevessin et SPS

2012-2013 Sous station BE91

2012-2013SPS consolidation

2012-2013Rénovation protection

66 kV

2012-2013Nouvelles lignes 66 kV et

18 kV vers Meyrin

Page 5: 112/06/2012. Summary  Network infrastructure consolidation & upgrade 66 kV et 18 kV  UPS SILCON replacement project  Projects and maintenance work.

5 LS1 Day - François Duval EN-EL

66 et 18 kV Networks Consolidation & Upgrade

12 Juin 2012

2012-2013Nouvelles lignes 66 kV

et18 kV vers Prevessin

2012-2013Nouvelle sous station

66 kV MEH59

2013-2014Nouvelles liaison 18 KV

entre ME9 –ME59

2012-2014Upgrade sous station

ME59

Page 6: 112/06/2012. Summary  Network infrastructure consolidation & upgrade 66 kV et 18 kV  UPS SILCON replacement project  Projects and maintenance work.

6 LS1 Day - François Duval EN-EL 12 Juin 2012

LS1 EN-EL activities Power distribution and Operation

Page 7: 112/06/2012. Summary  Network infrastructure consolidation & upgrade 66 kV et 18 kV  UPS SILCON replacement project  Projects and maintenance work.

7 LS1 Day - François Duval EN-EL

Replacement of SILCON UPSs

All cryo and machine : 82 UPS

Any new UPS connections Requests must be done before end of June 2012

12 Juin 2012

UPS machine : 2 UPS in RE (x16)2 UPS in UA (x8)2 UPS each LHC point (US, UW ou UJ) (x8)

UPS cryo :2 UPS on LHC even points (US, UW) (x4)2 UPS on surface even points (SA, SH) (x4)2 UPS in PM18

Page 8: 112/06/2012. Summary  Network infrastructure consolidation & upgrade 66 kV et 18 kV  UPS SILCON replacement project  Projects and maintenance work.

8 LS1 Day - François Duval EN-EL

Replacement of SILCON UPSs

Impact on other activities: 6 weeks per area (for 2 UPS)

Distribution downstream off during works

Possible refeeding from diesel network (subject to request justified by safety)

Transport and handling: ~ 660 kg for an UPS and 2000 kg for battery sets (removal of old ones as well ) Lifts on Points 3, 5 et 7 too small for UPS : Width > 800 mm

Alcoves RE : A safety issue has to be considered: Charging batteries may lead to hydrogen production. Ventilation must be dimensioned so that the risk of explosion is eliminated (EN/EL, GS/ASE, HSE)

12 Juin 2012

Page 9: 112/06/2012. Summary  Network infrastructure consolidation & upgrade 66 kV et 18 kV  UPS SILCON replacement project  Projects and maintenance work.

9 LS1 Day - François Duval EN-EL

66 & 400 kV Substations Maintenance & Projects

Maintenance 400 kV & 66kV substations Tests of the protection and signals on the RTE interfaces On-site maintenance of two 400 kV circuit breakers Factory maintenance of three 400 kV circuit breakers Maintenance of the 400 kV & 66kV transformers

Projects Consolidation of the66 kV protection (BE & LHC 1-2-4-6-8) Extension of the 66 kV substation Consolidation of the fire detection of the 400 kV substation & its transformers

Schedule contraints

12 Juin 2012

RTE (400 kV) Disconnected during 3-4 weeks

ALPIQ (SIG) 60 MVA max during 8 weeks after the LHC warm-up

Réseau de transport 66 kV Off during 8 weeks

AUTOTRANSFERT Inoperable during 8 weeks

Tests AUG LHC Cannot be done during this time

Page 10: 112/06/2012. Summary  Network infrastructure consolidation & upgrade 66 kV et 18 kV  UPS SILCON replacement project  Projects and maintenance work.

10 07/06/2012

66 & 400 kV Substations Maintenance & Projects

Page 11: 112/06/2012. Summary  Network infrastructure consolidation & upgrade 66 kV et 18 kV  UPS SILCON replacement project  Projects and maintenance work.

11 LS1 Day - François Duval EN-EL

18 kV, 3.3 kV & LV Networks Maintenance

1/3 of the equipment 18 kV et 3.3kV : 400 cubicles LHC General Services LV switchgears LHC Safety Network LV switchgears Replacement of all breakers dedicated to the LHC safety network

switching LHC Diesel PLC consolidation LHC 18 kV & 400 V switchgears in the alcoves

Planning - requirements Slots of 5 to 6 days for each LHC points (including the AUG tests on the

last day) No underground access for 2 to 3 days (safety network not available) No handling operations for 5 days (distribution off cranes off) No 18 KV maintenance during 400/66 kV maintenance operations No safety network maintenance while AUTOTRANSFERT is off Necessary coordination with CRG & CV

12 Juin 2012

Page 12: 112/06/2012. Summary  Network infrastructure consolidation & upgrade 66 kV et 18 kV  UPS SILCON replacement project  Projects and maintenance work.

12 LS1 Day - François Duval EN-EL

Yearly Test Campaigns

Diesel and safety network AUTOTRANSFERT AUG

Schedule - requirements PS / SPS magnet tests and run CTF3 until december 2012 Warm-up LHC Cryo To be scheduled:

end 2012 or early 2013 end 2013 or early 2014 end 2014 ? No AUG tests during maintenance on 400 kV

12 Juin 2012

Page 13: 112/06/2012. Summary  Network infrastructure consolidation & upgrade 66 kV et 18 kV  UPS SILCON replacement project  Projects and maintenance work.

13 LS1 Day - François Duval EN-EL

Other EL Consolidation Projects

12 Juin 2012

Description Confirmed ?

Technically defined?

Consolidation following task force «48V LHC2» (LHC)

yes yes (2012)

obsolete LV switchgears (ME23, ME24) yes yes

Replacement of obsolete switchgears (LHC, MEY)

yes yes

Replacement of LHC safety network PLC & Circuit breakers

yes yes

Consolidation of LHC Diesel PLC no no (LS2)

Increase reliability of AUG in LHC yes yes

Consolidation of EL SCADA system yes yes

Page 14: 112/06/2012. Summary  Network infrastructure consolidation & upgrade 66 kV et 18 kV  UPS SILCON replacement project  Projects and maintenance work.

14 LS1 Day - François Duval EN-EL

Projects for other groups EN/CV

12 Juin 2012

EL & CV meeting on 04/05/2012 New meeting to be scheduled asap

Description Confirmed ? Technically defined for EL?

Upgrade pumping station PM32 yes yes

SU2 & SU8 TRANE motors replacement yes yes

New cooling tower SHM LHC4 yes no (on its way)

New cooling tower LHC6 & LHC8 yes no (on its way)

New chiller SPS-BA3 no no

Closing collimators area LHC7 no no (Major issue)

Upgrade ventilation PS : Design and supply the new power supply for the ventilation units.

yes no

Safety measures for LHC: deltap tunnel UX85: New power line

yes no

New chillers SU2 for Alice no no (on its way)

Page 15: 112/06/2012. Summary  Network infrastructure consolidation & upgrade 66 kV et 18 kV  UPS SILCON replacement project  Projects and maintenance work.

15 LS1 Day - François Duval EN-EL

Projects for other groups TE/EPC

12 Juin 2012

Description Confirmed ? Technically defined for EL?

LHC filters protections from FIR to TENCH (new sepams ?)

yes yes

Converters replacement FMCM SR1 et SR5 no no

Control cabling for transformers SMB ? yes no

BEQ2 et BEQ3 protections from baycontroler to PLC

yes no

SVC : 18 kV cables LHC2 replacement yes yes

New feeder18 kV SMB for SPS 3 yes no

SPS Mains Converters: Consolidation : Supply and installation of Earthing Switches and 18kV cables

yes no

EPC High Voltage Power Converter Test Bench: Construction in building 377

yes yes

EPC Medium Power Converter Test Bench: Construction in building 287

yes no

Last meeting 7th of June 2012: Most of the requests clarified and will be defined soon.

Most of the requests scheduled on 1st semester 2014

Page 16: 112/06/2012. Summary  Network infrastructure consolidation & upgrade 66 kV et 18 kV  UPS SILCON replacement project  Projects and maintenance work.

16 LS1 Day - François Duval EN-EL

Projects for other groups various

12 Juin 2012

Description Confirmed ?

Technically defined for EL?

513 Upgrade automatic Normal / Secours yes yes

HIE ISOLDE yes yes

LV infrastructures for bungalows SMACC yes No, but on its

way(2012)

LINAC 4 yes yes

Moving transformer Civil Engineering on the Route Goward over the PS

no no

Electrical power supplies to new cranes. HE consolidation yes no

ELENA Extra Low Energy Antiproton (hall 193) no no

COMPASS no no

Page 17: 112/06/2012. Summary  Network infrastructure consolidation & upgrade 66 kV et 18 kV  UPS SILCON replacement project  Projects and maintenance work.

17 LS1 Day - François Duval EN-EL

R2E Relocation of equipment

Locations UJ14, 16, US15, UJ56, USC55, UL55, UL557, UJ76, TZ76, PM76, US85, UL84.

Work scheduled during all LS1. Contractors EMTE (Points 1, 7, 8) & SPIE (Point 5).

Impact on other activities: Difficult access to the work zone, transport not easy, limited co-activity (pts 5

(UP, UL) & 7 (TZ))

Coordination: Works done with MEF, MTE, EPC, CV, HE, EN-EL (consignation/déconsignation)

12 Juin 2012

Page 18: 112/06/2012. Summary  Network infrastructure consolidation & upgrade 66 kV et 18 kV  UPS SILCON replacement project  Projects and maintenance work.

18 LS1 Day - François Duval EN-EL

R2E Interruption of Service

Locations UJ14, 16 – UJ56 (+ adjacent tunnel area) – UJ76 (+ adjacent tunnel area) –

US85 (+ adjacent tunnel area)

Impact on networks and personnel safety: UPS network (EOD) : consignation schedule compatible with WARM-UP

cryo & other works? Converter network (ERD) en UJ14-15, UJ56, UJ76 Réseaux canalis racks – consignation schedule compatible with WARM-UP

cryo & other works?

The safety network (ESD) & general services networks (EBD – plugs & Lighting) will be operational during works but during 2 weeks, including one week without any EL safety systems: 48 VDC, AUG and safety lighting .

Presently scheduled : October / November 2013

12 Juin 2012

Page 19: 112/06/2012. Summary  Network infrastructure consolidation & upgrade 66 kV et 18 kV  UPS SILCON replacement project  Projects and maintenance work.

Replacement of water cooled cable hoses:

19 07/06/2012

Locations: UA/RA47, 63, 67, 83 et 87 12.5 months. Contractor: FLOHE, Supply: FLOHE & Contitech -

3200m. Impact on other activities:

Access to UAs & RAs, scaffolding around converters, access to RA tunnel close to DFBs

Coordination: Works done with CV, EPC, MEF, HE, MTE & EN-EL (consignation/décons.)

Schedule

2 shifts will not be possible (limited FLOHE manpower)

LS1 Day - François Duval EN-EL

Page 20: 112/06/2012. Summary  Network infrastructure consolidation & upgrade 66 kV et 18 kV  UPS SILCON replacement project  Projects and maintenance work.

basket 1, 2

Cable tray

New cable baskets LHC 1, 3 et 5

20 07/06/2012

following ALARA 01/2012 Locations: R34, R36, R37 – 2 cable baskets on 550m. 3 full months . Contractor C209, supply C209. Other areas: RB14, 16, R542, 561: câblofil/télex installation on the

ground. Impact on other activities:

Access to the tunnel pt 3, difficult transport activities.

Coordination: Works done with MEF et EN-HE et EN-EL (Integration)

Schedule:Lead by RP. New cables to be installed in point 3 (TE-VSC)

LS1 Day - François Duval EN-EL

Page 21: 112/06/2012. Summary  Network infrastructure consolidation & upgrade 66 kV et 18 kV  UPS SILCON replacement project  Projects and maintenance work.

12 Flexwell cables replacement PM45

21 07/06/2012

Locations: SR4, SL42, SD4, PM45, UJ44, UJ46, RA43, RA47 4 full weeks. Contractor: EMTE, supply: CERN.

Impact on other activities: Access to PM45, RA up to 12 cell including areas behind DFBs.

Coordination: Works to be done with BE-RF, MEF, MTE, EPC (consignation/décons.)

Schedule: to be defined with MEF et BE-RF (tests and connectors mounting).

Removal of 10km and installation of 7.4 km of Flexwell cable 7/8.

LS1 Day - François Duval EN-EL

Page 22: 112/06/2012. Summary  Network infrastructure consolidation & upgrade 66 kV et 18 kV  UPS SILCON replacement project  Projects and maintenance work.

TOTEM: modification of WCC circuits

22 07/06/2012

circuits RQ 4, 5, 6, 7, 8, 9, 10 Locations: RR53 & 57 5 full months on both sides Contractor FLOHE, supply: Technical Specification to be written.

Impact on other activities: Access to RR53 et 57, transport. Works above converters.

Coordination: Work to be done with MEF, HE, CV, TE-EPC, TE-MPE & EN-EL (Integration,

consignation/décons.)

Schedule: to be defined with MEF.

RR53

DFB+

-

+-

DFB

+-

DFB

+-

+

LS1 Day - François Duval EN-EL

Page 23: 112/06/2012. Summary  Network infrastructure consolidation & upgrade 66 kV et 18 kV  UPS SILCON replacement project  Projects and maintenance work.

Many requests from other groups and from the experiments to be finalised (CRG, ASE, etc.)

Experiments requests were not included in PLAN@CERN

LS1 EN-EL activities

23 07/06/2012LS1 Day - François Duval EN-EL

Page 24: 112/06/2012. Summary  Network infrastructure consolidation & upgrade 66 kV et 18 kV  UPS SILCON replacement project  Projects and maintenance work.

S12P1 S23P2 S34P3 S45P4 S56P5 S67P6 S78P7 S81P8

Nov.

Dec.Jan.Feb.Mar.Apr.MayJun.Jul.

Aug.Sep.Oct.Nov.

Dec.Jan.Feb.Mar.Apr.MayJun.

20

13

20

14

EN

K. Foraz - LHC Performance Workshop 2012

24Feb. 8th 2012

PT PTPT PT

PT PTPT PT

SplicesSplices

SplicesSplices

SplicesSplices

SplicesSplices

Cry

o M

ain

t.

Cry

o M

ain

t.

Cry

o M

ain

t.

Cry

o M

ain

t.

-> 10K

CSCM

CSCM preparation

Warm-upWarm-up Warm-upWarm-up

Warm-up Warm-up Warm-up

Warm-up

Powering Tests Powering

Tests Powering Tests Powering

Tests

Powering Tests

Powering Tests

Powering Tests Powering

Tests

Cool-down Cool-

down Cool-down Cool-

down

Cool-down

Cool-down

Cool-down Cool-

down

Travaux 400 kV et 66 kV – Pas d’autotransfert – S CERN <60MVA

Consignations pour R2E ?

Page 25: 112/06/2012. Summary  Network infrastructure consolidation & upgrade 66 kV et 18 kV  UPS SILCON replacement project  Projects and maintenance work.

25 LS1 Day - François Duval EN-EL

Summary of HV, LV & Controls during LS1

12 Juin 2012

Pro

ject

s +

Main

ten

ance

+ T

est

sEL

& o

ther

gro

up

s

Work

load f

or

Hig

h

Volt

age,

Low

Volt

age &

C

ontr

ols

Sect

ions

Requirements / Resources > 1,2 In particular during 2nd semester 2013)

More resourcesMore requests are not affordable

Page 26: 112/06/2012. Summary  Network infrastructure consolidation & upgrade 66 kV et 18 kV  UPS SILCON replacement project  Projects and maintenance work.

26 LS1 Day - François Duval EN-EL

Cables & Fibres: Requests from BE

12 Juin 2012

Page 27: 112/06/2012. Summary  Network infrastructure consolidation & upgrade 66 kV et 18 kV  UPS SILCON replacement project  Projects and maintenance work.

27 LS1 Day - François Duval EN-EL

Cables & Fibres: Requests from TE

12 Juin 2012

VSC requests were not fully considered yet

Page 28: 112/06/2012. Summary  Network infrastructure consolidation & upgrade 66 kV et 18 kV  UPS SILCON replacement project  Projects and maintenance work.

28 LS1 Day - François Duval EN-EL

Cables & Fibres: Requests from PH

12 Juin 2012

Page 29: 112/06/2012. Summary  Network infrastructure consolidation & upgrade 66 kV et 18 kV  UPS SILCON replacement project  Projects and maintenance work.

29 LS1 Day - François Duval EN-EL

Cables & Fibres: Requests from IT

12 Juin 2012

Page 30: 112/06/2012. Summary  Network infrastructure consolidation & upgrade 66 kV et 18 kV  UPS SILCON replacement project  Projects and maintenance work.

30 LS1 Day - François Duval EN-EL

Cables & Fibres

The preparation work behind the cabling workload estimate

12 Juin 2012

Page 31: 112/06/2012. Summary  Network infrastructure consolidation & upgrade 66 kV et 18 kV  UPS SILCON replacement project  Projects and maintenance work.

31 LS1 Day - François Duval EN-EL

Cables & Fibres

12 Juin 2012

requirements/resources

The LS1 Project Leader decided

Page 32: 112/06/2012. Summary  Network infrastructure consolidation & upgrade 66 kV et 18 kV  UPS SILCON replacement project  Projects and maintenance work.

32 LS1 Day - François Duval EN-EL

Cables & Fibres

Additional resources AGH (12 project associates from Krakow) Fellows & associates (+10 in 2011/2012) 2 installation contracts (doubled manpower) FSU being prepared Specialists + project managers required (skilled

and experienced people)

12 Juin 2012

Page 33: 112/06/2012. Summary  Network infrastructure consolidation & upgrade 66 kV et 18 kV  UPS SILCON replacement project  Projects and maintenance work.

33 LS1 Day - François Duval EN-EL

Cables & Fibres

Help from other departments & experiments

We still want new people working with EL team in order to have coherent works done

Work supervisors Knowledge and experience of cable laying or fibre blowing technologies Experience in work site supervision Knowledge of site works

Project managers Project management People management Schedule & Budget management Knowledge of dedicated softwares(GESMAR, Câblothèque)

12 Juin 2012

Page 34: 112/06/2012. Summary  Network infrastructure consolidation & upgrade 66 kV et 18 kV  UPS SILCON replacement project  Projects and maintenance work.

34 LS1 Day - François Duval EN-EL

Cables & Fibres

But there are limits to the increase of manpower:

Lack of experience Increase of manpower of contractors CERN access, hotels, logistics bottle neck, Base vie? Schedule/coactivity

12 Juin 2012

Page 35: 112/06/2012. Summary  Network infrastructure consolidation & upgrade 66 kV et 18 kV  UPS SILCON replacement project  Projects and maintenance work.

35 LS1 Day - François Duval EN-EL

LS1 will be a very huge shutdown also for EN/EL

On the HV & LV infrastructure side, The program will be done with some additional resources

On the cables & fibres side, the situation is critical: prioritization is done but the effort is huge for the section in charge. Additional resources have been deployed from other departments: more are needed.

We are worried about the flow of requests which are still popping up in PLAN@CERN or elsewhere

12 Juin 2012

EN/EL activities during LS1: Conclusion