1111~lllr---;32.1..-~-- · 17 18 19 Title Labora·tory Model with Original Spillway Configuration...
Transcript of 1111~lllr---;32.1..-~-- · 17 18 19 Title Labora·tory Model with Original Spillway Configuration...
1111~lllr---;32.1..-~--
LEHIGH UNIVERSITY,CIVIL ENGINEERING DEPARTMENT
FRITZ ENGINEERING LABORATORYHYDRAULIC AND SANITARY ENGINEERING DIVISION
MODEL STUDY OF NINETY DEGREE SPILLWAY
FOR
NOCKAMIXON DAM
Project Report No. 52
Prepared by
David R. Basco
John B. Herbich
and
Paul D. Erfle
Prepared for
The General State Authority
Harrisburg, Pennsylvania
March, 1967
Bethlehem, Pennsylvania
Fritz Engineering Laboratory Report No. 326.2
i
A B S T RAe T
A hydraulic model study of an unusually designed spillway ~as
requested by the- General State Authority, Commonwealth of Pennsylvania.
The dam is to be located in Bucks County, Pennsylvania and is part of
ItProject 70" designed to increase the number of recreational facilities
in the Commonwealth. Economics and the topography at the dam site
dictated the ninety degree turn in the spillway.
A 60 to 1 scale model was constructed in the Hydraulics
Laboratory, Civil Engineering Department, Lehigh University. The Con~
suIting Engineers' original design was tested and it was found that
several improvements in the hydraulic flow patterns should be made. The
flows over the control weirs, energy dissipators (hydraulic jumps) and
flow passages were all in need of hydraulic improvement. Modifications
made to the model primarily consisted of improving entrance conditions
to the first weir by use of a large streamlined dike; rounding the
corners of -the ninety degree turn to provide smoother flow; and redesig'n-
ing the second weir to produce a more efficient hydraulic jump. All
modifications resulted in totally improved flow patterns and energy
dissipation in the entire spillway structure. The model study also
resulted in some cost saving in construction which more than offset the
cost of the, rru)del study.,\"
ii
A B S T RAe T (continued)
It was therefore concluded that if the pro~otype spillway is
constructed according to the final design as determined by the model
study, the dam will adequately be protected from the Standard Project
Flood for the drainage basin.
iii
PRE F ACE
A research contract between the General State Authority,
Commonwealth of Pennsylvania, Harrisburg, Pennsylvania and Lehigh
University's Institute of Research provided for experimental hydraulic
studies of an unusually designed right angle spillway. Pickering,
Corts and Summerson, Inc., Consulting Engineers, Langhorne, Pennsylvania,
are responsible for the design of Project No. G.S.A. 194-12, Nockamixon
State Park, Bucks County, Pennsylvania. Justin and Courtney,- Consulting
Engineers, Philadelphia, Pennsylvania, have been subcontracted for
the dam and spillway design. The model investigation was conducted by
the Hydraulic and Sanitary Engineering Division of Fritz Engineering
Laboratory, Department of Civil Engineering.
The study was made on a dynamically similar model of the spil1-
way and was primarily concerned with checking the hydraulic performance
of the Consulting Engineer's uniquely arranged spillway design.
The project had been under the direction of Dr. John B. Herbich,
who was *Chairman of the Hydraulics and Sanitary Engineering Division at
Lehigh University. Dr. John R. Adams is currently Acting Chairman of
* Currently, Head of Hydraulic Engineering and Fluid Mechanics Division,Texas A &'M University, College Station, Texas.
iv
PRE F ACE (continued)
of the Division. Dr. Herbich was assisted by Mr. David R. Basco, Research
Instructor and Mr. Paul D. Erfle, Research Assistant.
Dr. L. S. Beedle is Acting Head of the Department of Civil
Engineering and Director of Fritz Engineering Laboratory.
TAB LEO F CON TEN T S
ABSTRACT
PREFACE
TABLE OF CONTENTS
LIST OF ILLUSTRATIONS, TABLES AND PHOTOGRAPHS
I. INTRODUCTION
A. Purpose of Study
B. Model Scale
C. General Test Program
II. MODEL TEST FACILITY
A. Original Model Design
B. Modifications
1. Spillway
2. Forebay
III. INSTRUMENTATION
IV. THEORETICAL ANALYSIS
A. Model Laws
B. Channel Roughness
V. RESULTS OF STUDY
A. General
B. Lower Half Spillway
C. Weirs and Forebay
i
iii
v
vii
1
1
7
8
9
9
15
15
18
24
27
28
29
33
33
36
41
v
TAB .L. E 0 F CON TEN T S (continued)
vi
V. TEST RESULTS (continued)
D. Miscellaneous Results
1. Retaining wall profile
2. Velocities
3. Channel Roughness
VI. SUMMARY OF RESULTS AND CONCLUSIONS
VIr. ACKNOWLEDGMENTS
VIII. APPENDICES
Al Lower Half Spillway - Contour Maps
A2 Weir Cross Sections
A3 References
56
56
56
60
64
66
67
68
85
107
LIS T o F ILL U S T RAT ION S
vii
TAB L E S ). AND P HOT a G RAP H S
Number
Frontispiece
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
Title
Labora·tory Model with Original Spillway Configuration
Location Plan
Drainage and Reservoir Areas
Proposed Spillway Design
Proposed Spillway Sections
Original Model Plan
Original Model Sections
Model Construction
Forebay Construction
Modified Spillway Plan
Modified Spillway Section
Original Forebay Plan and Sections
Original Forebay and First Weir Plan
Forebay Modification No. I
Forebay Modification No. II
Forebay Modification No. III - Final
8 11 x 5 11 Venturi Calibration
Model Test Data Table
·Predicted Tailwater Rating Curve
First Jump at 100% Flowrate - Original Design
2
3
5
6
10
11
12
14
16
17
19
20
'21
22
23
25
34
35
38
viii
L I 'SoT OF ILLUSTRATIONS,
TAB L E S, AND P HOT a G RAP H S (continued)
Number Title
20 Vortex at Inside Corner with 100% F10wrate - Original Design 38
21
22
23
24
25
26
27
28
Second Jump at 100% F10wrate - Original Design
Second Jump at 20% Flowrate - Original Design
First Jump at 100% Flowrate - Final Design
Elimination of Vortex - Final Design at 100% Flowrate
First Jump at 20% Flowrate - Final Design
Elimination of Vortex - Final Design at 100% Flowrate
Second Jump at 100% Flowrate - Normal Tailwater - Final
Original versu9 Final Design Comparison Contour - 100%Flowrate
40
40
42
42
43
43
44
45
29 Weir Cross Section Comparison 20% Flowrate 47
30 Weir Cross Section Comparison - 60% F10wrate 48
31 Weir Cross Section Comparison - 100% Flowrate 49
32 Original Forebay With Smooth Flow at 100% Flowrate 50
33 Forebay Modification No. I 52
34 Forebay Modification No. II at 100% Flowrate 53
35 Forebay Modification No. III (final) at 20% Flowrate 54
36 Forebay Modification No. III (final) at 100% Flowrate 55
37 F10wrate versus Forebay Water Surface Elevation Comparisons 57
38 Surface Profile Along Left Concrete Retaining Wall - Final 58Design at 100% Flowrate
39 Prototype Velocities at Critical Locations 59
40 Mesh Orientation 61
41 Effect of Mesh Orientation on First Hydraulic Jump 62
I. I N T ROD U C T ION
A. Purpose of Study
The Commonwealth of Pennsylvania has committed over seventy
million dollars for "Project 70" to increase the number of recreational
facilities for its people. As part of the project, a new state park
will be formed in Bucks County which will be known as Nockamixon State
Park. Originally a two-stage development was planned, as envisioned by
the Delaware River Basin Report; however, because of the small amount of
additional land required for ultimate stage development and also the
limited additional captial costs for the dam required for such develop
ment, the Department of-Forests and Waters decided for ultimate develop
ment of the Tohickon Site. The central feature of the 5000 acre park,
which is to be constructed by 1970, will be a lake seven miles long
created by a 100 foot high and 1200 foot long dam. The dam which is to
be of earth and rock fill construction will be built across the Tohickon
Creek just downstream of its confluence with Haycock Creek. The dam site
is located near the town of Ottsville, 10 miles east of Quakertown, and
about 30 miles north of Philadelphia, Pennsylvania, (Figure 1). The
extent of the drainage area and outline of the reservoir to be impounded
by the dam can be seen in Figure 2. The area of the reservoir will be
1460 acres and the gross storage will be approximately 41,000 acre feet~
or 13.4 billion gallons.
PLAN
OUTLINE OFRESERVOI R
j\HAGERSVILLE
To Chur~
LOCATION
~6§~e~_.~i~"'~§"~5;;;;;iio~~~~~~~~:MILE
-4
The sp~llway design, to handle the Standard Project Flood
expected in the area, was based on hydraulic requirements and construct
ion economy. It was desired to make the spillway as wide as possible
to protect the park beaches and limit the surcharge during large floods.
~The topography of the area necessitated the unusual geometric design.
As seen in Figure 3, a natural draw occurs in the terrain making an
ideal location for the return channel to the river downstream of the
dam. However, in order to take advantage of this natural site the
spillway flow will have to make a ninety degree turn after it passes
over the control weir lQcated on the west side hill. The spillway if
located and constructed as shown in Figure 3 would provide enough good
quality rock to construct the dam to the required elevation. It was
therefore decided to design the spillway with the ninety-degree turn.
Additional sectional views of the spillway design are shown in Figure 4.
Because of insufficient theoretical knowledge of supercritical
flows in open channels, exact computations ~annot be made of the surface
"elevations and velocities for flow around a sharp ninety-degree turn.
The location of areas of flow separation and vortices accompanying such
flows is also impossible to determine. The General State 'Authority
therefore requested that a hydraulic model be made to determine the
exact performance characteristics of the ninety-degree spillway, as
designed by the Consulting Engineers.
In particular the model study was desired in order to:
1. Check the overall hydraulic flow patterns in the spill
way resulting from the unusual design.
Spillway
- ----- .....---~- .....
Spillway
Maximum Flood Surchoroe £1. 40lUS
350'
SECTION A-A
PLANeo
100 I 0 100 2qo,......;;;; :BI •
SECTION B-B
Flr,t OQI.
400 ----..~r_t_=~--,----------=.:..W.:;.:.:.ir---=:.:;EI.:......·.:::..::39::..:::5_J_-----__r"--------_,__-------___r_---,400
380--~""""---+--------+------__---+---------+------------t--1 380
Exi,t
360-----.~~~===+================:t=============:::j-__4--------_+_----~--___t-~360Top of Rock olQno f Spill.
£1. '318
300 --+---------+------
Project No. G.S.A. 194-12Dam
Nockamixon State ParkBucks Coun ty t Pennsylvania
PROPOSED SPILLWAY DESIGN
280 -~0--------..L----------"--9-J0-O--------I~OOO~-------~110:-=0---'280
380t----t----------+---:....:.......- ~---
3601---+--------~-------____l~-_____"360
340I----+---------+----------lf.----340
320r----+---------+------,.-------1--~'320
300L-.-.-~O--------~IOO~--------J2001..-----J-i
Drawing Courtesy ofPickering t Corts and Summerson t Inc.
Langhorne 1 Pennsy 1vaniaLehigh University, Fritz Eng in. Lab.
Fig. No.3SCALE: ,If. 80'
-I ISECTION H-H
501-0.M~ I I
3401- ,.·w·, 1 ,,-.,.,,-., ~~
Strip Overburden to Compet.nt Rock
~30~ \I.
~20L IJSECTION L-L
370~i---------:..------------~
SECTION Q-Q
.370i ~
360 ~ ~ -...... \ 1 1f._----I\U-"..:L,!;~""Yz._ _
3501---------
3401 8-1 1-1-----
330 ~I-------
320L. I~
SECTION K-K
370..-.c~--
3601- ~
350
SECTION N-N
101-0.
RocII:
SECTION S-S
Project No. G.S.A. 194-12
Dam
NockamlKon Stat. ParkPROPOSED SPILLWAY SECllONS
Drawing Court•., ofJustin £ Courtn"
Phtladllphla. PennsylvaniaLahiQh Unlv,n'ly. Fritz EngIn. Lab..
FlO. No. 4 (J'\
-7
2. ,P~ovide the necessary design information for concrete
linings, wall h~ights, and the proposed protective dike.
3. Insure the overall safety of the dam under the worst pro
jected flood conditions.
B. Model Scale
Since the forebay entrance area ahead of the first agee weir
affects flow in the spillway, it must be modeled carefully. Enough of
the entrance are~ must be modeled'so that the model flow patterns
simulate as closely as possible those expected to occur in the prototype.
Modeling the tailwater area is not as critical. As long as
the correct tailwater elevation is maintained the model can deviate some
what from geometric similarity in this case.
Exact geometric similarity is important throughout the entire
spillway flow passages. In this regard the slopes of all walls, all
warped areas and all weir curvatures must be carefully scaled.
Laboratory space was the governing factor in determining the
smallest possible model scale. After a careful analysis of all possible
laboratory locations and model scales, a model of 60 to 1 waS chosen.
This scale is well within the 100 to 1 range -when surface tension forces
begin to influence the results.
Most important and unfortunately most difficult is the art of
modeling the exact surface roughness so that the frictional resistances
-8
in the model will.be dynamically similar to those in the prototype.
Since the prototype surface roughness after rock blasting is extremely
non-uniform and indeterminate, exact modeling is impossible. Details
of the model roughness calculations, methods used and tests made and
planned are given in the Theoretical Analysis Section of this report.
C. General Test Program
The original spillway design was tested with both a smooth and
artificially rough channel surface and after the latter test it became
apparent that a modification study was also necessary. The spillway
modifications were made in two steps and the second step became the
final design configuration.
The forebay was also redesigned and after a series of four
arrangements, modification No. III became the final configuration.
Some minor tests with the artificial roughness were also per-
formed.
The plan and elevation views of the model as originally con
structed in the Hydraulics Division Laboratory are shown in Figures 5
and 6. (See Frontispiece also).
II. MOD E L
A. Original Model Design
T EST F A elL I T Y
-9
The head box was constructed of steel plate, and a heavy
expanded metal lath was used to support the rocks in the rock baffle.
Wood was used to construct the remainder of the model. Floors and walls
were cut from marine plywood sheets to eliminate warping. Cross braced
Kiln-dryed two by fours and two by sixes were used for all beams and for
the leg columns to insure against misalignment. A stiff cement grout
was used to mold the forebay ground contours between templates cut from
masonite sheets and the corner of the dam was modeled from 1/16 inch
galvanized sheet steel.
Since change is the rule rather than the exception in hydraulic
models, the model was designed for ease in adjustment and modification.
It was built in sections which were either hinged or bolted together to
allow for fast leveling to exact floor elevations and to facilitate any
necessary modifications in design. (See Figure 7) The 4 to 1 sloping
section was hinged at the first agee to readily make slope changes and
all Itwo by four legs were fitted with leveling screws so that floor
Flow FromLaboratory Sump
3. Surface roughness not shown
4. Upstream topography Constructed of
sand - cement grout
Notes:
L Model downstream of First Ogee
constructed of 3t4" marine plywood
2. Wall slopes I horizontal to 10 vertical
200' Prototype100'o
o II 2011 2 1 31 40"I !! I I'
Scale
ORIGINAL MODEL PLAN
Project 1050 - 3,26
Nockamixon Spillway Model
Fritz Engineering La boratory
Hydraulics Division, Civil Engineering Dept.
Lehi gh Un iva rsity
Fig. No.5
Return toSump
TailwaterAdjustment
A"IIIIIIIIII
"II
Tailwater Hook Gage
SIlX all Calibrated
Manifold
Dam Axis
lUx 2" Wall Supports
Second
Stilling
Basin
Ogee
Plexiglass Wall
First Stilling Basin
Warped WallSection
t-o-lo
Flow
Second Ogee
3/411 Plywood Flooring
.. I I I ";» \~); ,-
IlI x 6 11 Wood Framing
211 x 4 11Wood Legs
I / Plywood Wall
Joint BoltedTogether
Leg Adjustment Screw
Scole
ORIGINAL MODEL SECTIONS
Project 1050-326
Nockamixon Spillway Model
Fritz Engineering Laboratory
Hydraulics Division, Civil Engineering Dept.
Lehigh University
Fig. No.6
1001o
o 20" 4011
i ! Model2001 Prototype
No,te:
Broken Wall Shown Above on RightHand Side Looking Downstream
~::t......,,- 3/8 " Bolt
'Wood Leg
1"'""_-,1-.='"'1t-=![=J
F'07 ' J.rj ,Bearing Plate
t-'to--l
(a) Table for first stilling basin being moved into position.
(b) Second table in place with some walls attached.
Fig. No. 7 Model Construction
-12 '
-13
elevations could.be set with a Dumpy level and rod. Elevations could
thus be set to + 0.15 feet on the prototype scale.
The laboratory's main pumping system was used to provide water
to the model. Water was pumped from the laboratory sump and returned
via the second floor drain for recycling. The flow was measured with a
calibrated venturi meter and controlled by a gate valve upstream from
the head box. A six inch diameter distribution manifold with jets fac
ing upstream resulted in a uniform flow distribution into the head box.
The six inch wide rock baffle with 1/2 to 3/4 inch crushed and washed
stone insured uniform flow into the model.
Both the first and second agee weirs were precisely cut from
hardwood by the Bethlehem Model Shop, Bethlehem, Pennsylvania. Reverse
templates were used to insure the exactness of the "weir profiles over
their entire length.
Figure 8 shows some details of th~ method of forebay con
struction. A false floor was constructed in the head box up to the rock
"baffle. On it rand the floor extending from the steel head box, templates
cut from~"1/4 inch masonite sheet were attached to aid in contouring the
ground surface. The template profiles were cut to match the existing
topography in the area and a light weight aggregate was poured over the
entire forebay area to be contoured to within an inch of the template
surface to lighten the load on the wooden flooring. Finally, a thick
sand-cement grout was hand placed and contoured to form an exact model
of the topography in the forebay area. Surface elevations were checked
to within + 0.5 feet qn the prototype scale.
(a) View before pouring grout between templates
(b) After modeling surface contours withgrout - corner of dam in place.
Fig. No.8 Forebay Construction
-14
-15
Wall sections at the inside corner were made from 3/4 inch
plexiglass so that visual observations of the turbulence and flow pat
terns in this critical area could be made.
The tailgate.was hinged to the model and held in place by two
3/8 inch diameter, 16 threads per inch, bo1t~ fitted with hand cranks.
This arrangement permitted fast and accurate adjustment of the tail
water to values above and below the required levels.
An expanded metal lath was selected to simulate the floor and
wall roughness for reasons of economy and ease of construction.
B. Modifications
1. Spillway
The modifications to the original spillway design were made
in two steps. Step one, called Part A, involv.ed moving the left side
concrete retaining wall 50 feet (in the direction of the stream's
centerline) thereby reducing the second weir length to 250 feet. The
inside and outside radii were also added at this time. The location
and design of the second weir agee remained unchanged. All floor
elevations did not change from original design. The modified spillway
(Part A modifications as noted) is shown in Figure 9.
Part B resulted in the final design. In this second part of
the modification program the first stilling basin floor elevation was
rai~ed two feet to Elevation 320 feet, and the second ogee weir was
moved downstream ~nd completely changed in design. The modified spill
way is sqown in Figures 9 and 10 with the original outline sU,perimposed.
See Detailed
Drawing Fig. 15
I~ First Ogee.
350 1
Flow
Final Weir Location
Final Wall Location1 I .[-2nd. Ogee AXIS ~Iev. 307.5Z! I
161 1 Original Wall ------.---,Ii ~----- I
Elev. 327fDO/.'"«!\
\\L -- ---- "I 'I ' _
Note:
I. Part A of modifications included only 30' and 150' radii s-hown
and decreased width of second ogee as shown. Elevation view r€mained
as originally shown.
2. Final design of spillway shown with final forebay design.
Project 1050 - 326
Nockamixon Spillway Model
MODIFIED SPILLWAY PLAN
Fritz Engineering Laboratory
Hydraulics Division, Civil Engineering Dept.
Lehigh University
Fig. No.9
.......-"Q'\
\ Top of Dam Elev. 412
7W. •• .'... •• ==".....~ Elev. 395
First Ogee Axis STA 255
Second Ogee
Floor Elev. 320~
430
400
350
300
I I I I I J I I I I
o 100 200 300 400 500 600 700 800 900
ELEVATION VIEW FIRST aGEE TO FIRST STILLING BASIN
Elev.3207
\30' Radius
\ \ Top of Wall Elev. 342
Sta.455 ct 2nd. Ogee
-Elev.326at Crest rElaV.332
£ 10 to 1.2 Slope
~Elev. 307STA 547
400
350
300
Elev.302 at
~ I Lowest Point1 I 1 I I I I I
200 300 400 500 600 700 800 900 1000 1100
ELEVA TION VIEW FIRST STILLING BASIN TO TAILRACE
Note:
See Justinand Courtne y dwg. no. 647- A for detai1s of
second ogee shape.Scale
All 20"9 I ! • Model
o 50' 1001 Prototype
Project 1050 -:3 26
Nockamixon Spillway Mode I
MODIFIED SPILLWAY SECTION
Fritz Engineering Laboratory
Hydraulics Division, Civil Engineering Dept.
Lehigh University
Fig. No. 10
t-l'-J
-18
Note also that the floor elevation profile was also completely changed
downstream of the second weir for the modified design.
2. Forebay
Figures 11 and 12 give complete details of the original fore
bay area design. Three modifications of the original design were made
and studied. After the original tests, Forebay Modification No. I shown
in Figure 13 was suggested by the Corisu1ting Engineers (Justin and
Courtney) and appropriate model changes made to test this design. Of
primary concern was the poor hydraulic entrance conditions that ~esu1ted
in inefficient flow on the left side of the first weir. The large fill
area and warped slope seen in Figure 13 was made to streamline the flow
as it approached the first weir. Modification No. II, shown in
Figure 14, was made by Lehigh University in search of further improve
ment. However, this design proved impractical due to the length of the
rock fill warped section. Figure 15 gives details of Modification
No. III which was incorporated in the final design.
Elev. 400
~\
I Elev.3902 ....l11 W
Section E-E
2Elev. 39Q I~"~
Section A-A
Section B-B
Section C-CG
=-1
40'-011
r=G
overburd7
(FlOW
Spillway Axis7
FORBAY PLAN
Radius =350'
Assumed
ROCk~
Elev.390
75 1-0"
FFIII~ I ' ~~( iti ........ '27°-151
420
"420
Project 1050-326Nockamixon Spillway Model
501o
a IOU 20" Model
i ! PrototypelOa'400
Elev. 390...,IE
Section G-G
IIf:'
400
Section D-D ORIGINAL FORBAY PLAN AND SECTIONS
Fritz Engineering Laboratory
Hydraulics Division 1 Civil Engineering Dept.
Lehigh University
Fig. No. II
......\.0
...--- l.-
Q)'
>
oa~~-----
Project 1050-326NOCKAMIXON SPILLWAY MODEL
Original Forebay andWeir Pion
Fritz Engineering LaboratoryHydraulics DivisionLa high University
Fig. No. 12
-o_I
orei
31-~
c0, II
-cQ)
c..~
c~
c c c::> 0 ..::> __ c~ 1: 0CD Q) -~.. >'--... 0
~oJ:
51-a"
~!
350'-0"
No
Rip. Rap. Fill
WarpSection
75 1
First Ogee -A-xiS--~
~ Contour Elev.380
.., ( r Side Slope 1.5: I
Axis
~FIOW ~Concrete WallProject 1050 -326
NOCKAMIXON SPILLWAY MODELForebey Modification - I
Fritz Engineering LaboratoryHydraulics DivisionLehigh University
Fig. No. 13
N~
First Ogee Axis
WarpedSection
13811 II Elev. 412
1581
Project 1050-326NOCKAMIXON SPILLWAY MODEL
Forebay Modification· - IIFritz Engineering Laboratory
Hydraulics DivisionLehigh University
Fig. No. 14
Ntv
R= 125 1
Sta. 1+ 69 Top
of Wall Elev.401
412
~r- 412 :11:' 412410 1\\1!!I"i!\"!t\410 ~
,Rock---- L~ Original Ground
Rock~0.2__ 400
390 390II;==. III '!!!O l/I 1f11f!:.\'1B..\f!Il,
2+47 2+40
412 412_~<2...___~ 410------
1.5 Ground / Original Ground
400 ~I~- 400-I ~o'ck ----II Rock
;~~\././II 390lIi/'!!.'=/
2+10 1+80
Rock Fill
I: 1.5 Slope
Curvature to Agree
With 3501 Radius of
Modification J[
Channel
Approach
Elevation 390
3 1Wide Beam
1+75
1+55
1+85
1+65
'1+95Slope
i l<2- - -- --~,
, I
Scale
o 101 201 301
Project 1050 - 326Nockamixon Spill way Model
FOREBAY MODIFICATION
NO• .m:. - FINAL
Fritz Engineering Laboratory
Hydraulics Division
Lehigh University
Fig. No.15
__Original Ground~02__
390We/-\?:...\
1+66
Scale
a 10' 201
Prototype
0 2" 4" Model
Prototype
Model4" 611o 2 11
2+55
2+15
2+25
2+35
2+05
2+45
NW
-24
III. INS T RUM E N TAT ION
A minimum amount of instrumentation was needed to obtain all
the experimental data. Most important was the determination of f1ow
rate so that the correct floods could be simulated in the model. In
this regard the eight inch by five inch venturi meter in the supply
line was recalibrated prior to the test program. The results of the
calibration using the volumetric method are shown in Figure 16. The
calibration was checked during the testing program and no devitation
noted. Extreme care was used to bleed the manometer lines of air
before each test.
Two hook gages in pot-type stilling wells were used to
determine and set the head water and tailwater surface elevations.
(See Figure 5). The zero reading was set on each hook gage using a
Dumpy level and rod.
Water depth measurements were made with an ordinary point .
gage. In some cases high and low water depth readings were taken and
an average value calculated. A coordinate system had to be established
to locate each depth measurement for later plotting purposes. The
prototype stationing system used on Figure 3 was used since the results
could be easily referenced back to the prototype for evaluation. The
spillway profile stations along Section C-C of Figure 3 were designated
8 10 12 14 16 18 20 22 24 26 28 30 32
45,000' DESIGN
FLOW EQUALS 100%
Rating EquationQ =1.16 HO.495
Q-cfsH- Manometer Differentialin Feet of Water
1.6,737
11,158
5,579
o
39,053 ~o:E
33,474:::0):>~
2 7,8950 ~
o22,316 ~
(J)
61,369
55,790
50,211
""0::0'o-Io-I-<44,632 -0fT1
66,918
.72,527
20%
40%
80%
60%
a"xs" VENTURI CALIBRATIONFOR-
NOCKAMIXON MODEL SPILLWAY
SCALE RATIO 60:1
CALIBRATED BY VOLUMETRIC
METHOD ON 6-11-66 BYD.R. BASC-O AND P.O. ERFLE
MANOMETER DEFLECTION (Inches Gauge Fluid)
64o 2
2.4
2.0
2.2
2.6
Cf)
1.8u.:u·
w 1.6l-e:(0:: .1.4~0
1.2..JLL
~ 1.0w00~ 0.8
0.6
0.4
0.2
Fig. No. 16
NLn
-26
the "Red Scale ll• Along Section D-D the term JlBlack Scale ll was used. The
point gage bar was also stationed to prototype scale and called the
IfBlue Scale". These designations were all used on the test result plots
and are referred to in the section on test results.
Velocity. measurements were made with a Leupold & Stevens
midget current meter. The calibration curve of this meter was checked
using the laboratory open-channel flume.
IV. THE 0 RET I CAL
A. Model Laws
A N A L Y SIS
-27
The model was tested according to the general practice for
open channel, free surface flows. Both the Reynolds Number and Froude
Number appear in a non-dimensionalized Navier-Stokes equation, indi-
eating that both viscous and gravity forces govern the flow. Standard
practice has been to design the model according to the predominant
Froude Law, while qualitatively noting the viscous force effects on the
results. Experience has shown that for models built for scales less
than 100 to 1 the surface tension effects at the boundary are negligible.
Using the Froude Law therefore, the following relationship
were used in all calculations:
LLength ratio, L --E 60
r Lm
VVelocity ratio, Vt
--EV
m
( 1)
(2)
Discharge ratio,Q
Q =--Er Q
m
7.745
27,850
(3)
-28
where: L len.gth
V velocity
Q volumetric flowrate
g gravitational constant, g = 1.0 on earthr
p subscript referring to prototype
r = subscript referring to ratio
m subscript referring to model
Pressure, force, power, etc. relationships were not involved.
Using conventional methods the water surface profiles for the
spillway can be predicted only in the ,straight sections of the channel.
Chow(4) gives methods for predicting surface elevations and losses
around bends in smooth curved channels. However, there is no accurate
information to the writer's knowledge about open> channel flow around
sharp, ninety-degree turns.
B. Channel Roughness
According to the best estimates of the Design Engineers,
(Pickering, Carts and Summerson, Inc.) the rock floor of the spillway
will vary between six and nine inches above ot below the design grade
line. The rock walls will also project about four inches above and below
the design slope. Scaling geometrically this prototype roughness becomes
in terms of the model scale:
1. floor, + (0.00833 - 0.0125) feet,
2. walls, + (0.0055) feet.
-29
For complete similitude the roughness should be modeled both
geometrically a~d dynamically. From the tables and photographs in
Chow(4) , Mannings I "n", is estimated to be about 0 .035. Chow also
gives an empirical equation for estimating lin" if the absolute rough-
ness, k, is known. Thus from the expression:
n = (4)
where: n = Manning roughness coefficient
Ro (k) = a constant of about 0.0342 (Strickler's Constant)
k = absolute surface roughness
If a value of nine inches is used for k in equation (4), IInlf is calcu-
lated to be 0.033 for the prototype. This value is the range of those
selected from tables and photographs.
From Manning's equation based on the Froude Law the relation-
ship between model and prototype "nil is
Using np
L1/6 1/6
n ( --!!!) (1-.)r L L
p r
11/6
n (60) 0.506 .r
0.033 (lin" for prototype)
(Sa) .
(Sb)
nill
0.0165 ("nll for model) (6)
-30
Now using equation (4) for the model with a model "n" of 0.0165, Iem
for the model can be obtained.
nm
C/J (R/k)(7a)
k 0.0127 feet for model (7b)
This value compares very favorably with the upper limit obtained by
geometric scaling of the floor roughness. Note however that the
assumption of 0 (R/k) being equal to Strickler's Constant for the model
must be made. As mentioned previously, an expanded metal lath was used
to model the roughness. The metal lath was stapled to the wood channel
and only the positive side of the plus or minus elevation was modeled.
The exact size and shape of the two types of lath used ~s given below.
Lath Floor Walls
Style Designation 1/2" No. 16 1/2" No. 18
Strand Width 0.078 in. 0.081 in.
Approximate Size of Mesh-Width 0.462 in. 0.462 in.
Center to Center of Bridges - Length 1.2 in. 1.2 in.
Strand Thick.ness 0.060 in. 0.048 in.
(Daub led) 0.120 in. 0.096 in.
Approximate Size of Opening 0.375 x 0.906 in. 0.392 x 0.920 in.
Percent Open Area 64 to 68% 70 to 75%
The doubled strand thickness was a good indication of the absolute ~rough-
ness. In this case the floor roughness was 0.010 feet which corresponded
to a prototype value of "about 7-1/2 inches and within the expected rough-
limits. The walls were about 5-1/2 inches rough on the prototype scale.
-31
In any. hydraulic model there are a number of limiting factors
that prohibit e~act geometric and dynamic similitude. These must be
kept in mind at all times. Surface tension effects although minimal,
are still present especially during low depth flows in the forebay area.
As a consequence prototype forebay water surface elevations will be
slightly lower than predicted. Also since the complete randomness of the
prototype roughness can never be modeled, the simulated roughness material
used is at best a good engineering approximation to the prototype. And
lastly, it must always be kept in mind that viscous forces are ever
present and also influencing the flow patterns to a limited extent.
v. T EST RES U L T S
-32
A. General
In order to intelligently judge the results of the model study,
the criteria for good hydraulic spillway design should be clearly under
stood. Therefore before beginning a detailed analysis of the test
results, the salient points of good hydraulic spillway design will be
presented.
The purpose of any spillway is simply to safely convey flood
flows around, through, or over the dam. The potential energy of water
behind the dam must be safely and efficiently controlled as it changes
to kinetic energy in its journey to the river downstream. The assurance
of complete safety for the dam under the waist possible flood conditions
is the ultimate goal for the design of any flood spillway.
In order for flow control weirs to perform as designed they
must have uniform depths and velocities over their entire length. This
means ,that great care must be taken in providing smooth entrance condi
tions. Inefficient weirs will result in higher reservoir surface
levels than expected, resulting in less freeboard on the dam and reduced
dam safety factors.
Hydraulic jumps, if. used as energy dissipators must be stable
and occur at the desired location. They must also be of a strong nature
if effective energy loss is to be realized. Unstable jumps cause
-33
undesirable su~ges and resulting shocks elsewhere in the spillway. The
high degree of turbulence and bottom eddies created must occur where
damage to the spillway floor surface is tolerable. Flow separated areas
and their accompanying vortices are undesirable in that they reduce
the efficiency or conveyance of the flow passages, resulting in higher
velocities in these areas which could result in erosion.
In general, all velocities in tailwater regions and other
critical areas must be low enough to prevent surface erosion. One
critical area would be the flow in the forebay area past the earth dam
itself. Erosion of the dam is most undesirable and dangerous.
Lastly, surface waves created downstream of hydraulic jumps
should be small and steady so that resulting wave impact forces and
possible erosion are insignificant.
The original spillway design as shown in Figures 3 and 4'was
studied at five different flowrates. The spillway design flood of
45,000 cfs was the maximum flowrate tested and thereby designated the"
100 percent flow. The other flowrates were called the 80, 60, 40,
and 20 percent flows. These prototype and model flowrates are shown
in Figure 17. The wide range of tests prevented any unusual quirks in
spillway performance from going unnoticed. The predicted tailwater curve
used in the tests is shown in Figure 18 and the first agee rating curve
is part of Figure 3. Elevations from these curves for the five flow
rates studi·ed for model and prototype are also shown on Figure 17.
Project 1050-326Nackomixon Spillway Test Data
Model Scole 60 1 I
Percent of Design Flood
20% 40~/o 60% 80% 100.%
Proto'typeFlowrat 9,000 18,00b 27.000 36,OOQ 45,000(cfs)
ModelFlowrate 0.326 0.646 0.968 1.290 1.613( cfs)
ManometerSetting
0.80" 2.05" 4.20" , 7.45 11 11.90"Inches ofGage Fluid
HeadWater
398.90 400.90 402.70 404.25 405.60Q) I Elev.a.
( feet)~..0
Tail..-0....
Watera..318.30 319.45 321.14 323.23 324.90
Elev.(feet)
HeadWater
1.948 1,982 2.012 2.038 2.060Rdg.-Q) (feet)"C
0Tail:EWater 1.980 1,999 2.028 2.062 2.094Rdg.( feet)
Note: Hook Gage Zero is 1.800 Feet
Fig. No. 17
34
326
35
TAlLWATER . RATING CURVE
NOCKAMIXON STATE PARKG.'S.A. 194-12
drawn by
Justin a CourtneyConsulting Engrs.
Phila., Penna.
I
321
320
319
318 '"--- L....- .L....- .&.-- .&.-- .l.-- ..L..- _
o 10,000 20,000 30,000 40,000 50,000 60,000
DISCHARGE· CFS
-36
Results. of the model test for the original design are pre
sented in a number of ways. Efficiency of the weirs and a resulting
indication of upstream entrance conditions is noted by plotting the
water surface profiles at the crest. Location and stability of jumps
and overall uniformity of depths along with vorticity identification has
been recorded by the use of water surface "contourll maps for the entire
lower half of the spillway. Photographs were taken of all critical
areas as a positive means of recording the exact flow patterns. Some
confetti-streak photographs were also made of the forebay entrance
flow patterns.
The results of the model test for the modification program
are presented in the same manner as for the original design with one
major exception. Only the 100, 60, and 20 percent flowrates were tested.
Therefore when comparisons are made these will be the only flowrates
presented. Velocity measurements were only made for the final design
configuration at 100 percent design flowra~e.
B. Lower Half Spillway
In order to record what occurred in this region of the spill
way, the model water depths were converted to prototype scale and
plotted at their location on a plan view of the prototype spillway.
Interpolation was necessary to construct the one foot interval water
surface contours, similar to the method used in making a topographic
map of earth surface contours. These water surface contour maps serve
then to show the location of the hydraulic jumps, depressed areas,
vortices, stagnation areas, and wave buildup areas. In effect, an
-37
indication of the flow-through efficiency can be obtained from the
contour maps. The results of all model depth measurements made are
conveniently recorded on the contour maps. The water surface contour
maps for all data taken for the entire model study are assembled in the
Appendices under A-I. A co~plete list of these contour maps appears
at the front of Appendix A-I.
The model spillway as originally tested had no simulated
channel roughness. Th{s test acted as a lower bound in viewing the
results of later tests with roughness added. Since a minimal amount
of resulting friction and energy loss occurred with the smooth channel,
this test bounded the effect of artificially adding surface roughness.
A more detailed discussion of some additional and planned tests with
the artificial roughness is given in a later section of Test Results.
Since these smooth and rough test results are only of academic interest,
the discussion of model performance will be confined to all tests with
the simulated rough channel surfaces.
In general no unexpected phenomena occurred at any of the
lower flowrates tested. In all cases undesirable hydraulic charac
teristics which occurred at 100 percent design flowrate decreased in
magnitude as the flowrate decreased.
The following undesirable flow characteristics were noted for
the original spillway design (see Figures Al-6 to AI-IO). The first
.hydraulic jump although mild'ly strong occurred on the stilling basin
floor and Qbliquely across the" basin as shown in Figure 19 for 100
percent flow. A large vortex appeared at the inside corner resulting
-38
Fig. No. 19 First jump at 100% flowrate - original design
Fig. No. 20 Vortex at inside corner with 100% flowrate - original design
-39
in a depressed region. (Figure 20). This vortex 'also caused the flow
over the second ogee weir to fluctuate approximately four feet in depth
at the worst condition. At the outside corner a pile-up took place
resulting in a net elevation difference of twelve feet over the first
stilling basin. The second hydraulic jump was very weak (undulating),
slightly oblique, and even partially submerged as shown in Figure 21
for 100 percent flowrate. The conditions at the second jump for 20
percent flowrate are shown in Figure 22. The surface contour maps in
the Appendix for the original design also reveal the unevenness down
stream of the second jump for all flowrates.
Undesirable hydraulic conditions were improved considerably
in the first stilling 'basin after modification Part A was made on the
model. These results can be seen in Figures AI-II to AI-13 in the
Appendix. However, there was not a great deal of difference in
hydraulic performance between Part A and Part B of the modification
program to warrant detailed discussion. Conditions remained poor down
stream of the second weir after the first modification.
After the s'econd modification was made (as shown in Figures
9 and 10) all undesirable flow characteristics that were associated with
the original design were either considerably improved or completely
eliminated. As shown in Figures Al-14 to Al-16 of the Appendix the
first hydraulic jump started on the slope and ended before the flow
passed around the corner as a result of moving the north side wall fifty
feet. This modification along with the thirty foot- inside radius,
completely eliminated the vortex from forming at this location for all
flowrates. The location and vigor of the first jump and elimination
-40
Fig. No. 21 Second jump at 100% flowrate original design
Fig. No. 22 Second jump at 20% flowrate - original design
-41
of the large vo~tex can be seen in Figures 23 and 24 for the 100 per
cen't flowrate. The same phenomena at 20 percent flow are shown in
Figures 25 and 26. There was practically no bulking at the outside
corner after the large radius was installed and the depth only varied
by seven feet (prototype) over the entire length of stilling basin.
The second jump although completely submerged was much stronger and
very uniform across the channel. Figure 27 shows the second jump with
normal tailwater and 100 percent flowrate. By lowering the tailwater
it was found that the second ogee jump was completely swept out at a
tailwater elevation of 321.1 feet. The water surface contour maps
also show the extremely smooth tailwater surface area with the final
design. To facilitate the comparisons between the original and final
designs, Figure 28 was prepared for 100 percent flowrate. The outline
and surface contours of the original design are shown by the dotted line.
c. Weirs and Forebay
By measuring the model water depths at closely spaced incre
ments along the weir crest centerline, a section view of the water
surface profile for each weir was obtained. These sectional views for
all flowrates and conditions studied are compiled in Appendix A2. If
uniform velocity distribution is assumed over the crest length, an ideal
weir will then have a uniform depth of flow over its entire length.
The criteria for good forebay ~nd spillway design was therefore to
determine how close the weir cross sections came to being uniform over
the entire length of crest.
Fig. No. 23 First jump at 100% flowrate - final design
Fig. No. 24 Elimination of vortex - final design at 100% flowrate
-42
Fig. No. 25 First jump at 20% flowrate ~ final design
Fig. No. 26 Elimination of vortex - final design at 20% flowrate
-43
(a) Facing south wall
(b) Facing north wall
Fig. No. 27 Second jump at 100% flowrate normal tailwater - final design
-44
Project 1050-326
NOCKAMIXON SPILLWAY MODEL
Original vs. Final Design
Percent Design Flow: 100 0/0
20I
(\
\\
\\\ ,""
--"'"\"---1\ II II
18
III
}
I
22
"\.\
\\\\\
\l\J
//
II
IJ
\24}
('\
\\\\\\\\\IJI
/ ......,I \\ \1 \
JI\\\
700
Fritz Engineering Laboratory
Hydraulics Division, Civil Engineering Dept
Lehigh University; Bethlehem, Penna.
Fig. No. 2.8
600500
Final Design - Solid Lines
Original Design- Dashed Lines.
400300
18
200lOao
r Start of Jump
,--Hydraulic Jum,E.._,-,---- ....
,...,......-,..,..",....""..,..,..,....
0 600 ..J->-'I
0- 20 -<...................-.J"...JZ W ....... ,,
"o 0 ," ~~~ 650 \
"-\
....- I 16w ..... 18 "C/) Z .......20 \0 \
(!) ..... 1Z w 700 "- \ Io ...J " \ 20 I"...J <t
" \ "- \<! (J
" \C/)\ \
C/) ::::r::: 750 " 1 \Z 0
,..... 20... \
o <t ...........22 18- ...J
\\ Il- aJ<t_ Il- 800 Ien I
22\ I 20\ ........ ~.. I
850'L ___""'-_
STATIONS ALONG SECTION D-D
(RED SCALE ON MODEL)I I I I J I 1
700 800 900 1000
+'"l.J1
-46
In order to easily compare the results for all forebay and
spillway modifications, Figures 29, 30, 31 were prepared for 20, 60,
and 100 percent design flowrates, respectively. No large differences
were evident at the 20 percent flowrate for either the first or second
agee. However, improvement in the flow patterns over the second weir
is quite apparent at the other two flowrates. At 100 percent flowrate
the depth varied from eleven to four feet over the crest or a difference
of seven feet for the original design. The final design varies only
four feet from eleven to seven on the crest. (Note that the Ilsuper
elevation" effect for flow around an open channel corner is still
apparent in the final design). This same improvement can also be seen
for 60 percent flow in Figure 30.
Comparisons of forebay modifications for the flow over the
first ogee can also be readily made in these figures. Once again the
20 percent flowrate shows little differences. The large improvements
made on the east side (facing upstream) by·;the forebay modifications
are quite evident in Figure 31 for 100 percent flow. It can also be
seen that although impractical from a constructional point of view,
Modification No. II (dotted line) gave the best profile on this side.
In Modification No. III there was slightly more of a dip in this area.
However, because of construction ease, Modification No. III became the
final design configuration. As shown in the time-streak photographs
taken (Figure 32) the water approached the spillway on the east side
along a line parallel with the dam axis. This resulted in a buildup in
the center of the first weir with a depressed area on the east side
(facing downstream). The small berm on this left side in the original
405~_~_~__~~~~~ ~~~~~~=~~=~~=_=~405I
.-L------ -_. ~-- .
I
1395395 E.~==~--=============:F:ir=s~t+1~o:g:e:e==--=--==----------'-------~O _~ ~;~~~~j400
II I
::: ~_:~~~:~+.~;~~~~;=~~=~~;~~~g~~-:~~:: :::~_ ~ ~~.~_~~ ~ .~_.__ ~_~~r.~ ~~~ _.~_~~.___ ------;---~~_&_~ __._.~.~_ - _
-----.-..------L-.____ ------ -- ~ .. -~----_. - - - - --~----_.~~~--- ----
323 1 I 1323Second I Ogee
Both Views Looking Upstream
-- Unmodified Original Design- - - Foreboy Mod. I Original Design
Forebay Mod.]I Mod. Part A-.- Forebay Mod. 1JI Final
Project 1050- 326NOCKAMIXON SPILLWAY MODELWeir Cross Section Comparisons
Design Flow - 20 %
Fritz Engineering LaboratoryHydraulics Division, Civil Engineering Dept.
Lehigh University; Bethlehem 1 Penna.Fig. No. 29
.po
........
405 ~----~----.---.-----.--- ---~---.-.-.-- .._---~_._-~-------~----~,~-- ~ ---.-------~- - -~-_. -------------~~--------------I-~--
_.- _._--- .._---_._-~---_ ..-:----._--_._._---_.----- ----------,--+-_._---_._-~----~--------,--------_._--_.-----_.._---_..._-.---
405
400~~- ~~~~~~---~=~.:~.~:~~~~.~.~~.~:.~.~.~ --~~400___ ~__._ ..._. ----L., _,•.• ~ • _.• . ._ •• . . •__~ . ._. .~_ ---.
395 1 I '395First I Ogee
333---
328
II
~~~-~~~~:~lf
----.- ..L.---
333
328
323' I '323Second I Ogee
Both Views Looking Upstream
--- Unmodified Original Design--- Forebay Mod. I Original Design••••••••• Forebay Mod. 1I Mod. Part A-.- Forebay Mod.lJI Final
Project 1050-326NOCKAMIXON SPILLWAY MODELWeir Cross Section Comparisons
Design Flow - 60 %
Fritz Engineering LaboratoryHydrouiicsDivision, Civil Engineering Dept.
Lehigh University; Bethlehem 1 Penna.Fig. No. _30
+'"co
405 ~--._ ....--.-.-.-----.- .--- -- ------. ----. ~ ..- ~_ ..--, -....-.._- -.--.-.-,.-.---..----~-------~-------- ..--~ ---.---+--.-------~~_._----_.. - .---..~---~---~.-.--.--.-.- _.. ----- --,._-~---_. --.-
--~.
405
400
'--~~:~~;;:'~~':~;-~~~:~~-=-'=--=~~~'I'- ~_==r7:==,:.~·~-:~·tr-=.....~~~~~ ..~._"· ----- ~ 400
395' I 1395First Ogee
II ... > •• >.L--...~.~.~-......I
333
328
--_. --- - - -~~-- - - ----
- --- -.----- t
L - ·1.....• "•••.••.... "'. I........:: "-"'-:~: - .----~..~...-..-"-....j
'- - --- - I
-- -l-~-
---- . - -t----·~·-·······lI - . -I' . ===-_'- --.----··r -__..__._ - ._.. .__
,-
333
328
323' I '323Second I Ogee
Both Views Looking Upstream
Unmodified Original DesignForebay Mod. I Original Design
.... ..... Forebay Mod. 1I Mod. Part A--- Forebay Mod.]I[ Final
Project 1050-326NOCKAMIXON SPILLWAY MODELWeir Cross Section Comparisons
Design Flow - 100 %
Fritz Engineering LaboratoryHydraulics Division t Civi I Engineering Dept.
Lehigh University; Bethlehem t Penna.Fig. No. 31 -
+:-\.0
(a) Depressed region in flow over first weir
(b) Time-streaks show flow entrance pattern resulting in depressed area at left over weir
Fig. No. 32 Original forebay with smooth floor at 100% flowrate
-50
-51
design also caused a small hydraulic jump to form (Figure 32a). The
objects of the forebay modification program were therefore to stream
line the flow patterns and to reduce the dip on the east side of the
weir and to minimize the boundary disturbances along the dam structure.
The results of flow improvement over the first agee weir have already
been discussed.
In Figu~e 33b the patterns along the boundary of the first
modification are evident. Although the hydraulic jump is no longer
present there was considerable IIbac,kup" behind the modification result
ing in a deep drop in surface level around the tip (arrow) of forebay.
By adding more fill material the flS" flow pattern around
Modification No. I was improved and a more streamlined flow around Modi
fication No. II was obtained (Figure 34).
Figures 35 and 36 show surface patterns around the final
design at 20 and 100 percent flowrates respectively. The 20 percent
flowrate (approximately the 200 year flood) showed an extremely smooth
surface profile around the modification. At 100 percent the surface +
was considerably rougher and some drop in surface elevation occurred.
Some of the backup behind the modifications for all' those tested was
felt to be due to the proximity of the inlet rock baffle to the edge
of the modification structure. Thus it is expected that the prototype
will experience a far lesser drop in surface elevation at this point.
Forebay surface elevations were measured for all test~ by the
hook gage with inlet located at approximately the spillway centerline
(a) At 20% flow extremely uniform around modification structure
(b) At 100%, dam addition caused "SII flow pattern resulting inlarge surface dip at tip of modification (arrow).
Fig. No. 33 Forebay Modification No. I
-52
(a) Flow has more uniform approach around modified area
(b) Bulking behind modified area causes somedrop down in surface elevation.
Fig. No. 34 Forebay Modification No. II at 100% flowrate
-53
(a) View of extremely tranquil surface profile at' this 'flowrate.
(b) View upstream of flow around modification
Fig. No. 35 Forebay Modification No. III (final) at 20% flowrate
" ';~"l
-54
(a) View partially downstream - some surface irregularities still present around modification.
(b) View of drop down in surface elevation at modification
Fig. No. 36 Forebay Modification No. III (final) at 100% flowrate
-55
-56
at the 390 floor elevation. (Figure 5). The resulting prototype
elevations were plotted against flowrate in Figure 37. Also shown is
the Consulting Engineers' predicted spillway rating curve. At the
higher flowrates, all tests were in fair agreement with the predicted
curve except for Modification No. I. The hook gage was believed to be
in error in zero reading for this test. At the lower flowrates surface
tension may account for some of the increase in surface elevation from
that predicted.
D. Miscellaneous Results
1. Retaining wall profile
As an aid in design of the left side concrete retaining wall
a water surface level profile was constructed for the final design at
100 percent flowrate. (Figure 38).
2. Velocities
As requested by the Consulting Engineers, model velocities
were measured for the final design configuration at 100 percent ,flow
rate. Only those areas of critical interest were investigated. As
shown in Figure 39 the maximum velocity around the edge of the forebay
modification was found to be about 23 ft/sec (prototype scale). In the
tailwater area a maximum of about 11 ft/sec was measured. These
velocities are felt to be very reasonable and should not result in
erosion in these areas, provided the rock fill is used to protect the
embankment.
57
407 Flowrate vs. Forebay Surface Elevations
.:''-Predicted by Justin ~ Courtney
401
405.60 a 45,000 cfs406
£Design Flow
Forebay Mod. n:" # It~b /
/IJ.~ I "--Foreboy
M f Mod. IIII /
Forebay Mod.:m: !"~/(Final Design) ~h, /
h :'1/. /
h :/h ./.
!J :I
hh'; Origina I Design
h rh /.'
II I.~:
/
1.f:
I ..399
402
405
400
4-03
404
zot<t>W-.JW
WU<tlL.0:::::>en
c::wte:(
~
><tCDlLJc:::oLL
398 '---_--L----""""-----------------.l'--------........----
o 10,000 20,000 30,000 40,000 50,000
SPILLWAY DISCHARGE, cfs
Fig. No. 37
Project 1050- 326
Nockomixon Spillway Model
Water Surface Profile Along Left
Concrete Retaining Wall
Fritz Engineering Laboratory
Hydrau lies Division I Civil Engineering Dept.
Lehigh University.
Fig. No. 38
Spray on Wall7at Corner RadiusAbout 201 High
410
400
390
380
370
360
350
dJ)'.Xi201::
Top of WallElev.342,
Ld=4~feetin Cross Wave at5to. 480 BlackSection C-c
(Black Scale on Model)
1"""---~ First Ogee
I /Elev.412
"wi. 8.405.6 ~W.S.Elev.400.3~ 1/~Elev.395
Elev. 390
400
Section 0-0Red Scale on Model)
600I350
340
330
320
310
300
J700650
550
v
~ Floor Elev. 307.5~
600
500
550
c
~Top of Wall Elev. 332
450
500455
350
Crest Elev.326
200 250 300
350t~ CornerRa~ius ____ Top of Wall Elev. 342
340
330~I1111 Floor Elev. 320
320
310
300
'L300 350 400
rTOP of Wall Elev. 332~
I
600t
650I
700
End of Concrete Wall/Elev.327 Top of Dike
~ Floor Elev. 307.5~
Section 0-0(Red Scale on Model)
I "I I
750 800 850
Note - Waves Formed Along Left
Wall About 5 feet High-1340
-1330
-1320
-1310
I IJ300
900 950 1000
Ln(X)
7.71/sec.~
IO.61/sec.~
Note:L Velocities measured with midget current meter.
2. Velocities measured at particular cross sectionshown were maximum in that area.
Project 1050 - 326
Nockamixon Spillway Model
Prototype Velocities at Critical
Locations
Final Design -100 % Flowra~e
Fritz Engineering Laboratory
Hydraulics Division t Civil Engineering Dept.
Lehigh University
Fig. No. 39
7.71/sec.
~ 2nd. Ogee
14..1/sec.
15.51/sec.::!!:=
Note:
This measurement was
slightly out of range of
the measuring equipment
although felt to be accurate
to within ± 10 %
ForebayModificationNo.:m::(Final~
,
~DamAXiS
I 1ll50'/sec.~
I
~:V.320<: _
Elev.390
/I
II
I
~.31/sec.
~ I sf. Ogee J
PLAN WIEW
In\0
-60
3. Channel' Roughness
As mentioned previously the original model design was tested
first without simulating the roughness to determine the upper bound on
the worst possible spillway performance (least natural energy dissi
pation due to roughness). The size of wire mesh was then determined
land installed in the model. This was mesh orientation No. I and was
installed with the long dimension of the diamond in the direction of
the flow on the sloping section of the spillway (Figure 40). The
location of the hydraulic jump in the first stilling basin has been
shown in Figure AI-lO and is reproduced in Figure 41. To determine
the effects, if any, of the orientation of the diamond pattern in the
mesh, orientation No. II was set-up in the model as shown in Figure 40.
The location of the resulting first hydraulic jump for 100 percent
flowrate has been superimposed on the original orientation in Figure 41.
The jump now occurs straight across the channel and starts on the slop
ing section well ahead of the original jump location. Thus mesh orient
ation No. II resulted in improved channel performance. Undoubtedly
channel hydraulic performance could be improved even further by decrea~
ing the size of the mesh opening (increasing number of roughness
elements). Therefore it may be assumed that mesh orientation No. II
placed an upper bound on channel performance. Since channel roughness
modeling could not exactly duplicate the prototype roughness, anyway,
it was felt that by using roughness orientation No. I for all model
tests, the results obtained would lie somewhere between a smooth chan
nel and extremely rough channel and therefore be somewhat represent
ative of what degree of roughness might be experienced on the prototype.
Flow
~tilling Basin
MESH ORIENTA TION I
Note: Mesh Orientation I- Long MeshDimension Runs Parallel toDirection of Flow
Floor MeshThickness 0.060"
0.375 11 IO~46211
0.906"1.2 II
~ Stilling Basin
MESH ORIENTATION][
Project 1050-326NOCKAMIXON SPILLWAY MODEL
Mesh OrientationFritz Engineering Laboratory
Hydraulics Divisio.n, Civil Engi~eering Dept.Lehigh University; Bethlehem, Penna.
Fig. No. 40
0\t---l
0\N
ctz nd. Ogee
Project 1050-326NOCKAMrXON SPILLWAY MODEL
Effect of Mesh Orientationon First Hydraulic Jump
Original Design -100 % FlowrateFritz Engineering Laboratory
Hydraulics Division, Civil Engineering Dept.Lehigh University; Bethlehem, Penna.
Fig. No. 41
16
1718
18
19
Stable Straight Jump WithMesh Orientation ][
850
800
550
650
750
700
600
-63
In this regard, the area of roughness modeling in relation
to the Manning's IInll will be the topic of a Master's Thesis by one of
the co-authors, Paul D. Erfle.
-64
VI. SUM MAR Y OF RES U L T S
AND CON C L U S ION S
By way of summarizing the model test results, the reader is
again referred to Figures 28 and 31. In general, all those salient
features of good hydraulic spillway design.which were found lacking or
worthy of improvement in the original design were incorporated in the
final design. Both weirs were much improved in efficiency as measured
by uniform depths over their lengths. Both hydraulic jumps were
"straightened Dutil and located in better positions in the spillway.
The energy dissipation of the second jump was much improved over the
original design. The flow separated areas and accompanying vortices
were eliminated in the final design. This provided more efficient flow
passage through the spillway. Surface wavi(l.e.ss, especially in the north
side tailwater region w&s also improved by the final design.
Velocities were found to be sufficiently low in critical areas
to minimize erosion.
In summary, therefore, it was felt that the model study acco~
plished the purpose for which it was intended by:
1. Checking the overall hydraulic flow patterns in the origin
ally, uniquely designed spillway and finding them unsatisfactory, modify
ing the spillway design until good hydraulic performance was achieved.
-65
2. Proyiding the necessary design information to adequately
specify concrete linings, wall heights, protective dikes, etc.
3. Insuring. the ultimate safety of the dam under the worst
flood conditions.
However, besides accomplishing these intended purposes, the
model study also enabled t~e design engineers ~o reduce the cost of the
prototype structure to such an extent that more than the cost of the
model itself will be saved in construction costs.
In conclusion it is felt that the prototype spillway structure
if constructed to the final design configuration and with the design
information provided from the model study will adequately handle the
Standard Project Flood expected in the area. Therefore, also adequately
protect the dam from failure by this flood.
-66
VII. A C K NOW LED G MEN T S
The cooperation and assistance of t;he following people and
their organizations involved in the project are gratefull appreciated.
Mr. C. H. McConnell, Chief Engineer and the Staffof the Pennsylvania Department of Forests andWaters
Mr. A. P. Scheich, Pickering, Corts and Summerson, Inc.,Consulting Engineers, Newtown, Pennsylvania
Mr. J. J. Williams, Justin and Courtney, ConsultingEngineers, Philadelphia, Pennsylvania
Mr. C. Lynn and his Staff of Bethlehem Pattern andModel Shop, Bethlehem, Pennsylvania
Mr. W. Miller and his Staff, Department of Buildingand Grounds, Lehigh University
Appreciation is also extended to Dr. John R. Adams for his
timely hints and suggestions and to Mr. E. Dittbrenner for his efforts
in model construction. Miss Linda Nuss typed the report.
A P PEN DIe I E S
-67
Figure No.
Al-l
AI-2
AI-3
Al-4
Al-5
Al-6
AI-7
AI-8
AI-9
AI-IO
Ai-Ii
Al-l2
Al-13
Al-14
AI-IS
Al-16
A P PEN D I X Al
LOWER HALF SPILLWA":( - CONTOUR MAPS
List of Illustrations
Title
Original Design, Smooth Channel, 20 Percent Flowrate
Original Design, Smooth- Channel, 40 Percent Flowrate
Original Design, Smooth Channel 60 Percent Flowrate
Original Design, Smooth Channel, 80 Percent Flowrate
Original Design, Smooth Channel, 100 Percent Flowrate
Original Design, Rough Channel, 20 Percent Flowrate
Original Design, Rough Channel, 40 Percent Flowrate
Original Design, Rough Channel, 60 Percent Flowrate
Original Design, Rough Channel, 80 Percent Flowrate
Original Design j Rough Channel, 100 Percent Flowrate
Modification Part A, Rough Channel, 20 Percent Flowrate
Modification Part A, Rough Channel, 60 Percent Flowrate
Modification Part A, Rough Channel, 100 Percent Flowrate
Final Design, Rough Channel, 20 Percent Flowrate
Final Design, Rough Channel, 60 Percent Flowrate
Final Design, Rough Channel, 100 Percent Flowrate
-68
Project. 1050-326
NOCKAMIXON SPILLWAY MODEL
PLAN VIEW - WATER SURFACE CONTOURS - PROTOTYPE DEPTHSForebay Modification: Original
Spillway Design; Original- Smooth Channel
Percent Design Flow; 20 0/0
17
17 16
/ /17 16
700
18
18
600
Fritz Engineering Laboratory
Hydraulics Division, Civil Engineering Dept.
Lehigh University; Bethlehem f Penna.
Fig. No. Al-l
500400
<t12 nd. Ogee Spillway
300200
First Stilling Basin
100o
(.)Iu_z-JOW_0~o(.)~lLJenZ
oC)ZW0....1....1«<t(.)
(J)
en~zu0«-....1~CDf--en
STATIONS ALONG SECTION D- D(RED SCALE ON MODEL)
I I 1 I I I I700 800 900 ' 1000
Project 1050-326
NOCKAMIXON SPILLWAY MODEL
PLAN VIEW - WATER SURFACE .CONTOURS- PROTOTYPE DEPTHS
Forebay Modification: Original
Spillway Design: Original- Smooth Channel
Percent Design Flow: 40 °/0
13
13
14
14
14
16 15
16 15
17
17
700
Fritz Engineering Laboratory
Hydraulics Division t Civil Engineering Dept.
Lehigh University; Bethlehem t Penna.
Fig. No. AI-Z
600500
2nd. Ogee Spillway
ct
400 '"300200
12
'-First Stilling Basin
100
g850
UIu_
-1ZlLJ00-0~~W(f)Z
o(!)W2-1:3«« g 750(f)~
2U0«
~ ~ 800«~(f)
STATIONS ALONG SECTION C-C(RED SCALE ON MODEL) I I I I I I I
700 800 900 1000
Project 1050-326
NOCKAMIXON SPILLWAY MODEL
PLAN VIEW - WATER SURFACE CONTOURS - PROTQTYPE DEPTHS
Forebay Modification: Original
Spillway Design: Original- Smooth Channel
Percent Design Flow: 60 %
1516171819
19
Fritz Engineering Laboratory
Hydraulics Division I Civil Engineering Dept.
Lehigh University I Bethlehem 1 Penna.
Fig. No. AI- 3
600500400300200100
Front Oscillates~
~lIcM14~"h ~ \J (),?~I
(15 ~~(~C2J ~~1514~~:
)\~~~:14 W
15
Hydraulic Jump
o
850
<..>Iu_
..JZ W00-0~:EIJ.JU>Z
o(!)zlJJo ...J...J ex:<:( 0
enen ~
z c.> 750o c:!-...JI- CD<:(-I-en 800
STA TIONS ALONG SECTION C-C
(RED SCALE ON MODEL)
I I I I 1 _~I
700 800 800 900 1000
Project 1050-326
NOCKAMIXON SPILLWAY MODEL
PLAN VIEW - WATER SURFACE CONTOURS - PROTOTYPE DEPTI:"IS
Forebay Modification: Original
Spillway Design: Original-Smooth Channel
Percent Design Flow: 800/0
1819
2021
2223
600
Fritz Engineering Laboratory
Hydraulics Division J Civil Engineering Dept
Lehigh University j Bethlehem J Penna.
Fig. No. AI-4
500400300
Basin
200100o
UIu_
Z -oJ
o~~ou~lJJCf) z I \ ~IO""'3--- .Icin1\\ " \ 'V////V//// I 22 21 20 '19 18
0~zwo .....J.....J ««uenen :x: 750 t \ \ r ,\ \ \ (\ ( ~14 ___ ~b~7-s~ ~\. \ ~ \ II./ _24z u0«i=~«-I- 800Cf)
850
ST ATIONS ALONG SECTION C-C
(RED SCALE ON MODEL)
I I I I I I __ I_--i700 800 900 1000
Project 1050-326
NOCKAMIXON SPILLWAY MODEL
PLAN VIEW - WATER SURFACE CONTOURS - PROTOTYPE DEPTHS
Forebay Modification: Original
Spillway Design: Original- Smooth Channel
Percent Design Flow: 100 0/0
20
21
21
22
2223
25
700600
.25
Fritz Engineering Labora tory
Hydraulics Division, Civil Engineering Dept.
Lehigh UniversitYi Bethlehem, Penna.
Fig. No. At-S
500400300200100o
850
UIu_z...Jo~i=ou::!WCJ)Z
oC)ZWo...J..J<[«u
CJ)
~ [5 7500<[
i=a$«-~ 800
STATIONS ALONG SECTION C-C(RED SCALE ON MODEL)
1 I 1 I I I L_:
700 800 900 1000
Project 1050-326
NOCKAMIXON SPILLWAY MODEL
PLAN VIEW - WATER SURFACE CONTOURS - PROTOTYPE DEPTHS
Forebay Modification: Original
Spillway Design: Original- Rough Channel
Percent Design Flow: 200/0
850
I I I I 1 1 I700 800 900 1000
Fritz. Engineering Laboratory
Hydraulics Division, Civil Engineering Dept
Lehigh UniversitYi Bethlehem, Penna.
Fig. No. AI-6
2 nd. agee Spillway
~
300
ST ATIONS ALONG SECTION D-D
(RED SCALE ON MODEL)
200100
Hydraulic Jump-
)'10
~II
~ . ()II
o
W.J«oen 750
(f):::S::::200«i=.J« ~ 800.....CI)
oI0_
z~00
~~WC/)2
(!) 0 7002o...J«
Project 1050-326
NOCKAMIXON SPILLWAY MODEL
PLAN VIEW - WATER SURFACE CONTOURS - PROTOTYPE DEPTHS
Forebay Modification: Original
Spillway Design: Original-Rough Channel
Percent Design Flow: 40%
1415
700600500
Fritz Engineering Laboratory
Hydraulics Division J Civil Engineering Dept.
Lehigh University; Bethlehem J Penna.
Fig. No~ AI ..7
'2 nd. Ogee Spillway
~
400
II
o
I?
300200
13
100
Hydraulic Jump
(!) 700ZW0...J...Jc::(c::(U
enen~
750zuOC::(~...J«mt; - 800
850
L0
UIu_z-'o~~ou~I.JJen z
o
STATIONS ALONG SECTION D-D
(RED SCALE ON MODEL)I I I I I 1 I
700 800 900 1000
Project 1050-326
NOCKAMIXON SPILLWAY MODEL
PLAN VIEW - WATER SURFACE CONTOURS - PROTOTYPE DEPTHSForebay Modification: Original
Spillway Design: Original-Rough Channel
Percent Design Flow: 60 %
15
16
1611
11
18
18
19
1920
20
700
GI
600500
Fritz Engineering Laboratory
Hydraulics Division, Civil Engineering Dept.
Lehigh Un iversity; Bethlehem , Penna~
Fig. No~ AI-8
~
I 2 nd~ Ogee Spillway
400300
14
14
200
15
Hydraulic Jump
()I<.)-
....JZWo 0-0~:!W zen 0
~ ~ 700o <{....J ()«en
~ 6 750OC:{-....JI- CD«-I-
8°°1 \ "-16
en
850
STATIONS ALONG SECTION D-D
(RED SCALE ON MODEL)I I I I I I I
700 800
Project 1050-326
NOCKAMIXON SPILLWAY MODEL
PLAN VIEW - WATER SUR'FACE CONTOURS - PROTOTYPE DEPTHS
Forebay Modification: Original
Spillway Design: Original Design -Rough Channel
Percent Design Flow: 80 0/0
700600
Fritz Engineering Laboratory
Hydraulics Division, Civil Engineering Dept.
Lehigh University i Bethlehem t Penna.
Fig. No. AI-9
500
~
400300 .200100
UI
I~\ ~~:::1~\\ \ \!6WjjJ t I I ,U _?I "1"'1. 19
...J 23 ""Zw00 23i=0u:Ew(f)Z
0(!)wZ...J3««0
(f)
(f)~
zo0«-...JI-- m«-f0-CI) 1 I 1:::1 "
, \ IlIIll \. I \ 111'1,...... I ".11 IJ 20 19
ST ATIONS ALONG SECTION 0-0(RED SCALE ON MODEL)
1 I 1 I I 1 .1
700 800 900 1000
Project 1050- 326
NOCKAMIXON SPILLWAY MODEL
PLAN VIEW - WATER SURFACE CONTOURS - PROTOTYPE DEPTHSForebay Modification: Original Design
Spillway Design: Original Design - Rough Charinel
Percent Design Flow: 100 0/0
21
2223
24
24
Q
700600
Fritz Engineering Laboratory
Hydraulics Division, Civil Engineering Dept.
Lehigh University; Bethlehem, Penna.
Fig. No. AI-IO
500
2 nd. Ogee Spillway
<l
400300200100
()I
() -.....J
Z Wo 0- 0I- :Euw zen 0
(!) IJJZ .....Jo <:t.....J U<:t en(/) ~
z uo <t- .....JI- m<[
I-(J)
.... vv
850
L0
STATIONS ALONG SECTION D-D
(BLACK SCALE ON -MODEL)I 1 I I __~ I 1
700 800 900 1000
I I I I I I 1 I
700 800 900 1000
Fritz Engineering Laboratory
Hydraulics Division t Civil Engineering Dept.
Lehigh University; Bethlehem t Penna.
Fig. No. At-If
Project 1050-326
NOCKAMIXON SPILLWAY MODEL
PLAN VIEW - WATER SURFACE CONTOURS - PROTOTYPE DEPTHS
Foreboy Modification: No.2
Spillway Design: Modification Port A
Percent Design Flow: 20 0/0
~
300
. STATIONS ALONG SECTION D-D
(RED SCALE ON MODEL)
II
II
200100
Weak Hydraulic Jump
a
850
UIu_z..Jo ~ 650
E~Wenz(!) 0 700ZW0..J.J««u
en 750Cf)~
zo0«
~ ~800~'f)
VIV_z-JOW_0~OV~WenZ
oC)ZWO..J..J<{<tVenen::::c:ZVO<t~..J<tID~en
700
750
800
850
o
Hydraulic Jump
16
100
~
STATIONS ALONG SECTION D-D
(RED SCALE ON MODEL)
Project 1~50-326
NOCKAMIXON SPILLWAY MODEL
PLAN VIEW..- WATER SURFACE CONTOURS - PROTOTYPE DEPTHS
Forebay Modification: Finol No.2
Spillway Design: Modification Port A
Percent Design Flow; 60 0/0
Fritz Engineering Laboratory
Hydraulics Division, Civil Engineering Dept.
Lehigh University; Bethlehem, Penna.
Fig. No. A\-(2.
I I I I I I I
700 800 900 1000
19
19
19
24
23 22 21 20
24ff~)20
700600
Fritz Engineering Laboratory
Hydraulics Division 1 Civil Engineering Dept.
Lehigh University; Bethlehem 1 Penna.
Fig. No. AI-13
,500
Project 1050-326
NOCKAMIXON SPILLWAY MODEL
PLAN VIEW - WATER~ SURFACE CONTOURS- PROTOTYPE DEPTHS
Forebay Modification: Final No.2
Spillway Design: Modification Part A
Percent Design Flow: 1000/0
~
400300200
2021
100
(!)ZW0...J...J««Uenen ~ 750ZUo «
~~t; - 800
850
La
UIu_
...JZ--w00-0t:EI.JJ zCf)o
STATIONS ALONG SECTION 0-0(RED SCALE ON MODEL)
I I I _----.l. I I I
700 800 900 1000"
~ All Depths -\0 Feel
\n This Area~
700
T _11
600
Fritz Engineering Laboratory
Hydraulics Division, Civil Engineering Dept
Lehigh University; Bethlehem, Penna.
Fig. No. Al- \4
Project 1050.. 326
NOCKAMIXON SPILLWAY MODEL
PLAN VIEW - WATER SURFACE CONTOURS- PROTOTYPE DEPTHSForebay Modification: Final No.3
Spillway Design: Final
Percent Design Flow: 20 %
500
I Length of IBottom Roller
2 nd~ Ogee Spillway
~
~
400
12
12
300200100
Hydraulic Jump
o
850
'-'I
'-'Z-'o~-0G~w(j)Z
o~ w 7000-'J<:(<to
(j)
(j) ~ 750Z'-'0<:(--'h--<o4..;"..._~ - 800
STATIONS ALONG SECTION 0-0
(RED SCALE ON MODEL)1 I I I I I I J
700 800 900 1000
- 14
~AII About 13' /~ Deep~
700
14
14
600500
Project 1050-326
NOCKAMIXON SPILLWAY MODEL
PLAN VIEW·- WATER SURFACE CONTOURS - PROTOTYPE DEPTHSForebay Modification: Final No.3
Spillway Design t Final
Percent Design Flow.: 60 %
Fritz Engineering Laboratory
Hydraulics Division J Civil Engineering Dept
Lehigh University; Bethlehem J Penna.
Fig. No. AI-IS
CL
1\;c
'C-cCD >Ct:J:QiE.c=t
C/)
1 Length of IBottom Roller
2 nd. Ogee Spillway
<k.
13
400
14
15
15
300
l6
16
200100o
850
u \Ju_
Z....JOW_0..... 0u~wCf)Z
0
~ W 7000....J....J««u
en~ [5 7500«-....Jf- m«-~ 800
STATIONS ALONG SECTION 0-0
(RED SCALE ON MODEL)f I I I 1 _~ f (
700 800 900 1000
18
o
600
Fritz Engineering Laboratory
Hydraulics Division) Civil Engineering Dept..
Lehigh University; Bethlehem. Penna.
Fig. No. Al-16
Project 1050-326
NOCKAMIXON SPILLWAY MODE~
PLAN VIEW - WATER SURFACE CONTOURS - PROTOTYPE DEPTHSForebay Modification: Final ·No. 3
Spillway Design: Final
Percent Design Flow: 100 0/0
500
2nd. Ogee Spillway
~
400
17
(}s
18
300
18
1718
200
1920
100
rstart of Jump
Hydraulic Jump
o
850
UI
0_z...Jo~~oo~IJJC/)Z
o~ ~ 700Set«0
C/)
~ n 7500«-...J1- 00«-~ 800
STATIONS ALONG SECTION 0-0
(RED SCALE ON MODEL)I I I I I I I
800 800 900 1000
A P PEN D I X A2
WEIR CROSS SECTIONS
List of Illustrations
-85
Figure No. Title
A2-l Original Design, Smooth Channel, 20 Percent Flowrate
A2-2 Original Design, Smooth Channel, 40 Percent Flowrate
A2-3 Original Design, Smooth Channel, 60 Percent Flowrate
A2-4 Original Design, Smooth Channel, 80 Percent Flowrate
A2-S Original Design, Smooth Channel, 100 Percent Flowrate
A2-6 Original Design, Rough Channel, 20 Percent Flowrate
A2-7 Original Design, Rough Channel, 40 Percent Flowrate
A2-8 Original Design, Rough Channel, 60 Percent Flowrate
A2-9 Original Design, Rough Channel, 80 Percent Flowrate
A2-10 Original Design, Rough Channel, 100 Percent Flowrate
A2-11 Forebay Modification No.1, Rough Channel, 20 Percent Flowrate
A2-12 Forebay Modification No.1, Rough Channel, 40 Percent Flowrate
A2-13 Forebay Modification No.1, Rough Channel, 60 Percent Flowrate
A2-l4 Forebay Modification No.1, Rough Channel, 80 Percent Flowrate
A2-lS Forebay Modification No.1, Rough Channel, 100 Percent Flowrate
A2-l6 Forebay Modification No.II, Rough Channel,20 Percent Flowrate
A2-17 Forebay Modification No.II, Rough Channel ,40 Percent Flowrate
A2-18 Forebay Modification No.II, Rough Channel,60 Percent Flowrate
A2-19 Forebay Modification No. III,Rough Channel,20 Percent Flowrate
A2-20 Forebay Modification No. III ,Rough Channel,60 Percent Flowrate
A2-21 Forebay Modification No.III,Rough Channel,lOO Percent Flowrate
4051---- -- ~-~--- --.~----~----- ~405
1-----_. - --. ~ - -,-
400~ --~400
-395 I I 1395
First Ogee
3331- -I 333
328~ -L--_ -I 328
..l
'323323 tl------------:s=-e-c-=o-=n-:d+l-;:o:g:e~e-----------====
Both Views Loo king Upstream
Project 1050-326NOCKAMIXON SPILL WAY MODEL
First and Second Weir Cross SectionsForebay Mod ification - OriginalSpillway Design - Original UnmodifiedDesign Flow - 20 % No Roughness
Fritz Engineering LaboratoryHydraulics Division, Civil Engineering Dept.
Lehigh University; Bethlehem , Penna.Fig. No. AZ.-I
405~-~-~-~------------ - .. I ··---·-------------·----1405
------------- +---_._----~-------~._------~.-_._-----
400C--- - m ! ~ __ .--1 400
1395395'~---~-------~--==~====-=F~ir~st+1~o=g:e~e===--......:.:~=---------.:....-----
333 _._~_.~~-~._~~~-~--~-~_._--~._~------_. ~-----~.. _. ~-- 333
328 - ---_ .."--- - - -.---.---- - .-. --- _n_ _ I - -. ------ ------ .- ---.--~---------I 328
---~1323----Second I Ogee
Both Views Looking UpstreamProject 1050-326
NOCKAMIXON SPILL WA Y MODELFirst and Second Weir, Cross Sections
Forebay Modification -UnmodifiedSpillway Design - UnmodifiedDesign Flow - 40 % - No Roughness
Fritz Engineering LaboratoryHydraulics Division, Civil Engineering Dept.
Lehigh University; Bethlehem, Penna.Fig. No. A2.-2
405
400
405
400
395' I '395
333
First Ogee
333
328 ~- - l ~o _.0 • • 0 0 0 -~ 328
---'323323 I Second I Ogee
Both Views Looking Upstream
Project 1050-326NOCKAMIXON SPILLWAY· MODEL
First and Second Weir Cross SectionsForebay Modification - OriginalSpillway Design - UnmodifiedDesign Flow - 60 °/0 - No Roughness
Fritz Engineering LaboratoryHydraulics Division t Civil Engineering Dept.
Lehigh University; Bethlehem , Penna.Fig. No. A'2..-3
4051 I 1405
~ ...............
400 I I ="-~ 1400
~~------- -_..__..._-~.-~~-~---_._--_._--- - ~ ---~------------I
1---------- - ----.-... -~--.. -------------- ... ---~----~-~--~------ I 1
395 1 I '395
First Ogee
~------ -=q 1333333 -. -- --._. -_~--~ __ -~ __ =- -s;:::: =:-:----.- ----l-----
"""
~~~========t~=====-------=== '323Second I Ogee
~---~- .. ---,.- .. ----- ---._ ..~---.--- I
328 E~===--==-=- .- -------- _ ~ 328
Both Views Looking UpstreamProject 1050-326
NOCKAMIXON SPILLWAY MODELFirst and Second Weir Cross Sections
Forebay Mod ification - OriginalSpillway Design - UnmooifiedDesign Flow - 800/0 - No Roughness
Fritz Engineering LaboratoryHydraulics Division, Civil Engineering Dept.
Lehigh University i Bethlehem , Penna.Fig. No. A2.-4
405--·...~.- -~. ~- -~~ .. ~~- ._--~-~-- -- --- ~ ~.~._~~ ~~~ -~~-~~ ~-~-- -- -- ._- -~- - .. _-
405
400 400
395' I '395First Ogee
338
333 l------ ---- ~~,-,-,------ - ---.'- ---------r ---- ... ,.---'..----.....---.. -.,.-,.--.----.--.-.-.-~--,-.------- --._-"---.,'-'---~-----------., 333
Project 1050-326NOCKAMIXON SPILLWAY MODEL
First and Second Weir Cross SectionsForebay Modification - OriginalSpillway Design - UnmodifiedDesign Flow - 100 % - No Roughness
Fritz Engineering LaboratoryHydraulics Division, Civil Engineering Dept.
Lehigh University; Bethlehem , Penna..Fig. No .. A?.-5
Both Views Looking Upstream
1323323--,E-------------=---------s~e=c=o=n~d11~o=g=e~e====------:--~===~
328~ ..L ~ .-/ ~ 328
405
400
.. ·······:-:---:-~~=:~===-==:--~-----:====L---------------______ -I 405____________ ~ • ............. o o_ .0. • 0 - • ._._~ _
I -- -.--- -- ------ -----------._---- ---0 .. --.
400
395 [ - -"-0 _H • ' 0- 0- --r . -.- 0- -~--.-- ---·-on-_- _On OO -0-_- --. - -- n_O mo -~-~- -0-0- 0 ---- -----_.- J 395
First I Ogee
333
328
~333
328
323 1 I 1323
Second I O-gee
Both Views Looking Upstream
Project 1050-326NOCKAMIXON SPILLWAY MODEL
First and Second Weir Cross SectionsForebay Modification - OriginalSpillway Design - UnmodifiedDesign Flow - 20 % - Roughness
Fritz Engineering LaboratoryHydraulics Divisio:n J Civil Engineering Dept.
Lehigh University; Bethlehem • Penna.Fig. No. A2.- "
405 ~~t 405
400 I-- l _ --1400
.......--------.-1395...... _---395 J First I Ogee
333 I- I .--1 333
328 F- I·~ --4 328
1323323
1l-------------=s~e~co~n~d+1~o~g:e:e~-----~--~===Both Views Looking Upstream
Project 1050-326NOCKAMIXON SPILLWAY MODEL
First and Second Weir Cross SectionsForebay Modification - OriginalSpillway Design- UnmodifiedDesign Flow - 40 % - Roughness
Fritz Engineering LaboratoryHydraulics Division t Civil Engineering Dept.
,Lehigh University; Bethlehem t Penna.Fig. No. A'Z.-1
405 -=:------=-==--=-d=.----==--==-==-~~=~=--- -=-=~===--~--- ---- -- 405-.----.- --- "to .
400 400
'3953951E=----------------:F~ir~st~tl~o~g:e:e-----.:--------~---
333 333
~__---' 328
~. ~~-~ _._~-~-~~- ~-_.----..~- ---~-~~._._._-~
328
323' I 1323
Second I Ogee
Both Views Loo king Upstream
Project 1050-326_
NOCKAMIXON SPJLLWAY MODELFirst and Second Weir Cross Sections
Forebay Modification - OriginalSpillway Design - UnmodifiedDesign Flow - 60 % - Roughness
Fritz Engineering LaboratoryHydraulics Division, Civil Engineering Dept..
Lehigh University; Bethlehem, Penna.
Fig. No. A2.- 8
405 ----~-----.---~ -----1 405
400 t---- -_.~--~-----.._----- 400
395 ' I '395
333
First Ogee
333
3 28 I----------~-~~-_..------------ 328
323 I I '323SecondlOgee
Both Views Looking Upstream Project 1050-326NOCKAMIXON SPILLWAY MODEL
First and Second Weir Cross SectionsForebay Modification - OriginalSpillway Design - Original Unmod ifiedDesign Flow - 80 % Rough
Fritz Engineering LaboratoryHydraulics Division, Civil Engineering Dept.
Lehigh University; Bethlehem, J Penna.Fig. N-o. - A2-9
405
400 ~,--,--,-----,--
l--====-====~=-=---====:-~==----1405
---~---------~----~l--~-~--:~=~_:_-=~~~~-~..... ~ ~--~ 400
395 I I '
First I Ogee
395
I'. --. I
333
328
333
328
323' I '323
Second I Ogee
Botb Views Looking Upstream
Project 1050-326NOCKAMIXON SPILLWAY MODEL
First and Second Weir Cross SectionsForebay Modification - OriginalSpillway Design - UnmodifiedDesign Flow- 100 %-Roughness
Fritz Engineering LaboratoryHydraulics Division t Civil Engineering Dept.
Lehigh University j Bethlehem t Penna.Fig. No. A2.-IO
405---
400__ ~I
405
400
395 1 I 1395
First Ogee
View Looking UpstreamProject 1050-326
NOCKAMIXON . SPILLWAY M,ODELFirst and Second Weir Cross Sections
Forebay Mod ification - Modification ISpillway Design - UnmodifiedDesign Flow - 20 % - Roughness
Fritz Engineering LaboratoryHydra ulics Division J Civil Eng4neering Dept.
Lehigh. University j Bethlehem , Penna.Fig. No. A2.-1I
405
400 t I --,--
405
400
395 I I 1395
First agee
View Looking Upstream Project 1050-326NOCKAMIXON SPILLWAY MODEL
First and Second Weir Cross SectionsForebay Modification - Modification ISpillway Design - UnmodifiedDesign Flow- 40 0/0- Roughness
Fritz Engineering LaboratoryHydraulics Division, Civil Engineering Dept.
Lehigh University; Bethlehem , PennOaFiga NOa A2.-fa
405~-
400~
:- -_~~~_~~-_._~--~_~-_--~~~~~~==~~~ .__._. --=1 .~ 405
~400
- - -- -- ~- --~ -- --~-~~~-~••~-~----~~----.--.--------.---~~~~&~--
Project 1050-326NOCKAMIXON_ SPILLWAY MODEL
First and Second Weir Cross SectionsForebay Modification - Modification ISpillway Design '- UnmodifiedDesign Flow - 60 % - Roughness
Fritz Engineering LaboratoryHydraulics Division, Civil- Engineering Dept.
Lehigh University; Bethlehem, Penna.Fig. No. A2.-13
395 I I '395First Ogee
View Looking Upstream
405 ~---~-------~---_.~~-_.__.--~--_._---~-~~~_.-----~.-, ...- .--.-.~-----.-.-~---~-.----.---.
400I'"
405
400
395' I '395First Ogee
View Looking Upstream
Project 1050-326NOCKAMIXON SPILLWAY MODEL
First and Second Weir Cross SectionsForebay Modification - Modification ISpillway Design - UnmodifiedDesign Flow - 80 % - Roughness
Fritz Engineering LaboratoryHydraulics Division, Civil Engineering Dept.
Lehigh University; Bethlehem , Penna.Fig. No. A2.- ~4
405 405
400 400. - -,,-._-- -----1.
1395395
1E=-----=-=~-------==-==-=-=-=-~F~i=rs~tJI~o~:ge:e~----==-=--------------View Looking Upstream
Project 1050-326NOCKAMIXON SPILLWAY MODEL
First and Second Weir Cross SectionsForeboy Modification - Modification ISpillway Design - UnmodifiedDesign Flow- 100 %-Roughness
Fritz Engineering LaboratoryHydraulics Division, Civil Engineering Dept.
Lehigh University; Bethlehem, Penna.Fig. No. A2..-15
405 l- I --I 405
400 ~ I --I 400
1395395'r===--~----------F~.I-rs~t~l~o=ge=e:-------------"----
336 t- I --I 336
331 t-- I --f 331
326 I Second I Ogee
Both Views Loo king UpstreamProject 1050-326
NOCKAMIXON SPILLWAY MODELFirst and Second Weir Cross Sections
Forebay Modification - Modification ]I
Spillway Design- Modified Part ADesign Flow - 20% - Roughness
Fritz Engineering LaboratoryHydraulics Division J Civil Engineering Dept.
Lehigh University; Bethlehem, Penna.Fig. No. A'2--l6
405
400
_.._-~--!, ...._.. - ~,
t-
405
400
395 1 I 1395
336
331
First Ogee
336
331
326' I 1326Second I Ogee
Both Views Looking UpstreamPrOject 1050-326
NOCKAMIXON SPILLW AY MODELFirst and Second Weir Cross Sections
Forebay Modification - Modification ]I
Spillway Design - Modified Part ADesign Flow - 60 % - Roughness
Fritz Engineering LaboratoryHydraulics Division i Civil Engineering Dept.
Lehigh University; Bethlehem , Penna.Fig. No. A2..- \1
405 I -+----~----.-------~---.------------.- .-.~---------~- ------ 405
400 400
395 1 I '395
336 ~----------
331 ~-------- ..-_..---------------
First
-t
Ogee
336
331
1----._--------------------.----- -. ------.-.----------- .._-- ---~-.-.--+--.---- -- ---- -------- -- .~----. -------'----------- ..-...
1326326 i Second IOgee
80th Views Looking UpstreamProject 1050-326
NOCKAMIXON SPILLWAY MODELFirst and Second Weir Cross Sections
Forebay Modification - Modification n:Spillway Design - Modified Part ADesign Flow - 100 % - Rroughness
Fritz Engineering LaboratoryHydraulics Division t Civil Engineering Dept.
Lehigh University; Bethlehem t Penna.Fig. No. A2.-18
405 ......I------------~, ~-- ~-~--1405
I ~~. =~---~-------~--~~.~-====--=..==~~-.~~--400 I---- I -.--,---- ----1400
395' I '395 .
First I Ogee
336 ~--~~---~=~-=-~~-=~=E=~:==~=--=-==_=~=:-----n----n-------l336
I
331 L ~~~-.--..---~.-. ------=t===-~-----.--'-,.---.-.-'------.----~---.------.------ ..--- --I 331
326' I 1326
Second IOgee
Both Views Looking UpstreamProject 1050-326
NOCKAMIXON SPILLWAY MODELFirst and second Weir Cross Sections
Forebay Mod ification - Modification]l[Spillway Design - Modified - FinalDesign Flow - 20 % - Roughness
Fritz Engineering LaboratoryHydraulics Division, Civil Engineering Dept.
Lehigh University; Bethlehem, Penna.- Fig. No.. A't. -19
405~-'- --I 405
400 r 1 --------:i 400
395' I '-395
336
331
First Ogee
336 -
331
326' I '326-Second I agee
Both Views Looking Upstream
Project 1050-326'NOCKAMIXON SPILLW AY MODEL
First and Second Weir Cross SectionsForebay Modification- Modification ]I[
Spillway Design - Modified FinalDesign Flow - 60% - Roughness
Fritz Engineering LaboratoryHydraulics Division, Civil Engineering Dept.
Lehigh University; Bethlehem , Penna.Fig. No. A2.. - 20
405 -~ -~-, ._----~- --- .--- ----~-------~----~.-----~~-~---.--- -- --------.--.-t------ -~---------~- ------ ----------- -- -- -- ..----~~~-- .--- --_. 405
400
-~-~--
r
400
~~ -~ ~~Y_I ._~ ~ ~ •• _._ ••• __~••_~••__~~_ ~ __
13953951l----------------=----=-------=~-=--~F~ir=s:t 11~o~g:e:e----..:..----------:-----
336__J
--_.-- 336
331 331
I
326 ' I 1326
Second I OgeeBoth Views Looking Upstream
Project 1050-326NOCKAMIXON SPILLWAY MODEL
First and Second Weir Cross Sections .Forebay Modification - Mod ification :m.Spillway Design - Modified - FinalDesign Flow- 100 % - Roughness
Fritz Engineering LaboratoryHydraulics Division. Civil Engineering Dept.
Lehigh University'; Bethlehem • Penna.Fig. No. AZ. - 2J
-107
A P PEN D I X A3
REFERENCES
1. "Preliminary Report - Site Investigation", by Pickering, Carts,and Summersorr, Inc., October 15, 1964 for Project No. GSA 194-12,Nockamixon State Park.
2. "Recommended Design of Dam ll, by'Pickering, Corts and Summerson,
Inc., May 17, 1965 for Project No. GSA 194-12, Nockamixon StatePark.
3. IIInterim Report - One Stage Construction", by Pickering, Carts,and Summerson, Inc., November 9, 1965 for Project No. GSA 194-12,Nockamixon State Park.
4. "Open-Channel Hydraulics", by V. T. Chow, McGraw-Hill, N.Y., 1959.
McPherson, M. B. DESIGN OF DAM OUTLET TRASH-LIKE VERIFIED BY MODELTESTS
Civil Eng1neering
LEHIGH UNIVERSITYDepartment of Civil Engineering
FRITZ ENGINEERING LABORATORY
HYDRAULIC DIVISIW
STAFF PUBLICATIONS
Herbieh, J. B..
1950
Discussion on: TRANSLATIONS OF FOREIGN LITERATUREON HYDRAULICS
Proe. ASCE, Jour. of Hydr. Div. Paper 2349, BY 1 1960
McPherson, M. B.
White, W. K.McPherson, K. B.
Macnaughton. M. F.Herbich, J. B.
AN INEXPENSIVE DEMONSTRATION FLUID POLARISCOPECivil Engineering
Discussion on Paper: DETERMINATION OF PRESSURECONTROLLED PROFILES
ASCE Proceedings, Separate No. 491
ACCIDENTAL AIR IN CONCRETEJour •• ACI, Vol" 26, No.3Proc., Vol. 51. Title 51-13
1950
1953
1953
Warnock, R. G.Howe, J. W..
Herbich. J. B.
Herbieh, J. B.
AN ANALYSIS OF THE RALSTON CREEK HYDROLOGIC RECORDBulletin No.. 16, Iowa Highway Research Board 1960 •
THE EFFECT OF SPUR. DIKES ON FLOOD FLOWS THaDUGHBRIDGE CONSTRICTIONS
Paper presented at ASCE National Conventionat Boston, Mass. 1960
FLUID MECHANICS LABORATORY MANUALLehigh University 153 pages 1960
SOME NarES ON COMPARISON OF .BRITISH AND AMERICANUNIVERSITIES
Edinburgh University EngineeringSociety Year Book 1962EdJ..nburgh. Scotland pp. 26-29 1962
Taylor, D. C.McPherson. M. B.
Macnaughton, M. F.
McPherson, K. B.Strausser, H. S.
ELBOW METER PERFORMANCEJour. AWWA, VoL 46, No. 11 pp. 1087-1095
ACCIDENTAL AIR IN CONCRETEEngineering Journal Vol. 38. No.
• BUTrERFLY VALVE FLOW CHARACTERISTICSFroc. ASCE, Jour" of Hydr. Div"Paper 1167, HY 1 28 pages
1954
1955
1957
Herbich, J. B.
Herbich. J. B.
Discussion on: LATEST DREOOING PRACTICEFroc. ASCE.- Jour. of Waterways and HarborsDivision, Paper 2914 1961
McPherson, M. B.Dittig, R. G.
McPherson, M. B.Karr. M. H.
McPherson, M. B.Morel, A. R. R.
Straub, L. G.Herbich, J. B"Bowers, C. E.
Straub, L. G.Bowers. C. E.Herbich, J. B"
Herbich. J. B,,·
Herbich, J. B.
DISCUSSION OF SEVEN EXPLORATORY STUDIES INHYDRAULICS
Froc. ASCE, Journal of Hydr. Div. Paper 1230
A STUDY OF BUCKET -TYPE ENERGY DISSIPATORCHARACTERISTICS
Froc. ASCE, Jour. of Hydr. Liv.Paper 1266, HY 3 12 pagesCorrections: Paper 1348, BY 4, PP 57-64
OurLET PORTAL :mESSURE DISTRIBUTIONPaper presented at ASCE Convention at Chicago
AN EXPERIMENTAL STUDY OF HYDRAULIC BREAKWATERSCoastal Engineering Chap. 43; pp. 715-728
LABORATORY TESTS OF PERMEABLE WAVE ABSORBERSCoastal Engineering Chap. 44; pp. 729-742
Discussion on: SHIPBOARD HYDRAULIC BREAKWATERFroc. ASCE, Jour. of Waterways and Harbors Div.Paper 1765
Discussion on: WAVE FORCES ON SUBMERGED STRUCTURESFroe .. ASCE. Jour. of Hydr. Div. Paper 2076
1957
1957
1958
1958
1958
1958
1959
Adams. J. R.
Herbich, J. B.
Herbich. J .. B.
Herbieh. J. B.Sorensen. R. M.Wil1enbroek. J. H.
Warnock. R. G.
Herbich, J .. B.Christopher, ,R. J.
SEDIMENT TRANSPORTATIONSpartan Engineer, March 1962
DIKES CURE SCOURING AT ABUTMENTSThe American City Magazine. Vol. 77. No. 12
p. 11 - 1962
EFFECT OF IMPELLER DESIGN CHANGES ON CHARACTERISTICSOF A MODEL DREDGE PUMP
ASHE Paper No. 63-AHGr-33 1963
EFFECT OF BERM ON WAVE RUN-UP ,ON COMPOSITE BEACHProc. ASCE, Jour. of Waterways and Harbors Div.Paper 3525 1963
VIBRATION FREQUENCIES OF A CIRCULAR CYLINDER OFFINITE LENGrH IN AN INVISCID FLUID
Part 3 of final report, Contract No. 3271(01) (x) Institute of Hydraulic Research,Universi ty of Iowa 1963
USE OF HIGH SPEED PHOTOGRAPHY TO ANALYZE PARTICLEMOTION IN A MODEL DREDGE PUMP
Proe •• I.A.H.R." Paper_ 4.12, London, England 1963
Herbich, J. B.
Herbich, J. B.
Herbich, J. B.Shulits, S.
Herbich, J. B.Sorensen, A. M.Willenbrock, J. H.
Shindala, A.
Herbich, J. B.Murphy, H. D.
Mariani, V. R.Herbich, J. B.
SIMULATED SILT STARS IN HIGH-SPEED MOVIES
IMIROVING DREDGE P1.1MP IMPELLER DESIGN
DIKES CURE SCOURING AT ABUTMENTSNews of the Sanitary Engineering Div. ofASCE, Vol. 89, No. SAl, Part 2
EFFECT OF LARGE -SCALE ROUGHNESS ELEMENTS ON FLCNIN OPEN ClLANNELS
"Dissertation Abstracts, Volume XXV, Number 2.
LARGE-SCALE ROUGHNESS IN OPEN-CHANNEL FLOWProc • .ASCE, Jour. of Hydr. Div. Paper 4145
EFFECT OF BERM ON WAVE RUN-UP ON COMPOSITE BEACHESTrans. ASCE, Vol. 129
MIXED CULTURE INTERACTIONS COMMENSALISM OFPROTEUS VULGARIS WITH SACCHARafiCES CEREVISIAEIN CONTINOOUS CULTURE
Jour. of Bacteriology, Vol. 89, 693
SCOUR. OF FLAT SAND BEACHES DUE TO WAVE ACTIONIN FRONT OF SEA WALLS
ASCE, Coastal Engineering Conference, SantaBarbara, California, October
EFFECT OF VISCOSITY OF SOLID-LIQUID MIXTURE ONPUMP CAVITATION
Prepared for 50th Anniversa,ry of CentralWater & Power Research Station, Poona, India
LEHIGH UNIVERSITYDepartment o£ Civil Engineering~TZ ENGINEERING LABORATORY
HYDR.AULIC DIVISION
STAFF PUBLICATIONS
1963
1964
1964
1964
1965
1965
1966
LEHIGH UNIVERSITYDepartment of Civil Engineering
FRITZ ENGINEERING LABORATORY
HYDRAULIC DIVISION
RtOJECT REPORXS
McPherson, M. B. STUDY OF MISALIGNMENTS IN AN OPEN CHANNEL McPherson, M. B. BUTTERFLY VALVE RESEARCHProject Report No. 16 12 pages 1950 Strausser, H. S. (Sponsored by CDC Control Service, Hatboro,
Mostert, J. G. Pennsylvania)McPherson, K. B. MODEL STUDY OF HILLS CREEK DAM SPILLWAY Colleville, P. J. Project Report No. 25, 48 pages 1953
Project Report No. 17 43 pages 1950Colleville, P. J. 6" BUTTERFLY VALVE HEAD LOSS TESTS
Eagleson, P. S. CONTINUATION OF MODEL STUDY OF HILLS CREEK (Sponsored by W. S. Rockwell C·o., Fairfield,DAM SPILLWAY Connecticut)
Project Report No. 18 75 pages 1951 Project Report No. 26 14 pages 1953
McPherson, M. B. MODEL STUDY OF A CORRECTIVE DESIGN FOR THE Reid, A. W. HODEL TESTS FOR SHAWVILLE DAMStrausser, H. S. LITTLE CREEK OurLET STRUCTURE (Sponsored by Gilbert Associates, Reading,Liebig, J. O. (Sponsored by Justin and Courtney, Pennsy1vania)
Consu1ting Engineers, Philade1phia , Pa • ) Project Report No. 1427 1953Project Report No. 19 41 pages 1952
Reid, A. W. MODEL TESTS FOR CONDENSING WATER OurLET STRUCTURE -William, J. C. TESTS OF A SIX-INCH BUTTERFLY VALVE DISCHARGING FRONT STREET STATION, Erie, PennsylvaniaMcPhers on, M. B. UNSUBMERGED (Sponsored by Gilbert Associates, Reading,
(Sponsored by Fluids Controls Company Pennsylvania)Phi lade1phia, Pa.) Project Report No. 1429 1953Project Report No. 20 23 pages 1952
McPherson, M. B. MOVABLE BED MODEL STUDY OF GREENSBCll0:J NORTHMcPherson, K. B. MODEL TESTS OF PROPOSED DESIGN OF ANTIETAM Strausser, H. S. CAR,pLINA. DAM
(WAYNESBORO) n.~ SHAIT SPILLwAY STRUCTURE (Sponsored by William C. Olsen and(Sponsored by Gannett, Fleming, ,Corddry and Associates, Raleigh, North Carolina)Carpenter, Inc., Harrisburg, Pa~) Project Report No. 27 20 pages 1955Project Report No. 21 76 pages 1952
McPherson, M. BOo 3 to 100 SCALE MODEL STUDY OF CHUTE SPILLWAYMcPherson) M. B. TESTS OF A 1:32 MODEL OF A mOPOSED OurLET Strausser, H. S. PENN FOREST DAMStrausser, H. S. STRUCTURE FOR FIRST FORK SINNEMAHONING, DAM (Sponsored by Bethlehem Authority, Bethlehem,
(Sponsored by Gannett, Fleming, Corddry and Pennsy1vania)Carpenter, Inc., Harrisburg, Pa~) Project Report No. 28 10 pages 1956Project Report No. 22 16 pages 1952
Reid, A. -W. MODEL TESTS - NEW DIVERSION ~Williams, J. C. REPORT ON TESTS OF BUTTERFLY VALVES DISCHARGING (Sponsored by Pennsylvania Electric Co.)Herbich, J. B. INTO A MODEL DISCHARGE CHAMBER AND FLUME Project Report No. 29 10 pages 1956
(Sponsored by Fluids Controls Company, Inc.,Philade1phia , PaOo) Dittig, R. G. TESTS OF A WIRE MESH FILTERProject Report No. 23 39 pages 1952 Herbich, J. B.. (Sponsored by Purolator Products, Inc~
Rahway, New Jersey) •McPherson, M. B. ADDITIONAL STILLING BASIN TESTS WITH A 1:32 Project Report No. 30 18 pages 1958Strausser, H. S. MODEL FOR FIRST PORK, SINNEMAHOnNG, DAM
(Sponsored by Gannett, Fleming, Corddry and Herbich, J. B. CHARACTERISTICS OF A MODEL DREDGE PUMPCarpenter, Inc., Harrisburg, Pa.) (Sponsored by U. S. Army Corps of Engineers,Project Report No .. 24 46 pages 1952 Philadelphia District)
Project Report No. 31 110 pages 1959
LEHIGH UNIVERSITYDepartment of Civil Engineering
FRITZ ENGINEERING LABORATORY
HYDRAULIC DIVISION
PROJECT REPORTS
Brach~ P. L.Herbich, J. B.
Waddington, W. M.Herbich, J. B.
Herbich, J. B.
Herbich. J. B.Vallentine. H. R.
Patel, M. S.Herbich. J. B.
Herbich, J. B.Vallentine, H.. R.
Herbich. J. B ..Vallentine, H.. R..
Herbic\.l. J .. B.
Ap:nann, R. P ..Ali~ S .. M..
Sorensen. R. M..Willenbrock. J. H.
Herbich, J .. B.
SCALE EFFECT ON 2700
PIPE BENDS FOR BINGHAMBODY FLUID
(Sponsored by U.. S. Army Corps of Engineers.Phi ladel phia District) Fritz Lab. Re portNo .. 277-M-1O 1960
ANALYSIS OF HIGH-SPEED MOVIES OF A MODEL PUMP(Sponsored by U. S .. Army Corps of Engineers,Phila .. District) Fritz Lab .. Report No .. 277-M-ll 1960
THE EFFECT OF SPUR DIKES ON FLOOD FLOWS THROUGHBRIDGE CONSTRICTIONS
(Sponsored by American Society of Civil Engineers,Boston. Mass.) Fritz Lab .. Report No .. 280-M-16 1960
CONTROL OF BRIDGE SCOUR BY SPUR DIKES(Sponsored by Modjeski and Masters. Harrisburg,Penna.) Fritz Lab .. Report No. 280-P..R .. 32 1961
SCOUR CONTROL AT SKEW BRIDGE ABUTMENTS BY USE OFSPUR DIKES
(Sponsored by Modjeski and Masters, Harrisburg,Penna .. ) Fritz Lab. Report No .. 280-M-30 1961
EFFECT OF IMPELLER DESIGN CHANGES ON CHARACTERISTICSOF A MODEL DRED:;E PUMP
(Sponsored by U.. S. Army Corps of Engineers,Phi1a .. District) Fritz Lab. Report No .. 277-P.. R.. 33 1961
INVESTlGATIO~ OF CAVITATION OF DREDGE PUMP IMPELLER(Sponsored by Ellicott Machine Corp .. , Baltimore,Maryland) Frit~ Lab. Report No .. 1049-CT-477.34 1961
STATUS REPORTS ON IMPROVING DESIGN OF A HOPPERDREDGE PUMP
(Sponsored by U. S. Army Corps of Engineers,Priila .. District) Fritz Lab .. Report No. 277 .. 34 1962
CONTROL OF BRIDGE SCOUR BY SPUR DIKES(Spons ored by Modjeski and Masters, Harrisburg,Pennsylvania) Fritz Lab .. Report No .. 280.17 1962
A STUDY OF THE EFFECT OF HORIZONTAL BERM VARIATIONON WAVE RUN-UP UPON A COMPOSITE BEACH SLOPE
(Partially Sponsored by The Institute of Research)Fritz Lab. Report No. 293.35 1962
MODIFICATIONS IN DESIGN IMPROVE DREDGE PUMP EFFICIENCY(Sponsored by U. S .. Army Corps of Engineers,Philadelphia District) Fritz Lab. Report No.277.35 1962
Warnock. R.. G.Herbich. J. B.
Murphy, H.. D.Herbich, J .. B.
Isaacs, W. P.Mariani, V.. R.Murphy, R. D..Ta1ian, S .. F ..
Isaacs, W. P.
Murphy, H. D..
Isaacs, W. P ..Herbich, J. B.
Herbieb., J. B.Isaacs, W. P.
Shindah., A.Herbich. J. B..
Cassan, J. T.Herbich. J. B.
Basco, D. R..Herbich, J. B.
EFFICIENCY OF PUMPING AND PIPING lAyOUT(Sponsored by National Bulk Carriers, Inc.)Fritz Lab. Report No .. 294 .. 1
sucrION DREDGING LITERATURE SURVEY(Sponsored by Ellicott Machine Corporation,Baltimore. Maryland) Fritz Lab. ReportNo. 301.1
PERFORMANCE STUDY OF A 1: 6 MODEL DREDGE PUMP(Sponsored by Ellicott Machine Corporation)Fritz Lab .. Report No. 301.2
MEASUREMENI OF SLURRY FLOW BY USE OF 900
ELBOWMETER
(Sponsored by National Bulk Carriers) FritzLab. Report No .. 2991.
scoUR OF FLAT SAND BEACHES DUE TO WAVE ActION(Sponsored by the Institute of Research)Fritz Lab .. Report No .. 2932
MODIFICATIONS IN A DREDGE PUMP AFFEct !UGH SPEEDAND CAVITATION CHARActERISTICS
(Sponsored by Ellicott Machine Corporation)Fritz Lab. Report No .. 301.3
GAS REMOVAL SYSTEMS PART I: LITERATURE SURVEYAND FORMULATION OF TEST PROGRAM
(8ponsored by U. S. Army Corps of Engineers,Philadelphia District. Fritz Lab .. ReportNo. 310 .. 3
GAS REMOVAL SYSTEMS PART II: DEVELOPMENT OFFACILITY LAyour AND FORMUIATION OF TEST PROGRAM
(Sponsored by U. S. Army Corps of Engineers,Philadelphia District). Fritz Lab. ReportNo. 310.7
EFFECT OF IMPELLER MODIFICATIONS ON CAVITATIONCHARACIERISTICS
-(Sponsored by Ellicott Machine Corporation)Fritz Lab. Report No. 301.4 .
EFFECI OF IMPELLER WIDrR AND MODIFICATIONS ONPERFORMANCE AND CAVITATION CHARACTERISTICS
(Sponsored .by Ellicott Machine Corporation)Eri tz Lab. Report No. 301.5
1962
1963
1963
1964
1964
1964
1964
1965
1965
De lany, A. G.
Dawson, J. H.
Coles, D.
Jacobsen, J. T.
Becker, H. L.
Becker, H. L.
Williams. J. C.
THE FLUSH VALVE UNDER LOW PRESSUREUnpublished Thesis 45 pages
THE EFFECT OF lATERAL CONTRACTIONS ON SUPERCRITICAL FLOW IN OPEN CHANNELS
M. S. Thesis 76 pages
EXPERIMENTAL RELATION BETWEEN SUDDEN WALL ANGLECHANGES AND STANDING WAVES IN SUPERCRITlCAL FLOW
27 pages
HYDRAULIC LABORATORY MANUALAn Undergraduate Thesis
43 pages
INVESTIGATION OF mESSURE MAGNITUDES AT.MISALIGNMENTS IN AN OPEN CHANNEL
12 pages
DESIGN OF LONG-RADIUS, HIGH-RATIO FLOW NOZZLE6 pages
A STUDY OF MISALIGNMENT IN A CLOSED CONDUIT22 pages
LEHIGH UNIVERSITYDepartment of Civil Engineering
FRITZ ENGINEERING LABORATORY
HYDRAULIC DIVISION
SPECIAL REPORTS
VanQmmeren. W.1940
Taylor, D. C.1943
Karr. H. H.
1943Murthy. D. S. N.
1948Karr, M. H.
1949Horel. A. R. R.
1949G1o;nb, J. W.
1951
THE CHARACTERISTICS AND ACCURACY OF RECTANGULARBENDS USED AS FLail METERS
18 pages
THE CALIBRATION AND ACCURACY OF ELBOW METERSUndergraduate Study Report
BUCKET -TYPE ENERGY DISSIPATORSGraduate Study Report 30 pages
POIENTIAL FLOW IN 900
BENDS BY ELECTRICALANALOGY
Graduate Study Report 23 pages
A STUDY OF BUCKET - TYPE ENERGY DISSIPATORCHARACTERISTICS
Graduate Study Report 15 pages
EXIT PORTAL ERESSURE STUDY; SQUARE CONDUITGraduate Study Report 13 pages
INVESTIGATION BY ELEctRICAL ANALOGY OF POTENTIALFLOW IN A 90
0ELBOW WITH A DIVIDING VANE
Undergraduate Study Report17 pages
1953
1953
1956
1956
1956
1957
1957
Nece. R. E.
Brey. G. H.
Housley, J. B.
Williams, J. C., Jr.
Williams. J. C.
McPherson. K. B.
Wiliams, J. C. Jr.
THE CONSTRUcrION AND TESTING OF A SCALE HODELOF A DAM SPILLWAY AND STILLING BASIN (FALL RIVERDAM, KANSAS)
44 pages
EXPERIMENTAL DETERHINATION OF CIRCUIAR WEIRCHARACTERISTICS
17 pages
MODEL STUDY TO DETERMINE PitESSURE DISTRIBUTION ONTHE SPILLWAY FACES OF THE FALL RIVER (KANSAS) nAM
Graduate Study Report 42 pages
'lESTS OF A SIX-INCH BUITERFLY VALVE DISCHARGINGUNSUBMERGED
Graduate Study Report 23 pages
STUDY OF MISALIGNMENT IN AN OPEN CHANNEL AND ACLOSED CONDUIT
H. S. Thesis 61 pages
TRE DESIGN OF BENDS F03. HYDRAULIC STRUCIURESC. E. Thesis 46 pages
TESTS OF A SIX-INCH BUTTERFLY VALVE DISCHARGINGIDiSUBMERGED
Gradua te Study Roe-port 25 pages
1951
1951
1951
1951
1952
1952
1952
Brach, P.Castro, V. A.Kable, J. C.
Reimer, P.
Carle, R. J.
Carle, R. J.Kable, J. C.
Kable, J. C.
Weiss, W. L.
Hansen, R. M.
HYDRAULIC MODEL INVESTIGATION ON CHIEF JOSEPHDAM SPILLWAY
Graduate Study Report 41 pages
DESIGN OF A CAVITATION UNITUndergraduate Report 22 pages
THE USE OF SPUR DIKES WITH BRIIX;E AButMENTSGraduate Study Report 16 pages
THE EFFECT OF SPUR DIKES ON FLOOD FLOWSTHROUGH HIGHWAY BRIDGE ABtTrMENTS
Graduate Study Report 135 pages
THE DETERMINATION OF THE LENGrH OF SPfJR DIKESFOR FLOOD FLOWS THROUGH HIGHWAY BRIDGE ABurMENTS
Graduate Study Report 61 pages
SUGGESTED DESIGN CHANGES FOR A CENTRIFUGAL PUMPIMPELLER HANDLING DREDGED MUD
Graduate Study. Report 20 pages
THE NIAGARA POWER PROJECT: A SURVEYGraduate Study Report 17 pages
1959
1959
1959
1959
1959
1959
1960
Sweet, R. W.
Herbich, J. B.
Dwyer, T •. J.
WATER WAVESUndergraduate Study Report
46 pages
FACILITIES FCR INSTRUCTION AND RESEARCH INFLUID MECHANICS AND HYDRAULICS
Fritz Lab. Report No .. 237. 16-M-23
BIBLIOGRAPHYFritz Lab. Report No .. 237.18
LEHIGH UNIVERSITYDeparment of Civil Engineering
FRITZ ENGINEERING LABORATORY
HYDRAULIC DIVISION
·SPECIAL REPORTS
1960
1961
1962
Joshi, D. B.. STUDY OF SPUR. DIKESM.. S. Thesis 40 pages 1963
Patel, G.
Ta1ian, S. F.Vesi1ind, P. A.
Hariani, V. R.
Herbich, J. B.
REPORT ON STUDY OF GRAVITY WAVE REFLEcrICJotSFRCM FLOATING RECfANGULAR. BODIES
Graduate Study Report 22 pages
A STUDY OF THE EFFEcr OF HORIZONTAL BERMVARIATION IN WAVE RUN-UP UPON A CCMPOSITEBEACH SLOPE WITH DEPTH OF WATER EQUAL TO BERM.HEIGHr
Graduate Study Report 46 pages
CAVITATION CHARACTERISTICS OF A MODEL DREDGE PI:IIPGraduate Study Report 34 pages
EFFEcr OF LARGE -SCALE ROUGHNESS ELEMENTS ON FLOWIN OPEN CHANNELS
Ph.. D.. Thesis, The Pennsylvania StateUniversity 95 pages
1963
1963
1963
1963
Mariani, V. R. TESTS OF A CAVITATION UNITGr aduate Study Report pages 1963
Vesi1and, P. A.Ta1ian, ·S. F ..
De11eur, J. W.Herbich, .J. B.Schneib1e, D. E.Tracy, H• .1.
VanWee1e, B..
Koste, P.. L.
Anderson, C.
RESISTANCE OF ORGANIC mSECIICIDES TO BIOOXIDATION
Graduate Study Report 39 pages
HYDRAULICS OF BRIDGESASCE Task Force, Progress Report presentedat the ASeE Hydraulics Division meetingVicksburg, Mississippi 69 pages
SCOUR OF FLAT SAND BEACHES DUE TO WAVE ACTIONON MILD SLOPED SEAWALLS
Graduate Study Report 27 pages
FLOOD FLOWS AND RIVER BED SCOURINGUndergraduate Study Report
11 pages
WATER RESOURCESUndergraduate Study Report
10 pages
1963
1964
1965
1965
1965
LEHIGH UNIVERSITYDepartment of Civil Engineering
FRITZ ENGINEERING LABORATORY
HYDRAULIC DIVISION
TRANSLATIONS
Armanet, L.
Krisam, F.
Kinami, 1.
Sezginer, Y.Aymer, M.
Marik, M.Somogyi, M..Szabo, A.
TURBINE BUTTERFLY VALVES (VANNES - PAPILLON DESTURBINES)
Genis s iat pp. 199 -219La Houi lIe BlancheTranslated by P. J. CollevilleFritz Engineering LaboratoryTranslation No. T-l
INFLUENCE OF VOLUTES ON CHARAcrERISTIC CURVESOF CENTRIFUGAL PUMPS(DER EINFLUS DER LEITVORRICHTUNG AUF DIEKENNLINEN VON KREISELPUMPEN)
Zeitschrift des Vereines DeutscherIngenieure, Vol. 94, No. 11/12
pp. 319-366 April 1952Translated by A. Ostapenko and J. B. HerbichFritz Engineering Laborato ry Trans lation No. T-5
A STUDY ON A HOT ANEMOMETER TO MEASURE SLOWWATER VELOCITY(JOURNAL OF THE AGRICULTURAL ENGINEERING SOCIETY,JAPAN, Vol. 32, No.2, August 1964)
Tr ans lated by Jun Kondo, Fritz EngineeringLaboratory Report No. 320.1
INTERESTINH CONSTRUCTION OF A FORCED CONDUIT(TtlRKrYE MUHENDISLIK HABERLERI, Vol. 2. No. 124)
Translated by E. Yarimci. Fritz EngineeringLaboratory Report No. 301.5
EFFEcr OF AIR CONTENT IN FLUID ON CHARACTERISTICSOF CENTRIFUGAL PUMPS(UBER DEN EINFLUSS DER LUFTZUFthm.UNG AUF DIEKENNZAHLEN VON KREISELPUMPEN)
Periodica Polytechnica. Vol. 5, pp. 25-30Translated by John B. Herbich, FritzEngineering Laboratory Report No. 310-12
1953
1959
1965
1965
1966