±1100kV Guquan Converter Station PMC Project · ±1100kV Guquan Converter Station with a contract...

1
IPMA Global Project Excellence Award 2019 Small-/Medium - Sized projects Duration: 3,5 years; Budget: € 17 M Project description This PMC project was entrusted by the owner (State Grid Corpora- tion of China). The PMC team was responsible for the management of the entire project construction process for the realisation of a ±1100kV Guquan Converter Station with a contract amount of EUR 21,220,000 and a construction period of 42 months. State Grid DC Engineering Construction Company & State Grid Anhui Electric Power Engineering Supervision Co., Ltd., China ±1100kV Guquan Converter Station PMC Project Category: Construction/ Engineering/ Infrastructure

Transcript of ±1100kV Guquan Converter Station PMC Project · ±1100kV Guquan Converter Station with a contract...

Page 1: ±1100kV Guquan Converter Station PMC Project · ±1100kV Guquan Converter Station with a contract amount of EUR 21,220,000 and a construction period of 42 months. State Grid DC Engineering

IPMA Global Project Excellence Award 2019Small-/Medium - Sized projects

Duration: 3,5 years; Budget: € 17 M

Project description This PMC project was entrusted by the owner (State Grid Corpora-tion of China). The PMC team was responsible for the management of the entire project construction process for the realisation of a ±1100kV Guquan Converter Station with a contract amount of EUR 21,220,000 and a construction period of 42 months.

State Grid DC Engineering Construction Company & State Grid Anhui Electric Power Engineering Supervision Co., Ltd., China±1100kV Guquan Converter Station PMC Project

Category: Construction/ Engineering/ Infrastructure