11 mrp
Transcript of 11 mrp
![Page 1: 11 mrp](https://reader030.fdocuments.us/reader030/viewer/2022020307/559e11351a28abb8158b465c/html5/thumbnails/1.jpg)
Material Material Requirement Requirement PlanningPlanning
Dr. Nimit Chowdhary Professor
Production and Operations Management
![Page 2: 11 mrp](https://reader030.fdocuments.us/reader030/viewer/2022020307/559e11351a28abb8158b465c/html5/thumbnails/2.jpg)
Material Requirements Material Requirements PlanningPlanning
Computerized inventory control & Computerized inventory control & production planning systemproduction planning system
Schedules component items when Schedules component items when they are needed - no earlier and no they are needed - no earlier and no laterlater
![Page 3: 11 mrp](https://reader030.fdocuments.us/reader030/viewer/2022020307/559e11351a28abb8158b465c/html5/thumbnails/3.jpg)
ERP and MRPERP and MRP MRP (material requirements planning) MRP (material requirements planning)
was the precursor to ERPwas the precursor to ERP Primarily a production planning and Primarily a production planning and
control systemcontrol system MRP evolved to MRP II (manufacturing MRP evolved to MRP II (manufacturing
resource planning)resource planning) ERP and ERP II continue to extend the ERP and ERP II continue to extend the
links through all business processeslinks through all business processes
![Page 4: 11 mrp](https://reader030.fdocuments.us/reader030/viewer/2022020307/559e11351a28abb8158b465c/html5/thumbnails/4.jpg)
When to Use MRPWhen to Use MRP
Dependent and discrete itemsDependent and discrete items Complex productsComplex products Job shop productionJob shop production Assemble-to-order environmentsAssemble-to-order environments
![Page 5: 11 mrp](https://reader030.fdocuments.us/reader030/viewer/2022020307/559e11351a28abb8158b465c/html5/thumbnails/5.jpg)
Demand CharacteristicsDemand Characteristics
11 22 33 44 55WeekWeek
400 400 –
300 300 –
200 200 –
100 100 –
No
. of
tab
les
No
. of
tab
les
Continuous demandContinuous demand
M T W Th F M T W Th FM T W Th F M T W Th F
400 400 –
300 300 –
200 200 –
100 100 –
No
. o
f ta
ble
sN
o.
of
tab
les
Discrete demandDiscrete demand
Independent demandIndependent demand
100 tables100 tables
Dependent demandDependent demand
100 x 1 = 100 x 1 = 100 tabletops100 tabletops
100 x 4 = 400 table legs100 x 4 = 400 table legs
Figure 12.4Figure 12.4
![Page 6: 11 mrp](https://reader030.fdocuments.us/reader030/viewer/2022020307/559e11351a28abb8158b465c/html5/thumbnails/6.jpg)
Material Material Requirements Requirements PlanningPlanning
![Page 7: 11 mrp](https://reader030.fdocuments.us/reader030/viewer/2022020307/559e11351a28abb8158b465c/html5/thumbnails/7.jpg)
Material Material Requirements Requirements PlanningPlanning
Materialrequirements
planning
Planned order
releases
Work orders
Purchase orders
Rescheduling notices
Itemmaster
file
Productstructure
file
Master production schedule
![Page 8: 11 mrp](https://reader030.fdocuments.us/reader030/viewer/2022020307/559e11351a28abb8158b465c/html5/thumbnails/8.jpg)
Master Production Master Production ScheduleSchedule
Drives MRP process with a schedule of Drives MRP process with a schedule of finished productsfinished products
Quantities represent production not Quantities represent production not demanddemand
Quantities may consist of a combination of Quantities may consist of a combination of customer orders & demand forecastscustomer orders & demand forecasts
Quantities represent what needs to be Quantities represent what needs to be produced, not what can be producedproduced, not what can be produced
![Page 9: 11 mrp](https://reader030.fdocuments.us/reader030/viewer/2022020307/559e11351a28abb8158b465c/html5/thumbnails/9.jpg)
Master Production Master Production ScheduleSchedule
PERIODPERIODMPS ITEMMPS ITEM 11 22 33 44 55
ClipboardClipboard 8585 9595 120120 100100 100100LapdeskLapdesk 00 5050 00 5050 00LapboardLapboard 7575 120120 4747 2020 1717Pencil CasePencil Case 125125 125125 125125 125125 125125
![Page 10: 11 mrp](https://reader030.fdocuments.us/reader030/viewer/2022020307/559e11351a28abb8158b465c/html5/thumbnails/10.jpg)
Product Structure TreeProduct Structure Tree
Top clip (1) Bottom clip (1)
Pivot (1) Spring (1)
Rivets (2)Finished clipboard Pressboard (1)
Clipboard
![Page 11: 11 mrp](https://reader030.fdocuments.us/reader030/viewer/2022020307/559e11351a28abb8158b465c/html5/thumbnails/11.jpg)
Product Structure TreeProduct Structure Tree
Clipboard Level 0Level 0
Level 1Level 1
Level 2Level 2Spring
(1)Bottom Clip
(1)Top Clip
(1)Pivot
(1)
Rivets (2)
Clip Ass’y (1)
Pressboard (1)
![Page 12: 11 mrp](https://reader030.fdocuments.us/reader030/viewer/2022020307/559e11351a28abb8158b465c/html5/thumbnails/12.jpg)
Indented Bill of MaterialIndented Bill of Material
0 - - - -0 - - - - ClipboardClipboard eaea 11- 1 - - -- 1 - - - Clip AssemblyClip Assembly eaea 11- - 2 - -- - 2 - - Top ClipTop Clip eaea 11- - 2 - -- - 2 - - Bottom ClipBottom Clip eaea 11- - 2 - -- - 2 - - PivotPivot eaea 11- - 2 - -- - 2 - - SpringSpring eaea 11- 1 - - -- 1 - - - RivetRivet eaea 22- 1 - - -- 1 - - - Press BoardPress Board eaea 11
LEVELLEVEL ITEMITEM UNIT OF MEASUREUNIT OF MEASURE QUANTITYQUANTITY
![Page 13: 11 mrp](https://reader030.fdocuments.us/reader030/viewer/2022020307/559e11351a28abb8158b465c/html5/thumbnails/13.jpg)
Specialized BOMSSpecialized BOMS Phantom billsPhantom bills
Transient subassembliesTransient subassembliesNever stockedNever stocked Immediately consumed in next stageImmediately consumed in next stage
K-billsK-billsGroup small, loose parts under Group small, loose parts under
pseudo-item numberpseudo-item numberReduces paperworkReduces paperwork
![Page 14: 11 mrp](https://reader030.fdocuments.us/reader030/viewer/2022020307/559e11351a28abb8158b465c/html5/thumbnails/14.jpg)
Specialized BOMSSpecialized BOMS Modular billsModular bills
Product assembled from major Product assembled from major subassemblies & customer optionssubassemblies & customer options
Modular bill kept for each major Modular bill kept for each major subassemblysubassembly
Simplifies forecasting & planningSimplifies forecasting & planning X10 Automobile exampleX10 Automobile example
3 x 8 x 3 x 8 x 4 = 2,304 configurations3 x 8 x 3 x 8 x 4 = 2,304 configurations 3 + 8 + 3 + 8 + 4 = 26 modular bills3 + 8 + 3 + 8 + 4 = 26 modular bills
![Page 15: 11 mrp](https://reader030.fdocuments.us/reader030/viewer/2022020307/559e11351a28abb8158b465c/html5/thumbnails/15.jpg)
Basic MRP Basic MRP ProcessesProcesses
1.1. Exploding the bill of materialExploding the bill of material
2.2. Netting out inventoryNetting out inventory
3.3. Lot sizingLot sizing
4.4. Time-phasing requirementsTime-phasing requirements
![Page 16: 11 mrp](https://reader030.fdocuments.us/reader030/viewer/2022020307/559e11351a28abb8158b465c/html5/thumbnails/16.jpg)
School Mate ProductsSchool Mate ProductsMaster Production ScheduleMaster Production Schedule
11 22 33 44 55
ClipboardClipboard 8585 9595 120120 100100 100100LapdeskLapdesk 00 6060 00 6060 00
Item Master FileItem Master File
CLIPBOARDCLIPBOARD LAPDESKLAPDESK PRESSBOARDPRESSBOARDOn handOn hand 2525 2020 150150On orderOn order 175 (Period 1)175 (Period 1) 00 00 (sch receipt)(sch receipt)LLCLLC 00 00 11Lot sizeLot size L4LL4L Mult 50Mult 50 Min 100Min 100Lead timeLead time 11 11 11
![Page 17: 11 mrp](https://reader030.fdocuments.us/reader030/viewer/2022020307/559e11351a28abb8158b465c/html5/thumbnails/17.jpg)
School Mate ProductsSchool Mate ProductsProduct Structure RecordProduct Structure Record
Clipboard
Lapdesk
Pressboard(2)
Trim(3’)
Beanbag(1)
Glue(4 oz)
Level 0Level 0
Level 0Level 0
Pressboard(1)
Clip Ass’y(1)
Rivets(2) Level 1Level 1
Level 1Level 1
![Page 18: 11 mrp](https://reader030.fdocuments.us/reader030/viewer/2022020307/559e11351a28abb8158b465c/html5/thumbnails/18.jpg)
School Mate ProductsSchool Mate Products
ITEM: CLIPBOARDITEM: CLIPBOARD LLC: 0LLC: 0 PERIODPERIOD
LOT SIZE: L4LLOT SIZE: L4L LT: 1LT: 1 11 22 33 44 55
Gross RequirementsGross Requirements 8585 9595 120120 100100 100100
Scheduled ReceiptsScheduled Receipts 175175
Projected on HandProjected on Hand 2525
Net RequirementsNet Requirements
Planned Order ReceiptsPlanned Order Receipts
Planned Order ReleasesPlanned Order Releases
![Page 19: 11 mrp](https://reader030.fdocuments.us/reader030/viewer/2022020307/559e11351a28abb8158b465c/html5/thumbnails/19.jpg)
School Mate ProductsSchool Mate Products
ITEM: CLIPBOARDITEM: CLIPBOARD LLC: 0LLC: 0 PERIODPERIOD
LOT SIZE: L4LLOT SIZE: L4L LT: 1LT: 1 11 22 33 44 55
Gross RequirementsGross Requirements 8585 9595 120120 100100 100100
Scheduled ReceiptsScheduled Receipts 175175
Projected on HandProjected on Hand 2525 115115
Net RequirementsNet Requirements 00
Planned Order ReceiptsPlanned Order Receipts
Planned Order ReleasesPlanned Order Releases
(25 + 175) = 200 units available(25 + 175) = 200 units available(200 - 85) = 115 on hand at the end of Period 1(200 - 85) = 115 on hand at the end of Period 1
![Page 20: 11 mrp](https://reader030.fdocuments.us/reader030/viewer/2022020307/559e11351a28abb8158b465c/html5/thumbnails/20.jpg)
School Mate ProductsSchool Mate Products
ITEM: CLIPBOARDITEM: CLIPBOARD LLC: 0LLC: 0 PERIODPERIOD
LOT SIZE: L4LLOT SIZE: L4L LT: 1LT: 1 11 22 33 44 55
Gross RequirementsGross Requirements 8585 9595 120120 100100 100100
Scheduled ReceiptsScheduled Receipts 175175
Projected on HandProjected on Hand 2525 115115 2020
Net RequirementsNet Requirements 00 00
Planned Order ReceiptsPlanned Order Receipts
Planned Order ReleasesPlanned Order Releases
115 units available115 units available(115 - 85) = 20 on hand at the end of Period 2(115 - 85) = 20 on hand at the end of Period 2
![Page 21: 11 mrp](https://reader030.fdocuments.us/reader030/viewer/2022020307/559e11351a28abb8158b465c/html5/thumbnails/21.jpg)
School Mate ProductsSchool Mate Products
ITEM: CLIPBOARDITEM: CLIPBOARD LLC: 0LLC: 0 PERIODPERIOD
LOT SIZE: L4LLOT SIZE: L4L LT: 1LT: 1 11 22 33 44 55
Gross RequirementsGross Requirements 8585 9595 120120 100100 100100
Scheduled ReceiptsScheduled Receipts 175175
Projected on HandProjected on Hand 2525 115115 2020 00
Net RequirementsNet Requirements 00 00 100100
Planned Order ReceiptsPlanned Order Receipts 100100
Planned Order ReleasesPlanned Order Releases 100100
20 units available20 units available(20 - 120) = -100 — 100 additional Clipboards are required(20 - 120) = -100 — 100 additional Clipboards are requiredOrder must be placed in Period 2 to be received in Period 3Order must be placed in Period 2 to be received in Period 3
![Page 22: 11 mrp](https://reader030.fdocuments.us/reader030/viewer/2022020307/559e11351a28abb8158b465c/html5/thumbnails/22.jpg)
School Mate ProductsSchool Mate Products
ITEM: CLIPBOARDITEM: CLIPBOARD LLC: 0LLC: 0 PERIODPERIOD
LOT SIZE: L4LLOT SIZE: L4L LT: 1LT: 1 11 22 33 44 55
Gross RequirementsGross Requirements 8585 9595 120120 100100 100100
Scheduled ReceiptsScheduled Receipts 175175
Projected on HandProjected on Hand 2525 115115 2020 00 00 00
Net RequirementsNet Requirements 00 00 100100 100100 100100
Planned Order ReceiptsPlanned Order Receipts 100100 100100 100100
Planned Order ReleasesPlanned Order Releases 100100 100100 100100
Following the same logic Gross Requirements in Periods 4 Following the same logic Gross Requirements in Periods 4 and 5 develop Net Requirements, Planned Order Receipts, and and 5 develop Net Requirements, Planned Order Receipts, and Planned Order ReleasesPlanned Order Releases
![Page 23: 11 mrp](https://reader030.fdocuments.us/reader030/viewer/2022020307/559e11351a28abb8158b465c/html5/thumbnails/23.jpg)
School Mate ProductsSchool Mate Products
ITEM: LAPDESKITEM: LAPDESK LLC: 0LLC: 0 PERIODPERIOD
LOT SIZE: MULT 50LOT SIZE: MULT 50 LT: 1LT: 1 11 22 33 44 55
Gross RequirementsGross Requirements 00 6060 00 6060 00
Scheduled ReceiptsScheduled Receipts
Projected on HandProjected on Hand 2020
Net RequirementsNet Requirements
Planned Order ReceiptsPlanned Order Receipts
Planned Order ReleasesPlanned Order Releases
![Page 24: 11 mrp](https://reader030.fdocuments.us/reader030/viewer/2022020307/559e11351a28abb8158b465c/html5/thumbnails/24.jpg)
School Mate ProductsSchool Mate Products
ITEM: LAPDESKITEM: LAPDESK LLC: 0LLC: 0 PERIODPERIOD
LOT SIZE: MULT 50LOT SIZE: MULT 50 LT: 1LT: 1 11 22 33 44 55
Gross RequirementsGross Requirements 00 6060 00 6060 00
Scheduled ReceiptsScheduled Receipts
Projected on HandProjected on Hand 2020 2020 1010 1010 00 00
Net RequirementsNet Requirements 00 4040 5050
Planned Order ReceiptsPlanned Order Receipts 5050 5050
Planned Order ReleasesPlanned Order Releases 5050 5050
Following the same logic, the Lapdesk MRP matrix is Following the same logic, the Lapdesk MRP matrix is completed as showncompleted as shown
![Page 25: 11 mrp](https://reader030.fdocuments.us/reader030/viewer/2022020307/559e11351a28abb8158b465c/html5/thumbnails/25.jpg)
School Mate ProductsSchool Mate Products
ITEM: PRESSBOARDITEM: PRESSBOARD LLC: 0LLC: 0 PERIODPERIOD
LOT SIZE: MIN 100LOT SIZE: MIN 100 LT: 1LT: 1 11 22 33 44 55
Gross RequirementsGross RequirementsScheduled ReceiptsScheduled ReceiptsProjected on HandProjected on Hand 150150Net RequirementsNet RequirementsPlanned Order ReceiptsPlanned Order ReceiptsPlanned Order ReleasesPlanned Order Releases
ITEM: CLIPBOARDITEM: CLIPBOARD LLC: 0LLC: 0 PERIODPERIOD
LOT SIZE: L4LLOT SIZE: L4L LT: 1LT: 1 11 22 33 44 55
Planned Order ReleasesPlanned Order Releases 100100 100100 100100
ITEM: LAPDESKITEM: LAPDESK LLC: 0LLC: 0 PERIODPERIOD
LOT SIZE: MULT 50LOT SIZE: MULT 50 LT: 1LT: 1 11 22 33 44 55
Planned Order ReleasesPlanned Order Releases 5050 5050
![Page 26: 11 mrp](https://reader030.fdocuments.us/reader030/viewer/2022020307/559e11351a28abb8158b465c/html5/thumbnails/26.jpg)
School Mate ProductsSchool Mate Products
ITEM: PRESSBOARDITEM: PRESSBOARD LLC: 0LLC: 0 PERIODPERIOD
LOT SIZE: MIN 100LOT SIZE: MIN 100 LT: 1LT: 1 11 22 33 44 55
Gross RequirementsGross Requirements 100100 100100 200200 100100 00Scheduled ReceiptsScheduled ReceiptsProjected on HandProjected on Hand 150150Net RequirementsNet RequirementsPlanned Order ReceiptsPlanned Order ReceiptsPlanned Order ReleasesPlanned Order Releases
ITEM: CLIPBOARDITEM: CLIPBOARD LLC: 0LLC: 0 PERIODPERIOD
LOT SIZE: L4LLOT SIZE: L4L LT: 1LT: 1 11 22 33 44 55
Planned Order ReleasesPlanned Order Releases 100100 100100 100100
ITEM: LAPDESKITEM: LAPDESK LLC: 0LLC: 0 PERIODPERIOD
LOT SIZE: MULT 50LOT SIZE: MULT 50 LT: 1LT: 1 11 22 33 44 55
Planned Order ReleasesPlanned Order Releases 5050 5050
x2x2 x2x2
x1x1 x1x1x1x1
![Page 27: 11 mrp](https://reader030.fdocuments.us/reader030/viewer/2022020307/559e11351a28abb8158b465c/html5/thumbnails/27.jpg)
School Mate ProductsSchool Mate Products
ITEM: PRESSBOARDITEM: PRESSBOARD LLC: 0LLC: 0 PERIODPERIOD
LOT SIZE: MIN 100LOT SIZE: MIN 100 LT: 1LT: 1 11 22 33 44 55
Gross RequirementsGross Requirements 100100 100100 200200 100100 00Scheduled ReceiptsScheduled ReceiptsProjected on HandProjected on Hand 150150 5050 5050 00 00 00Net RequirementsNet Requirements 5050 150150 100100Planned Order ReceiptsPlanned Order Receipts 100100 150150 100100Planned Order ReleasesPlanned Order Releases 100100 150150 100100
ITEM: CLIPBOARDITEM: CLIPBOARD LLC: 0LLC: 0 PERIODPERIOD
LOT SIZE: L4LLOT SIZE: L4L LT: 1LT: 1 11 22 33 44 55
Planned Order ReleasesPlanned Order Releases 100100 100100 100100
ITEM: LAPDESKITEM: LAPDESK LLC: 0LLC: 0 PERIODPERIOD
LOT SIZE: MULT 50LOT SIZE: MULT 50 LT: 1LT: 1 11 22 33 44 55
Planned Order ReleasesPlanned Order Releases 5050 5050
![Page 28: 11 mrp](https://reader030.fdocuments.us/reader030/viewer/2022020307/559e11351a28abb8158b465c/html5/thumbnails/28.jpg)
School Mate ProductsSchool Mate Products
Planned Order ReportPlanned Order Report
PERIODPERIOD
ITEMITEM 11 22 33 44 55
ClipboardClipboard 100100 100100 100100
LapdeskLapdesk 5050 5050
PressboardPressboard 100100 150150 100100
![Page 29: 11 mrp](https://reader030.fdocuments.us/reader030/viewer/2022020307/559e11351a28abb8158b465c/html5/thumbnails/29.jpg)
MRP OutputsMRP Outputs
Planned ordersPlanned ordersWork ordersWork ordersPurchase ordersPurchase orders
Changes to previous plans or Changes to previous plans or existing schedulesexisting schedulesAction noticesAction noticesRescheduling noticesRescheduling notices
![Page 30: 11 mrp](https://reader030.fdocuments.us/reader030/viewer/2022020307/559e11351a28abb8158b465c/html5/thumbnails/30.jpg)
Planned Order ReportPlanned Order ReportItemItem #2740#2740 DateDate 9 - 25 - 029 - 25 - 02On handOn hand 100100 Lead timeLead time 2 weeks2 weeksOn orderOn order 200200 Lot sizeLot size 200200AllocatedAllocated 5050 Safety stockSafety stock 5050
SCHEDULEDSCHEDULED PROJECTEDPROJECTEDDATEDATE ORDER NO.ORDER NO. GROSS REQS.GROSS REQS. RECEIPTSRECEIPTS ON HANDON HAND ACTIONACTION
50509-269-26 AL 4416AL 4416 2525 25259-309-30 AL 4147AL 4147 2525 0010-0110-01 GR 6470GR 6470 5050 - 50- 5010-0810-08 SR 7542SR 7542 200200 150150 Expedite SR 10-01Expedite SR 10-0110-1010-10 CO 4471CO 4471 7575 757510-1510-15 GR 6471GR 6471 5050 252510-2310-23 GR 6471GR 6471 2525 0010-2710-27 GR 6473GR 6473 5050 - 50- 50 Release PO 10-13Release PO 10-13
Key:Key: ALAL = allocated= allocated WOWO = work order= work orderCOCO = customer order= customer order SRSR = scheduled receipt= scheduled receiptPOPO = purchase order= purchase order GRGR = gross requirement= gross requirement
![Page 31: 11 mrp](https://reader030.fdocuments.us/reader030/viewer/2022020307/559e11351a28abb8158b465c/html5/thumbnails/31.jpg)
MRP Action ReportMRP Action ReportCurrent date 9-25-02Current date 9-25-02
ITEMITEM DATEDATE ORDER NO.ORDER NO. QTY.QTY. ACTIONACTION
#2740#2740 10-0810-08 75427542 200200 ExpediteExpedite SRSR 10-0110-01
#3616#3616 10-0910-09 Move forwardMove forward POPO 10-0710-07
#2412#2412 10-1010-10 Move forwardMove forward POPO 10-0510-05
#3427#3427 10-1510-15 Move backwardMove backward POPO 10-2510-25
#2516#2516 10-2010-20 76487648 100100 De-expediteDe-expedite SRSR 10-3010-30
#2740#2740 10-2710-27 200200 ReleaseRelease POPO 10-1310-13
#3666#3666 10-3110-31 5050 ReleaseRelease WOWO 10-2410-24