11 00750 FUL Variation of Condition 18 PLY EC ABG Red

download 11 00750 FUL Variation of Condition 18 PLY EC ABG Red

of 104

description

11 00750 FUL Variation of Condition 18 PLY EC ABG Red

Transcript of 11 00750 FUL Variation of Condition 18 PLY EC ABG Red

  • Construction Environmental Management Plan

    (CEMP)

    Plymouth EfW CHP Facility

    PLY-EC--ABG-0000004-P00000000000-01-EC-11 pc 180612.docx Page 1

  • Table of Contents 1 INTRODUCTION 3

    2 CEMP OVERVIEW 3

    3 ROLES AND RESPONSIBILITIES 4

    4 ENVIRONMENTAL MANAGEMENT 7 4.1 Overall Project Management Actions 8

    4.2 Dust 11

    4.3 Noise 20

    4.4 Vibration 27

    4.5 Light Disturbance 27

    4.6 Heritage And Archaeology 28

    4.7 Waste Management 29

    4.8 Water 29

    4.9 Transportation And Traffic Management 31

    4.10 Ecological Management 31

    4.11 Land Contamination 35

    4.12 Resource Use 36

    4.13 Energy Consumption/Monitoring 37

    4.14 Water Usage 37

    4.15 Visual Amenity 37

    4.16 Vermin 38

    Attachment 1 - Wildlife & Construction Best Practice Guidance 39

    Attachment 2 - Wildlife & Construction Best Practice Guidance Poster 40

    Attachment 3 Weekly Checklist

    Attachment 4 Environmental Risk Assessment & Aspects And Impacts Matrix

    Attachment 5 Pollution Prevention Plan (Civil Construction Works)

    Attachment 6 Training And Responsibilities Matrix (Civil Construction Works)

    Attachment 7 Preliminary Works Site Establishment Plan

    Attachment 8 Main Works Site Establishment Plan

    Attachment 9 Details Of Wheelwash

    Attachment 10 Location Of Potential Dust Emission Receptors

    Attachment 11 Location Of Sensitive Noise Receptors

    Attachment 12 Construction Phasing Plans Attachment 13 Tree and Vegetation clearance plans

    PLY-EC--ABG-0000004-P00000000000-01-EC-11 pc 180612.docx Page 2

  • 1 Introduction

    MVV Environment Devonport Limited (MVV) has been awarded the South West Devon Waste

    Partnerships (SWDWP) residual waste treatment and disposal contract. The SWDWP is a

    collaboration between Plymouth City Council, Torbay Council and Devon County Council

    which is to provide a long term solution to manage waste from the southwest Devon area,

    which is not re-used, recycled or composted.

    MVV's proposal is to construct and operate an Energy from Waste (EfW) facility, incorporating

    Combined Heat and Power (CHP) technology, on land currently situated in the north east of

    Her Majesty's Naval Base (HMNB) Devonport, Plymouth.

    This Construction Environmental Management Plan (CEMP) is for the construction phase of

    the development, and sets out the intended methods of effectively managing potential

    environmental impacts arising from the construction of the EfW CHP facility.

    The responsibility for implementation of the CEMP lies with the Principal Contractor MVV O&M

    GmbH and it shall be implemented and controlled by the Site Manager who shall work in

    conjunction with key personnel (Construction Director, contractors, suppliers, etc.) to ensure it

    is implemented. In order to ensure that the plan remains relevant it will be the responsibility of

    the Site Manager to take ownership of the CEMP and ensure its relevance to activities being

    undertaken on site in light of any changes from the initial scope of the plan, this requires its

    regular revision and updating as necessary. Any revisions or updates shall be subject to

    agreement in writing with the LPA.

    2 CEMP Overview

    This CEMP identifies the project management structure roles and responsibilities with regard

    to managing and reporting on the environmental impact of the construction phase. An

    Environmental Impact Assessment (EIA) was undertaken during the planning process which

    identified and assessed the aspects of construction that could have an environmental impact.

    All proposed mitigation measures described in the EIA will be applied and are specifically

    described in the applicable sections of the CEMP.

    PLY-EC--ABG-0000004-P00000000000-01-EC-11 pc 180612.docx Page 3

  • The overall environmental objectives that will be applied to the project are:

    All practicable steps shall be taken to minimise the environmental effects of construction works.

    All activities shall be conducted in accordance with the CEMP, relevant legislation, Codes of Practices, Guidelines, and any local environmental procedures.

    Environmental licenses, permits and consents and other statutory requirements are to be obtained prior to works commencing, and fully complied with.

    All staff (including sub-contractors) shall be aware of the environmental issues relevant to the Project through the provision of site specific information on the

    environmental impacts of construction and the mitigation measures to be applied

    during inductions, briefings and tool box talks and other relevant .

    Regularly reviewing of the environmental requirements of the project and ensuring that environmental controls remain adequate throughout the duration of the project.

    3 Roles and Responsibilities

    This section describes the environmental roles and responsibilities of key members of the

    project team and provides contact details for the relevant personnel. The Principal Contractor

    (MVV O&M GmbH) shall assign individuals to each of the roles and responsibilities outlined

    below.

    Construction Director

    To lead by example and champion all areas of environmental management. Ensure that appropriate resources are in place to effectively implement the CEMP and

    deliver all legal requirements.

    Site Manager

    To lead by example and champion all areas of environmental management. Ensure that appropriate resources are in place to effectively implement the CEMP and

    deliver all legal requirements.

    Review the CEMP throughout the construction process to ensure it remains relevant and effective in identifying and managing environmental risks.

    Report to and agree in writing with the LPA any amendments to the CEMP. Ensure that all legal requirements are identified and met. Implement the use of an accurate Site Waste Management Plan (SWMP) and ensure

    its applicability to the site operations.

    Ensure that the site is safe and that hazards are identified and secured. Undertake (or nominate others) to undertake audits, as outlined in section 4.

    PLY-EC--ABG-0000004-P00000000000-01-EC-11 pc 180612.docx Page 4

  • Monitor performance of the project against statutory requirements, objectives and targets.

    Ensure that all legal requirements are identified and met. Ensure the accurate reporting of resource usage e.g. energy and water. Ensure that all documentation referencing environmental procedures and policy are

    relevant and up-to-date and included within the CEMP.

    Manage all necessary documentation to demonstrate compliance with appropriate legislation for the required period.

    Identify necessary levels of environmental competence in staff and ensure necessary training is delivered to personal.

    Manage investigation and resolution of complaints in accordance with the Complaints Handling Protocol (Planning Condition 56).

    Ensure correct procedures are followed in case of an environmental incident.

    Construction Supervisors

    Ensure that the CEMP and associated documents and control methods are effectively implemented on site on a day to day basis.

    Fully investigate and act on any environmental incidents and report findings to the Site Manager.

    Conduct and document weekly environmental inspections. Ensure that environmentally orientated briefings and Toolbox Talks are being

    delivered to the site workforce.

    Implement and maintain environmental controls on site. Ensure action is taken on any spills/incidents that occur on site. Report any activity that has potential to have an environmental effect immediately to

    the site manager. Site Staff & Sub-Contractors

    Compliance with direction given in the Site Induction Proactively approach environmental issues whilst on site Site staff should ensure they are fully aware of the environmental procedures in place

    and if they have any questions they should be directed towards the Site Manager.

    Ensure all construction activities are carried out in line with the procedures detailed in the CEMP.

    Report any environmental incident to the Site Manager

    PLY-EC--ABG-0000004-P00000000000-01-EC-11 pc 180612.docx Page 5

  • Contact Details During the preliminary works (Stage 1) phase contact can be made with the construction site

    on the following number:

    07786 626 515

    During the main construction works (Stage 2) phase contact can be made with the

    construction site as follows:

    Phone: [To be advised prior to the start of main construction works] Email: [To be advised prior to the start of main construction works]

    Contact can also be made by email with the following persons:

    Role Name Email

    Construction Director John Wade [email protected]

    Site Manager Jurgen Folz [email protected]

    Community Liaison Manager Jane Ford [email protected]

    Training All site personnel with environmental responsibilities shall be suitably trained and qualified.

    Where it is indicated that additional specific training requirements are needed, it is the

    responsibility of the site management to ensure these needs are met at the earliest possible

    opportunity.

    The induction given to all site personnel shall include a general overview of site specific

    environmental issues, as well as details of how these issues shall be managed. All appropriate

    site personnel shall undertake environmental awareness training and if supplementary training

    is needed over the course of the works it will be provided as necessary.

    Detailed information shall be communicated to personnel by means of regular Environmental

    Briefings and Toolbox Talks covering topics relating to specific site activities. These shall be

    given to all site personnel at a period of no less than fortnightly.

    PLY-EC--ABG-0000004-P00000000000-01-EC-11 pc 180612.docx Page 6

  • Environmental Bulletins and Newsflashes shall be clearly displayed in all mess / office areas.

    Any actions relating to these shall be implemented immediately, and all site personnel made

    fully aware of any changes.

    4 Environmental Management

    The site shall implement a project specific Environmental Management System (EMS)

    complying with BS EN ISO 14001. The EMS shall be monitored and audited by appropriate

    personnel throughout the duration of the works. An audit schedule shall be created which

    includes both internal and external EMS and legal compliance audits. Any system failures

    shall be documented and appropriate corrective actions issued and implemented.

    An environmental impact assessment has been undertaken for the project during the planning

    process. All identified risks are addressed within this document. However, should any

    additional risks be identified, other than those outlined in this report, supplementary

    management plans shall be put into place.

    The construction of the facility is anticipated to take approximately 30 months and will involve

    a phased construction programme involving a number of main construction activities. A set of

    phasing diagrams are included in attachment 12 which illustrate the sequence of construction

    and the areas of the site in which work will be carried out during the various main construction

    phases .

    Pre-Phase/Activity planning

    During the initial planning of each phase of construction and prior to the commencement of the

    relevant phase the activities likely to cause environmental impacts will be identified and the

    most suitable mitigation measures selected from those identified generally in this CEMP for

    the specific activities will be incorporated within the relevant phase activity method statement .

    These mitigation activities will be communicated to and agreed with the LPA no later than 2

    weeks prior to the start of the relevant phase of the construction.

    The following subsections outline the processes and methods to be implemented on site to

    ensure all environmental risks are identified and sufficient mitigation measures are put in place

    to reduce environmental impacts associated with the works.

    PLY-EC--ABG-0000004-P00000000000-01-EC-11 pc 180612.docx Page 7

  • 4.1 Overall Project Management Actions

    All environmental documentation shall be kept on site at all times and be available for

    inspection by internal and external auditors and regulators, as well as the client and

    management. Site personnel shall be made aware immediately if any significant changes in

    work procedures are implemented.

    Relevant documentation shall include the following:

    Site Weekly Checklist Impacts and Aspects Matrix Environmental Risk Assessment Construction Environmental Management Plan Site Waste Management Plan Pollution Prevention Plan including emergency response Training and Responsibilities Matrix

    Weekly environmental inspections shall take place on site by the construction supervisor. The

    findings of these inspections and any associated actions shall be appropriately documented

    on the Weekly Checklist.

    Site management shall meet as necessary with the LPA to review activities on site and the

    potential environmental impacts and mitigation measures relevant to those activities that will

    be implemented.

    MVV O&Ms site management shall regularly liaise with the Environment Agency and other

    authorities and regulatory bodies with regards to all consents, exemptions and licences. Any

    applications shall be made with consideration of appropriate timescales.

    A consents schedule shall be completed and held on site files, detailing information from date

    of application. Where specific limitations are set through any licence, consent or exemption,

    this is to be clearly identified and regularly reviewed to ensure compliance.

    The Site Emergency Response shall be found within the Pollution Prevention Plan. Contact

    details shall be clearly displayed on site and information explained to all site personnel. The

    Pollution Prevention Plan shall contain a clear detailed plan of the site which indicates the

    location of sensitive receptors such as watercourses and drainage points. An appropriate

    number of spill kits shall be located within these areas and will be clearly marked on the plan.

    PLY-EC--ABG-0000004-P00000000000-01-EC-11 pc 180612.docx Page 8

  • It is the responsibility of the site management to ensure all spill kits are fully stocked at all

    times, and an inventory of equipment within the spill kit is to be clearly displayed within.

    The project is registered with the Considerate Constructors Scheme (CCS) under registration

    number: 19164.

    The CCS is a non-profit-making, independent organisation founded by the construction

    industry to improve its image. The CCS is neither grant maintained, nor funded by the

    government, and is solely financed by its registrations. The CCS Codes of Considerate

    Practice commit those sites and companies registered with the Scheme to be considerate and

    good neighbours, as well as respectful, environmentally conscious, responsible and

    accountable. Registered sites and companies must also consider their appearance and safety.

    This commitment is maintained by the CCS monitoring registered sites and by the display of

    posters around the construction site, setting out the Code to which the sites or companies are

    committed. If passers-by wish to comment, the name and telephone number of the site

    manager or company contact are clearly displayed, alongside the freephone telephone

    number of the CCSs administration office.

    CCS Monitors who are drawn from the senior ranks of all disciplines within the construction

    industry, with a fairly even division between architects, engineers, contractors and surveyors,

    visit the site on a regular basis. The Monitor acts as an 'informed member of the public' and is

    looking at how the site represents the company and the industry. During the visit, the Monitor

    will assess the perimeter of the site, the access to the site offices and the facilities provided for

    the operatives. The Monitor will also review whether the site's procedures are in accordance

    with the Scheme's Site Code of Considerate Practice.

    The Monitor will write a report for the Site Manager and this will include the score achieved

    against each of the eight categories of the Scheme's Site Code of Considerate Practice. The

    purpose of this score is to indicate how well the site is performing against the Code.

    The site shall comply with the CCS Site Code of Considerate Practice and target to maintain a

    score of no less than 33 on each site monitor's visit. The site shall clearly display the

    associated posters and banners allowing local residents to see clearly all contact numbers.

    MVV shall ensure all works carried out are undertaken in a manner which not only ensures

    best practice, but ensures minimal disruption and cause for complaint by the public.

    PLY-EC--ABG-0000004-P00000000000-01-EC-11 pc 180612.docx Page 9

  • Training and management procedures

    To ensure that mitigation methods and measures are applied, appropriate training and

    management procedures will be implemented in accordance with Building Research

    Establishments (BRE): The Pollution control Guide: Part 1 Pre-project planning and

    effective management.

    The BRE guidance makes the following recommendations: Before the start of any project,

    appropriate training on how to control pollution emissions should be given to all personnel

    expected to be present on site. This training should include;

    The benefits of reducing pollution to health and environment, The benefits of minimising disruption from complaints and enforcement actions, Methods to minimise the generation of pollution, Actions plans on what should be done if emissions breach any limits that have

    been set for the particular site,

    Individual responsibilities and management procedures, The importance of effective communication between relevant personnel at all

    levels.

    All site personnel, site operatives and sub-contractors will be made aware of the risks and

    mitigation methodology for any potential environmental impacts relevant to their specific

    activities through the Site Induction and regular briefings and toolbox talks.

    Consultation with the public

    In conjunction with appropriate mitigation, operating hours and employee training, handling

    public relations in an appropriate way will help to reduce the potential for air quality

    complaints. BRE: The Pollution control Guide: Part 1 Pre-project planning and effective

    management makes recommendations regarding the handling of public relations. These

    recommendations will be implemented at the site;

    Notice boards on the site perimeter fencing will display telephone and email contacts for

    enquiries and receipt of complaints, and the name of the persons who should be contacted

    PLY-EC--ABG-0000004-P00000000000-01-EC-11 pc 180612.docx Page 10

  • 4.2 Dust

    The site is located within the Weston Mill area of HM Naval Base Devonport. The Naval base

    borders the majority of the site with the exception of the northern boundary. The boundary to

    the site has a range of residential properties which are noted as sensitive receptors. The

    potential receptors were identified in the EIA and these are shown in Attachment 10.

    Other ecologically sensitive receptors are noted as being;

    Tamar Estuary Blackies Wood Weston Mill Stream Weston Mill Lake Barne Brake Camels Heal Creek Groundwater

    It is also recognised that in periods of high winds the receptors affected by wind blown dust

    could be areas further away than those mentioned above if suitable dust mitigation measures

    are not implemented.

    The generation of dust outside of the site boundary is a potential source of statutory nuisance

    and can lead to complaints being received. As well as receiving complaints dust can also have

    an impact on human health and local ecology. The Environmental statement outlined the

    residential properties within 100m of the main construction area who may experience

    occasional increase in local soiling during activities being carried out in extremely dry and

    windy weather. These are deemed to be short-term episodes with a likely result in increased

    soiling of property surfaces, and are not normally associated with the general risk to health.

    Whilst this statement outlines the potential impact from dust on residents the mitigation

    outlined in this section will focus on removing the potential from nuisance dust emissions.

    It should also be noted that the naval base and its operations are also a consideration during

    the project phases.

    Potential dust sources during the construction phases of the development works:

    Site clearance Ground excavation, piling and earthworks

    PLY-EC--ABG-0000004-P00000000000-01-EC-11 pc 180612.docx Page 11

  • On site earth moving operations, site levelling, cut and fill etc. Vehicle movements over haul roads (especially unpaved) Vehicle movements on site during dry periods Re-suspension of particulates from construction vehicle movements on site, Wind blowing across the site during dry periods Stockpiling of excavated materials Cutting, grinding and drilling operations Accidental spillage and loss of load from vehicles carrying loose material Deep excavations Tipping Earthworks

    The generation of dust nuisance requires consideration of additional factors such as:

    Prevailing wind (speed, direction) Prevailing climate, including rainfall Location of sensitive receptors (including residential and commercial properties,

    habitats and watercourses)

    Potential impacts

    Background information

    The Environmental Protection Act lists the emission of dust from industrial, trade or business

    premises in sufficient quantity to be prejudicial to health or a nuisance as a statutory nuisance.

    Dust which is raised by site operations may be carried to nearby residential areas and if

    present in sufficient quantities has the potential to cause a nuisance by settling on clean

    surfaces.

    There are no UK statutory or recommended levels of dust deposition that constitute a statutory

    nuisance; whether or not a nuisance exists is determined in the first instance by the

    professional judgement of the environmental health officer.

    Dust contains particles in the range of sizes. The finer fraction of dust particle range is more

    likely to become airborne and to travel beyond the boundary of a site.

    The fine particles which comprise dust can become suspended and entrained in air and, as

    such they can disperse from a source. They will progressively fall out of the air stream; in fact

    PLY-EC--ABG-0000004-P00000000000-01-EC-11 pc 180612.docx Page 12

  • most dust settles out close to the source. Fugitive dust is that which escapes from the

    immediate vicinity of the source and may affect the area surrounding the site.

    Particulate dust emissions from construction works associated with the development have the

    potential to impact upon local residents, and on-site workers during the works. Dust which is

    raised by onsite operations may be carried to nearby residential areas, if present in sufficient

    quantities. Concerns have been raised by the inhalation of dust particles and the possible

    health effects this may have. This has the potential to impact upon local residents and on-site

    workers.

    Where mud from a development site is allowed to spread onto local roads, it can form a

    secondary source of dust. The mechanical action of wheels on the road surface material will

    reduce the particle sizes by crushing and the potential for emission of dust from these roads

    can be quite high. As vehicle pass along the road, dust is re-suspended into the turbulent air

    stream both beneath and behind the vehicle and this can become entrained into a moving air

    flow. The erosive action of road traffic depends on the number and size of wheels, the vehicle

    speeds and the moisture content of the surface material.

    Good environmental practices will as described below will be used to control these dust

    emissions, and mitigate against any nuisance problems arising.

    Monitoring programme

    On-going monitoring shall be undertaken by the construction supervisors on a regular basis,

    both on and off site for visible signs of dust emissions and deposition originating from the site

    to ensure the adequacy of the mitigation measures being employed. On site daily monitoring

    of dust emissions will be undertaken for each construction activity which is deemed to pose a

    risk, with records maintained.

    The monitoring programme will record:

    Date Activity/Location Weather Conditions Wind Direction and Speed Dust suppression method(s) implemented

    Excessively windy conditions can increase the propagation of dust. The local weather forecast

    will be taken into account as part of the monitoring procedure. These conditions will be noted

    PLY-EC--ABG-0000004-P00000000000-01-EC-11 pc 180612.docx Page 13

  • and the activities which have an increased risk of causing dust nuisance (e.g excavations and

    earthworks) during windy conditions will be restricted or the mitigation level increased.

    Construction supervisors will assess if the weather conditions are appropriate for the types of

    activities being undertaken.

    Any complaints in relation to fugitive dust will be logged and appropriate action taken by site

    management in accordance with the Complaints Protocol (Planning Condition 56) to ensure

    any further potential for complaint is minimised. Logs of any complaints will be made available

    to the LPA.

    Mitigation Techniques

    Mitigation measures will be implemented to ensure effective control of dust emissions from the

    construction works. These are industry best practices. The best practices are proven, well

    established, techniques to mitigate nuisance dust emissions.

    The mitigation measures proposed in this plan are based on guidance provided by the

    following documents;

    The BRE Guidance Document, controlling particles, vapour and noise pollution from construction sites.

    London Best Practice Guidance, The control of dust and emissions from construction and demolition.

    General mitigation techniques for the various construction activities will include:

    Activity Mitigation measures

    Construction

    Traffic All construction traffic shall follow specifically designated routes Speed limits shall be put into place on site for all vehicular movements All vehicles carrying loose material shall be covered Wheel wash facility shall be used for vehicles leaving site

    Highways Where necessary, use of road sweepers shall be incorporated to ensure highways remain clear of dust and mud

    Road edges and pathways shall be swept by hand and damped down as necessary Stockpiles To be damped down enclosed or covered as appropriate.

    To be sealed or sprayed with chemical bonding agents as required Location of stockpiles away from any sensitive receptors wherever possible

    Dust

    Suppression Mobile bowsers to be deployed on site at regular intervals as necessary. Monitoring and mitigation activity to be increased during significantly dry and windy

    PLY-EC--ABG-0000004-P00000000000-01-EC-11 pc 180612.docx Page 14

  • Activity Mitigation measures

    periods

    Where necessary, use of enclosures to be considered to ensure reduction in dust migration

    Deliveries of significantly dusty materials to be sprayed to reduce dust potential All cutting and grinding operations to be conducted in ways to reduce risk of dust

    migration (wet cutting techniques etc.)

    There will be a complete prohibition on the burning of any materials on the site during

    construction.

    Mitigation equipment will be readily available on site from the commencement of the works.

    These will include sheeting, and damping equipment; such as, tractor bowsers, road sweepers

    etc.

    Where processes are intrinsically dusty and alternative processes exist which are less dusty,

    these will be implemented. Prefabricated components and construction will be used wherever

    possible to minimise the need for on-site construction which may cause the emission of dust.

    Suitable control procedures for minimising dust during the various construction phases

    The scale of the preliminary works, (Stage 1), is minor in comparison to the main construction

    works (Stage 2). Stage 1 provides the enabling packages to ensure the Main Construction

    works can be undertaken without logistical restrictions.

    Stage 1 comprises;

    Wolseley Road junction improvements The junction improvements involve minor road-works including traffic island

    modifications, new traffic signals and resurfacing.

    Access road from Camels Head RN4 car-park to the main construction site Security Fencing Bull Point access road Erection of Acoustic Barriers Setting up of the main site establishment Further site investigation works on the main construction site (including relocation

    of exiting stockpiles and earthworks to facilitate the works) and access road bridge

    areas.

    PLY-EC--ABG-0000004-P00000000000-01-EC-11 pc 180612.docx Page 15

  • These elements will incorporate small scale earthworks. The fence will be erected manually

    without the need for craneage.

    All sensitive receptors are a consideration during these works. However as a result of the

    scale of the operations required the nuisance potential is reduced with smaller scale plant,

    smaller work areas and a reduced frequency/duration of relevant activities.

    Earthworks and piling (Main construction months 1 to 8)

    Excavations, piling, loading and unloading of materials on-site and stockpiling of materials

    have the potential to be a major contributor to dust emissions. During excavation, previously

    stable surfaces are disrupted and exposed to the wind. As these materials are generally dry

    they can easily become suspended by the wind or mechanical disturbance and readily

    become airborne in significant quantities.

    Surfaces will be disturbed as little as possible and where necessary stabilised as soon as

    possible after disturbance by damping down with water sprays to minimise dust emission and

    re-suspension.

    Where the construction logistics on site allows stockpiles will be located away from areas of

    the site close to the sensitive receptors. All stockpiles will be treated with water sprays to

    prevent dusting or covered correctly with secured tarpaulins where necessary.

    Reinforced concrete structures (Main construction months 2 to 13)

    The fabrication and construction process will involve the construction of reinforced concrete

    (RC) foundations and structures . There is potential for the emission of dust in both open and

    enclosed areas during the RC construction stage and mitigation methods are necessary to

    reduce these.

    Off site fabrication and construction will be used wherever possible. If this is not possible, the

    fabrication processes will be undertaken away from sensitive receptor areas.

    Dust suppression methods will be implemented by using fixed enclosures or equipment with

    water sprays, local exhaust ventilation or particle extraction/minimisation systems.

    Mixing of concrete will occur off site and be directly delivered to the required area of the

    construction site. On site batching will not be used. Any small scale mixing requirements will

    be undertaken in shielded areas away from sensitive receptors.

    PLY-EC--ABG-0000004-P00000000000-01-EC-11 pc 180612.docx Page 16

  • Dry sweeping will be avoided and damp sweeping using a fine mist will be used. Washing and

    damping down will be implemented as required.

    Materials handling (throughout the construction period)

    A wide range of materials will be handled during the construction phases of the development

    and the handling of these materials has the potential to create dust emissions. Generally the

    use of dry or powdery material on site will be minimised. The following precautions will be

    implemented to minimise dust emissions arising from materials handling;

    Material drop heights will be minimised,

    Damping down will be used to reduce dust emissions. in dry, hot weather damping down frequency will be increased,

    Steep sided stockpiles or mounds or those with sharp changes in shape will be avoided, Heights of stockpiles will be restricted to mitigate airborne dust potential.

    Wherever possible stockpiled materials will be kept away from the site boundary and sensitive receptor locations and damped down, enclosed or securely sheeted

    as appropriate.

    Wind barriers will be used to protect stock piled loose material and skips will be enclosed or covered, Lorries will be covered and closed tankers will be used for

    transporting dry and fine powdery materials,

    Materials delivered to site will be left wrapped until needed,

    Methods and equipment will be in place in case of spillages. The site will be regularly inspected for spillages and wet handling methods for cleaning up spillages

    such as cement powder will be used.

    Site, Access and Public roads (throughout the construction period)

    During development it will be necessary to construct access and site roads to accommodate

    vehicle and plant movements on the site and for delivery of required materials.

    PLY-EC--ABG-0000004-P00000000000-01-EC-11 pc 180612.docx Page 17

  • Unpaved site roads can greatly contribute to dust emissions, especially in dry or windy

    conditions therefore compacted hard surfaces will be used wherever possible, even if the

    routes are only temporary. Traffic on site roads located close to sensitive receptor locations

    will be kept to a minimum where construction requirements allow.

    Vehicle movements and behaviour on site will be controlled by appropriate signage and

    compliance will be monitored by construction site supervisors. Vehicles will be restricted to a

    minimum commensurate with the construction requirements and speeds will be limited to 5

    mph on un-surfaced roads and 10 mph on properly surfaced and maintained roads. This will

    contribute to the reduction in the re-suspension of dust as a result of the movement of

    vehicles.

    Site roads will be inspected regularly and kept in a compacted condition using static sprinklers,

    bowsers, low emission additives and binders if necessary. The access road to the main

    construction site will be cleaned daily during the working week and more frequently if

    necessary using a mechanical road sweeper. Edges of the access road and footpaths will be

    cleaned with a hand broom and controlled damping.

    Damping down techniques used to minimise the re-suspension of dust into the air can also

    cause the build up of mud and dirt on roads which is picked up by vehicle wheels. Therefore

    wheel washing techniques and rumble grids will be implemented, before vehicles enter public

    highways, to prevent the transportation of mud and dirt off site.

    During the preliminary works simultaneous activities will be taking place in a number of

    locations both inside and outside the naval base and therefore multiple wheel wash facilities

    will be established in this period. Due to the short term nature of these works these facilities

    will take the form of a manually operated high pressure jet wash located in the positions

    indicated on the drawing included in attachment 7. Vehicles leaving the construction areas will

    be inspected at the wheelwash points and thoroughly cleaned as required.

    During the main construction works a permanent wheel wash facility with bunded enclosure

    will be installed on the access road at the exit point of the main site in the position indicated on

    the drawing included in attachment 8. The wheel wash will be the same as or of a similar

    standard to that shown in attachment 9.

    Asbestos

    The main risk from asbestos in soils is the potential to liberate fibres into the air, as a result of

    attrition of cement products and or disturbance of the soil, and which may subsequently be

    inhaled. Post development, in those areas of the site covered by hardstanding, the risk to

    PLY-EC--ABG-0000004-P00000000000-01-EC-11 pc 180612.docx Page 18

  • human health will be negligible since the hardstanding will present a barrier to the liberation of

    airborne particulates including asbestos fibres. However, there may be a potential increased

    risk during construction related activities such as piling where significant ground disturbance

    may take place.

    Although the available information does not suggest the widespread presence of asbestos

    containing material within the fill deposits at the site, occasional asbestos containing material

    has been identified which if disturbed may have the potential to liberate asbestos fibres into

    the air and will therefore need to be appropriately managed. The following protocol for

    managing asbestos containing material (ACM) that may be encountered at the Site during will

    be adopted:

    All pile arisings comprising of fill materials should be subject to routine damping down as piling progresses.

    A person competent in identifying all types of ACM should be present on Site at all times to inspect pile arisings.

    Any arisings where ACMs are identified should be separated, damped down further and covered by plastic sheeting or similar.

    The management of arisings in this way should be maintained until the material can be removed from site for appropriate disposal.

    If ACMs are encountered, air monitoring should be undertaken in the immediate vicinity of and downwind of the works. The air monitoring should be maintained

    during ongoing works whilst a source of ACMs is present on site in order to

    demonstrate the effectiveness of the control measures, such as damping down and

    covering, being employed.

    It will be necessary for an appropriate asbestos air monitoring contractor to be retained who

    can attend the site to undertake air monitoring, as detailed above at short notice should ACMs

    be identified.

    Site specific procedures will put in place to identify testing regimes and what to do in the event

    of asbestos being found. This will vary on the type of asbestos found and its condition as to

    the level of decontamination, segregation, remediation etc. Specialist advice will be obtained

    to complete such a procedure

    If asbestos is identified during excavation works then activities will stop in the area, and the

    area quarantined whilst a specialist is employed to clear the contamination.

    PLY-EC--ABG-0000004-P00000000000-01-EC-11 pc 180612.docx Page 19

  • The most effective control of the harmful particles is by means of dust control. If asbestos is in

    the ground then it is usually wet or bound up with mud / soil / organic material etc. therefore,

    the risk is reduced. The best practice control measures already outlined will ensure this risk is

    minimised.

    Selected site personnel will be trained in asbestos awareness and will be able to identify the

    material if encountered. If this event is realised the element of work affected will be suspended

    and the area segregated prior to the necessary remediation strategy being implemented.

    Mitigating exposure of on-site workers

    Whilst it is important to minimise the impacts of the works on local residents and other

    sensitive receptors, it is also necessary to consider the effects of exposure to dust on site

    workers during the various construction phases.

    Training will be provided for all on-site workers regarding suppression of pollution emissions

    and minimising exposure to potentially harmful emissions. Appropriate PPE will be worn as

    determined by the risk assessment for the relevant activity.

    Workers will at all times reduce their exposure to emissions. Excessive time will not be spent

    by one person on one activity which is inherently dusty.

    Wherever equipment is being used within enclosed spaces, ventilation or particle extraction

    systems will be used at all times.

    4.3 Noise

    Background information

    Like dust, the generation of noise beyond of the site boundary is a potential source of statutory

    nuisance and can lead to complaints. Such complaints, if upheld, can lead to legal action

    which causes resultant delays and costs to the project. The site is directly adjacent to various

    residential areas making construction noise a particularly sensitive issue to local residents

    A basic element in the mitigation of nuisance due to noise is adherence to acceptable working

    hours. All works shall be undertaken in compliance with the working hours specified in

    Plymouth City Council's "Code of Practice: Control of Pollution & Noise from Demolition &

    Construction Sites" ie:

    PLY-EC--ABG-0000004-P00000000000-01-EC-11 pc 180612.docx Page 20

  • Monday to Friday 8am - 6pm Saturday 8.30am - 1pm No Sunday, Bank holiday or Public holiday working

    Should work be required outside of these hours prior permission must be sought from the local

    authority including details of any noise that may result from the activities.

    Construction site noise has the potential to impact upon the current amenity of local residents.

    The EIA has identified the following properties as sensitive receptors to noise and vibration:

    C1: 25 36 Talbot Gardens C2: 1-12 Talbot Gardens C3: 13-18 Savage Road C4: 471 Wolseley Road C5: 21 Hamoaze Avenue

    The locations of these receptors in relation to the site are shown in attachment 11.

    Good relations with people living and working in the vicinity of site operations are of

    paramount importance. Early establishment and maintenance of these relations throughout

    the carrying out of site operations will contribute towards allaying peoples fears. Good

    relations can be developed by keeping people informed of progress and by treating complaints

    fairly and expeditiously.

    Noise can also interfere with working efficiency of site workers by inducing stress, by

    disturbing concentration and by increasing accident risk. Effects of noise on persons on site

    are similar to the effects on nearby residents, and the benefits of good control measures will

    apply equally on and off site.

    Noise Monitoring Programme

    Noise levels will be monitored at the sensitive locations nearest to site during the main

    construction works in accordance with a Noise Monitoring Plan to be agreed with the LPA in

    accordance with the requirements of the S106 Agreement. The noise monitoring programme

    will be undertaken by suitably qualified specialist consultants. All noise level monitoring

    equipment used will be well maintained and calibrated in accordance with manufacturers

    guidance. Logs of all noise monitoring will be kept within the site files and will be made readily

    available for inspection. The following will be noted at each identified sensitive receptor when

    noise monitoring is being undertaken.

    PLY-EC--ABG-0000004-P00000000000-01-EC-11 pc 180612.docx Page 21

  • Time Weather conditions and wind direction Location of monitoring Background noise level LAeq dB reading over the relevant time period

    All results will be monitored against the predicted noise levels detailed within the Acoustic

    Technical Note dated 28-7-11 in compliance with planning condition 19. Where noise levels

    from any activities are outside of the predicted levels the LPA will be informed immediately

    and alternative or additional mitigation methodology will be investigated and implemented.

    Where any noise complaints are received, these will be thoroughly investigated by the site

    management in accordance with the Complaints Protocol (Planning Condition 56) and actions

    implemented to ensure repetition of the issues are avoided.

    Site Investigation and Assessment

    Planning condition 19 requires compliance with the construction noise levels predicted in the

    Acoustic Technical Note dated 28-7-11 which provides a technical assessment of the

    predicted noise levels from the various construction phases in comparison with the 10 hour

    period acceptable noise levels given in the PCC Code of Construction Practice. The mitigation

    detailed in this document is intended to reduce the construction noise to the predicted levels in

    the assessment.

    Noise Control Measures

    A number of control measures will be implemented at the site to minimise noise. These

    measures are developed from current best practice and the BRE Pollution control Guide: Part

    1 Pre-project planning and effective management. In particular the following control

    measures will be applied;

    Acoustic barriers for static activities will be used where necessary and practicable. The extent to which this can be done depends on the nature and mode of operation

    of the machines to be enclosed and the ventilation requirements, in particular and

    where practicable, acoustic barriers shall be provided when working in the vicinity

    of properties on Talbot Gardens,. This will provide additional mitigation for the

    short-term significant construction noise effects at these properties.

    PLY-EC--ABG-0000004-P00000000000-01-EC-11 pc 180612.docx Page 22

  • A permanent acoustic barrier is to be installed along the new access road providing mitigation for residents off Wolseley Road Hamoaze and Harbour Avenue.

    All construction plant and equipment shall comply with EU noise emission limits. All vehicles and mechanical plant used for the purpose of the works shall be fitted

    with effective exhaust silencers.

    Selection of inherently quiet plant. All major compressors, generators etc. shall be sound reduced models fitted with

    properly lined and sealed acoustic covers which shall be kept closed whenever the

    machines are in use and all ancillary pneumatic percussive tools shall be fitted with

    silencers of the type recommended by the manufacturers.

    Machines in intermittent use shall be shut down in the intervening periods between works or throttled down to a minimum.

    Materials shall be delivered during normal site working hours. All ancillary plant such as generators, compressors and pumps shall be positioned

    so as to cause minimum noise disturbance, i.e. furthest from receptors or if

    necessary, behind acoustic enclosures and /or shielding. Where possible, loading

    and unloading will also be carried out away from such areas,

    Constant monitoring and review of operations Monitoring of feedback from local residents during site activities Site training and awareness for all site personnel with regard to behaviour on site to

    minimise nuisance and engender a considerate approach.

    Modification of existing plant and equipment. Noise from existing plant and equipment can often be modified at source if necessary or improved sound

    reduction methods can be applied,

    Maintenance: Regular and effective maintenance by trained personnel is essential and will do much to reduce noise from machinery. Increases in plant noise are often

    indicative of future mechanical failure. Regular maintenance will form part of an

    effective housekeeping management programme.

    The hours of operation of all plant and vehicles will be limited to the normal site working hours and any use of equipment outside of these hours will be avoided,

    The drop heights will be minimised as much as possible, No plant or machinery will be left running unnecessarily. Plant and equipment such as flatbed lorries, skips and chutes will be lined where

    possible with noise attenuating materials,

    Materials will be handled as carefully as possible when loading lorries and skips to minimise noise,

    Queuing of vehicles wanting to enter the site will be minimised and a policy relating to this will be clearly set out in the site rules,

    PLY-EC--ABG-0000004-P00000000000-01-EC-11 pc 180612.docx Page 23

  • Whilst reversing alarms do present audible impact their necessity is a reflection of the high risk

    associated with reversing vehicles. They must be distinct to ensure they are audible above

    background noise. Despite their need, mitigation can be introduced to prevent nuisance to

    residents. The site layout will introduce and maintain one-way vehicle movements with

    unloading areas and lay-bys to prevent the need for vehicles to reverse. Any reversing areas

    needed or introduced will be located away from sensitive receptors. Pre-established reversing

    areas will also allow additional acoustic barriers to be introduced to provide further mitigation.

    All practicable additional measures will be taken to minimise nuisance from reversing alarms

    Project Specific Elements

    The scale of the preliminary works, (Stage 1), is minor in comparison to the main construction

    works (Stage 2). Stage 1 provides the enabling packages to ensure the Main Construction

    works can be undertaken without logistical restrictions.

    Stage 1 comprises;

    Wolseley Road junction improvements The junction improvements involve minor road-works including traffic island

    modifications, new traffic signals and resurfacing.

    Access road from Camels Head RN4 car-park to the main construction site Security Fencing Bull Point access road Erection of Acoustic Barriers Setting up of the main site establishment Further site investigation works on the main construction site (including relocation

    of exiting stockpiles and earthworks to facilitate the works) and access road bridge

    areas.

    These elements will incorporate small scale earthworks. The fence will be erected manually

    without the need for craneage.

    All sensitive receptors are a consideration during these works. However as a result of the

    scale of the operations required the nuisance potential is reduced with smaller scale plant,

    smaller work areas and a reduced frequency/duration of relevant activities.

    The project will incorporate the following major elements of construction during the Main

    Construction Works;

    PLY-EC--ABG-0000004-P00000000000-01-EC-11 pc 180612.docx Page 24

  • Earthworks and Excavations (Main construction months 1&2)

    Fully detailed planning will use suitable methodology to ensure noise impacts are minimised

    using the appropriate mitigation methods selected from those outlined above.

    Rotary Bored Piling (Main construction months 2 to 8)

    Piling activities have the potential to create the most significant noise impact. Three piling rigs

    will be in use simultaneously but in different areas of the site and this was taken into account

    in the noise predictions made in the Acoustic Technical Note dated 28-7-11. Tthe trial piling

    operations provided further practical assessment of the potential noise levels that may be

    encountered. Whilst the resultant noise levels recorded were generally below those predicted

    in the test piling planning application further lessons were also learned. The element of the

    piling activity resulting in the highest level of noise was the cleaning of the drill string when

    drilling debris was shaken from the drill string. Significant improvements will be made with a

    mechanical application to clear the drill string upon extraction without the need for the vigorous

    shaking witnessed during the trial piling works thereby reducing this element of noise

    generation.

    Consideration was given to restricting the daily hours for piling operations however since there

    is a fixed number of piles that have to be installed this simply results in a corresponding

    extension to the total duration of the piling and construction period overall and has

    consequently been discounted.

    Reinforced Concrete Construction (Main construction months 2 to 13)

    Fully detailed planning will use suitable methodology to ensure noise impacts are minimised

    using the appropriate mitigation methods selected from those outlined above.

    Steelwork and Cladding Erection (Main construction months 14 to 21)

    Fully detailed planning will consider suitable methodology to ensure noise impacts minimised

    using the appropriate range of mitigation methods from those outlined above.

    Reinforced Concrete Construction and Steelwork and Cladding Erection activities will be

    planned so that wherever possible walls and structures closest to the sensitive receptors will

    be constructed first so as to provide acoustic barriers for the subsequent construction

    activities.

    PLY-EC--ABG-0000004-P00000000000-01-EC-11 pc 180612.docx Page 25

  • Construction traffic (throughout the construction period) - Sensitive residential receptors have

    been identified as the properties on Wolseley Road, Weston Mill Drive and the Weston Mill

    Community Primary School. The noise levels in these locations are anticipated to be

    increased by less than 1dB(A) and the risk is assessed as negligible. The acoustic barriers

    that will be erected along the new access road will provide mitigation to receptors in the

    Hamoaze Avenue area for construction traffic accessing the site.

    PLY-EC--ABG-0000004-P00000000000-01-EC-11 pc 180612.docx Page 26

  • 4.4 Vibration

    Initial assessments undertaken during the environmental impact assessment indicated that the

    works should not pose any significant risks in relation to vibration. However, if it becomes

    apparent that vibration may give rise to an environmental impact a full investigation shall be

    undertaken by the site manager using where necessary external specialist consultants to carry

    out monitoring at the receptor locations.

    Best practice techniques shall be utilised at all times to minimise vibration from construction

    activities. Speeds will be limited to 5 mph on un-surfaced site roads and 10 mph on properly

    surfaced and maintained site roads.

    Any complaints relating to vibration disturbance will be fully investigated by the site

    management team in line with the Complaints Protocol (Planning Condition 56).

    4.5 Light Disturbance

    It will be necessary particularly during darker months to light the construction site and office

    complex and there is the potential for poorly aimed or controlled lighting to intrude or irritate

    local residents.

    Possible sources of nuisance are

    Light trespass light spilling beyond the boundary of the property on which a light is located, sometimes shining through windows and curtains.

    Glare the uncomfortable brightness of a light source when viewed against a darker background

    The major mitigating factor is the project working hours. (0800-1800, Monday to Friday), this

    will prevent the more severe element of intrusion, ie sleep deprivation, being realised.

    Due to the location of properties nearby to the site, consideration shall be given to the location

    and angle of site lighting to ensure minimum potential for disturbance to local residents. The

    sensitive receptors are those nearest to the site namely;

    C1: 25 36 Talbot Gardens

    PLY-EC--ABG-0000004-P00000000000-01-EC-11 pc 180612.docx Page 27

  • C2: 1-12 Talbot Gardens

    The following mitigation and best practice will be implemented

    Lights will where practicable, be positioned facing away from residential properties, however adequate lighting of working areas is an essential safety consideration

    and where this is not possible lighting units will be placed in such a way as to pose

    minimal risk of light disturbance. Unless health and safety requirements dictate

    otherwise, no lighting shall face towards any property identified as a sensitive

    receptor.

    Lighting will be directed towards the site activity so as to avoid the possibility of any lights shining directly onto nearby residential properties

    Lighting will be suitable for the application Unnecessary lighting will be removed Lights will be switched off when they are not needed; this will include periods

    outside of normal site working hours.

    Any security lighting will be kept to a minimum at all times and powered by mains supply.

    Checks will be made each evening to ensure no lights are left on in error

    Any complaints relating to light disturbance will be fully investigated by the site management

    team in line with the Complaints Protocol (Planning Condition 56).

    4.6 Heritage and Archaeology

    Initial assessments in the environmental impact assessment do not anticipate that there are

    any archaeologically sensitive areas within the site boundaries. However, the following

    procedures shall be followed in the event of such a find or discovery:

    Immediately stop works in the area of the find Protect the find and the area surrounding by fencing/blocking off and immediately

    contact the Site Manager

    Contact an archaeologist and obtain advice on how to proceed All significant finds must be reported to the County Archaeologist

    The County Archaeologist in charge will be contacted by the site management. The contact

    telephone number is: 01752 305433/304397.

    PLY-EC--ABG-0000004-P00000000000-01-EC-11 pc 180612.docx Page 28

  • 4.7 Waste Management

    The site will implement a Site Waste Management Plan (SWMP) which describes the

    procedures for management of waste arising from the construction activities. The SWMP shall

    comply with the Site Waste Management Plans Regulations 2008.

    The project shall utilise the BRE SMARTWaste online tool as its method of meeting the Site

    Waste Management Plans Regulations and recording the movements of wastes from the site.

    4.8 Water

    A stream known as Weston Mill Creek and a small tributary known as Barne Brake are located

    in close proximity to the site boundaries which discharge into Weston Mill Lake with the tidal

    range extending upstream beyond the site and it is essential that no contaminants enter this

    water course.

    Betterment of the aquatic ecological environment shall be achieved by removal of a disused

    culvert with footway over the Barne Brake. The creek bed shall be returned to its natural state

    and an extensive clean-up of the rest of the creek between Wolseley Road and the site shall

    be completed.

    Following this a schedule of marine litter monitoring and removal shall be implemented in

    accordance with the scheme agreed with the LPA in accordance with the planning conditions.

    Mitigation

    The following mitigation measures shall be employed:

    All necessary consents shall be applied for prior to commencement of works e.g. Land Drainage Consent shall be requested from the Environment Agency under the Land

    Drainage Act of 1991.

    The design of the new development has been significantly influenced by the need to ensure protection of the water environment, for example, the span of the new bridge

    shall keep the new abutments clear of the water.

    The existing sheet pile abutments shall be extended, as well as new abutments constructed so that any loose material cannot enter the watercourse.

    The excavations shall be dewatered as necessary and all pumped water shall be discharged through a series of Siltbuster settlement tanks before it is allowed to enter

    the stream.

    PLY-EC--ABG-0000004-P00000000000-01-EC-11 pc 180612.docx Page 29

  • Spill kits shall be made available, and site operatives trained in their use, to deal with any spillages of materials likely to contaminate the watercourses. All spill kits shall be

    fully stocked at all times and an inventory of equipment within the container shall be

    clearly displayed on the lid.

    Due care and attention shall be given to the prevention of surface run-off. For example, stockpiling of materials within the vicinity of the watercourses shall be

    discouraged. Where stockpiles have to be located in the vicinity of a watercourse a 7

    m buffer strip shall be in place to reduce pollution risks.

    A temporary swale shall be installed along the eastern side of the site, into which runoff can be directed to reduce silt and suspended solids before discharge into the

    watercourse.

    The positioning of fuel storage tanks and other potentially polluting materials and maintenance/refuelling facilities shall be on areas of hard standing with dedicated

    drainage systems. Stored materials on site shall be checked regularly for containment

    integrity (both primary and secondary), quantity stored and security of storage.

    Monitoring

    Monitoring shall be as follows:

    Short term surveillance monitoring shall be undertaken in advance of construction in order to establish a baseline. The short term surveillance monitoring shall include

    specific water quality monitoring for shallow groundwater and surface water and

    assessment of existing Water Framework Directive data regarding the ecological

    status of the watercourse.

    Further surveillance monitoring shall then be undertaken during construction. Regular weekly monitoring and water sampling shall be undertaken at specific points, these

    inspections shall include as a minimum visual reference, turbidity and pH levels.

    In addition to this, during the more environmentally risky operations such as piling or concrete placement, the stream shall be continually visually monitored for turbidity and

    any impending risk of contamination. Plant maintenance checks shall also be

    increased in frequency during these operations.

    In periods of heavy rainfall or excessive vehicle movements within the vicinity, monitoring shall be increased to reduce risks of pollution incidents.

    Construction of concrete structures during the construction phase shall be monitored to prevent associated contaminated material entering any watercourses. Pre-cast

    work or permanent formwork shall be used where possible to reduce the amount of in-

    situ concreting required adjacent to and above the watercourses. Washing out of

    concrete wagons or other equipment used in concreting operations shall only be

    PLY-EC--ABG-0000004-P00000000000-01-EC-11 pc 180612.docx Page 30

  • undertaken in designated contained washout areas. These shall be located away from

    all watercourses and drains and shall be impermeable to prevent infiltration to ground.

    Piling activities required for the waste bunker and building foundations may extend down to the Secondary (B) Aquifer (Saltash Formation). A Foundation Works Risk

    Assessment shall be prepared by the Contractor to confirm that the risk of

    contamination of the Secondary Aquifer through the mobilisation of contaminants

    within the made ground is low with the proposed use of rotary bored piles. The risk

    assessment shall be agreed with the Environment Agency.

    Where over pumping is required, the water shall be put through an appropriate sized settlement tank, the flow rate set up shall allow appropriate timescales for settlement.

    If the discharge is still showing as heavily silted, then a Silt buster settlement tank (or

    series of) shall be used with flocculants if appropriate.

    Permission for any dewatering activities shall be sought from the Environment Agency under the terms of the Water Act 2003, well in advance of the dewatering activity

    commencing.

    All records of water monitoring inspections shall be kept on site throughout the duration of the project and be readily available for inspection by the relevant

    authorities.

    4.9 Transportation and Traffic Management

    A Construction Traffic Management Plan (CTMP) shall be implemented on the site. The plan

    shall outline timings of deliveries and routes to be taken by construction vehicles to ensure

    minimal disruption to local residents and businesses. This shall include potential risk for noise

    disturbance as well as minimising additional traffic during peak periods. The CTMP is provided

    as a separate document.

    4.10 Ecological Management

    The existing ecological features could potentially be affected by the proposed construction

    works. However, the initial environmental impact assessment concluded that if appropriate

    mitigation and enhancement activities were to be undertaken then the impacts would not be

    considered significant.

    General Ecological Mitigation

    The following mitigation measures will be employed. Refer also attachments No 1 and 2 -

    Wildlife and Construction Best Practice Guidance. These posters will be prominently displayed

    on the site on notice boards on the site and in site cabins and offices.

    PLY-EC--ABG-0000004-P00000000000-01-EC-11 pc 180612.docx Page 31

  • Dust minimisation methods shall be employed Construction lighting shall be directed away from retained areas of habitat wherever

    possible.

    Security lighting and non-essential lighting shall be fitted with automatic cut-off switches where practicable.

    Pollution prevention controls shall be utilised to reduce the risk of sediment pollution resettling further downstream and potentially smothering benthic habitats (see section

    4.8).

    All tree and vegetation clearance works within the area defined on the Vegetation Clearance Plan dated 1st May 2012 and Drawing No 47031683 300 Rev C shall be carried out under the supervision of an experienced ecologist to prevent disturbance

    to nesting birds and other protected species. Where vegetation clearance is being

    carried out in teams, each team will be accompanied by an experienced ecologist.

    The ecologist will check and observe each 20m sector of vegetation for approximately

    20 minutes prior to clearance works commencing. If an active bird nest is detected at

    any point, works in that sector will immediately cease and an area of 5m radius around

    the nest will be cordoned off and clearly marked using hi-visibility tape and appropriate

    signage to prevent disturbance to nesting birds. Any noisy machinery such as chippers

    will be moved at least 10m away from the location of the nest. Works within the

    cordoned off area where active bird nests have been detected will only proceed once

    an experienced ecologist has confirmed the nests are no longer active.

    As an additional measure, throughout the duration of the proposed tree and vegetation

    clearance works, a falconer will be employed Monday to Friday for at least two hours a

    day to act as a deterrent to birds wishing to nest on site. The falconer will walk a

    continuous transect covering the periphery of the areas to be cleared as shown on the

    Vegetation Clearance Plan dated 1st May 2012 and Drawing No 47031683 300 Rev

    C any other areas where it is necessary to deter nesting birds..

    Where any unexpected species are identified by any personnel on site, all works within that area shall cease immediately. Site management shall be immediately

    informed and they shall contact the project ecologist. No further work may take place

    within that area until permission has been given by the project ecologist and site

    management.

    The contact details for the Project Ecologist are Paul Gregory or Melanie Pritchard; URS Infrastructure & Environment UK Limited, Mayflower House, Armada Way,

    Plymouth, PL1 1LD, United Kingdom telephone 01752 676700

    PLY-EC--ABG-0000004-P00000000000-01-EC-11 pc 180612.docx Page 32

  • Bats

    The site is considered to be of negligible conservation value for roosting bats and low

    (parish/neighbourhood) value for foraging/feeding and/or commuting habitat for bats.

    Reptiles

    Reptiles are protected creatures making it an offence to intentionally and recklessly kill, injure

    or take from existing habitats. A reptile survey has been undertaken and a translocation

    habitat area identified and a reptile barrier has been installed separating the translocation area

    from the site works. The reptile barrier will be maintained throughout the duration of the

    project. A series of trapping visits was commenced in 2011 and 48 of the 60 required visits

    have been carried out prior to the temperature dropping and the reptiles going into hibernation. As reptiles were still being trapped up to hibernation, the site cannot be declared clear until the

    remaining visits have been concluded.

    It is planned to re-commence the trapping visits in April 2012 providing the ground temperature

    is conducive for reptiles to come out of hibernation. It is anticipated that the remaining 12 visits

    will take approximately 2 weeks

    Under current guidance / legislation / best practice a period of 5 clear visits must be achieved

    in order to demonstrate that all practicable efforts have been made to trap a significant number

    of reptiles, if they are present on site. However in order that construction works can continue in

    the event that the conditions have not been suitable to carry out the remaining visits, the

    project ecologist has confirmed the following:-

    The largely flat, well compacted, barren areas of the site would not be conducive for reptile habitat; therefore, works can be carried out on these areas.

    The stockpiles of crushed aggregate located on the Eastern side of the site are not suitable for reptile habitat; therefore, this material can be excavated and used.

    The stockpiles of crushed and un-crushed aggregate located on the Western side of the site could be suitable habitat; therefore, these areas should be avoided until reptile

    clearance has been completed.

    The earth bund around the site may contain reptiles and should be avoided. However, once the conditions are suitable, these areas could be cleared or excavated under a

    watching brief by the ecologist in a controlled manner.

    The side slopes and lower area around the site (MOD security patrol zone adjacent to the security fence) may be reptile habitats and should be avoided. However, once the

    PLY-EC--ABG-0000004-P00000000000-01-EC-11 pc 180612.docx Page 33

  • conditions are suitable, these areas could be cleared, excavated or filled under a

    watching brief by the ecologist in a controlled manner.

    Table Top Mountain is not suitable habitat; therefore, the planned mobilisation works i.e. site facilities set-up, installation of temporary security fence, repositioning MOD

    CCTV masts and cameras etc can be carried out without further ecologist supervision.

    Bull Point Access Road is not ideal reptile habitat but could suit nesting birds, therefore, this area should be cleared under a watching brief as soon as possible to

    mitigate any risk.

    New Access Road is not reptile habitat but has areas suitable for nesting birds and therefore should be trimmed / coppiced / cleared as soon as possible under a

    watching brief to mitigate any risk.

    Planned early works or the main works should not be adversely affected by the possibility that reptiles are still present on site as the risk can be managed and

    mitigated with early clearance of suitable habitats and / or works being undertaken

    under a watching brief.

    Briefings about the reptiles on site shall be included as part of the induction process. Regular toolbox talks shall be held prior to any construction activities commencing, re-

    iterating the ecological issues.

    Species identification training and posters shall be available on site to assist all site personnel with identification (See attachments 1 and 2).

    In the event of the discovery of any reptiles during the construction works, immediate

    surrounding works shall cease. The site foreman shall contact the site manager, who shall in

    turn contact the ecologist. No works may commence within the area until an ecologist has

    given permission.

    Flora

    Site preparation works includes the levelling of earth mounds and clearance of areas of scrub

    and trees using specialist contractors.

    Individual trees and tree groups not requiring removal shall be protected in accordance with

    BS5837:2005 Trees in Relation to Construction. A Tree Protection Zone shall be established

    within which no work shall take place without the prior authorisation of a suitably qualified

    arboricultural consultant. Clear signage shall be placed on all fencing surrounding the

    protected tree area. The fencing shall be regularly checked and any areas found to be of poor

    quality or damaged, shall be repaired or replaced immediately. All site personnel shall be

    PLY-EC--ABG-0000004-P00000000000-01-EC-11 pc 180612.docx Page 34

  • made aware of which areas are not to be entered within the Induction Programme and this

    shall be reinforced throughout the duration of the works through regular toolbox talks.

    The existing Blackies Wood habitat shall be managed to promote the wildlife which already

    exists.

    Landscape design shall incorporate native planted woodland and shrubs that shall represent

    the existing landscape character; the creation of wildlife corridors boundaries; the

    reinstatement of an existing ditch to connect to a newly created freshwater pond; areas of

    open species-rich neutral grassland and bird, bat and insect boxes.

    The Japanese knotweed within Blackies Wood and on the slopes of Table Top Mountain

    (outside the site boundary but adjacent to the construction compound) shall be treated and

    eradicated to halt the spread of this invasive species.

    4.11 Land contamination

    Ground investigations at the site have not encountered significant contamination of either soils

    or groundwater and the ground has been classified as suitable for commercial and industrial

    use and it is intended that all excavated material shall be re-used on the site.

    There is a potential risk to off site receptors from emissions of contaminated dust but the

    Environmental Statement identified that the risks from contaminated dusts are deemed to be

    low due to the lack of significant contamination within the site soils and will be further

    controlled with good working practices and the implementation of dust control measures

    during the construction works as described in Section 4.2 above.

    During the site induction all personnel shall be made aware of their responsibility to be vigilant

    with regards to identification of potential soil contamination. Key personnel in this respect are

    ground workers, machine operators and their banksman. Training will be provided to

    supervisors to provide the necessary awareness to identify areas of contamination.. They will

    report any suspicions of contaminated soil or groundwater to the site management.

    If unforeseen contamination is encountered during site works, the specific element of work will

    be suspended and the area will be segregated. The result of any notification will also be

    reported to the LPA and the Environment Agency, remediation options shall be considered

    following assessment and identification of contaminants. Any remediation process shall

    comply with all legislative and best practice guidance.

    PLY-EC--ABG-0000004-P00000000000-01-EC-11 pc 180612.docx Page 35

  • Should any excavated soils need to be removed from site for disposal to a landfill the soils

    shall undergo Waste Acceptance Criteria (WAC) testing in order to correctly classify the

    material in terms of waste disposal. The results of the WAC testing shall be supplied to the

    chosen waste acceptor at an early stage of the process in order to locate a suitable landfill

    site.

    Excavations and Stockpiles

    All stockpiled material will be located away from sensitive receptors with suitable bunds and

    /or barriers to prevent cross contamination as a result of run-off.

    Deep excavations always pose a potential hazard with regard to encountering contaminated

    materials or the build up of hazardous gases. Methane was detected at depth in one location

    on the site during the ground investigation but no evidence of elevated levels were detected

    elsewhere across the site.

    Strict Health and safety precautions will be implemented for all excavations and this may

    include the use of gas monitors should the need be defined from a thorough risk assessment

    of the activity being undertaken. The risk assessment will identify the necessary actions to be

    taken in the event of activation of any gas alarms.

    4.12 Resource use

    MVV shall ensure where practicable, that the use of recycled or sustainable materials shall be

    utilised. All wood should be obtained from a certified sustainable source, such as FSC.

    MVV shall ensure that up to fifteen per cent (15%) and at least a minimum of ten per cent

    (10%) of total material value of the civil construction and building works derives from reused

    and recycled content in new build. Appropriate opportunities shall be accepted to exceed this

    figure without increasing the cost of materials.

    A dedicated area shall be maintained for storage of all materials and due care and appropriate

    handling shall be undertaken at all times to reduce any risk of damages and wastage.

    Packaging of items should not be removed until required, to ensure maximum potential for

    returning of unused goods.

    As much office waste as possible shall be sent for recycling and also strategies are to be put

    in place to ensure minimal wastage on site, for example avoiding unnecessary printing etc.

    Where possible, use of local suppliers shall be considered to reduce transportation costs and

    maintain a low carbon footprint.

    PLY-EC--ABG-0000004-P00000000000-01-EC-11 pc 180612.docx Page 36

  • Waste disposal options shall be investigated to ensure minimal transportation requirements

    where possible. Onsite crushing and reuse of materials shall be incorporated into the project.

    This shall aid reduction in waste going to landfill as well as minimising vehicular movements

    on the local road systems.

    4.13 Energy Consumption/Monitoring

    Switch it Off schemes and other energy saving campaigns shall be implemented on site to

    encourage all personnel to consider their carbon footprint. Use of car sharing and buses shall

    be encouraged as outlined in the CTMP. Posters shall be clearly displayed within the site

    offices to ensure all personnel are aware of the CTMP requirements. This shall also be

    covered within the site induction and regular toolbox talks held relating to the subject.

    4.14 Water usage

    Within site accommodation taps shall be switched off when not in use and all staff shall be

    made aware of water saving techniques. Every effort to ensure reduction in water use shall be

    implemented where available.

    4.15 Visual Amenity

    The environmental impact assessment process identified that the construction process posed

    a potentially short term impact. The following mitigation measures shall be deployed to

    minimise the impacts;

    The proposed Devon hedge bank and avenue planting are to be implemented at the earliest opportunity upon commencement of construction. This is to allow maximum

    time for establishment prior to completion and operation.

    Visual issues should be considered in deciding upon the need for lighting and its location and specification. Temporary lighting should use suitable lamps with flat glass

    lanterns and cut-off beams in order to minimise light spillage.

    Provision by the contractors of records of all pesticide / herbicide use. Provision by the landscape contractor of evidence that planting complies with

    provenance requirements as applicable.

    Weed control in general and actions taken to ensure that hazardous weeds in the area are destroyed and not spread (e.g. Japanese knotweed).

    Handling of soils in accordance with British Standard (BS) 3822:2007 Topsoil; and locating, where possible, temporary materials storage mounds in areas that would

    PLY-EC--ABG-0000004-P00000000000-01-EC-11 pc 180612.docx Page 37

  • PLY-EC--ABG-0000004-P00000000000-01-EC-11 pc 180612.docx Page 38

    mitigate views of the proposed development for adjacent receptors and without

    damaging the ecological resource.

    Ensure that the site boundaries are kept clean and tidy at all times, including local roads

    The site shall be securely fenced and the fencing shall be well maintained and kept free of attachments and non-site specific posters.

    Damaged or unsightly fencing must be repaired or replaced as soon as possible.

    4.16 Vermin

    Maintenance of a clean and tidy site including vermin control is essential. An appropriate pest

    control measure will be adopted as necessary. The site has already been subject to a pest

    control survey and baiting programme and control measures shall continue throughout the

    construction phase including;

    Correct and satisfactory stopping and sealing of all disused drains and sewers where applicable

    Prevention of accumulation of refuse and putrescent materials Ensuring any on-site catering facilities pay careful attention to food delivery, handling

    and storage and disposal of any food waste.

    A baiting and survey programme was commenced on the 12 October 2011 and a survey

    report with any recommendations for further actions will be made available prior to

    commencement of the main construction works.

  • PLY-EC--ABG-0000004-P00000000000-01-EC-11 pc 180612.docx

    Attachment 1 - Wildlife & Construction Best Practice Guidance Poster

  • Attachment 2 - Wildlife & Construction Best Practice Guidance Poster

    PLY-EC--ABG-0000004-P00000000000-01-EC-11 pc 180612.docx

  • PLY-EC--ABG-0000004-P00000000000-01-EC-11 pc 040512.docx

    Attachment 3 Weekly checklist

    The weekly checklist shall be used to ensure that the regular environmental monitoring activities are carried out. This checklist is intended as a summary record of the site environmental conditions and monitoring activities and of any environmental incidents.

    The checklist will be developed as necessary to include any further environmental impacts that may be identified as construction progresses and individual incidents will be further documented as and when necessary to fully record all details and actions taken.

  • EfW CHP Facility CEMP: Weekly checklist

    Reporting period: Week beginning:

    Main Sub Contractors on site: Kier BBS Imtech LAB SAR Sutco

    Short description of work carried out within reporting period: Weather conditions Environmental incidents in the reporting period: Weekly Activities: (to be completed by Environmental Manager). Name Date Note

    Watercourse/discharge monitoring Carried out according to WMP

    Spill kits checked Completeness of inventory

    Reptile barrier Checked for integrity

    Noise monitoring Carried out according to NMP

    Tree protection Checked for integrity

    Site boundary Cleanliness checked according to LMP

    Fuel storage checked (containment integrity, storage quantity)

    Dust situation (Requirement for anti-dust measures)

    Vehicles (Is everybody aware of vehicle coverage needs? Wheel wash in good order?)

    Environmental toolbox talks held (indicate topics as note!)

    Lighting Check location and direction

    Environmental training requirements identified any requirements and arrange.

    4 3 2 Second issue 05/10/2012 JW 1 First issue 02/01/2012 Ham

    Rev. Changes Created EC Checked EC Approved MVV Date Name Date Name Date Name

    Rev.: 1 Page 1 of 1

  • Attachment 4 Environmental Risk Assessment & Aspects and Impacts Matrix (civil construction works)

    The majority of the civil construction works will take place before the process equipment installation

    commences. Therefore an initial risk assessment has been prepared for the potential environmental impacts

    of the civil works.

    Additional risk assessments will be prepared for the other construction activities in due course prior to

    commencement of the relevant activity on site.

    PLY-EC--ABG-0000004-P00000000000-01-EC-11 pc 040512.docx

  • Infrastructure & Overseas ENVIRONMENTAL RISK ASSESSMENT ENV01

    Revised C1005 ENV01 Risk Assessment.doc - 1 -

    Contract Name & Number C1005 - Plymouth Activity/Operations All

    Risk Residual Risk

    Environmental Aspect (delete as

    necessary)

    Data Sheet

    (ENV02)

    Potential Environmental

    Impact O +D

    x C Total

    Control Measures

    (add/delete as necessary)

    O +D

    x C Total

    Method Statement /Procedure Number

    Associated Toolbox

    Talk

    DUST Piling Activities

    3 2 8 40 Visual inspection and monitoring Dust sheeting or fencing off activity where possible

    2 1 6 18

    Excavations