1.5M CONFIGURATIONBase Pack
2.3M CONFIGURATIONBase Pack + Extension Pack + Outrigger Pack + Toe Board Pack + Horizontal Pack
1.5M CONFIGURATIONBase Pack + Guardrail Pack + Toe Board Pack
3.4M CONFIGURATIONBase Pack + Extension Pack + Outrigger Pack + Guardrail Pack + Toe Board Pack
ASSEMBLY MANUAL
READ THESE INSTRUCTIONS COMPLETELY BEFORE STARTING WORKWARNING Failure to comply with all instructions may result in serious injury. Before assembling this product, identify all components. If any components are missing or damaged, return to the place of purchase. Do not substitute any components.
ATTENTION This product is to be stored in a clean dry location. It is not designed to be left out and exposed to the elements for extended periods of time.
1
SCAN TO VIEWASSEMBLYVIDEO
1. Unfold Base Pack2. Lock Brace Locks3. Lock Castors
UNLOCKED LOCKED
UNLOCKED LOCKED
4. Install Platform
1. Install Guardrail End Frames2. Engage Spring Clips3. Install Horizontal Braces4. Install End Toe Boards5. Install Side Toe Boards
ENGAGED
Install Horizontal Braces on theinside of the Standards.
1.5m Configuration Erection(Base Pack)
1.5m Configuration Erection(Base Pack, Guardrail Pack & Toe Board Pack)
1.5M CONFIGURATIONBase Pack
1.5M CONFIGURATIONBase Pack + Guardrail Pack + Toe Board Pack
ENGAGE SPRING CLIPS
INSTALL HORIZONTAL BRACES ON THE INSIDE OF THE STANDARDS
1. Unfold Base Pack2. Lock Brace Locks3. Lock Castors
UNLOCKED LOCKED
UNLOCKED LOCKED
4. Install Platform
1. Install Guardrail End Frames2. Engage Spring Clips3. Install Horizontal Braces4. Install End Toe Boards5. Install Side Toe Boards
ENGAGED
Install Horizontal Braces on theinside of the Standards.
1.5m Configuration Assembly(Base Pack)
1.5m Configuration Assembly(Base Pack, Guardrail Pack & Toe Board Pack)
1. Unfold Base Pack2. Lock Brace Locks3. Lock Castors
UNLOCKED LOCKED
UNLOCKED LOCKED
4. Install Platform
1. Install Guardrail End Frames2. Engage Spring Clips3. Install Horizontal Braces4. Install End Toe Boards5. Install Side Toe Boards
ENGAGED
Install Horizontal Braces on theinside of the Standards.
1.5m Configuration Assembly(Base Pack)
1.5m Configuration Assembly(Base Pack, Guardrail Pack & Toe Board Pack)
1. Unfold Base Pack2. Lock Brace Locks3. Lock Castors
UNLOCKED LOCKED
UNLOCKED LOCKED
4. Install Platform
1. Install Guardrail End Frames2. Engage Spring Clips3. Install Horizontal Braces4. Install End Toe Boards5. Install Side Toe Boards
ENGAGED
Install Horizontal Braces on theinside of the Standards.
1.5m Configuration Assembly(Base Pack)
1.5m Configuration Assembly(Base Pack, Guardrail Pack & Toe Board Pack)
1. Unfold Base Pack2. Lock Brace Locks3. Lock Castors
UNLOCKED LOCKED
UNLOCKED LOCKED
4. Install Platform
1. Install Guardrail End Frames2. Engage Spring Clips3. Install Horizontal Braces4. Install End Toe Boards5. Install Side Toe Boards
ENGAGED
Install Horizontal Braces on theinside of the Standards.
1.5m Configuration Assembly(Base Pack)
1.5m Configuration Assembly(Base Pack, Guardrail Pack & Toe Board Pack)
UNLOCKED
UNLOCKED
LOCKED
LOCKED
1. Unfold Base Pack2. Lock Brace Locks3. Lock Castors
UNLOCKED LOCKED
UNLOCKED LOCKED
4. Install Platform
1. Install Guardrail End Frames2. Engage Spring Clips3. Install Horizontal Braces4. Install End Toe Boards5. Install Side Toe Boards
ENGAGED
Install Horizontal Braces on theinside of the Standards.
1.5m Configuration Erection(Base Pack)
1.5m Configuration Erection(Base Pack, Guardrail Pack & Toe Board Pack)
1. Unfold Base Pack2. Lock Brace Locks3. Lock Castors
UNLOCKED LOCKED
UNLOCKED LOCKED
4. Install Platform
1. Install Guardrail End Frames2. Engage Spring Clips3. Install Horizontal Braces4. Install End Toe Boards5. Install Side Toe Boards
ENGAGED
Install Horizontal Braces on theinside of the Standards.
1.5m Configuration Erection(Base Pack)
1.5m Configuration Erection(Base Pack, Guardrail Pack & Toe Board Pack)
1. Unfold Base Pack2. Lock Brace Locks3. Lock Castors
UNLOCKED LOCKED
UNLOCKED LOCKED
4. Install Platform
1. Install Guardrail End Frames2. Engage Spring Clips3. Install Horizontal Braces4. Install End Toe Boards5. Install Side Toe Boards
ENGAGED
Install Horizontal Braces on theinside of the Standards.
1.5m Configuration Erection(Base Pack)
1.5m Configuration Erection(Base Pack, Guardrail Pack & Toe Board Pack)
1. Unfold Base Pack2. Lock Brace Locks3. Lock Castors
UNLOCKED LOCKED
UNLOCKED LOCKED
4. Install Platform
1. Install Guardrail End Frames2. Engage Spring Clips3. Install Horizontal Braces4. Install End Toe Boards5. Install Side Toe Boards
ENGAGED
Install Horizontal Braces on theinside of the Standards.
1.5m Configuration Erection(Base Pack)
1.5m Configuration Erection(Base Pack, Guardrail Pack & Toe Board Pack)
2
1. Unfold Base Pack
2. Lock Brace Locks
3. Lock Castors
4. Install Platform
1. Install Guardrail End Frames
2. Engage Spring Clips
3. Install Horizontal Braces (YELLOW)
4. Install End Toe Boards
5. Install Side Toe Boards
1. Unfold Base Pack2. Lock Brace Locks3. Lock Castors4. Install Lower Platform5. Install Outriggers6. Install Extension End Frames7. Engage Spring Clips
3055
307
8
8. Install Lower Diagonal Brace9. Install Ladder10. Install Upper Platform
11. Install Horizontal Braces12. Install Upper Diagonal Brace13. Install End Toe Boards14. Install Side Toe Boards
2.3m Configuration Assembly(Base Pack, Extension Pack, Outrigger Pack,
Toe Board Pack & Horizontal Pack)
2.3M CONFIGURATIONBase Pack + Extension Pack + Outrigger Pack + Toe Board Pack + Horizontal Pack
1. Unfold Base Pack2. Lock Brace Locks3. Lock Castors4. Install Lower Platform5. Install Outriggers6. Install Extension End Frames7. Engage Spring Clips
3055
307
8
8. Install Lower Diagonal Brace9. Install Ladder10. Install Upper Platform
11. Install Horizontal Braces12. Install Upper Diagonal Brace13. Install End Toe Boards14. Install Side Toe Boards
2.3m Configuration Assembly(Base Pack, Extension Pack, Outrigger Pack,
Toe Board Pack & Horizontal Pack)
1. Unfold Base Pack2. Lock Brace Locks3. Lock Castors4. Install Lower Platform5. Install Outriggers6. Install Extension End Frames7. Engage Spring Clips
3055
307
8
8. Install Lower Diagonal Brace9. Install Ladder10. Install Upper Platform
11. Install Horizontal Braces12. Install Upper Diagonal Brace13. Install End Toe Boards14. Install Side Toe Boards
2.3m Configuration Assembly(Base Pack, Extension Pack, Outrigger Pack,
Toe Board Pack & Horizontal Pack)
1. Unfold Base Pack2. Lock Brace Locks3. Lock Castors4. Install Lower Platform5. Install Outriggers6. Install Extension End Frames7. Engage Spring Clips
3055
307
8
8. Install Lower Diagonal Brace9. Install Ladder10. Install Upper Platform
11. Install Horizontal Braces12. Install Upper Diagonal Brace13. Install End Toe Boards14. Install Side Toe Boards
2.3m Configuration Assembly(Base Pack, Extension Pack, Outrigger Pack,
Toe Board Pack & Horizontal Pack)
3
1. Unfold Base Pack
2. Lock Brace Locks
3. Lock Castors
4. Install Lower Platform
5. Install Outriggers
6. Install Extension End Frames
7. Engage Spring Clips
8. Install Lower Diagonal Brace (BLUE)
9. Install Ladder
10. Install Upper Platform
11. Install Horizontal Braces (YELLOW)
12. Install Upper Diagonal Brace (BLUE)
13. Install End Toe Boards
14. Install Side Toe Boards
3.4M CONFIGURATIONBase Pack + Extension Pack + Outrigger Pack + Guardrail Pack + Toe Board Pack
1. Unfold Base Pack2. Lock Brace Locks3. Lock Castors4. Install Lower Platform5. Install Outriggers6. Install Extension End Frames7. Engage Spring Clips
3055
307
8
8. Install Diagonal Braces9. Install Guardrail End Frames10. Engage Spring Clips11. Install Ladder12. Install Upper Platform
13. Install Horizontal Braces14. Install End Toe Boards15. Install Side Toe Boards
3.4m Configuration Assembly(Base Pack, Extension Pack, Outrigger Pack,
Guardrail Pack & Toe Board Pack)
1. Unfold Base Pack2. Lock Brace Locks3. Lock Castors4. Install Lower Platform5. Install Outriggers6. Install Extension End Frames7. Engage Spring Clips
3055
307
8
8. Install Diagonal Braces9. Install Guardrail End Frames10. Engage Spring Clips11. Install Ladder12. Install Upper Platform
13. Install Horizontal Braces14. Install End Toe Boards15. Install Side Toe Boards
3.4m Configuration Assembly(Base Pack, Extension Pack, Outrigger Pack,
Guardrail Pack & Toe Board Pack)
1. Unfold Base Pack2. Lock Brace Locks3. Lock Castors4. Install Lower Platform5. Install Outriggers6. Install Extension End Frames7. Engage Spring Clips
3055
307
8
8. Install Diagonal Braces9. Install Guardrail End Frames10. Engage Spring Clips11. Install Ladder12. Install Upper Platform
13. Install Horizontal Braces14. Install End Toe Boards15. Install Side Toe Boards
3.4m Configuration Assembly(Base Pack, Extension Pack, Outrigger Pack,
Guardrail Pack & Toe Board Pack)
1. Unfold Base Pack2. Lock Brace Locks3. Lock Castors4. Install Lower Platform5. Install Outriggers6. Install Extension End Frames7. Engage Spring Clips
3055
307
8
8. Install Diagonal Braces9. Install Guardrail End Frames10. Engage Spring Clips11. Install Ladder12. Install Upper Platform
13. Install Horizontal Braces14. Install End Toe Boards15. Install Side Toe Boards
3.4m Configuration Assembly(Base Pack, Extension Pack, Outrigger Pack,
Guardrail Pack & Toe Board Pack)
Werner Co Australia reserves the right to alter product specifications at any time without notice.
©2016 Werner Co. P/N109447-01 Rev A 9/164
1. Unfold Base Pack
2. Lock Brace Locks
3. Lock Castors
4. Install Lower Platform
5. Install Outriggers
6. Install Extension End Frames
7. Engage Spring Clips
8. Install Diagonal Braces (BLUE)
9. Install Guardrail End Frames
10. Engage Spring Clips
11. Install Ladder
12. Install Upper Platform
13. Install Horizontal Braces (YELLOW)
14. Install End Toe Boards
15. Install Side Toe Boards