1050 Grinding and Flotation Circuits Integration and ... · values (JKSimMet, Rosin-Rammler model)...
-
Upload
dangkhuong -
Category
Documents
-
view
259 -
download
17
Transcript of 1050 Grinding and Flotation Circuits Integration and ... · values (JKSimMet, Rosin-Rammler model)...
Grinding and Flotation Circuit Integration and
Optimisation
Kym RungeErico Tabosa
Peter Holtham
© Metso© Metso
Presentation Outline
• Link between Grinding and Flotation
• Bazin Analysis Technique
• 3 Industrial Case Studies
• Conclusions
© Metso© Metso
PTI Optimisation Consulting ServicesStage versus Overall Efficiencies
3
Drill and Blasting‐ Grade Control
‐ Tonnage
Comminution‐ Energy
‐ Particle Size Distribution
‐ Tonnage
Flotation‐ Grade
‐ Recovery
Optimising each stage in isolation may not result in overall process optimisationThe Process Integration and Optimisation (PIO) methodology optimises each stage in the context of the overall operation
© Metso© Metso
A relationship is required linking grinding circuit product size to overall flotation recovery
• Flotation recovery is a strong functionof particle size
• Overall flotation recovery andconcentrate grade tends to improve asthe grind size is reduced
• Finer grinding, however, increasesenergy consumption, processing costsand often limits grinding circuitthroughput
Link Between Grinding and Flotation
0102030405060708090100
Recovery (%
)
Size
Recovery loss dueto poor collision efficiency
Recovery loss due to poorliberation
Metso PTI uses a Bazin analysis technique to predict flotation recovery as a function of grind size
© Metso© Metso
Bazin Analysis AssumptionFundamentals
Bazin et al., 1994
Bazin et al (1994) presented a novel technique for predicting the distribution of metal within a particular grind size distribution
They observed a single relationship between the cumulative percent passing size distribution and cumulative percent passing metal distribution in both laboratory and industrial scale data
© Metso© Metso
Bazin Analysis AssumptionMetso PTI Observations
Bazin assumption holds as long as• Feed ore composition doesn’t significantly change• Fixed grinding circuit design
Case Study 2
Case Study 3
0
10
20
30
40
50
60
70
80
90
100
0 20 40 60 80 100
Cumulative Mass %
Passin
g
Cumulative Copper % Passing
January
February
March
April
June
August
September
October
December
0102030405060708090100
0 50 100
Cumulative Mass %
Passing
Cumulative Copper % Passing
Plant P80=127
Plant P80=139
Plant P80=155
© Metso© Metso
• Alternative feed size distributions are created for different P80values (JKSimMet, Rosin-Rammler model)
• The metal distribution in the feed is predicted for eachalternative feed size distribution
• The metal distributions of the alternative feed size distributionsare inputted into a flotation model to predict recovery
• Flotation modelling can range from a JKSimFloat sized floatability component model to assuming the size versus recovery relationship remains constant
Bazin Analysis TechniqueThree-step process
1. Prediction of the grinding circuit product size distribution
2. Prediction of metal distribution within size distribution
3. Calculation of overall flotation recovery for each feed
© Metso© Metso
Analysis Performed
Copper/Gold circuit – Osborne, AustraliaCase Study 1
• Simultaneous flotation and grindingcircuit surveys
• Mass balancing of sizing and assaydata
• Mineralogical analysis of key streams
• Development of sized grinding andflotation models in JKSimMet andJKSimFloat
© Metso© Metso
Flotation circuit evaluation
0
5
10
15
20
25
30
35
Cop
per D
istr
ibut
ion
(%)
Size Fraction
Tailing
0102030405060708090
100
Cop
per R
ecov
ery
(%)
Size Fraction
Concentrate Tail
FeedRougher
Scavenger 1AScavenger 1B
Scavenger 2
Pyrite RougherPyrite Scavenger
Findings
Copper/Gold flotation circuit – Osborne, AustraliaCase Study 1
© Metso© Metso
Grind Float Optimisation
Findings
Copper/Gold flotation circuit – Osborne, AustraliaCase Study 1
Integrated grinding and flotation modelling can be used to optimise total processrevenue rather than maximise performance in individual process stages
58.5
59.0
59.5
60.0
60.5
61.0
4 5 6 7 8 9 10 11
Nett reven
ue (A
$/t)
Energy consumption (kWhr/t)
240 t/hr265 t/hr290 t/hrBaseline
12000
13000
14000
15000
16000
17000
18000
4 5 6 7 8 9 10 11
Nett reven
ue (A
$/hr)
Energy consumption (kWhr/t)
240 t/hr265 t/hr290 t/hrBaseline
© Metso© Metso
Case Study 2Copper/gold operation – Australia
• Recoveries were being under-predicted by geometallurgical models
• Grinding circuit throughput and P80 had increased over time and wasinversely correlated with recovery
R² = 0.3142
0 50 100 150 200
Copp
er Recov
ery (%
)
P80 (Micron)
Recovery = ‐0.11 P80 + InterceptR² = 0.239
0 50000 100000 150000Co
pper Recov
ery (%)
Dry Tonnes Milled
Recovery = ‐0.11 Solids + Intercept
© Metso© Metso
Case Study 2Copper flotation circuit – Australia
• Site had monthly composite data of product streams, suitable for massbalancing on a size by assay basis
The size‐by‐size recovery remained reasonably constant
0
20
40
60
80
100
0 20 40 60 80 100
Cumulative Mass % Passing
Cumulative Copper % Passing
Plant P80=127 µmPlant P80=139 µmPlant P80=155 µm
Relationship between cumulative mass and metal distribution was similar
© Metso© Metso
Case Study 2Copper flotation circuit – Australia
0
20
40
60
80
100
10 100 1000
Cumulative Mass % Passing
Size (µm)
P80 µm1751571461361271121049889
50 100 150 200
Concen
trate Re
covery
Effective Feed P80 (µm)
Recovery = ‐0.09 P80 + Intercept
Different flotation feed size distributions were created
Bazin analysis predicted a 0.9%drop in copper recovery forevery 10 µm increase in feedP80
- 0.9% in Cu Recovery every 10 µm
Drop in recovery due to grind size
© Metso© Metso
Case Study 3Copper/molybdenum operation
• Metso PTI provided monthly composite data for review with the objectiveof determining opportunities for circuit improvement
• Data suitable for mass balancing on a size by assay basis
Rougher and Scavenger
CleaningFinal Concentrate
Final Tailing
© Metso© Metso
Case Study 3Copper/molybdenum flotation circuit
The size‐by‐size recovery variable in terms of coarse particles
Large variation in amount of ultrafines in feed
© Metso© Metso
Case Study 3Copper/molybdenum flotation circuit
0
10
20
30
40
50
60
70
80
90
100
0 10 20 30 40 50 60 70
Copp
er Rou
ger Re
covery, %
% of Copper in Feed Ultrafine (25µm)
+106um
+150um
+212um
+295um
Coarse particle recovery proportional to ultrafines in feed
© Metso© Metso
Case Study 3Copper/molybdenum flotation circuit
Optimum flotation recoveryat P80 65 µm
Grinding finer drops recovery(higher amount of ‐10 µm)
Excessive ultrafines in feed dropsrecovery by 6%
Drop is primarily due to poorcoarse particle recovery
70
72
74
76
78
80
82
84
86
88
0 20 40 60
Cu Con
centrate Recovery, %
% of Copper in Feed Ultrafine (25µm)
Coarse Particle Recovery Unchanged
Coares Particle Recovery Variable
0
10
20
30
40
50
60
70
80
90
100
2952121501067553453825‐25
Copp
er Recovery, %
Size (micron)
45
40
39
34
29
0
10
20
30
40
50
60
70
80
90
100
2952121501067553453825
Copp
er Recovery, %
Size (micron)
44
40
39
34
29
Step 1
Step 2
Step 3
© Metso© Metso
Limitations of Bazin Analysis
• The Bazin assumption no longer holds if there has been a significant change ingrinding circuit design or ore type. Recalibration is required.
• If regrind is used within a flotation circuit, use of an overall size versus recoveryrelationship for overall flotation recovery prediction is not possible. In thesecases, useful insights of the feed grind size effect can be drawn by performinganalysis over the rougher scavenger section of the circuit.
© Metso© Metso
Conclusions
• Integrated simulation of grinding and flotation circuits can be carried outusing the Bazin assumption. It allows integrated simulation to estimatethe relationship between grind size and flotation circuit performance.Metso PTI has used this approach to:
- Determine the throughput and grind size which optimises total process profitability
- Effect of grind size for use in geometallurgical ore prediction
- Assess impact of grind size parameters (e.g. effect of ultrafines) on overall recovery
© Metso© Metso
Conclusions
• In its simplest form, only sized and assayed flotation plant feed,concentrate and tailing are required (often readily available)
• Many mining companies routinely collect monthly composite samples ofkey flotation streams. This information is often under-utilised. Bazinanalysis is a tool that can help interpret this information.
• Integrated grinding-flotation simulation is superior to simulation of eachstage in isolation
© Metso© Metso
Acknowledgements
• Metso PTI and company personnel who were involved in collecting datafor these studies or assisted with the analysis
• Companies involved who gave permission to publish the data
© Metso© Metso
Process Technology and Innovation
Thank you!
Grinding and Flotation Circuit Integration and OptimisationKym Runge, Erico Tabosa and Peter Holtham
www.metso.com/pti
company/metso metsogroup metsoworldmetsoworld metsogroup
www.metso.com