1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

148
Up gradation of DR Module 1 Mesaieed, Qatar CONSTRUCTION MANUAL FOR UPGRADATION PROJECT ESSAR ENGINEERING SERVICES LTD. HAZIRA PREPARED BY (EESL) CHECKED & APPROVED BY (EESL) APPROVED BY (QSC) JR/PS/KCP JEGA/VHP DOC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 1

Transcript of 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Page 1: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR UPGRADATION PROJECT

ESSAR ENGINEERING SERVICES LTD.HAZIRA

PREPARED BY(EESL)

CHECKED & APPROVED BY

(EESL)

APPROVED BY(QSC)

JR/PS/KCP JEGA/VHP

DATE DETAILS OF REVISION REV NO

DOC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10Page 1

Page 2: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

14.09.10 Issued for Client Approval 00

CONTENTS

1. GENERAL................................................................................................................................... 61

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 2 of 106

Page 3: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

1.1. BACKGROUND........................................................................................................................... 61

1.2. PROJECT SCHEDULE...............................................................................................................62

1.3. GENERAL INSTRUCTION..........................................................................................................62

2. TOP GAS SCRUBBER,TGS VENTURI AND TGS DUCT...........................................................64

2.1. SCOPE OF WORK......................................................................................................................64

2.2. REFRENCE DRAWINGS & DOCUMENTS................................................................................65

2.3. SHUT DOWN ACTIVITIES..........................................................................................................66

2.3.1. DEMOLITION ACTIVITIES.........................................................................................................66

2.3.2. CONSTRUCTION ACTIVITIES...................................................................................................69

3. COOLING ZONE SCRUBBER,CZS VENTURY AND EXTERNAL CZS MIST ELIMINATOR.....71

3.1. SCOPE OF WORK......................................................................................................................71

3.2. REFRENCE DRAWINGS & DOCUMENTS................................................................................72

3.3. PRE-SHUTDOWN ACTIVITIES..................................................................................................74

3.3.1. CZS EXTERNAL MIST ELIMINATOR ERECTION.....................................................................74

3.4. SHUT DOWN ACTIVITIES..........................................................................................................74

3.4.1. DEMOLITION ACTIVITIES.........................................................................................................74

3.4.2. CONSTRUCTION ACTIVITIES...................................................................................................76

4. DIRECT RECYCLE PROCESS GAS MIST ELIMINATOR..........................................................77

4.1. SCOPE OF WORK......................................................................................................................77

4.2. REFRENCE DRAWINGS & DOCUMENTS................................................................................78

4.3. PRE-SHUTDOWN ACTIVITIES..................................................................................................80

4.3.1. DEMOLITION ACTIVITIES.........................................................................................................80

4.3.2. CONSTRUCTION ACTIVITIES...................................................................................................80

4.4. SHUT DOWN ACTIVITIES..........................................................................................................80

4.4.1. DEMOLITION ACTIVITIES.........................................................................................................80

4.4.2. CONSTRUCTION ACTIVITIES...................................................................................................80

5. COLD VENT BUBBLER..............................................................................................................81

5.1. SCOPE OF WORK......................................................................................................................81

5.2. REFRENCE DRAWINGS & DOCUMENTS................................................................................82

5.3. PRE-SHUTDOWN ACTIVITIES..................................................................................................83

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 3 of 106

Page 4: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

5.3.1. COLD VENT BUBBLER & ITS SUPPORT STRUCTURE INSTALLATION................................83

5.4. SHUT DOWN ACTIVITIES..........................................................................................................83

5.4.1. CONSTRUCTION ACTIVITIES...................................................................................................83

6. FURNACE LOWER SEAL LEG...................................................................................................84

6.1. SCOPE OF WORK......................................................................................................................84

6.2. REFRENCE DRAWINGS & DOCUMENTS................................................................................85

6.3. PRE-SHUTDOWN ACTIVITIES..................................................................................................86

6.4. SHUT DOWN ACTIVITIES..........................................................................................................86

6.4.1. DEMOLITION ACTIVITIES.........................................................................................................86

6.4.2. CONSTRUCTION ACTIVITIES...................................................................................................86

7. HEAT RECOVERY,FLUE GAS STACK......................................................................................87

7.1. SCOPE OF WORK......................................................................................................................87

7.2. REFRENCE DRAWINGS & DOCUMENTS................................................................................88

7.3. PRE-SHUTDOWN ACTIVITIES..................................................................................................90

7.3.1. DEMOLITION OF EXISTING H2S REMOVAL FACILITY............................................................90

7.3.2. CIVIL........................................................................................................................................... 91

7.3.3. FLUE GAS STACK ERECTION..................................................................................................91

7.3.4. STRUCTURE.............................................................................................................................. 91

7.3.5. PIPING AND DUCTING..............................................................................................................93

7.3.6. REFRACTORY............................................................................................................................ 94

7.4. SHUT DOWN ACTIVITIES..........................................................................................................96

7.4.1. DEMOLITION OF EXISTING POWER STACK AND POWER STACK FAN...............................96

7.4.2. CIVIL........................................................................................................................................... 96

7.4.3. STRUCTURE.............................................................................................................................. 97

7.4.4. PIPING AND DUCTING..............................................................................................................98

7.4.5. REFRACTORY............................................................................................................................ 98

7.4.6. EQUIPMENT............................................................................................................................... 99

8. REFORMER.............................................................................................................................. 100

8.1. SCOPE OF WORK....................................................................................................................100

8.2. REFRENCE DRAWINGS & DOCUMENTS..............................................................................101

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 4 of 106

Page 5: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

8.3. SHUT DOWN ACTIVITIES........................................................................................................102

8.3.1. DEMOLITION ACTIVITIES.......................................................................................................102

8.3.2. CONSTRUCTION ACTIVITIES.................................................................................................107

9. SEAL GAS COOLER................................................................................................................117

9.1. SCOPE OF WORK....................................................................................................................117

9.2. REFRENCE DRAWINGS & DOCUMENTS..............................................................................117

9.3. SHUTDOWN ACTIVITIES.........................................................................................................119

9.3.1. DEMOLITION ACTIVITIES.......................................................................................................119

9.3.2. CONSTRUCTION ACTIVITIES.................................................................................................119

10. FLUE GAS FAN & TRANSITION PIECE...................................................................................119

10.1. SCOPE OF WORK....................................................................................................................119

10.2. PRE-SHUTDOWN ACTIVITIES................................................................................................120

10.2.1. PRE-SHURDOWN DEMOLITION ACTIVITIES.........................................................................120

10.2.2. PRE-SHUTDOWN DEMOLITION REFERENCE DOCUMENTS..............................................121

10.2.3. PRE-SHUTDOWN DEMOLITION SCOPE................................................................................121

10.2.4. PRE-SHUTDOWN CONSTRUCTION ACTIVITIES..................................................................122

10.2.5. PRE-SHUTDOWN COMMISSIONING AND STARTUP ACTIVITIES.......................................125

10.2.6. PRE-SHUTDOWN CONSTRUCTION REFERENCE DOCUMENTS........................................125

10.2.7. PRE-SHUTDOWN CONSTRUCTION SCOPE.........................................................................126

10.3. SHUT DOWN ACTIVITIES........................................................................................................127

10.3.1. SHUTDOWN DEMOLITION ACTIVITIES.................................................................................127

10.3.2. SHUTDOWN CONSTRUCTION ACTIVITIES...........................................................................127

10.4. FINAL COMMISSIONING AND STARTUP ACTIVITIES...........................................................127

11. MAIN AIR BLOWER..................................................................................................................128

11.1. SCOPE OF WORK....................................................................................................................128

11.2. PRE-SHUTDOWN ACTIVITIES................................................................................................129

11.2.1. PRE-SHUTDOWN DEMOLITION ACTIVITIES.........................................................................129

11.2.2. PRE-SHUTDOWN DEMOLITION REFERENCE DOCUMENTS..............................................129

11.2.3. PRE-SHUTDOWN DEMOLITION SCOPE................................................................................130

11.2.4. PRE-SHUTDOWN CONSTRUCTION ACTIVITIES..................................................................130

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 5 of 106

Page 6: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

11.2.6. PRE-SHUTDOWN CONSTRUCTION REFERENCE DOCUMENTS........................................134

11.2.7. PRE-SHUTDOWN CONSTRUCTION SCOPE.........................................................................134

11.3. SHUT DOWN ACTIVITIES........................................................................................................135

11.3.1. SHUTDOWN DEMOLITION ACTIVITIES.................................................................................135

11.3.2. SHUTDOWN CONSTRUCTION ACTIVITIES...........................................................................135

11.4. FINAL COMMISSIONING AND STARTUP ACTIVITIES...........................................................136

12. AUXILIARY AIR BLOWER........................................................................................................136

12.1. SCOPE OF WORK....................................................................................................................136

12.2. PRE-SHUTDOWN ACTIVITIES................................................................................................137

12.2.1. PRE-SHUTDOWN DEMOLITION ACTIVITIES.........................................................................137

12.2.2. PRE-SHUTDOWN CONSTRUCTION ACTIVITIES..................................................................137

12.2.3. PRE-SHUTDOWN COMMISSIONING AND STARTUP ACTIVITIES.......................................139

12.2.4. PRE-SHUTDOWN CONSTRUCTION REFERENCE DOCUMENTS........................................140

12.2.5. PRE-SHUTDOWN CONSTRUCTION SCOPE.........................................................................141

12.3. SHUT DOWN ACTIVITIES........................................................................................................141

12.3.1. SHUTDOWN-DEMOLITION ACTIVITIES.................................................................................141

12.3.2. SHUTDOWN-DEMOLITION REFERENCE DOCUMENTS.......................................................142

12.3.3. SHUTDOWN-DEMOLITION SCOPE........................................................................................143

12.3.4. SHUTDOWN-CONSTRUCTION ACTIVITIES...........................................................................144

12.3.5. SHUTDOWN-CONSTRUCTION REFERENCE DOCUMENTS................................................145

12.3.6. SHUTDOWN-CONSTRUCTION SCOPE..................................................................................146

12.4. FINAL COMMISSIONING AND STARTUP ACTIVITIES...........................................................147

13. BSG COMPRESSOR UNIT.......................................................................................................147

13.1. SCOPE OF WORK....................................................................................................................147

13.2. PRE-SHUTDOWN ACTIVITIES................................................................................................148

13.2.1. PRE-SHUTDOWN DEMOLITION ACTIVITIES.........................................................................148

13.2.2. PRE-SHUTDOWN CONSTRUCTION ACTIVITIES..................................................................148

13.2.3. PRE-SHUTDOWN COMMISSIONING AND STARTUP ACTIVITIES.......................................151

13.2.4. PRE-SHUTDOWN CONSTRUCTION REFERENCE DOCUMENTS........................................151

13.2.5. PRE-SHUTDOWN CONSTRUCTION SCOPE.........................................................................152

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 6 of 106

Page 7: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

13.3. SHUT DOWN ACTIVITIES........................................................................................................153

13.3.1. SHUTDOWN-DEMOLITION ACTIVITIES.................................................................................153

13.3.2. SHUTDOWN-DEMOLITION REFERENCE DOCUMENTS.......................................................153

13.3.3. SHUTDOWN-DEMOLITION SCOPE........................................................................................154

13.3.4. SHUTDOWN-CONSTRUCTION ACTIVITIES...........................................................................155

13.3.5. SHUTDOWN-CONSTRUCTION REFERENCE DOCUMENTS................................................156

13.3.6. SHUTDOWN-CONSTRUCTION SCOPE..................................................................................157

13.4. FINAL COMMISSIONING AND STARTUP ACTIVITIES...........................................................158

14. FIRST STAGE PROCESS GAS COMPRESSOR.....................................................................158

14.1. SCOPE OF WORK....................................................................................................................158

14.2. PRE-SHUTDOWN ACTIVITIES................................................................................................159

14.2.1. PRE-SHUTDOWN DEMOLITION ACTIVITIES.........................................................................159

14.2.2. PRE-SHUTDOWN CONSTRUCTION ACTIVITIES..................................................................159

14.2.3. PRE-SHUTDOWN COMMISSIONING AND STARTUP ACTIVITIES.......................................161

14.2.4. PRE-SHUTDOWN CONSTRUCTION REFERENCE DOCUMENTS........................................161

14.2.5. PRE-SHUTDOWN CONSTRUCTION SCOPE.........................................................................162

14.3. SHUT DOWN ACTIVITIES........................................................................................................163

14.3.1. SHUTDOWN-DEMOLITION ACTIVITIES.................................................................................163

14.3.2. SHUTDOWN-DEMOLITION REFERENCE DOCUMENTS.......................................................163

14.3.3. SHUTDOWN-DEMOLITION SCOPE........................................................................................164

14.3.4. SHUTDOWN-CONSTRUCTION ACTIVITIES...........................................................................165

14.3.5. SHUTDOWN-CONSTRUCTION REFERENCE DOCUMENTS................................................167

14.3.6. SHUTDOWN-CONSTRUCTION SCOPE..................................................................................168

14.4. FINAL COMMISSIONING AND STARTUP ACTIVITIES...........................................................168

15. SECOND STAGE COMPRESSOR...........................................................................................169

15.1. SCOPE OF WORK....................................................................................................................169

15.2. PRE-SHUTDOWN ACTIVITIES................................................................................................170

15.2.1. PRE-SHUTDOWN DEMOLITION ACTIVITIES.........................................................................170

15.2.2. PRE-SHUTDOWN CONSTRUCTION ACTIVITIES..................................................................170

15.2.3. PRE-SHUTDOWN COMMISSIONING AND STARTUP ACTIVITIES.......................................172

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 7 of 106

Page 8: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

15.2.4. ERECTION REFERENCE DOCUMENTS.................................................................................172

15.2.5. PRE-SHUTDOWN CONSTRUCTION SCOPE.........................................................................173

15.3. SHUT DOWN ACTIVITIES........................................................................................................174

15.3.1. SHUTDOWN DEMOLITION ACTIVITIES.................................................................................174

15.3.2. SHUTDOWN-DEMOLITION REFERENCE DOCUMENTS.......................................................175

15.3.3. SHUTDOWN-DEMOLITION SCOPE........................................................................................175

15.3.4. SHUTDOWN-CONSTRUCTION ACTIVITIES...........................................................................176

15.3.5. SHUTDOWN-CONSTRUCTION REFERENCE DOCUMENTS................................................178

15.3.6. SHUTDOWN-CONSTRUCTION SCOPE..................................................................................179

15.4. FINAL COMMISSIONING AND STARTUP ACTIVITIES...........................................................180

16. FURNACE HYDRAULIC ROOM & HYDRAULIC UNIT.............................................................180

16.1. SCOPE OF WORK....................................................................................................................180

16.2. PRE-SHUTDOWN ACTIVITIES................................................................................................182

16.2.1. PRE-SHUTDOWN DEMOLITION ACTIVITIES.........................................................................182

16.2.2. PRE-SHUTDOWN CONSTRUCTION ACTIVITIES..................................................................182

16.2.3. PRE-SHUTDOWN COMMISSIONING AND STARTUP ACTIVITIES.......................................184

16.2.4. PRE-SHUTDOWN CONSTRUCTION REFERENCE DOCUMENTS........................................185

16.2.5. PRE-SHUTDOWN CONSTRUCTION SCOPE.........................................................................186

16.3. SHUT DOWN ACTIVITIES........................................................................................................186

16.3.1. SHUTDOWN-DEMOLITION ACTIVITIES.................................................................................186

16.3.2. SHUTDOWN-DEMOLITION REFERENCE DOCUMENTS.......................................................187

16.3.3. SHUTDOWN-DEMOLITION SCOPE........................................................................................188

16.3.4. SHUTDOWN-CONSTRUCTION ACTIVITIES...........................................................................188

16.3.5. SHUTDOWN-CONSTRUCTION REFERENCE DOCUMENTS................................................189

16.3.6. SHUTDOWN-CONSTRUCTION SCOPE..................................................................................190

16.4. FINAL COMMISSIONING AND STARTUP ACTIVITIES...........................................................190

17. EXISTING DILUTION AIR BLOWER DEMOLITION.................................................................191

17.1. SCOPE OF WORK....................................................................................................................191

17.2. PRE-SHUTDOWN ACTIVITIES................................................................................................191

17.3. SHUT DOWN ACTIVITIES........................................................................................................192

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 8 of 106

Page 9: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

17.3.1. EQUIPMENT DEMOLITION......................................................................................................192

17.3.2. STRUCTURE DEMOLITION.....................................................................................................192

17.3.3. PIPING DEMOLITION...............................................................................................................193

17.4. SHUTDOWN-DEMOLITION REFERENCE DOCUMENTS.......................................................193

17.5. SHUTDOWN-DEMOLITION SCOPE........................................................................................194

18. EXISTING AUXILIARY AIR BLOWER DEMOLITION...............................................................194

18.1. SCOPE OF WORK....................................................................................................................195

18.2. PRE-SHUTDOWN ACTIVITIES................................................................................................195

18.3. SHUT DOWN ACTIVITIES........................................................................................................195

18.3.1. EQUIPMENT DEMOLITION......................................................................................................195

18.3.2. STRUCTURE DEMOLITION.....................................................................................................196

18.3.3. PIPING DEMOLITION...............................................................................................................196

18.4. SHUTDOWN-DEMOLITION REFERENCE DOCUMENTS.......................................................197

18.5. SHUTDOWN-DEMOLITION SCOPE........................................................................................198

DEFINITIONS & ABBREVIATIONS

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 9 of 106

PATEL, 09/14/10,
Cooling gas compressor gear box job missing
Page 10: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

DEFINITIONS

Owner-shall mean M/s Qatar Steel Company that owns the DR-1 Module up

gradation project

Purchaser-shall mean an entity that owns the Procurement support contract

of the project tendered by Owner

Engineering Consultant-shall mean an entity that owns the Engineering

contract of the project.

Vendor/Manufacturer – shall mean an entity that owns the Hoist supplier of

the project fixed by purchaser/owner.

ABBREVIATIONS

EESL - Essar Engineering Services Ltd

QSC - Qatar Steel Company

1. BACKGROUND

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 10 of 106

Page 11: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

Qatar Steel is one among the top steel producers in the Middle East. The

Integrated Steel Plant consists of the following:

DR Plant.

Electric Arc Furnace.

Continuous Casting Machine.

Rolling Mill.

DR Plant has 2 Modules which capacities as below

Module 1 – 0.4 Million tons per year capacity DRI producing 0.8 Millions

Module 2 – 1.5 Million tons per year DRI

This Project is aimed at upgrading Module 1 from 0.8 Million tons per year to 1

Million tons per year production capacity

More about Company details and process description can be found on website

www.qatarsteel.com

2. PROJECT SCHEDULE

Engineering Completed by October 2010.

Procurement activities complete and items on site by 1st August 2011(2

months float).

(This is applicable only for long lead items, other items shall reach site

earlier).

Pre shutdown activities in August & September 2011.

Shutdown starts from 1st October and completes by January 3rd week.

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 11 of 106

Page 12: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

Start-up & commissioning during 4th week of January 2012.

3. GENERAL INSTRUCTION

Match Marking Activities before shutdown and dismantling

Below listed activity should be completed prior to shut down.

o Scaffolding and approach to be provided near piping and ducting tie

in point or as required.

o Provide temporary support to all piping and ducting and structures to

be dismantle in order to avoid any movement after cutting.

o Items to be removed should be matched marked properly.

o Match marking of all structures and piping as require.

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 12 of 106

Page 13: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

4. TOP GAS SCRUBBER,TGS VENTURI

4.1. SCOPE OF WORK

4.1.1. The work involves the following activities for the demolition of existing

TGS and installation of new TGS for plant up gradation

Prefabrication and supply

Demolition

Construction

Tie in activities

Start up & Commissioning

4.1.2. The Main activities are consisting of but not limited to the following:

Pre shut down fabrication of Top Gas scrubber, TGS supporting

structures, top gas duct spools etc.

During shutdown, assembly & erection as per the scope specified

herein.

Demolition of existing Top Gas Scrubber.

Demolition of existing TGS structure and civil work.

Installation of new TGS and existing ventury

Tie-in with existing ducts and pipes with new TGS

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 13 of 106

Page 14: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

4.2. REFRENCE DRAWINGS & DOCUMENTSSr.N

oArea Drawing / Document Numbers

A. Demolition

P&ID1033-H000-A11000-0019-1904-

0004

Equipment1033-H000-A11350-0019-1910-

0009

B. Pre-Shutdown Work

Fabrication of Top Gas Scrubber

1033-H000-A11350-0019-1911-0031 to

1033-H000-A11350-0019-1911-0046

C. Shut Down Work

Erection/Assembly of New Top Gas Scrubber

1033-H000-A11350-0019-1911-0031 to

1033-H000-A11350-0019-1911-0046

4.3. SHUT DOWN ACTIVITIES

4.3.1. DEMOLITION ACTIVITIES

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 14 of 106

Page 15: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

Remove the packing from existing top gas scrubber and

preserve it for reuse in cooling zone scrubber prior to start

dismantling.

Items (Mechanical, Ducting, Piping, Electrical,

Instrumentation etc.) to be removed must match marked and

secure properly.

4.3.1.1. TOP GAS SCRUBBER VENTURI AND SUPPORT STRUCTURE Fix Bellow Position by providing the appropriate stoppers

then cut bellow from its bottom flange. Dismantle the

water connection line for Swirl and throat spray nozzles.

Remove the necessary instrumentation and electrical

cables. Provide lifting lug on venturi and remove it and

keep it for reuse. Extra care need to be taken for bellow

as it will be reuse.

Remove Spring support and preserved it for reuse.

Venturi’s existing supporting structure above

EL+52061(GL+21881) will be reused as per drawing

1033-H000-A11350-0019-1910-0009. Before dismantling

the structure all the pipe supports, cable and cable trays

supports on the structure to be removed. Engage the

crane and hold the structure cut the columns as shown in

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 15 of 106

Page 16: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

drawing (structure drawing reference) remove the

structure and preserve it for reuse.

4.3.1.2. TOP GAS SCRUBBER Process Gas, Top Gas Fuel and Process gas recycle

existing duct to be cut and support as specified in the

construction manual no.: 1033-H000-A11360-0015-1500-

0000. All the supply line to be dismantles. Return water

line to be cut as specified in the construction manual no.:

1033-H000-A11360-0015-1500-0000. Remove the U-loop

ducting and keep it safe for reuse. Drain line of TGS to be

removed.

Check lifting lug provision on existing TGS provide if not

available engage the crane and hold the TGS and

dismantle it from existing support structure and keep it on

ground.

4.3.2. CONSTRUCTION ACTIVITIES

4.3.2.1. TOP GAS SCRUBBER & VENTURI TGS Erection weight = 59000 Kg.

Place top gas scrubber on support structure as shown in

1033-H000-A11350-0019-1911-0031. Existing preserved

venturi supporting structure to be erected on new

structure. Place the venturi along with bellow and weld

the bellow bottom flange with TGS Inlet nozzle flange.

Install TGS spray nozzles.

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 16 of 106

PATEL, 14/09/10,
Water supply
Page 17: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

Fill up the packing inside New Top gas Scrubber and box-

up the manholes after completion of all hot works.

4.3.2.2. REFRACTORY Do the necessary refractory work inside the Top gas duct

(scaffolding may require) as per 1003-H000-A11350-

0019-1911-7001.

5. COOLING ZONE SCRUBBER,CZS VENTURY AND EXTERNAL CZS MIST ELIMINATOR

5.1. SCOPE OF WORK

5.1.1. The work involves the following activities for the demolition,

modification and installation of CZS, CZS ventury and External

CZS Mist Eliminator for plant up gradation

Prefabrication and supply

Demolition

Construction

Tie in activities

Start up & Commissioning assistance

5.1.2. The Main activities are consisting of but not limited to the

following:

Pre shut down fabrication, assembly

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 17 of 106

PATEL, 09/14/10,
Manhole to be boxed up after cleaning and inspection of top gas scrubber, Pressure leak test to be carried out during start up for flanges of piping connected to top gas scrubber and PG mist eliminator
PATEL, 09/14/10,
Spray nozzle to be erected after flushing the water header. Spray pattern to be confirm before closing man way.
Page 18: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

Erection as per the scope specified herein.

Demolition of existing Internal CZS Roof and CZS internal Mist

Eliminator.

Modification of existing Cooling Zone Scrubber

Demolition of existing CZS Ventury and Replace it by new CZS

Ventury.

Installation of CZS Roof and water distribution headers

Installation of New External CZS Mist Eliminator on its civil

foundation

Ducting work between CZS and mist eliminator and to CZ

compressor

CZS U seal pipe modification work

Other miscellaneous activities as explained in the scope of work.

5.2. REFRENCE DRAWINGS & DOCUMENTSSr.N

oArea

Drawing / Document Numbers

A. Demolition

P&ID1033-H000-A11000-0019-

1904-0024Equipment 1033-H000-A11350-0019-

1911-00011033-H000-A11350-0019-

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 18 of 106

Page 19: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

1911-0016B. Pre-Shutdown Work

Fabrication of Cooling Zone Scrubber Top roof , External Mist Eliminator & Venturi

1033-H000-A11350-0019-1911-0001

to1033-H000-A11350-0019-

1911-00081033-H000-A11350-0019-

1911-00181033-H000-A11350-0019-

1911-00191033-H000-A11350-0019-

1911-00201033-H000-A11350-0019-

1911-0021To

1033-H000-A11350-0019-1911-0025

Erection of CZS External Mist Eliminator

1033-H000-A11350-0019-1911-0021

C. Shut Down WorkCooling Zone Scrubber

1033-H000-A11350-0019-1911-0001

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 19 of 106

Page 20: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

Modification & Venturi Erection

to1033-H000-A11350-0019-

1911-00081033-H000-A11350-0019-

1911-0016

5.3. PRE-SHUTDOWN ACTIVITIES

5.3.1. CZS EXTERNAL MIST ELIMINATOR ERECTION Erection Weight = 9273 Kg.

CZS mist eliminator to be fixed on civil foundation as shown

in drawing 1033-H000-A11350-0019-1911-0021. Water

supply and drain line to be erected and cabling for electrical

and instrumentation accessories to be done as required.

Install and fix the demister pad on support inside the vessel

and Install spray nozzle for flushing and spray to be check

then Box-up the manhole.

5.4. SHUT DOWN ACTIVITIES

5.4.1. DEMOLITION ACTIVITIES Items (Mechanical, Ducting, Piping, Electrical,

Instrumentation etc.) to be removed must match marked and

secure properly.

5.4.1.1. COOLING GAS VENTURI INLET PIPE

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 20 of 106

Page 21: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

Check the lifting lug provision on exiting cooling gas inlet

duct to CZS Venturi, provide if not available. Provide

support to existing cooling gas off take. Position the crane

and hold the cooling gas inlet duct. Remove the existing

spray nozzle inserted up to existing CZS venturi throat.

Cut & Remove the cooling gas duct at CZS venturi and

cooling gas off take end and keep it on ground for reuse.

5.4.1.2. COOLING ZONE SCRUBBER VENTURI Dismantle the CZS Venturi Swirl and throat spray nozzle

water connections. Cut the CZS inlet pipe by keeping

outer projection margin 253mm and remove the venturi as

shown in drawing 1033-H000-A11350-0019-1911-0016.

5.4.1.3. COOLING ZONE SCRUBBER Remove the packing from existing cooling zone scrubber

prior to start dismantling.

Cooling gas Inlet and outlet duct to be supported and

dismantle. Dismantle all the water supply line. Provide the

temporary supports inside CZS to inlet pipe as shown in

drawing 1033-H000-A11350-0019-1911-0016 now

remove welding between inlet pipe and top roof and

welding between internal mist eliminator vanes and top

roof. Remove top cover along with stiffeners, spray

nozzles, outlet nozzle and quick opening manway.

Remove the welding between the internal mist eliminator

vanes and CZS shell plate and inlet pipe and remove

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 21 of 106

Page 22: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

internal mist eliminator Refer drawing 1033-H000-

A11350-0019-1911-0016.

5.4.2. CONSTRUCTION ACTIVITIES

5.4.2.1. COOLING ZONE SCRUBBER MODIFICATION AND MIST ELIMINATOR DUCTING Erection Weight for CZS Modifications = 5397 Kg.

Install Bottom and top grating. Install new top cover of

Cooling zone scrubber stiffeners, outlet and spray nozzles

can be pre install before erection. Weld existing inlet pipe

with new top roof. Remove Temporary supports provided

to inlet pipe. Provide the new flange to inlet duct with

maintaining the outer projection 250mm as shown in

drawing 1033-H000-A11350-0019-1911-0016.

Install water header with spray nozzles.

5.4.2.2. COOLING ZONE SCRUBBER VENTURI Erection weight for Venturi = 4087 Kg.

Place the new venturi and weld it with CZS modified inlet

pipe. Install water supply, return and drain line for CZS

and its venturi. Remove the bored blind flange from top of

cooling gas inlet duct and provide new blind as shown in

drawing 1033-H000-A11350-0019-1911-0016 and place it

and weld with cooling gas off take and cooling gas

venturi. Does the necessary refractory work inside the

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 22 of 106

PATEL, 14/09/10,
Spray nozzle to be erected after flushing the water header. Spray pattern to be confirm before closing man way.
Page 23: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

cooling gas duct (scaffolding may require) refer 1033-

H000-A11350-0019-1911-7002.

Fix the spray nozzles inside the scrubber and spray to be

check. Fill the packing inside CZS and box up the

manholes.

6. DIRECT RECYCLE PROCESS GAS MIST ELIMINATOR

6.1. SCOPE OF WORK

6.1.1. The work involves the following activities for demolition of existing

RG cooler and the installation of new direct recycle process gas

mist eliminator for plant up gradation

Prefabrication and supply

Demolition

Construction

Tie in activities

Start up & Commissioning

6.1.2. The Main activities are consisting of but not limited to the

following:

Pre shut down fabrication

Assembly &erection as per the scope specified herein.

Demolition of existing RG cooler

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 23 of 106

PATEL, 14/09/10,
It is a part of scrubber and already written
PATEL, 14/09/10,
Manhole to be boxed up after cleaning and inspection of CZ scrubber, CZMEPressure leak test to be carried out during start up for flanges of piping connected to CZME and scrubber.
Page 24: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

Installation of new direct recycle process gas mist eliminator

6.2. REFRENCE DRAWINGS & DOCUMENTSSr.N

oArea

Drawing / Document Numbers

A. Demolition

P&ID1033-H000-A11000-0019-

1904-0012RG Cooler Dismantling

SIM3-541 (QSC Drawing)

B. Pre-Shutdown WorkDismantling of RG Cooler

SIM3-541 (QSC Drawing)

Fabrication of Mist Eliminator

1033-H000-A11350-0019-1911-0051

1033-H000-A11350-0019-1911-0052

1033-H000-A11350-0019-1911-0053

1033-H000-A11350-0019-1911-0054

Erection of DR PG Mist Eliminator

1033-H000-A11350-0019-1910-0008

C. Shut Down Work

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 24 of 106

Page 25: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

6.3. PRE-SHUTDOWN ACTIVITIES

6.3.1. DEMOLITION ACTIVITIES Existing RG cooler ducting, piping, electrical and

instrumentation cable to be removed if available. Unfasten the

RG cooler from the structure by removing all fasteners then

dismantle the RG cooler and keep it on ground.

6.3.2. CONSTRUCTION ACTIVITIES Erection Weight = 2248 Kg.

Install New Support Structure Require to install the mist

eliminator at floor level EL+46792(GL+16612). Install mist

eliminator on new support structure as per drawing 1033-

H000-A11350-0019-1911-0051.

7. COLD VENT BUBBLER

7.1. SCOPE OF WORK

7.1.1. The work involves the following activities for the installation of new

cold vent bubbler for plant up gradation

Prefabrication and supply

Demolition

Construction

Tie in activities

Start up & Commissioning

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 25 of 106

PATEL, 14/09/10,
Manhole to be boxed up after cleaning and inspection of direct recycle mist eliminatorPressure leak test to be carried out during start up for flanges of piping connected to direct recycle ME
Page 26: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

7.1.2. The Main activities are consisting of but not limited to the

following:

Pre shut down fabrication

Assembly & erection as per the scope specified herein.

Installation of new cold vent bubbler

7.2. REFRENCE DRAWINGS & DOCUMENTSSr.N

oArea

Drawing / Document Numbers

A. DemolitionP&ID 1033-H000-A11000-0019-1904-0004

B. Pre-Shutdown WorkFabrication of Cold Vent Bubbler & Erection of Cold Vent Bubbler

1033-H000-A11350-0019-1911-0062

1033-H000-A11350-0019-1911-0063

1033-H000-A11350-0019-1911-0069

7.3. PRE-SHUTDOWN ACTIVITIES

7.3.1. COLD VENT BUBBLER & ITS SUPPORT STRUCTURE INSTALLATION

Erection Weight = 1274 Kg.

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 26 of 106

Page 27: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

New Support Structure Require to install the cold vent bubbler at

floor level EL+55220(GL+25040). Erect the Cold vent bubbler on

support structure as per drawing 1033-H000-A11350-0019-1911-

0062.

8. FURNACE LOWER SEAL LEG

8.1. SCOPE OF WORK

8.1.1. The work involves the following activities for the installation of new

lower seal leg for plant up gradation

Prefabrication and supply

Demolition

Construction

Tie in activities

Start up & Commissioning

8.1.2. The Main activities are consisting of but not limited to the

following:

Pre shut down fabrication, assembly &erection as per the scope

specified herein.

Installation of new lower seal leg

8.2. REFRENCE DRAWINGS & DOCUMENTSSr.N Area Drawing / Document

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 27 of 106

PATEL, 09/14/10,
Manhole to be boxed up after cleaning and inspection of clod vent bubblerPressure leak test to be carried out during start up for flanges of piping connected to bubbler
Page 28: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

o NumbersA. Demolition

P&ID 1033-H000-A11000-0019-1904-0002

Equipment1033-H000-A11350-0019-1910-0017

1033-H000-A11350-0019-1911-0061

SIFU-049 (QSC Drawing)

B. Pre-Shutdown Work

Fabrication of Lower Seal leg

1033-H000-A11350-0019-1911-0061

1033-H000-A11350-0019-1911-0064

1033-H000-A11350-0019-1911-0070

C. Shut Down Work

Erection of Lower Seal Leg

1033-H000-A11350-0019-1911-0061

1033-H000-A11350-0019-1911-0064

SIFU-049 (QSC Drawing)

8.3. PRE-SHUTDOWN ACTIVITIES There are no activities in the pre-shutdown.

8.4. SHUT DOWN ACTIVITIES

8.4.1. DEMOLITION ACTIVITIES Provide temporary support to existing lower seal leg if

required at EL+37034(GL+6854) and Remove the wiper bar

assembly by de-bolting from the bottom flange of lower slide

gate preserve the Nuts, bolts and gasket for reuse.

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 28 of 106

Page 29: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

8.4.2. CONSTRUCTION ACTIVITIES Erection weight = 1273 Kg.

Provide support structure at EL+35180(GL+5000). Provide

gusset plate and base plate to existing lower seal leg (refer

drawing SIFU-049) and position the spring as per drawing

1033-H000-A11350-0019-1911-0061.

Fasten the top part of bottom spool of lower seal leg with

bottom flange of lower slide gate refer drawing 1033-H000-

A11350-0019-1911-0064. Lower part of bottom spool of

lower seal leg to be erected along with furnace discharge

vibro-feeder.

9. HEAT RECOVERY,FLUE GAS STACK

9.1. SCOPE OF WORK

9.1.1. The work involves the following activities for Dismantling of the

existing power stack fan, stack & H2S removal system and

construction of new heat recovery system, flue gas fan & stack for

the DR-1 plant up gradation.

Prefabrication and supply

Demolition

Construction

Tie in activities

Start up & Commissioning

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 29 of 106

PATEL, 14/09/10,
Pressure leak test to be carried out during start up for flanges of lower slide gate
Page 30: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

9.1.2. The Main activities are consisting of but not limited to the

following:

Pre shut down fabrication

Pre assembly & erection as per the scope specified herein.

Demolition of existing power stack fan, stack and H2S

removal system

Installation of new heat recovery system, flue gas stack and

refractory work.

9.2. REFRENCE DRAWINGS & DOCUMENTSSr.N

oArea

Drawing / Document Numbers

A. Demolition

P&ID1033-H000-A11000-0019-1904-

0008,0009,0010,0020

EquipmentPower stack and power stack fan

S1C2-014 (Demolition Mark-up)

H2S removal facility DH2S-810 (Demolition Mark-up)

B. Pre-Shutdown WorkFabrication of equipment

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 30 of 106

Page 31: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

Cold combustion air pre-heater B04-1(A&B) B04-2(A&B)

1033-H000-A11370-0019-

1911-0001 to 0003.

Feed gas pre-heater first stage (HE-A61-1&2)

1033-H000-A11370-0019-

1911-0021 to 0029.

Feed gas pre-heater second stage (HE-A65-1,2)

1033-H000-A11370-0019-

1911-0031 to 0039.

Natural gas pre-heater (HE-B62-1/2)

1033-H000-A11370-0019-

1911-0041 to 0045.

Flue gas fan 1033-H000-A11390-0019-1917-0001

Flue gas stack1033-H000-A11390-0019-1911-0001

to 0010

Flue gas fan to flue gas stack transition piece

1033-H000-A11390-0019-1911-0011

C. Shut Down WorkErection of the Equipment

Hot combustion air pre-heater B05-1(A&B) B05-2(A&B)

1033-H000-A11370-0019-1911-0011

To 0013.

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 31 of 106

Page 32: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

9.3. PRE-SHUTDOWN ACTIVITIES

9.3.1. DEMOLITION OF EXISTING H2S REMOVAL FACILITY. Reference Drawing DH2S-810 (Demolition Mark-up)

The existing H2S removal facility with connecting

equipments, ducts, pipes to be demolish and area to be

made free for the new heat recovery system, flue gas fan

and stack at ground level at GL +300 (EL +30480). After

dismantling of all equipments, ducts, pipes to be removed

and to be shifted to designated area. Area to be demolished

is marked in the QSC drg no.DH2S-810.

9.3.2. CIVIL Civil foundations shall be carried as per the civil

construction manual no.:1033-H000-A11000-0008-0811-

0005.

Before shut down piling, foundation, activities can be

completed for total heat recovery unit except axis A’, A and

for Axis B, works for north side train (between grid 1 and 2)

can complete as per civil construction manual.

9.3.3. FLUE GAS STACK ERECTION Flue gas stacks shall be erected with refractory, reference

drawing 1033-H000-A11390-0019-1911-0001 to 0010

before proceeding with heat recovery erection activities.

Flue gas stack refractory to be done as per the drawing

1033-H000-A11390-0019-1911-7001, 7002 before erection.

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 32 of 106

Page 33: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

9.3.4. STRUCTURE Structural Erection shall be carried as per the construction

manual no.:1033-H000-A11000-0008-0811-0006.

9.3.5. EQUIPMENT

9.3.5.1. PREHEATERS Cold combustion air pre-heater B04-1(A&B) B04-2(A&B)

to be erect and assemble as per the reference drawing

1033-H000-A11370-0019-1911-0001 to 0003.

Feed gas pre-heater first stage (HE-A61-1&2) to be erect

as per the reference drawing 1033-H000-A11370-0019-

1911-0021 to 0024.

Feed gas pre-heater second stage (HE-A65-1, 2) to be

erect as per the reference drawing 1033-H000-A11370-

0019-1911-0031 to 0034.

Natural gas pre-heater (HE-B62-1/2) to be erect as per

the reference drawing 1033-H000-A11370-0019-1911-

0041 to 0043.

After installation of feed gas heaters refractory dummy

shall be installed.

9.3.6. REFRACTORY

9.3.6.1. HEAT RECOVERY CASING After erection and alignment of heat recovery casing

refractory to be done as per the drawing 1033-H000-

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 33 of 106

PATEL, 14/09/10,
Top cover to be installed after placing bundles
Page 34: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

A11370-0019-1911-7001 to 7003 from flue gas stacks

side to column axis B.

9.3.6.2. HOT AIR DUCTS External insulation to be provided for duct from air

Preheater to hot combustion air Preheater as per

reference drawing no 1033-H000-A11370-0015-1516-

0022,0023 and external insulation specification no 1033-

H000-A11000-0019-1915-0035.

9.3.6.3. FEED GAS DUCTS External insulation to be provided for the feed gas duct

from the feed gas mixer to first stage feed gas Preheater

inlet as per reference drawing no 1033-H000-A11370-

0015-1516-0022,0023 and external insulation

specification no 1033-H000-A11000-0019-1915-0035.

External insulation to be provided for the feed gas duct

from the feed gas Preheater outlet to Second stage

Preheater inlet as per reference drawing no 1033-H000-

A11370-0015-1516-0022,0023 and external insulation

specification no 1033-H000-A11000-0019-1915-0035.

9.3.6.4. NATURAL GAS LINE External insulation to be provided for natural gas

Preheater outlet to feed gas mixture as per reference

drawing no 1033-H000-A11370-0015-1516-0022,0023

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 34 of 106

PATEL, 14/09/10,
First stage
PATEL, 14/09/10,
Cold combustion air
Page 35: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

and external insulation specification no 1033-H000-

A11000-0019-1915-0035.

9.3.6.5. CASING COVER Refractory of casing cover of feed gas first and second

stage preheater,natural gas Preheater to be done before

erection .Refer drawing no. 1033-H000-A11370-0019-

1911-7001 to 7003

9.3.6.6. DUMMY The refractory work for dummy shall be carried out

separately and to be placed inside casing after feed gas

pre-heaters installation. Refer drawing no. 1033-H000-

A11370-0019-1911-7001 & 7002.

9.4. SHUT DOWN ACTIVITIES

9.4.1. DEMOLITION OF EXISTING POWER STACK AND POWER STACK FAN Reference Drawing S1C2-014 (Demolition Mark-up)

The existing power stack (K-C10) and power stack fan with

connecting equipments, ducts, pipes to be demolish and

area to be made free for the new heat recovery system at

ground level at GL +300 (EL +30480). After dismantling of

all equipments, ducts, pipes to be removed and to be

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 35 of 106

Page 36: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

shifted to designated area. Area to be demolished is

marked in the QSC drg no.S1C2-014. The existing cable

trench to be keep as it is and work in this area to be carry

out with very carefully

9.4.2. EQUIPMENT CONSTRUCTION

9.4.2.1. PREHEATERS Hot combustion air pre-heater B05-1(A&B) B05-2(A&B) to

be erect and assemble as per the reference drawing

1033-H000-A11370-0019-1911-0011 to 0013.

9.4.3. REFRACTORY

9.4.3.1. HEAT RECOVERY CASING After erection and alignment of balance heat recovery

casing and transition piece from flue gas duct to heat

recovery casing refractory to be done as per the drawing

1033-H000-A11370-0019-1911-7001.

9.4.3.2. HOT AIR DUCTS After the erection of the hot air duct from hot combustion

air Preheater to main air header and main air manifold

refractory to be done as per the drawing 1033-H000-

A11370-0019-1911-7004.

9.4.3.3. FEED GAS DUCTS After the erection of the feed gas duct from feed gas

second stage Preheater outlet to feed gas manifold and

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 36 of 106

Page 37: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

feed gas manifold refractory to be done as per the

drawing 1033-H000-A11370-0019-1911-7025.

10. REFORMER

10.1. SCOPE OF WORK

10.1.1. The work involves the following activities for the dismantling of the

existing heat recovery system and construction of 3 bay

extensions for the DR-1 plant up gradation.

Prefabrication and supply

Demolition

Construction

Tie in activities

Start up & Commissioning

10.1.2. The Main activities are consisting of but not limited to the following

Pre shut down fabrication, assembly &erection as per the

scope specified herein.

Dismantling of the existing heat recovery system

Installation of Reformer tube assembly, Burners and its

accessories and refractory work for reformer 3 bay

extension

10.2. REFRENCE DRAWINGS & DOCUMENTSSr.N

oArea

Drawing / Document Numbers

A. Demolition

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 37 of 106

PATEL, 14/09/10,
Manhole to be boxed up after cleaning and inspection of all ductPressure leak test to be carried out during start up for flanges of process gas, feed gas natural gas and main air system
Page 38: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

P&ID1033-H000-A11000-0019-

1904-0011,14 to 17

Equipment

B. Pre-Shutdown Work

Fabrication of reformer equipment assembly and erection

1033-H000-A11360-0019-1911-

0003,0004,0006,0008,0009,0011, 0012,0015 to 0020

C. Shut Down Work

Installation of Equipment and refractory work

1033-H000-A11360-0019-1911-

0003,0004,0006,0008,0009,0011, 0012,0015 to 0020,7000,7001 to 7018,7023 to 7030

10.3. SHUT DOWN ACTIVITIES

10.3.1. DEMOLITION ACTIVITIES

10.3.1.1. HEAT RECOVERY SYSTEM

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 38 of 106

Page 39: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

After dismantling of all ducts and pipes from Heat

recovery area, heat recovery bundles to be removed and

to be shifted to designated area.

The existing heat recovery system casing and structures

which is at the ground level to be completely dismantled.

10.3.1.2. REFRACTORY Reformer doors to be opened and refractory at both

end walls to be removed.

The reformer end wall refractory to be removed

completely as shown the drawing no.1033-A11360-

0019

The existing reformer side wall refractory to be

removed from the nearest expansion joint at the 11th

bay as shown in the drawing no.1033-H000-A11360-

0019

The reformer floor refractory to be completely removed

for all the existing 11 bays and to be replaced with new

refractory and extended till the 14th bay as shown in

the drawing no.1033-H000-A11360-0019

The existing reformer roof refractory to be extended

from the 11th bay till the 14th bay of the reformer. Care

should be taken the existing roof refractory should not

be disturbed.

10.3.2. CONSTRUCTION ACTIVITIES

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 39 of 106

PATEL, 14/09/10,
Repeating the same point
PATEL, 14/09/10,
Why both end wall?
Page 40: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

10.3.2.1. EQUIPMENT

10.3.2.1.1. BURNER The burner to be installed at the reformer bottom floor

as per the drawing no.1033-H000-A11360-0019-1910-

0003. The burners to be installed before the floor

refractory are carried out. The alignment of the burners

is to be properly checked. The burners to be protected

while carrying out the floor refractory.

10.3.2.1.2. REFORMER TUBE ASSEMBLY Install 10” reformer tube (1033-H000-A11360-0019-

1917-0001) to the flanged nozzle in the reformer roof

plate with the rope gasket and high temp red RTV

silicon (Refer Drg No.1033-H000-A11360-0019-191-

0015)

Install reformer tube top canister (1033-H000-A11360-

0019-1911-0011) on top of the reformer tube. The

verticality of the top canister and the reformer tube to

be maintained. The top canister to be installed in

concentric with the reformer tube. The ceramic blanket

to be filled inside the reformer tube as per the drawing

no1033-H000-A11360-0019-1911-7017.

Install reformer tube dogleg filled with insulation

castable & ceramic blanket (1033-H000-A11360-

0019-1911-7026) on top of reformer tube. The flatness

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 40 of 106

PATEL, 14/09/10,
Filled word to be replaced with proper word
Page 41: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

of the dogleg to be maintained. The bottom of dogleg

to be welded air tight with the top of the reformer tube.

The joint of the dogleg connecting with the reformer

gas duct to be welded at site (1033-H000-A11360-

0019-1911-0015).

Install bellows (1033-H000-A11360-0019-1911-0006)

by bolting it to the flanged nozzle in reformer floor plate

with rope gasket and high temp red RTV silicon as

shown in drawing 1033-H000-A11360-0019-1911-

0015.

Install split ring flange (1033-H000-A11360-0019-1911-

00) in the groove near bottom of the reformer tube with

rope gasket and high temp red RTV silicon. Make sure

those split ring flanges are aligned properly with the

bellows.

Install catalyst support tube (1033-H000-A11360-0019-

1911-0008) with vacuum formed special shapes

through bottom of the reformer tube, aligning the slots

in catalyst support plate with lugs on I.D of the reformer

tube and rotating after insertion so that catalyst support

plate is seated on top of the lugs.

With gasket and ceramic fibre blanket (1033-H000-

A11360-0019-1911-7017) bolt feed gas inlet flange to

split ring flange with and high temp red RTV silicon

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 41 of 106

Page 42: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

between flange (refer drawing no.1033-H000-A11360-

0019-1911-0015)

Remove bellows shipping bars and bolt bellows to split

ring flange and gas inlet flange installation length of the

bellow to be maintained as shown in drawing (1033-

H000-A11360-0019-1911-0015)

Thread tube support rod into spring adjustment

bracket. Place tube spring over the spring adjustment

bracket attach to reformer casing floor beams.

Form rope gasket seals by installing two concentric

rings and hold in place with the high temp red RTV

silicon. The ends of each rope should overlap a

minimum of 40 mm with no gap between to typical

installation refer drawing no.1033-H000-A11360-0019-

1911-0015

Feed gas flexible hose to be wrapped with the mineral

wool 50mm thick. Covered with Denel fabric and

flexible mastic.

Do not install insulation around flange connection of

flex hose.

10.3.2.1.3. INSTALLATION OF CATALYST INSIDE REFORMER TUBE

The 10” reformer tube to be filled with the catalyst of

two types:

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 42 of 106

PATEL, 09/14/10,
Exiting 11 bay catalyst to be dump, catalyst to be clean and fill uniformly old and new active catalyst.
Page 43: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

Bottom of reformer tube –Low Active R8 up to 1.2 m

Top of Reformer tube – High Active R7GG 6.8 m

The catalyst to be filled after completion of upper

reformer tube assembly and lower tube assembly from

top dogleg flange opening and before the fixing of the

flexible hose.

10.3.2.2. REFRACTORY

10.3.2.2.1. REFORMER BOX After the erection of reformer columns with top and

bottom grids along with end wall, side wall, roof and

floor , the roof refractory to be done as per the drawing

1033-H000-A11360-0019-1911

The end wall refractory to be done as per the drawing

no.1033-H000-A11360-0019-1911-

The side wall refractory to be carried out from the 14th

bay to the 12th bay.

The floor refractory to be carried out from the 14th bay

to 12th bay. The floor refractory to be carried out after

the installation of reformer burner is scaffoldings to be

provided for last four bays for carrying out the erection

jobs. completed

10.3.2.2.2. HOT AIR DUCT After the erection of the hot air ducts it is to be filled

inside with refractory from 12th bay to 14th bay as

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 43 of 106

PATEL, 14/09/10,
Filled word to be replaced with proper word
PATEL, 14/09/10,
Statement is mismatching
PATEL, 14/09/10,
Floor refrectory for all bays
PATEL, 14/09/10,
Pressure drop check after catalyst filling to be mention
PATEL, 14/09/10,
Including old and new catalyst
PATEL, 14/09/10,
Including old and new catalyst
Page 44: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

shown in the drawing no.1033-H000-A11360-0019-

1911-.External insulation to be provided for the risers

at the extended bays as shown in the drawing 1033-

H000-A11360-0019-

10.3.2.2.3. FEED GAS DUCT External insulation to be provided for the fabricated

feed gas duct from the 1st bay to 14th bay and the

feed gas risers to be insulated as shown in the drawing

no.1033-H000-A11360-0019-1911

10.3.2.2.4. REFORMED GAS DUCT After the erection of the reformed gas duct it is to be

filled with the inside refractory from 12th bay to 14th

bay as shown in the drawing no.1033-H000-A11360-

0019-1911

11. SEAL GAS COOLER

11.1. SCOPE OF WORK

11.1.1. The work involves the following activities for demolition of existing

seal gas water distribution trays, replacing packing materials, and

modifying cooling water distribution spray system.

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 44 of 106

PATEL, 09/14/10,
Manhole to be boxed up after cleaning and inspection of all ductPressure leak test to be carried out during start up for flanges of process gas, feed gas, refromed gas,natural gas and main air system
PATEL, 14/09/10,
Filled word to be replaced with proper word
Page 45: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

Prefabrication and supply of spray nozzles

Demolition

Construction

Tie in activities

Start up & Commissioning

11.1.2. The Main activities are consisting of but not limited to the

following:

Pre shut down fabrication

Assembly &erection as per the scope specified herein.

Demolition of existing water spray trays

Installation of water spray pipes and spray nozzles

11.2. REFRENCE DRAWINGS & DOCUMENTSSr.N

oArea

Drawing / Document Numbers

A. DemolitionP&ID 1033-H000-A11000-0019-1904-0012

Seal gas Cooler Dismantling

SIM3-541 (QSC Drawing)

B. Shutdown WorkDismantling of SG Cooler

SIM3-541 (QSC Drawing)

Modifying Seal gas Cooler

1033-H000-A11350-0019-1911-0051

1033-H000-A11350-0019-1911-0052

1033-H000-A11350-0019-1911-0053

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 45 of 106

PATEL, 14/09/10,
0027
Page 46: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

1033-H000-A11350-0019-1911-0054

11.3. SHUTDOWN ACTIVITIES

11.3.1. DEMOLITION ACTIVITIES The Existing SG cooler water inlet piping and distribution

trays to be removed as per drawing 1033-H000-A11350-

0019-1911-0051 to 0054.

11.3.2. CONSTRUCTION ACTIVITIES Erection Weight = 2248 Kg.

Install new water spray pipes, headers and spray nozzle as

per drawing 1033-H000-A11350-0019-1911-0051 to 0054.

Rerouting the spray water inlet header and patching the

existing water inlet pipe opening with a blind plate as per

drawing 1033-H000-A11350-0019-1911-0051 to 0054.

12. FLUE GAS FAN & TRANSITION PIECE

12.1. SCOPE OF WORK

12.1.1. The work involves the following activities for Dismantling of the

existing H2S removal system and construction of flue gas fan for

the DR-1 plant up gradation.

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 46 of 106

PATEL, 14/09/10,
Manhole to be boxed up after cleaning and inspection.Pressure leak test to be carried out during start up.
PATEL, 14/09/10,
Packing to be removed before any mechanical work. New packing to be filled after all mechanical work completed. Nozzel to be fixed after flushing the water pipe.
Page 47: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

Prefabrication, assembly and Supply

Demolition

Construction

Tie in activities

Start up & Commissioning

12.1.2. The Main activities are consisting of but not limited to the

following:

Pre shut down fabrication, assembly & erection as per the scope

specified herein.

Demolition of existing H2S removal system Equipments, structures,

piping’s.

Installation of new Flue fan and transition Piece refractory work.

12.2. PRE-SHUTDOWN ACTIVITIES

12.2.1. PRE-SHURDOWN DEMOLITION ACTIVITIES

Demolition activities to be carried as per the reference drawing

& instruction as per the site Engineer.

The existing H2S removal facility with connecting equipments,

ducts, pipes to be demolish and area to be made free for the

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 47 of 106

Page 48: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

flue gas fan at ground level at GL +300 (EL +30480). After

dismantling of all equipments, ducts, pipes to be removed and

to be shifted to designated area. Area to be demolished is

marked in the drawing.

During the demolition activities take care of the running

existing connecting lines, equipments.

Safety procedure to be follow as per the QSC procedure & Site

engineer requirement.

And the Heavy & rotary equipments dismantling to be done as

per the equipment manufacturer manual & the site engineer

requirement

12.2.2. PRE-SHUTDOWN DEMOLITION REFERENCE DOCUMENTS

General Drawings & Documents:

The H2S removal facilities for QATAR - G701-LD003

12.2.3. PRE-SHUTDOWN DEMOLITION SCOPE

Sr.N

oDescription Weight(Kg)

Others

01. Equipments QSC12.2.4. PRE-SHUTDOWN CONSTRUCTION ACTIVITIES

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 48 of 106

Page 49: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

12.2.4.1. EQUIPMENT ERECTION

Flue gas fan to be erection to be carried as per the reference

drawing and Erection specification enclosed with document.

The Transition piece between the fan outlet to flue gas stack to

be done as per the reference drawings before the transition

piece erection the refractory to done as per the refractory

requirement in this document.

The alignments of the Rotary and static equipments to be

carried as per the erection specification if the manufacturer

manual not available.

The Manufacturer manual shall be referring the rotary

equipment erection procedures.

12.2.4.2. REFRACTORY ERECTION

The Transition refractory between the fan outlet to flue

gas stack to be done as per the reference drawings

before the transition piece erection.

The Manufacturer manual shall be referring the refractory

erection procedures.

The general refractory erection procedure to be follow for

the erection of refractory as per the Enclosed documents

along with this document.

12.2.5. PRE-SHUTDOWN COMMISSIONING AND STARTUP ACTIVITIES

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 49 of 106

PATEL, 09/14/10,
Something wromg
PATEL, 09/14/10,
I think no refractory pl check
PATEL, 09/14/10,
I think no refractory pl check
Page 50: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

All Pressure test and cleaning of piping of lubrication system

and utility system up to hook up point shall be carried as per

the Enclosed erection specification.

Lubrication System test and cleaning shall be carried as per

the enclosed erection specification.

After that the Lubrication system shall be started and

performance shall be checked as per the manufacturer Manual

and specification.

12.2.6. PRE-SHUTDOWN CONSTRUCTION REFERENCE DOCUMENTS

Equipment drawings & Documents:

Vendor Drawings & Manual -

P & ID drawings:

P & ID for the Flue gas & stack-

1033-H000-A11000-1909-0009/10 and 0019

General Drawings & Documents:

General arrangement of flue gas fan & stack

- 1033-H000-A11000-1904-0020

12.2.7. PRE-SHUTDOWN CONSTRUCTION SCOPE

Sr.N

oDescription Weight(Kg)

Others

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 50 of 106

PATEL, 09/14/10,
Check number
Page 51: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

01. Equipments 20000(App)

12.3. SHUT DOWN ACTIVITIES

12.3.1. SHUTDOWN DEMOLITION ACTIVITIES

The demolition works not there during shutdown.

12.3.2. SHUTDOWN CONSTRUCTION ACTIVITIES

12.3.2.1. CIVIL ERECTION

The civil foundation works not there during shutdown.

12.3.2.2. STRUCTURE ERECTION

The structural works not there during shutdown.

12.3.2.3. PIPING ERECTION

12.3.2.3.1. Utility piping

The hook up of the utility piping with existing utility

facilities as per the reference drawing.

The erection procedures will be as per the enclosed

erection specification

12.3.2.4. REFRACTORY ERECTION

The Refractory works not there during shutdown.

12.3.2.5. EQUIPMENT ERECTION

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 51 of 106

Page 52: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

The Equipment Erection works not there during

shutdown.

12.4. FINAL COMMISSIONING AND STARTUP ACTIVITIES

All Pressure test and cleaning of piping of lubrication system

and utility system with hook up point shall be carried as per the

Enclosed erection specification.

After that the Flue gas fan system shall be started and

performance shall be checked as per the manufacturer Manual

and specification.

Note: Before starting the Flue gas fan the Heat recovery

system all activities should be completed and hook up with

reformer should be completed.

13. MAIN AIR BLOWER

13.1. SCOPE OF WORK

13.1.1. The work involves the following activities for construction of Main

Air Blower for the DR-1 plant up gradation.

Prefabrication, assembly and Supply

Construction

Tie in activities

Start up & Commissioning

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 52 of 106

PATEL, 09/14/10,
Guide vane checking before fan start up. Inspection in casing nothing is left out. Inspection also to be carried out from inside recuperator that nothing is lying on guide vane and any loose material which sucked in
PATEL, 09/14/10,
Motor direction to be checked and then couple
PATEL, 09/14/10,
Already mention earlier
Page 53: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

13.1.2. The Main activities are consisting of but not limited to the

following:

Pre shut down fabrication, assembly & erection as per the scope

specified herein.

Installation of new Main Air Blower including civil, structure, piping

and refractory work.

13.2. PRE-SHUTDOWN ACTIVITIES

13.2.1. PRE-SHUTDOWN DEMOLITION ACTIVITIES

Demolition activities are not there in the Main Air Blower

because it’s totally new blower and the separate location.

13.2.2. PRE-SHUTDOWN DEMOLITION REFERENCE DOCUMENTS

Equipment drawings & Documents:

------------------Nil----------------

General Drawings & Documents:

------------------Nil----------------

13.2.3. PRE-SHUTDOWN DEMOLITION SCOPE

Sr.N

oDescription Weight(Kg)

Others

01. Equipments ---Nil--- ---Nil---

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 53 of 106

Page 54: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

13.2.4. PRE-SHUTDOWN CONSTRUCTION ACTIVITIES

13.2.4.1. CIVIL FOUNDATIONS

Civil foundations shall be carried as per the civil

construction manual no.:1033-H000-A11000-0008-0811-

0005.

13.2.4.2. EQUIPMENT ERECTION

Main Air Blower to be erection to be carried as per the

reference drawing and Erection specification enclosed with

document.

The Transition piece between the Blower outlets to 550

pipe racks to be done as per the reference drawings.

The alignments of the Rotary and static equipments to be

carried as per the erection specification if the manufacturer

manual not available.

The Manufacturer manual shall be referring the rotary

equipment erection procedures.

13.2.4.3. STRUCTURE ERECTION

Structural Steel Erections shall be carried as per the

construction manual no.:1033-H000-A11000-0008-0811-

0006.

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 54 of 106

PATEL, 09/14/10,
Erection of lube oil system
Page 55: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

13.2.4.4. PIPING & DUCT ERECTION

13.2.4.4.1. Lubrication system piping

The new pipe from Blower lubrication system to Blower

bearing block inlet to be erected with control instruments

and accessories as shown in the drawings

The new pipe from Blower bearing block outlet to Blower

lubrication system be erected with control instruments

and accessories as shown in the drawings

The erection procedures will be as per the enclosed

erection specification

13.2.4.4.2. Utility piping

The new pipe from Blower lubrication system cooler to

plant utility system facility to be erected with control

instruments and accessories as shown in the drawings

The new pipe from blower lubrication system cooler to

plant utility system facility to be erected with control

instruments and accessories as shown in the drawings

All other utility gas pipe lines from blower lubrication

system, blower unit to plant utility system facility to be

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 55 of 106

Page 56: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

erected with control instruments and accessories as

shown in the drawings

The erection procedures will be as per the enclosed

erection specification

13.2.4.4.3. Blower Outlet Duct

The new fabricated duct from Blower outlet to plant pipe

rack 550 facility to be erected with control instruments

and accessories as shown in the drawings

The venting provision from Blower outlet to blower

silencer room open area facility to be erected with control

instruments and accessories as shown in the drawings

The erection procedures will be as per the enclosed

erection specification

13.2.5. COMMISSIONING AND STARTUP ACTIVITIES

All Pressure test and cleaning of piping of lubrication system

and utility system up to hook up point shall be carried as per

the Enclosed erection specification.

Lubrication System test and cleaning shall be carried as per

the enclosed erection specification.

After that the Lubrication system shall be started and

performance shall be checked as per the manufacturer

Manual and specification.

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 56 of 106

Page 57: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

13.2.6. PRE-SHUTDOWN CONSTRUCTION REFERENCE DOCUMENTS

Equipment drawings & Documents:

Vendor Drawings & Manual –

General Drawings & Documents:

Main Air blower assignment drawings

- 1033-H000-A11180-0019-1910-0001

P & ID Drawing:

P & ID drawing for Main Air Blower

- 1033-H000-A11000-0019-1904-0019

13.2.7. PRE-SHUTDOWN CONSTRUCTION SCOPE

Sr.N

oDescription Weight(Kg)

Others

01. Equipments 17000(App)

13.3. SHUT DOWN ACTIVITIES

13.3.1. SHUTDOWN DEMOLITION ACTIVITIES

The demolition works not there during shutdown.

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 57 of 106

Page 58: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

13.3.2. SHUTDOWN CONSTRUCTION ACTIVITIES

13.3.2.1. CIVIL ERECTION

The civil foundation works not there during shutdown.

13.3.2.2. STRUCTURE ERECTION

The structural works not there during shutdown.

13.3.2.3. PIPING ERECTION

13.3.2.3.1. Utility piping

The hook up of the utility piping with existing utility

facilities as per the reference drawing.

The erection procedures will be as per the enclosed

erection specification

13.3.2.4. EQUIPMENT ERECTION

The Equipment Erection works not there during shutdown.

13.4. FINAL COMMISSIONING AND STARTUP ACTIVITIES

All Pressure test and cleaning of piping of lubrication system

and utility system with hook up point shall be carried as per the

Enclosed erection specification.

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 58 of 106

PATEL, 09/14/10,
Motor direction rotation to be checked before coupling Inlet Guide vane to be stroke checked
Page 59: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

After that the Main Air Blower system shall be started and

performance shall be checked as per the manufacturer Manual

and specification.

Note: Before starting the Main Air Blower the Downstream

system all activities should be completed and hook up with

reformer should be completed.

14. AUXILIARY AIR BLOWER

14.1. SCOPE OF WORK

14.1.1. The work involves the following activities demolition of existing

main air blower, its duct and construction of New Aux Air Blower,

its duct for the DR-1 plant up gradation.

Demolition of the Existing main air Blower & its duct

Prefabrication, assembly and Supply

Construction

Tie in activities

Start up & Commissioning

14.1.2. The Main activities are consisting of but not limited to the

following:

Demolition of the Existing main air blower & its Duct.

Pre shut down fabrication, assembly & erection as per the scope

specified herein.

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 59 of 106

Page 60: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

Installation of new Main Air Blower including civil, structure, piping

and refractory work.

14.2. PRE-SHUTDOWN ACTIVITIES

14.2.1. PRE-SHUTDOWN DEMOLITION ACTIVITIES

There are no demolition activities in pre-shutdown activities.

14.2.2. PRE-SHUTDOWN CONSTRUCTION ACTIVITIES

14.2.2.1. CIVIL FOUNDATIONS

Civil foundations shall be carried as per the civil

construction manual no.:1033-H000-A11000-0008-0811-

0005.

14.2.2.2. EQUIPMENT ERECTION

The new auxiliary air blower to be shift at site

The preassembly required with silencer and blower shall

be carried.

14.2.2.3. STRUCTURE ERECTION

Structure Erection shall be carried as per the construction

manual no.:1033-H000-A11000-0008-0811-0006.

14.2.2.4. PIPING & DUCT ERECTION

14.2.2.4.1. Utility piping

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 60 of 106

Page 61: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

All other utility gas pipe lines from blower unit to plant

utility system facility to be erected with control

instruments and accessories as shown in the drawings

The erection procedures will be as per the enclosed

erection specification

14.2.2.4.2. Blower Outlet Duct

The new fabricated duct from Blower outlet to reformer

auxiliary air header and the bypass line from pipe rack

550 and dilution line shall be erected with control

instruments and accessories as shown in the drawings

The venting provision from Blower outlet to open area

facility to be erected with control instruments and

accessories as shown in the drawings

The erection procedures will be as per the enclosed

erection specification

14.2.3. PRE-SHUTDOWN COMMISSIONING AND STARTUP ACTIVITIES

All Pressure test and cleaning of piping of utility system up to hook

up point shall be carried as per the Enclosed erection specification.

The outlet duct and bypass line for the main air duct and the

dilution air duct shall be clean and test shall be carried as per the

reference drawings.

Venting line clean and test shall be carried.

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 61 of 106

Page 62: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

All controls in the duct except the auxiliary TV-B22 shall be check

and clear for the further process.

14.2.4. PRE-SHUTDOWN CONSTRUCTION REFERENCE DOCUMENTS

Equipment drawings & Documents:

------------------Nil---------------------

General Drawings & Documents:

----------------Nil--------------------

14.2.5. PRE-SHUTDOWN CONSTRUCTION SCOPE

Sr.N

oDescription Weight(Kg)

Others

01. Equipments ---Nil---

14.3. SHUT DOWN ACTIVITIES

14.3.1. SHUTDOWN-DEMOLITION ACTIVITIES

Demolition activities to be carried as per the reference drawing &

instruction as per the site Engineer.

The existing main air blower removal with connecting equipments,

ducts, pipes to be demolish and area to be made free for the

Aux.air blower at level of GL +1753 (EL

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 62 of 106

Page 63: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

+32233),GL+970(EL+31450). After dismantling of all equipments,

ducts, pipes to be removed and to be shifted to designated area.

Area to be demolished is marked in the drawing.

During the demolition activities take care of the running existing

connecting lines, equipments.

Safety procedure to be follow as per the QSC procedure & Site

engineer requirement.

And the Heavy & rotary equipments dismantling to be done as per

the equipment manufacturer manual & the site engineer

requirement

14.3.2. SHUTDOWN-DEMOLITION REFERENCE DOCUMENTS

Equipment drawings & Documents:

Existing Main Air blower - 76-0030

General Drawings & Documents:

------------------Nil----------------

14.3.3. SHUTDOWN-DEMOLITION SCOPE

Sr.N

oDescription Weight(Kg)

Others

01. Equipments 12000(QSC)

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 63 of 106

Page 64: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

14.3.4. SHUTDOWN-CONSTRUCTION ACTIVITIES

14.3.4.1. CIVIL ERECTION

Civil foundations shall be carried as per the civil

construction manual no.:1033-H000-A11000-0008-0811-

0005.

14.3.4.2. STRUCTURE ERECTION

Structural Erection shall be carried as per the construction

manual no.:1033-H000-A11000-0008-0811-0006.

14.3.4.3. PIPING ERECTION

14.3.4.3.1. Utility piping

The hook up of the utility piping with existing utility

facilities as per the reference drawing.

The erection procedures will be as per the enclosed

erection specification

14.3.4.4. EQUIPMENT ERECTION

New auxiliary air blower to be erection to be carried as per

the reference drawing and Erection specification enclosed

with document.

The Transition piece between the blower outlets to auxiliary

air shall be done as per the reference drawings before the

transition piece erection all alignments of equipments, duct

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 64 of 106

Page 65: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

to done as per the requirement in erection specification

document.

The alignments of the Rotary and static equipments to be

carried as per the erection specification if the manufacturer

manual not available.

The Manufacturer manual shall be referring the rotary

equipment erection procedures.

14.3.5. SHUTDOWN-CONSTRUCTION REFERENCE DOCUMENTS

Equipment drawings & Documents:

Vendor Drawings & Manual -

General Drawings & Documents:

General Arrangement drawings for the Auxiliary Air Blower -

1033-H000-A11180-0019-1910-0002

P & ID Drawings:

P & ID drawing for the Auxiliary Burner System -

1033-H000-A11000-0019-1904-0021

14.3.6. SHUTDOWN-CONSTRUCTION SCOPE

Sr.N

oDescription Weight(Kg)

Others

01. Equipments 8000(App)

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 65 of 106

Page 66: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

14.4. FINAL COMMISSIONING AND STARTUP ACTIVITIES

All Pressure test and cleaning of piping of utility system and the

outlet duct with hook up point shall be carried as per the

Enclosed erection specification.

After that the Auxiliary Air Blower system shall be started and

performance shall be checked as per the manufacturer Manual

and specification.

Note: Before starting the Auxiliary Air Blower the Downstream

system all activities should be completed and hook up with

reformer, heat recovery system should be completed.

15. BSG COMPRESSOR UNIT

15.1. SCOPE OF WORK

15.1.1. The work involves the following activities demolition of existing

desiccant dryer, its piping and construction of New BSG

Compressor, its duct, piping for the DR-1 plant up gradation.

Demolition of the Existing desiccant dryer & its piping

Prefabrication, assembly and Supply

Construction

Tie in activities

Start up & Commissioning

15.1.2. The Main activities are consisting of but not limited to the

following:

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 66 of 106

PATEL, 09/14/10,
Motor direction rotation to be checked before coupling. Inlet Guide vane to be stroke checked
Page 67: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

Demolition of the Existing desiccant dryer & its piping.

Pre shut down fabrication, assembly & erection as per the scope

specified herein.

Installation of new BSG Compressor including civil, structure,

piping and refractory work.

15.2. PRE-SHUTDOWN ACTIVITIES

15.2.1. PRE-SHUTDOWN DEMOLITION ACTIVITIES

There are no demolition activities in pre-shutdown activities.

15.2.2. PRE-SHUTDOWN CONSTRUCTION ACTIVITIES

15.2.2.1. CIVIL FOUNDATIONS

Civil foundations shall be carried as per the civil

construction manual no.:1033-H000-A11000-0008-0811-

0005.

15.2.2.2. EQUIPMENT ERECTION

The new BSG Compressor to be shift at site

The preassembly required with separator, cooler shall be

carried.

15.2.2.3. STRUCTURE ERECTION

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 67 of 106

Page 68: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

Civil foundations shall be carried as per the civil

construction manual no.:1033-H000-A11000-0008-0811-

0005.

15.2.2.4. PIPING ERECTION

15.2.2.4.1. Utility piping

All other utility gas pipe lines from compressor unit to plant

utility system facility to be erected with control instruments

and accessories as shown in the drawings

All water pipe lines from compressor unit,seperater,cooler

to plant utility system facility to be erected with control

instruments and accessories as shown in the drawings

The erection procedures will be as per the enclosed

erection specification

15.2.2.4.2. Compressor Inlet & Outlet Duct

The new pipe from seal gas cooler outlet to new BSG

compressor line shall be erected with control instruments

and accessories as shown in the drawings

The BSG Compressor to water separator pipe and

separator to cooler pipe line shall be erect with control

instruments and accessories as show in the drawings.

BSG cooler to plant facilities pipe line shall be erect with

control instruments and accessories as show in the

drawings.

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 68 of 106

PATEL, 09/14/10,
piping
Page 69: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

The venting provision from compressor outlet to open area

facility to be erected with control instruments and

accessories as shown in the drawings

The erection procedures will be as per the enclosed

erection specification

15.2.3. PRE-SHUTDOWN COMMISSIONING AND STARTUP ACTIVITIES

All Pressure test and cleaning of piping of utility system up to hook

up point shall be carried as per the Enclosed erection specification.

The inlet, outlet line for the BSG compressor shall be clean and

test shall be carried as per the reference drawings.

Venting line clean and test shall be carried.

All controls in the duct shall be check and clear for the further

process.

15.2.4. PRE-SHUTDOWN CONSTRUCTION REFERENCE DOCUMENTS

Equipment drawings & Documents:

-------------Nil--------------

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 69 of 106

Page 70: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

General Drawings & Documents:

------------Nil------------

15.2.5. PRE-SHUTDOWN CONSTRUCTION SCOPE

Sr.N

oDescription Weight(Kg)

Others

01. Equipments ----Nil----

15.3. SHUT DOWN ACTIVITIES

15.3.1. SHUTDOWN-DEMOLITION ACTIVITIES

Demolition activities to be carried as per the reference drawing &

instruction as per the site Engineer.

The existing desiccant dryer removal with connecting equipments,

ducts, pipes to be demolish and area to be made free for the new

BSG compressor at level of GL +300 (EL +30480). After

dismantling of all equipments, pipes to be removed and to be

shifted to designated area. Area to be demolished is marked in the

drawing.

During the demolition activities take care of the running existing

connecting lines, equipments.

Safety procedure to be follow as per the QSC procedure & Site

engineer requirement.

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 70 of 106

Page 71: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

And the Heavy & rotary equipments dismantling to be done as per

the equipment manufacturer manual & the site engineer

requirement

15.3.2. SHUTDOWN-DEMOLITION REFERENCE DOCUMENTS

Equipment drawings & Documents:

-----------------Nil-----------------

General Drawings & Documents:

Equipment Arrangement Plan Blower Area-

3134-G3-03

15.3.3. SHUTDOWN-DEMOLITION SCOPE

Sr.N

oDescription Weight(Kg)

Others

01. Equipments 5000(QSC)

15.3.4. SHUTDOWN-CONSTRUCTION ACTIVITIES

15.3.4.1. CIVIL ERECTION

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 71 of 106

Page 72: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

Civil foundations shall be carried as per the civil

construction manual no.:1033-H000-A11000-0008-0811-

0005.

15.3.4.2. STRUCTURE ERECTION

Structural Erection shall be carried as per the construction

manual no.:1033-H000-A11000-0008-0811-0006.

15.3.4.3. PIPING ERECTION

15.3.4.3.1. Utility piping

The hook up of the utility piping with existing utility

facilities as per the reference drawing.

The inlet, outlet pipe line from the BSG compressor to

plant facilities shall be hook up as per the enclosed

erection specification.

The erection procedures will be as per the enclosed

erection specification

15.3.4.4. EQUIPMENT ERECTION

New BSG compressor unit to be erection to be carried as

per the reference drawing and Erection specification

enclosed with document.

The connecting piece between the compressor inlet, outlets

to pipe line shall be done as per the reference drawings

before the connecting piece erection all alignments of

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 72 of 106

Page 73: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

equipments, pipe to done as per the requirement in

erection specification document.

The alignments of the Rotary and static equipments to be

carried as per the erection specification if the manufacturer

manual not available.

The Manufacturer manual shall be referring the rotary

equipment erection procedures.

15.3.5. SHUTDOWN-CONSTRUCTION REFERENCE DOCUMENTS

Equipment drawings & Documents:

Vendor Drawings & Manual -

P & ID Drawings:

P & ID for BSG Compressor-

1033-H000-A11000-0019-1904-0029

General Drawings & Documents:

General Plan of Blower House-

1033-H000-A11260-0019-1909-0001

15.3.6. SHUTDOWN-CONSTRUCTION SCOPE

Sr.N Description Weight(Kg) Others

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 73 of 106

Page 74: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

o

01. Equipments 10000(App)

15.4. FINAL COMMISSIONING AND STARTUP ACTIVITIES

All Pressure test and cleaning of piping of utility system and the

inlet, outlet pipe with hook up point shall be carried as per the

Enclosed erection specification.

After that the BSG compressor system shall be started and

performance shall be checked as per the manufacturer Manual

and specification.

Note: Before starting the BSG compressor unit the Upstream,

Downstream system all activities should be completed and hook

up with seal gas cooler, furnace system should be completed.

16. FIRST STAGE PROCESS GAS COMPRESSOR

16.1. SCOPE OF WORK

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 74 of 106

Page 75: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

16.1.1. The work involves the following activities demolition of existing

first stage compressor gearboxes, motors, gearbox lubrication

system & its piping, silencers & its duct and construction of New

Compressor gearboxes, motors, gearbox lubrication system & its

piping, silencers & its duct for the DR-1 plant up gradation.

Demolition of the Existing first stage compressor gearboxes,

motors, gearbox lubrication system & its piping, silencers & its duct

Prefabrication, assembly and Supply

Construction

Tie in activities

Start up & Commissioning

16.1.2. The Main activities are consisting of but not limited to the

following:

Demolition of the Existing first stage compressor gearboxes,

motors, gearbox lubrication system & its piping, silencers & its

duct.

Pre shut down fabrication, assembly & erection as per the scope

specified herein.

Installation of new Compressor gearboxes, motors, gearbox

lubrication system & its piping, silencers & its duct including civil,

structure, piping work.

16.2. PRE-SHUTDOWN ACTIVITIES

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 75 of 106

Page 76: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

16.2.1. PRE-SHUTDOWN DEMOLITION ACTIVITIES

There are no demolition activities in pre-shutdown activities.

16.2.2. PRE-SHUTDOWN CONSTRUCTION ACTIVITIES

16.2.2.1. CIVIL FOUNDATIONS

Civil foundations shall be carried as per the civil

construction manual no.:1033-H000-A11000-0008-0811-

0005.

16.2.2.2. EQUIPMENT ERECTION

The new PG Compressor gearboxes,motor,gearbox

lubrication system to be shift at site

The preassembly required for gearbox input/output

couplings motor half coupling shall be carried.

16.2.2.3. STRUCTURE ERECTION

Structural Erection shall be carried as per the construction

manual no.:1033-H000-A11000-0008-0811-0006.

16.2.2.4. PIPING ERECTION

16.2.2.4.1. Utility piping

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 76 of 106

Page 77: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

All other utility gas pipe lines from compressor unit to plant

utility system facility to be erected with control instruments

and accessories as shown in the drawings

All water pipe lines from compressor unit,silencer,cooler to

plant utility system facility to be erected with control

instruments and accessories as shown in the drawings

The erection procedures will be as per the enclosed

erection specification

16.2.3. PRE-SHUTDOWN COMMISSIONING AND STARTUP ACTIVITIES

All Pressure test and cleaning of piping of utility system up to hook

up point shall be carried as per the Enclosed erection specification.

All controls in the duct shall be check and clear for the further

process.

16.2.4. PRE-SHUTDOWN CONSTRUCTION REFERENCE DOCUMENTS

Equipment drawings & Documents:

-------------------Nil---------------

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 77 of 106

Page 78: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

General Drawings & Documents:

-------------------Nil---------------

16.2.5. PRE-SHUTDOWN CONSTRUCTION SCOPE

Sr.N

oDescription Weight(Kg)

Others

01. Equipments ----Nil----

16.3. SHUT DOWN ACTIVITIES

16.3.1. SHUTDOWN-DEMOLITION ACTIVITIES

Demolition activities to be carried as per the reference drawing &

instruction as per the site Engineer.

The existing gearbox, gearbox lubrication system & its piping,

silencer removal with connecting equipments, ducts, pipes to be

demolish and area to be made free for the new gearboxes,

gearbox lube oil system & its piping, silencer & its piping at its

corresponding level. After dismantling of all equipments, pipes to

be removed and to be shifted to designated area. Area to be

demolished is marked in the drawing.

During the demolition activities take care of the running existing

connecting lines, equipments.

Safety procedure to be follow as per the QSC procedure & Site

engineer requirement.

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 78 of 106

Page 79: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

And the Heavy & rotary equipments dismantling to be done as per

the equipment manufacturer manual & the site engineer

requirement

16.3.2. SHUTDOWN-DEMOLITION REFERENCE DOCUMENTS

Equipment drawings & Documents:

Dimensional Drawing of Existing Gearbox-

1905507.

Existing Motor Drawing-

3AFB 5236832

Existing Silencer Drawing-

DR-V1468-1

General Drawings & Documents:

Equipment Arrangement Area Section I – I

3134-G3-05

Equipment Arrangement Area Section 2 – 2

3134-G3-06

16.3.3. SHUTDOWN-DEMOLITION SCOPE

Sr.N

oDescription Weight(Kg)

Others

01. Equipments 30000

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 79 of 106

Page 80: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

16.3.4. SHUTDOWN-CONSTRUCTION ACTIVITIES

16.3.4.1. CIVIL ERECTION

Civil foundations shall be carried as per the civil construction

manual no.:1033-H000-A11000-0008-0811-0005.

16.3.4.2. STRUCTURE ERECTION

Structural Erection shall be carried as per the construction

manual no.:1033-H000-A11000-0008-0811-0006.

16.3.4.3. PIPING ERECTION

16.3.4.3.1. Lubrication system piping

The new pipe from compressor gearbox lubrication

system to cooler inlet to be erected with control

instruments and accessories as shown in the drawings

The new pipe from cooler outlet to compressor gearbox

lubrication system be erected with control instruments

and accessories as shown in the drawings

The erection procedures will be as per the enclosed

erection specification

16.3.4.3.2. Utility piping

The hook up of the utility piping with existing utility

facilities as per the reference drawing.

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 80 of 106

Page 81: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

The inlet, outlet pipe line from the compressor unit to

plant facilities shall be hook up as per the enclosed

erection specification.

The erection procedures will be as per the enclosed

erection specification

16.3.4.4. EQUIPMENT ERECTION

New compressor gearboxes, silencer, gearbox lubrication

system to be erection to be carried as per the reference

drawing and Erection specification enclosed with document.

The connecting piece between the compressor inlet, outlets

to pipe line shall be done as per the reference drawings

before the connecting piece erection all alignments of

equipments, pipe to done as per the requirement in erection

specification document.

The alignments of the Rotary and static equipments to be

carried as per the erection specification if the manufacturer

manual not available.

The Manufacturer manual shall be referring the rotary

equipment erection procedures.

16.3.5. SHUTDOWN-CONSTRUCTION REFERENCE DOCUMENTS

Equipment drawings & Documents:

Vendor Drawings & Manual for Gearbox -

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 81 of 106

Page 82: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

Vendor Drawings & Manual for Motor -

Silencer Drawings-

General Drawings & Documents:

GA Drawing for Process gas Compressor -

1033-H000-A11260-0019-1917-0001

P & ID Drawing:

P & ID Drawing for 1st stage (K-A48A)-

1033-H000-A11000-0019-1904-0005

P & ID Drawing for 1st stage (K-A48B)-

1033-H000-A11000-0019-1904-0006

16.3.6. SHUTDOWN-CONSTRUCTION SCOPE

Sr.N

oDescription Weight(Kg)

Others

01. Equipments 40000(App)

16.4. FINAL COMMISSIONING AND STARTUP ACTIVITIES

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 82 of 106

Page 83: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

All Pressure test and cleaning of piping of utility system and the

inlet, outlet pipe with hook up point shall be carried as per the

Enclosed erection specification.

After that the compressor system shall be started and

performance shall be checked as per the manufacturer Manual

and specification.

Note: Before starting the compressor unit the Upstream,

Downstream system all activities should be completed and hook

up with process gas system and furnace should be completed.

17. SECOND STAGE COMPRESSOR

17.1. SCOPE OF WORK

17.1.1. The work involves the following activities demolition of existing

second stage compressor, compressor lubrication system & its

piping, gearbox, motor, gearbox lubrication system & its piping,

silencer & its duct and construction of new compressor,

compressor lubrication system & its piping,gearbox,motor,gearbox

lubrication system & its piping, silencers & its duct for the DR-1

plant up gradation.

Demolition of the Existing second stage compressor, compressor

lubrication system & its piping, gearbox, motor, gearbox lubrication

system & its piping, silencer & its duct.

Prefabrication, assembly and Supply

Construction

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 83 of 106

Page 84: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

Tie in activities

Start up & Commissioning

17.1.2. The Main activities are consisting of but not limited to the

following:

Demolition of the Existing second stage compressor, compressor

lubrication system & its piping, gearbox, motor, gearbox lubrication

system & its piping, silencer & its duct.

Pre shut down fabrication, assembly & erection as per the scope

specified herein.

construction of new compressor, compressor lubrication system &

its piping, gearbox, motor, gearbox lubrication system & its piping,

silencers & its duct including civil, structure, piping work.

17.2. PRE-SHUTDOWN ACTIVITIES

17.2.1. PRE-SHUTDOWN DEMOLITION ACTIVITIES

There are no demolition activities in pre-shutdown activities.

17.2.2. PRE-SHUTDOWN CONSTRUCTION ACTIVITIES

17.2.2.1. CIVIL FOUNDATIONS

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 84 of 106

Page 85: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

Civil foundations shall be carried as per the civil

construction manual no.:1033-H000-A11000-0008-0811-

0005.

17.2.2.2. EQUIPMENT ERECTION

The new compressor, compressor lubrication system parts

gearbox, motor, gearbox lubrication system, silencer to be

shift at site.

The preassembly required for compressor coupling,

gearbox input/output couplings motor half coupling shall be

carried.

17.2.2.3. STRUCTURE ERECTION

Structural Erection shall be carried as per the construction

manual no.:1033-H000-A11000-0008-0811-0006.

17.2.2.4. PIPING ERECTION

17.2.2.4.1. Utility piping

All other utility gas pipe lines from compressor unit to

plant utility system facility to be erected with control

instruments and accessories as shown in the drawings

All water pipe lines from compressor unit,silencer,cooler

to plant utility system facility to be erected with control

instruments and accessories as shown in the drawings

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 85 of 106

Page 86: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

The erection procedures will be as per the enclosed

erection specification

17.2.3. PRE-SHUTDOWN COMMISSIONING AND STARTUP ACTIVITIES

All Pressure test and cleaning of piping of utility system up to hook

up point shall be carried as per the Enclosed erection specification.

All controls in the duct shall be check and clear for the further

process.

17.2.4. PRE-SHUTDOWN ERECTION REFERENCE DOCUMENTS

Equipment drawings & Documents:

----------Nil--------------

General Drawings & Documents:

-----------Nil--------------

17.2.5. PRE-SHUTDOWN CONSTRUCTION SCOPE

Sr.N

oDescription Weight(Kg)

Others

01. Equipments ----Nil----

17.3. SHUT DOWN ACTIVITIES

17.3.1. SHUTDOWN DEMOLITION ACTIVITIES

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 86 of 106

Page 87: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

Demolition activities to be carried as per the reference drawing &

instruction as per the site Engineer.

The existing compressor, compressor lubrication system & its

piping, gearbox, gearbox lubrication system & its piping, silencer

removal with connecting equipments, ducts, pipes to be demolish

and area to be made free for the new compressor, gearbox,

gearbox lube oil system & its piping, silencer & its piping at its

corresponding level. After dismantling of all equipments, pipes to

be removed and to be shifted to designated area. Area to be

demolished is marked in the drawing.

During the demolition activities take care of the running existing

connecting lines, equipments.

Safety procedure to be follow as per the QSC procedure & Site

engineer requirement.

And the Heavy & rotary equipments dismantling to be done as per

the equipment manufacturer manual & the site engineer

requirement

17.3.2. SHUTDOWN-DEMOLITION REFERENCE DOCUMENTS

Equipment drawings & Documents:

Dimensional Drawing of Existing Gearbox-

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 87 of 106

Page 88: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

1905507.

Existing Motor Drawing-

3AFB 5236832

Existing Silencer Drawing-

SIBL-910

General Drawing for 3649 RGS-VJ Unit-

84867013

General Drawings & Documents:

Equipment Arrangement Area Section I – I

3134-G3-05

Equipment Arrangement Area Section 2 – 2

3134-G3-06

17.3.3. SHUTDOWN-DEMOLITION SCOPE

Sr.N

oDescription Weight(Kg)

Others

01. Equipments 50000

17.3.4. SHUTDOWN-CONSTRUCTION ACTIVITIES

17.3.4.1. CIVIL ERECTION

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 88 of 106

Page 89: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

Civil foundations shall be carried as per the civil

construction manual no.:1033-H000-A11000-0008-0811-

0005.

17.3.4.2. STRUCTURE ERECTION

Structural Erection shall be carried as per the construction

manual no.:1033-H000-A11000-0008-0811-0006.

17.3.4.3. PIPING ERECTION

17.3.4.3.1. Lubrication system piping

The new pipe from compressor lubrication unit to

compressor inlet, compressor gearbox lubrication

system to cooler inlet to be erected with control

instruments and accessories as shown in the drawings

The new pipe from compressor outlet to compressor

lubrication system, cooler outlet to compressor gearbox

lubrication system be erected with control instruments

and accessories as shown in the drawings

The erection procedures will be as per the enclosed

erection specification

17.3.4.3.2. Utility piping

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 89 of 106

Page 90: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

The hook up of the utility piping with existing utility

facilities as per the reference drawing.

The inlet, outlet pipe line from the compressor unit to

plant facilities shall be hook up as per the enclosed

erection specification.

The erection procedures will be as per the enclosed

erection specification

17.3.4.4. EQUIPMENT ERECTION

New compressor, compressor lubrication system,

compressor gearbox, silencer, gearbox lubrication system

to be erection to be carried as per the reference drawing

and Erection specification enclosed with document.

The connecting piece between the compressor inlet,

outlets to pipe line shall be done as per the reference

drawings before the connecting piece erection all

alignments of equipments, pipe to done as per the

requirement in erection specification document.

The alignments of the Rotary and static equipments to be

carried as per the erection specification if the manufacturer

manual not available.

The Manufacturer manual shall be referring the rotary

equipment erection procedures.

17.3.5. SHUTDOWN-CONSTRUCTION REFERENCE DOCUMENTS

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 90 of 106

Page 91: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

Equipment drawings & Documents:

Vendor Drawing & Manual for Compressor-

Vendor Drawing & Manual for gearbox-

Vendor Drawing & Manual for Motor-

Silencer Drawings-

P & ID Drawing:

P & ID Drawing for the 2nd stage (K-A51)-

1033-H000-A11000-0019-1904-0007

General Drawings & Documents:

General Arrangement drawing of PGC 2nd Stage-

17.3.6. SHUTDOWN-CONSTRUCTION SCOPE

Sr.N

oDescription Weight(Kg)

Others

01. Equipments 60000(App)

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 91 of 106

Page 92: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

17.4. FINAL COMMISSIONING AND STARTUP ACTIVITIES

All Pressure test and cleaning of piping of utility system and the

inlet, outlet pipe with hook up point shall be carried as per the

Enclosed erection specification.

After that the compressor system shall be started and

performance shall be checked as per the manufacturer Manual

and specification.

Note: Before starting the compressor unit the Upstream,

Downstream system all activities should be completed and hook

up with process gas system and furnace should be completed.

18. FURNACE HYDRAULIC ROOM & HYDRAULIC UNIT

18.1. SCOPE OF WORK

18.1.1. The work involves the following activities demolition of existing

hydraulic unit and tubing from the hydraulic unit to individual

cylinder and individual cylinder to hydraulic unit, accumulator unit

and construction of new hydraulic unit, valve stands, hydraulic

room, hydraulic room hoist, tubing from hydraulic unit to valve

stands, tubing from valve stands to individual cylinders & its return

lines tubing to valve stands, return lines from valve stands to

hydraulic unit, all supports for the tubing’s for the DR-1 plant up

gradation.

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 92 of 106

Page 93: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

Demolition of the Existing hydraulic unit and tubing from the

hydraulic unit to individual cylinder and individual cylinder to

hydraulic unit, accumulator unit.

Prefabrication, assembly and Supply

Construction

Tie in activities

Start up & Commissioning

18.1.2. The Main activities are consisting of but not limited to the

following:

Demolition of the Existing hydraulic unit and tubing from the

hydraulic unit to individual cylinder and individual cylinder to

hydraulic unit, accumulator unit.

Pre shut down fabrication, assembly & erection as per the scope

specified herein.

Construction of new hydraulic unit, valve stands, hydraulic room,

hydraulic room hoist, tubing from hydraulic unit to valve stands,

tubing from valve stands to individual cylinders & its return lines

tubing to valve stands, return lines from valve stands to hydraulic

unit, all supports for the tubing’s including civil, structure, piping

work.

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 93 of 106

Page 94: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

18.2. PRE-SHUTDOWN ACTIVITIES

18.2.1. PRE-SHUTDOWN DEMOLITION ACTIVITIES

There are no demolition activities in pre-shutdown activities.

18.2.2. PRE-SHUTDOWN CONSTRUCTION ACTIVITIES

18.2.2.1. CIVIL FOUNDATIONS

Civil foundations shall be carried as per the civil

construction manual no.:1033-H000-A11000-0008-0811-

0005.

18.2.2.2. EQUIPMENT ERECTION

The new hydraulic unit, valve stands, Hoist erection shall

be carried after the completion of the civil & structure

activities.

The alignments of the Rotary and static equipments to be

carried as per the erection specification if the manufacturer

manual not available.

The Manufacturer manual shall be referring the rotary

equipment erection procedures.

18.2.2.3. STRUCTURE ERECTION

Structure Erection shall be carried as per the construction

manual no.:1033-H000-A11000-0008-0811-0006.

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 94 of 106

Page 95: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

18.2.2.4. PIPING & TUBING ERECTION

18.2.2.4.1. Hydraulic Tubing’s

Once the hydraulic unit erection was completed the

tubing from the hydraulic unit to valve stands and valve

stands to individual cylinders hook up point at different

elevation shall be carried as per the drawings &

specifications.

The all tubing supports shall be carried as per the

drawings & specifications.

All tubing’s shall be carried with all instruments &

accessories (Hoses, clamps).

During the tubing erection all running equipments and

running lines shall be protect from the damage.

18.2.2.4.2. Utility piping

All water pipe lines from hydraulic unit, to plant utility

system facility to be erected with control instruments and

accessories as shown in the drawings

The erection procedures will be as per the enclosed

erection specification

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 95 of 106

Page 96: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

18.2.3. PRE-SHUTDOWN COMMISSIONING AND STARTUP ACTIVITIES

The testing of the hydraulic room hoist shall be carried as per the

enclosed specification and manufacturer manuals.

All Pressure test and cleaning of hydraulic tubing’s, cooling water

piping up to hook up point shall be carried as per the Enclosed

erection specification.

The hydraulic unit cleaning shall be carried as per the

specifications.

During the hydraulic tube cleaning the NASS value must attain 5

for the tubing surface.

The Hydraulic unit performance test shall be carried as per the

manufacturer manual once the tubing testing completed.

All controls in the system shall be check and clear for the further

process.

18.2.4. PRE-SHUTDOWN CONSTRUCTION REFERENCE DOCUMENTS

Equipment drawings & Documents:

Vendor Drawings for the Hydraulic System-

Vendor Drawings for the Hoist

General Drawings & Documents:

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 96 of 106

Page 97: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

General Arrangement Drawing of Furnace hydraulic system-

P & ID Drawing:

P& ID Drawing of Cluster Breaker hydraulic unit-

1033-H000-A11000-0019-1904-0003

18.2.5. PRE-SHUTDOWN CONSTRUCTION SCOPE

Sr.N

oDescription Weight(Kg)

Others

01. Equipments 13000(App)

18.3. SHUT DOWN ACTIVITIES

18.3.1. SHUTDOWN-DEMOLITION ACTIVITIES

Demolition activities to be carried as per the reference drawing &

instruction as per the site Engineer.

The existing hydraulic unit and tubing from the hydraulic unit to

individual cylinder and individual cylinder to hydraulic unit,

accumulator unit to be demolish area to be made free. After

dismantling of all equipments, pipes to be removed and to be

shifted to designated area. Area to be demolished is marked in the

drawing.

During the demolition activities take care of the running existing

connecting lines, equipments.

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 97 of 106

Page 98: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

Safety procedure shall be follow as per the QSC requirements &

Site engineer requirement.

And the Heavy & rotary equipments dismantling to be done as per

the equipment manufacturer manual & the site engineer

requirement

18.3.2. SHUTDOWN-DEMOLITION REFERENCE DOCUMENTS

Equipment drawings & Documents:

Hydraulic Unit schematic Drawing-

3134-F1-215

Lower & wiper bar cluster breaker-

SIFU-402

Middle, Upper cluster breaker & Slide Gates-

SIFU-401

General Drawings & Documents:

------------------Nil----------------

18.3.3. SHUTDOWN-DEMOLITION SCOPE

Sr.N

oDescription Weight(Kg)

Others

01. Equipments QSC

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 98 of 106

Page 99: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

18.3.4. SHUTDOWN-CONSTRUCTION ACTIVITIES

18.3.4.1. CIVIL ERECTION

Civil foundations shall be carried as per the civil

construction manual no.:1033-H000-A11000-0008-0811-

0005.

18.3.4.2. STRUCTURE ERECTION

Structural Erection shall be carried as per the construction

manual no.:1033-H000-A11000-0008-0811-0006.

18.3.4.3. PIPING ERECTION

18.3.4.3.1. Hydraulic Tubing’s

Only the tubing’s which are not completed during the

running time shall be carried at different elevation as per

the drawings & specifications.

The tubing’s Hydraulic cylinder ends shall be connected

with the hydraulic cylinders.

18.3.4.3.2. Utility piping

The hook up of the utility piping with existing utility

facilities as per the reference drawing.

The erection procedures will be as per the enclosed

erection specification

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 99 of 106

Page 100: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

18.3.4.4. EQUIPMENT ERECTION

The equipment erection works not there during shutdown.

18.3.5. SHUTDOWN-CONSTRUCTION REFERENCE DOCUMENTS

Equipment drawings & Documents:

-----------Nil-----------

General Drawings & Documents:

-----------Nil---------

18.3.6. SHUTDOWN-CONSTRUCTION SCOPE

Sr.N

oDescription Weight(Kg)

Others

01. Equipments ----Nil----

18.4. FINAL COMMISSIONING AND STARTUP ACTIVITIES

All Pressure test and cleaning of tubing’s, utility piping with hook

up point shall be carried as per the enclosed erection

specification if required.

After that the total hydraulic system shall be started and

performance shall be checked as per the manufacturer Manual

and specification.

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 100 of 106

Page 101: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

Note: Before starting the hydraulic unit the cluster breakers,

slide gates activities should be check with furnace system.

19. EXISTING DILUTION AIR BLOWER DEMOLITION

19.1. SCOPE OF WORK

19.1.1. The work involves the following activities demolition of Existing

dilution air blower & its piping for the DR-1 plant up gradation.

Preparation for demolition

Demolition

Shifting the equipments to safe place.

19.1.2. The Main activities are consisting of but not limited to the

following:

Pre shut down preparations for the demolition of existing dilution

air blower & its piping as per the scope specified herein.

19.2. PRE-SHUTDOWN ACTIVITIES

The required tools & tackles shall be prepared for the demolition.

Shifting of the required materials to site.

Preparation of Approaches for the demolition works.

19.3. SHUT DOWN ACTIVITIES

19.3.1. EQUIPMENT DEMOLITION

The existing dilution air blower Motor electrical connection

shall be demolished as per the standard procedures.

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 101 of 106

Page 102: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

And the electrical cables, control cables from the existing

plant facilities to the equipment shall demolished as per the

standard procedure.

And then the electrical motor, blower shall be demolished

from the existing foundations.

During the demolition activities take care of the running

existing connecting lines, equipments.

Safety procedure shall be follow as per the QSC

requirements & Site engineer requirement.

All instruments shall be demolished.

19.3.2. STRUCTURE DEMOLITION

Structural Erection shall be carried as per the construction

manual no.:1033-H000-A11000-0008-0811-0006.

19.3.3. PIPING DEMOLITION

The all utility pipe lines from the plant facilities to dilution air

blower shall be demolished or modified as per the hook up

drawings and reference drawings.

The outlet pipes from the dilution air blower to the flue gas

mixer shall be demolished as per the standard procedure.

The all valves and fittings shall be demolished as per the site

engineer instructions and reference drawings.

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 102 of 106

Page 103: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

All control cables for the piping instruments shall be

demolished or modified as per the reference drawings.

19.4. SHUTDOWN-DEMOLITION REFERENCE DOCUMENTS

Equipment drawings & Documents:

Assembly drawing for Dilution Air fan-

76-0114-C

General Drawings & Documents:

------------------Nil----------------

19.5. SHUTDOWN-DEMOLITION SCOPE

Sr.N

oDescription Weight(Kg)

Others

01. Equipments 6000(QSC)

20. EXISTING AUXILIARY AIR BLOWER DEMOLITION

20.1. SCOPE OF WORK

20.1.1. The work involves the following activities demolition of Existing

Auxiliary air blower & its piping for the DR-1 plant up gradation.

Preparation for demolition

Demolition

Shifting the equipments to safe place.

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 103 of 106

Page 104: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

20.1.2. The Main activities are consisting of but not limited to the

following:

Pre shut down preparations for the demolition of existing Auxiliary

air blower & its piping as per the scope specified herein.

20.2. PRE-SHUTDOWN ACTIVITIES

The required tools & tackles shall be prepared for the demolition.

Shifting of the required materials to site.

Preparation of Approaches for the demolition works.

20.3. SHUT DOWN ACTIVITIES

20.3.1. EQUIPMENT DEMOLITION

The existing Auxiliary air blower Motor electrical connection

shall be demolished as per the standard procedures.

And the electrical cables, control cables from the existing

plant facilities to the equipment shall demolished as per the

standard procedure.

And then the electrical motor, blower shall be demolished

from the existing foundations.

During the demolition activities take care of the running

existing connecting lines, equipments.

Safety procedure shall be follow as per the QSC

requirements & Site engineer requirement.

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 104 of 106

Page 105: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

All instruments shall be demolished.

20.3.2. STRUCTURE DEMOLITION

Structural Erection shall be carried as per the construction

manual no.:1033-H000-A11000-0008-0811-0006.

20.3.3. PIPING DEMOLITION

The all utility pipe lines from the plant facilities to Auxiliary air

blower shall be demolished or modified as per the hook up

drawings and reference drawings.

The outlet pipes from the Auxiliary air blower to the flue gas

mixer shall be demolished as per the standard procedure.

The all valves and fittings shall be demolished as per the site

engineer instructions and reference drawings.

All control cables for the piping instruments shall be

demolished or modified as per the reference drawings.

20.4. SHUTDOWN-DEMOLITION REFERENCE DOCUMENTS

Equipment drawings & Documents:

Assembly Drawing of Auxiliary Air fan-

76-0113

General Drawings & Documents:

------------------Nil----------------

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 105 of 106

Page 106: 1033 H000 A11000 019 XXXX XXXX(Construction Manual for Final) Rev 00

Conf

ident

ial

Up gradation of DR Module 1Mesaieed, Qatar

CONSTRUCTION MANUAL FOR

UPGRADATION PROJECT

ESSAR ENGINERING

SERVICES LTD - HAZIRA

20.5. SHUTDOWN-DEMOLITION SCOPE

Sr.N

oDescription Weight(Kg)

Others

01. Equipments 5000(QSC)

SPEC.NO: 1033-H000-A11000-0019-XXXX-XXXX Rev00 DATE: 14.09.10 Page 106 of 106