Web-PCS – System Guideline - Overview
C. Project Planning - Construction Phase
C1Create Construction Project Using Project
Copy
C1Create Construction Project Using Project
Copy
C2Update the
Project Status
C2Update the
Project Status
C3Related Reports
C3Related Reports
B. Set-up and Plan Project (Project Planning)
B2Create ProjectDetails - WSIP
B2Create ProjectDetails - WSIP
B3Set the
Project Status
B3Set the
Project Status
B5Add Timescale
InformationTo Tasks
B5Add Timescale
InformationTo Tasks
B7Create Risk Assessment
B7Create Risk Assessment
B1Create New Project
Using Project Wizard
B1Create New Project
Using Project Wizard
B6Add Planned
Resources to Tasks
B6Add Planned
Resources to Tasks
B4Complete/Adjust
Project Plan
B4Complete/Adjust
Project Plan
B8Submit
Planned Budget
B8Submit
Planned Budget
B9Approve
Planned Budget
B9Approve
Planned Budget
A. User Set-up Administration – Login & Change Profile
A1Set-up User
Details
A1Set-up User
Details
B10Related Reports
B10Related Reports
2
Web-PCS – System Guideline - Overview
E. Project Control and Reporting - Financial Management & Reporting
E6View WSIP01
Summary
E6View WSIP01
Summary
E5Create WSIP02
Claims
E5Create WSIP02
Claims
E7Submit WSIP05 Claim for Over
Expenditure
E7Submit WSIP05 Claim for Over
Expenditure
E2Enter Approved Cost
Details
E2Enter Approved Cost
Details
E8Submit Final Project Costs and Accounts
E8Submit Final Project Costs and Accounts
E9Related Reports
E9Related Reports
E1Check Project
Interface Details are Created
E1Check Project
Interface Details are Created
E3Enter Approved
Grant
E3Enter Approved
Grant
E4Request FMS
Data
E4Request FMS
Data
F. Project Close Out – Final Status & Accounts
F1Prepare Final Project Status & Accounts & Circulate Reports
F1Prepare Final Project Status & Accounts & Circulate Reports
F2Related Reports
F2Related Reports
D. Project Control & Reporting – Project Management & Reporting
D3Update Task Progression
D3Update Task Progression
D4Record & Update
Project Risks & Issues
D4Record & Update
Project Risks & Issues
D5Related Reports
D5Related Reports
D2Update Construction
Phase PCSDocumentation
D2Update Construction
Phase PCSDocumentation
D1Update
Project Status
D1Update
Project Status
3
Web-PCS – System Guideline - Overview
G. Log Support Ticket to Ticket Resolution - HELPDESKVISION
G1Open Helpdesk Support Ticket
G1Open Helpdesk Support Ticket
G2Assign Ticket to Resource
G2Assign Ticket to Resource
G3Resolve & Close
Call
G3Resolve & Close
Call
4
Login to Training & Live Production Site
Login to Training Site
http://80.93.5.181/projectvision_doe_training/menu.aspx
Enter your user name and password. Login to Live Production Site:
http://80.93.5.181/ProjectVisionDOE/manuallogon.aspx
or navigate from www.wsntg.ie (Select Web-enabled PCS live) Helpdesk:
http://80.93.5.181/helpdeskvisiondoe/
or navigate from www.wsntg.ie (Select web-enabled PCS helpdesk)
5
Section A - Over-View User Set-up Administration – Login & Change Profile
This section tells you the steps you need to logon to the systems and how to change your user profile.
Note:
It is important that you update your profile as ProjectVision can automatically send your password to your email address.
Overview - Business ProcessesA. User Set-up Administration – Login & Change Profile
A1Set-up User
Details
A1Set-up User
Details
A. Set-up User Details – Web PCS ProjectVision
A1. Set-up User Details – Web PCS ProjectVision
A102Select
My ProfileEntry Screen
A102Select
My ProfileEntry Screen
A103Update Email
Address
A103Update Email
Address
• 1) In the “Email Address” field – add your current email address to which you wish to receive System and Helpdesk messages
• 2) Overnight your email address will be synchronised with the HelpdeskVision system
A101Log-on to
Web-PCS in ProjectVision
A101Log-on to
Web-PCS in ProjectVision
• 1) Log-on with the generic Username and Password issued by Cora Systems
• 2) Your Welcome Page Appears - log-on to the system
• 1) To update your details for go-live navigate to the Menu Path: “Utilities/My Profile”
• 2) The “My Profile” entry screen tab is displayed
A104Change
Password
A104Change
Password
• 1) In the “New Password” field – add your chosen password
• 2) In the “Confirm New Password” field – confirm your new chosen password by re-entering it in this field
• 3) Overnight your username and password details will be synchronised with the HelpdeskVision system
A105Save Details
A105Save Details
• 1) If you have completed required changes or updates to your profile – save your entries using the “Update” button located at the bottom of the screen
Project Owner
Project Leader
Project Rights
Management (read only)
WSIP Admin
8
Section B - Over-View Set-up and Plan Project Over-view
This section tells you the steps you need to create a project in the web-PCS system
It shows you the steps required to add mandatory information or data required to support the operation of the project in ProjectVision from status reporting and financial management standpoint
It shows you how to add other optional information you may require that is relevant to the project
It shows you how to schedule and manage your project plan and assign resources
9
Web-PCS – System Guideline – Detailed Steps
B. Set-up and Plan Project (Project Planning)
B2Create ProjectDetails - WSIP
B2Create ProjectDetails - WSIP
B3Set the
Project Status
B3Set the
Project Status
B5Add Timescale
InformationTo Tasks
B5Add Timescale
InformationTo Tasks
B7Create Risk Assessment
B7Create Risk Assessment
B1Create New Project
Using Project Wizard
B1Create New Project
Using Project Wizard
B6Add Planned
Resources to Tasks
B6Add Planned
Resources to Tasks
B4Complete/Adjust
Project Plan
B4Complete/Adjust
Project Plan
B8Submit
Planned Budget
B8Submit
Planned Budget
B9Approve
Planned Budget
B9Approve
Planned Budget
B9Run Related Reports
B9Run Related Reports
10
Step Over-View B1. Create New Project using Project Wizard
The project is created using the Project Wizard functionality in the system from a predefined template
There are 4 templates as follows: Project Template (Consisting of Planning &
Construction) < 5 million (Construction) > 5 million (Construction) Design Build Operate (Construction)
11
B. Project Planning – Planning Phase
B1. Create New Project Using Project Wizard
B101Navigate to Project
Wizard
B101Navigate to Project
Wizard
=
B102Select Target
Directory
B102Select Target
Directory
• Target directory: Select your Local Authority
• What is the Target Directory? This is where you save the project(s) that you create. It is the topmost directory.
• The Directory manages or stores your projects just like a folder so it is used for navigation purposes.
• It is also used for applying access rights to Projects within the system.
• Who does it? The person setting up the project (Admin or Engineer)
B103Select Project
Template to copy
B103Select Project
Template to copy
B104Give New Project a
Name
B104Give New Project a
Name
• New Project Name: Give the project a name that best describes the project e.g. Kilmacross Waste Water.
• In Phase 2, the Project Name will now automatically appear in all the PCS documents from this entry
• The Project Name should be easy to understand and kept to 50 characters or lessThe Project Name will appear in the project drop-down box under the Target Directory once it has been created and on associated Project Reports – it is how the user recognises or identifies their Project.
• Navigate using the Menu Path: Project Planning/Project Wizard
• The “Project Wizard” facility allows you to select the areas from the Project Template that you wish to copy by ticking or un-ticking the options available.
• Directory: Select
Templates.
• The Template Project selected is a predefined project which contains the relevant tasks to run projects with different budgets
• Project: Select the template you wish to use. i.e. Project Template, < 5million, > 5 million, DBO.
• Note: You are copying from the templates directory into your project workspace. For a new project use Project Template
Project Owner
Project Leader
Project Rights
Management (read only)
WSIP Admin
The person who creates a project using project Wizard has Project Owner rights by default. The Project Owner assigns the rights to the other resources in the project. This is a unique function of the Project OwnerThe person who creates a project using project Wizard has Project Owner rights by default. The Project Owner assigns the rights to the other resources in the project. This is a unique function of the Project Owner
12
B. Project Planning – Planning Phase
B1. Create New Project Using Project Wizard
B105Add Project Dates
B105Add Project Dates
• The Project Dates to be added include the Project Start Date i.e.: The date the Project is due to commence and the Project “Live” date. The “Live” date is the date the system will start tracking changes and updates to the Project in the audit trail.
B106Select Project
Parameters to copy
B106Select Project
Parameters to copy
• This section contains the information that we want to populate the template with e.g. what predefined tasks do you want to bring into your template, what rights do you want to set on the project?
B107Select Tasks
to Copy
B107Select Tasks
to Copy
• All Tasks: This contains a set of predefined tasks e.g. Create PQP, Create Preliminary Report, etc.
• The “All Tasks” tick box allows you to look into the Project Template and de-select tasks you do not wish to copy from the Template – These tasks will therefore not be copied over to your new Project
• Note: If you are a new user, leave this box checked. If you need to delete tasks you can do so later.
B108Assign User Rights
B108Assign User Rights
• Rights: Check this radio box to set the project rights i.e. Who has authority to read, write and make changes to the project The authority of the different rights are described in Appendix 1.
B109Create Project
B109Create Project
• The new Project is created using the “Create Project” button at the bottom of the screen.
• The Project should now be available for selection in the navigation window i.e. in the Directory drop down menu and the Project drop down menu.
See Appendix 1See Appendix 1See Appendix 1See Appendix 1
Project Owner
Project Leader
Project Rights
Management (read only)
WSIP Admin
13
B. Project Planning – Planning Phase
B2. Create Project Details - WSIP
B201Navigate to Project
Details - WSIP
B201Navigate to Project
Details - WSIP
• Navigate using the menu:
• Project Planning/ Background
• Note: In this section you set up the WSIP details (e.g. FMS Job Code, Project Reference Number, Local Authority Reference number, Scheme Category, Scheme Sub-category.
B202View the Project
Details
B202View the Project
Details
• From the Project Details Screen you can view:
• Project: Start Date/Finish Date.
• Tasks with status -Tasks Due: Review the tasks that have a due date.
• Planned Resources: Review what resources are planned to complete work.
• Project Status: From here you can set the current status of your project (planning or construction)
B203Enter Project
Reference Number
B203Enter Project
Reference Number
• Navigate using the menu:
• Project Planning/ Background/WSIP details.
• The project reference number is a unique number in the format: 1234567.12 (This will be given to you by the DEHLG)
Note: In Phase 2, this number will automatically appear in all PCS headers once entered in the Project Background section
B204Enter FMS Job Code
B204Enter FMS Job Code
• Enter the FMS Code for your project
• You get this number from your Finance Department
Project Owner
Project Leader
Project Rights
Management (read only)
WSIP Admin
14
B. Project Planning – Planning Phase
B2. Create Project Details - WSIP
B205Enter Local Project
Reference
B205Enter Local Project
Reference
• This is a local project reference number. For example you may have a local filing number.
B206Select Scheme
Category
B206Select Scheme
Category
• Select the “Water” or “Waste Water” Radio Button
• Note: The Scheme Category Report is run by the DEHLG (Navigation: Reports/ WSIP Reports/ Scheme Category
B207Select Scheme Sub-
Category
B207Select Scheme Sub-
Category
• This is a predefined scheme sub-category e.g. Water Treatment Plant.
• Note: The Scheme Sub Category Report is run by the DEHLG (Navigation: Reports/ WSIP Reports/ Scheme Sub-Category
B208Update Details
B208Update Details
• Select: “Update Details” button to save the WSIP details on to your Project.
Project Owner
Project Leader
Project Rights
Management (read only)
WSIP Admin
15
B. Project Planning – Planning Phase
B2. Create Project Details - Other
B209Adding Project
Details
B209Adding Project
Details
• Any background Project Details can be added to the Project Via the “New Details Tab”
• Navigate using the menu:
• Project Planning/ Background
• Note: In this section you add project details. e.g. Project leaders details, contractors details, etc.
B210Predefined Details.
B210Predefined Details.
• Select “Project Leader” from the drop down menu.
• Add the Project leader name.
• Enter the Details and click on “Create Details”
• Note: In Phase 2 the Project Leaders name will automatically appear in the PCS documentation header. All information added in the description window will appear in the header of all PCS Forms
B211DetailB211Detail
• Detail: Create a project detail. Select from drop down menu or add new detail: e.g. Specialist Contractor.
B212Description
B212Description
For example:
• Name: Joe Bloggs
• Email: [email protected]
• Phone: 123456
• Contractor Firm Name
Project Owner
Project Leader
Project Rights
Management (read only)
WSIP Admin
16
B. Project Planning – Planning Phase
B3. Set the Project Status
B301Set Status
B301Set Status
• The Project Status can be set using the “Project Status” Field on the View Details Tab
• Navigate using the menu:
• Project Planning/ Background/Project Status
• Select “Planning” or “Construction”
• Select “Update Project Status" button to save your change
B302Run Traffic Light
Report(Status)
B302Run Traffic Light
Report(Status)
• Navigate using the menu:
• Reports/Portfolio Management/Traffic Light Report
• Select Directory: (This will be your Local Authority)
• Available Status e.g. planning or construction
• To run the report Select “Run Report”
Project Owner
Project Leader
Project Rights
Management (read only)
WSIP Admin
17
B4. Complete/Adjust Project Work Break Down
B401 Create Tasks
B401 Create Tasks
• Menu Path: Project Planning/WBS
• Select “T” icon to add a new task. Click on the task you wish to place the new task beside or underneath. The “Add New Task” Box appears – you can now add your tasks. If you have more than one task to create at this level simply hit the “return” key when mouse is in the new task window to bring up a new entry line.
• When completed, save your work using the Green Tick
B. Project Planning – Planning Phase
B402 Order Tasks
B402 Order Tasks
• Main Tasks or High Level Deliverables should be placed in the order they will be carried out on the WBS.
• Move Tasks on the WBS into the correct order by pointing at the top of the Task.
• Wait for the “Click to Move Task” Box to appear.
• Then Point and Click on the target task you wish to move your task to.
• Then select the appropriate Level
B403 Create Sub–Tasks under
Main Tasks
B403 Create Sub–Tasks under
Main Tasks
• Sub-Tasks can be created underneath the Main Tasks should you wish to manage tasks at a lower level.
• These lower-level tasks are created as Sub-tasks underneath the appropriate Main Tasks (High Level Deliverables).
• Menu Path: Project Planning/ WBS (Work Breakdown Structure): Use the “T” icon and click on the target task that you wish to place the new task underneath.
B404 Delete Tasks
B404 Delete Tasks
• You may wish to delete tasks from the standard template that are not required for this project.
• To do this click on the bin icon. Bin shadow appears on your cursor, point and click on the task or tasks you wish to delete. The shadow will confirm the task reference numbers of the task or tasks you have selected, point and click on the bin icon again (which has now turned red once tasks have been selected). The selected tasks will then be deleted.
• The Add New Task Box appears. Enter tasks. If you have more than one task to create at this level simply hit the “return” key when mouse is in the new task window to bring up a new entry line.
• When completed save your work using the Green Tick in the top right hand corner.
Project Owner
Project Leader
Project Rights
Management (read only)
WSIP Admin
18
B4. Complete/Adjust Project Work Break Down
B405 Create Project
Milestones
B405 Create Project
Milestones
• Menu Path: Project Planning/ WBS
• Milestones are created to denote certain Gateways or Deliverables along the course of the Project
• This assists the Project Team with staying on the planned timeline and provides a benchmark against which to measure the Project progression. It also provides control points where certain deliverables need to be met and approvals may be required at these points to move the project forward to the next stage.
B. Project Planning – Planning Phase
B406 Milestones
B406 Milestones
Project Owner
Project Leader
Project Rights
Management (read only)
WSIP Admin
Menu Path: Project Planning/ WBS or Gantt “Task Manager” functionality: Click the Milestone icon. Check the Milestone check box. Select Deliverable type from the drop-down list. Enter details about what must happen for this milestone i.e. what should be delivered, what needs to be produced, what needs to be approved. Save using the Green Tick. You will notice that a “diamond” appears beside the milestone tasks.
B407 Milestones
B407 Milestones
Menu Path: Reports/Project Management/Milestone
Directory: Select the directory that contains your project.
Project: Select the project you wish to run the report for.
From/to Date: Chose from calendar function.
Select Run Report
19
B5. Add Timescale Information to Tasks
B501Add Task Start &
Finish Dates
B501Add Task Start &
Finish Dates
• Task Start and Finish Dates should be added to Tasks at the lowest level sub-task. The dates applied will then aggregate to form the overall Higher Level task Start and Finish Date.
• Start and Finish Dates can be added as you create the Task in the WBS using the T- “Add Task” functionality or afterwards through the WBS or Gantt
• To access Task Manager simply point at the Task in the WBS or the Gantt view and click once to open the Task
B503Check Overall Project
Schedule
B503Check Overall Project
Schedule
• The Start and Finish Dates of each task aggregate to form the overall Project Start and Finish Dates.
• Check your overall Project Timeframe is correct in the Gantt View and make any required adjustments to Start and Finish Dates. Menu Path: Project Planning/Gantt
B. Project Planning – Planning Phase
B502Create Task Links /
Dependencies
B502Create Task Links /
Dependencies
• Links can be created between one task and another to drive the project schedule in an automated way and create finish to start dependencies between one task and another. This ensures if one task moves out or is late all future tasks will be re-scheduled by the system accordingly.
• To link tasks in the schedule, navigate to the Gantt View
• Menu Path: Project Planning/Gantt - slide to the end of the task bar you wish to create the link from, then “click here to link task” . Message appears, then click/point at the task bar you wish to create the link to and click again. The “Links Pending” box appears showing you all the task references for which you have requested links. Several links can be made at a time before saving.
• Save your work using the Green Tick from the “Links Pending” box.
Project Owner
Project Leader
Project Rights
Management (read only)
WSIP Admin
20
B6. Add Planned Resources to Tasks
B601Assign Task Resource
B601Assign Task Resource
• The Task Resource can be added as you create the Task in the WBS using the T- “Add Task” functionality under the Planned Resource Button or can alternatively be assigned later using the Task Manager found under the Menu Path/WBS. Point at the Task and click to open the Task Manager. Select the Planned Resources button. Task Owner's are assigned at the lowest-level Task in a group or set of tasks.
B. Project Planning – Planning Phase
B602Inputting the Planned Time
B602Inputting the Planned Time
• Open the WBS by clicking on “+” on the left of each task.
• Open the Task Manager by double clicking on task.
• Select icon
• Select from “Available resources ”
• Select icon to add them to the planned Resource List.
• Define the number of days they are assigned to the task
• Click on the Green Tick Icon to update the Task
Project Owner
Project Leader
Project Rights
Management (read only)
WSIP Admin
21
B. Project Planning – Planning Phase
B7. Create Risk Assessment B701
Open Risk Definition Screen
B701Open Risk Definition
Screen
Navigate using menu:
▪ Project Planning/ Risks/Issue ->Risks
-> Issues
B703View Risks
B703View Risks
• Select “View Risks” Pane.
Review:• Risk ID: Unique
Identifier• Description: Defined
when creating a new risk• Related Tasks: Is the
Risk related to one task or does it impact all tasks.
• Owner: Who owns the task i.e. the project leader, DEHLG etc.
• Target Date: Date risk will be mitigated
• Strategy/Comment: Further information on risk, and its mitigation plan
B702Create a Risk
B702Create a Risk
• Select New Risk• Related to Task:
Does it relate to a task or does it impact all tasks.
• New Risk Name: Name
• Impact: 1 low 10 high (the impact the risk may have)
• Probability: 1 low 10 high (the probability the risk will take place)
• Area: Time or Cost or Quality
• Raised by: Name• Owned by: e.g.
Project Leader.• Enter Strategy to
mitigate risk.• Click Add Risk
B705Create an Issue
B705Create an Issue
• Navigate using the menu:
• Project Planning/ Risks/Issue/Issues
• Select New Issue• Related to Task:
Does it relate to a task or does it impact all tasks.
• New Issue Name: Name
• Impact: 1 low 10 high• Probability: 1 low 10
high (the probability the risk will take place)
• Area: Time or Cost or Quality
• Raised by: Name• Owned by: e.g.
Project Leader
B704Transfer a Risk to an
Issue
B704Transfer a Risk to an
Issue
• Sometimes a Risk may not be mitigated in time and may become an “Issue”
• To save time re-tying the Risk to the Issue Log, the system allows you to “Transfer” the Risk to the Issues Log automatically.
• On the create risk pane select the icon
• This transfers the risk to an issue.
Project Owner
Project Leader
Project Rights
Management (read only)
WSIP Admin
22
B. Project Planning – Planning Phase
B7. Create Risk Assessment (Related Reports)
B706Run the Risk report
B706Run the Risk report
• Navigate using the menu:
• Reports/Project Management/Risk Analysis
• Select Directory: Directory where project is.
• Select Project: or select “current project”
• Define the Period which you wish the report to be run
• Select “Run Report”
B707Run the Issue Report
B707Run the Issue Report
• Navigate using the menu:
• Reports/Project Management/Issue Analysis
• Select Directory: Directory where project is.
• Select Project: or select “Current Project”
• Define the Period which you wish the report to be run
• Select “Run Report”
Project Owner
Project Leader
Project Rights
Management (read only)
WSIP Admin
23
B. Project Planning – Planning Phase
B8. Submit Planned Budget
B801Open the Planned Budget Interface
B801Open the Planned Budget Interface
• Menu Path: Project Finances/Planned
and Recouped
Project Owner
Project Leader
Project Rights
Management (read only)
WSIP Admin
B802 Inputting LA Planned
Cost of Project
B802 Inputting LA Planned
Cost of Project
• Enter the Local Authorities Planned Cost of the Project amount in the “Project Planned Cost” data entry tab for Planning or Construction Costs
• The Sub Total Column details the Total Planned Budget.
• Print and submit to the DEHLG for approval.
• Note: The Planned Budget Column is a new column in Phase 2
23
24
B. Project Planning – Planning Phase
B9. Approved Planned Budget
B902 Inputting Breakdown
of Cost
B902 Inputting Breakdown
of Cost
• Upon receipt of the Approved Cost of Project from the DEHLG enter the Details of the Breakdown of Planned amounts for Planning or Construction.
• Select the expenditure item you wish to update and click on the “edit” button on the right hand column of the screen
• Note: If a WSIP 05 claim form was completed already for this item select the relevant WSIP 05 claim form from the drop down menu (new to Phase 2)
B903Inputting Recouped to
Date
B903Inputting Recouped to
Date
• After recoupment payments have been received from the DEHLG enter the Details of the Recouped to Date amounts for Planning or Construction.
•Select the Item you wish to update and click on the “edit” button on the right hand column of the screen
• Note: If a WSIP 2A/2B claim form was completed for this item select the relevant WSIP 2A/2B claim period (new to Phase 2)
B901Dept Returns
Approved Cost of Project
B901Dept Returns
Approved Cost of Project
• The Department returns the ApprovedCost of Projectamount.
• The Department also returns the ProjectRef Number at thisstage
•Note: The returned Approved Budget from the DEHLG should be distributed across the Categories and Sub-Categories
Project Owner
Project Leader
Project Rights
Management (read only)
WSIP Admin
25
B. Run Related Reports
B10. Related Reports
B102 Detailed Project Expenditure Report
B102 Detailed Project Expenditure Report
Menu Path: Reports/WSIP
Reports/ Detailed Project Expenditure Report
Note: This is a new Report in Phase 2.
B101 Project Financial Tracking Report
B101 Project Financial Tracking Report
Menu Path: Reports/WSIP
Reports/ProjectFinancial Tracking
Note: This is a new Report in Phase 2.
System AdministratorProject Owner
Project Leader
Project Rights
Management (read only)
WSIP Admin
26
Section C - Over-View Project Planning – Construction Phase
This section tells you how to copy the construction templates (< 5million, >5 million, DBO) into your Work Breakdown structures
How to update the Project Status How to run related reports
27
Web-PCS – System Guideline – Detailed Steps
C. Project Planning - Construction Phase
C1Create Construction Project Using Project
Copy
C1Create Construction Project Using Project
Copy
C2Update the
Project Status
C2Update the
Project Status
C3Related Reports
C3Related Reports
28
C. Project Planning – Construction Phase
C1. Project Planning-Construction Phase
C101Create a Contract Using the Copy
Project
C101Create a Contract Using the Copy
Project
• Navigate using the menu:
• Project Planning/WBS
C102 Adding a Contract
Type
C102 Adding a Contract
Type
C103Choosing Your Contract Type
C103Choosing Your Contract Type
C104Adding Contract
Details
C104Adding Contract
Details
C105Creating the
Contract
C105Creating the
Contract
Once all of these details have been added the contract can then be created on the system
Click on the P Icon from the Function Bar in the WBS
Then Click on the “Choosing the Right Contract Type” Task from the Construction Phase of the WBS
Select the Templates Directory from the Directory List.You can then Choose from the Following Contract Types:
Project: Select the template you wish to use. i.e. < 5million, > 5 million, DBO.
Note: You are copying from the templates directory into your project workspace
A Contract Type is Configured to be a “Sub Project” of the Main Project you are working on similar to adding a New Project Via the Project Wizard, you will need to determine the Following Details:-
Tasks, Rights,Project Name,Live Date
Project Owner
Project Leader
Project Rights
Management (read only)
WSIP Admin
29
C. Project Planning – Construction Phase
C2. Project Status
C201Updating the Project
Status
C201Updating the Project
Status
• Navigate using the menu:
• Project Planning/ Background/ Project Status
C202 Setting the Status to
Construction
C202 Setting the Status to
Construction
• Select “Construction”
• Select “Update Project Status" button to save your change
Project Owner
Project Leader
Project Rights
Management (read only)
WSIP Admin
30
C. Project Planning - Construction Phase
C3. Related Reports
C301Project Summary
Reports
C301Project Summary
Reports
• Navigate using the menu:
• Reports/Project Management/ Project Summary
C302Project Tasks List
C302Project Tasks List
• Navigate Using the Menu:
• Reports/Project Management/Project Task List
C303Milestone Report
C303Milestone Report
• Navigate Using the Menu:
• Reports/Project Management/Milestone
Project Owner
Project Leader
Project Rights
Management (read only)
WSIP Admin
31
Section D – Over-ViewProject Control & Reporting – Project Management &
Reporting
This section tells you how to control and report using ProjectVision and the Project Control System
32
D. Project Control & Reporting – Project Management & Reporting
D2Update Task Progression
D2Update Task Progression
D3Record & Update
Project Risks & Issues
D3Record & Update
Project Risks & Issues
D4Related Reports
D4Related Reports
D1Update Construction
Phase PCSForms
D1Update Construction
Phase PCSForms
Web-PCS – System Guideline – Detailed Steps
Web-PCS – System Guideline – Detailed Steps
D. Project Control & Reporting – Project Management & Reporting
D1. Update the Planning Phase PCS Documentation
D101Open a link to a PCS
document
D101Open a link to a PCS
document
• Open a link to a PCS document by clicking on the icon
• Select the “Link to document” radio ButtonAttached documents: Select the document you want to open from the drop down list
• View the document by clicking on the icon
• Note: There are now NO LINKS to PCS documents. This feature links to circulars, guidance docs etc in Phase 2
Project Owner
Project Leader
Project Rights
Management (read only)
WSIP Admin
Important: In Phase 2
• The Notes function is used to store project notes i.e. DEHLG communication, project decisions, delays etc.
• The Guidance Notes function stores guidance notes to simplify or clarify a specific task.
• There are only links to circulars, guidance documents and WSIP. There are NO links to PCS documents (which are now in HTML format)
Important: In Phase 2
• The Notes function is used to store project notes i.e. DEHLG communication, project decisions, delays etc.
• The Guidance Notes function stores guidance notes to simplify or clarify a specific task.
• There are only links to circulars, guidance documents and WSIP. There are NO links to PCS documents (which are now in HTML format)
D102Open a PCS Document
D102Open a PCS Document
• Navigate using the menu: Project Planning/WBS
• In “WBS” view navigate to a Task in the Planning Phase of the Project that has a PCS Document attached
• Open the Task Manager by clicking on task
• Click “PCS Forms” radio box.
• Select Form Template e.g. PCS 03 Project Quality Plan
• Select Form e.g. PCS 03 Project Quality Plan
• View the document by clicking on the icon
34
D. Project Control & Reporting – Project Management & Reporting
D1. Update the Planning Phase PCS Documentation
D103Validate PCS Project
Name
D103Validate PCS Project
Name
• Validate that the Project Name entered once using Project Wizard (new to Phase 2).
• Validate that the Project Number is correct. (Entered using Project Planning-Background- WSIP Details- Project Reference Number.)
• Validate that the Project Leader Name is correct. (Entered using Project Planning-Background- New Details- Predefined Detail-Project Leader.)
Project Owner
Project Leader
Project Rights
Management (read only)
WSIP Admin
D104Enter the Project
Value
D104Enter the Project
Value
• This is a manual entry on each PCS document.
• This is the DEHLG Approved Cost of the Project.
• At Planning Stage this is the value from the WSIP.
• Note: This value will change during the project lifecycle.
D106Update/Save
Version of PCS Document
D106Update/Save
Version of PCS Document
• To create a new version of a document, select “Save New Version”
• Note: Each new version will get a new iterative document number
• To create a new version select “Update this Version”
• Note: This will overwrite the old version and save the new data.
• Note: The new % complete will be reflected in the Task Manager
D105Enter Dates &
Update % Completeon PCS document
D105Enter Dates &
Update % Completeon PCS document
• The date entries must be typed in the following format: 1 Jan 2007, 1 Jun 2007, 1 Jul 2007.
• Enter the task Percentage (%) Complete by checking the % complete radio box on the PCS document.
• Note: Once we “Save New Version” or “Update this Version” the % complete will automatically appear in the main task manager % complete window
35
D. Project Control & Reporting – Project Management & Reporting
D201 Update Task %
Percentage Complete
D201 Update Task %
Percentage Complete
• You can enter the Task Percentage Complete in three different ways:
1. WBS2. Gantt3.Dashboard
• This can be entered using the Menu/ WBS/Task Manager/% Complete field - save using the Green Tick.
• On the “Dashboard” function under Menu Path: Dashboard - Select End User view via the correct Radio Button. Select the task % complete field, enter %complete, save using the “Update” Button
• The Task Status or Percentage Complete will automatically role up to its higher-level or parent task which will roll up to the overall Project Status or Percentage Complete.
• The project status will correspondingly update the overall status of the Programme to which it is linked and status reports are viewable at any level of the Hierarchy from Programme to Project, down to the task level
The % Complete to be entered in each Task can be taken from the % Complete section of the PCS Document relevant to the Task
D2. Update Task Progression
D202 Task Status D202 Task Status
D203 % Complete D203 % Complete
Project Owner
Project Leader
Project Rights
Management (read only)
WSIP Admin
Phase 2 Note: Remember you can do % completes through the new HTML PCS form and/or using the % complete function on the task manager.
D204Open/Add a Note
D204Open/Add a Note
• Navigate using the menu:
• Project Planning/WBS
• In “WBS” view navigate to a Task with this icon
• Open the Task Manager by clicking on task
• Open/Review the Note by clicking on the icon
• Add specific project related notes i.e. notes from project meetings, communication with DEHLG etc.
D205Open a Guidance
Note
D205Open a Guidance
Note
• In “WBS” view navigate to a Task in the Planning Phase of the Project that has a icon
• Open the Task Manager by clicking on task
• Open/Review the Guidance Note by clicking on the icon
• The Information Contained on the Note is DEHLG information from circulars, inspector requirements and/or DEHLG admin.
• This is a new feature in phase 2.
36
D3. Record, Update & Monitor Project Issues
• Any Issues that occur whilst the Project is in process should be recorded on the Project Issue Log.
• Each Issue should have a Strategy worked out for dealing with the Issue or closing it down.
• The Strategy/ Comments field should be updated each time the Issue is reviewed with the latest status.
• The issue should always be assigned to an Owner who is responsible for closing down or escalating the Issue accordingly.
D302Record or Project
Issues
D302Record or Project
Issues
• Risks & Issues should be reviewed on a regular basis.
• The Logs can be used to assist this process by printing and circulating the Reports or Logs regularly to relevant parties and applying updates on status to the Logs so the current status is available Menu Path: Reports/ Project Management/Risk Analysis or Issue Analysis
• Higher impact Issues should be progressed as a higher priority.
D303Review & Progress
Risk & Issues
D303Review & Progress
Risk & Issues
D304Escalate
Risk & Issues
D304Escalate
Risk & Issues
• Risks & Issues that cannot be closed down or resolved at the Team Level or Project Management level should be escalated.
• The Issue is recorded in the Projects Issue Log.
• Menu Path: Project Planning/Risk&Issues/ Issues/New or View Issues. Enter the name of the Issue. Enter the required details about the Issue and updates as the Issue progresses. Enter an Impact value. Select the Area to which the Issue relates. Add an Owner. Add the Target Date for reviewing the Issue. Add the Strategy for closing down the Issue or the latest update on progression in the Strategy/Comments field. Click “Add Issue” or “Update Issue” button to Save.
D. Project Control & Reporting
D301Update ProjectRisk Register
D301Update ProjectRisk Register
• The Risk Register should be reviewed and updated at a regular frequency throughout the Project life-cycle to ensure appropriate action is taken to mitigate risks
• Menu Path: Project Planning/ Risks& Issues/Risks. Select the View Risks tab, use the Edit button to update the appropriate Risk Information.
• Circulate the Risk Report for meetings: Menu Path: Reports/ Project Management/ Risk Analysis
Project Owner
Project Leader
Project Rights
Management (read only)
WSIP Admin
37
D4. Related Reports
• Menu Path Reports/ProjectManagement/Issue Analysis
• Run Report
D402Issues Report
D402Issues Report
D. Project Control & Reporting
D401Risks Report
D401Risks Report
• Menu PathReports/ProjectManagement/Risk Analysis
• Run Report
Project Owner
Project Leader
Project Rights
Management (read only)
WSIP Admin
38
Section E - Over-View Project Control & Reporting-Financial Management and Reporting
This section tells you how to control and report all aspects of financial management using ProjectVision.
39
E. Project Control & Reporting - Financial Management and Reporting
E. Project Control and Reporting - Financial Management & Reporting
E5View WSIP01
Summary
E5View WSIP01
Summary
E4Create WSIP02
Claims
E4Create WSIP02
Claims
E6Submit WSIP05 Claim for Over
Expenditure
E6Submit WSIP05 Claim for Over
Expenditure
E7Submit Final Project Costs and Accounts
E7Submit Final Project Costs and Accounts
E8Related Reports
E8Related Reports
E1Check Project
Interface Details are Created
E1Check Project
Interface Details are Created
E2Enter Approved
Grant
E2Enter Approved
Grant
E3Request FMS
Data
E3Request FMS
Data
Project Owner
Project Leader
Project Rights
Management (read only)
WSIP Admin
40
E. Project Control and Reporting-Financial Management and Reporting
E1. Check Project Interface Details are Created
E101Check Project
Interface Details
E101Check Project
Interface Details
Menu PathProject Planning/Background/WSIP details
Check that you have entered:• Project Reference Number (The Department will communicate the amount of funding approved via letter) • FMS Job Code• Local Authority Reference number (option)
Update details
Project Owner
Project Leader
Project Rights
Management (read only)
WSIP Admin
41
E. Project Control and Reporting-Financial Management and Reporting
E2. Updating the Tasks with the Approved Grant Totals
E201Dept Communicates
the Grant Amount
E201Dept Communicates
the Grant Amount
• The Department will communicate the amount of funding approved via letter
• This “Approved Grant” amount then needs to be entered on to the project
• Navigate using the menu:
• Project Planning/WBS
E202Updating the
Relevant Task
E202Updating the
Relevant Task
• Go to the Appropriate Phase (Planning/ Construction) Task, in the WBS
• Open the Task Manager
• Select the Budget Icon
• Update the Budget Amount with the approved amount as per the Department
E203Updating the
Relevant Task
E203Updating the
Relevant Task
• Select the Budget Name and Budget Type from the available options in the drop down lists
• This Figure will then be displayed on the WSIP01 Form
Project Owner
Project Leader
Project Rights
Management (read only)
WSIP Admin
42
E. Project Control and Reporting-Financial Management and Reporting
E3. Request FMS Data
E301Claim Form
Administration
E301Claim Form
Administration
• Navigate using the menu:
• WSIP/Claim Forms
E302WSIP Form Control
E302WSIP Form Control
• Select a Claim Period
• Request the Relevant FMS data (Request an FMS Code Number from your Trainer at this point).
• Project Reference Number
• FMS Code• Local Authority Ref
No
E303Old/New Codes
E303Old/New Codes
• Please Note that if you are using Old Codes on your project these must be mapped directly against the relevant expenditure category using the “Unmapped FMS Data” Tab. This Tab Displays all of the data passed from the Financial System (AGRESSO, JD Edwards, Integra, Oracle) that has not been mapped directly on to your Claim Form.
E304New Codes
E304New Codes
• If you are using new Codes for your project then these will be mapped directly onto your LA Claim Form (no need to map)
• Select the Unmapped Radio Button and then click Edit on the RHS of the List to Map the op code to the relevant expenditure Category
Project Owner
Project Leader
Project Rights
Management (read only)
WSIP Admin
43
E. Project Control and Reporting-Financial Management and Reporting
E4. Create WSIP02 Claim Forms
E401Claim Form 02A and
02B
E401Claim Form 02A and
02B
• The Data you have Mapped/Input will now be viewable in the 02A(Planning Costs) and 02B (Construction Costs) forms which the system will automatically generate
• Navigate using the menu:
• Project Finances/ClaimForms/02A/02B
E402Claim Forms
E402Claim Forms
• These are the forms that are submitted to the dept
• You can Drill down under the headings in each report to see a further breakdown
• At the Bottom of the report all Totals are displayed
• Each of these forms can be Exported to Word and printed for Submission
Project Owner
Project Leader
Project Rights
Management (read only)
WSIP Admin
44
E. Project Control and Reporting-Financial Management and Reporting
E5. WSIP01 Form
E50101 Claim Form
E50101 Claim Form
• Navigate using the menu:
• Project Finances/ClaimForms/WSIP01
E502Claim Forms
E502Claim Forms
This is the Summary Form that is also Submitted with the 02A and 02B forms.Note that it also Contains the Figure for the Approved Cost of the Project that you entered on the WBS earlier
Project Owner
Project Leader
Project Rights
Management (read only)
WSIP Admin
45
E. Project Control and Reporting-Financial Management and Reporting
E6. Submit WSIP05 Form for Over Expenditure
E601Requests for further
Funding
E601Requests for further
Funding
• Additional request for Further Funding can be processed via the WSIP05 Claim Form
• Navigate using the menu:
Project Finances/WSIP05
E602Updating the
Relevant Task
E602Updating the
Relevant Task
• Select The Expense Category (Planning or Construction)
• Define the Additional Extra Works Undertaken
• Enter the Proposed Increase in Costs
• Attach a Technical Document or Justification Document using the “Browse” Button
• Select the “Generate Claim” Button
E603Viewing the Claim
E603Viewing the Claim
• The Claim will be generated and can now be viewed on the “Previous Claims” Tab
• Select the Previous Claims Tab and select the appropriate Claim from the Drop down list
• The Claim form will then be displayed and can be exported to word for Submission
Project Owner
Project Leader
Project Rights
Management (read only)
WSIP Admin
46
E. Project Control and Reporting-Financial Management and Reporting
E7. Submit Final Project Costs and Accounts
E701Submitting Final
Project Costs and Accounts
E701Submitting Final
Project Costs and Accounts
• Navigate Using the Menu Path:
• Project Finances/WSIP07A/WSIP07B
E702WSIP07A and 07B
E702WSIP07A and 07B
• At the end of a Project the Project Manager will need to Submit the Final Project Costs and Accounts
• This is done using the WSIP07A and WSIP07B forms
E703Completing the
Forms
E703Completing the
Forms
• Simply access the Forms using the menu path defined in step E701
• Export the Relevant Form into Word and print it off for Manual Completion and submission
Project Owner
Project Leader
Project Rights
Management (read only)
WSIP Admin
E705 Detailed Project Expenditure Report
E705 Detailed Project Expenditure Report
Menu Path: Reports/WSIP
Reports/ Detailed Project Expenditure Report
Note: This is a new Report in Phase 2.
E704 Project Financial Tracking Report
E704 Project Financial Tracking Report
Menu Path: Reports/WSIP
Reports/ProjectFinancial Tracking
Note: This is a new Report in Phase 2.
47
Overview - Business Processes
F. Project Close Out
F1 Confirm Task &
Project Completion
F1 Confirm Task &
Project Completion
F2 Related Reports
F2 Related Reports
48
F. Project Close Out - Final Status and Accounts
F1. Confirm Task & Project Completion (Project Close Out)
F101 Check Final Task &
Project Status
F101 Check Final Task &
Project Status
• The Project Leader should ensure all tasks on the Project Plan are 100% complete on the ProjectVision System
F102 Update & Review
Final Risk Log
F102 Update & Review
Final Risk Log
• The Risk Log should be updated to reflect the final status of all logged issues. All risks should be closed or escalated as appropriate.
F103 Update & Review
Final Issue Log
F103 Update & Review
Final Issue Log
• The Issue Log should be updated to reflect the final status of all logged issues. All issues should be closed or escalated as appropriate.
Project Owner
Project Leader
Project Rights
Management (read only)
WSIP Admin
49
F. Project Close Out
F2. Related Reports
F201 Project Task List
Report
F201 Project Task List
Report
• Menu Path: Reports/Project
Management/Project Task List
System Administrator
F202 Risk Analysis
Report
F202 Risk Analysis
Report
F203 Issue Analysis
Report
F203 Issue Analysis
Report
• Menu Path Reports/Project
Management/ Risk Analysis Report
• Menu Path Reports/Project
Management/ Issue Analysis Report
Project Owner
Project Leader
Project Rights
Management (read only)
WSIP Admin
50
F. Project Close Out
F2. Related Reports
F206 Detailed Project Expenditure Report
F206 Detailed Project Expenditure Report
Menu Path: Reports/WSIP
Reports/ Detailed Project Expenditure Report
Note: This is a new Report in Phase 2.
F205 Project Financial Tracking Report
F205 Project Financial Tracking Report
• Menu Path: Reports/WSIP
Reports/ProjectFinancial Tracking
Note: This is a new Report in Phase 2.
System AdministratorProject Owner
Project Leader
Project Rights
Management (read only)
WSIP Admin
51
Section G - Over-View Log Support Ticket to Ticket Resolution -
HELPDESKVISION This section tells you the steps you need to
logon to the helpdesk function, how to create a call and check logged call.
52
Web-PCS – System Guideline - Overview
G. Log Support Ticket to Ticket Resolution - HELPDESKVISION
G1Open Helpdesk Support Ticket
G1Open Helpdesk Support Ticket
G2Assign Ticket to Resource
G2Assign Ticket to Resource
G3Resolve & Close
Call
G3Resolve & Close
Call
G. Log Support Ticket to Ticket Resolution
G1. Open Helpdesk Support Call - HelpdeskVision
G101Log-on to
HelpdeskVision
G101Log-on to
HelpdeskVision
• 1) Using the same username and password as your web-PCS ProjectVision password Log-on to the helpdesk via the HelpdeskVision link located on the PCS-website at www.wsntg.ie/pcs.asp
• 2) The Welcome Page Appears on log-on
G102Create
New Call
G102Create
New Call
G103Select
Problem Type
G103Select
Problem Type
• 1) To open a new Support “Call” either select the “New Call” link from the Welcome Page or from the Main Menu select Menu Path: “Create New Call”
• 2) The “New Call” entry screen tab is displayed
• 1) At the “New Call” entry screen tab select the “Problem Type”. This is categorised into the different menu areas of the web-PCS system and the PCS process
• 2) Once the “Problem Type” has been selected the “Category” drop-down box will appear beneath it
G104Select
Category
G104Select
Category
• 1) The selections in this box are a sub-category of the Problem Type based again on the web-PCS menu sub-options
• 2) Select the relevant category for your problem
• In some cases this may be the same as the “Problem Type” if menu sub-options are not relevant but an entry needs to be made to this field
System AdministratorProject Owner
Project Leader
Project Rights
Management (read only)
WSIP Admin
G. Log Support Ticket to Ticket Resolution
G1. Open Helpdesk Support Ticket - HelpdeskVision
G105Enter Problem
Description
G105Enter Problem
Description
• 1) In the “Brief Description “ field enter the main details of the Problem
• There are 255 characters available for your description
• 2) In the “Additional Details” field enter any other relevant details regarding the Problem giving examples or data references in the system where applicable
G106Select
Problem Priority
G106Select
Problem Priority
G107Attach
Supporting Documents
G107Attach
Supporting Documents
• 1) In the “Priority” drop-down box select the severity of the Problem
• The Choices are Low/ Normal or Urgent
• 1) In the “Attach File” field you can attach any supporting documents of any file type
• You should only do this when you are ready to submit the “Call” entry
• You can browse for documents using the “Browse” button
G108Submit
Call
G108Submit
Call
• 1) Using the “Submit Call” button on the top right-hand corner of the screen submit the “Call”
• The “Call” or ticket will be sent to the System Administrator and assigned accordingly to the correct Support Analyst
G109View
Logged Calls
G109View
Logged Calls
• 1) Navigate to Menu Path: Logged Calls/My Opened Calls to view any Support Calls you have opened
• 2) View Closed Calls under the “My Closed Calls” heading
Project Owner
Project Leader
Project Rights
Management (read only)
WSIP Admin
G2. Assign Ticket to Support Analyst - HelpdeskVision
G201Call Submitted
From User
G201Call Submitted
From User
• 1) The “Call” is submitted by the user as per step G108
• It is then available to the System Administrator for assignment to a Support Analyst
B. Log Support Ticket to Ticket Resolution
G202Assign “Call” Ticketto Support Analyst
G202Assign “Call” Ticketto Support Analyst
• 1) The “Call” is reviewed by the System Administrator and assigned to the appropriate Support Analyst
• The System Administrator will contact the Support Analyst via the appropriate media and seek to resolve the Problem within the given Service Level Agreement timelines in place
Project Owner
Project Leader
Project Rights
Management (read only)
WSIP Admin
G3. Resolve Ticket Query - HelpdeskVision
B. Log Support Ticket to Ticket Resolution
G301Resolve
“Call” Problem
G301Resolve
“Call” Problem
• 1) The Support Analyst will review the “Call” details and will resolve the problem via the appropriate means.
• 2) The Support Analyst will then provide the solution to the System Administrator.
• 3) The System Administrator will update the resolution in the HelpdeskVision system under the appropriate “Call”.
G302Inform User
of “Call” Resolution
G302Inform User
of “Call” Resolution
• 1) The user will be informed of the “Call” resolution via email from the HelpdeskVision System once the System Administrator has closed the “Call” in the HelpdeskVision System.
• 2) In some cases it may be necessary that the System Administrator contacts the user via phone to check that the problem has been resolved in the web-PCS Production System, prior to closing the “Call” in the help desk system.
G303Close “Call”
G303Close “Call”
• 1) Once the “Call” resolution has been resolved and confirmed, it can be closed in the HelpdeskVision System
• The “call” is then viewable by the user under “My Closed Calls” in the “Logged calls” menu option.
Project Owner
Project Leader
Project Rights
Management (read only)
WSIP Admin
57
Appendix 1 Project Rights - Project Owner
The rights for Project Owner cannot be changed by anyone on the system.
User is allowed to edit Recorded History
User is allowed to edit the Project Name or move it to a different directory
Details - Add, update and remove Details
General - View project and general report section
History Update - Add/Edit History on all tasks in project
Reports - User is allowed to view special reports which have a cost element
Reports - User is allowed to view the Cost section in Reports
Reports - User is allowed to view the Time section in Reports
Risks/Issues/Change Requests - User is allowed to add/edit Risk and Issues
Scope - Add, update Scope
Tasks - Full task changes on the Work Breakdown Structure and Gantt
Organisations - User can assign organisations to project
WSIP - User can edit all claim data
WSIP - User can edit the 'Breakdown of Costs'
WSIP - User can Create and Delete all the WSIP claim forms
Strategies - User can assign strategies to project
Tasks - Full task changes on the Work Breakdown Structure and Gantt
MSP - Can Export
58
Appendix 1 Project Rights - Project Leader
User is allowed to edit Recorded History
User is allowed to edit the Project Name or move it to
a different directory
Details - Add, update and remove Details
General - View project and general report section
History Update - Add/Edit History on all tasks in
project
Reports - User is allowed to view special reports
which have a cost element
Reports - User is allowed to view the Cost section in Reports
Reports - User is allowed to view the Time section in Reports
Risks/Issues/Change Requests - User is allowed to add/edit Risk and Issues
Scope - Add, update Scope
Tasks - Full task changes on the Work
Breakdown Structure and Gantt
Organisations - User can assign organisations to project
WSIP - User can edit all claim data
WSIP - User can edit the 'Breakdown of Costs'
WSIP - User can Create and Delete all the WSIP claim forms
Strategies - User can assign strategies to project
Tasks - Full task changes on the Work Breakdown Structure and Gantt
Organisations - User can assign organisations to project
59
Appendix 1 Project Rights - Team Member
History Update - Add/Edit History, but only on tasks where the user is a resource
Reports - User is allowed to view the Time section in Reports
Tasks - User can only edit tasks that they have been assigned to
60
Appendix 1 Project Rights - WSIP Admin
WSIP - User can edit all claim data
WSIP - User can Create and Delete all the WSIP claim forms
WSIP-User CANNOT enter FMS Job Code data using Project Planning-Background