(VOL. 2) GOVERNMENT OF INDIA 2018

Transcript of 1. Title Page · Delhi.Tel No. 01123062339.Email: [email protected] Also available at All...

  • (VOL. 2)

    GOVERNMENT OF INDIA

    2018

  • Price : Rs. 3000/- (for both volumes) excluding postage and forwarding charges etc.

    © All rights reserved. No part of this publication, either in English or in Hindi, may be reproduced in any form or byany means, electronic or mechanical including photocopy, recording or any information storage and retrieval system,without permission, in writing, from the Director General, CPWD, New Delhi.

    DISCLAIMER

    The Delhi Analysis of Rates is indicative, as coefficients for labour are likely to vary due to technological innovations,skill of workman and other local factors affecting the efficiency and output of labour. Further its use by Govt.Departments, PSUs, private bodies & individuals shall be at their own discretion. CPWD shall not be responsible forany ambiguity, discrepancy, dispute or financial loss, arising directly or indirectly by using or following items of DelhiAnalysis of Rates by such Govt./Private bodies or individuals.

    For feed back and suggestions, please contact SE(TAS),CPWD, Room No. 418, ''A'' Wing, Nirman Bhawan, NewDelhi.Tel No. 01123062339.Email: [email protected]

    Also available atAll Leading Booksellers & Authorised Govt. Dealers In India

    Books will be delivered next day by COURIER(Payment to courier-boy)

    in Delhi, Noida, Ghaziabad, Faridabad & Gurgaon (nominal courier charges extra)

    JAIN BOOK AGENCY (SOUTHEND)1, Aurobindo Place Market,

    Hauz Khas, New Delhi-110016Phone : 41755666

    E-mail : [email protected] : www.jainbookagency.com

    JAIN BOOK AGENCY (GURGAON)19, Central Plaza Mall, Sector 53,

    Golf Course Road,Gurgaon 122002 Haryana

    Phone : 4143020Mobile : 9810666810

    JAIN BOOK AGENCY (INTERNATIONAL)RA- 11, Sector- 126,

    Opp. Gate No. 2A of Amity University,Noida

    Mobile. : 9210080580

    JAIN BOOK AGENCY (GREATER NOIDA)11 Jagat farm ComplexGama Sector Market

    Near OBC BankGreater Noida

    Phone : 0120-4206655

    A GOVERNMENT OF INDIA PUBLICATION

    Published by

    DIRECTOR GENERALCPWD, Nirman Bhawan, New Delhi - 110011

    &

    Printed & Marketed by

    JAIN BOOK AGENCYAuthorised Dealers of Govt. PublicationsC-9, Connaught Place, New Delhi-110001

    Phones : 44556677, 23416390 upto 94E-mail : [email protected] : www.jainbookagency.com

    ISBN : 978-81-932679-1-2

    DIAL-A-BOOK011-44332211(

    Distributed byJBA DISTRIBUTORS

    4574 / 15, 2nd Floor, Padamchand Marg,Opposite Happy School, Darya Ganj, New Delhi- 110002

    Tel.: 011-44332211, 44332222E-mail : [email protected] : www.jba.in

    JAIN BOOK DEPOTC - 4, Opp. PVR Plaza, Post Box. No. 51,Connaught Place, New Delhi-110001 (India)

    Phone : 011- 23416101 / 02 / 03E-mail : [email protected]

  • dsUnzh; yksd fuekZ.k foHkkxdsUnzh; yksd fuekZ.k foHkkxdsUnzh; yksd fuekZ.k foHkkxdsUnzh; yksd fuekZ.k foHkkxdsUnzh; yksd fuekZ.k foHkkx

    fuekZ.k Hkou] ubZ fnYyh 110011fuekZ.k Hkou] ubZ fnYyh 110011fuekZ.k Hkou] ubZ fnYyh 110011fuekZ.k Hkou] ubZ fnYyh 110011fuekZ.k Hkou] ubZ fnYyh 110011Central Public Works DepartmentNirman Bhawan, New Delhi- 110011

    Tel : 23062556 / 1317, Fax : 23061884

    E-Mail : [email protected]

    Hkkjr ljdkjHkkjr ljdkjHkkjr ljdkjHkkjr ljdkjHkkjr ljdkj

    Government of India

    FOREWORD

    PRABHAKAR SINGHDirector General

    Central Public Works Department Analysis of Rates for Delhi is a very comprehensive and

    useful document forming basis for the rates of various items. It is based on scientific

    assessment of Inputs of materials, labour and machinery in various items of work normally

    involved in civil construction projects.

    It was first compiled in the year 1950, followed by subsequent publication or revision in the

    years 1955, 1962, 1972, 1977, 1985, 1997, 2007, 2012, 2013, 2014 & 2016.

    Last Delhi Analysis of Rates was published in the year 2016. Revision of this DAR has

    become necessary due to changes in wages of labour & price of materials, adoption of

    new construction technologies & materials as well as implementation of GST. This has

    necessitated revision of existing Analysis of Rates for Delhi 2016 to include the above

    changes. Accordingly, this Analysis of Rates for Delhi 2018 has been prepared.

    The analysis of existing items has been updated in conformity with updated items of works

    in DSR 2018.

    I wish to place on record the technical input and the effective coordination on the part of

    Shri A.S. Arora ADG (S&P), Dr K M Soni ADG(TD), Shri Manu Amitabh CE(CSQ) (Civil)

    and team efforts put in by Shri Divakar Agrawal SE(TAS), Shri D.S.Panwar EE(TAS-I),

    Shri M.L.Prasad EE(TAS-II). Shri D.S.Adhikari AE(QA), Shri Naveenkumar P JE(TAS) and

    team of officers in CSQ unit in finalizing Analysis of Rates for Delhi 2018 in a record time.

    I am sure that C.P.W.D. Analysis of Rates for Delhi 2018 shall be very useful document to

    various Central Govt. Ministries, Departments & Public Sector Undertakings also besides

    various units of CPWD.

    (PRABHAKAR SINGH)

    Director General

    Place : New Delhi

    Date : December 14, 2018

  • V

    1. C.P.W.D. Analysis of Rates for Delhi 2018 is the revised edition of C.P.W.D. Analysis of Rates

    for Delhi 2016.

    2. Analysis of Rates for Delhi 2018 incorporates most of the analysis of items of Analysis of Rates for

    Delhi 2016 with updated correction slips, including analysis of existing items and also corresponding

    new items introduced in DSR 2018.

    3. Analysis of Rates for Delhi, 2018 is published in two volumes i.e. volume I & II as under:

    Volume Sub-head No. Content/ Sub-head

    Number

    One 00 Basic Rates

    01 Carriage of Materials

    02 Earth Work

    03 Mortars

    04 Concrete Work

    05 Reinforced Cement Concrete

    06 Masonry Work

    07 Stone Work

    08 Cladding Work

    09 Wood and PVC Work

    10 Steel Work

    11 Flooring

    12 Roofing

    Two 13 Finishing

    14 Repairs to Buildings

    15 Dismantling and Demolishing

    16 Road Work

    17 Sanitary Installations

    18 Water Supply

    19 Drainage

    20 Pile work

    21 Aluminium Work

    22 Water Proofing

    23 Rain Water Harvesting & Tubewells

    24 Conservation of Heritage Buildings.

    25 Structural Glazing Aluminium Composite Panel

    26 New Technologies and Materials

    PREFACE

  • VI

    4. Analysis of few existing items in sub head - 13 (Finishing) have been deleted. Similarly, analysis of

    many items have been modified correspond to items of DSR 2018. Several new analysis and existing

    subhead renamed in sub head 6 (Masonry work instead Brick work) Sub head 8 (Cladding work

    instead of Marble & Granite work) have been introduced in Analysis of Rates for Delhi 2018.

    5. Analysis of Rates for Delhi 2018 is based on the study of current market rates of materials at Delhi,

    prevailing as on 01.10.2018. The basic rates of materials, incorporated in the analysis, pertain to

    materials conforming to BIS Standards/ CPWD Specifications/Materials of good quality generally

    available in the market. The effect of GST on works contracts has been incorporated in all items.

    Labour rates are taken from the minimum wages issued by the Government of Delhi and Govt. of

    India (whichever is higher) w.e.f. 01.10.2018.

    6. The nomenclatures of main items have been printed along with the analysis of first Sub item only to

    conserve the space and number of pages.

    7. Sundries have been considered as 2.00 times based on Cost Index of Delhi as on 01.10.2018

    (118) with base as per PAR-2012 as 100.

    8. Lot of efforts has gone into the preparation of this Analysis of Rates for Delhi. I convey my deep

    appreciation and sincere thanks to:

    Shri Manu Amitabh CE(CSQ); Shri Divakar Agrawal SE (TAS); Shri Sudhir Kumar Dak, SE

    (C&M); Shri D.S. Panwar EE (TAS-I); Shri M.L. Prasad EE-(TAS-II); Shri P. Goyal EE-(TAD);

    Shri A.K. Sikka EE (QA) Shri M.C. Singal EE (QA); Shri S N Jaiswal EE (HQ); Shri Shivani

    Kaushal EE (M); Shri Sajal Mitra, EE (CON); Shri Kunwar Chandresh EE (TLC);

    Shri D.S. Adhikari AE (QA); Shri D.K. Malhotra AE (TAS); Shri Patta Madhukumar AE(TAS);

    Shri Prabhat Kumar Srivastav AE(TAS); Shri Gurmeet Singh AE (TAD); Shri H.K. Gupta AE,

    (M); Shri Mohammad Tarik AE, (QA); Shri S.K. Sharma, AE, (QA); Shri Gopal Warshney AE,

    (QA); Shri K.R. Meena AE, (CON); Shri Ved Khurana AE, (TLC); Shri Jai Bhagwan AE, (M);

    Shri Chalapaka Ramaraju JE, (TAD); Shri Naveenkumar P, JE (TAS); Shri Jay Prakash, Chief

    Estimator (TAS); Shri Bhim Singh Sr. D/man (TAS); Shri Hariram Sr. D/man (TAS); Shri. Prabhat

    Singh Sr. D/man (TAS) and other officers and staff of CSQ unit whose names are not mentioned here,

    for sincere efforts made in the preparation of this document in such a short time. Various Committees

    and field units, who contributed field inputs, also deserve appreciation for their timely help.

    9. Due care has been taken to print the C.P.W.D. Analysis of Rates for Delhi as correctly as possible.

    It is, however possible that some errors might have crept in. In case any error or omission is

    noticed, it may be brought to the notice of the Superintending Engineer (TAS), CPWD, Room no.

    418, A-wing, Nirman Bhawan, New Delhi.

    (Dr K M SONI)

    ADG (TD) CPWD

  • VII

    SH. No. NAME OF SUB-HEAD PAGE No.

    A. BASIC RATES

    0.1 HIRE CHARGES OF PLANTS & MACHINERY 3-6

    0.2 LABOUR 7-8

    0.3 MATERIALS 9-61

    0.4 CARRIAGE CODES 62-64

    B. SUB -HEADS

    1. Carriage of Materials 65-76

    2. Earth Work 77-132

    3. Mortars 133-142

    4. Concrete Work 143-178

    5. Reinforced Cement Concrete 179-270

    6. Masonry Work 271-312

    7. Stone Work 313-356

    8. Cladding Work 357-416

    9. Wood and PVC Work 417-664

    10. Steel Work 665-710

    11. Flooring 711-802

    12. Roofing 803-894

    C O N T E N T S

    Vol. 1

  • VIII

    SH. No. NAME OF SUB-HEAD PAGE No.

    13. Finishing 895-994

    14. Repairs to Buildings 995-1064

    15. Dismantling and Demolishing 1065-1112

    16. Road Work 1113-1256

    17. Sanitary Installations 1257-1370

    18. Water Supply 1371-1638

    19. Drainage 1639-1740

    20. Pile work 1741-1772

    21. Aluminium Work 1773-1804

    22. Water Proofing 1805-1830

    23. Rain Water Harvesting & Tubewells 1831-1856

    24 Conservation of Heritage Buildings. 1857-1864

    25. Structural Glazing Aluminium Composite Panel 1865-1876

    26. New Technologies and Materials 1877-1994

    Note: For Sub Heads 1 to 12 refer to Vol. 1

    C O N T E N T S

    Vol. 2

  • SUB HEAD : 13.0

    FINISHING

    895

  • 897SUB HEAD : 13- FINISHING

    13.1 12 mm cement plaster of mix :13.1.1 1:4 (1 cement: 4 fine sand)

    Detail of cost for 10 sqm

    MATERIAL

    Cement mortar 1 : 4 (1 cement :

    4 fine sand)

    3.4 Rate as per Item Number 3.4 of

    SH: Mortars cum 0.144 3528.85 508.15

    LABOUR

    0155 Mason (average) day 0.67 709.00 475.03

    0115 Coolie day 0.75 558.00 418.50

    0101 Bhisti day 0.92 617.00 567.64

    9999 Scaffolding and sundries L.S. 12.61 2.00 25.22

    TOTAL 1994.54 W

    Add 1 % Water charges on "W" 19.95

    TOTAL 2014.49 X

    Add GST on "X" (multiplying

    factor 0.1405) 283.04

    TOTAL 2297.53 Y

    Add 15% CPOH on "Y" 344.63

    TOTAL 2642.15 Z

    Add Cess @ 1% on "Z" 26.42

    Cost of 10.00 sqm 2668.58

    Cost of 1.00 sqm 266.86

    Say 266.85

    Code Description Unit Quantity Rate Amount

    13.1.2 1:6 (1 cement: 6 fine sand)

    Detail of cost for 10 sqm

    MATERIAL

    Cement mortar 1 : 6 (1 cement :

    6 fine sand)

    3.6 Rate as per Item Number 3.6 of

    SH: Mortars cum 0.144 2874.65 413.95

    LABOUR

    0155 Mason (average) day 0.67 709.00 475.03

    0115 Coolie day 0.75 558.00 418.50

    0101 Bhisti day 0.92 617.00 567.64

    9999 Scaffolding and sundries L.S. 12.61 2.00 25.22

    TOTAL 1900.34 W

    Add 1 % Water charges on "W" 19.00

    TOTAL 1919.34 X

    Add GST on "X" (multiplying

    factor 0.1405) 269.67

    TOTAL 2189.01 Y

    Add 15% CPOH on "Y" 328.35

    TOTAL 2517.36 Z

    Add Cess @ 1% on "Z" 25.17

    Cost of 10.00 sqm 2542.54

    Cost of 1.00 sqm 254.25

    Say 254.25

    Code Description Unit Quantity Rate Amount

  • 898SUB HEAD : 13- FINISHING

    13.2 15 mm cement plaster on the rough side of single or half brick wall of mix :13.2.1 1:4 (1 cement: 4 fine sand)

    Detail of cost for 10 sqm

    MATERIAL

    Cement mortar 1 : 4 (1 cement :

    4 fine sand)

    3.4 Rate as per Item Number 3.4 of

    SH: Mortars cum 0.172 3528.85 606.96

    LABOUR

    0155 Mason (average) day 0.80 709.00 567.20

    0115 Coolie day 0.88 558.00 491.04

    0101 Bhisti day 0.99 617.00 610.83

    9999 Scaffolding and sundries L.S. 12.61 2.00 25.22

    TOTAL 2301.25 W

    Add 1 % Water charges on "W" 23.01

    TOTAL 2324.26 X

    Add GST on "X" (multiplying

    factor 0.1405) 326.56

    TOTAL 2650.82 Y

    Add 15% CPOH on "Y" 397.62

    TOTAL 3048.45 Z

    Add Cess @ 1% on "Z" 30.48

    Cost of 10.00 sqm 3078.93

    Cost of 1.00 sqm 307.89

    Say 307.90

    Code Description Unit Quantity Rate Amount

    13.2.2 1:6 (1 cement: 6 fine sand)

    Detail of cost for 10 sqm

    MATERIAL

    Cement mortar 1 : 6 (1 cement :

    6 fine sand)

    3.6 Rate as per Item Number 3.6 of

    SH: Mortars cum 0.172 2874.65 494.44

    LABOUR

    0155 Mason (average) day 0.80 709.00 567.20

    0115 Coolie day 0.88 558.00 491.04

    0101 Bhisti day 0.99 617.00 610.83

    9999 Scaffolding and sundries L.S. 12.61 2.00 25.22

    TOTAL 2188.73 W

    Add 1 % Water charges on "W" 21.89

    TOTAL 2210.62 X

    Add GST on "X" (multiplying

    factor 0.1405) 310.59

    TOTAL 2521.21 Y

    Add 15% CPOH on "Y" 378.18

    TOTAL 2899.39 Z

    Add Cess @ 1% on "Z" 28.99

    Cost of 10.00 sqm 2928.38

    Cost of 1.00 sqm 292.84

    Say 292.85

    Code Description Unit Quantity Rate Amount

  • 899SUB HEAD : 13- FINISHING

    13.3 20 mm cement plaster of mix :13.3.1 1:4 (1 cement: 4 fine sand)

    Detail of cost for 10 sqm

    MATERIAL

    Cement mortar 1 : 4 (1 cement :

    4 fine sand)

    3.4 Rate as per Item Number 3.4 of

    SH: Mortars cum 0.224 3528.85 790.46

    LABOUR

    0155 Mason (average) day 0.94 709.00 666.46

    0115 Coolie day 1.02 558.00 569.16

    0101 Bhisti day 1.10 617.00 678.70

    9999 Scaffolding and sundries L.S. 12.61 2.00 25.22

    TOTAL 2730.00 W

    Add 1 % Water charges on "W" 27.30

    TOTAL 2757.30 X

    Add GST on "X" (multiplying

    factor 0.1405) 387.40

    TOTAL 3144.70 Y

    Add 15% CPOH on "Y" 471.71

    TOTAL 3616.41 Z

    Add Cess @ 1% on "Z" 36.16

    Cost of 10.00 sqm 3652.57

    Cost of 1.00 sqm 365.26

    Say 365.25

    Code Description Unit Quantity Rate Amount

    13.3.2 1:6 (1 cement: 6 fine sand)

    Detail of cost for 10 sqm

    MATERIAL

    Cement mortar 1 : 6 (1 cement :

    6 fine sand)

    3.6 Rate as per Item Number 3.6 of

    SH: Mortars cum 0.224 2874.65 643.92

    LABOUR

    0155 Mason (average) day 0.94 709.00 666.46

    0115 Coolie day 1.02 558.00 569.16

    0101 Bhisti day 1.10 617.00 678.70

    9999 Scaffolding and sundries L.S. 12.61 2.00 25.22

    TOTAL 2583.46 W

    Add 1 % Water charges on "W" 25.83

    TOTAL 2609.30 X

    Add GST on "X" (multiplying

    factor 0.1405) 366.61

    TOTAL 2975.90 Y

    Add 15% CPOH on "Y" 446.39

    TOTAL 3422.29 Z

    Add Cess @ 1% on "Z" 34.22

    Cost of 10.00 sqm 3456.51

    Cost of 1.00 sqm 345.65

    Say 345.65

    Code Description Unit Quantity Rate Amount

  • 900SUB HEAD : 13- FINISHING

    13.4 12 mm cement plaster of mix :13.4.1 1:4 (1 cement: 4 coarse sand)

    Detail of cost for 10 sqm

    MATERIAL

    Cement mortar 1 : 4 (1 cement :

    4 coarse sand)

    3.9 Rate as per Item Number 3.9 of

    SH: Mortars cum 0.144 4010.35 577.49

    LABOUR

    0155 Mason (average) day 0.67 709.00 475.03

    0115 Coolie day 0.75 558.00 418.50

    0101 Bhisti day 0.92 617.00 567.64

    9999 Scaffolding and sundries L.S. 12.61 2.00 25.22

    TOTAL 2063.88 W

    Add 1 % Water charges on "W" 20.64

    TOTAL 2084.52 X

    Add GST on "X" (multiplying

    factor 0.1405) 292.87

    TOTAL 2377.39 Y

    Add 15% CPOH on "Y" 356.61

    TOTAL 2734.00 Z

    Add Cess @ 1% on "Z" 27.34

    Cost of 10.00 sqm 2761.34

    Cost of 1.00 sqm 276.13

    Say 276.15

    Code Description Unit Quantity Rate Amount

    13.4.2 1:6 (1 cement: 6 coarse sand)

    Detail of cost for 10 sqm

    MATERIAL

    Cement mortar 1 : 6 (1 cement :

    6 coarse sand)

    3.11 Rate as per Item Number 3.11 of

    SH: Mortars cum 0.144 3356.15 483.29

    LABOUR

    0155 Mason (average) day 0.67 709.00 475.03

    0115 Coolie day 0.75 558.00 418.50

    0101 Bhisti day 0.92 617.00 567.64

    9999 Scaffolding and sundries L.S. 12.61 2.00 25.22

    TOTAL 1969.68 W

    Add 1 % Water charges on "W" 19.70

    TOTAL 1989.37 X

    Add GST on "X" (multiplying

    factor 0.1405) 279.51

    TOTAL 2268.88 Y

    Add 15% CPOH on "Y" 340.33

    TOTAL 2609.21 Z

    Add Cess @ 1% on "Z" 26.09

    Cost of 10.00 sqm 2635.30

    Cost of 1.00 sqm 263.53

    Say 263.55

    Code Description Unit Quantity Rate Amount

  • 901SUB HEAD : 13- FINISHING

    13.5 15 mm cement plaster on rough side of single or half brick wall of mix:13.5.1 1:4 (1 cement: 4 coarse sand)

    Detail of cost for 10 sqm

    MATERIAL

    Cement mortar 1 : 4 (1 cement :

    4 coarse sand)

    3.9 Rate as per Item Number 3.9 of

    SH: Mortars cum 0.172 4010.35 689.78

    LABOUR

    0155 Mason (average) day 0.80 709.00 567.20

    0115 Coolie day 0.88 558.00 491.04

    0101 Bhisti day 0.99 617.00 610.83

    9999 Scaffolding and sundries L.S. 12.61 2.00 25.22

    TOTAL 2384.07 W

    Add 1 % Water charges on "W" 23.84

    TOTAL 2407.91 X

    Add GST on "X" (multiplying

    factor 0.1405) 338.31

    TOTAL 2746.22 Y

    Add 15% CPOH on "Y" 411.93

    TOTAL 3158.16 Z

    Add Cess @ 1% on "Z" 31.58

    Cost of 10.00 sqm 3189.74

    Cost of 1.00 sqm 318.97

    Say 318.95

    Code Description Unit Quantity Rate Amount

    13.5.2 1:6 (1 cement: 6 coarse sand)

    Detail of cost for 10 sqm

    MATERIAL

    Cement mortar 1 : 6 (1 cement :

    6 coarse sand)

    3.11 Rate as per Item Number 3.11 of

    SH: Mortars cum 0.172 3356.15 577.26

    LABOUR

    0155 Mason (average) day 0.80 709.00 567.20

    0115 Coolie day 0.88 558.00 491.04

    0101 Bhisti day 0.99 617.00 610.83

    9999 Scaffolding and sundries L.S. 12.61 2.00 25.22

    TOTAL 2271.55 W

    Add 1 % Water charges on "W" 22.72

    TOTAL 2294.26 X

    Add GST on "X" (multiplying

    factor 0.1405) 322.34

    TOTAL 2616.61 Y

    Add 15% CPOH on "Y" 392.49

    TOTAL 3009.10 Z

    Add Cess @ 1% on "Z" 30.09

    Cost of 10.00 sqm 3039.19

    Cost of 1.00 sqm 303.92

    Say 303.90

    Code Description Unit Quantity Rate Amount

  • 902SUB HEAD : 13- FINISHING

    13.6 20 mm cement plaster of mix :13.6.1 1:4 (1 cement: 4 coarse sand)

    Detail of cost for 10 sqm

    MATERIAL

    Cement mortar 1 : 4 (1 cement :

    4 coarse sand)

    3.9 Rate as per Item Number 3.9 of

    SH: Mortars cum 0.224 4010.35 898.32

    LABOUR

    0155 Mason (average) day 0.94 709.00 666.46

    0115 Coolie day 1.02 558.00 569.16

    0101 Bhisti day 1.10 617.00 678.70

    9999 Scaffolding and sundries L.S. 12.61 2.00 25.22

    TOTAL 2837.86 W

    Add 1 % Water charges on "W" 28.38

    TOTAL 2866.24 X

    Add GST on "X" (multiplying

    factor 0.1405) 402.71

    TOTAL 3268.94 Y

    Add 15% CPOH on "Y" 490.34

    TOTAL 3759.28 Z

    Add Cess @ 1% on "Z" 37.59

    Cost of 10.00 sqm 3796.88

    Cost of 1.00 sqm 379.69

    Say 379.70

    Code Description Unit Quantity Rate Amount

    13.6.2 1:6 (1 cement: 6 coarse sand)

    Detail of cost for 10 sqm

    MATERIAL

    Cement mortar 1 : 6 (1 cement :

    6 coarse sand)

    3.11 Rate as per Item Number 3.11 of

    SH: Mortars cum 0.224 3356.15 751.78

    LABOUR

    0155 Mason (average) day 0.94 709.00 666.46

    0115 Coolie day 1.02 558.00 569.16

    0101 Bhisti day 1.10 617.00 678.70

    9999 Scaffolding and sundries L.S. 12.61 2.00 25.22

    TOTAL 2691.32 W

    Add 1 % Water charges on "W" 26.91

    TOTAL 2718.23 X

    Add GST on "X" (multiplying

    factor 0.1405) 381.91

    TOTAL 3100.14 Y

    Add 15% CPOH on "Y" 465.02

    TOTAL 3565.16 Z

    Add Cess @ 1% on "Z" 35.65

    Cost of 10.00 sqm 3600.82

    Cost of 1.00 sqm 360.08

    Say 360.10

    Code Description Unit Quantity Rate Amount

  • 903SUB HEAD : 13- FINISHING

    13.7 12 mm cement plaster finished with a floating coat of neat cement of mix :13.7.1 1:3 (1 cement: 3 fine sand)

    Detail of cost for 10 sqm

    MATERIAL

    Cement mortar 1 : 3 (1 cement :

    3 fine sand)

    3.3 Rate as per Item Number 3.3 of

    SH: Mortars cum 0.144 4183.05 602.36

    LABOUR

    0155 Mason (average) day 0.67 709.00 475.03

    0115 Coolie day 0.75 558.00 418.50

    0101 Bhisti day 0.92 617.00 567.64

    9999 Scaffolding and sundries L.S. 12.61 2.00 25.22

    0367 Portland Cement (OPC-43 grade) tonne 0.02 4940.00 98.80

    2209 Carriage of Cement tonne 0.02 92.24 1.84

    0155 Mason (average) day 0.27 709.00 191.43

    0115 Coolie day 0.27 558.00 150.66

    9999 Scaffolding and sundries L.S. 8.06 2.00 16.12

    TOTAL 2547.60 W

    Add 1 % Water charges on "W" 25.48

    TOTAL 2573.08 X

    Add GST on "X" (multiplying

    factor 0.1405) 361.52

    TOTAL 2934.60 Y

    Add 15% CPOH on "Y" 440.19

    TOTAL 3374.79 Z

    Add Cess @ 1% on "Z" 33.75

    Cost of 10.00 sqm 3408.54

    Cost of 1.00 sqm 340.85

    Say 340.85

    Code Description Unit Quantity Rate Amount

    13.7.2 1:4 (1 cement: 4 fine sand)

    Detail of cost for 10 sqm

    MATERIAL

    Cement mortar 1 : 4 (1 cement :

    4 fine sand)

    3.4 Rate as per Item Number 3.4 of

    SH: Mortars cum 0.144 3528.85 508.15

    LABOUR

    0155 Mason (average) day 0.67 709.00 475.03

    0115 Coolie day 0.75 558.00 418.50

    0101 Bhisti day 0.92 617.00 567.64

    9999 Scaffolding and sundries L.S. 12.61 2.00 25.22

    0367 Portland Cement (OPC-43 grade) tonne 0.02 4940.00 98.80

    2209 Carriage of Cement tonne 0.02 92.24 1.84

    0155 Mason (average) day 0.27 709.00 191.43

    0115 Coolie day 0.27 558.00 150.66

    Code Description Unit Quantity Rate Amount

  • 904SUB HEAD : 13- FINISHING

    9999 Scaffolding and sundries L.S. 8.06 2.00 16.12

    TOTAL 2453.40 W

    Add 1 % Water charges on "W" 24.53

    TOTAL 2477.93 X

    Add GST on "X" (multiplying

    factor 0.1405) 348.15

    TOTAL 2826.08 Y

    Add 15% CPOH on "Y" 423.91

    TOTAL 3250.00 Z

    Add Cess @ 1% on "Z" 32.50

    Cost of 10.00 sqm 3282.50

    Cost of 1.00 sqm 328.25

    Say 328.25

    Code Description Unit Quantity Rate Amount

    13.8 15 mm cement plaster on rough side of single or half brick wall finished with afloating coat of neat cement of mix :

    13.8.1 1:3 (1 cement: 3 fine sand)

    Detail of cost for 10 sqm

    MATERIAL

    Cement mortar 1 : 3 (1 cement :

    3 fine sand)

    3.3 Rate as per Item Number 3.3 of

    SH: Mortars cum 0.172 4183.05 719.48

    LABOUR

    0155 Mason (average) day 0.80 709.00 567.20

    0115 Coolie day 0.88 558.00 491.04

    0101 Bhisti day 0.99 617.00 610.83

    9999 Scaffolding and sundries L.S. 12.61 2.00 25.22

    0367 Portland Cement (OPC-43 grade) tonne 0.02 4940.00 98.80

    2209 Carriage of Cement tonne 0.02 92.24 1.84

    0155 Mason (average) day 0.27 709.00 191.43

    0115 Coolie day 0.27 558.00 150.66

    9999 Scaffolding and sundries L.S. 8.06 2.00 16.12

    TOTAL 2872.63 W

    Add 1 % Water charges on "W" 28.73

    TOTAL 2901.36 X

    Add GST on "X" (multiplying

    factor 0.1405) 407.64

    TOTAL 3309.00 Y

    Add 15% CPOH on "Y" 496.35

    TOTAL 3805.35 Z

    Add Cess @ 1% on "Z" 38.05

    Cost of 10.00 sqm 3843.40

    Cost of 1.00 sqm 384.34

    Say 384.35

    Code Description Unit Quantity Rate Amount

  • 905SUB HEAD : 13- FINISHING

    13.8.2 1:4 (1 cement: 4 fine sand)

    Detail of cost for 10 sqm

    MATERIAL

    Cement mortar 1 : 4 (1 cement :

    4 fine sand)

    3.4 Rate as per Item Number 3.4 of

    SH: Mortars cum 0.172 3528.85 606.96

    LABOUR

    0155 Mason (average) day 0.80 709.00 567.20

    0115 Coolie day 0.88 558.00 491.04

    0101 Bhisti day 0.99 617.00 610.83

    9999 Scaffolding and sundries L.S. 12.61 2.00 25.22

    0367 Portland Cement (OPC-43 grade) tonne 0.02 4940.00 98.80

    2209 Carriage of Cement tonne 0.02 92.24 1.84

    0155 Mason (average) day 0.27 709.00 191.43

    0115 Coolie day 0.27 558.00 150.66

    9999 Scaffolding and sundries L.S. 8.06 2.00 16.12

    TOTAL 2760.11 W

    Add 1 % Water charges on "W" 27.60

    TOTAL 2787.71 X

    Add GST on "X" (multiplying

    factor 0.1405) 391.67

    TOTAL 3179.38 Y

    Add 15% CPOH on "Y" 476.91

    TOTAL 3656.29 Z

    Add Cess @ 1% on "Z" 36.56

    Cost of 10.00 sqm 3692.85

    Cost of 1.00 sqm 369.29

    Say 369.30

    Code Description Unit Quantity Rate Amount

    13.9 Cement plaster 1:3 (1 cement: 3 coarse sand) finished with a floating coat ofneat cement.

    13.9.1 12 mm cement plaster

    Detail of cost for 10 sqm

    MATERIAL

    Cement mortar 1:3 (1 cement :

    3 coarse sand)

    3.8 Rate as per Item Number 3.8 of

    SH: Mortars cum 0.144 4664.55 671.70

    LABOUR

    0155 Mason (average) day 0.67 709.00 475.03

    0115 Coolie day 0.75 558.00 418.50

    0101 Bhisti day 0.92 617.00 567.64

    9999 Scaffolding and sundries L.S. 12.61 2.00 25.22

    0367 Portland Cement (OPC-43 grade) tonne 0.02 4940.00 98.80

    2209 Carriage of Cement tonne 0.02 92.24 1.84

    0155 Mason (average) day 0.27 709.00 191.43

    0115 Coolie day 0.27 558.00 150.66

    Code Description Unit Quantity Rate Amount

  • 906SUB HEAD : 13- FINISHING

    9999 Scaffolding and sundries L.S. 8.06 2.00 16.12

    TOTAL 2616.94 W

    Add 1 % Water charges on "W" 26.17

    TOTAL 2643.11 X

    Add GST on "X" (multiplying

    factor 0.1405) 371.36

    TOTAL 3014.47 Y

    Add 15% CPOH on "Y" 452.17

    TOTAL 3466.64 Z

    Add Cess @ 1% on "Z" 34.67

    Cost of 10.00 sqm 3501.30

    Cost of 1.00 sqm 350.13

    Say 350.15

    Code Description Unit Quantity Rate Amount

    13.9.2 20 mm cement plaster

    Detail of cost for 10 sqm

    MATERIAL

    Cement mortar 1:3 (1 cement :

    3 coarse sand)

    3.8 Rate as per Item Number 3.8 of

    SH: Mortars cum 0.224 4664.55 1044.86

    LABOUR

    0155 Mason (average) day 0.94 709.00 666.46

    0115 Coolie day 1.02 558.00 569.16

    0101 Bhisti day 1.10 617.00 678.70

    9999 Scaffolding and sundries L.S. 12.61 2.00 25.22

    0367 Portland Cement (OPC-43 grade) tonne 0.02 4940.00 98.80

    2209 Carriage of Cement tonne 0.02 92.24 1.84

    0155 Mason (average) day 0.27 709.00 191.43

    0115 Coolie day 0.27 558.00 150.66

    9999 Scaffolding and sundries L.S. 8.06 2.00 16.12

    TOTAL 3443.25 W

    Add 1 % Water charges on "W" 34.43

    TOTAL 3477.69 X

    Add GST on "X" (multiplying

    factor 0.1405) 488.61

    TOTAL 3966.30 Y

    Add 15% CPOH on "Y" 594.95

    TOTAL 4561.25 Z

    Add Cess @ 1% on "Z" 45.61

    Cost of 10.00 sqm 4606.86

    Cost of 1.00 sqm 460.69

    Say 460.70

    Code Description Unit Quantity Rate Amount

  • 907SUB HEAD : 13- FINISHING

    13.10 15 mm cement plaster 1:3 (1 cement: 3 coarse sand) finished with a floatingcoat of neat cement on the rough side of single or half brick wall.

    Detail of cost for 10 sqm

    MATERIAL

    Cement mortar 1:3 (1 cement :

    3 coarse sand)

    3.8 Rate as per Item Number 3.8 of

    SH: Mortars cum 0.172 4664.55 802.30

    LABOUR

    0155 Mason (average) day 0.80 709.00 567.20

    0115 Coolie day 0.88 558.00 491.04

    0101 Bhisti day 0.99 617.00 610.83

    9999 Scaffolding and sundries L.S. 12.61 2.00 25.22

    0367 Portland Cement (OPC-43 grade) tonne 0.02 4940.00 98.80

    2209 Carriage of Cement tonne 0.02 92.24 1.84

    0155 Mason (average) day 0.27 709.00 191.43

    0115 Coolie day 0.27 558.00 150.66

    9999 Scaffolding and sundries L.S. 8.06 2.00 16.12

    TOTAL 2955.45 W

    Add 1 % Water charges on "W" 29.55

    TOTAL 2985.00 X

    Add GST on "X" (multiplying

    factor 0.1405) 419.39

    TOTAL 3404.39 Y

    Add 15% CPOH on "Y" 510.66

    TOTAL 3915.05 Z

    Add Cess @ 1% on "Z" 39.15

    Cost of 10.00 sqm 3954.20

    Cost of 1.00 sqm 395.42

    Say 395.40

    Code Description Unit Quantity Rate Amount

    13.11 18 mm cement plaster in two coats under layer 12 mm thick cement plaster 1:5(1 cement : 5 coarse sand) finished with a top layer 6 mm thick cement plaster1:6 (1 cement : 6 fine sand).

    Detail of cost for 10 sqm

    MATERIAL

    Under layer Cement mortar

    1 : 5 (1 cement : 5 coarse sand)

    3.10 Rate as per Item Number 3.10 of

    SH: Mortars cum 0.144 3658.10 526.77

    Top layer Cement mortar

    1 : 6 (1 cement : 6 fine sand)

    3.6 Rate as per Item Number 3.6 of

    SH: Mortars cum 0.072 2874.65 206.97

    LABOUR

    0155 Mason (average) day 1.21 709.00 857.89

    0115 Coolie day 1.29 558.00 719.82

    0101 Bhisti day 1.05 617.00 647.85

    Code Description Unit Quantity Rate Amount

  • 908SUB HEAD : 13- FINISHING

    9999 Scaffolding and sundries L.S. 12.61 2.00 25.22

    TOTAL 2984.52 W

    Add 1 % Water charges on "W" 29.85

    TOTAL 3014.37 X

    Add GST on "X" (multiplying

    factor 0.1405) 423.52

    TOTAL 3437.88 Y

    Add 15% CPOH on "Y" 515.68

    TOTAL 3953.57 Z

    Add Cess @ 1% on "Z" 39.54

    Cost of 10.00 sqm 3993.10

    Cost of 1.00 sqm 399.31

    Say 399.30

    Code Description Unit Quantity Rate Amount

    13.12 18 mm cement plaster in two coats under layer 12 mm thick cement plaster 1:5(1 cement : 5 coarse sand) and a top layer 6 mm thick cement plaster 1:3 (1cement : 3 coarse sand) finished rough with sponge.

    Detail of cost for 10 sqm

    MATERIAL

    Under layer Cement mortar

    1 : 5 (1 cement : 5 coarse sand)

    3.10 Rate as per Item Number 3.10 of

    SH: Mortars cum 0.144 3658.10 526.77

    Top layer Cement mortar

    1:3 (1 cement : 3 coarse sand)

    3.8 Rate as per Item Number 3.8 of

    SH: Mortars cum 0.072 4664.55 335.85

    LABOUR

    0155 Mason (average) day 1.21 709.00 857.89

    0115 Coolie day 1.29 558.00 719.82

    0101 Bhisti day 1.05 617.00 647.85

    9999 Scaffolding and sundries L.S. 12.61 2.00 25.22

    TOTAL 3113.39 W

    Add 1 % Water charges on "W" 31.13

    TOTAL 3144.53 X

    Add GST on "X" (multiplying

    factor 0.1405) 441.81

    TOTAL 3586.33 Y

    Add 15% CPOH on "Y" 537.95

    TOTAL 4124.28 Z

    Add Cess @ 1% on "Z" 41.24

    Cost of 10.00 sqm 4165.53

    Cost of 1.00 sqm 416.55

    Say 416.55

    Code Description Unit Quantity Rate Amount

  • 909SUB HEAD : 13- FINISHING

    13.13 12 mm cement plaster 1:2 (1 cement : 2 stone dust).

    Detail of cost for 10 sqm

    MATERIAL

    Cement mortar 1:2 (1 Cement :

    2 stone dust)

    3.12 Rate as per Item Number 3.12 of

    SH: Mortars cum 0.144 5108.05 735.56

    LABOUR

    0155 Mason (average) day 0.67 709.00 475.03

    0115 Coolie day 0.75 558.00 418.50

    0101 Bhisti day 0.92 617.00 567.64

    9999 Scaffolding and sundries L.S. 12.61 2.00 25.22

    TOTAL 2221.95 W

    Add 1 % Water charges on "W" 22.22

    TOTAL 2244.17 X

    Add GST on "X" (multiplying

    factor 0.1405) 315.31

    TOTAL 2559.47 Y

    Add 15% CPOH on "Y" 383.92

    TOTAL 2943.40 Z

    Add Cess @ 1% on "Z" 29.43

    Cost of 10.00 sqm 2972.83

    Cost of 1.00 sqm 297.28

    Say 297.30

    Code Description Unit Quantity Rate Amount

    13.14 15 mm cement plaster 1:2 (1 cement : 2 stone dust) on the rough side of singleor half brick wall.

    Detail of cost for 10 sqm

    MATERIAL

    Cement mortar 1:2 (1 Cement :

    2 stone dust)

    3.12 Rate as per Item Number 3.12 of

    SH: Mortars cum 0.172 5108.05 878.58

    LABOUR

    0155 Mason (average) day 0.80 709.00 567.20

    0115 Coolie day 0.88 558.00 491.04

    0101 Bhisti day 0.99 617.00 610.83

    9999 Scaffolding and sundries L.S. 12.61 2.00 25.22

    TOTAL 2572.87 W

    Add 1 % Water charges on "W" 25.73

    TOTAL 2598.60 X

    Add GST on "X" (multiplying

    factor 0.1405) 365.10

    TOTAL 2963.71 Y

    Add 15% CPOH on "Y" 444.56

    TOTAL 3408.26 Z

    Add Cess @ 1% on "Z" 34.08

    Cost of 10.00 sqm 3442.35

    Cost of 1.00 sqm 344.23

    Say 344.25

    Code Description Unit Quantity Rate Amount

  • 910SUB HEAD : 13- FINISHING

    13.15 20 mm cement plaster 1:2 (1 cement : 2 stone dust).

    Detail of cost for 10 sqm

    MATERIAL

    Cement mortar 1:2 (1 Cement :

    2 stone dust)

    3.12 Rate as per Item Number 3.12 of

    SH: Mortars cum 0.224 5108.05 1144.20

    LABOUR

    0155 Mason (average) day 0.94 709.00 666.46

    0115 Coolie day 1.02 558.00 569.16

    0101 Bhisti day 1.10 617.00 678.70

    9999 Scaffolding and sundries L.S. 12.61 2.00 25.22

    TOTAL 3083.74 W

    Add 1 % Water charges on "W" 30.84

    TOTAL 3114.58 X

    Add GST on "X" (multiplying

    factor 0.1405) 437.60

    TOTAL 3552.18 Y

    Add 15% CPOH on "Y" 532.83

    TOTAL 4085.01 Z

    Add Cess @ 1% on "Z" 40.85

    Cost of 10.00 sqm 4125.86

    Cost of 1.00 sqm 412.59

    Say 412.60

    Code Description Unit Quantity Rate Amount

    13.16 6 mm cement plaster of mix :13.16.1 1:3 (1 cement : 3 fine sand)

    Detail of cost for 10 sqm

    MATERIAL

    Cement mortar 1 : 3 (1 cement :

    3 fine sand)

    3.3 Rate as per Item Number 3.3 of

    SH: Mortars cum 0.072 4183.05 301.18

    LABOUR

    0155 Mason (average) day 0.51 709.00 361.59

    0115 Coolie day 0.75 558.00 418.50

    0101 Bhisti day 0.92 617.00 567.64

    9999 Extra for removing burrs, cleaning with

    wire brushes, pock making with pointed

    tool etc. complete. L.S. 13.39 2.00 26.78

    Code Description Unit Quantity Rate Amount

  • 911SUB HEAD : 13- FINISHING

    9999 Scaffolding and sundries L.S. 11.70 2.00 23.40

    TOTAL 1699.09 W

    Add 1 % Water charges on "W" 16.99

    TOTAL 1716.08 X

    Add GST on "X" (multiplying

    factor 0.1405) 241.11

    TOTAL 1957.19 Y

    Add 15% CPOH on "Y" 293.58

    TOTAL 2250.77 Z

    Add Cess @ 1% on "Z" 22.51

    Cost of 10.00 sqm 2273.28

    Cost of 1.00 sqm 227.33

    Say 227.35

    Code Description Unit Quantity Rate Amount

    13.17 6 mm cement plaster 1:3 (1 cement : 3 fine sand) finished with a floating coat ofneat cement and thick coat of Lime wash on top of walls when dry for bearingof R.C.C. slabs and beams.

    Detail of cost for 10 sqm

    MATERIAL

    Cement mortar 1 : 3 (1 cement :

    3 fine sand)

    3.3 Rate as per Item Number 3.3 of

    SH: Mortars cum 0.072 4183.05 301.18

    LABOUR

    0155 Mason (average) day 0.51 709.00 361.59

    0115 Coolie day 0.75 558.00 418.50

    0101 Bhisti day 0.92 617.00 567.64

    9999 Extra for removing burrs, cleaning with

    wire brushes, pock making with pointed

    tool etc. complete. L.S. 13.39 2.00 26.78

    9999 Scaffolding and sundries L.S. 11.7 2.00 23.40

    0367 Portland Cement (OPC-43 grade) tonne 0.02 4940.00 98.80

    2209 Carriage of Cement tonne 0.02 92.24 1.84

    0155 Mason (average) day 0.27 709.00 191.43

    0115 Coolie day 0.27 558.00 150.66

    9999 Scaffolding and sundries L.S. 8.06 2.00 16.12

    0776 Satna lime quintal 0.01 370.00 3.70

    9999 Indigo gum etc L.S. 2.08 2.00 4.16

    9999 Sundries ladder etc. L.S. 0.52 2.00 1.04

    0141 White Washer day 0.07 617.00 43.19

    0115 Coolie day 0.07 558.00 39.06

    Code Description Unit Quantity Rate Amount

  • 912SUB HEAD : 13- FINISHING

    9999 Sundries L.S. 2.73 2.00 5.46

    TOTAL 2254.55 W

    Add 1 % Water charges on "W" 22.55

    TOTAL 2277.10 X

    Add GST on "X" (multiplying

    factor 0.1405) 319.93

    TOTAL 2597.03 Y

    Add 15% CPOH on "Y" 389.55

    TOTAL 2986.59 Z

    Add Cess @ 1% on "Z" 29.87

    Cost of 10.00 sqm 3016.45

    Cost of 1.00 sqm 301.65

    Say 301.65

    Code Description Unit Quantity Rate Amount

    13.18 Neat cement punning.

    Detail of cost for 10 sqm

    LABOUR

    0367 Portland Cement (OPC-43 grade) tonne 0.022 4940.00 108.68

    2209 Carriage of Cement tonne 0.022 92.24 2.03

    0155 Mason (average) day 0.27 709.00 191.43

    0115 Coolie day 0.27 558.00 150.66

    9999 Scaffolding and sundries L.S. 8.06 2.00 16.12

    TOTAL 468.92 W

    Add 1 % Water charges on "W" 4.69

    TOTAL 473.61 X

    Add GST on "X" (multiplying

    factor 0.1405) 66.54

    TOTAL 540.15 Y

    Add 15% CPOH on "Y" 81.02

    TOTAL 621.17 Z

    Add Cess @ 1% on "Z" 6.21

    Cost of 10.00 sqm 627.38

    Cost of 1.00 sqm 62.74

    Say 62.75

    Code Description Unit Quantity Rate Amount

    13.19 Rough cast plaster upto 10 m height above ground level with a mixture of sandand gravel or crushed stone from 6 mm to 10 mm nominal size, dashed overand including the fresh plaster in two layers, under layer 12 mm cement plaster1:4 (1 cement : 4 coarse sand) and top layer 10 mm cement plaster 1:3 (1 cement: 3 fine sand) mixed with 10% finely grounded hydrated lime by volume of cement.

    13.19.1 Ordinary cement finish using ordinary cement

    Detail of cost for 10 sqm

    MATERIAL

    Under layer 12 mm thick cement plaster

    Cement mortar 1 : 4 (1 cement :

    4 coarse sand)

    Code Description Unit Quantity Rate Amount

  • 913SUB HEAD : 13- FINISHING

    3.9 Rate as per Item Number 3.9 of

    SH: Mortars cum 0.144 4010.35 577.49

    LABOUR

    0155 Mason (average) day 0.67 709.00 475.03

    0114 Beldar day 0.75 558.00 418.50

    0101 Bhisti day 0.92 617.00 567.64

    9999 Scaffolding and sundries L.S. 9.88 2.00 19.76

    Top layer 10 mm thick cement plaster

    Cement mortar 1 : 3 (1 cement :

    3 fine sand)

    3.3 Rate as per Item Number 3.3 of

    SH: Mortars cum 0.12 4183.05 501.97

    0155 Mason (average) day 0.61 709.00 432.49

    0114 Beldar day 0.69 558.00 385.02

    0101 Bhisti day 0.85 617.00 524.45

    9999 Scaffolding and sundries L.S. 9.88 2.00 19.76

    1179 Crushed stone 2.36 mm to

    12.5 mm size cum 0.10 900.00 90.00

    0101 Bhisti day 0.01 617.00 6.17

    0777 Dry hydrated lime (factory made) quintal 0.09 290.00 26.10

    9977 Carriage of lime L.S. 3.64 2.00 7.28

    0155 Mason (average) day 0.50 709.00 354.50

    0114 Beldar day 0.50 558.00 279.00

    0101 Bhisti day 0.10 617.00 61.70

    9999 Scaffolding and sundries L.S. 9.88 2.00 19.76

    Labour for scooping

    0123 Mason (brick layer) 1st class day 0.25 738.00 184.50

    0114 Beldar day 0.25 558.00 139.50

    TOTAL 5090.62 W

    Add 1 % Water charges on "W" 50.91

    TOTAL 5141.52 X

    Add GST on "X" (multiplying

    factor 0.1405) 722.38

    TOTAL 5863.91 Y

    Add 15% CPOH on "Y" 879.59

    TOTAL 6743.49 Z

    Add Cess @ 1% on "Z" 67.43

    Cost of 10.00 sqm 6810.93

    Cost of 1.00 sqm 681.09

    Say 681.10

    Code Description Unit Quantity Rate Amount

    13.20 Pebble dash plaster upto 10 m height above ground level with a mixture ofwashed pebble or crushed stone 6 mm to 12.5 mm nominal size, dashed overand including fresh plaster in two layers under layer 12 mm cement plaster 1:4(1 cement : 4 coarse sand) and top layer 10 mm cement plaster with cementmortar 1:3 (1 cement : 3 fine sand) mixed with 10% finely grounded hydratedlime by volume of cement.

    Detail of cost for 10 sqm

    MATERIAL

    Under layer 12 mm thick cement plaster

    Code Description Unit Quantity Rate Amount

  • 914SUB HEAD : 13- FINISHING

    Cement mortar 1 : 4 (1 cement :

    4 coarse sand)

    3.9 Rate as per Item Number 3.9 of

    SH: Mortars cum 0.144 4010.35 577.49

    LABOUR

    0155 Mason (average) day 0.67 709.00 475.03

    0114 Beldar day 0.75 558.00 418.50

    0101 Bhisti day 0.92 617.00 567.64

    9999 Scaffolding and sundries L.S. 9.88 2.00 19.76

    Top layer 10 mm thick cement plaster

    Cement mortar 1 : 3 (1 cement :

    3 fine sand)

    3.3 Rate as per Item Number 3.3 of

    SH: Mortars cum 0.12 4183.05 501.97

    0155 Mason (average) day 0.61 709.00 432.49

    0114 Beldar day 0.69 558.00 385.02

    0101 Bhisti day 0.85 617.00 524.45

    9999 Scaffolding and sundries L.S. 9.88 2.00 19.76

    1179 Crushed stone 2.36 mm to

    12.5 mm size cum 0.10 900.00 90.00

    0101 Bhisti day 0.01 617.00 6.17

    0777 Dry hydrated lime (factory made) quintal 0.09 290.00 26.10

    9977 Carriage of lime L.S. 3.64 2.00 7.28

    0155 Mason (average) day 0.50 709.00 354.50

    0114 Beldar day 0.50 558.00 279.00

    0101 Bhisti day 0.10 617.00 61.70

    9999 Scaffolding and sundries L.S. 9.88 2.00 19.76

    9999 Scaffolding and sundries L.S. 4.42 2.00 8.84

    TOTAL 4775.46 W

    Add 1 % Water charges on "W" 47.75

    TOTAL 4823.21 X

    Add GST on "X" (multiplying

    factor 0.1405) 677.66

    TOTAL 5500.87 Y

    Add 15% CPOH on "Y" 825.13

    TOTAL 6326.00 Z

    Add Cess @ 1% on "Z" 63.26

    Cost of 10.00 sqm 6389.26

    Cost of 1.00 sqm 638.93

    Say 638.95

    Code Description Unit Quantity Rate Amount

    13.21 Extra for providing and mixing water proofing material in cement plaster workin proportion recommended by the manufacturers.

    Detail of cost for 12mm cement

    plaster 1:3

    (1 cement :3 sand) = 10 sqm or 1.48

    bags of cement used in the mix.

    Cement required for 10 sqm = 73.89kg.

    Water proofing material required @

    1 kg per 50 kg of cement = 1.48 kg.

    Code Description Unit Quantity Rate Amount

  • 915SUB HEAD : 13- FINISHING

    1213 Water proofing materials kilogram 1.48 35.00 51.80

    9999 Sundries L.S. 7.15 2.00 14.30

    TOTAL 66.10 W

    Add 1 % Water charges on "W" 0.66

    TOTAL 66.76 X

    Add GST on "X" (multiplying

    factor 0.1405) 9.38

    TOTAL 76.14 Y

    Add 15% CPOH on "Y" 11.42

    TOTAL 87.56 Z

    Add Cess @ 1% on "Z" 0.88

    Cost of 1.48 bags of cement used in

    the mix. 88.44

    Cost of 1.00 bag of 50 kg cement

    used in the mix. 59.76

    Say 59.75

    Code Description Unit Quantity Rate Amount

    13.22 Extra for plastering exterior walls of height more than 10 m from ground levelfor every additional height of 3 m or part thereof.

    Detail of cost for 10 sqm

    9999 Scaffolding and sundries L.S. 53.82 2.00 107.64

    LABOUR

    0155 Mason (average) day 0.20 709.00 141.80

    0115 Coolie day 0.30 558.00 167.40

    0101 Bhisti day 0.10 617.00 61.70

    9999 Sundries L.S. 7.15 2.00 14.30

    TOTAL 492.84 W

    Add 1 % Water charges on "W" 4.93

    TOTAL 497.77 X

    Add GST on "X" (multiplying

    factor 0.1405) 69.94

    TOTAL 567.70 Y

    Add 15% CPOH on "Y" 85.16

    TOTAL 652.86 Z

    Add Cess @ 1% on "Z" 6.53

    Cost of 10.00 sqm 659.39

    Cost of 1.00 sqm 65.94

    Say 65.95

    Code Description Unit Quantity Rate Amount

    13.23 Extra for plastering on circular work not exceeding 6 m in radius:13.23.1 In one coat

    Detail of cost for 10 sqm

    LABOUR

    0155 Mason (average) day 0.20 709.00 141.80

    0114 Beldar day 0.20 558.00 111.60

    Code Description Unit Quantity Rate Amount

  • 916SUB HEAD : 13- FINISHING

    9999 Sundries L.S. 7.15 2.00 14.30

    TOTAL 267.70 W

    Add 1 % Water charges on "W" 2.68

    TOTAL 270.38 X

    Add GST on "X" (multiplying

    factor 0.1405) 37.99

    TOTAL 308.36 Y

    Add 15% CPOH on "Y" 46.25

    TOTAL 354.62 Z

    Add Cess @ 1% on "Z" 3.55

    Cost of 10.00 sqm 358.17

    Cost of 1.00 sqm 35.82

    Say 35.80

    Code Description Unit Quantity Rate Amount

    13.23.2 In two coats

    Detail of cost for 10 sqm

    LABOUR

    0155 Mason (average) day 0.30 709.00 212.70

    0114 Beldar day 0.30 558.00 167.40

    9999 Sundries L.S. 13.39 2.00 26.78

    TOTAL 406.88 W

    Add 1 % Water charges on "W" 4.07

    TOTAL 410.95 X

    Add GST on "X" (multiplying

    factor 0.1405) 57.74

    TOTAL 468.69 Y

    Add 15% CPOH on "Y" 70.30

    TOTAL 538.99 Z

    Add Cess @ 1% on "Z" 5.39

    Cost of 10.00 sqm 544.38

    Cost of 1.00 sqm 54.44

    Say 54.45

    Code Description Unit Quantity Rate Amount

    13.24 Extra for plastering done on moulding, cornices or architraves including neatfinish to line and level:

    13.24.1 In one coat

    Detail of cost for 10 sqm

    LABOUR

    0155 Mason (average) day 3.00 709.00 2127.00

    0114 Beldar day 2.00 558.00 1116.00

    0115 Coolie day 1.00 558.00 558.00

    0101 Bhisti day 0.25 617.00 154.25

    Code Description Unit Quantity Rate Amount

  • 917SUB HEAD : 13- FINISHING

    9999 Sundries L.S. 13.39 2.00 26.78

    TOTAL 3982.03 W

    Add 1 % Water charges on "W" 39.82

    TOTAL 4021.85 X

    Add GST on "X" (multiplying

    factor 0.1405) 565.07

    TOTAL 4586.92 Y

    Add 15% CPOH on "Y" 688.04

    TOTAL 5274.96 Z

    Add Cess @ 1% on "Z" 52.75

    Cost of 10.00 sqm 5327.71

    Cost of 1.00 sqm 532.77

    Say 532.75

    Code Description Unit Quantity Rate Amount

    13.24.2 In two coats

    Detail of cost for 10 sqm

    LABOUR

    0155 Mason (average) day 5.00 709.00 3545.00

    0114 Beldar day 3.00 558.00 1674.00

    0115 Coolie day 2.00 558.00 1116.00

    0101 Bhisti day 0.33 617.00 203.61

    9999 Sundries L.S. 13.39 2.00 26.78

    TOTAL 6565.39 W

    Add 1 % Water charges on "W" 65.65

    TOTAL 6631.04 X

    Add GST on "X" (multiplying

    factor 0.1405) 931.66

    TOTAL 7562.71 Y

    Add 15% CPOH on "Y" 1134.41

    TOTAL 8697.11 Z

    Add Cess @ 1% on "Z" 86.97

    Cost of 10.00 sqm 8784.08

    Cost of 1.00 sqm 878.41

    Say 878.40

    Code Description Unit Quantity Rate Amount

    13.25 Extra for plastering:13.25.1 Spherical ceiling

    Detail of cost for 10 sqm

    LABOUR

    0155 Mason (average) day 0.75 709.00 531.75

    0114 Beldar day 0.74 558.00 412.92

    Code Description Unit Quantity Rate Amount

  • 918SUB HEAD : 13- FINISHING

    9999 Sundries L.S. 26.91 2.00 53.82

    TOTAL 998.49 W

    Add 1 % Water charges on "W" 9.98

    TOTAL 1008.47 X

    Add GST on "X" (multiplying

    factor 0.1405) 141.69

    TOTAL 1150.17 Y

    Add 15% CPOH on "Y" 172.52

    TOTAL 1322.69 Z

    Add Cess @ 1% on "Z" 13.23

    Cost of 10.00 sqm 1335.92

    Cost of 1.00 sqm 133.59

    Say 133.60

    Code Description Unit Quantity Rate Amount

    13.25.2 Groined ceiling

    Detail of cost for 10 sqm

    LABOUR

    0155 Mason (average) day 0.80 709.00 567.20

    0114 Beldar day 0.80 558.00 446.40

    9999 Sundries L.S. 34.06 2.00 68.12

    TOTAL 1081.72 W

    Add 1 % Water charges on "W" 10.82

    TOTAL 1092.54 X

    Add GST on "X" (multiplying

    factor 0.1405) 153.50

    TOTAL 1246.04 Y

    Add 15% CPOH on "Y" 186.91

    TOTAL 1432.94 Z

    Add Cess @ 1% on "Z" 14.33

    Cost of 10.00 sqm 1447.27

    Cost of 1.00 sqm 144.73

    Say 144.75

    Code Description Unit Quantity Rate Amount

    13.25.3 Flewing soffits

    Detail of cost for 10 sqm

    LABOUR

    0155 Mason (average) day 0.50 709.00 354.50

    0114 Beldar day 0.50 558.00 279.00

    Code Description Unit Quantity Rate Amount

  • 919SUB HEAD : 13- FINISHING

    9999 Sundries L.S. 13.39 2.00 26.78

    TOTAL 660.28 W

    Add 1 % Water charges on "W" 6.60

    TOTAL 666.88 X

    Add GST on "X" (multiplying

    factor 0.1405) 93.70

    TOTAL 760.58 Y

    Add 15% CPOH on "Y" 114.09

    TOTAL 874.67 Z

    Add Cess @ 1% on "Z" 8.75

    Cost of 10.00 sqm 883.41

    Cost of 1.00 sqm 88.34

    Say 88.35

    Code Description Unit Quantity Rate Amount

    13.26 Providing and applying plaster of paris putty of 2 mm thickness over plasteredsurface to prepare the surface even and smooth complete.

    Detail of cost for 10 sqm

    MATERIAL

    Plaster of paris 10x0.002x1121 =

    22.42kg

    Add 2% wastage= 0.45kg

    Total = 22.87kg. Say23kg

    0869 Plaster of Paris kilogram 23.00 5.00 115.00

    9977 Carriage of plaster of paris L.S. 3.90 2.00 7.80

    LABOUR

    0122 Mason (for plaster of paris work)

    1st class day 0.91 738.00 671.58

    0114 Beldar day 0.91 558.00 507.78

    9999 Scaffolding and sundries L.S. 83.98 2.00 167.96

    TOTAL 1470.12 W

    Add 1 % Water charges on "W" 14.70

    TOTAL 1484.82 X

    Add GST on "X" (multiplying

    factor 0.1405) 208.62

    TOTAL 1693.44 Y

    Add 15% CPOH on "Y" 254.02

    TOTAL 1947.45 Z

    Add Cess @ 1% on "Z" 19.47

    Cost of 10.00 sqm 1966.93

    Cost of 1.00 sqm 196.69

    Say 196.70

    Code Description Unit Quantity Rate Amount

  • 920SUB HEAD : 13- FINISHING

    13.27 Extra for lining out plaster to imitate stone or concrete blocks walling.

    Detail of cost for 10 sqm

    LABOUR

    0155 Mason (average) day 0.50 709.00 354.50

    0114 Beldar day 0.50 558.00 279.00

    9999 Solution of lime putty L.S. 1.82 2.00 3.64

    TOTAL 637.14 W

    Add 1 % Water charges on "W" 6.37

    TOTAL 643.51 X

    Add GST on "X" (multiplying

    factor 0.1405) 90.41

    TOTAL 733.92 Y

    Add 15% CPOH on "Y" 110.09

    TOTAL 844.01 Z

    Add Cess @ 1% on "Z" 8.44

    Cost of 10.00 sqm 852.45

    Cost of 1.00 sqm 85.25

    Say 85.25

    Code Description Unit Quantity Rate Amount

    13.28 12 mm thick plain cement mortar bands in cement mortar 1:4 (1 cement : 4 finesand):

    13.28.1 Flush Band

    Detail of cost for 10 metre long and

    10 cm wide band

    MATERIAL

    Cement mortar 1 : 4 (1 cement :

    4 fine sand)

    3.4 Rate as per Item Number 3.4 of

    SH: Mortars cum 0.014 3528.85 49.40

    LABOUR

    0155 Mason (average) day 0.27 709.00 191.43

    0115 Coolie day 0.27 558.00 150.66

    0101 Bhisti day 0.05 617.00 30.85

    9999 Sundries L.S. 1.43 2.00 2.86

    TOTAL 425.20 W

    Add 1 % Water charges on "W" 4.25

    TOTAL 429.46 X

    Add GST on "X" (multiplying

    factor 0.1405) 60.34

    TOTAL 489.79 Y

    Add 15% CPOH on "Y" 73.47

    TOTAL 563.26 Z

    Add Cess @ 1% on "Z" 5.63

    Cost of 10.00 metre long and 10 cm

    wide band 568.90

    Cost of 1.00 metre long and 1 cm

    wide band 5.69

    Say 5.70

    Code Description Unit Quantity Rate Amount

  • 921SUB HEAD : 13- FINISHING

    13.28.2 Sunk Band

    Detail of cost for 10 metre long and

    10 cm wide band

    MATERIAL

    Cement mortar 1 : 4 (1 cement :

    4 fine sand)

    3.4 Rate as per Item Number 3.4 of

    SH: Mortars cum 0.014 3528.85 49.40

    LABOUR

    0155 Mason (average) day 0.30 709.00 212.70

    0115 Coolie day 0.30 558.00 167.40

    0101 Bhisti day 0.05 617.00 30.85

    9999 Sundries L.S. 2.08 2.00 4.16

    TOTAL 464.51 W

    Add 1 % Water charges on "W" 4.65

    TOTAL 469.16 X

    Add GST on "X" (multiplying

    factor 0.1405) 65.92

    TOTAL 535.08 Y

    Add 15% CPOH on "Y" 80.26

    TOTAL 615.34 Z

    Add Cess @ 1% on "Z" 6.15

    Cost of 10.00 metre long and

    10 cm wide band 621.49

    Cost of 1.00 metre long and

    1 cm wide band 6.21

    Say 6.20

    Code Description Unit Quantity Rate Amount

    13.28.3 Raised Band

    Detail of cost for 10 metre long and

    10 cm wide band

    MATERIAL

    Cement mortar 1 : 4 (1 cement :

    4 fine sand)

    3.4 Rate as per Item Number 3.4 of

    SH: Mortars cum 0.014 3528.85 49.40

    LABOUR

    0155 Mason (average) day 0.35 709.00 248.15

    0115 Coolie day 0.35 558.00 195.30

    0101 Bhisti day 0.05 617.00 30.85

    Code Description Unit Quantity Rate Amount

  • 922SUB HEAD : 13- FINISHING

    9999 Sundries L.S. 2.73 2.00 5.46

    TOTAL 529.16 W

    Add 1 % Water charges on "W" 5.29

    TOTAL 534.46 X

    Add GST on "X" (multiplying

    factor 0.1405) 75.09

    TOTAL 609.55 Y

    Add 15% CPOH on "Y" 91.43

    TOTAL 700.98 Z

    Add Cess @ 1% on "Z" 7.01

    Cost of 10.00 metre long and 10 cm

    wide band 707.99

    Cost of 1.00 metre long and 1 cm

    wide band 7.08

    Say 7.10

    Code Description Unit Quantity Rate Amount

    13.28.4 Moulded Band

    Detail of cost for 10 metre long and

    10 cm wide band

    MATERIAL

    Cement mortar 1 : 4 (1 cement :

    4 fine sand)

    3.4 Rate as per Item Number 3.4 ofSH: Mortars cum 0.014 3528.85 49.40

    LABOUR

    0155 Mason (average) day 0.65 709.00 460.85

    0115 Coolie day 0.65 558.00 362.70

    0101 Bhisti day 0.05 617.00 30.85

    9999 Sundries L.S. 1.56 2.00 3.12

    TOTAL 906.92 W

    Add 1 % Water charges on "W" 9.07

    TOTAL 915.99 X

    Add GST on "X" (multiplying

    factor 0.1405) 128.70

    TOTAL 1044.69 Y

    Add 15% CPOH on "Y" 156.70

    TOTAL 1201.39 Z

    Add Cess @ 1% on "Z" 12.01

    Cost of 10.00 metre long and 10 cm

    wide band 1213.41

    Cost of 1.00 metre long and 1 cm

    wide band 12.13

    Say 12.15

    Code Description Unit Quantity Rate Amount

  • 923SUB HEAD : 13- FINISHING

    13.29 18 mm thick plain cement mortar band in cement mortar 1:4 (1 cement :4 fine sand):

    13.29.1 Flush Band

    Detail of cost for 10 metre long and

    10 cm wide band

    MATERIAL

    Cement mortar 1 : 4 (1 cement :

    4 fine sand)

    3.4 Rate as per Item Number 3.4 of

    SH: Mortars cum 0.02 3528.85 70.58

    LABOUR

    0155 Mason (average) day 0.32 709.00 226.88

    0115 Coolie day 0.32 558.00 178.56

    0101 Bhisti day 0.06 617.00 37.02

    9999 Sundries L.S. 2.08 2.00 4.16

    TOTAL 517.20 W

    Add 1 % Water charges on "W" 5.17

    TOTAL 522.37 X

    Add GST on "X" (multiplying

    factor 0.1405) 73.39

    TOTAL 595.76 Y

    Add 15% CPOH on "Y" 89.36

    TOTAL 685.13 Z

    Add Cess @ 1% on "Z" 6.85

    Cost of 10.00 metre long and 10 cm

    wide band 691.98

    Cost of 1.00 metre long and 1 cm

    wide band 6.92

    Say 6.90

    Code Description Unit Quantity Rate Amount

    13.29.2 Sunk Band

    Detail of cost for 10 metre long and

    10 cm wide band

    MATERIAL

    Cement mortar 1 : 4 (1 cement :

    4 fine sand)

    3.4 Rate as per Item Number 3.4 of

    SH: Mortars cum 0.02 3528.85 70.58

    LABOUR

    0155 Mason (average) day 0.36 709.00 255.24

    0115 Coolie day 0.36 558.00 200.88

    0101 Bhisti day 0.06 617.00 37.02

    Code Description Unit Quantity Rate Amount

  • 924SUB HEAD : 13- FINISHING

    9999 Sundries L.S. 2.73 2.00 5.46

    TOTAL 569.18 W

    Add 1 % Water charges on "W" 5.69

    TOTAL 574.87 X

    Add GST on "X" (multiplying

    factor 0.1405) 80.77

    TOTAL 655.64 Y

    Add 15% CPOH on "Y" 98.35

    TOTAL 753.98 Z

    Add Cess @ 1% on "Z" 7.54

    Cost of 10.00 metre long and 10 cm

    wide band 761.52

    Cost of 1.00 metre long and 1 cm

    wide band 7.62

    Say 7.60

    Code Description Unit Quantity Rate Amount

    13.29.3 Raised Band

    Detail of cost for 10 metre long and

    10 cm wide band

    MATERIAL

    Cement mortar 1 : 4 (1 cement :

    4 fine sand)

    3.4 Rate as per Item Number 3.4 of

    SH: Mortars cum 0.02 3528.85 70.58

    LABOUR

    0155 Mason (average) day 0.42 709.00 297.78

    0115 Coolie day 0.42 558.00 234.36

    0101 Bhisti day 0.06 617.00 37.02

    9999 Sundries L.S. 4.42 2.00 8.84

    TOTAL 648.58 W

    Add 1 % Water charges on "W" 6.49

    TOTAL 655.06 X

    Add GST on "X" (multiplying

    factor 0.1405) 92.04

    TOTAL 747.10 Y

    Add 15% CPOH on "Y" 112.06

    TOTAL 859.16 Z

    Add Cess @ 1% on "Z" 8.59

    Cost of 10.00 metre long and 10 cm

    wide band 867.76

    Cost of 1.00 metre long and 1 cm

    wide band 8.68

    Say 8.70

    Code Description Unit Quantity Rate Amount

    13.29.3 Raised Band

    Detail of cost for 10 metre long and

    10 cm wide band

    Code Description Unit Quantity Rate Amount

  • 925SUB HEAD : 13- FINISHING

    13.29.4 Moulded Band

    Detail of cost for 10 metre long and

    10 cm wide band

    MATERIAL

    Cement mortar 1 : 5 (1 cement :

    5 coarse sand)

    3.10 Rate as per Item Number 3.4 of

    SH: Mortars cum 0.024 3658.10 87.79

    LABOUR

    0155 Mason (average) day 0.86 709.00 609.74

    0115 Coolie day 0.86 558.00 479.88

    0101 Bhisti day 0.05 617.00 30.85

    9999 Sundries L.S. 2.73 2.00 5.46

    TOTAL 1213.72 W

    Add 1 % Water charges on "W" 12.14

    TOTAL 1225.86 X

    Add GST on "X" (multiplying

    factor 0.1405) 172.23

    TOTAL 1398.10 Y

    Add 15% CPOH on "Y" 209.71

    TOTAL 1607.81 Z

    Add Cess @ 1% on "Z" 16.08

    Cost of 10.00 metre long and 10 cm

    wide band 1623.89

    Cost of 1.00 metre long and 1 cm

    wide band 16.24

    Say 16.25

    Code Description Unit Quantity Rate Amount

    MATERIAL

    Cement mortar 1 : 4 (1 cement :

    4 fine sand)

    3.4 Rate as per Item Number 3.4 of

    SH: Mortars cum 0.02 3528.85 70.58

    LABOUR

    0155 Mason (average) day 0.42 709.00 297.78

    0115 Coolie day 0.42 558.00 234.36

    0101 Bhisti day 0.06 617.00 37.02

    9999 Sundries L.S. 4.42 2.00 8.84

    TOTAL 648.58 W

    Add 1 % Water charges on "W" 6.49

    TOTAL 655.06 X

    Add GST on "X" (multiplying

    factor 0.1405) 92.04

    TOTAL 747.10 Y

    Add 15% CPOH on "Y" 112.06

    TOTAL 859.16 Z

    Add Cess @ 1% on "Z" 8.59

    Cost of 10.00 metre long and 10 cm

    wide band 867.76

    Cost of 1.00 metre long and 1 cm

    wide band 8.68

    Say 8.70

    Code Description Unit Quantity Rate Amount

  • 926SUB HEAD : 13- FINISHING

    13.30 18 mm thick moulded cement mortar band in two coats under layer 12 mm thickwith cement mortar 1:5 (1 cement : 5 coarse sand) top layer 6 mm thick withcement mortar 1:4 (1 cement : 4 fine sand).

    Detail of cost for 10 metre long and

    10 cm wide band

    MATERIAL

    Cement mortar 1 : 5 (1 cement :

    5 coarse sand)

    3.10 Rate as per Item Number 3.10 of

    SH: Mortars cum 0.014 3658.10 51.21

    Cement mortar 1 : 4 (1 cement :

    4 fine sand)

    3.4 Rate as per Item Number 3.4 of

    SH: Mortars cum 0.01 3528.85 35.29

    LABOUR

    0155 Mason (average) day 0.86 709.00 609.74

    0115 Coolie day 0.86 558.00 479.88

    0101 Bhisti day 0.05 617.00 30.85

    9999 Sundries L.S. 2.73 2.00 5.46

    TOTAL 1212.43 W

    Add 1 % Water charges on "W" 12.12

    TOTAL 1224.56 X

    Add GST on "X" (multiplying

    factor 0.1405) 172.05

    TOTAL 1396.61 Y

    Add 15% CPOH on "Y" 209.49

    TOTAL 1606.10 Z

    Add Cess @ 1% on "Z" 16.06

    Cost of 10.00 metre long and 10 cm

    wide band 1622.16

    Cost of 1.00 metre long and 1 cm

    wide band 16.22

    Say 16.20

    Code Description Unit Quantity Rate Amount

    13.31 Pointing on brick work or brick flooring with cement mortar 1:3 (1 cement : 3fine sand):

    13.31.1 Flush / Ruled/ Struck or weathered pointing

    Detail of cost for 10 sqm

    MATERIAL

    Cement mortar 1 : 3 (1 cement :

    3 fine sand)

    3.3 Rate as per Item Number 3.3 of

    SH: Mortars cum 0.03 4183.05 125.49

    LABOUR

    0155 Mason (average) day 0.50 709.00 354.50

    0115 Coolie day 0.60 558.00 334.80

    0101 Bhisti day 0.93 617.00 573.81

    9999 Sundries L.S. 7.15 2.00 14.30

    Code Description Unit Quantity Rate Amount

  • 927SUB HEAD : 13- FINISHING

    9999 Scaffolding and racking out joints

    including sundries L.S. 14.30 2.00 28.60

    TOTAL 1431.50 W

    Add 1 % Water charges on "W" 14.32

    TOTAL 1445.82 X

    Add GST on "X" (multiplying

    factor 0.1405) 203.14

    TOTAL 1648.95 Y

    Add 15% CPOH on "Y" 247.34

    TOTAL 1896.30 Z

    Add Cess @ 1% on "Z" 18.96

    Cost of 10.00 sqm 1915.26

    Cost of 1.00 sqm 191.53

    Say 191.55

    Code Description Unit Quantity Rate Amount

    13.31.2 Raised and cut pointing

    Detail of cost for 10 sqm

    MATERIAL

    Cement mortar 1 : 3 (1 cement :

    3 fine sand)

    3.3 Rate as per Item Number 3.3 of

    SH: Mortars cum 0.046 4183.05 192.42

    LABOUR

    0155 Mason (average) day 1.07 709.00 758.63

    0115 Coolie day 1.31 558.00 730.98

    0101 Bhisti day 1.00 617.00 617.00

    9999 Sundries L.S. 7.15 2.00 14.30

    9999 Scaffolding and racking out joints

    including sundries L.S. 16.12 2.00 32.24

    TOTAL 2345.57 W

    Add 1 % Water charges on "W" 23.46

    TOTAL 2369.03 X

    Add GST on "X" (multiplying

    factor 0.1405) 332.85

    TOTAL 2701.87 Y

    Add 15% CPOH on "Y" 405.28

    TOTAL 3107.16 Z

    Add Cess @ 1% on "Z" 31.07

    Cost of 10.00 sqm 3138.23

    Cost of 1.00 sqm 313.82

    Say 313.80

    Code Description Unit Quantity Rate Amount

    13.32 Pointing on tile brick work with cement mortar 1:3 (1 cement : 3 fine sand):13.32.1 Flush/ Ruled/ Struck or weathered pointing

    Detail of cost for 10 sqm

    MATERIAL

    Cement mortar 1 : 3 (1 cement :

    3 fine sand)

    Code Description Unit Quantity Rate Amount

  • 928SUB HEAD : 13- FINISHING

    3.3 Rate as per Item Number 3.3 of

    SH: Mortars cum 0.046 4183.05 192.42

    9999 Sundries L.S. 7.15 2.00 14.30

    LABOUR

    0155 Mason (average) day 0.67 709.00 475.03

    0115 Coolie day 0.80 558.00 446.40

    0101 Bhisti day 1.28 617.00 789.76

    9999 Scaffolding and racking out joints

    including sundries L.S. 16.12 2.00 32.24

    TOTAL 1950.15 W

    Add 1 % Water charges on "W" 19.50

    TOTAL 1969.65 X

    Add GST on "X" (multiplying

    factor 0.1405) 276.74

    TOTAL 2246.39 Y

    Add 15% CPOH on "Y" 336.96

    TOTAL 2583.35 Z

    Add Cess @ 1% on "Z" 25.83

    Cost of 10.00 sqm 2609.18

    Cost of 1.00 sqm 260.92

    Say 260.90

    Code Description Unit Quantity Rate Amount

    13.33 Pointing on stone work with cement mortar 1:3 (1 cement : 3 fine sand) :13.33.1 Flush/ Ruled pointing

    Detail of cost for 10 sqm

    MATERIAL

    Cement mortar 1 : 3 (1 cement :

    3 fine sand)

    3.3 Rate as per Item Number 3.3 of

    SH: Mortars cum 0.023 4183.05 96.21

    9999 Sundries L.S. 7.15 2.00 14.30

    LABOUR

    0155 Mason (average) day 0.92 709.00 652.28

    0115 Coolie day 1.37 558.00 764.46

    0101 Bhisti day 0.93 617.00 573.81

    9999 Scaffolding and racking out joints

    including sundries L.S. 16.12 2.00 32.24

    TOTAL 2133.30 W

    Add 1 % Water charges on "W" 21.33

    TOTAL 2154.63 X

    Add GST on "X" (multiplying

    factor 0.1405) 302.73

    TOTAL 2457.36 Y

    Add 15% CPOH on "Y" 368.60

    TOTAL 2825.96 Z

    Add Cess @ 1% on "Z" 28.26

    Cost of 10.00 sqm 2854.22

    Cost of 1.00 sqm 285.42

    Say 285.40

    Code Description Unit Quantity Rate Amount

  • 929SUB HEAD : 13- FINISHING

    13.33.2 Raised and cut pointing

    Detail of cost for 10 sqmMATERIALCement mortar 1 : 3 (1 cement :3 fine sand)

    3.3 Rate as per Item Number 3.3 ofSH: Mortars cum 0.038 4183.05 158.96

    9999 Sundries L.S. 7.15 2.00 14.30LABOUR

    0155 Mason (average) day 2.00 709.00 1418.000115 Coolie day 2.96 558.00 1651.680101 Bhisti day 1.00 617.00 617.009999 Scaffolding and racking out joints

    including sundries L.S. 16.12 2.00 32.24TOTAL 3892.18 WAdd 1 % Water charges on "W" 38.92TOTAL 3931.10 XAdd GST on "X" (multiplyingfactor 0.1405) 552.32TOTAL 4483.42 YAdd 15% CPOH on "Y" 672.51TOTAL 5155.93 ZAdd Cess @ 1% on "Z" 51.56Cost of 10.00 sqm 5207.49Cost of 1.00 sqm 520.75Say 520.75

    Code Description Unit Quantity Rate Amount

    13.34 Raised and cut pointing on stone work in white cement mortar 1:3 (1 whitecement : 3 marble dust).

    Detail of cost for 10 sqmMATERIALWhite Cement mortar 1:3 (1 whitecement : 3 marble dust)

    3.16 Rate as per Item Number 3.16 ofSH: Mortars cum 0.038 7621.75 289.63

    9999 Sundries L.S. 7.15 2.00 14.30LABOUR

    0155 Mason (average) day 2.00 709.00 1418.000115 Coolie day 2.96 558.00 1651.680101 Bhisti day 1.00 617.00 617.009999 Scaffolding and racking out joints

    including sundries L.S. 16.12 2.00 32.24TOTAL 4022.85 WAdd 1 % Water charges on "W" 40.23TOTAL 4063.07 XAdd GST on "X" (multiplyingfactor 0.1405) 570.86TOTAL 4633.94 YAdd 15% CPOH on "Y" 695.09TOTAL 5329.03 ZAdd Cess @ 1% on "Z" 53.29Cost of 10.00 sqm 5382.32Cost of 1.00 sqm 538.23Say 538.25

    Code Description Unit Quantity Rate Amount

  • 930SUB HEAD : 13- FINISHING

    13.35 Pointing on stone slab ceiling with cement mortar 1:2 (1 cement : 2 fine sand):13.35.1 Flush/ Ruled pointing

    Detail of cost for 10 sqm

    MATERIAL

    Cement mortar 1:2 (1 cement :

    2 fine sand)

    3.2 Rate as per Item Number 3.2 of

    SH: Mortars cum 0.015 4918.05 73.77

    LABOUR

    0155 Mason (average) day 0.47 709.00 333.23

    0115 Coolie day 0.69 558.00 385.02

    0101 Bhisti day 0.59 617.00 364.03

    9999 Scaffolding and racking out joints

    including

    sundries L.S. 16.12 2.00 32.24

    TOTAL 1188.29 W

    Add 1 % Water charges on "W" 11.88

    TOTAL 1200.17 X

    Add GST on "X" (multiplying

    factor 0.1405) 168.62

    TOTAL 1368.80 Y

    Add 15% CPOH on "Y" 205.32

    TOTAL 1574.12 Z

    Add Cess @ 1% on "Z" 15.74

    Cost of 10.00 sqm 1589.86

    Cost of 1.00 sqm 158.99

    Say 159.00

    Code Description Unit Quantity Rate Amount

    13.36 Extra for pointing on walls on the outside at height more than 10 m from groundlevel for every additional height of 3 m or part there of.

    Detail of cost for 10 sqm

    LABOUR

    9999 Scaffolding L.S. 13.39 2.00 26.78

    9999 Sundries L.S. 13.39 2.00 26.78

    TOTAL 53.56 W

    Add 1 % Water charges on "W" 0.54

    TOTAL 54.10 X

    Add GST on "X" (multiplying

    factor 0.1405) 7.60

    TOTAL 61.70 Y

    Add 15% CPOH on "Y" 9.25

    TOTAL 70.95 Z

    Add Cess @ 1% on "Z" 0.71

    Cost of 10.00 sqm 71.66

    Cost of 1.00 sqm 7.17

    Say 7.15

    Code Description Unit Quantity Rate Amount

  • 931SUB HEAD : 13- FINISHING

    13.37 White washing with lime to give an even shade :13.37.1 New work (three or more coats)

    Detail of cost for 10 sqm

    MATERIAL

    0775 Dehradun white lime quintal 0.03 600.00 18.00

    9977 Carriage of lime L.S. 0.91 2.00 1.82

    LABOUR

    0141 White Washer day 0.20 617.00 123.40

    0115 Coolie day 0.10 558.00 55.80

    9999 Indigo gum etc L.S. 4.42 2.00 8.84

    9999 Sundries ladders etc L.S. 2.73 2.00 5.46

    TOTAL 213.32 W

    Add 1 % Water charges on "W" 2.13

    TOTAL 215.45 X

    Add GST on "X" (multiplying

    factor 0.1405) 30.27

    TOTAL 245.72 Y

    Add 15% CPOH on "Y" 36.86

    TOTAL 282.58 Z

    Add Cess @ 1% on "Z" 2.83

    Cost of 10.00 sqm 285.41

    Cost of 1.00 sqm 28.54

    Say 28.55

    Code Description Unit Quantity Rate Amount

    13.38 Satna lime wash on walls with one coat.

    Detail of cost for 10 sqm

    MATERIAL

    0776 Satna lime quintal 0.01 370.00 3.70

    9977 Carriage of lime L.S. 2.08 2.00 4.16

    9999 Indigo gum etc L.S. 0.52 2.00 1.04

    LABOUR

    0141 White Washer day 0.08 617.00 49.36

    0115 Coolie day 0.04 558.00 22.32

    9999 Sundries ladders etc L.S. 2.73 2.00 5.46

    TOTAL 86.04 W

    Add 1 % Water charges on "W" 0.86

    TOTAL 86.90 X

    Add GST on "X" (multiplying

    factor 0.1405) 12.21

    TOTAL 99.11 Y

    Add 15% CPOH on "Y" 14.87

    TOTAL 113.98 Z

    Add Cess @ 1% on "Z" 1.14

    Cost of 10.00 sqm 115.12

    Cost of 1.00 sqm 11.51

    Say 11.50

    Code Description Unit Quantity Rate Amount

  • 932SUB HEAD : 13- FINISHING

    13.39 Colour washing such as green, blue or buff to give an even shade :13.39.1 New work (two or more coats) with a base coat of white washing with lime

    Detail of cost for 10 sqm

    MATERIAL

    0775 Dehradun white lime quintal 0.03 600.00 18.00

    9977 Carriage of lime L.S. 8.06 2.00 16.12

    9999 Add for colouring stuff L.S. 0.91 2.00 1.82

    LABOUR

    0141 White Washer day 0.30 617.00 185.10

    0115 Coolie day 0.10 558.00 55.80

    9999 Indigo gum etc L.S. 4.42 2.00 8.84

    9999 Sundries ladders etc L.S. 2.73 2.00 5.46

    TOTAL 291.14 W

    Add 1 % Water charges on "W" 2.91

    TOTAL 294.05 X

    Add GST on "X" (multiplying

    factor 0.1405) 41.31

    TOTAL 335.37 Y

    Add 15% CPOH on "Y" 50.30

    TOTAL 385.67 Z

    Add Cess @ 1% on "Z" 3.86

    Cost of 10.00 sqm 389.53

    Cost of 1.00 sqm 38.95

    Say 38.95

    Code Description Unit Quantity Rate Amount

    13.39.2 New work (two or more coats) with a base coat of whiting

    Detail of cost for 10 sqm

    MATERIAL

    0775 Dehradun white lime quintal 0.03 600.00 18.00

    9977 Carriage of lime L.S. 8.06 2.00 16.12

    9999 Add for colouring stuff L.S. 0.91 2.00 1.82

    LABOUR

    0141 White Washer day 0.30 617.00 185.10

    0115 Coolie day 0.10 558.00 55.80

    9999 Indigo gum etc L.S. 2.73 2.00 5.46

    9999 Sundries ladders etc L.S. 2.73 2.00 5.46

    TOTAL 287.76 W

    Add 1 % Water charges on "W" 2.88

    TOTAL 290.64 X

    Add GST on "X" (multiplying

    factor 0.1405) 40.83

    TOTAL 331.47 Y

    Add 15% CPOH on "Y" 49.72

    TOTAL 381.19 Z

    Add Cess @ 1% on "Z" 3.81

    Cost of 10.00 sqm 385.00

    Cost of 1.00 sqm 38.50

    Say 38.50

    Code Description Unit Quantity Rate Amount

  • 933SUB HEAD : 13- FINISHING

    13.40 Distempering with dry distemper of approved brand and manufacture (two ormore coats) of required shade on new work, over and including water thinnablepriming coat to give an even shade.

    Detail of cost for 10 sqm

    MATERIAL

    0808 Water thinnable cement primer for

    interior wall surface, having VOC

    content less than 50 gms/lit. litre 0.70 50.00 35.00

    9999 Putty, glue etc L.S. 2.73 2.00 5.46

    For distempering

    0815 Dry distemper kilogram 1.50 30.00 45.00

    9977 Carriage of material L.S. 1.56 2.00 3.12

    9999 Brushes, sand paper etc L.S. 7.15 2.00 14.30

    LABOUR

    0131 Painter day 0.80 679.00 543.20

    0115 Coolie day 0.40 558.00 223.20

    9999 Sundries L.S. 5.33 2.00 10.66

    TOTAL 879.94 W

    Add 1 % Water charges on "W" 8.80

    TOTAL 888.74 X

    Add GST on "X" (multiplying

    factor 0.1405) 124.87

    TOTAL 1013.61 Y

    Add 15% CPOH on "Y" 152.04

    TOTAL 1165.65 Z

    Add Cess @ 1% on "Z" 11.66

    Cost of 10.00 sqm 1177.30

    Cost of 1.00 sqm 117.73

    Say 117.75

    Code Description Unit Quantity Rate Amount

    13.41 Distempering with oil bound washable distemper of approved brand andmanufacture to give an even shade :

    13.41.1 New work (two or more coats) over and including water thinnable priming coatwith cement primer

    Detail of cost for 10 sqm

    MATERIAL

    0808 Water thinnable cement primer for

    interior wall surface, having VOC

    content less than 50 gms/lit. litre 0.70 50.00 35.00

    9999 Brushes, putty etc L.S. 7.15 2.00 14.30

    9988 Sundries including Carriage L.S. 8.06 2.00 16.12

    0816 Ist quality Acrylic distemper(Ready

    mix) having VOC content less than 50

    grams/ litre kilogram 1.50 50.00 75.00

    9977 Carriage of material L.S. 4.42 2.00 8.84

    9999 Brushes, sand paper and putty for filling

    holes L.S. 11.70 2.00 23.40

    LABOUR

    0131 Painter day 1.00 679.00 679.00

    0115 Coolie day 0.50 558.00 279.00

    Code Description Unit Quantity Rate Amount

  • 934SUB HEAD : 13- FINISHING

    9999 Sundries L.S. 8.06 2.00 16.12

    TOTAL 1146.78 W

    Add 1 % Water charges on "W" 11.47

    TOTAL 1158.25 X

    Add GST on "X" (multiplying

    factor 0.1405) 162.73

    TOTAL 1320.98 Y

    Add 15% CPOH on "Y" 198.15

    TOTAL 1519.13 Z

    Add Cess @ 1% on "Z" 15.19

    Cost of 10.00 sqm 1534.32

    Cost of 1.00 sqm 153.43

    Say 153.45

    Code Description Unit Quantity Rate Amount

    13.42 Distempering with 1st quality acrylic distemper (ready mixed) having VOCcontent less than 50 gms/litre, of approved manufacturer, of required shadeand colour complete, as per manufacturer's specification.

    13.42.1 Two or more coats on new work

    Detail of cost for 10 sqm

    MATERIAL

    0816 Oil bound washable distemper/ Acrylic

    distemper kilogram 1.50 50.00 75.00

    9977 Carriage of material L.S. 4.42 2.00 8.84

    9999 Brushes, sand paper and putty for

    filling holes L.S. 11.57 2.00 23.14

    LABOUR

    0131 Painter day 0.40 679.00 271.60

    0114 Beldar day 0.46 558.00 256.68

    9999 Sundries L.S. 8.06 2.00 16.12

    TOTAL 651.38 W

    Add 1 % Water charges on "W" 6.51

    TOTAL 657.89 X

    Add GST on "X" (multiplying

    factor 0.1405) 92.43

    TOTAL 750.33 Y

    Add 15% CPOH on "Y" 112.55

    TOTAL 862.88 Z

    Add Cess @ 1% on "Z" 8.63

    Cost of 10.00 sqm 871.51

    Cost of 1.00 sqm 87.15

    Say 87.15

    Code Description Unit Quantity Rate Amount

  • 935SUB HEAD : 13- FINISHING

    13.43 Applying one coat of water thinnable cement primer of approved brand andmanufacture on wall surface :

    13.43.1 Water thinnable cement primer

    Detail of cost for 10 sqm

    MATERIAL

    0808 Water thinnable cement primer for

    interior wall surface, having VOC

    content less than 50 gms/lit. litre 0.70 50.00 35.00

    9999 Brushes, putty etc L.S. 7.15 2.00 14.30

    LABOUR

    0131 Painter day 0.40 679.00 271.60

    0115 Coolie day 0.20 558.00 111.60

    9988 Sundries including carriage L.S. 8.06 2.00 16.12

    TOTAL 448.62 W

    Add 1 % Water charges on "W" 4.49

    TOTAL 453.11 X

    Add GST on "X" (multiplying

    factor 0.1405) 63.66

    TOTAL 516.77 Y

    Add 15% CPOH on "Y" 77.52

    TOTAL 594.28 Z

    Add Cess @ 1% on "Z" 5.94

    Cost of 10.00 sqm 600.23

    Cost of 1.00 sqm 60.02

    Say 60.00

    Code Description Unit Quantity Rate Amount

    13.44 Finishing walls with water proofing cement paint of required shade :13.44.1 New work (Two or more coats applied @ 3.84 kg/10 sqm)

    Detail of cost for 10 sqm

    MATERIAL

    0851 Water proofing cement paint kilogram 3.84 38.00 145.92

    9977 Carriage of material L.S. 1.56 2.00 3.12

    LABOUR

    0131 Painter day 0.46 679.00 312.34

    0115 Coolie day 0.23 558.00 128.34

    0101 Bhisti day 0.10 617.00 61.70

    9999 Brushes, sand paper etc L.S. 7.15 2.00 14.30

    9999 Sundries L.S. 8.06 2.00 16.12

    TOTAL 681.84 W

    Add 1 % Water charges on "W" 6.82

    TOTAL 688.66 X

    Add GST on "X" (multiplying

    factor 0.1405) 96.76

    TOTAL 785.41 Y

    Add 15% CPOH on "Y" 117.81

    TOTAL 903.23 Z

    Add Cess @ 1% on "Z" 9.03

    Cost of 10.00 sqm 912.26

    Cost of 1.00 sqm 91.23

    Say 91.25

    Code Description Unit Quantity Rate Amount

  • 936SUB HEAD : 13- FINISHING

    13.45 Finishing walls with textured exterior paint of required shade :13.45.1 New work (Two or more coats applied @ 3.28 ltr/10 sqm) over and including

    priming coat of exterior primer applied @ 2.20kg/10 sqm

    Detail of cost for 10 sqmMATERIAL

    8507 Textured exterior paint litre 3.28 240.00 787.200809 Exterior primer kilogram 2.20 140.00 308.009977 Carriage of material L.S. 1.56 2.00 3.12

    LABOUR0131 Painter day 0.60 679.00 407.400115 Coolie day 0.30 558.00 167.400101 Bhisti day 0.05 617.00 30.859999 Brushes, sand paper etc L.S. 7.02 2.00 14.049999 Sundries L.S. 8.06 2.00 16.12

    TOTAL 1734.13 WAdd 1 % Water charges on "W" 17.34TOTAL 1751.47 XAdd GST on "X" (multiplyingfactor 0.1405) 246.08TOTAL 1997.55 YAdd 15% CPOH on "Y" 299.63TOTAL 2297.19 ZAdd Cess @ 1% on "Z" 22.97Cost of 10.00 sqm 2320.16Cost of 1.00 sqm 232.02Say 232.00

    Code Description Unit Quantity Rate Amount

    13.46 Finishing walls with Acrylic Smooth exterior paint of required shade :13.46.1 New work (Two or more coat applied @ 1.67 ltr/10 sqm over and including priming

    coat of exterior primer applied @ 2.20 kg/10 sqm)

    Detail of cost for 10 sqmMATERIAL

    8505 Acrylic exterior paint litre 1.67 170.00 283.900809 Exterior Primer Kg 2.20 140.00 308.009977 Carriage of material L.S. 1.56 2.00 3.12

    LABOUR0131 Painter day 0.60 679.00 407.400115 Coolie day 0.30 558.00 167.400101 Bhisti day 0.05 617.00 30.859999 Brushes, sand paper etc L.S. 7.15 2.00 14.309999 Sundries L.S. 8.06 2.00 16.12

    TOTAL 1231.09 WAdd 1 % Water charges on "W" 12.31TOTAL 1243.40 XAdd GST on "X" (multiplyingfactor 0.1405) 174.70TOTAL 1418.10 YAdd 15% CPOH on "Y" 212.71TOTAL 1630.81 ZAdd Cess @ 1% on "Z" 16.31Cost of 10.00 sqm 1647.12Cost of 1.00 sqm 164.71Say 164.70

    Code Description Unit Quantity Rate Amount

  • 937SUB HEAD : 13- FINISHING

    13.47 Finishing walls with Premium Acrylic Smooth exterior paint with Siliconeadditives of required shade:

    13.47.1 New work (Two or more coats applied @ 1.43 ltr/10 sqm over and includingpriming coat of exterior primer applied @ 2.20 kg/10 sqm)

    Detail of cost for 10 sqm

    MATERIAL

    8506 Premium Acrylic exterior paint litre 1.43 180.00 257.40

    0809 Exterior primer kilogram 2.20 140.00 308.00

    9977 Carriage of material L.S. 1.56 2.00 3.12

    LABOUR

    0131 Painter day 0.60 679.00 407.40

    0115 Coolie day 0.30 558.00 167.40

    0101 Bhisti day 0.05 617.00 30.85

    9999 Brushes, sand paper etc L.S. 7.15 2.00 14.30

    9999 Sundries L.S. 8.06 2.00 16.12

    TOTAL 1204.59 W

    Add 1 % Water charges on "W" 12.05

    TOTAL 1216.64 X

    Add GST on "X" (multiplying

    factor 0.1405) 170.94

    TOTAL 1387.57 Y

    Add 15% CPOH on "Y" 208.14

    TOTAL 1595.71 Z

    Add Cess @ 1% on "Z" 15.96

    Cost of 10.00 sqm 1611.67

    Cost of 1.00 sqm 161.17

    Say 161.15

    Code Description Unit Quantity Rate Amount

    13.48 Finishing with Deluxe Multi surface paint system for interiors and exteriors usingPrimer as per manufacturers specifications :

    13.48.1 Two or more coats applied on walls @ 1.25 ltr/10 sqm over and including onecoat of Special primer applied @ 0.75 ltr /10 sqm

    Detail of cost for 10 sqm

    MATERIAL

    8504 Multi surface paint litre 1.25 255.00 318.75

    8509 Special Primer (C.W.) litre 0.75 140.00 105.00

    9977 Carriage of material L.S. 1.56 2.00 3.12

    LABOUR

    0131 Painter day 0.60 679.00 407.40

    0115 Coolie day 0.30 558.00 167.40

    0101 Bhisti day 0.05 617.00 30.85

    9999 Brushes, sand paper etc L.S. 7.02 2.00 14.04

    Code Description Unit Quantity Rate Amount

  • 938SUB HEAD : 13- FINISHING

    Code Description Unit Quantity Rate Amount

    13.48.2 Painting wood work with Deluxe Multi Surface Paint of required shade. Two ormore coat applied @ 0.90 ltr/10 sqm over an under coat of primer applied @0.75ltr/10 sqm of approved brand and manufacture

    Detail of cost for 10 sqm

    MATERIAL

    8504 Multi surface paint litre 0.90 255.00 229.50

    8509 Special Primer (C.W.) litre 0.75 140.00 105.00

    9977 Carriage of material L.S. 1.56 2.00 3.12

    LABOUR

    0131 Painter day 0.60 679.00 407.40

    0115 Coolie day 0.30 558.00 167.40

    0101 Bhisti day 0.05 617.00 30.85

    9999 Brushes, sand paper etc L.S. 7.02 2.00 14.04

    9999 Sundries L.S. 8.06 2.00 16.12

    TOTAL 973.43 W

    Add 1 % Water charges on "W" 9.73

    TOTAL 983.16 X

    Add GST on "X" (multiplying

    factor 0.1405) 138.13

    TOTAL 1121.30 Y

    Add 15% CPOH on "Y" 168.19

    TOTAL 1289.49 Z

    Add Cess @ 1% on "Z" 12.89

    Cost of 10.00 sqm 1302.39

    Cost of 1.00 sqm 130.24

    Say 130.25

    Code Description Unit Quantity Rate Amount

    9999 Sundries L.S. 8.06 2.00 16.12

    TOTAL 1062.68 W

    Add 1 % Water charges on "W" 10.63

    TOTAL 1073.31 X

    Add GST on "X" (multiplying

    factor 0.1405) 150.80

    TOTAL 1224.11 Y

    Add 15% CPOH on "Y" 183.62

    TOTAL 1407.72 Z

    Add Cess @ 1% on "Z" 14.08

    Cost of 10.00 sqm 1421.80

    Cost of 1.00 sqm 142.18

    Say 142.20

  • 939SUB HEAD : 13- FINISHING

    13.48.3 Painting Steel work with Deluxe Multi Surface Paint to give an even shade. Twoor more coat applied @ 0.90 ltr/10 sqm over an under coat of primer applied @0.80 ltr/10 sqm of approved brand and manufacture

    Detail of cost for 10 sqm

    MATERIAL

    8504 Multi surface paint litre 0.90 255.00 229.50

    8510 Metal Primer (U.G.) litre 0.80 90.00 72.00

    9977 Carriage of material L.S. 1.56 2.00 3.12

    LABOUR

    0131 Painter day 0.60 679.00 407.40

    0115 Coolie day 0.30 558.00 167.40

    0101 Bhisti day 0.05 617.00 30.85

    9999 Brushes, sand paper etc L.S. 7.02 2.00 14.04

    9999 Sundries L.S. 8.06 2.00 16.12

    TOTAL 940.43 W

    Add 1 % Water charges on "W" 9.40

    TOTAL 949.83 X

    Add GST on "X" (multiplying

    factor 0.1405) 133.45

    TOTAL 1083.29 Y

    Add 15% CPOH on "Y" 162.49

    TOTAL 1245.78 Z

    Add Cess @ 1% on "Z" 12.46

    Cost of 10.00 sqm 1258.24

    Cost of 1.00 sqm 125.82

    Say 125.80

    Code Description Unit Quantity Rate Amount

    13.48A Finishing walls with 100% Premium acrylic emulsion paint having VOC lessthan 50 gm/litre and UV resistance as per IS 15489:2004, Alkali & fungalresistance, dirt resistance exterior paint of required shade (Company DepotTinted) with silicon additives.

    13.48A.1 New work (Two or more coats applied @ 1.43 litre/ 10 sqm. Over and includingpriming coat of exterior primer applied @ 0.90 litre/10 sqm.

    Details of cost for 10 sqm (Based on

    item no 13.47)

    Material

    0836 100% Premium acrylic dirt resistance,

    Silicone additives exterior paint litre 1.43 270.00 386.10

    0837 Acrylic Exterior Primer litre 0.90 100.00 90.00

    9977 Carriage of material L.S. 1.56 2.00 3.12

    Labour

    0131 Painter day 0.45 679.00 305.55

    0101 Bhisti day 0.45 617.00 277.65

    9999 Brushes, sand paper etc. L.S. 7.15 2.00 14.30

    Code Description Unit Quantity Rate Amount

  • 940SUB HEAD : 13- FINISHING

    9999 Sundries L.S. 8.06 2.00 16.12

    Total 1092.84 W

    Add 1 % Water charges on "W" 10.93

    TOTAL 1103.77 X

    Add GST on "X" (multiplying

    factor 0.1405) 155.08

    TOTAL 1258.85 Y

    Add 15% CPOH on "Y" 188.83

    TOTAL 1447.68 Z

    Add Cess @ 1% on "Z" 14.48

    Cost of 10 sqm 1462.15

    Cost of 1 sqm 146.22

    Say 146.20

    Code Description Unit Quantity Rate Amount

    13.50 Applying priming coat:13.50.1 With ready mixed pink or Grey primer of approved brand and manufacture on

    wood work (hard and soft wood)

    Detail of cost for 10 sqm

    MATERIAL

    0823 Pink primer (for wood) litre 0.75 105.00 78.75

    9999 Putty L.S. 2.73 2.00 5.46

    9977 Carriage L.S. 0.39 2.00 0.78

    LABOUR

    0131 Painter day 0.25 679.00 169.750115 Coolie day 0.25 558.00 139.50

    9999 Brushes, sand paper etc L.S. 5.33 2.00 10.66

    9999 Sundries L.S. 10.79 2.00 21.58

    TOTAL 426.48 W

    Add 1 % Water charges on "W" 4.26

    TOTAL 430.74 X

    Add GST on "X" (multiplying

    factor 0.1405) 60.52

    TOTAL 491.26 Y

    Add 15% CPOH on "Y" 73.69

    TOTAL 564.95 Z

    Add Cess @ 1% on "Z" 5.65

    Cost of 10.00 sqm 570.60

    Cost of 1.00 sqm 57.06

    Say 57.05

    Code Description Unit Quantity Rate Amount

    13.50.2 With ready mixed aluminium primer of approved brand and manufacture onresinous wood and plywood

    Detail of cost for 10 sqm

    MATERIAL

    4201 Aluminium primer litre 0.75 110.00 82.50

    9999 Putty L.S. 2.73 2.00 5.46

    9977 Carriage L.S. 0.39 2.00 0.78

    Code Description Unit Quantity Rate Amount

  • 941SUB HEAD : 13- FINISHING

    LABOUR

    0131 Painter day 0.25 679.00 169.75

    0115 Coolie day 0.25 558.00 139.50

    9999 Brushes, sand paper etc L.S. 5.33 2.00 10.66

    9999 Sundries L.S. 10.79 2.00 21.58

    TOTAL 430.23 W

    Add 1 % Water charges on "W" 4.30

    TOTAL 434.53 X

    Add GST on "X" (multiplying

    factor 0.1405) 61.05

    TOTAL 495.58 Y

    Add 15% CPOH on "Y" 74.34

    TOTAL 569.92 Z

    Add Cess @ 1% on "Z" 5.70

    Cost of 10.00 sqm 575.62

    Cost of 1.00 sqm 57.56

    Say 57.55

    Code Description Unit Quantity Rate Amount

    13.50.3 With ready mixed red oxide zinc chromate primer of approved brand andmanufacture on steel galvanised iron/ steel works

    Detail of cost for 10 sqm

    MATERIAL

    4202 Red oxide Zinc chromate primer litre 0.54 110.00 59.40

    9977 Carriage L.S. 0.52 2.00 1.04

    LABOUR

    0131 Painter day 0.24 679.00 162.96

    0115 Coolie day 0.24 558.00 133.92

    9999 Brushes,sand paper including sundries L.S. 10.79 2.00 21.58

    TOTAL 378.90 W

    Add 1 % Water charges on "W" 3.79

    TOTAL 382.69 X

    Add GST on "X" (multiplying

    factor 0.1405) 53.77

    TOTAL 436.46 Y

    Add 15% CPOH on "Y" 65.47

    TOTAL 501.93 Z

    Add Cess @ 1% on "Z" 5.02

    Cost of 10.00 sqm 506.94

    Cost of 1.00 sqm 50.69

    Say 50.70

    Code Description Unit Quantity Rate Amount

    13.50.4 With ready mixed red oxide zinc chromate primer of approved brand andmanufacture on steel work (second coat)

    Detail of cost for 10 sqm

    MATERIAL

    4202 Red oxide Zinc chromate primer litre 0.36 110.00 39.60

    9977 Carriage L.S. 0.39 2.00 0.78

    Code Description Unit Quantity Rate Amount

  • 942SUB HEAD : 13- FINISHING

    LABOUR

    0131 Painter day 0.12 679.00 81.48

    0115 Coolie day 0.12 558.00 66.96

    9999 Brushes,sand paper including L.S. 7.15 2.00 14.30

    TOTAL 203.12 W

    Add 1 % Water charges on "W" 2.03

    TOTAL 205.15 X

    Add GST on "X" (multiplying

    factor 0.1405) 28.82

    TOTAL 233.97 Y

    Add 15% CPOH on "Y" 35.10

    TOTAL 269.07 Z

    Add Cess @ 1% on "Z" 2.69

    Cost of 10.00 sqm 271.76

    Cost of 1.00 sqm 27.18

    Say 27.20

    Code Description Unit Quantity Rate Amount

    13.51 Painting with silicon & acrylic emulsion based water thinnable sealer of approvedbrand and manufacture on wet or patchy portion of plastered surfaces :

    13.51.1 One coat

    Detail of cost for 10 sqm

    MATERIAL

    0801 Silicon and acrylic emulsion litre 1.80 130.00 234.00

    9977 Carriage of material L.S. 0.52 2.00 1.04

    9999 Putty etc L.S. 2.73 2.00 5.46

    LABOUR

    0131 Painter day 0.27 679.00 183.33

    0115 Coolie day 0.27 558.00 150.66

    9999 Brushes, sand paper etc L.S. 5.33 2.00 10.66

    9999 Sundries L.S. 10.79 2.00 21.58

    TOTAL 606.73 W

    Add 1 % Water charges on "W" 6.07

    TOTAL 612.80 X

    Add GST on "X" (multiplying

    factor 0.1405) 86.10

    TOTAL 698.90 Y

    Add 15% CPOH on "Y" 104.83

    TOTAL 803.73 Z

    Add Cess @ 1% on "Z" 8.04

    Cost of 10.00 sqm 811.77

    Cost of 1.00 sqm 81.18

    Say 81.20

    Code Description Unit Quantity Rate Amount

  • 943SUB HEAD : 13- FINISHING

    13.51.2 Two coats

    Detail of cost for 10 sqm

    MA