1 SMS – Spares Management Software Overview and Case Studies.
-
Upload
charlie-atwell -
Category
Documents
-
view
213 -
download
0
Transcript of 1 SMS – Spares Management Software Overview and Case Studies.
1
SMS – Spares Management SMS – Spares Management SoftwareSoftware
Overview and Case StudiesOverview and Case Studies
2
Interval StockReliability
Spares Management Software (SMS)Spares Management Software (SMS)
Optimal
Spares
Requirement
Optimization criteria
Instant. StockReliability
Availability
CostMinimization
Supportability
Stock
Remaining
Life
Non-Repairable Non-Repairable SparesSpares
Repairable Repairable SparesSpares
3
Repairable Spares# items in service
Repairshop
repaired units
stock
time
Failures
failed units
4
Criteria for Decision Making
1.Instant reliability
2.Interval reliability
3.Cost minimization
4.(Process) Availability
5
Scenario
• Plant has 62 electric motors on their conveyor systems (Mining company)
• MTBReplacements of motors is 3000 days (8 years)
• Planning horizon is 1825 days (5 years)
• Cost of spare motor is 15,000 $
• Value of unused spare is 10,000 $
• Cost of emergency spare is 75,000 $
• MTTRepair a motor is 80 days
• Cost of plant downtime for a single motor is 1000 $ per day
• Holding cost of a spare is 4.11 $ per day (10% of value of part/annum)
QUESTION: HOW MANY SPARE PARTS TO STOCK?
6
Results: Repairable Parts
Electric motors
• Interval reliability: 95% reliability requires 7 spares
• Instant reliability: 95% reliability requires 4 spares
• Cost minimization: requires 6 spares. Associated plant availability is 100.00%
• Availability of 95%: requires 0 spares. Associated electric motor availability is 97.4% [Note: If availability of 99% was required (rather than the specified 95%) then spares required would be 2]
7
Reference Case
Population 100 transformers
Failure Rate 0.005 failures/transformer/yr
Repair Time 1 yr
Replacement Time
0.001yr
Interval 1 yr
8
Repairable Instantaneous Reliability
Vary Spares
0.9
0.91
0.92
0.93
0.94
0.95
0.96
0.97
0.98
0.99
1
1 2 3 4 5
Spares
Rel
iab
ility
9
Case studies:
1. Fume fan shaft, blast furnace in a steel operation: non-repairable part, decision support
2. Power train component, haul trucks: repairable parts, multiple criteria
3. Frigate control system: supportability interval
Additional CasesAdditional Cases
10
1. Fume fan shaft – steel mill1. Fume fan shaft – steel mill
Spares provisioning optimization project
• Part: fume fan shaft used in a Blast Furnace• Decision: should there be 0 or 1 spares?• Complication:
• Part has long lifespan (25-40 years).• Long lead time (22 weeks).• If part fails, results are catastrophic (loss of almost $6
million per week).• Inventories are trying to be minimized.
SMS was used to quantify the risk involved in not having a spare
Decision supportDecision support
11
How many spares – Fume fan shaft?How many spares – Fume fan shaft?
MTBF Vs Reliability with 22 week LT
97
97.5
98
98.5
99
99.5
100
100.5
0 5 10 15 20 25 30 35 40 45
Mean time between failures
Rel
iabi
lity 0 spares
1 spare
2 spares
12
2. Repairable components – haul 2. Repairable components – haul truckstrucks
Open pit mining operation in South America
Haul truck power train component: COMPONENT X
13
6,600 operating hours per truck per year (average fleet utilization)
Preventive replacement policy at 9,000 operating hours in place
Repairable components - Data / 1Repairable components - Data / 1
GeneralGeneral
Two parameter Weibull distribution, fitted using Weibull++
• 171 events: 86 failures, 85 suspensions (preventive replacements)
• Beta = 0.8565
• Eta = 14,650 operating hours
• Mean time to replacement = 6,420.3 operating hours
Time to replacementTime to replacement
14
Based on estimations provided by maintenance personnel
Estimated at MTTR = 452 operating hours
Repairable components - Data / 2Repairable components - Data / 2
Time to repairTime to repair
Downtime: estimated using operational indicators (value of lost production, $2,173.3 / op. hour)
Holding: 25% of the value of the part per annum ($1.51/ op. hour)
Cost of downtime and holding costsCost of downtime and holding costs
15
Repairable components - Data SummaryRepairable components - Data Summary
SMS can perform the optimization based on four criteriaSMS can perform the optimization based on four criteria
Parameter Value
Number of components in operation 78
MTBReplacements (μ) 6420.3 (op. hours)
Planning horizon (T) 6600 (op. hours)
MTTRepair (μR) 452 (op. hours)
Holding cost for one spare $1.51 per op. hour (25% of value of part/annum)
Cost of plant downtime for a single component
$2173.3 per op. hour
16
Repairable components - ResultsRepairable components - Results
Case & Optimization criteria Optimal Stock level
Associated Values
Interval Reliability(goal = 95%)
15 Reliability = 98.05%(for stock=14, Rel.=94.99%)
Instantaneous Reliability(goal = 95%)
10 Reliability = 97.53%(for stock=9, Rel.=94.75%)
Availability(goal = 99%)
6 Availability = 99.14 %
Cost minimization 14 Total cost per unit time = $23
Inst. Reliability = 99.94%
17
4. Frigate control system – supportability 4. Frigate control system – supportability intervals (S.I.)intervals (S.I.)
Determination of supportability intervals
• Several electronic components – control system• Parts no longer available - discontinued• Decision: how long can we support the operation of
the system using only the current stock? (achieving the desired reliability of the stock)
18
Case Study – Supportability Interval Case Study – Supportability Interval (S.I.)(S.I.)
Summary of Data
Part # Parts in Operation
(complete fleet)
Rate of Replacements yearpart
tsreplacemen
Stock Level
V 12 0.0556 6 W 12 0.4259 8 X 12 0.3241 16 Y 12 0.3796 19 Z 36 0.0432 11
Supportability interval (RUL of current stock) can be rapidly calculated using SMS – NEWLY ADDED FEATURE
19
Case Study (S.I.) / 2Case Study (S.I.) / 2
Results
Supportability for the system is influenced by the (shortest) supportability for any of its critical parts
Supportability Interval T* (years) Part Stock Level Reliability=90% Reliability=95% Reliability=99%
V 6 5.84 4.92 3.49 W 8 1.06 0.92 0.69 X 16 3.08 2.79 2.28 Y 19 3.19 2.91 2.43 Z 11 5.03 4.45 3.49
20
Case Study (S.I.) / 3Case Study (S.I.) / 3
Informed decisions for:
• Adequate timing for replacement of current system
• Placement of final orders for discontinued parts
• Maximum supportability interval for current stock – procurement planning
21
Thank youThank you