1 Session 8 Master Production Scheduling (MPS) – Managing the MPS lecture session 7 .

19
1 Session 8 Master Production Scheduling (MPS) – Managing the MPS http:// www.pom.edu/mpc/lectures_in_manufacturing_planning.htm lecture session 7 • Example Company MPS Records • Handling MPS Lead Time • Incorporating Capacity Constraints • MPS Stability • Managing the MPS • Master Production Scheduler’s Job • Concluding Principles

Transcript of 1 Session 8 Master Production Scheduling (MPS) – Managing the MPS lecture session 7 .

1

Session 8Master Production Scheduling (MPS) –

Managing the MPShttp://www.pom.edu/mpc/lectures_in_manufacturing_planning.htm

lecture session 7

• Example Company MPS Records• Handling MPS Lead Time• Incorporating Capacity Constraints• MPS Stability• Managing the MPS• Master Production Scheduler’s Job • Concluding Principles

2

Jet Spray Corporation Master Planning Schedule

3

Handling MPS Lead Time

The Spencer Optics Company produces an inexpensive line of sunglasses. The manufacturing process consists of assembling two plastic lenses (produced by the firm's plastic molding department) into a finished frame (purchased from an outside supplier).

The firm's sales manager has prepared a 10-period sales forecast for one of the more popular sunglasses (the Classic model). The forecast is 100 orders per period. Spencer has customer orders of 110 units, 80 units. 50 units, and 20 units in periods l , 2, 3, and 4, respectively. The sunglasses are assembled in batches of 300. Presently, three such batches are scheduled: one in period 2, one in period 5, and one in period 8.

4

Spencer Optics (Continued)

a. Complete the time-phased record.

Period 1 2 3 4 5 6 7 8 9 10Forecast 100 100 100 100 100 100 100 100 100 100Orders 110 80 50 20Available 30 230 130 30 230 130 30 230 130 30Available to Promise 30 150 300 300MPS (Completion) 300 300 300On-hand = 140, MPS lot size = 300

a. Classic Model

5

Spencer Optics (Continued)

b. Prepare the MRP record for the assembly of the sunglasses. The final assembly quantity is 300, lead time is 2 periods, and there’s a scheduled receipt in period 2. Note that no inventory is shown for the assembled sunglasses in this record, since it’s accounted for in the MPS record.

1 2 3 4 5 6 7 8 9 10300 300 300300

Projected available balance 0 0 0 0 0 0 0 0 0 0 0300 300

b. Final Assembly - Classic Model

Q = 300; LT = 2; SS = 0

Period

Scheduled receipts

Planned order release

Gross requirements

6

Incorporating Capacity Constraints

End Product Beginning Inventory Period Forecast Lot size Hours per lot size

A 60 10 30 30B 20 5 20 20C 30 15 50 50

a. Prepare the master production schedule for these items during the next four periods using the Ethan Allen master production scheduling method.

7

Incorporating Capacity Constraintsa. Capacity=

Hours Period 1 Period 2 Period 3 Period 44035302520151050

C

B

AC

C

C

B

Produce Period 1 Period 2 Period 3 Period 4A 60/10 = 6 50 / 10 = 5 30 / 10 = 3B 20/5 = 4 15 / 5 = 3* 25 / 5 = 5*C 30 / 15 = 2* 55 / 15 = 3.7 85 / 15 = 5.67

8

Incorporating Capacity Constraints (Continued)

b. Should the plant increase or decrease the capacity of the final assembly line?

The plant should decrease capacity by 10 hours/period because the total units forecast each period totals 30 units (10 + 5 + 15) and the time to produce each unit is 1 hour. Therefore, 30 hours of capacity are required each period versus 40 units of available capacity.

9

Incorporating Capacity Constraints (Continued)

c. Suppose that the master production schedule is frozen for the next three periods. What specific impact would the policy have on the firm's performance?

Freezing the MPS for the next three periods would not allow the plant to adjust to any radical changes in demand but it would stabilize plant operations.

10

MPS Stability

• Freezing the MPS

• Time Fencing– Demand Fence– Planning Fence

11

Ethan Allen FirmPlanned Order Approach

Period

Production

Hours

12

Managing the MPS

• Overstated MPS

• MPS Performance Measures

• Monitoring the MPS

13

MPS Performance Measures

14

Mitel’s Master Production Scheduler Job Description

A. Identifying InformationJob Title: Master SchedulerDepartment/Unit: Planning & AdministrationJob Location: Kanata, Ontario

B. Job Purpose and MandateThe incumbent of this position is responsible for the day to day management of the Master Production Schedule, as it relates to actioning unplanned forecast demand, forecast shortfalls, production and inventory changes, allowing accurate and up-to-date information which in turn drives material and capacity requirements and customer order dating. An advanced level of material planning and manufacturing process knowledge is required.

C. Organization StructureThe Master Production Scheduler reports to the Manager, Planning who reports to the Director, Planning and Administration.

15

Mitel’s Master Production Scheduler Job Description

D. Job Description1. Specific Activities and Accountabilities:

- Responsible for the creation and continuous update of the master schedule that satisfies customer demand, maintains stability in terms of material and capacity requirements and minimizes RAW. WIP, and Finished Goods inventory levels by:• Managing day to day increases/decreases to the schedule through

interface with Materials, Manufacturing and Order Administration.

• Working with Materials to ensure smooth E.C.O. transition into factory

• Continuously monitor the impact of ''Performance to Forecast'' on inventory levels for the current month, and implement any necessary changes to the schedule; i.e. cut rollover, Increase availability through Fast-Man MRP tool.

- Act as a focal point between N.A. Order Administration, Manufacturing and Distribution to ensure configured system orders are:• Scheduled to meet customer cut-over requirements• Scheduled to meet manufacturing cell capacity.• Quoted and reviewed with manufacturing, initiating build and test.• Free of any discrepancies, with Order Administration notified to

correct any problems.

16

Mitel’s Master Production Scheduler Job Description

- Continuously monitor problem inventory, taking advantage of any conversion opportunities, making recommendations for scrapping, or potential ''Fire Sale's".

- Assess the impact to capacity, inventory levels, purchase order activity and problem inventory levels that result from any proposed major change to the master schedule, utilizing the Fast-Man MRP tool.

2. Supervisory Responsibilities: Direct ( ) Indirect ( )

3. Key relationships (internal and external)• Internal and external auditors• Marketing• Order Administration• Distribution• A1l levels of management within Mitel• Traffic• Manufacturing• Materials Planning• Product Management

17

Mitel’s Master Production Scheduler Job Description

E. Job requirements• superior product knowledge• 3-4 years progressive experience in materials or production control• knowledge of internal Mitel processes and procedures• APIC's Certification a definite asset• knowledge gained through APIC's Certification• organizational and planning skills• secondary education• high degree of initiative and personal motivation• personal computer skills• broad based knowledge of supply/demand process

18

MPS – Concluding Principles

• The MPS unit should reflect the company's approach to the business environment in which it operates.

• The MPS is one part of an MPC system-the other parts need to be in place as well for a fully effective MPS activity.

• Time-phased MPS records should incorporate useful features of standard MRP record processing.

• Customer order promising activities must be closely coupled to the MPS.

• Available-to-promise information should be provided to both the master scheduler and the sales department.

19

MPS – Concluding Principles• A final assembly schedule (FAS) should be used to

convert an anticipated build schedule (MPS) into an actual build schedule.

• The master production scheduler must keep the sum of the parts (MPS) equal to the whole (production plan).

• The MPS activity must be clearly defined organizationally.

• Stability must be designed into the MPS and managed.

• The MPS should be evaluated with a formal performance measurement system.

• The MPS can be usefully considered as a set of firm planned orders.