Scheduling and Budgeting for Survey-Related Activities
Kathleen BeegleJuan MuñozModule 1: Multi-Purpose Household SurveysJanuary 2008
Margaret E. Grosh and Juan Munoz. 1996 "A Manual for Planning and Implementing the LSMS Survey." World Bank Living Standards Measurement Study, Working Paper No. 126.
2
Building the in-country work program
Juan Muñoz
3
Activity groups(See page 200)
• 1 Management and logistics• 2 Questionnaire development• 3 Sampling• 4 Staffing and training• 5 Data management• 6 Field work• 7 Data analysis and documentation
4
Activity groups 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
1 Management and logistics2 Questionnaire development3 Sampling4 Staffing and training5 Data management6 Field work7 Data analysis and documentation
Design
Data collection
Analysis
5
1 Management and logistics
1 Management and logistics 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
1.01 Agreements and institutional environment1.02 Appoint core staff1.03 Core staff logistics1.04 Acquire anthropometric equipment1.05 Acquire computers1.06 Acquire survey materials1.07 Mobility startegy and vehicle acquisition1.08 Publicity and hh motivation strategy
6
2 Questionnaire development
2 Questionnaire development 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
2.01 Identify policy-relevant issues2.02 Prepare draft of household questionnaire2.03 Distribute draft of household questionnaire2.04 Seminar2.05 Finalize the draft and plan the field test2.06 Field test2.07 Review field test2.08 Print household questionnaire2.09 Prepare community/price questionnaires
7
3 Sampling
3 Sampling 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
3.01 Sample design3.02 Develop the sample frame3.03 Select Primary Sampling Units (PSUs)3.04 Plan the field assignments3.05 Dwelling listing and cartographic updating3.06 Select dwellings in each PSU
8
4 Staffing and training
4 Staffing and training 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
4.01 Select and train field test staff4.02 Prepare supervision procedures & manuals4.03 Prepare interviewer manual4.04 Select interviewers4.05 Train interviewers
9
5 Data management
5 Data management 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
5.01 Prepare first version of data entry program5.02 Final version of data entry program5.03 Prepare data entry manual5.04 Install data entry computers for training5.05 Train data entry operators5.06 Install data entry computers in the field5.07 Data entry in the field (first month)5.08 Evaluation and debugging5.09 Define data management procedures5.10 Data entry in the field
10
6 Field work
6 Field work 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
6.01 Survey in the field (first month field test)6.02 Evaluation6.03 Survey in the field
11
7 Data analysis and documentation
7 Data analysis and documentation 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
7.01 Define first plan of tabulations7.02 Create data sets for first six months7.03 Prepare preliminary statistical abstract7.04 Distribute statistical abstract7.05 Seminar7.06 Revise contents of abstracts7.07 Create complete data sets7.08 Prepare complete statistical abstract7.09 Prepare survey documentation7.10 Distribute raw data sets to analysts
12
Activity groups 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
1 Management and logistics2 Questionnaire development3 Sampling4 Staffing and training5 Data management6 Field work7 Data analysis and documentation
Design
Data collection
Analysis
Nominate core team
Field test
Training
First statistical abstract
Key activities
13
Shaking the Trees for People
Kathleen Beegle
14
Skills Needed
Sampling and Statistics Knowledge of Policy Issues
Questionnaire DesignProcurement and LogisticsProgramming and Data EntryTrainingData Analysis
15
WHO DOES WHAT?
• LOCAL TEAM• TECHNICAL ASSISTANCE• SUPERVISION FROM THE
BANK
16
Local Team
• Responsible for overall project
• Interaction among all phases
• Entity to receive any needed technical assistance
17
Role of Local Team• Depends on goals of project
• Expand or contract based on skills
• Actual Implementation ---------------------------------- Responsible for the survey Links with end users Specific Tasks
18
Specific Tasks: Local Team• Steering Committee, “Champion”• Sample: Select, enumerate, materials prep.• Questionnaire Production• Advertising and hiring• Training• D.E. Customization• Personnel Management, Logistics, Field• Documentation, Dissemination
19
WHO DOES WHAT?
• LOCAL TEAM
• TECHNICAL ASSISTANCE
• SUPERVISION FROM THE BANK
20
Technical Assistance• Original Mode - Research Projects
– Researcher - Designer- Supervisor
• Now roles separated
• Three primary methods– One long term consultant [and others?]– Series of short term experts– Firm
21
Long Term Consultant
Advantages
• Continuity
• Responsibility• Timing
Disadvantages
• Head of project
• Cost
• Few
22
Short Term Consultants
Advantages
• Expertise-high
• Each piece gets attention
Disadvantages
• Need good local team--continuity
• Logistics/Time
23
Firm
Advantages
• Continuity
• Decrease logistics
• Expertise
Disadvantages
• Cost
• Few
• Time lag
• Institution Build.
24
WHO DOES WHAT?
• LOCAL TEAM
• TECHNICAL ASSISTANCE
• SUPERVISION FROM THE BANK
25
Minimum Tasks for Project Supervision
• Initial Contacts, Identification 3 wks
• Design 5 wks
• Administrative 3 wks
• Review Documents 2 wks
• Review Pilot 2 wks
• Analysis 4 wks MINIMUM 19 wks
26
Who in the Bank?• Task Manager
• DECRG (includes LSMS team)– Advice in planning and design– Participate in missions– Carry out supervision– Review at key stages
• Consultants– Long term– Short term
27
Budgeting for Data Collection
Juan Muñoz
28
395,300114,400313,330
16,500236,500147,000
1,214,030121,303
1,335,333
Generic budgetFor a 1 year, 3,200 household LSMS (all-
inclusive)(see page 190)
1 Base salaries2 Travel allowance3 Materials4 Printing and xerox5 Consultancy and travel6 Other
Sub-TotalContingency (10%)Total
29
1 Base salariesLevel of Unit Total
No. effort amount
Base salaries 385,300
Project manager 1 30 months 800 24,000Data manager 1 30 months 600 18,000Field manager 1 30 months 600 18,000Assistant managers 2 30 months 450 27,000Accountant 1 24 months 450 10,800Secretary 1 30 months 350 10,500Supervisors 10 14 months 400 56,000Interviewers 20 13 months 350 91,000Anthropometrists 10 13 months 350 45,500Data entry operators 10 13 months 350 45,500Drivers 10 13 months 300 39,000
Female Facilitators 200 PSUs 50 10,000
30
2 Travel allowance
Level of Unit TotalNo. effort amount
Travel allowance 114,400
Project manager 1 90 days 40 3,600Data manager 1 60 days 40 2,400Field manager 1 90 days 40 3,600Assistant managers 2 60 days 40 4,800Supervisors 10 200 days 10 20,000Interviewers 20 200 days 10 40,000Anthropometrists 10 200 days 10 20,000Drivers 10 200 days 10 20,000
31
3 MaterialsLevel of Unit Total
No. effort amount
Materials 313,330
Vehicles 12 15,000 180,000Fuel 12 13 months 220 34,320Car maintenance 12 13 months 110 17,160
Data entry computers 10 1,200 12,000Data entry printers 10 500 5,000UPS, stabilizers, etc. 12 800 9,600Air conditioners and safety 12 1,200 14,400
Core team computers 4 1,400 5,600Computer for analysis 1 6,000 6,000Core team printer 1 500 500Laser printer 1 1,500 1,500Computer supplies 15 13 months 50 9,750
Photocopier 1 4,000 4,000Fax machine 1 500 500Stationery, toner, etc 30 months 50 1,500
Measuring tapes (adults) 10 50 500Scales (adults) 10 150 1,500Measuring boards (children) 10 300 3,000Scales (children) 10 150 1,500Survey material 10 50 500
32
4 Printing and xerox
Level of Unit Total No. effort amount
Printing and xerox 16,500
Questionnaires 4000 2 8,000Manuals 400 5 2,000First abstract 1000 4 4,000Other 500 5 2,500
33
5 Consultancy and travel
Level of Unit TotalNo. effort amount
Consultancy and travel 236,500
Foreign consultants 14 months 10,000 140,000Local consultants 5 months 2,500 12,500International travel 12 trips 4,000 48,000International per diem 240 days 150 36,000
34
6 Other
Level of Unit TotalNo. effort amount
Other 147,000
Office space 100,000 100,000Communications 30 months 200 6,000Pilot survey 5,000 5,000Household listing 20,000Software 10,000 10,000Translation 6,000 6,000
35
Comparing Budgets across Surveys• Often difficult to compare costs since reported
budgets don’t always include some important costs:– WB staff time and travel– Technical assistance (STCs, sampling expert)
• Sometimes budgets include costs not related to data collection itself– Analysis– Study tours for NSO staff
• Sometimes budgets include capital equipment which has value after the survey (computers, vehicles)
36
Timor-Leste Survey of Living Standards 2006
• 5,400 households• $1.8 million ($333 per household)
– $500,000 financed by government– includes some TA (Juan...) but not all (WB staff
time and travel)• Had to ‘purchase’ lots of cars
37
Angola Income and Expenditure Survey 2007
• 12,400 households• $4.9 million ($395 per household)
– $1 million financed by government– includes all TA (Juan, Diane): $300,000, which
includes travel costs• High transport costs ($1.2 million)
38
Albania LSMS 2002
• 3,600 households• $550,000 ($153 per household)
– $400,000 DFID TF – $150,000 WB project– includes TA (Gero,…)
• DFID did not cover equipment/vehicles
39
Panama ENV 2003• 6,800 households• $1.6 million ($235 per household)
– funded by GoP and WB– includes buying lot of equipment and vehicle rental
(which is more costly than buying)– includes some TA but not WB TA time and travel
(Kinnon)– includes analysis: poverty profile and map
40
Iraq Household Socio-Economic Survey 2006
• ~18,000 households• $3.3 million: expenses within Iraq (field work, some
analysis)• $1.5 million: TA and analysis from WB• These budget figures exclude government contribution • At least $267 per household• High transport costs ($1.2 million of budget)
41
Kagera Health and Development Survey, Tanzania, 2004
• 2,700 households• $400,000 ($148 per household)
– $200,000 TF at WB– $200,000 Danida (local)– not including TA (Kathleen)
• Panel data: Most HH interviewed in baseline village but many of the households entailed tracking within region and to other regions
42
Kenya Integrated Household Budget Survey 2005/06
• 13,430 households • $8.6 million ($660 per household)
– funding from multiple donors including WB Stat Capacity Building loan
– not including TA for design (Juan, Kathleen…)• Includes new vehicles, maybe analysis
43
Shaking the Trees for People Pesos
Kathleen Beegle
44
Financing
• Originally Research Funding
• Now other sources of funding
• Implications– administration– content– time– credibility
45
Grant / Loan Funding
• Sources– Government– U.N. Agencies - Multilaterals– Bilaterals - Development Bank
• Why Fund?-Recognize Need
-Political Mandate
-Decrease Poverty
-Convenience
-Increase Effectiveness
-Special Interests
46
Bank Funding• Sources Loan Projects (traditional, PRSC) Paris21: Trust Fund for Statistical Capacity
Building- NSDS Statistical Capacity Loans Institutional Development Funds Japanese Grant Funds Trust funds
47
Advantage and Disadvantages
• Loans: long term, capacity building– Procurement, flow of funds, gov’t staff
• TFSC- primarily NSDS• IDF- small, capacity building focus• Trust funds- tied aid, often good for
analysis• Multiple funding sources => multiple rules
for procurement/auditing
48
Key Messages
• REQUIRES CAREFUL PLANNING
• Commitment from Country
• Adequate Budget
• Time schedule reasonable and flexible
• Assess Technical Assistance Needs Early– Budget time and resources for this
• Plan explicitly for capacity building
49
Key Messages
Have Patience:
the end results areare worth it