Responsibilities & CostResponsibilities & Cost
ALICE DCS Review 14 Nov 05For the DCS Team
L.Jirden
2
ResponsibilitiesResponsibilities ACC (and its CERN partners) will provide
DCS H/W Infrastructure Back-End System Common Services Interface to TRG, DAQ, HLT, LHC via ECS S/W Infrastructure for Detector Applications
Detectors will provide Detector Sub-System Devices and Cabling Detector Specific Networking (Ethernet switches) Detector Applications for each Sub-System Detector Specific Services Integration of all Detector Sub-Systems to a full
Detector Control System Interface to the Alice Detector Control System layer
3
Magnets
Rack
contr
ol
Ele
ctri
city
Safe
ty:
DSS
Safe
ty:
CSA
M
Infr
ast
ruct
ure
LAN
WAN
Storage
Configuration DB,ArchivesFSM serversTerminal servers,ACR consoles, etc
Experimental equipment
Controller/PLC VME
Field Bus
LAN
Node Node
coolin
g
gas
Services
Central DCS
Detectors
Global ResponsibilitiesACC
DetectorsACCCommon items
4
Detector common Detector common itemsitems
Provided, installed, maintained by ACC (and their CERN collaborators) DCS Racks in CR3 Global network
Exception: detectors are responsible for the “on-detector” networks
Computers and interfaces Software infrastructure for front-end
computers ELMB Controllers with centralized Power CANbus cables - entry in cable dB Device interlock cables - entry in cable dB
WXP
PCI
OPCserver
PVSS II
FW
LIBRARIES
5
Magnets
Rack
contr
ol
Ele
ctri
city
Safe
ty:
DSS
Safe
ty:
CSA
M
Infr
ast
ruct
ure
LAN
WAN
Storage
Configuration DB,ArchivesFSM serversTerminal servers,ACR consoles, etc
Experimental equipment
Controller/PLC VME
Field Bus
LAN
Node Node
coolin
g
gas
Services
Central DCS
Detectors
Global CostACC
DetectorsACCCommon items
~1440K ?
?
?
6
Central DCSCentral DCS
Firewall
Terminal Server
Terminal Server
IP Reach for KVM
Domain Controller
Domain ControllerDB Server (Config.)
DB Server (Archive)File Server
Network and Security
FSMAlarms
General DCSElectricity & Racks
Gas & Cooling
EnvironmentGeneral servicesLHC & Access
Alignment
Information Server
CERN
System ManagementDCS Operator
DCS Status
Safety Status
Consoles Remote Access Backend Servers
Worker Nodes
Detector DCS
ACR Consoles
DB Server (Archive)
Infrastructure, network
Racks, network, cablingKVM switchescontrolled power plugs
Hot swap spare serversDisks & memories
Spares
12 KCHF
13.1 KCHF 34.5 KCHF
18.5 KCHF
43.6 KCHF
On DAQ budget
TOTAL: ~150 KCHF
7.1 KCHF
DCS network
7
Detector DCS Detector DCS costcost
SPD 21K 75k
SDD 25K guess 50k
SSD 25K 20k
TPC 100K 300k
TRD 80K guess 82k
TOF 43K 89k
HMPID 80K 15k
PHOS 44K 150k
CPV 20K 0
PMD 11K 100k
FMD 8K 0
V0 7K 0
T0 16K 0
ZDC 5K guess 0
MUON TRK 42K 200k
MUON TRG 11K 50k
ACORDE 5K guess 0
TOTAL ~ 550K ~ 1130K
Estimation today
Quoted in MOU
NOTE:Cables and connectors are probably under-estimated
Installation cost is not included
8
Detector common itemsDetector common itemsItem number Unit price
(KCHF)Total Cost
(KCHF)
DCS racks 4 8 32
Global network 325 0.4 * 130
Computers 76 1.6 125
Interfaces 35 0.6 21
Software infrastructure
76 0 0
ELMB’s 50 0.3 15
ELMB power 1 6 6
Total ~ 330K* Very approximative - IT/CS will provide a precise offer
9
Magnets
Rack
contr
ol
Ele
ctri
city
Safe
ty:
DSS
Safe
ty:
CSA
M
Infr
ast
ruct
ure
LAN
WAN
Storage
Configuration DB,ArchivesFSM serversTerminal servers,ACR consoles, etc
Experimental equipment
Controller/PLC VME
Field Bus
LAN
Node Node
coolin
g
gas
Services
Central DCS
Detectors
Global CostACC
DetectorsACCCommon items
~1440K ~550K
~150K
~330K
10
DCS costs to be DCS costs to be shared shared
Central DCS 150K Weighted according to agreed formula
Detector Common items 330K According to actually used items
TOTAL 480K
via a DCS common budget code.
12
Backend serversBackend servers
Server Role Hardware Configuration Cost (CHF)
Primary Domain Controller 1xXeon, 2 GB RAM 2500
Secondary Domain Controller 1xXeon 2 Gb RAM 2500
Configuration Database Server 2xXEON, 4 GB RAM 4000
Archive Database Server (P2) 2xXEON, 4 GB RAM 4000
Archive Database Server (IT) 2xXEON, 4 GB RAM, disk array
12000
DCS Disk server 2xXEON , 4 GB RAM, disk array
7000
DCS Information Server PIV or XEON, 4 GB RAM 2500
Total (7 backend servers) 34500
13
Worker NodesWorker Nodes
WN Role Hardware Configuration Cost (CHF)
DCS network (monitor and management) PIV, 2 GB RAM 1600
DCS general (FSM) PIV, 2 GB RAM 1600
DCS general (alarm/messages) PIV, 2 GB RAM 1600
DCS general (general DCS) PIV, 2 GB RAM 1600
Infra/services (electricity & racks) PIV, 2 GB RAM 1600
Infra/services (gas & cooling) PIV, 2 GB RAM 1600
Infra/services (environment) PIV, 2 GB RAM 1600
Infra/services (general services) PIV, 2 GB RAM 1600
Infra/services (LHC & access) PIV, 2 GB RAM 1600
Infra/services (alignment) PIV, 2 GB RAM 1600
PCI + ELMB for infrastructure 2500
Total (10 worker nodes) 18500
14
Infrastructure and Infrastructure and NetworkNetwork
WN Role Hardware Configuration Cost (CHF)
3 Powered Racks (8000/rack) 24000
Network installation (400/port) To be detailed by IT/CO 10000
KVM switch Raritan Z-series 2000
KVM user stations USTSZ4000U – 20 pack 3600
Power plug control Spectrum control 4000
Total 43600
15
Remote accessRemote access
WN Role Hardware Configuration Cost (CHF)
Main network gateway/firewall To be detailed by CNIC 5000
DCS Terminal Server PIV or XEON, 4 GB RAM 2500
DCS Terminal Server PIV or XEON, 4 GB RAM 2500
IP reach for KVM Raritan IPR-M1 3100
Total 13100
16
ConsolesConsoles
WN Role Hardware Configuration Cost (CHF)
DCS System Administrator Console PIV, 1 GB RAM + Monitor 2500
DCS Operator Consoles PIV, 1 GB RAM + Monitor 2500
DCS Status Display PIV, 1 GB RAM + Monitor 2500
Safety Display PIV, 1 GB RAM + Monitor 2500
KVM Switches 2000
ACR Consoles (on DAQ budget) 0
Total (4 consoles) 12000