Page 1: 1 Radhika Bharat, Senior Investment Officer, Private Sector Infrastructure Development Africa Carbon Forum, Nairobi, March 2010 Clean Development Mechanism.

1

Radhika Bharat,Senior Investment Officer,Private Sector Infrastructure Development

Africa Carbon Forum, Nairobi, March 2010

Clean Development Mechanism

Projects utilizing Carbon Credits

Page 2: 1 Radhika Bharat, Senior Investment Officer, Private Sector Infrastructure Development Africa Carbon Forum, Nairobi, March 2010 Clean Development Mechanism.

2

The 15MW Sahanivotry Small Hydroelectric Power Project, a catalyst for Power Sector in Madagascar

Madagascar

• Project Cost EUR 14 mn

• ADB loan EUR 6 mn

ADB roles

– Project Structuring

– Long-term Lender

Benefits

– Independent power project (IPP)

– Expand the supply for electricity

– Reduce generation cost

– Long-term socio economic benefits

Page 3: 1 Radhika Bharat, Senior Investment Officer, Private Sector Infrastructure Development Africa Carbon Forum, Nairobi, March 2010 Clean Development Mechanism.

3

Country : Madagascar

Annual Electricity Production 80,000 MWhGrid Displacement Factor 0.496 tCO2e/KWh

Annual CO2 Reduction 39,680 tCO2

Price of Carbon 9 €/tCO2eNumber of year to benefit from carbon trade 5Start of Operation 2008

Total CO2 Reduction 198,400 tCO2

Estimation Total CER generated 1,785,600 EUR

Project: Sahanivotry Small Hydropower (15 MW)

Page 4: 1 Radhika Bharat, Senior Investment Officer, Private Sector Infrastructure Development Africa Carbon Forum, Nairobi, March 2010 Clean Development Mechanism.

4

The 9MW Buseruka Small Hydroelectric Power Project, a catalyst for Power Sector in Uganda

Project costs

• Project Cost USD 26 mn

• ADB loan USD 9 mn

ADB roles

– Project Structuring

– Long-term Lender

Benefits

– Independent power project (IPP)

– Connection of rural population

– Reduce generation cost

– Long-term socio economic benefits

Page 5: 1 Radhika Bharat, Senior Investment Officer, Private Sector Infrastructure Development Africa Carbon Forum, Nairobi, March 2010 Clean Development Mechanism.

5

Country : Uganda

Annual Electricity Production 47,304 MWhGrid Displacement Factor 0.496 tCO2e/KAnnual CO2 Reduction 23,463 tCO2

Price of Carbon 9 €/tCO2e

Number of year to benefit from carbon trade 3Start of Operation 2011

Total CO2 Reduction 70,388 tCO2

Estimation Total CER generated 633,495 EUR

Project: Buseruka Small Hydropower (9 MW)

Page 6: 1 Radhika Bharat, Senior Investment Officer, Private Sector Infrastructure Development Africa Carbon Forum, Nairobi, March 2010 Clean Development Mechanism.

6

CDM – Project Status

Project PIN

Project Design Document (PDD)

Validation CER

Sahanivotry Done Done under processing 2010

Buseruka Done Under review will be submitted June 2011

Page 7: 1 Radhika Bharat, Senior Investment Officer, Private Sector Infrastructure Development Africa Carbon Forum, Nairobi, March 2010 Clean Development Mechanism.

7

Project AfDB Other Donor

• Support to the sponsor on follow ups of Carbon

document processing

Technical Assistance

Sahanivotry

Austria – Komunal Credit provided grant to prepare the Carbon Credit documentation

Buseruka

Denmark – “UNIT Energy Styrelsen” provided grant to prepare the Carbon Credit documentation

• Guidance to the sponsor

• Preparation of request for technical assistance

Page 8: 1 Radhika Bharat, Senior Investment Officer, Private Sector Infrastructure Development Africa Carbon Forum, Nairobi, March 2010 Clean Development Mechanism.

Lake Turkana Wind Farm in Marsabit District, near Lake Turkana in north-western part of Kenya

• Project Cost EUR 300 mn

• ADB loan EUR 100 mn

ADB roles

– Mandated Lead Arranger for financing from DFIs and Commercial sources

– Project Structuring

– Long-term Lender

Notable features:

– Project is 300MW, with a capacity factor of 55%

– Project will supply up to 20% of Kenya’s total installed power

– Kenyan- Dutch project developer, JDA signed with UK based firm

– Carbon credits to be shared between the Government and project sponsor.