Project Management for Construction of N P P
2013The Japan Atomic Power CompanyProjects Development Department
The following materials may contain JAPC’s proprietary proprietary and confidential information; and all of or any part of these materials or information contained herein may NOT be used for any purposes other than originally intended or may NOT be reproduced, disclosed, transferred, distributed or in any manner transmitted in any tangible, electronic or any other form to any third party without prior written consent thereto by JAPC.
Lec. 3(Seminar on “Sharing Experience on Nuclear Power for Development” in Vietnam)
2
Contents-1【 Title 】 ----------------------------------------------------------------------------------------------------------------------------------------
1
1. About JAPC ------------------------------------------------------------------------------------------------------------------------------ - 4(1) Construction & Operation of the First of a Kind Reactors(2) Outline of Tsuruga Units 3&4 ( Current Status, APWR Main Specification / Design Features)
【 Outline of Construction Procedures of Nuclear Power Plants (NPPs) 】 ------------------------------------------------------------- 9
1. Law and Regulation for Construction of NPPs ---------------------------------------------------------------------------------- ----10(1) Two Important Laws as the regulation of NPPs in Japan(2) Main Guidelines for Safety Examination for LWRs(3) Endorsement of Academic Society and Association Codes, etc by Government
2. Procedural Steps for NPP Construction ---------------------------------------------------------------------------------- ------------ 14
3. Stage of Planning ------------------------------------------------------------------------------------------------------------------------ 15(1) Site Selection (Important site conditions)(2) Procedures for Site Selection(3) Requirement for NPP Siting (Nuclear Reactor Site Evaluation Guidelines)(4) Site Selection (Accompanying events of earthquake)(5) Safety Examination(6) Requirement for NPP Siting (A large volume of condenser cooling water)(7) Requirement for NPP Siting (Solid bedrock for Earthquake-resistance)(8) Site Selection (Service Water, transportation, large temporary area)(9) Environmental Survey (Determine the Site, Topographic , Geological, Meteorological, Oceanographic and Marine Life Survey)
May contain JAPC’s proprietary information. Subject to JAPC’s prior written consent before using for any other purposes than originally intended or before disclosing to any third party.
3
(10) Environmental Impact Assessment(11) 1st Public Hearing(12) Direct Dialogues with Residents (Home visits, Meeting, Newspapers, TV)
4. Preparation for Construction -------------------------------------------------------------------------------------------------------- 40(1) Procedure of Reactor Installation License from NSC Viewpoint(2) Approval Criteria for Reactor Installation LicenseApproval Criteria for Reactor Installation License(3) Application Document for Reactor Installation License (Application Text, Appendix documents)(4) Law and Regulation for Construction of Nuclear Power PlantsLaw and Regulation for Construction of Nuclear Power Plants(5) Safety Examination (Site Evaluation Guidelines)(6) Safety Design Guidelines (7) Dose-objective Guidelines(8) 2nd Public Hearing(9) Construction permit (Examination of Detailed Design, Approval of Construction Plan) Approval of Construction Plan)
5. Stage of Construction ---------------------------------------------------------------------------------------------------------------- 55(1) Major Activities in the construction of NPPMajor Activities in the construction of NPP(2) Flow of Construction Works (Example of PWR Plant) Flow of Construction Works (Example of PWR Plant) (3) Introduction of Many Tests and Inspections (4) Pre-service Inspection (Overview, Test items, Criteria, Schedule)Pre-service Inspection (Overview, Test items, Criteria, Schedule)(5) Operational Safety Program
6. Design and Construction Schedule of NPP in JAPANDesign and Construction Schedule of NPP in JAPAN--------------------------------------------------------------------------- 64
Contents-2
May contain JAPC’s proprietary information. Subject to JAPC’s prior written consent before using for any other purposes than originally intended or before disclosing to any third party.
4
Construction & Operation Construction & Operation of the First of a Kind Reactorsof the First of a Kind Reactors
About JAPCAbout JAPC
0
10
20
30
40
50
60
70
1965 1970 1975 1980 1985 1990 1995 2000 2005 2010 2015
(GW)
(Year)
ImageImage
May contain JAPC’s proprietary information. Subject to JAPC’s prior written consent before using for any other purposes than originally intended or before disclosing to any third party.
5
Outline of Tsuruga Units 3&4Outline of Tsuruga Units 3&4
■ ■ Type : APWR (Twin Type)Type : APWR (Twin Type)
■ ■ Location : Tsuruga City, Fukui Prefecture Location : Tsuruga City, Fukui Prefecture
■ ■ Electrical Output : 1,538MWe x 2Electrical Output : 1,538MWe x 2
■ ■ Operation Start (Target) : Unit 3; Mar.2016, Operation Start (Target) : Unit 3; Mar.2016, Unit 4; Mar.2017Unit 4; Mar.2017 May contain JAPC’s proprietary information. Subject to JAPC’s prior written consent before using for any other purposes than originally intended or before disclosing to any third party.
About JAPCAbout JAPC
6
Current Status of Site Preparation WorkCurrent Status of Site Preparation Work
Tsuruga-3&4(image)Tsuruga-3&4(image)Mountain-sideMountain-side
Sea-sideSea-side
May contain JAPC’s proprietary information. Subject to JAPC’s prior written consent before using for any other purposes than originally intended or before disclosing to any third party.
7
APWR Main SpecificationsAPWR Main Specifications
2
(PCCV: Pre-stressed Concrete Containment Vessel)
May contain JAPC’s proprietary information. Subject to JAPC’s prior written consent before using for any other purposes than originally intended or before disclosing to any third party.
About JAPCAbout JAPC
8
APWR Design FeaturesAPWR Design Features
3May contain JAPC’s proprietary information. Subject to JAPC’s prior written consent before using for any other purposes than originally intended or before disclosing to any third party. Quotation of the above pictures in this document has been allowed by MHI
About JAPCAbout JAPC
9
Outline of Construction Procedures Outline of Construction Procedures of Nuclear Power Plantsof Nuclear Power Plants
10
LawLaw・ Atomic Energy Basic Law
・ The Law on the Regulation of Nuclear Source Material, Nuclear Fuel Material and Reactors
・ Electricity Utilities Industry Law
・ Law for Environmental Impact Assessment
・ Industrial Safety and Health Law, etc.
May contain JAPC’s proprietary information. Subject to JAPC’s prior written consent before using for any other purposes than originally intended or before disclosing to any third party.
Law and RegulationLaw and Regulationfor Construction of Nuclear Power Plantsfor Construction of Nuclear Power Plants
Law and RegulationLaw and Regulation
11
Electricity Utilities Industry Law
The Law on the Regulation of Nuclear Source Material, Nuclear Fuel Material and Reactors
-Ensure of peaceful uses of nuclear fuel material and reactors
-Secure public safety by preventing accidents
-Accordance with the sprits of the Atomic Energy Basic Law
-Protect the benefits of consumers of electricity
-Contrive sound development of the electric utility
-Secure public safety / contribute to environmental preservation by
regulating its work of installing, constructing, maintaining and operating its
electrical facilities.
May contain JAPC’s proprietary information. Subject to JAPC’s prior written consent before using for any other purposes than originally intended or before disclosing to any third party.
Law and RegulationLaw and Regulationfor Construction of Nuclear Power Plantsfor Construction of Nuclear Power Plants
Law and RegulationLaw and Regulation
12May contain JAPC’s proprietary information. Subject to JAPC’s prior written consent before using for any other purposes than originally intended or before disclosing to any third party.
Main Guidelines for Safety Examination for LWRsMain Guidelines for Safety Examination for LWRs
Site Evaluation Guidelines
Safety Evaluation Guidelines
Safety Design Guidelines
Dose-objectives Guidelines
Priority Classification Guidelines
ECCS Performance Evaluation Guidelines
Meteorological Guidelines for Safety Analysis
Reactivity Initiated Event Evaluation Guidelines
PWR Core Thermal Design Evaluation Guidelines
Dose Target Evaluation Guidelines
Radioactive Material Emission Measurement Guidelines
Fire Protection Guidelines
Seismic Design Guidelines
Radiation Measurement Guidelines
Law and RegulationLaw and Regulationfor Construction of Nuclear Power Plantsfor Construction of Nuclear Power Plants
Law and RegulationLaw and Regulation
13
Law and RegulationLaw and Regulationfor Construction of Nuclear Power Plantsfor Construction of Nuclear Power Plants
- Technical Guideline and Rules of the Japan Electric Association (JEA)
- Technical codes of the Japan Society of Mechanical Engineering (JSME)
- Technical Standards of the Atomic Energy Society of Japan (AESJ), etc.
Law and RegulationLaw and Regulation
Technical Standards of METI for nuclear facility, Technical Standards of METI for nuclear facility, electric equipment, fossil fuel facility, etc.electric equipment, fossil fuel facility, etc.
Academic Society and Association Codes, etc.Academic Society and Association Codes, etc.
EndorseEndorse
May contain JAPC’s proprietary information. Subject to JAPC’s prior written consent before using for any other purposes than originally intended or before disclosing to any third party.
14
Procedural Steps for NPP ConstructionProcedural Steps for NPP ConstructionP
lann
ing
Pre
para
tion
for
Con
stru
ctio
nC
onst
ruct
ion
Ope
ratio
n
Utilities Government
Site SelectionEnvironmentalExamination
Opinions ofinhabitants
1st PublicHearing
Advisory Committee for Resource & Energy
Decision on basic program of power development
Local Governor’s
Consent
Application for Reactor Installation
License
Safety Examination 2nd PublicHearing
Opinions ofinhabitants
Reactor Installation LicenseApplication for
Construction Plan Construction Permit (approval of Construction Plan)
Start ofConstruction
WeldingInspection
Pre-serviceInspection
Fuel Inspection
Start ofOperation
PeriodicalInspection
SafetyInspection
PeriodicalSafety Review
EnvironmentalSurvey
EnvironmentalAssessment
May contain JAPC’s proprietary information. Subject to JAPC’s prior written consent before using for any other purposes than originally intended or before disclosing to any third party
Local Community
Approval of Operational Safety Program
Application for Operational
Safety Program
15
Stage ofStage of PlanningPlanning
Site Selection
– Selection of Project Site– Feasibility Study for Siting
In order to determine the site, topographic, geological, meteorological and oceanographic surveys have to be carried out.
– One of the most important conditions is acceptance of local community and local government.
May contain JAPC’s proprietary information. Subject to JAPC’s prior written consent before using for any other purposes than originally intended or before disclosing to any third party.
Stage ofStage of PlanningPlanning
16
Site Selection
Important site conditions are as follows:
May contain JAPC’s proprietary information. Subject to JAPC’s prior written consent before using for any other purposes than originally intended or before disclosing to any third party.
1. A large site area with enough distance from the public
2. A large volume of sea water for condenser cooling
3. Solid bedrock from the view point of Earthquake-resistance
4. Easy to obtain plant services water
5. Convenience for transportation of heavy components and a large temporary area for the construction work
Stage ofStage of PlanningPlanning
17
Procedures for Site SelectionProcedures for Site Selection
Candidate SitesBasic program of power development
Project Scale (Number of Units & Capacity)
Topographical Feature : Scale of Environmental Modification and Civil Work
Geological Feature : Bedrock Depth, Ground Stability, Earthquake History, etc.
Geographical Feature: Social & Environmental Features (Separation form public, etc.)
Plot PlanStudy
Site Determination
Survey Items, Scope, MethodGeological:Bedrock/ Plant Design Parameter
Environmental Survey
Requirements for Plant (Area, Cooling Water, Plant Fresh Water, etc.)
Infrastructure (Power-line / Access Road / Harbor Facilities, etc.)
Preliminary Site Survey (Geological Feature: Solid Bedrock/ quantity of Plant Fresh Water etc. )
Assessment (Total Cost, Safety)
Land, Marine, Atmospheric & Social environment
May contain JAPC’s proprietary information. Subject to JAPC’s prior written consent before using for any other purposes than originally intended or before disclosing to any third party.
Stage ofStage of PlanningPlanning
18
Nuclear Reactor Site Evaluation GuidelineNuclear Reactor Site Evaluation Guideline(by Nuclear Safety Commission)
From the view point of public safety in case of accident, the following siting conditions are required in principle.
– There have not been any events which induce large accident, and no such event is expected to occur in the future.There have also been very few events which expand disaster.
– Nuclear reactors shall be located at a sufficient distance from the public.
– The environment of the nuclear reactor site shall be such that appropriate measures for the public protection can be implemented as required.
Requirement for NPP SitingRequirement for NPP Siting
Stage ofStage of PlanningPlanning
May contain JAPC’s proprietary information. Subject to JAPC’s prior written consent before using for any other purposes than originally intended or before disclosing to any third party.
19
Consideration of the accompanying events of earthquake
- inclined planes around Facilities (stability on slide)- tsunami (run-up/down)
Reactor Building
Regulatory guide for Reviewing Seismic Design of Nuclear Power Reactor Facilities (Sep.19,2006 NSC)
May contain JAPC’s proprietary information. Subject to JAPC’s prior written consent before using for any other purposes than originally intended or before disclosing to any third party.
Site Selection ( Accompanying events of earthquake )
Stage ofStage of PlanningPlanning
20
Stage ofStage of PlanningPlanning
• <Site Evaluation Guidelines>
• Purpose To confirm Adequacy of isolation between Reactor and Public in Accident
• Criteria
– Major Accident accidents which may occur in the worst case from technical point of view
– Hypothetical Accident accidents exceeding major accidents which may not occur from technical point of view
Safety ExaminationSafety Examination [[ Site Evaluation GuidelinesSite Evaluation Guidelines ]]
Power Station
The area where radiation hazard may occur if people stayed in the area continuously in case of a major accident.
Non-residential Area
Low Population Zone(Power Station Site)
The area where appropriate measures can be taken to project the public from radiation in case of a hypothetical accident.
Residential Area
High Population Area
The non-residential area and low population zone are included in the site of the power station.(There are no residents in these areas in Japan.)
Collective doses; 20,000man-Sv or less
Adults thyroid exposure doses; 3Sv or lessAccidents
Whole body exposure doses; 0.25Sv or lessHypothetical
Infants thyroid exposure doses; 1.5Sv or lessaccidents
Whole body exposure doses; 0.25Sv or lessMajor
May contain JAPC’s proprietary information. Subject to JAPC’s prior written consent before using for any other purposes than originally intended or before disclosing to any third party.
Preparation for ConstructionPreparation for Construction
21
Requirement for NPP SitingRequirement for NPP Siting
A large volume of condenser cooling water
• Required Cooling Water Flow : 70 - 80 ton/sec (1,100MW class)
• Cooling Water Candidates: Seawater, Large River Water, Lake Water, etc.
• Because there are not large rivers in Japan, all the NPP sites are located beside the sea and use seawater for condenser cooling.
May contain JAPC’s proprietary information. Subject to JAPC’s prior written consent before using for any other purposes than originally intended or before disclosing to any third party.
Stage ofStage of PlanningPlanning
22
Solid bedrock for Earthquake-resistance
• In Japan, the important buildings, structures and equipment has been erected directly on a solid bedrock or been supported by an artificial bedrock placed on a solid bedrock to suppress the amplification of vibration in case of earthquakes.
• It is desirable to select a site at which such solid bedrock is found at a relatively shallow level from the ground surface.
May contain JAPC’s proprietary information. Subject to JAPC’s prior written consent before using for any other purposes than originally intended or before disclosing to any third party.
Requirement for NPP SitingRequirement for NPP Siting
Stage ofStage of PlanningPlanning
23
Easy to obtain plant services water• Fresh water for plant services
Reactor make-up water, House-boiler, Washing insulators, System Flushing, etc.
• Quantity of make-up water about several hundred to one thousand tons per day (1,000 MW Plant)
• In Japan, fresh water is taken from a river near the power plant, or demineralization units supply fresh water.
May contain JAPC’s proprietary information. Subject to JAPC’s prior written consent before using for any other purposes than originally intended or before disclosing to any third party.
Stage ofStage of PlanningPlanning
Site SelectionSite Selection (( Site ConditionSite Condition ))
24
•Unloading facilities for heavy components near the site. – Transportation of spent fuel casks (about 70 - 100 tons) – Transportation of heavy components, such as the
reactor pressure vessel, steam generators, main transformers and generators in construction work
•Temporary area for construction is needed to use for locating the contractor's temporary building, construction materials and machinery storage yards, etc. during construction period.
– Single unit : 13-17×10 4 (m2) – Twin unit : 18-29×10 4 (m2) (@1,000 MW ~ 1,500MW class)
May contain JAPC’s proprietary information. Subject to JAPC’s prior written consent before using for any other purposes than originally intended or before disclosing to any third party.
Convenience for transportation of heavy components and a large temporary area for the construction work
Reactor Vessel of Tsuruga-2 (320ton)
Site SelectionSite Selection (( Site ConditionSite Condition ))Stage ofStage of PlanningPlanning
25
Pla
nnin
gP
repa
ratio
n fo
rC
onst
ruct
ion
Con
stru
ctio
nO
pera
tion
Utilities Government Local Community
Site SelectionEnvironmentalExamination
Opinions ofinhabitants
1st PublicHearing
Advisory Committee for Resource & Energy
Decision on basic program of power development
Local Governor’s
Consent
Safety Examination 2nd PublicHearing
Opinions ofinhabitants
Reactor Installation LicenseApplication for
Construction Plan Construction Permit (approval of Construction Plan)
WeldingInspection
Pre-serviceInspection
Fuel Inspection
Start ofOperation
PeriodicalInspection
SafetyInspection
PeriodicalSafety Review
EnvironmentalAssessment
May contain JAPC’s proprietary information. Subject to JAPC’s prior written consent before using for any other purposes than originally intended or before disclosing to any third party
EnvironmentalSurvey
Procedural Steps for NPP ConstructionProcedural Steps for NPP Construction
Start ofConstruction
Application for Reactor Installation
License
Approval of Operational Safety Program
Application for Operational
Safety Program
26
Survey to Determine the Site Survey to Determine the Site
In order to determine the site, several kinds of surveys have to be carried out as follows:
1. Topographic and Geological Survey
2. Meteorological Survey
3. Oceanographic Survey and Marine Life Survey
May contain JAPC’s proprietary information. Subject to JAPC’s prior written consent before using for any other purposes than originally intended or before disclosing to any third party.
Stage ofStage of PlanningPlanning
27
Topographic and Geological SurveyTopographic and Geological Survey
the topography of the plant site and its surrounding area are investigated :
<core drilling, test pitting, seismic prospecting, aerial photogrammetric etc.>
(shape, depth and strength of bedrock, etc.)– to locate important structures including the reactor building
(seismic history, geological structure, measured seismic waves)– to determine the seismic design inputs (ex. maximum
acceleration of the foundation ground)
May contain JAPC’s proprietary information. Subject to JAPC’s prior written consent before using for any other purposes than originally intended or before disclosing to any third party.
Stage ofStage of PlanningPlanning
28
Topographic and Geological SurveyTopographic and Geological Survey - Geological Survey - Geological Survey [[ ExampleExample ] ] --
May contain JAPC’s proprietary information. Subject to JAPC’s prior written consent before using for any other purposes than originally intended or before disclosing to any third party.
Stage ofStage of PlanningPlanning
29
Meteorological SurveyMeteorological Survey
Wind velocity, temperature, moisture, rain precipitation, salinity, etc. are investigated :
– To be reflected in the building and equipment design conditions
Wind direction and velocity distributions, vertical distribution of temperature, etc. are investigated :
– To evaluate the effects of released gaseous radioactive wastes under normal and accidental conditions on the public
– To evaluate the adequacy of the stack height
May contain JAPC’s proprietary information. Subject to JAPC’s prior written consent before using for any other purposes than originally intended or before disclosing to any third party.
Stage ofStage of PlanningPlanning
30
Meteorological Survey [ Example ]
May contain JAPC’s proprietary information. Subject to JAPC’s prior written consent before using for any other purposes than originally intended or before disclosing to any third party.
Stage ofStage of PlanningPlanning
31
Oceanographic Survey and Marine Life SurveyOceanographic Survey and Marine Life Survey
Wave height, wave direction, tidal level, depth of water, drift sand, tidal current, and marine life are investigated :
– to design of the intake and discharge facilities of the condenser cooling sea water
– to assess the impacts of the diffusion of thermal discharge on marine life
May contain JAPC’s proprietary information. Subject to JAPC’s prior written consent before using for any other purposes than originally intended or before disclosing to any third party.
Stage ofStage of PlanningPlanning
32
OceanographicOceanographic Survey and Marine Life Survey and Marine Life Survey Survey [Example][Example]
May contain JAPC’s proprietary information. Subject to JAPC’s prior written consent before using for any other purposes than originally intended or before disclosing to any third party.
Stage ofStage of PlanningPlanning
Deep layer discharge
Surface layer discharge
1℃ up
2℃ up
3℃ up
Reduction of Diffusion Area of Thermal Effluent
May contain JAPC’s proprietary information. Subject to JAPC’s prior written consent before using for any other purposes than originally intended or before disclosing to any third party
An Image of Nuclear Power Station after EIA Review
Native tree planting
Minimize reclamation area
An Image of Nuclear Power Station at Basic Plan Stage
35
Environmental Impact AssessmentEnvironmental Impact Assessment
- The utility surveys the natural and social environment of the selected site and makes environmental impact forecasts and assessments both during the period of construction and operation as required in EIAL and EUIL.
- In accordance with EIAL and EUIL, an environmental impact report is submitted from the utility to METI and the local government. The report is also reviewed by local residents, and their comments are invited. METI examine the report considering the comments from the local governor and local residents.
May contain JAPC’s proprietary information. Subject to JAPC’s prior written consent before using for any other purposes than originally intended or before disclosing to any third party.
Stage ofStage of PlanningPlanning
36
Pla
nnin
gP
repa
ratio
n fo
rC
onst
ruct
ion
Con
stru
ctio
nO
pera
tion
Utilities Government Local Community
Site SelectionEnvironmentalExamination
Opinions ofinhabitants
1st PublicHearing
Advisory Committee for Resource & Energy
Decision on basic program of power development
Local Governor’s
Consent
Safety Examination 2nd PublicHearing
Opinions ofinhabitants
Reactor Installation LicenseApplication for
Construction Plan Construction Permit (approval of Construction Plan)
WeldingInspection
Pre-serviceInspection
Fuel Inspection
Start ofOperation
PeriodicalInspection
SafetyInspection
PeriodicalSafety Review
EnvironmentalSurvey
EnvironmentalAssessment
May contain JAPC’s proprietary information. Subject to JAPC’s prior written consent before using for any other purposes than originally intended or before disclosing to any third party
Procedural Steps for NPP ConstructionProcedural Steps for NPP Construction
Start ofConstruction
Application for Reactor Installation
License
Approval of Operational Safety Program
Application for Operational
Safety Program
37
1st Public Hearing1st Public Hearing
During the environmental examination, METI holds the 1st Public hearing to gain a deeper understanding of local communities concerning :
- Necessity and outline of the construction plan - Environmental impacts of the NPP installation - Basic policy of safety measures & environmental
protection
May contain JAPC’s proprietary information. Subject to JAPC’s prior written consent before using for any other purposes than originally intended or before disclosing to any third party.
Stage ofStage of PlanningPlanning
38
Direct Dialogues with Residents (Home visits)
Visiting all 26,000 households in Tsuruga
Stage ofStage of PlanningPlanning
May contain JAPC’s proprietary information. Subject to JAPC’s prior written consent before using for any other purposes than originally intended or before disclosing to any third party.
39
At takahama At echizen
Meetings with the Residents
5000 participants
Stage ofStage of PlanningPlanning
May contain JAPC’s proprietary information. Subject to JAPC’s prior written consent before using for any other purposes than originally intended or before disclosing to any third party.
40
Newspaper Advertisements
TV Commercials Stage ofStage of PlanningPlanning
41
Pla
nnin
gP
repa
ratio
n fo
rC
onst
ruct
ion
Con
stru
ctio
nO
pera
tion
Utilities Government Local Community
Site SelectionEnvironmentalExamination
Opinions ofinhabitants
1st PublicHearing
Advisory Committee for Resource & Energy
Decision on basic program of power development
Local Governor’s
Consent
Safety Examination 2nd PublicHearing
Opinions ofinhabitants
Reactor Installation LicenseApplication for
Construction Plan Construction Permit (approval of Construction Plan)
WeldingInspection
Pre-serviceInspection
Fuel Inspection
Start ofOperation
PeriodicalInspection
SafetyInspection
PeriodicalSafety Review
EnvironmentalSurvey
EnvironmentalAssessment
May contain JAPC’s proprietary information. Subject to JAPC’s prior written consent before using for any other purposes than originally intended or before disclosing to any third party
Procedural Steps for NPP ConstructionProcedural Steps for NPP Construction
Start ofConstruction
Application for Reactor Installation
License
Approval of Operational Safety Program
Application for Operational
Safety Program
42
Pla
nnin
gP
repa
ratio
n fo
rC
onst
ruct
ion
Con
stru
ctio
nO
pera
tion
Utilities Government Local Community
Site SelectionEnvironmentalExamination
Opinions ofinhabitants
1st PublicHearing
Advisory Committee for Resource & Energy
Decision on basic program of power development
Local Governor’s
Consent
Safety Examination 2nd PublicHearing
Opinions ofinhabitants
Reactor Installation LicenseApplication for
Construction Plan Construction Permit (approval of Construction Plan)
WeldingInspection
Pre-serviceInspection
Fuel Inspection
Start ofOperation
PeriodicalInspection
SafetyInspection
PeriodicalSafety Review
EnvironmentalSurvey
EnvironmentalAssessment
May contain JAPC’s proprietary information. Subject to JAPC’s prior written consent before using for any other purposes than originally intended or before disclosing to any third party
Procedural Steps for NPP ConstructionProcedural Steps for NPP Construction
Start ofConstruction
Application for Reactor Installation
License
Approval of Operational Safety Program
Application for Operational
Safety Program
43
Procedure of Reactor Installation License from NSC Viewpoint
(Source:NSC Annual Report)
May contain JAPC’s proprietary information. Subject to JAPC’s prior written consent before using for any other purposes than originally intended or before disclosing to any third party.
Preparation for ConstructionPreparation for Construction
44
Approval Criteria for Reactor Installation LicenseApproval Criteria for Reactor Installation License
1. The Reactors will not be used for non-peaceful purpose.
2. The permission will cause no hindrance to the planned development and utilization of atomic energy.
3. The applicant has technological ability and financial position sound enough to establish reactor, and has such technical ability to operate them competently.
4. The location, structure and equipment of reactor facilities are such that they will cause no hindrance to the prevention from the hazard by reactor fuel material and by reactors.
1st Examination 2nd Examination(Double check)
METI
Atomic Energy
Commission
NuclearSafety
Commission
Approval Criteria
May contain JAPC’s proprietary information. Subject to JAPC’s prior written consent before using for any other purposes than originally intended or before disclosing to any third party.
Preparation for ConstructionPreparation for Construction
45
Application Document for Reactor Installation License (1)
Application Text
(1) name & address of applicant
(2) purpose
(3) type, thermal output and number
(4) name & address of facility
(5) Location, structure and equipment
(6) Construction Plan
(7) Fuel material and estimated annual consumption
(8) Method of disposing of spent fuel
A. location of reactor facilities
B. structure of reactor facilities a. seismic structure b. other main structure
C. structure and equipment of reactor a. reactor core b. fuel c. coolant & reflector d.reactor vessel e. radiation shield f. others
D. fuel handling & storage facilities
E. reactor cooling system a. primary cooling system b. secondary cooling system c. emergency cooling system d. others
F. instrumentation and control system
F. radioactive waste treatment facilities
G. radiation control system
H. other facilities
May contain JAPC’s proprietary information. Subject to JAPC’s prior written consent before using for any other purposes than originally intended or before disclosing to any third party.
Preparation for ConstructionPreparation for Construction
46
Application Document for Reactor Installation License (1)
Appendix documents
chapter 1 : purpose of reactor establishment
chapter 2 : reactor thermal output calculation
chapter 3 : economic plan for construction
chapter 4 : nuclear fuel acquisition plan
chapter 5 : technical ability of applicant to establish and operate reactor
chapter 6 : siting condition
chapter 7 : topographical map around reactor
chapter 8 : safety design of reactor facilities
chapter 9 : radiation protection and waste treatment
chapter 10 : safety analysis
(1) site outline(2) meteorological condition(3) geological condition(4) sea & water condition(5) earthquake(6) social environment
(1) safety design philosophy (2) facility layout (3) reactor & core (4) reactor cooling system (5) reactor containment system (6) turbine system (7) instrumentation & control system (8) electricity facility (9) fuel handling & storage system(10) radioactive waste treatment system(11) radiation control system(12) plant support facilities(13) emergency control center(14) operation & maintenance(15) quality assurance
(1) radiation protection policy (2) radiation control(3) peripheral radiation monitored area & environmental radiation monitoring (4) radioactive waste treatment (5) dose evaluation of public around site
(1) safety assessment policy (2) anticipated transient analysis(3) accident analysis (4) major accident & hypothetical accident analysis
May contain JAPC’s proprietary information. Subject to JAPC’s prior written consent before using for any other purposes than originally intended or before disclosing to any third party.
Preparation for ConstructionPreparation for Construction
47May contain JAPC’s proprietary information. Subject to JAPC’s prior written consent before using for any other purposes than originally intended or before disclosing to any third party.
Main Guidelines for Safety Examination for LWRsMain Guidelines for Safety Examination for LWRs
Site Evaluation Guidelines
Safety Evaluation Guidelines
Safety Design Guidelines
Dose-objectives Guidelines
Priority Classification Guidelines
ECCS Performance Evaluation Guidelines
Meteorological Guidelines for Safety Analysis
Reactivity Initiated Event Evaluation Guidelines
PWR Core Thermal Design Evaluation Guidelines
Dose Target Evaluation Guidelines
Radioactive Material Emission Measurement Guidelines
Fire Protection Guidelines
Seismic Design Guidelines
Radiation Measurement Guidelines
Law and RegulationLaw and Regulationfor Construction of Nuclear Power Plantsfor Construction of Nuclear Power Plants
Law and RegulationLaw and Regulation
48
<Site Evaluation Guidelines>Purpose To confirm Adequacy of isolation between Reactor and Public in AccidentCriteria
Major Accident accidents which may occur in the worst case from technical point of viewHypothetical Accident accidents exceeding major accidents which may not occur from technical
point of view
Safety ExaminationSafety Examination [[ Site Evaluation GuidelinesSite Evaluation Guidelines ]]
Power Station
The area where radiation hazard may occur if people stayed in the area continuously in case of a major accident.
Non-residential Area
Low Population Zone(Power Station Site)
The area where appropriate measures can be taken to project the public from radiation in case of a hypothetical accident.
Residential Area
High Population Area
The non-residential area and low population zone are included in the site of the power station.(There are no residents in these areas in Japan.)
Collective doses; 20,000man-Sv or less
Adults thyroid exposure doses; 3Sv or lessAccidents
Whole body exposure doses; 0.25Sv or lessHypothetical
Infants thyroid exposure doses; 1.5Sv or lessaccidents
Whole body exposure doses; 0.25Sv or lessMajor
May contain JAPC’s proprietary information. Subject to JAPC’s prior written consent before using for any other purposes than originally intended or before disclosing to any third party.
Preparation for ConstructionPreparation for Construction
49
Safety Design Guidelines (1)Safety Design Examination Guideline for
Power-generating LWR Facilities
No. Requirement
1 Compliance to Codes & Standards
2 Consideration of Natural Phenomena (Earthquake, Flooding, Tsunami, Wind,Snow, etc.)
3 Consideration of External Events (Physical Protection, Airplane, etc. )
4 Internally Generated Missile (Pipe Break, Rotating Equipment, Explosion, Fall, etc.)
5 Fire Protection (Prevention, Detection, Extinguish, Mitigation of damage)
6 Environmental Conditions for Equipment
7 Sharing Facilities (Maintain safety when facilities are shared by two or more reactors)
8 Man-machine Interface (Proper measures to prevent operators’ errors)
9 Reliability of Safety Facilities (Redundancy or diversity and Independency, Emergency Power Supply)
10 TestabilityMay contain JAPC’s proprietary information. Subject to JAPC’s prior written consent before using for any other purposes than originally intended or before disclosing to any third party.
Preparation for ConstructionPreparation for Construction
50
Safety Design Guidelines (2)Safety Design Examination Guideline for
Power-generating LWR Facilities
No. Requirement
11-18 Reactor & Reactor Shutdown System (Fuel Integrity, One Rod Stack Margin, Diversity of Shutdown System, etc.)
19-27 Reactor Coolant System(Integrity of RCPB, RCPB Leak Detection, Reactor Make-up, Residual Heat Removal, Emergency Core Cooling, Heat sink, Station Black Out, etc.)
28-33 Reactor Containment System (Integrity of Containment Boundary, Isolation Valves, Containment Heat Removal, In-containment Atmosphere Control, etc.)
34-40 Safety Protection System(Redundancy and Independency, Fail-safe, Separation from Normal Control System, etc.)
41-46 Control room & Technical Support Center(Plant Monitoring & Control Function, Remote Shutdown from other place, Comfortableness of control room, Technical Support Center, Communication Equipment, etc.)
(RCPB : Reactor Coolant Pressure Boundary)May contain JAPC’s proprietary information. Subject to JAPC’s prior written consent before using for any other purposes than originally intended or before disclosing to any third party.
Preparation for ConstructionPreparation for Construction
51
Safety Design Guidelines (3)Safety Design Examination Guideline for
Power-generating LWR Facilities
No. Requirement
47-48 Control System & Electric System
49-51 Fuel Storage System & Fuel Handling System
52-55 Radioactive Waste Treatment System
56-59 Radiation Protection & Control
May contain JAPC’s proprietary information. Subject to JAPC’s prior written consent before using for any other purposes than originally intended or before disclosing to any third party.
Preparation for ConstructionPreparation for Construction
52
Dose-objective GuidelinesGuideline for Dose-objective in the Vicinity of
LWR Facilities for Power Generation
Basic Philosophy Dose Limit for Public : 1mSv/y (← prescribed in the Law)
As low as reasonably achievable
Dose Objective : 0.05mSv/y
Assessment Condition
- Public near the P/S (considering future community formation)
- Radiation Source : Gaseous radioactive waste (noble-gas, iodine) Liquid radioactive waste - External Dose / Internal Dose (Food Chain)
(About 1/50 of annual exposure from natural radiation sources)
Target for dose reduction effort of Utilities
Preparation for ConstructionPreparation for Construction
≦0.05mSv/yNatural Radiation 2.4mSv/y
May contain JAPC’s proprietary information. Subject to JAPC’s prior written consent before using for any other purposes than originally intended or before disclosing to any third party.
53
2nd Public Hearing
In the period of the safety examination by Nuclear Safety Commission (NSC), called the second examination (the double check), NSC holds the 2nd public hearing to consider the opinions of local communities on the safety examination of the plant.
May contain JAPC’s proprietary information. Subject to JAPC’s prior written consent before using for any other purposes than originally intended or before disclosing to any third party.
Preparation for ConstructionPreparation for Construction
54
Pla
nnin
gP
repa
ratio
n fo
rC
onst
ruct
ion
Con
stru
ctio
nO
pera
tion
Utilities Government Local Community
Site SelectionEnvironmentalExamination
Opinions ofinhabitants
1st PublicHearing
Advisory Committee for Resource & Energy
Decision on basic program of power development
Local Governor’s
Consent
Safety Examination 2nd PublicHearing
Opinions ofinhabitants
Reactor Installation LicenseApplication for
Construction Plan Construction Permit (approval of Construction Plan)
WeldingInspection
Pre-serviceInspection
Fuel Inspection
Start ofOperation
PeriodicalInspection
SafetyInspection
PeriodicalSafety Review
EnvironmentalSurvey
EnvironmentalAssessment
May contain JAPC’s proprietary information. Subject to JAPC’s prior written consent before using for any other purposes than originally intended or before disclosing to any third party
Procedural Steps for NPP ConstructionProcedural Steps for NPP Construction
Start ofConstruction
Application for Reactor Installation
License
Approval of Operational Safety Program
Application for Operational
Safety Program
55
Examination of Detailed DesignExamination of Detailed Design
-The utility is required by EUIL to obtain an approval for detailed design and the construction plan of the plant from METI before fabrication and construction.
Approval of Construction Plan (Construction Permit)
- These applications are usually submitted on the separate basis in accordance with the schedule of fabrication of each component and construction at site.
Generally, the first application that covers the construction of the reactor building and the installation of reactor containment is submitted to METI.
May contain JAPC’s proprietary information. Subject to JAPC’s prior written consent before using for any other purposes than originally intended or before disclosing to any third party.
Preparation for ConstructionPreparation for Construction
56
Construction PermitConstruction Permit(Approval of Construction Plan)(Approval of Construction Plan)
METI(Examinations)
Application for approval of construction plan
Advisory Committee on Technical Matters
Approval of Construction(Construction Permit)
Explanations
Comments
Utility
UtilityStart of Construction
JNES(ex-NUPEC)(Audit Analysis)
Instructions
Experts
May contain JAPC’s proprietary information. Subject to JAPC’s prior written consent before using for any other purposes than originally intended or before disclosing to any third party.
Preparation for ConstructionPreparation for Construction
57
Pla
nnin
gP
repa
ratio
n fo
rC
onst
ruct
ion
Con
stru
ctio
nO
pera
tion
Utilities Government Local Community
Site SelectionEnvironmentalExamination
Opinions ofinhabitants
1st PublicHearing
Advisory Committee for Resource & Energy
Decision on basic program of power development
Local Governor’s
Consent
Safety Examination 2nd PublicHearing
Opinions ofinhabitants
Reactor Installation LicenseApplication for
Construction Plan Construction Permit (approval of Construction Plan)
WeldingInspection
Pre-serviceInspection
Fuel Inspection
Start ofOperation
PeriodicalInspection
SafetyInspection
PeriodicalSafety Review
EnvironmentalSurvey
EnvironmentalAssessment
May contain JAPC’s proprietary information. Subject to JAPC’s prior written consent before using for any other purposes than originally intended or before disclosing to any third party
Procedural Steps for NPP ConstructionProcedural Steps for NPP Construction
Start ofConstruction
Application for Reactor Installation
License
Approval of Operational Safety Program
Application for Operational
Safety Program
58
- excavation of building foundation
- reinforced concrete works of reactor building’s base mat- primary containment Vessel works- other building works
- installation of reactor vessel
- installation of piping and equipment- installation of core internals- cold / hot function test- fuel loading
- startup test
Major Activities in the construction of NPPMajor Activities in the construction of NPP
May contain JAPC’s proprietary information. Subject to JAPC’s prior written consent before using for any other purposes than originally intended or before disclosing to any third party.
Stage of ConstructionStage of Construction
59
Phase Ⅰ Phase Ⅱ Phase Ⅲ Phase Ⅳ
▽ Start of ConstructionStart of Commercial Operation ▽
Preparatory Work(Site Preparation)
Flow of Construction Works (Example of PWR Plant) Flow of Construction Works (Example of PWR Plant)
▽ Fuel Loading
May contain JAPC’s proprietary information. Subject to JAPC’s prior written consent before using for any other purposes than originally intended or before disclosing to any third party.
Stage of ConstructionStage of Construction
●
60
Pla
nnin
gP
repa
ratio
n fo
rC
onst
ruct
ion
Con
stru
ctio
nO
pera
tion
Utilities Government Local Community
Site SelectionEnvironmentalExamination
Opinions ofinhabitants
1st PublicHearing
Advisory Committee for Resource & Energy
Decision on basic program of power development
Local Governor’s
Consent
Safety Examination 2nd PublicHearing
Opinions ofinhabitants
Reactor Installation LicenseApplication for
Construction Plan Construction Permit (approval of Construction Plan)
WeldingInspection
Pre-serviceInspection
Approval of Operational Safety Program
Fuel Inspection
Start ofOperation
PeriodicalInspection
SafetyInspection
PeriodicalSafety Review
EnvironmentalSurvey
EnvironmentalAssessment
May contain JAPC’s proprietary information. Subject to JAPC’s prior written consent before using for any other purposes than originally intended or before disclosing to any third party
Procedural Steps for NPP ConstructionProcedural Steps for NPP Construction
Start ofConstruction
Application for Operational
Safety Program
Application for Reactor Installation
License
61
- EUIL requires the pre-service inspection by METI at each stage of the fabrication and construction.
- METI confirms that the utility has been conducting construction works in compliance with the construction plan and technical standards, and that the plant has adequate performance as prescribed in the construction plan and other licensing documents.
Pre-service InspectionPre-service Inspection
May contain JAPC’s proprietary information. Subject to JAPC’s prior written consent before using for any other purposes than originally intended or before disclosing to any third party.
Stage of ConstructionStage of Construction
62
Pre-Service InspectionPre-Service Inspection
TEST ITEM
CRITERIA(1) Accordance with the construction plan(2) Not such that facilities do not conform to the technological standards
Stage (a)
Stage (b)
Stage (c)
Stage (d)
Stage (e)
When the situation allows to test the structure, strength, or leakage of each facilities
When the installation of the lower part of the steam turbine cabin or main unit of the auxiliary boiler is completed
When the situation allows to load fuels
When the Reactor reaches criticality
When all the works stated in the construction plan is completed
May contain JAPC’s proprietary information. Subject to JAPC’s prior written consent before using for any other purposes than originally intended or before disclosing to any third party.
Stage of ConstructionStage of Construction
63
May contain JAPC’s proprietary information. Subject to JAPC’s prior written consent before using for any other purposes than originally intended or before disclosing to any third party
FactoryInspection
InstallationInspection
Equipment unitexamination
SystemFunction test
Heat uptest
On powertest
Stage (a),(b) Stage (a) Stage (c) Stage (d),(e) Stage(e)
QualityManagement
WeldingInspection
FuelInspection
Pre-servicePre-serviceinspectioninspection
Stage of ConstructionStage of Construction
Major Regulatory Inspections in NPP Construction
Pre-Service InspectionPre-Service Inspection
HFTCFT
Fuel Loading
Factory Site
Major Activities of Utility & Manufacturer
64
(c)Pressurizer Safety Valve Function Test (FT)RCS Pressure/Level Control System FTChemical Volume Control System FTSafety Injection System FTResidual Heat Removal System FTComponent Cooling Water System FTMain Steam Safety Valve FTMain Steam Relief Valve FTSafety Protection System FTCore Instrumentation System FTReactor Make-up System FTFuel Handling System FTSFP Purification & Cooling System FTRadiation Monitoring Facility FTHVAC System FTRadioactive Waste Treatment System FT Containment Spray System FTContainment Isolation Valve FTReactor Containment FTMain Feedwater System FTAuxiliary Feedwater System FTEmergency Power Supply System FTTotal Facility Inspection FT
(d) Fuel Loading TestControl Rod Drive Mechanism TestPressurizer Spray TestControl Rod Control Range Confirmation TestTotal Interlock TestModerator Temperature Efficiency MeasurementMinimum Shutdown Margin Boron Concentration Measurement
Critical Boron Concentration Measurement
(e) Load Reduction TestPlant Trip TestLoss of Offsite Power TestGenerator Load Loss TestTotal Load Test
Pre-Service InspectionPre-Service Inspection
May contain JAPC’s proprietary information. Subject to JAPC’s prior written consent before using for any other purposes than originally intended or before disclosing to any third party.
Stage of ConstructionStage of Construction
65
Prior to the startup of the reactor, the utility, pursuant to the LRNR*, establishes the operational safety program to adequately prevent accidents that may arise from the operation of the nuclear power plant. The operational safety program must be authorized by METI.
May contain JAPC’s proprietary information. Subject to JAPC’s prior written consent before using for any other purposes than originally intended or before disclosing to any third party.
Stage of ConstructionStage of Construction
* The Law on the Regulation of Nuclear Source Material, Nuclear Fuel Material and Reactors
Operational Safety ProgramOperational Safety Program
66
Design and Construction Schedule of NPP in JAPANDesign and Construction Schedule of NPP in JAPAN
May contain JAPC’s proprietary information. Subject to JAPC’s prior written consent before using for any other purposes than originally intended or before disclosing to any third party.
▼▼▼ ▼ ▼
- - - - - - - - - -
▼
▼
139 10 11 125 6 7 84321
Safety ExaminationEnviron.Assess.
Environ. Scope Assess.
#1 #2 #6 to 8
Construction Permit
Preparation for construction
Decision of site and start construction (Electric Power Development Coordination Council)
Basic Site Plot Plan / GA Study Examination by METI & NSC/AEC
R/B,C/B,A/B Structure Case Study
NSSS/BOP basic system design
Safety Analysis & Safety Document
Environ. Survey
R/B,A/B Seismic Analysis & Design
Detail Plot Plan / GA design
Detailed Design of NSSS / BOP system / equipment
Equipment installation (on site)
Functional Test
Excavation work
Pre-Service inspection
CommercialOperation
Fuel Loading
Bed Lock Inspection
material properties, welding, fabrication, installation and functional test, etc.
material procurement, processing, fabrication of equipment
Documents (structure design, seismic Integrity, Quality Management, etc.)
PCCV Construction
Civil ConstructionLeak Rate Test
CFT
Example
Welding Safety Management inspection
HFT
May contain JAPC’s proprietary information. Subject to JAPC’s prior written consent before using for any other purposes than originally intended or before disclosing to any third party
END
Appendix
May contain JAPC’s proprietary information. Subject to JAPC’s prior written consent before using for any other purposes than originally intended or before disclosing to any third party
Basic Policy of the reform on Nuclear Regulatory Organizations and Lows
2013The Japan Atomic Power Company
The following materials may contain JAPC’s proprietary and confidential information; and all or any part of these materials or information contained herein may NOT be used for any purposes other than originally intended or may NOT be reproduced, disclosed, transferred, distributed or in any manner transmitted in any tangible, electronic or any other form to any third party without prior written consent thereto by JAPC.
May contain JAPC’s proprietary information. Subject to JAPC’s prior written consent before using for any other purposes than originally intended or before disclosing to any third party
Background2011/03/11 : The Great East Japan Earthquake, tsunami and
Fukushima No.1 NPP accident happened
2011/08/15 : The Cabinet of Japanese government decided “the
basic policy of the revision on nuclear regulatory organizations
and related matters.
2012/01/31:The Cabinet decided “nuclear regulatory organizations
and lows reform act draft”
2012/06/20:The enactment of the reform act above is passed by
the Diet.
2012/09/19:The new nuclear regulatory organizations and lows
reform system were activated
May contain JAPC’s proprietary information. Subject to JAPC’s prior written consent before using for any other purposes than originally intended or before disclosing to any third party
Basic points of the reform on this nuclear regulatory system
1.The clear Separation between utilization and regulation
“Nuclear safety and Industrial Agency” is separated from “Ministry of Economy
Trade and Industry” and adds the function of Nuclear Safety Committee, and
“Nuclear Regulation Authority ” was established.
2. Integration
Nuclear safety regulations are divided in several organizations, so they haven’t
been worked effectively so those works are interrogated in Nuclear Regulation
Authority to enhance the function of nuclear safety
3.Crisis Management
Nuclear Regulation Authority positions crisis management in initial response for
accidents as their important task and arrange their system for that.
4.Development of Human Resources
Making much efforts to secure high quality human resource without regarded to
public or private sectors to make sure works in the new agency.
5.New safety regulation
Reviewing adequate regulations and related system such as introducing new
regulatory constructers based on the accident at Fukushima NO.1
NRA( Nuclear Regulation Authority )
May contain JAPC’s proprietary information. Subject to JAPC’s prior written consent before using for any other purposes than originally intended or before disclosing to any third party
Cabinet
Office
Outline of the new organization System
Atomic
Energy
Commission
Nuclear
Safety
Commission
Nuclear and
Industrial Safety
Agency
METI
Ministry of
Economy
Trade Industry
The conventional Nuclear Safety regulatory organization
The new Nuclear Safety regulatory organization
Nuclear
Security
Double
Check
Ministry
of Education
Culture
Sports
Science and
Technology
Regulation
against
NPP
Regulation
against Test
Reactor
METI
Securing Independence of
Regulations
Realizing objective and
scientific Regulations
Separation Use & Regulations
Integration on Nuclear Safety
Enhancing Emergency
Ministry of Environment
TheSecretariat
of the NRA
Pla
nnin
gP
repa
ratio
n fo
rC
onst
ruct
ion
Con
stru
ctio
nO
pera
tion
METI
Environmental Examination
Decision on basic program of power development
Safety Examination PublicHearing
Reactor Installation License
Construction Permit (approval of Construction Plan)
Welding Inspection
Fuel Inspection
PeriodicalInspection
SafetyInspection
PeriodicalSafety Review
May contain JAPC’s proprietary information. Subject to JAPC’s prior written consent before using for any other purposes than originally intended or before disclosing to any third party
Procedural Steps for NPP ConstructionProcedural Steps for NPP Construction
Approval of Operational Safety Program
NRA
Pre-serviceInspection
Pre-serviceInspection
Construction Permit (approval of Construction Plan)