1 Progress of, and prospects for, commercial applications of UHV 1100kV Transmission System in TEPCO...
-
Upload
beatrix-gregory -
Category
Documents
-
view
212 -
download
0
Transcript of 1 Progress of, and prospects for, commercial applications of UHV 1100kV Transmission System in TEPCO...
1
Progress of, and prospects for, Progress of, and prospects for, commercial applications of UHV commercial applications of UHV 1100kV Transmission System in 1100kV Transmission System in TEPCOTEPCO
2nd International Symposium on International Standards for Ultra High Voltage, New Delhi, January 29-30, 2009
Hiroshi OKAMOTO
TEPCO
2
UHV Transmission Lines in TEPCO
〈〈 North-South RouteNorth-South Route 〉 〉 [1993][1993]Minami-Nigata LineMinami-Nigata Line: : 49km49km×2cct×2cct (Total Length: 111km)(Total Length: 111km)
Nishi-Gunma Line: Nishi-Gunma Line: 138km138km×2cct×2cct
〈〈 East-West RouteEast-West Route 〉 〉 [1999][1999]Minami-Iwaki LineMinami-Iwaki Line: : 194km194km×2cct×2cct
Higashi-Gunma LineHigashi-Gunma Line: : 44km44km×2cct×2cct
〈〈 North-South RouteNorth-South Route 〉 〉 [1993][1993]Minami-Nigata LineMinami-Nigata Line: : 49km49km×2cct×2cct (Total Length: 111km)(Total Length: 111km)
Nishi-Gunma Line: Nishi-Gunma Line: 138km138km×2cct×2cct
〈〈 East-West RouteEast-West Route 〉 〉 [1999][1999]Minami-Iwaki LineMinami-Iwaki Line: : 194km194km×2cct×2cct
Higashi-Gunma LineHigashi-Gunma Line: : 44km44km×2cct×2cct
3
UHV System DesignUHV System Design
Secondary arc extinction for fast reclosing, etc.Secondary arc extinction for fast reclosing, etc.
Size reduction of UHV transmission towerSize reduction of UHV transmission tower
Electric and Magnetic field, corona noise, wind noiseElectric and Magnetic field, corona noise, wind noise
Rationalization of insulation coordinationRationalization of insulation coordination
Transmission line Transmission line designdesign
Insulation Insulation designdesign
Solution for network problem peculiar to Solution for network problem peculiar to UHV systemUHV system
Size reduction of substation equipmentSize reduction of substation equipment
Development of highly reliable equipmentDevelopment of highly reliable equipment
Substation Substation designdesign
High Speed Grounding Switch(HSGS)
MOSA, CB with resistor
4
Issues to be addressedIssues to be addressedin voltage upgradein voltage upgrade
To reduce annual capital expenditure below a certain rational level,
To ensure flexibility under uncertainty in the development of power plants,
To reduce a risk of degradation of reliability during the construction period for upgrading, and
To shorten the planned outage of transmission lines during the construction.
5
Schematic diagram of UHV designed transmission lines
~U5 U1
200km40km50km
140km
~~
~
~
U2
UN
U3
6
Option 1
1100kV circuit
550kV circuitU1U5
3 or 4.5GVA
550kV 550kV
1100kV circuit
550kV circuitU1U5
3 or 4.5GVA
550kV 550kV
Only single circuit will be operated at 1100kV and the other circuit at 550kV in the very first stage of the upgrading.
7
Studied Issues
a. switching overvoltage induced in 1100kV and 550kV circuits,
b. lightning overvoltage in the substations,c. short circuit phenomena between 1100kV and 550kV
circuits,d. necessity of HSGS in the 550kV circuit to extinguish
secondary arc current after the fault in the circuit,e. operation and maintenance considering outage of eq
uipment,f. protection,g. TRV andh. voltage deviation due to energization and de-energiz
ation
8
Option 2Simplified bus configuration may be applied as a cost-effective solution for line U1-U5 only if the subsequent upgrade is not expected over the long term.
U1U5
bypass circuit550kV 550kV
U1U5
bypass circuit550kV 550kV
9
Switching Overvoltage Analysis
simplified bus configurationdouble-bus-bar four-bus-tie configuration
U1
U5
U1
U5
10
Option 3
Double T connection at U2 S/S, instead of double connection, can reduce the installation cost.
U1U5U2
U3
U1U5U2
U3
11
Concluding RemarksTEPCO is now studying the issues for upgrading the operating voltage of the constructed UHV transmission lines from 550kV to 1100kV.
We will finalize technical specification of substation equipment shortly so as to be able to respond quickly and flexibly to future generation developments.
In this context, standardization of the UHV technology is urgently needed.