1 Planning Reserve Margin Dan Egolf Senior Manager, Power Supply & Planning.
-
Upload
dorcas-webb -
Category
Documents
-
view
212 -
download
0
Transcript of 1 Planning Reserve Margin Dan Egolf Senior Manager, Power Supply & Planning.
1
Planning Reserve Margin
Dan Egolf
Senior Manager, Power Supply & Planning
2
Resource Adequacy Requirements
• Planning Reserve Margin (PRM): power supply buffer that allows a utility to reliably serve customers
• Three primary drivers:
• Dependent on resource portfolio and is utility-specific
• Industry standard is Loss-Of-Load-Expectation (LOLE) of 1 day in 10 years
Resource forced outages
Increased demand due to
weather
Higher than expected load
growth
3
What is Planning Reserve Margin (PRM)?
• Extra capacity
• Not having enough won’t get the job done
• Having too much is costly
• Shown in MW or percentage
• Lots of different ways of measuring it
• No “one size fits all” solution
• Are additional resources required?
• Our study is based on 2012 Load Forecast and information
4
So What’s the Problem?• A basic assumption is that enough resources exist to meet the load
• Do we really need PRM?
- Load Uncertainty
A. Short-term weather-related
B. Long-term load growth
- Resource Uncertainty
A. Generation risk
B. Contract risk
C. Market risk
• With perfect knowledge far enough in advance, PRM wouldn’t be needed
• Every utility’s situation is different
5
How do we evaluate PRM?• This requires two steps:
1. Measurement Options:
- Loss of Load Expectation (LOLE, in days per year)
- Loss of Load Hours (LOLH, in hours per year)
- Expected Unserved Energy (EUE, in MWh per year)
- Loss of Load Probability (LOLP, in %)
2. Methodology Approaches:
- Older rule-based
- Modern probabilistic Monte Carlo based
• FBC is using LOLE of 1 day in 10 years, or 0.1 day per year using a Monte Carlo simulation
6
Risk Assumptions• Load uncertainty
- Long-term load uncertainty is covered as part of the load forecast
- Short-term weather has a significant impact on loads and the timing of the peak load is particularly risky
• Generation Risk
- Required operating reserves are part of PRM
- Unit Forced Outage Rate (FOR) based on historical data or reasonable assumptions
• Contract Risk: PPA assumed to have no risk
• Market Risk (Short-Term)
- Market access of 150 MW is assumed
- Transmission Forced Outage Rate of 0.74%
7
Results: LOLE in the Base Case
Year Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec AnnualWinter
PRM
%
2014 0.000 0.000 0.002 0.000 0.000 0.001 0.002 0.004 0.000 0.000 0.002 0.005 0.016 27%
2015 0.002 0.000 0.015 0.000 0.000 0.001 0.000 0.000 0.000 0.000 0.000 0.006 0.024 26%
2016 0.002 0.000 0.001 0.000 0.000 0.002 0.002 0.000 0.000 0.000 0.000 0.009 0.016 26%
2017 0.002 0.000 0.001 0.000 0.000 0.001 0.000 0.000 0.000 0.000 0.000 0.005 0.009 26%
2018 0.000 0.001 0.000 0.000 0.006 0.006 0.001 0.000 0.000 0.000 0.000 0.002 0.016 25%
2019 0.002 0.000 0.000 0.000 0.003 0.005 0.003 0.000 0.000 0.000 0.000 0.007 0.020 25%
2020 0.001 0.000 0.000 0.001 0.001 0.004 0.002 0.000 0.000 0.000 0.000 0.006 0.015 25%
2025 0.000 0.001 0.001 0.001 0.000 0.012 0.003 0.000 0.000 0.000 0.000 0.003 0.021 24%
2030 0.000 0.002 0.000 0.000 0.000 0.007 0.001 0.000 0.000 0.000 0.000 0.014 0.024 23%
2033 0.001 0.002 0.000 0.000 0.000 0.003 0.001 0.000 0.000 0.000 0.000 0.023 0.030 23%
• LOLE 0.1 day per year met in all years
• PRM is about 25%
8
Results: Cases for Sensitivity AnalysisCase Description Meet LOLE Target?
Load Sensitivity Analysis
Case 1 1-in-10 economic drivers
Case 2 Industrial self-generating demand of 40 MW
Case 3 Time of seasonal peaks
Resource Sensitivity Analysis
Case 4 WAX FOR
Case 5 Double FOR
Case 6 No WAX surplus taken into account for PRM requirements
Case 7 No additional capacity planned for gaps expected gaps must be met
Market Sensitivity Analysis
Case 8 Market sizes at the base case FOR
Case 9 No market access alternative capacity needed
Case 10 Market FOR at 150 MW
9
Next Steps
• We can present a detailed ½ day technical workshop on PRM if there is interest
• Our PRM Report will be updated and included as part of the 2016 Long Term Electric Resource Plan
• Questions?