1 PFP QSR, 4/19/2011 Particles and Fields Package Quarterly Status Review (QSR) April 19, 2011 Dave...
-
Upload
melina-malone -
Category
Documents
-
view
212 -
download
0
Transcript of 1 PFP QSR, 4/19/2011 Particles and Fields Package Quarterly Status Review (QSR) April 19, 2011 Dave...
1PFP QSR, 4/19/2011
Particles and Fields PackageQuarterly Status Review (QSR)
April 19, 2011
Dave Curtis, PFP PM
2PFP QSR, 4/19/2011
SSL Contracting Status
• Funded through the end of April• More info in the Business Splinter presentation
3PFP QSR, 4/19/2011
Schedule Status
• EMs have made a lot of progress this month– All EM PWBs in test but ~2 (HVPS boards, in fab)– SEP, LPW, SWEA, MAG EM mechanical assembly complete– STATIC EM TDC complete random vibe– SWIA/STATIC analyzers parts out to fab
• EM Package I&T in progress– LPW, SEP, SWEA test with PFDPU complete– EM ‘Early Payload Test’ with LM complete– MAG next week– Pushing to complete before CDR– EM Instrument calibrations don’t complete till after Package I&T
• STATIC is on critical path– 13.6 weeks margin to delivery– Driven be delays in EM I&T
• Status at instrument CDR – SWIA, STATIC EM will not be complete– SWIA, STATIC attenuator life test not done– SWIA, STATIC power converters may still be in test– Rest of instrument EM will be complete, with perhaps some system
level test still in progress
4PFP QSR, 4/19/2011
Manpower
• RBSP-EFW instrument still not delivered – this month?– A number of problems encountered in thermal vacuum– Resolving those problems have impacted MAVEN power
converter team, delayed STATIC & SWIA
• We are still under planned FTE rate– but climbing a bit– Mostly due to people splitting time between projects
• Note that 100% activity is often more than 40 hours/week in these cases
– Plan was based on conservative assumptions about covering people
5PFP QSR, 4/19/2011
Accomplishments
• LPW, SEP, SWEA EM integrated with PFDPU EM• PFDPU EM Early Payload test with Spacecraft EM• SWEA Peer Review Completed• STATIC Random Vibration Completed• SEP Attenuator Life Test Completed
• More in instrument sections…
6PFP QSR, 4/19/2011
Ongoing Work
• Supporting Project planning process• Supporting EMC, Payload, SDT working groups
• Completing EM board testing• Completing SWIA/STATIC EM mechanical part
fabrication• Complete PF Package EM I&T• Prepare for CDR
7PFP QSR, 4/19/2011
EM Status
Required for I/F Testing at LM
In Lay-out
In Fab / Assembly
In Test
Integrated to chassis
Not Required for EM
Ready for Test
Test Completed
Ready to Integrate
REG1
DCB1
REG2
DCB2
IIB
SEP1
MAG1
LPW BEB
LPW DFB
LPW 1
EUV
MAG 1
STATIC
SWEAtt
SWIA
PFP
Flash FPGA***
LVPS
LVPS
DIG
Sweep
Preamp + MCP
Anode
LVPS
ACC + MCP
Anode
TDC
Preamp
DAP
SEP1
DFE
DFE
MAG HTRT
Preamptt
Anode
tt
HVPStt
PFDPU
Flash FPGA***
Flash FPGA***
Preamp
Sweep
DIG
DIG
Preamp
IF TesT3 /15/11
8PFP QSR, 4/19/2011
PFP RFA Status
Review Actions Closed %SWEA Peer 20 20 100%
Mechanical Peer 8 8 100%Analyzer Peer 11 11 100%Power Peer 0Digital Peer 4 4 100%FSW Peer 0LPW Peer 11 11 100%MAG Peer 5 5 100%
LPW Mech Peer 7 7 100%
IPDR 6 6 100%
Totals 72 72 100%
All Done!
9PFP QSR, 4/19/2011
Trades, Issues
• HV801 issue still open– Current plan is to buy HV801s from LADEE NMS, who has parts
on order they no longer need.– We still don’t have the parts in hand
• Working on an analysis to decide if the PFDPU mechanical design needs to be augmented to support the PWBs to avoid excessive displacements in vibe– Analysis complete, passed on to GSFC expert for review.
• LPW Stacer Plating issue (NEW)– After plating stacer with black Nickel it no longer stows properly– Need plating for thermal reasons (aeroheating, thruster heating)– Historically we have used a paint (DAG213), but that will not
survive atomic oxygen at Mars– Working with GSFC Materials on possible solutions
10PFP QSR, 4/19/2011
Thermal Status
• Received ‘Thermal Memos’ as well as spacecraft thermal model
• Some of the instruments are in trouble according to the thermal memo– For example, STATIC goes to -100C
• We are working on identifying if the issue is the model or the design– Our preliminary results are more benign
11PFP QSR, 4/19/2011
Top Risks
P-20 reduced (mating procedure)
MAVEN PFP RISK MANAGEMENT Chg RANK ID Approach TITLE
55 10 15 20 25
1 P-17 Mitigate Parts Qualification
44 8 12 16 20
2 P-01 Mitigate SSL Manpower
33 8 9 12 15
3 P-21 Mitigate PFP to Spacecarft ICD
22 4 6 8 10
4 P-20 Mitigate PFDPU Connectors
11 2 3 4 5
5 P-18 Watch Magnetics Implementation
1 2 3 4 5
Criticality Approach
High
Medium
Low
LIKELIHOOD
Improved
Worsening
Unchanged
New this month
Mitigate
Watch
Accept
Research
CONSEQUENCES
L * C Trend
*
P01
P18
P20 P21
P17
12PFP QSR, 4/19/2011
Risks ListID Title Type P I Crit Risk Statement Impact Term Plan Approach Comments
P-01 SSL ManpowerProject
Execution3 2 M
Delays in RBSP leads to manpower conflicts at SSL
Schedule erosion, cost to recover
Near Term
Hire new people to take routine tasks off key personnel
Mitigate Review in March 2010Add extra Power Converter person 1/2010Add extra ME 2/2010Add extra QA 8/2010Add extra Tech & Test Engineer 1/2011Tap into campus technician pool 2/2011
P-07Delayed LPW
Boom Deployment
Mission Performance
1 3 L
Waiting till after MOI to deploy LPW booms results in them sitting undeployed for over a year, increasing the risk of deployment failure
Potential severe degradation of LPW measurement
Far Term
Investigate if LPW booms can be deployed early
Research Early deployment of LPW booms reduces this risk. Actual risk of failure is very low. Risk that we may be asked to do an expensive verification is moderate
P-14 HV801 ProblemProject
Execution1 3 L
If HV801 not available a redesign would be required to use alternate (larger) parts
Schedule, Mass Near Term
Watch what programs ahead of MAVEN do; look into alternate parts
Mitigate Micropak alternate part in test. EM parts found, FM parts identified
P-17Parts
QualificationProject
Execution3 3 M
If parts fail qualification then system would have to be redesigned for alternate (which may also have to be qualified and may have lower performance)
Schedule, Cost, Performance
Near Term
Start parts qualification as soon as possible (but delayed to FY11 for funding)
Mitigate First round of parts radiation testing started. SEL test results look good
P-18Magnetics
ImplementationMission
Performance1 4 L
If unanticipated magnetics issues are found on observatory late (or not found at all) then MAG instrument performance could be degraded
Magnetics [MRD84]
Mid Term
Magnetics Working Group to monitor implementation (materials lists, etc)
Watch
P-19Electrostatics
ImplementationMission
Performance1 4 L
If unanticipated electrostatic issues are found on observatory late (or not found at all) then LPW, SWEA, SWIAm, instrument performance could eb degraded
Electrostatics [MRD 83]
Mid Term
Magnetics Working Group to monitor implementation (materials lists, etc)
Watch
P-20PFDPU
ConnectorsProject
Execution2 2 L
If fragile flight PFDPU connectors damaged then PFDPU schedule will be delayed by rework
Schedule Mid Term
Look for ways to protect pins - connector savers? Working on a plan
Mitigate Improved mate procedure reduces risk
P-21PFP to
Spacecarft ICDProject
Execution2 3 L
If the instrument FSW interpretation of the ICD does not match the Spacecraft interpretation then the instrument will not work at integration, requiring a PROM change to fix (and PFDPU requal)
Schedule Far Term
Work with LM on clarifying the ICD.
Mitigate Early Payload Test reduces risk on hardware side.
13PFP QSR, 4/19/2011
PFP Mass
• CCR262 approved to reallocate NTE amongst PFP
InstrumentCBE
Total [kg] Cont. (%)Total [kg] (CBE+cnt)
Particles and Fields 23.74 15.3% 27.37LPW Total 6.18 15.2% 7.12
LPW Booms 5.150 15.1% 5.930EUV Assembly 1.030 15.5% 1.190
STATIC Total 2.87 15.4% 3.31SWEA Total 1.82 15.2% 2.10SWIA Total 2.59 15.2% 2.98SEP Total 1.27 16.1% 1.47MAG Total 0.84 16.2% 0.97PFDPU Total 5.89 15.0% 6.78PF Intra-Instrument Harness Total 2.29 15.5% 2.64
14PFP QSR, 4/19/2011
Mass Tracking Chart
PFP Mass Trend
10.00
15.00
20.00
25.00
30.00
35.00
10/1/2009
12/1/2009
1/31/2010
4/2/2010 6/2/2010 8/2/2010 10/2/2010
12/2/2010
2/1/2011 4/3/2011
Date
kg
10.0%
15.0%
20.0%
25.0%
30.0%
35.0%
Mass CBE, kg
Mass NTE, kg
Mass Margin %
15PFP QSR, 4/19/2011
PFP Power
• Small increase in MAG power• Small decrease in SWEA power.
Instrument CBE [W] Cont. (%) NTE [W] CBE [W] Cont. (%) NTE[W] CBE [W] Cont. (%) NTE[W]Particles and Fields
Off (heater only) 0.00 0.00 18.56 9% 20.31 18.56 9% 20.31Standby 9.22 36% 12.52 15.35 8% 16.62 24.57 19% 29.14Nominal 18.78 19% 22.29 17.32 12% 19.34 36.10 15% 41.63
Peak 30.83 20% 37.01 101.34 14% 115.70 132.16 16% 152.71Orbit Average 18.89 19% 22.39 17.32 12% 19.34 36.21 15% 41.73
Orbit Average:LPW 3.71 48% 5.49 0.00 0% 0.00 3.71 48% 5.49EUV 0.16 15% 0.18 2.30 -10% 2.07 2.46 -8% 2.25STATIC 4.39 19% 5.21 1.91 15% 2.20 6.30 18% 7.41SWEA 0.99 25% 1.24 2.95 15% 3.39 3.94 17% 4.63SWIA 2.05 22% 2.50 3.08 15% 3.54 5.13 18% 6.04SEP 2.60 -14% 2.24 5.48 15% 6.30 8.08 6% 8.54MAG 3.20 -11% 2.84 1.60 15% 1.84 4.80 -3% 4.68PFDPU 1.78 51% 2.69 0.00 0% 0.00 1.78 51% 2.69
Operational Heater Total
16PFP QSR, 4/19/2011
PFP Power Trend
PFP Power Trend
0.00
5.00
10.00
15.00
20.00
25.00
30.00
35.00
40.00
45.00
10/1/2009
12/1/2009
1/31/2010
4/2/2010 6/2/2010 8/2/2010 10/2/2010
12/2/2010
2/1/2011 4/3/2011
Date
W
0.0%
5.0%
10.0%
15.0%
20.0%
25.0%
30.0%
35.0%
40.0%
45.0%
Power CBE, W
Power NTE, W
Power Margin %
17PFP QSR, 4/19/2011
PFP Data Rate
• Per 2009-6-9 allocations from Bruce• New MAG requirements on telemetry formatting puts
MAG 4% over allocation
Rate [bps]Particles and FieldsLPW/EUV 717.0STATIC 2000.0SWEA 600.0SWIA 604.0SEP 160.0MAG 660.0PFDPU 30.0
Total 4771.0
Instrument
18PFP QSR, 4/19/2011
Requirements Verification Status
• CCR (265) to update PFP Functional Requirements (Level 3) approved– some old requirements need updating
• Verification matrix mostly complete– Have Functional, ERD, ICD requirements complete, in review
• Boot software verification has started– against software level 5 requirements, which link back to FRD
and ICD.• STATIC TOF EM Acoustics and Vibration test complete
– All but coarsest grid with thinnest foils passed– Will not use coarsest grids– Will repeat on full EM and FM
• EM Interface tests started– Reduces risk, not a qualification test
• SEP Attenuator Mechanism Life Test complete
19PFP QSR, 4/19/2011
Life Testing
• SEP Attenuator life test complete– 4100 cycles on EM twice expected life– ~1000 in air, ~3000 in vacuum– Will collect some more cycles over the next few months
• SWIA, STATIC attenuator life test pending completion of EM attenuator– ~June
• SWEA door mechanism identical to STEREO• SWEA, STATIC door mechanism functional, life test
pending• LPW relay life test expected to start soon• LPW deployment life test expected to start soon
– Stacer coating problem holding that up
20PFP QSR, 4/19/2011
MAVEN Magnetometer Status
April 2011
Connerney, Sheppard, Schnurr, Oliversen, Espley, etc.
21PFP QSR, 4/19/2011
GSFC/MAG - Accomplishments Last Month
• EM sensor assembly, pigtail, GSE sensor harness completed. • Breakout PWBs fabrication completed.• Draft MAG Flight Software Requirements Specification (for PFDPU).• Completed Safe-to-Mate procedures for MAD board (MAVEN-MAG-
PROC-0026).• Completed EM Magnetometer board scale factors calibration at GSFC
22’ MAG Test Site; scale factor resistors installed on board.• FPGA (rev 0) burned at Aeroflex, received and installed on MAD
board. Functional testing in progress.• GSE (UCB emulator) development continues; CMD and TLM
successfully flowing between GSE and MAD board.• Sensor non-magnetic heaters design received from vendor (Tayco),
under review.• Frames for MAD board and ACHE board fabricated at GSFC; boards
installed in frames (see pix).
22PFP QSR, 4/19/2011
GSFC/MAG - Accomplishments Last Month
A/C Heater Electronics (ACHE) Board in frame ->
MAG Analog and Digital (MAD) Board & frame
23PFP QSR, 4/19/2011
GSFC/MAG Near Term Plans & Open Issues
• Mature MAG software requirements draft w/UCB.• Hypertronics KPC120 connectors installation and mating issues. • Radiation test plan for MIL spec CD4066 quad bilateral switches
completed; testing scheduled to begin April 18, 2011.• Integration and test of MAG (MAD board and sensor) w/ PFDPU at
UCB scheduled April 26-28, 2011.• MAD board frame modifications (test connector placement,
mechanical mod for center board support) pending final approval.• Continue winding FM sensor ring cores, feedback/sense bobbins,
and magnetic piece parts per technician availability; fabricate sensor assembly terminal boards.
• Draft worst case analysis of MAD board.• MAG Peer Review scheduled for May 5, 2011 @ GSFC.• Workload: RBSP FM post-environmental test evaluation drags on;
Juno FM system integration work in progress @ Astrotech, KSC.
24PFP QSR, 4/19/2011
MAVEN PFP SWIA Status
April 2011
Jasper Halekas, SWIA Lead
25PFP QSR, 4/19/2011
SWIA Progress
• Electrical Progress– Anode and digital boards tested– Preamp/MCP loaded on preamp half
• Preamp half integrated and in testing with digital• MCP half delayed by RBSP
– LVPS mostly loaded, waiting for testing, delayed by RBSP– Sweep in testing
• Mechanical Progress– E-Box fabricated and assembled– Analyzer in progress
• Many major parts already out for fabrication• Final drawings being finished up
• Detector Progress– MCPs in testing
• Early results using spare THEMIS plates indicate anode board working nominally
26PFP QSR, 4/19/2011
SWIA EM Electronics & Chassis
27PFP QSR, 4/19/2011
SWIA Issues
• Staffing/Schedule– More RBSP delays hurting mechanical and power supplies– Mechanical parts may not all be done in time for peer reviews– Power supplies waiting for loading and testing
28PFP QSR, 4/19/2011
SWIA Test Data
1
2
3
45
6
7
8
9
10
11
12
13
14
15 21
22
2317
18
19
16 20 24
• Anode counts from integrated test pulser correctly counted• P0, P1, P2 data products correctly generated by FPGA
Test pulser outputdivided by four ratios, sent to alternating anodes
Pseudo Data Products
3-d Sky Plot
Energy Spectra
29PFP QSR, 4/19/2011
MAVEN PFP SWEA Status
April 2011
Dave Mitchell, SWEA Lead
30PFP QSR, 4/19/2011
SWEA Status – IRAP (CESR)
• Mechanical– Plating of external parts (Black-Ni, Gold, Alodyne) at Anoplate in New York.
• Most parts delivered to SSL on 4/5 and passed magnetic screening (< 3 nT at 1 cm before and after exposure to >10-Gauss magnetizing field)
• Black-Ni/Gold parts (lower deflector and interface tube) are delayed (expected 4/25) Mechanical assembly at IRAP delayed ~3 weeks
• Electrical: Amp, HV coupling, and HVPS boards assembled at Microtec – expecting delivery at IRAP on 4/19, then functional testing can begin.
• AIT: Facilities in large clean room are in progress as scheduled (installed rolling table and tools, vacuum chamber expected week of 4/18) on schedule for AIT
Magnetic screening station at SSL
SWEA parts plated with high-P electroless black-Ni
top cover
upper deflector toroidal grid
10 cm
31PFP QSR, 4/19/2011
SWEA Status, EM - SSL
• Mechanical: No change from last month: Pedestal fabrication and test fitting complete, ready to assemble when boards available
• LVPC: Some voltages not within spec, and one exhibits and oscillation. Board will be reworked (~2-3 weeks).
Digital
LVPS
STEREO SWEA EM front-end boards
SWEA Electronics I&T
• Digital: – Fab complete and
tested.
– Housekeeping and Data messages from FPGA verified.
– Test pulser demonstrates that counters working as expected.
– Integration with PFDPU EM and functional tests on 4/13 successful
32PFP QSR, 4/19/2011
MAVEN PFP STATIC Status
April 2011
Jim McFadden, STATIC Lead
33PFP QSR, 4/19/2011
STATIC Accomplishments
• Carbon foils mounted in TOF units survive vibration test – automated software used to evaluate foil breakage
• Ordered carbon foils on mica slides to improve mounting yield • The design of START foil grid-frames was modified to compensate for
poor clamping due to fabrication tolerances - new grid-frames ordered. • Design of attenuator motor completed, drawings for ETU in process• Energy analyzer/deflector parts drafted and ordered • EM TDC board bench testing complete, part modifications made• EM preamp 1 modified and working adequately for integration w/ TDC
board – will be used while optimized preamp board is developed • EM Anode, Preamp and TDC boards integrated – working• EM Digital board passed power and PFDPU simulator interface testing,
ready for interface test with TDC• EM Sweep HV board partly loaded and in test (see pictures)• Clean room equipment installed – racks, SS table, GN2 purge, etc.• Helmholtz coil template fabricated, waiting on welding before assembly
34PFP QSR, 4/19/2011
STATIC EM Sweep HV Board
35PFP QSR, 4/19/2011
STATIC Open Issues
• One of two TOF electrical connections broke in 1 of the 3 units during vibration test (see pics) – connection redesigned for stress relief
• Mounting fixtures for handling flight carbon foil frames need to be fabricated before additional EM carbon foils are loaded
• New START foil grid-frames will require inspections after fabrication• Preamp design changes nearly complete for optimal dynamic range –
may require new layout• EM 15kV-MCP board changed, MCP “stack stick” multiplier abandoned
in favor of a pair of VMI multipliers and a tapped transformer – EM waiting on part placement changes (Berg).
• Digital board FPGA still in development• EM LVPS loaded – waiting to be tested• Manipulator fixtures for calibration chamber testing in development• Some test harnesses and test cables still on order• New calibration chamber ordered – delivery late May• SS sink for clean room assembled – waiting for drain assembly
36PFP QSR, 4/19/2011
STATIC EM TOF Post Vib Disassembly
37PFP QSR, 4/19/2011
Post-vib broken electrical connection
38PFP QSR, 4/19/2011
Post-vib broken electrical connection
39PFP QSR, 4/19/2011
MAVEN PFP SEP Status
April, 2011
Davin Larson, SEP Lead
40PFP QSR, 4/19/2011
SEP Accomplishments2011-04-12
• Mechanical attenuator tests completed – ~4500 cycles completed (all but ~1000 in vacuum)
• Integration of DAP board (& ½ sensor sans detectors) with PFDPU begun on 2011-04-11
– Safe to mate –ok– Initial power on - ok
• but receiving +6V and -6.3 volts instead of nominal +/- 5V– Command test – ok
• Successfully turned on test pulser• Bias voltage setting not working (not yet functional on DAP?
– Telemetry tests – ok• Successful run of ‘SEP_DAPINIT’• Unbalanced analog voltages result in offset from baseline• Successful run of “SEP_THRESH_SWEEP”• Successful run of “SEP_TPSWEEP”
– Some cross talk visable that was not seen with MISG– Noise level is substantially larger and assymetric
– Timing Tests – skipped – SEP Aperture tests – ok– SEP auto aperture closure – problem on REG– SEP power inrush current test - OK
• ETU Silicon detectors (1 stack) delivered on 2011-04-12.• DAP board
– 3 channels loaded on DAP #1– 12 channels loaded on DAP #2– Actel programming: Using FPGA version 0x32
41PFP QSR, 4/19/2011
SEP PFDPU Interface Test Data
Cross talk?
Dropouts?Data collected through PFDPU in APID 30
Increased noise(and asymmetric)
42PFP QSR, 4/19/2011
Attenuator life test
• Life tests were done on 3 separate days.
• TCP/IP connection from computer to MISG was unreliable.
• Difference in actuation time is probably temperature related.
43PFP QSR, 4/19/2011
Attenuator Stroke vs. bus voltage
• Tested the range of bus voltages that would cause actuation.• Below 22 V (2.08 V across nanomuscle), actuation failed in air.
44PFP QSR, 4/19/2011
SEP Open issues
• What voltage to use for +/- 5VA supply.– Analog supply NOT currently regulated– Need secondary regulation for A250?– Eliminate requirement of 5V Digital altogether
• Mods needed for flight DAP board:– Use faster transisters on pulse generator (fixes 3.3 volt logic problem)– Use 2.5V reference instead of 5VA for baseline trim– Use Valid signal for hysteresis on peak detect– Gain change on peak detect circuit (perhaps not needed now)– Switch from 10 MΩ to 1MΩ resister on bias voltage control– 5 MΩ resistor to -5VA (-2.5R?) to correct for OpAmp input current (this mod is questionable if BLRena mode
is working properly)• Sensor
– Add detectors!!!!– Insert caps on attenuator lines to clean up some noise
• FPGA Mods from version 0x32– Eliminate secondary pulse by applying BLRena for 6 μsec on test pulse return– Extend test pulse duration from 10 μsec to 20 μsec – 16 bit counters on no peak counters– Ability to turn off housekeeping measurement– Event mode resolution
• Testing:– Purchase new nimbin and test pulser to replace AWOL test pulser– Test for correct coincidence determination with FPGA– New radiation source
• PFDPU testing– Cross talk observed in PFDPU but not MISG?– Increased Noise observed in PFDPU (probably resolved with shield boards)– Telemetry dropouts from PFDPU science packets– Possible change in opto coupler wiring of actuator control on DCB to eliminate any possibility of noise
• Baseline shift at high count rates – (probably not an issue)• 1 mv shift in baseline shortly after the 1 pps signal• More to come
45PFP QSR, 4/19/2011
MAVEN PFP DCB, Power Converter & GSE Status
April 2011
Dorothy Gordon
Timothy Quinn
Peter Berg
Chris Tiu
46PFP QSR, 4/19/2011
PFDPU/DCB Status
PFDPU Overall Integration o DCB/REG
o Functional and electrical verification ongoingo Actuator Control, Housekeeping, Instrument Current Monitoring
o DCB/REG/IIB o Verified LPW signal routing through IIB and Low Voltage Power
Supply
o DCB/REG/IIB/LPW (see next page)o Upcoming PFDPU integration tests
o Remaining power services and signal routing to be checked on a per instrument basis
47PFP QSR, 4/19/2011
PFDPU/DCB Status (2)
o DCB/REG/IIB/LPWo Tested/Verified
o Power-switch, current monitoring on REGo Operation of LPW via the Supplies IIB LVPSo LPW/DCB Interaction via serial interfaceo Operation of the EUV Door Actuator
o LPW Data analyzed for noise and anomalies
10 Hz – 4Vpk-pk 1KHz – 4Vpk-pk 100KHz – 4Vpk-pk
48PFP QSR, 4/19/2011
PFDPU/DCB Status (3)
PFDPU – S/C Interface Testo DCB/REG Verification at Lockheed-Martin
o Integrated power subsystem o Inrush current characterized o Tested S/C Discrete commands and Side Selecto Reset, TIME commands verified
o Operated PFDPU with the Lockheed-Martin Spacecraft Emulator
o Verified signal protocol of RS422 command and telemetry interfaces
o Operation with Flight Software – sent a variety of packets in order to work through the checksum generation algorithm. FSW is working this issue with Lockheed-Martin.
49PFP QSR, 4/19/2011
DCB Status
DCB ETU Buildo DCB ETU #2 Build completeo Delivered (along with FLASH FPGA daughter board)o Short on main DCB power supply (3.3V)
o Problem needs to be identified and fixed
DCB FPGAo Changes added to support the S/C interface modificationso Functional design is complete; undergoing life-test with flight
software and PFDPU Integration
50PFP QSR, 4/19/2011
GSE Hardware Status
MISG Instrument Simulator o First cut operational instrument simulator delivered
o uses the MISG-FPGA Block RAMo Implements the final Instrument Mode functionality
o covers all 8 Instrument Interfaceso with a subset of the final pattern generator buffer space
o Next Stepso Use MISG based SDRAM for Instrument Pattern storage
(allowing for increased buffer space)o Incorporate new modules into next MISG-FPGA release
51PFP QSR, 4/19/2011
GSE Software Status
• SSG– Software updated to handle special case where calculated
checksum equals zero. When this occurs checksum is set to 0xFFFF
• GSEOS– Python modules added to perform checksum processing and
verification on PFDPU telemetry – Python module added to support PFDPU Memory Loads – Delivered first rev of STATIC configuration – Created Python module for playing back raw data over TCP
link with GSEOS – Supported LPW EM integration testing
52PFP QSR, 4/19/2011
Power Converter Status (1)
• REG Board • We are working on a second PCB layout for the REG board
ETU#2 due to a connector mis-wiring issue on the first layout. This re-layout process has begun.
• The REG board tester was built and is now in operation• All REG based switchable services have been tested• Still pending: adjustment/tuning of the current monitoring
subsystem; complete verification of the digital portion of the circuit
• REG Board system checkout via PFDPU I/F Tests• DCB Interface/Housekeeping addressing• Instrument Power Switches
53PFP QSR, 4/19/2011
Power Converter Status (2)
• IIB board• All power converter sections of the EM board have been tested with only
the magnetics of MAG2 and off board connectors for STATIC, SWIA, and MAG left to be populated. (This excludes the MAG HEATER daughter boards from Goddard that are to be mounted on the IIB at a later date.)
• The ±90V outputs on the LPW section sat at 114V when integrated with the system. This would indicate an unloaded state as the voltage would normally drop closer to ±90V when loaded (10mA peak).
• The 5VD regulator on the SEP section will be changed to an LDO as the actual load is much lower with the system. The LTC1877 may have stability issues with such a low load.
• ACTEL turn-off delay circuit for the LPW section will be added and tested on the EM board.
• Optimization for noise, efficiency, and voltage levels will also be done after and in between integration.
54PFP QSR, 4/19/2011
Concerns/Issues
• PC104 Connectors– One of the Hypertronics PC104 connectors delivered to us appear
to have been assembled incorrectly– Connectors are very fragile, pins have bent and even broken during
our ETU testing• We have implemented a mating procedure to mitigate this issue
– We still need to verify the connection insertion is met with the boards installed in their frames
• Schedule– Schedule for testing is tight– As the integration progresses, we are finding issues that require
resolution (e.g. power supply regulation, clock distribution). We need time to sort through all the open-items (hopefully prior to CDR) yet the individual subsystem testing/tuning is still ongoing.
55PFP QSR, 4/19/2011
MAVEN PFP Flight Software Status
April 12 2011
Peter Harvey
56PFP QSR, 4/19/2011
Boot Status
Interface Documents, Meetings Reviewed PFEPTPlan.
IV&V 3/31/11 Discussion confirmed Boot Requirements OK
FSW Development Added temporary diagnostic outputs to support PFEPTPlan at LM Removed automatic safing sequence since S/C will not be sending ZoneAlerts “Inverted” checksum logic w/ no-0000 allowed logic added to CMD and TM
Test Status All Boot Packets are Displayed in RealTime, Hot Buttons installed Retested with DCB FPGA update revision 07 and 08 PF-Spacecraft Simulator (PFEPT) test support at LM CMD Rate Test to be Repeated when GSEOS can support it Formal Test Scripts to be Developed Module tests Comprehensive Performance
• Dates coming up August - PROM Burn
57PFP QSR, 4/19/2011
Operational Status
Interface Documents, Meetings Reviewed DFB specification rev J – OK. Implemented changes to IO regs Reviewed SEP specifications rev B, C, D – OK. Supported SEP.c development Reviewed “MAG software requirements” – Not OK. Conflicts with FSW-010
IV&V Reviewed IV&V comments w.r.t Operational - OK
FSW Development SSR - Developed Generic Message-APID software for I&T tests (SEP,SWEA,SWIA, STA) Wrote MAG Build1 & Build2 software (before requirements change) Wrote SEP Build1*
Wrote STATIC, SWEA, SWIA Build1 software Test Status
LPW, SSR(RealTime) simulations completed LPW EM I&T test support MAG simulations completed SEP Build1 simulations complete, SEP Build1 DCB/REG/IIB/SEP EM I&T complete STA Build1 simulation – 50% complete. AHSK to be done SWIA, SWEA Build1 simulations to be done shortly.
• Important Dates coming up April 11 2011 – Interface test with SEP April 13 2011 – Interface test with SWEA April 27 2011 – Interface test with MAG
*: Build1 supports ETU-level I&T tests
58PFP QSR, 4/19/2011
Test Environment
GSEOS Status: Generally functional though issues internal error messages, and crashes periodically Added APID 11 (Memory Loads) Needs Zone Alerts (for compatibility) Needs 30 ms delay between messages (per ICD) Limit checking error messages (uses raw values, not converted) Updated New Checksum needs to be checking all telemetry
GSEOS Python Test Scripts, Displays Developed SEP, SWEA, SWIA, STATIC EMIT Test scripts Included/modified SEP HSK displays for EMIT test Include/modify SWEA HSK displays for EMIT test Include/modify SWIA HSK displays for EMIT test Include/modify STATIC HSK displays for EMIT test MAG has not updated scripts, HSK display (according to SVN)
FSW Development Platform: DCB EM2 Built, tests are in progress Regulation board built Instrument Simulator Functional Test Scripts for Instrument Simulation being built ( LPW, SEP tested so far) PROM emulator ESD mat, wrist-straps etc installed in Rm 124 (my office)
59PFP QSR, 4/19/2011
Documentation
SW Product Preliminary Due Baseline Due DateSoftware Development Plan 6 AUG 2009 26 MAY 2010Software Safety PlanSoftware Configuration Management PlanSW Quality Assurance PlanSW Risk Management PlanNPR 7150.2 Compliance Matrix w/Software Development IS: Update w/ each deliverableSoftware Requirements SpecificationSoftware Requirements Traceability MatrixSoftware Requirements ReviewSoftware Design Document IS: ISwPDR -10 days IS: ISwCDR -10 days 4/29/2011Software Preliminary Design ReviewSoftware Critical Design Review 4/28/2011Software Test Plan/Procedures IS: ICDR -30 days IS: Run-for-score -3 days 4/23/2011Software Requirements Verification Matrix 4/23/2011Software Acceptance Test Readiness ReviewSoftware User’s ManualTelemetry & Command DatabaseSoftware Acceptance Test ReportsSoftware Acceptance ReviewSoftware Maintenance Plan Prior to CDR Mission Ops Readiness Review 5/13/2011Software Version Description Document
28 APR 2010w/Software Requirements Specification
w/Software Development Plan
w/Software Development Planw/Software Development Planw/Software Development Plan
18 FEB 2011
IS: IPSR
IS: With each software delivery
Run-for-score +15 daysw/ Software User’s Manual
Prior to acceptance test run-for-scoreWith software delivery, IPSR
IS: IPDR -25 daysIS: ICDR -25 days
w/Software Test Plan
SW Product Preliminary Due Baseline Due DateSoftware Development Plan 6 AUG 2009 26 MAY 2010Software Safety PlanSoftware Configuration Management PlanSW Quality Assurance PlanSW Risk Management PlanNPR 7150.2 Compliance Matrix w/Software Development IS: Update w/ each deliverableSoftware Requirements SpecificationSoftware Requirements Traceability MatrixSoftware Requirements ReviewSoftware Design Document IS: ISwPDR -10 days IS: ISwCDR -10 days 4/29/2011Software Preliminary Design ReviewSoftware Critical Design Review 4/28/2011Software Test Plan/Procedures IS: ICDR -30 days IS: Run-for-score -3 days 4/23/2011Software Requirements Verification Matrix 4/23/2011Software Acceptance Test Readiness ReviewSoftware User’s ManualTelemetry & Command DatabaseSoftware Acceptance Test ReportsSoftware Acceptance ReviewSoftware Maintenance Plan Prior to CDR Mission Ops Readiness Review 5/13/2011Software Version Description Document
28 APR 2010w/Software Requirements Specification
w/Software Development Plan
w/Software Development Planw/Software Development Planw/Software Development Plan
18 FEB 2011
IS: IPSR
IS: With each software delivery
Run-for-score +15 daysw/ Software User’s Manual
Prior to acceptance test run-for-scoreWith software delivery, IPSR
IS: IPDR -25 daysIS: ICDR -25 days
w/Software Test Plan
60PFP QSR, 4/19/2011
Metrics ChartMilestone PDRDescription Apr-10 May-10 Jun-10 Jul-10 Aug-10 Sep-10 Oct-10 Nov-10 Dec-10 Jan-11 Feb-11 Mar-11Product Characteristics
Project Name MAVEN MAVEN MAVEN MAVEN MAVEN MAVEN MAVEN MAVEN MAVEN MAVEN MAVEN MAVENLanguage C C C C C C C C C C C C
Software Domain (FSW) FSW FSW FSW FSW FSW FSW FSW FSW FSW FSW FSW FSWBOOT SLOC Expected 9180 9180 9180 9180 9180 9180 9180 9180 9180 9180 9180 9180
BOOT SLOC To Date 0 0 771 1645 2841 2841 2841 2841 2841 3636 3799 3939OPER SLOC Expected 9180 9180
OPER SLOC To Date 5290 7299Software Progress
Major Events Planned 1 1 1 0 0 0 0 0 0 0 0 1Major Events Actual 1 1 1 0 0 0 0 0 0 0 0 1
Progress Points Planned 1 1 1 1 1 1 1 1 1 1 1 1Progress Points Actual 0 1 0 1 1 1 1 1 1 1 1 1
Effort-Software Planned 90% 90% 90% 90% 90% 90% 90% 90% 90% 90% 90% 90%Effort-Software Actual 0% 0% 24% 45% 51% 7% 7% 6% 7% 64% 63% 37%
Risks (Low) 0 3 4 4 4 4 4 4 4 3 3 3Risks (Med) 0 0 0 0 0 0 0 0 0 1 1 1Risks (High) 0 0 0 0 0 0 0 0 0 0 0 0
Project PlanningCost/Schedule Revs Planned 0 0 1 0 0 0 0 0 0 0 0 0
Cost/Schedule Revs Actual 1 0 1 0 0 0 0 0 0 0 0 0Effort-Management Planned 10% 10% 10% 10% 10% 10% 10% 10% 10% 10% 10% 10%
Effort-Management Actual 24% 79% 37% 10% 5% 10% 7% 9% 8% 6% 5% 5%Software Functionality
Requirements Planned 8.1 16.2 24.3 32.4 40.5 55.75 71 86.25 97.0 107.8Requirements Actual 0 0 19 28 51 51 51 51 57 61 142 157
Software QualityFSW Defect Count 0 0 0 0 0 0 0 0 0 0 0 2
non-FSW Defect Count 0 0 0 0 0 0 0 0 0 0 0 0Inspections Planned 0 0 0 0 0 0 1 0 0 1 0 0
Inspections Actual 0 0 0 0 0 0 0 0 0 0 0 0Effort-Quality Planned 0 0 0 0 0 0 0.2 0 0 0.2 0 0
Effort-Quality Actual 0 0 0 0 0 0 0 0 0 0 0 0Configuration Management
VDD Reviews Planned 0 0 0 0 0 0 1 0 0 1 0 0VDD Reviews Actual 0 0 0 0 0 0 0 0 0 0 0 0
CM Meetings Planned 0 0 0 0 0 0 0 0 0 0 0 0CM Meetings Actual 0 0 0 0 0 0 0 0 0 0 0 0
Requirements ManagementRequirements Changes 0 0 2 0 1 0 12 0 31 17 52 0
Effort-Engineering 24% 0% 3% 0% 0% 3% 5% 12% 29% 17% 5% 9%
61PFP QSR, 4/19/2011
Margin Chart
Apr-10 May-10 Jun-10 Jul-10 Aug-10 Sep-10 Oct-10 Nov-10 Dec-10 Jan-11 Feb-11 Mar-11DCB
Spec A D E E E E F G H I I JPROM SIZE 32 32 32 32 32 32 32 32 32 32 32 32
EEPROM SIZE 256 256 256 256 256 256 256 256 256 256 256 256FLASH TABLES 512 512 512 512 512 512 512 512 512 512 512 512
RAM SIZE 3072 3072 3072 3072 3072 3072 3072 3072 3072 3072 3072 3072CPU Cycles/sec 16777216 16777216 16777216 16777216 16777216 16777216 16777216 16777216 16777216 16777216 16777216 16777216CPU Cycles/int 65536 65536 65536 65536 65536 65536 65536 65536 65536 65536 65536 65536
CMD UART bps 57600 57600 57600 57600 57600 57600 57600 57600 57600 57600 57600 57600TM UART bps 57600 57600 57600 57600 57600 57600 57600 57600 57600 57600 57600 57600
FSWVERSION 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 1.0 1.0 1.0
PROM (BOOT) 0.00 0.00 0.00 4.44 7.46 7.46 7.46 7.46 7.46 8.61 12.61 12.61EEPROM (OPx2) 0.00 0.00 0.00 0.03 0.03 0.03 0.03 0.03 0.03 0.03 25.21 25.21
FLASH 0.00 0.00 0.00 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03RAM 0.00 0.00 0.00 6.59 14.80 14.80 14.80 14.80 14.80 14.80 14.80 14.80
CPU Cycles/4s 6710886 6710886 6710886 6710886 6710886 6710886 6710886 6710886 6710886 6710886 6710886 6710886CPU Cycles/Int 6550 6550 6550 6550 6550 6550 6550 6550 6550 6550 6550 6550
CMD UART% 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000TLM UART% 27000 27000 27000 27000 27000 27000 27000 27000 27000 27000 27000 27000
MARGINS 50% 50% 50% 49% 48% 48% 47% 46% 45% 44% 43% 43%PROM (BOOT) 620% 329% 329% 329% 329% 329% 272% 154% 154%
EEPROM (OPx2) 819100% 819100% 819100% 819100% 819100% 819100% 819100% 915% 915%FLASH 1638300% 1638300% 1638300% 1638300% 1638300% 1638300% 1638300% 1638300% 1638300%
RAM 46517% 20656% 20656% 20656% 20656% 20656% 20656% 20656% 20656%CPU Cycles/4s 150% 150% 150% 150% 150% 150% 150% 150% 150% 150% 150% 150%CPU Cycles/Int 901% 901% 901% 901% 901% 901% 901% 901% 901% 901% 901% 901%
CMD UART% 5660% 5660% 5660% 5660% 5660% 5660% 5660% 5660% 5660% 5660% 5660% 5660%TLM UART% 113% 113% 113% 113% 113% 113% 113% 113% 113% 113% 113% 113%
62PFP QSR, 4/19/2011
Fever Chart
1. MAG delivered a completely new version of software requirements, conflicting with implemented software.
LegendGreat. Ahead of ScheduleConcern about somethingProblems!
BOOT Apr-10 May-10 Jun-10 Jul-10 Aug-10 Sep-10 Oct-10 Nov-10 Dec-10 Jan-11 Feb-11 Feb-11RequirementsSpecificationsSoftware DevelopmentTesting
OPERATIONAL Apr-10 May-10 Jun-10 Jul-10 Aug-10 Sep-10 Oct-10 Nov-10 Nov-10 Jan-11 Feb-11 Feb-11RequirementsSpecificationsSoftware DevelopmentTesting