1 PFP QSR, 4/19/2011 Particles and Fields Package Quarterly Status Review (QSR) April 19, 2011 Dave...

62
1 PFP QSR, 4/19/2011 Particles and Fields Package Quarterly Status Review (QSR) April 19, 2011 Dave Curtis, PFP PM

Transcript of 1 PFP QSR, 4/19/2011 Particles and Fields Package Quarterly Status Review (QSR) April 19, 2011 Dave...

Page 1: 1 PFP QSR, 4/19/2011 Particles and Fields Package Quarterly Status Review (QSR) April 19, 2011 Dave Curtis, PFP PM.

1PFP QSR, 4/19/2011

Particles and Fields PackageQuarterly Status Review (QSR)

April 19, 2011

Dave Curtis, PFP PM

Page 2: 1 PFP QSR, 4/19/2011 Particles and Fields Package Quarterly Status Review (QSR) April 19, 2011 Dave Curtis, PFP PM.

2PFP QSR, 4/19/2011

SSL Contracting Status

• Funded through the end of April• More info in the Business Splinter presentation

Page 3: 1 PFP QSR, 4/19/2011 Particles and Fields Package Quarterly Status Review (QSR) April 19, 2011 Dave Curtis, PFP PM.

3PFP QSR, 4/19/2011

Schedule Status

• EMs have made a lot of progress this month– All EM PWBs in test but ~2 (HVPS boards, in fab)– SEP, LPW, SWEA, MAG EM mechanical assembly complete– STATIC EM TDC complete random vibe– SWIA/STATIC analyzers parts out to fab

• EM Package I&T in progress– LPW, SEP, SWEA test with PFDPU complete– EM ‘Early Payload Test’ with LM complete– MAG next week– Pushing to complete before CDR– EM Instrument calibrations don’t complete till after Package I&T

• STATIC is on critical path– 13.6 weeks margin to delivery– Driven be delays in EM I&T

• Status at instrument CDR – SWIA, STATIC EM will not be complete– SWIA, STATIC attenuator life test not done– SWIA, STATIC power converters may still be in test– Rest of instrument EM will be complete, with perhaps some system

level test still in progress

Page 4: 1 PFP QSR, 4/19/2011 Particles and Fields Package Quarterly Status Review (QSR) April 19, 2011 Dave Curtis, PFP PM.

4PFP QSR, 4/19/2011

Manpower

• RBSP-EFW instrument still not delivered – this month?– A number of problems encountered in thermal vacuum– Resolving those problems have impacted MAVEN power

converter team, delayed STATIC & SWIA

• We are still under planned FTE rate– but climbing a bit– Mostly due to people splitting time between projects

• Note that 100% activity is often more than 40 hours/week in these cases

– Plan was based on conservative assumptions about covering people

Page 5: 1 PFP QSR, 4/19/2011 Particles and Fields Package Quarterly Status Review (QSR) April 19, 2011 Dave Curtis, PFP PM.

5PFP QSR, 4/19/2011

Accomplishments

• LPW, SEP, SWEA EM integrated with PFDPU EM• PFDPU EM Early Payload test with Spacecraft EM• SWEA Peer Review Completed• STATIC Random Vibration Completed• SEP Attenuator Life Test Completed

• More in instrument sections…

Page 6: 1 PFP QSR, 4/19/2011 Particles and Fields Package Quarterly Status Review (QSR) April 19, 2011 Dave Curtis, PFP PM.

6PFP QSR, 4/19/2011

Ongoing Work

• Supporting Project planning process• Supporting EMC, Payload, SDT working groups

• Completing EM board testing• Completing SWIA/STATIC EM mechanical part

fabrication• Complete PF Package EM I&T• Prepare for CDR

Page 7: 1 PFP QSR, 4/19/2011 Particles and Fields Package Quarterly Status Review (QSR) April 19, 2011 Dave Curtis, PFP PM.

7PFP QSR, 4/19/2011

EM Status

Required for I/F Testing at LM

In Lay-out

In Fab / Assembly

In Test

Integrated to chassis

Not Required for EM

Ready for Test

Test Completed

Ready to Integrate

REG1

DCB1

REG2

DCB2

IIB

SEP1

MAG1

LPW BEB

LPW DFB

LPW 1

EUV

MAG 1

STATIC

SWEAtt

SWIA

PFP

Flash FPGA***

LVPS

LVPS

DIG

Sweep

Preamp + MCP

Anode

LVPS

ACC + MCP

Anode

TDC

Preamp

DAP

SEP1

DFE

DFE

MAG HTRT

Preamptt

Anode

tt

HVPStt

PFDPU

Flash FPGA***

Flash FPGA***

Preamp

Sweep

DIG

DIG

Preamp

IF TesT3 /15/11

Page 8: 1 PFP QSR, 4/19/2011 Particles and Fields Package Quarterly Status Review (QSR) April 19, 2011 Dave Curtis, PFP PM.

8PFP QSR, 4/19/2011

PFP RFA Status

Review Actions Closed %SWEA Peer 20 20 100%

Mechanical Peer 8 8 100%Analyzer Peer 11 11 100%Power Peer 0Digital Peer 4 4 100%FSW Peer 0LPW Peer 11 11 100%MAG Peer 5 5 100%

LPW Mech Peer 7 7 100%

IPDR 6 6 100%

Totals 72 72 100%

All Done!

Page 9: 1 PFP QSR, 4/19/2011 Particles and Fields Package Quarterly Status Review (QSR) April 19, 2011 Dave Curtis, PFP PM.

9PFP QSR, 4/19/2011

Trades, Issues

• HV801 issue still open– Current plan is to buy HV801s from LADEE NMS, who has parts

on order they no longer need.– We still don’t have the parts in hand

• Working on an analysis to decide if the PFDPU mechanical design needs to be augmented to support the PWBs to avoid excessive displacements in vibe– Analysis complete, passed on to GSFC expert for review.

• LPW Stacer Plating issue (NEW)– After plating stacer with black Nickel it no longer stows properly– Need plating for thermal reasons (aeroheating, thruster heating)– Historically we have used a paint (DAG213), but that will not

survive atomic oxygen at Mars– Working with GSFC Materials on possible solutions

Page 10: 1 PFP QSR, 4/19/2011 Particles and Fields Package Quarterly Status Review (QSR) April 19, 2011 Dave Curtis, PFP PM.

10PFP QSR, 4/19/2011

Thermal Status

• Received ‘Thermal Memos’ as well as spacecraft thermal model

• Some of the instruments are in trouble according to the thermal memo– For example, STATIC goes to -100C

• We are working on identifying if the issue is the model or the design– Our preliminary results are more benign

Page 11: 1 PFP QSR, 4/19/2011 Particles and Fields Package Quarterly Status Review (QSR) April 19, 2011 Dave Curtis, PFP PM.

11PFP QSR, 4/19/2011

Top Risks

P-20 reduced (mating procedure)

MAVEN PFP RISK MANAGEMENT Chg RANK ID Approach TITLE

55 10 15 20 25

1 P-17 Mitigate Parts Qualification

44 8 12 16 20

2 P-01 Mitigate SSL Manpower

33 8 9 12 15

3 P-21 Mitigate PFP to Spacecarft ICD

22 4 6 8 10

4 P-20 Mitigate PFDPU Connectors

11 2 3 4 5

5 P-18 Watch Magnetics Implementation

1 2 3 4 5

Criticality Approach

High

Medium

Low

LIKELIHOOD

Improved

Worsening

Unchanged

New this month

Mitigate

Watch

Accept

Research

CONSEQUENCES

L * C Trend

*

P01

P18

P20 P21

P17

Page 12: 1 PFP QSR, 4/19/2011 Particles and Fields Package Quarterly Status Review (QSR) April 19, 2011 Dave Curtis, PFP PM.

12PFP QSR, 4/19/2011

Risks ListID Title Type P I Crit Risk Statement Impact Term Plan Approach Comments

P-01 SSL ManpowerProject

Execution3 2 M

Delays in RBSP leads to manpower conflicts at SSL

Schedule erosion, cost to recover

Near Term

Hire new people to take routine tasks off key personnel

Mitigate Review in March 2010Add extra Power Converter person 1/2010Add extra ME 2/2010Add extra QA 8/2010Add extra Tech & Test Engineer 1/2011Tap into campus technician pool 2/2011

P-07Delayed LPW

Boom Deployment

Mission Performance

1 3 L

Waiting till after MOI to deploy LPW booms results in them sitting undeployed for over a year, increasing the risk of deployment failure

Potential severe degradation of LPW measurement

Far Term

Investigate if LPW booms can be deployed early

Research Early deployment of LPW booms reduces this risk. Actual risk of failure is very low. Risk that we may be asked to do an expensive verification is moderate

P-14 HV801 ProblemProject

Execution1 3 L

If HV801 not available a redesign would be required to use alternate (larger) parts

Schedule, Mass Near Term

Watch what programs ahead of MAVEN do; look into alternate parts

Mitigate Micropak alternate part in test. EM parts found, FM parts identified

P-17Parts

QualificationProject

Execution3 3 M

If parts fail qualification then system would have to be redesigned for alternate (which may also have to be qualified and may have lower performance)

Schedule, Cost, Performance

Near Term

Start parts qualification as soon as possible (but delayed to FY11 for funding)

Mitigate First round of parts radiation testing started. SEL test results look good

P-18Magnetics

ImplementationMission

Performance1 4 L

If unanticipated magnetics issues are found on observatory late (or not found at all) then MAG instrument performance could be degraded

Magnetics [MRD84]

Mid Term

Magnetics Working Group to monitor implementation (materials lists, etc)

Watch

P-19Electrostatics

ImplementationMission

Performance1 4 L

If unanticipated electrostatic issues are found on observatory late (or not found at all) then LPW, SWEA, SWIAm, instrument performance could eb degraded

Electrostatics [MRD 83]

Mid Term

Magnetics Working Group to monitor implementation (materials lists, etc)

Watch

P-20PFDPU

ConnectorsProject

Execution2 2 L

If fragile flight PFDPU connectors damaged then PFDPU schedule will be delayed by rework

Schedule Mid Term

Look for ways to protect pins - connector savers? Working on a plan

Mitigate Improved mate procedure reduces risk

P-21PFP to

Spacecarft ICDProject

Execution2 3 L

If the instrument FSW interpretation of the ICD does not match the Spacecraft interpretation then the instrument will not work at integration, requiring a PROM change to fix (and PFDPU requal)

Schedule Far Term

Work with LM on clarifying the ICD.

Mitigate Early Payload Test reduces risk on hardware side.

Page 13: 1 PFP QSR, 4/19/2011 Particles and Fields Package Quarterly Status Review (QSR) April 19, 2011 Dave Curtis, PFP PM.

13PFP QSR, 4/19/2011

PFP Mass

• CCR262 approved to reallocate NTE amongst PFP

InstrumentCBE

Total [kg] Cont. (%)Total [kg] (CBE+cnt)

Particles and Fields 23.74 15.3% 27.37LPW Total 6.18 15.2% 7.12

LPW Booms 5.150 15.1% 5.930EUV Assembly 1.030 15.5% 1.190

STATIC Total 2.87 15.4% 3.31SWEA Total 1.82 15.2% 2.10SWIA Total 2.59 15.2% 2.98SEP Total 1.27 16.1% 1.47MAG Total 0.84 16.2% 0.97PFDPU Total 5.89 15.0% 6.78PF Intra-Instrument Harness Total 2.29 15.5% 2.64

Page 14: 1 PFP QSR, 4/19/2011 Particles and Fields Package Quarterly Status Review (QSR) April 19, 2011 Dave Curtis, PFP PM.

14PFP QSR, 4/19/2011

Mass Tracking Chart

PFP Mass Trend

10.00

15.00

20.00

25.00

30.00

35.00

10/1/2009

12/1/2009

1/31/2010

4/2/2010 6/2/2010 8/2/2010 10/2/2010

12/2/2010

2/1/2011 4/3/2011

Date

kg

10.0%

15.0%

20.0%

25.0%

30.0%

35.0%

Mass CBE, kg

Mass NTE, kg

Mass Margin %

Page 15: 1 PFP QSR, 4/19/2011 Particles and Fields Package Quarterly Status Review (QSR) April 19, 2011 Dave Curtis, PFP PM.

15PFP QSR, 4/19/2011

PFP Power

• Small increase in MAG power• Small decrease in SWEA power.

Instrument CBE [W] Cont. (%) NTE [W] CBE [W] Cont. (%) NTE[W] CBE [W] Cont. (%) NTE[W]Particles and Fields

Off (heater only) 0.00 0.00 18.56 9% 20.31 18.56 9% 20.31Standby 9.22 36% 12.52 15.35 8% 16.62 24.57 19% 29.14Nominal 18.78 19% 22.29 17.32 12% 19.34 36.10 15% 41.63

Peak 30.83 20% 37.01 101.34 14% 115.70 132.16 16% 152.71Orbit Average 18.89 19% 22.39 17.32 12% 19.34 36.21 15% 41.73

Orbit Average:LPW 3.71 48% 5.49 0.00 0% 0.00 3.71 48% 5.49EUV 0.16 15% 0.18 2.30 -10% 2.07 2.46 -8% 2.25STATIC 4.39 19% 5.21 1.91 15% 2.20 6.30 18% 7.41SWEA 0.99 25% 1.24 2.95 15% 3.39 3.94 17% 4.63SWIA 2.05 22% 2.50 3.08 15% 3.54 5.13 18% 6.04SEP 2.60 -14% 2.24 5.48 15% 6.30 8.08 6% 8.54MAG 3.20 -11% 2.84 1.60 15% 1.84 4.80 -3% 4.68PFDPU 1.78 51% 2.69 0.00 0% 0.00 1.78 51% 2.69

Operational Heater Total

Page 16: 1 PFP QSR, 4/19/2011 Particles and Fields Package Quarterly Status Review (QSR) April 19, 2011 Dave Curtis, PFP PM.

16PFP QSR, 4/19/2011

PFP Power Trend

PFP Power Trend

0.00

5.00

10.00

15.00

20.00

25.00

30.00

35.00

40.00

45.00

10/1/2009

12/1/2009

1/31/2010

4/2/2010 6/2/2010 8/2/2010 10/2/2010

12/2/2010

2/1/2011 4/3/2011

Date

W

0.0%

5.0%

10.0%

15.0%

20.0%

25.0%

30.0%

35.0%

40.0%

45.0%

Power CBE, W

Power NTE, W

Power Margin %

Page 17: 1 PFP QSR, 4/19/2011 Particles and Fields Package Quarterly Status Review (QSR) April 19, 2011 Dave Curtis, PFP PM.

17PFP QSR, 4/19/2011

PFP Data Rate

• Per 2009-6-9 allocations from Bruce• New MAG requirements on telemetry formatting puts

MAG 4% over allocation

Rate [bps]Particles and FieldsLPW/EUV 717.0STATIC 2000.0SWEA 600.0SWIA 604.0SEP 160.0MAG 660.0PFDPU 30.0

Total 4771.0

Instrument

Page 18: 1 PFP QSR, 4/19/2011 Particles and Fields Package Quarterly Status Review (QSR) April 19, 2011 Dave Curtis, PFP PM.

18PFP QSR, 4/19/2011

Requirements Verification Status

• CCR (265) to update PFP Functional Requirements (Level 3) approved– some old requirements need updating

• Verification matrix mostly complete– Have Functional, ERD, ICD requirements complete, in review

• Boot software verification has started– against software level 5 requirements, which link back to FRD

and ICD.• STATIC TOF EM Acoustics and Vibration test complete

– All but coarsest grid with thinnest foils passed– Will not use coarsest grids– Will repeat on full EM and FM

• EM Interface tests started– Reduces risk, not a qualification test

• SEP Attenuator Mechanism Life Test complete

Page 19: 1 PFP QSR, 4/19/2011 Particles and Fields Package Quarterly Status Review (QSR) April 19, 2011 Dave Curtis, PFP PM.

19PFP QSR, 4/19/2011

Life Testing

• SEP Attenuator life test complete– 4100 cycles on EM twice expected life– ~1000 in air, ~3000 in vacuum– Will collect some more cycles over the next few months

• SWIA, STATIC attenuator life test pending completion of EM attenuator– ~June

• SWEA door mechanism identical to STEREO• SWEA, STATIC door mechanism functional, life test

pending• LPW relay life test expected to start soon• LPW deployment life test expected to start soon

– Stacer coating problem holding that up

Page 20: 1 PFP QSR, 4/19/2011 Particles and Fields Package Quarterly Status Review (QSR) April 19, 2011 Dave Curtis, PFP PM.

20PFP QSR, 4/19/2011

MAVEN Magnetometer Status

April 2011

Connerney, Sheppard, Schnurr, Oliversen, Espley, etc.

Page 21: 1 PFP QSR, 4/19/2011 Particles and Fields Package Quarterly Status Review (QSR) April 19, 2011 Dave Curtis, PFP PM.

21PFP QSR, 4/19/2011

GSFC/MAG - Accomplishments Last Month

• EM sensor assembly, pigtail, GSE sensor harness completed. • Breakout PWBs fabrication completed.• Draft MAG Flight Software Requirements Specification (for PFDPU).• Completed Safe-to-Mate procedures for MAD board (MAVEN-MAG-

PROC-0026).• Completed EM Magnetometer board scale factors calibration at GSFC

22’ MAG Test Site; scale factor resistors installed on board.• FPGA (rev 0) burned at Aeroflex, received and installed on MAD

board. Functional testing in progress.• GSE (UCB emulator) development continues; CMD and TLM

successfully flowing between GSE and MAD board.• Sensor non-magnetic heaters design received from vendor (Tayco),

under review.• Frames for MAD board and ACHE board fabricated at GSFC; boards

installed in frames (see pix).

Page 22: 1 PFP QSR, 4/19/2011 Particles and Fields Package Quarterly Status Review (QSR) April 19, 2011 Dave Curtis, PFP PM.

22PFP QSR, 4/19/2011

GSFC/MAG - Accomplishments Last Month

A/C Heater Electronics (ACHE) Board in frame ->

MAG Analog and Digital (MAD) Board & frame

Page 23: 1 PFP QSR, 4/19/2011 Particles and Fields Package Quarterly Status Review (QSR) April 19, 2011 Dave Curtis, PFP PM.

23PFP QSR, 4/19/2011

GSFC/MAG Near Term Plans & Open Issues

• Mature MAG software requirements draft w/UCB.• Hypertronics KPC120 connectors installation and mating issues. • Radiation test plan for MIL spec CD4066 quad bilateral switches

completed; testing scheduled to begin April 18, 2011.• Integration and test of MAG (MAD board and sensor) w/ PFDPU at

UCB scheduled April 26-28, 2011.• MAD board frame modifications (test connector placement,

mechanical mod for center board support) pending final approval.• Continue winding FM sensor ring cores, feedback/sense bobbins,

and magnetic piece parts per technician availability; fabricate sensor assembly terminal boards.

• Draft worst case analysis of MAD board.• MAG Peer Review scheduled for May 5, 2011 @ GSFC.• Workload: RBSP FM post-environmental test evaluation drags on;

Juno FM system integration work in progress @ Astrotech, KSC.

Page 24: 1 PFP QSR, 4/19/2011 Particles and Fields Package Quarterly Status Review (QSR) April 19, 2011 Dave Curtis, PFP PM.

24PFP QSR, 4/19/2011

MAVEN PFP SWIA Status

April 2011

Jasper Halekas, SWIA Lead

Page 25: 1 PFP QSR, 4/19/2011 Particles and Fields Package Quarterly Status Review (QSR) April 19, 2011 Dave Curtis, PFP PM.

25PFP QSR, 4/19/2011

SWIA Progress

• Electrical Progress– Anode and digital boards tested– Preamp/MCP loaded on preamp half

• Preamp half integrated and in testing with digital• MCP half delayed by RBSP

– LVPS mostly loaded, waiting for testing, delayed by RBSP– Sweep in testing

• Mechanical Progress– E-Box fabricated and assembled– Analyzer in progress

• Many major parts already out for fabrication• Final drawings being finished up

• Detector Progress– MCPs in testing

• Early results using spare THEMIS plates indicate anode board working nominally

Page 26: 1 PFP QSR, 4/19/2011 Particles and Fields Package Quarterly Status Review (QSR) April 19, 2011 Dave Curtis, PFP PM.

26PFP QSR, 4/19/2011

SWIA EM Electronics & Chassis

Page 27: 1 PFP QSR, 4/19/2011 Particles and Fields Package Quarterly Status Review (QSR) April 19, 2011 Dave Curtis, PFP PM.

27PFP QSR, 4/19/2011

SWIA Issues

• Staffing/Schedule– More RBSP delays hurting mechanical and power supplies– Mechanical parts may not all be done in time for peer reviews– Power supplies waiting for loading and testing

Page 28: 1 PFP QSR, 4/19/2011 Particles and Fields Package Quarterly Status Review (QSR) April 19, 2011 Dave Curtis, PFP PM.

28PFP QSR, 4/19/2011

SWIA Test Data

1

2

3

45

6

7

8

9

10

11

12

13

14

15 21

22

2317

18

19

16 20 24

• Anode counts from integrated test pulser correctly counted• P0, P1, P2 data products correctly generated by FPGA

Test pulser outputdivided by four ratios, sent to alternating anodes

Pseudo Data Products

3-d Sky Plot

Energy Spectra

Page 29: 1 PFP QSR, 4/19/2011 Particles and Fields Package Quarterly Status Review (QSR) April 19, 2011 Dave Curtis, PFP PM.

29PFP QSR, 4/19/2011

MAVEN PFP SWEA Status

April 2011

Dave Mitchell, SWEA Lead

Page 30: 1 PFP QSR, 4/19/2011 Particles and Fields Package Quarterly Status Review (QSR) April 19, 2011 Dave Curtis, PFP PM.

30PFP QSR, 4/19/2011

SWEA Status – IRAP (CESR)

• Mechanical– Plating of external parts (Black-Ni, Gold, Alodyne) at Anoplate in New York.

• Most parts delivered to SSL on 4/5 and passed magnetic screening (< 3 nT at 1 cm before and after exposure to >10-Gauss magnetizing field)

• Black-Ni/Gold parts (lower deflector and interface tube) are delayed (expected 4/25) Mechanical assembly at IRAP delayed ~3 weeks

• Electrical: Amp, HV coupling, and HVPS boards assembled at Microtec – expecting delivery at IRAP on 4/19, then functional testing can begin.

• AIT: Facilities in large clean room are in progress as scheduled (installed rolling table and tools, vacuum chamber expected week of 4/18) on schedule for AIT

Magnetic screening station at SSL

SWEA parts plated with high-P electroless black-Ni

top cover

upper deflector toroidal grid

10 cm

Page 31: 1 PFP QSR, 4/19/2011 Particles and Fields Package Quarterly Status Review (QSR) April 19, 2011 Dave Curtis, PFP PM.

31PFP QSR, 4/19/2011

SWEA Status, EM - SSL

• Mechanical: No change from last month: Pedestal fabrication and test fitting complete, ready to assemble when boards available

• LVPC: Some voltages not within spec, and one exhibits and oscillation. Board will be reworked (~2-3 weeks).

Digital

LVPS

STEREO SWEA EM front-end boards

SWEA Electronics I&T

• Digital: – Fab complete and

tested.

– Housekeeping and Data messages from FPGA verified.

– Test pulser demonstrates that counters working as expected.

– Integration with PFDPU EM and functional tests on 4/13 successful

Page 32: 1 PFP QSR, 4/19/2011 Particles and Fields Package Quarterly Status Review (QSR) April 19, 2011 Dave Curtis, PFP PM.

32PFP QSR, 4/19/2011

MAVEN PFP STATIC Status

April 2011

Jim McFadden, STATIC Lead

Page 33: 1 PFP QSR, 4/19/2011 Particles and Fields Package Quarterly Status Review (QSR) April 19, 2011 Dave Curtis, PFP PM.

33PFP QSR, 4/19/2011

STATIC Accomplishments

• Carbon foils mounted in TOF units survive vibration test – automated software used to evaluate foil breakage

• Ordered carbon foils on mica slides to improve mounting yield • The design of START foil grid-frames was modified to compensate for

poor clamping due to fabrication tolerances - new grid-frames ordered. • Design of attenuator motor completed, drawings for ETU in process• Energy analyzer/deflector parts drafted and ordered • EM TDC board bench testing complete, part modifications made• EM preamp 1 modified and working adequately for integration w/ TDC

board – will be used while optimized preamp board is developed • EM Anode, Preamp and TDC boards integrated – working• EM Digital board passed power and PFDPU simulator interface testing,

ready for interface test with TDC• EM Sweep HV board partly loaded and in test (see pictures)• Clean room equipment installed – racks, SS table, GN2 purge, etc.• Helmholtz coil template fabricated, waiting on welding before assembly

Page 34: 1 PFP QSR, 4/19/2011 Particles and Fields Package Quarterly Status Review (QSR) April 19, 2011 Dave Curtis, PFP PM.

34PFP QSR, 4/19/2011

STATIC EM Sweep HV Board

Page 35: 1 PFP QSR, 4/19/2011 Particles and Fields Package Quarterly Status Review (QSR) April 19, 2011 Dave Curtis, PFP PM.

35PFP QSR, 4/19/2011

STATIC Open Issues

• One of two TOF electrical connections broke in 1 of the 3 units during vibration test (see pics) – connection redesigned for stress relief

• Mounting fixtures for handling flight carbon foil frames need to be fabricated before additional EM carbon foils are loaded

• New START foil grid-frames will require inspections after fabrication• Preamp design changes nearly complete for optimal dynamic range –

may require new layout• EM 15kV-MCP board changed, MCP “stack stick” multiplier abandoned

in favor of a pair of VMI multipliers and a tapped transformer – EM waiting on part placement changes (Berg).

• Digital board FPGA still in development• EM LVPS loaded – waiting to be tested• Manipulator fixtures for calibration chamber testing in development• Some test harnesses and test cables still on order• New calibration chamber ordered – delivery late May• SS sink for clean room assembled – waiting for drain assembly

Page 36: 1 PFP QSR, 4/19/2011 Particles and Fields Package Quarterly Status Review (QSR) April 19, 2011 Dave Curtis, PFP PM.

36PFP QSR, 4/19/2011

STATIC EM TOF Post Vib Disassembly

Page 37: 1 PFP QSR, 4/19/2011 Particles and Fields Package Quarterly Status Review (QSR) April 19, 2011 Dave Curtis, PFP PM.

37PFP QSR, 4/19/2011

Post-vib broken electrical connection

Page 38: 1 PFP QSR, 4/19/2011 Particles and Fields Package Quarterly Status Review (QSR) April 19, 2011 Dave Curtis, PFP PM.

38PFP QSR, 4/19/2011

Post-vib broken electrical connection

Page 39: 1 PFP QSR, 4/19/2011 Particles and Fields Package Quarterly Status Review (QSR) April 19, 2011 Dave Curtis, PFP PM.

39PFP QSR, 4/19/2011

MAVEN PFP SEP Status

April, 2011

Davin Larson, SEP Lead

Page 40: 1 PFP QSR, 4/19/2011 Particles and Fields Package Quarterly Status Review (QSR) April 19, 2011 Dave Curtis, PFP PM.

40PFP QSR, 4/19/2011

SEP Accomplishments2011-04-12

• Mechanical attenuator tests completed – ~4500 cycles completed (all but ~1000 in vacuum)

• Integration of DAP board (& ½ sensor sans detectors) with PFDPU begun on 2011-04-11

– Safe to mate –ok– Initial power on - ok

• but receiving +6V and -6.3 volts instead of nominal +/- 5V– Command test – ok

• Successfully turned on test pulser• Bias voltage setting not working (not yet functional on DAP?

– Telemetry tests – ok• Successful run of ‘SEP_DAPINIT’• Unbalanced analog voltages result in offset from baseline• Successful run of “SEP_THRESH_SWEEP”• Successful run of “SEP_TPSWEEP”

– Some cross talk visable that was not seen with MISG– Noise level is substantially larger and assymetric

– Timing Tests – skipped – SEP Aperture tests – ok– SEP auto aperture closure – problem on REG– SEP power inrush current test - OK

• ETU Silicon detectors (1 stack) delivered on 2011-04-12.• DAP board

– 3 channels loaded on DAP #1– 12 channels loaded on DAP #2– Actel programming: Using FPGA version 0x32

Page 41: 1 PFP QSR, 4/19/2011 Particles and Fields Package Quarterly Status Review (QSR) April 19, 2011 Dave Curtis, PFP PM.

41PFP QSR, 4/19/2011

SEP PFDPU Interface Test Data

Cross talk?

Dropouts?Data collected through PFDPU in APID 30

Increased noise(and asymmetric)

Page 42: 1 PFP QSR, 4/19/2011 Particles and Fields Package Quarterly Status Review (QSR) April 19, 2011 Dave Curtis, PFP PM.

42PFP QSR, 4/19/2011

Attenuator life test

• Life tests were done on 3 separate days.

• TCP/IP connection from computer to MISG was unreliable.

• Difference in actuation time is probably temperature related.

Page 43: 1 PFP QSR, 4/19/2011 Particles and Fields Package Quarterly Status Review (QSR) April 19, 2011 Dave Curtis, PFP PM.

43PFP QSR, 4/19/2011

Attenuator Stroke vs. bus voltage

• Tested the range of bus voltages that would cause actuation.• Below 22 V (2.08 V across nanomuscle), actuation failed in air.

Page 44: 1 PFP QSR, 4/19/2011 Particles and Fields Package Quarterly Status Review (QSR) April 19, 2011 Dave Curtis, PFP PM.

44PFP QSR, 4/19/2011

SEP Open issues

• What voltage to use for +/- 5VA supply.– Analog supply NOT currently regulated– Need secondary regulation for A250?– Eliminate requirement of 5V Digital altogether

• Mods needed for flight DAP board:– Use faster transisters on pulse generator (fixes 3.3 volt logic problem)– Use 2.5V reference instead of 5VA for baseline trim– Use Valid signal for hysteresis on peak detect– Gain change on peak detect circuit (perhaps not needed now)– Switch from 10 MΩ to 1MΩ resister on bias voltage control– 5 MΩ resistor to -5VA (-2.5R?) to correct for OpAmp input current (this mod is questionable if BLRena mode

is working properly)• Sensor

– Add detectors!!!!– Insert caps on attenuator lines to clean up some noise

• FPGA Mods from version 0x32– Eliminate secondary pulse by applying BLRena for 6 μsec on test pulse return– Extend test pulse duration from 10 μsec to 20 μsec – 16 bit counters on no peak counters– Ability to turn off housekeeping measurement– Event mode resolution

• Testing:– Purchase new nimbin and test pulser to replace AWOL test pulser– Test for correct coincidence determination with FPGA– New radiation source

• PFDPU testing– Cross talk observed in PFDPU but not MISG?– Increased Noise observed in PFDPU (probably resolved with shield boards)– Telemetry dropouts from PFDPU science packets– Possible change in opto coupler wiring of actuator control on DCB to eliminate any possibility of noise

• Baseline shift at high count rates – (probably not an issue)• 1 mv shift in baseline shortly after the 1 pps signal• More to come

Page 45: 1 PFP QSR, 4/19/2011 Particles and Fields Package Quarterly Status Review (QSR) April 19, 2011 Dave Curtis, PFP PM.

45PFP QSR, 4/19/2011

MAVEN PFP DCB, Power Converter & GSE Status

April 2011

Dorothy Gordon

Timothy Quinn

Peter Berg

Chris Tiu

Page 46: 1 PFP QSR, 4/19/2011 Particles and Fields Package Quarterly Status Review (QSR) April 19, 2011 Dave Curtis, PFP PM.

46PFP QSR, 4/19/2011

PFDPU/DCB Status

PFDPU Overall Integration o DCB/REG

o Functional and electrical verification ongoingo Actuator Control, Housekeeping, Instrument Current Monitoring

o DCB/REG/IIB o Verified LPW signal routing through IIB and Low Voltage Power

Supply

o DCB/REG/IIB/LPW (see next page)o Upcoming PFDPU integration tests

o Remaining power services and signal routing to be checked on a per instrument basis

Page 47: 1 PFP QSR, 4/19/2011 Particles and Fields Package Quarterly Status Review (QSR) April 19, 2011 Dave Curtis, PFP PM.

47PFP QSR, 4/19/2011

PFDPU/DCB Status (2)

o DCB/REG/IIB/LPWo Tested/Verified

o Power-switch, current monitoring on REGo Operation of LPW via the Supplies IIB LVPSo LPW/DCB Interaction via serial interfaceo Operation of the EUV Door Actuator

o LPW Data analyzed for noise and anomalies

10 Hz – 4Vpk-pk 1KHz – 4Vpk-pk 100KHz – 4Vpk-pk

Page 48: 1 PFP QSR, 4/19/2011 Particles and Fields Package Quarterly Status Review (QSR) April 19, 2011 Dave Curtis, PFP PM.

48PFP QSR, 4/19/2011

PFDPU/DCB Status (3)

PFDPU – S/C Interface Testo DCB/REG Verification at Lockheed-Martin

o Integrated power subsystem o Inrush current characterized o Tested S/C Discrete commands and Side Selecto Reset, TIME commands verified

o Operated PFDPU with the Lockheed-Martin Spacecraft Emulator

o Verified signal protocol of RS422 command and telemetry interfaces

o Operation with Flight Software – sent a variety of packets in order to work through the checksum generation algorithm. FSW is working this issue with Lockheed-Martin.

Page 49: 1 PFP QSR, 4/19/2011 Particles and Fields Package Quarterly Status Review (QSR) April 19, 2011 Dave Curtis, PFP PM.

49PFP QSR, 4/19/2011

DCB Status

DCB ETU Buildo DCB ETU #2 Build completeo Delivered (along with FLASH FPGA daughter board)o Short on main DCB power supply (3.3V)

o Problem needs to be identified and fixed

DCB FPGAo Changes added to support the S/C interface modificationso Functional design is complete; undergoing life-test with flight

software and PFDPU Integration

Page 50: 1 PFP QSR, 4/19/2011 Particles and Fields Package Quarterly Status Review (QSR) April 19, 2011 Dave Curtis, PFP PM.

50PFP QSR, 4/19/2011

GSE Hardware Status

MISG Instrument Simulator o First cut operational instrument simulator delivered

o uses the MISG-FPGA Block RAMo Implements the final Instrument Mode functionality

o covers all 8 Instrument Interfaceso with a subset of the final pattern generator buffer space

o Next Stepso Use MISG based SDRAM for Instrument Pattern storage

(allowing for increased buffer space)o Incorporate new modules into next MISG-FPGA release

Page 51: 1 PFP QSR, 4/19/2011 Particles and Fields Package Quarterly Status Review (QSR) April 19, 2011 Dave Curtis, PFP PM.

51PFP QSR, 4/19/2011

GSE Software Status

• SSG– Software updated to handle special case where calculated

checksum equals zero. When this occurs checksum is set to 0xFFFF

• GSEOS– Python modules added to perform checksum processing and

verification on PFDPU telemetry – Python module added to support PFDPU Memory Loads – Delivered first rev of STATIC configuration – Created Python module for playing back raw data over TCP

link with GSEOS – Supported LPW EM integration testing

Page 52: 1 PFP QSR, 4/19/2011 Particles and Fields Package Quarterly Status Review (QSR) April 19, 2011 Dave Curtis, PFP PM.

52PFP QSR, 4/19/2011

Power Converter Status (1)

• REG Board • We are working on a second PCB layout for the REG board

ETU#2 due to a connector mis-wiring issue on the first layout. This re-layout process has begun.

• The REG board tester was built and is now in operation• All REG based switchable services have been tested• Still pending: adjustment/tuning of the current monitoring

subsystem; complete verification of the digital portion of the circuit

• REG Board system checkout via PFDPU I/F Tests• DCB Interface/Housekeeping addressing• Instrument Power Switches

Page 53: 1 PFP QSR, 4/19/2011 Particles and Fields Package Quarterly Status Review (QSR) April 19, 2011 Dave Curtis, PFP PM.

53PFP QSR, 4/19/2011

Power Converter Status (2)

• IIB board• All power converter sections of the EM board have been tested with only

the magnetics of MAG2 and off board connectors for STATIC, SWIA, and MAG left to be populated.  (This excludes the MAG HEATER daughter boards from Goddard that are to be mounted on the IIB at a later date.)

• The ±90V outputs on the LPW section sat at 114V when integrated with the system.  This would indicate an unloaded state as the voltage would normally drop closer to ±90V when loaded (10mA peak).

• The 5VD regulator on the SEP section will be changed to an LDO as the actual load is much lower with the system.  The LTC1877 may have stability issues with such a low load.

• ACTEL turn-off delay circuit for the LPW section will be added and tested on the EM board.

• Optimization for noise, efficiency, and voltage levels will also be done after and in between integration.

Page 54: 1 PFP QSR, 4/19/2011 Particles and Fields Package Quarterly Status Review (QSR) April 19, 2011 Dave Curtis, PFP PM.

54PFP QSR, 4/19/2011

Concerns/Issues

• PC104 Connectors– One of the Hypertronics PC104 connectors delivered to us appear

to have been assembled incorrectly– Connectors are very fragile, pins have bent and even broken during

our ETU testing• We have implemented a mating procedure to mitigate this issue

– We still need to verify the connection insertion is met with the boards installed in their frames

• Schedule– Schedule for testing is tight– As the integration progresses, we are finding issues that require

resolution (e.g. power supply regulation, clock distribution). We need time to sort through all the open-items (hopefully prior to CDR) yet the individual subsystem testing/tuning is still ongoing.

Page 55: 1 PFP QSR, 4/19/2011 Particles and Fields Package Quarterly Status Review (QSR) April 19, 2011 Dave Curtis, PFP PM.

55PFP QSR, 4/19/2011

MAVEN PFP Flight Software Status

April 12 2011

Peter Harvey

Page 56: 1 PFP QSR, 4/19/2011 Particles and Fields Package Quarterly Status Review (QSR) April 19, 2011 Dave Curtis, PFP PM.

56PFP QSR, 4/19/2011

Boot Status

Interface Documents, Meetings Reviewed PFEPTPlan.

IV&V 3/31/11 Discussion confirmed Boot Requirements OK

FSW Development Added temporary diagnostic outputs to support PFEPTPlan at LM Removed automatic safing sequence since S/C will not be sending ZoneAlerts “Inverted” checksum logic w/ no-0000 allowed logic added to CMD and TM

Test Status All Boot Packets are Displayed in RealTime, Hot Buttons installed Retested with DCB FPGA update revision 07 and 08 PF-Spacecraft Simulator (PFEPT) test support at LM CMD Rate Test to be Repeated when GSEOS can support it Formal Test Scripts to be Developed Module tests Comprehensive Performance

• Dates coming up August - PROM Burn

Page 57: 1 PFP QSR, 4/19/2011 Particles and Fields Package Quarterly Status Review (QSR) April 19, 2011 Dave Curtis, PFP PM.

57PFP QSR, 4/19/2011

Operational Status

Interface Documents, Meetings Reviewed DFB specification rev J – OK. Implemented changes to IO regs Reviewed SEP specifications rev B, C, D – OK. Supported SEP.c development Reviewed “MAG software requirements” – Not OK. Conflicts with FSW-010

IV&V Reviewed IV&V comments w.r.t Operational - OK

FSW Development SSR - Developed Generic Message-APID software for I&T tests (SEP,SWEA,SWIA, STA) Wrote MAG Build1 & Build2 software (before requirements change) Wrote SEP Build1*

Wrote STATIC, SWEA, SWIA Build1 software Test Status

LPW, SSR(RealTime) simulations completed LPW EM I&T test support MAG simulations completed SEP Build1 simulations complete, SEP Build1 DCB/REG/IIB/SEP EM I&T complete STA Build1 simulation – 50% complete. AHSK to be done SWIA, SWEA Build1 simulations to be done shortly.

• Important Dates coming up April 11 2011 – Interface test with SEP April 13 2011 – Interface test with SWEA April 27 2011 – Interface test with MAG

*: Build1 supports ETU-level I&T tests

Page 58: 1 PFP QSR, 4/19/2011 Particles and Fields Package Quarterly Status Review (QSR) April 19, 2011 Dave Curtis, PFP PM.

58PFP QSR, 4/19/2011

Test Environment

GSEOS Status: Generally functional though issues internal error messages, and crashes periodically Added APID 11 (Memory Loads) Needs Zone Alerts (for compatibility) Needs 30 ms delay between messages (per ICD) Limit checking error messages (uses raw values, not converted) Updated New Checksum needs to be checking all telemetry

GSEOS Python Test Scripts, Displays Developed SEP, SWEA, SWIA, STATIC EMIT Test scripts Included/modified SEP HSK displays for EMIT test Include/modify SWEA HSK displays for EMIT test Include/modify SWIA HSK displays for EMIT test Include/modify STATIC HSK displays for EMIT test MAG has not updated scripts, HSK display (according to SVN)

FSW Development Platform: DCB EM2 Built, tests are in progress Regulation board built Instrument Simulator Functional Test Scripts for Instrument Simulation being built ( LPW, SEP tested so far) PROM emulator ESD mat, wrist-straps etc installed in Rm 124 (my office)

Page 59: 1 PFP QSR, 4/19/2011 Particles and Fields Package Quarterly Status Review (QSR) April 19, 2011 Dave Curtis, PFP PM.

59PFP QSR, 4/19/2011

Documentation

SW Product Preliminary Due Baseline Due DateSoftware Development Plan 6 AUG 2009 26 MAY 2010Software Safety PlanSoftware Configuration Management PlanSW Quality Assurance PlanSW Risk Management PlanNPR 7150.2 Compliance Matrix w/Software Development IS: Update w/ each deliverableSoftware Requirements SpecificationSoftware Requirements Traceability MatrixSoftware Requirements ReviewSoftware Design Document IS: ISwPDR -10 days IS: ISwCDR -10 days 4/29/2011Software Preliminary Design ReviewSoftware Critical Design Review 4/28/2011Software Test Plan/Procedures IS: ICDR -30 days IS: Run-for-score -3 days 4/23/2011Software Requirements Verification Matrix 4/23/2011Software Acceptance Test Readiness ReviewSoftware User’s ManualTelemetry & Command DatabaseSoftware Acceptance Test ReportsSoftware Acceptance ReviewSoftware Maintenance Plan Prior to CDR Mission Ops Readiness Review 5/13/2011Software Version Description Document

28 APR 2010w/Software Requirements Specification

w/Software Development Plan

w/Software Development Planw/Software Development Planw/Software Development Plan

18 FEB 2011

IS: IPSR

IS: With each software delivery

Run-for-score +15 daysw/ Software User’s Manual

Prior to acceptance test run-for-scoreWith software delivery, IPSR

IS: IPDR -25 daysIS: ICDR -25 days

w/Software Test Plan

SW Product Preliminary Due Baseline Due DateSoftware Development Plan 6 AUG 2009 26 MAY 2010Software Safety PlanSoftware Configuration Management PlanSW Quality Assurance PlanSW Risk Management PlanNPR 7150.2 Compliance Matrix w/Software Development IS: Update w/ each deliverableSoftware Requirements SpecificationSoftware Requirements Traceability MatrixSoftware Requirements ReviewSoftware Design Document IS: ISwPDR -10 days IS: ISwCDR -10 days 4/29/2011Software Preliminary Design ReviewSoftware Critical Design Review 4/28/2011Software Test Plan/Procedures IS: ICDR -30 days IS: Run-for-score -3 days 4/23/2011Software Requirements Verification Matrix 4/23/2011Software Acceptance Test Readiness ReviewSoftware User’s ManualTelemetry & Command DatabaseSoftware Acceptance Test ReportsSoftware Acceptance ReviewSoftware Maintenance Plan Prior to CDR Mission Ops Readiness Review 5/13/2011Software Version Description Document

28 APR 2010w/Software Requirements Specification

w/Software Development Plan

w/Software Development Planw/Software Development Planw/Software Development Plan

18 FEB 2011

IS: IPSR

IS: With each software delivery

Run-for-score +15 daysw/ Software User’s Manual

Prior to acceptance test run-for-scoreWith software delivery, IPSR

IS: IPDR -25 daysIS: ICDR -25 days

w/Software Test Plan

Page 60: 1 PFP QSR, 4/19/2011 Particles and Fields Package Quarterly Status Review (QSR) April 19, 2011 Dave Curtis, PFP PM.

60PFP QSR, 4/19/2011

Metrics ChartMilestone PDRDescription Apr-10 May-10 Jun-10 Jul-10 Aug-10 Sep-10 Oct-10 Nov-10 Dec-10 Jan-11 Feb-11 Mar-11Product Characteristics

Project Name MAVEN MAVEN MAVEN MAVEN MAVEN MAVEN MAVEN MAVEN MAVEN MAVEN MAVEN MAVENLanguage C C C C C C C C C C C C

Software Domain (FSW) FSW FSW FSW FSW FSW FSW FSW FSW FSW FSW FSW FSWBOOT SLOC Expected 9180 9180 9180 9180 9180 9180 9180 9180 9180 9180 9180 9180

BOOT SLOC To Date 0 0 771 1645 2841 2841 2841 2841 2841 3636 3799 3939OPER SLOC Expected 9180 9180

OPER SLOC To Date 5290 7299Software Progress

Major Events Planned 1 1 1 0 0 0 0 0 0 0 0 1Major Events Actual 1 1 1 0 0 0 0 0 0 0 0 1

Progress Points Planned 1 1 1 1 1 1 1 1 1 1 1 1Progress Points Actual 0 1 0 1 1 1 1 1 1 1 1 1

Effort-Software Planned 90% 90% 90% 90% 90% 90% 90% 90% 90% 90% 90% 90%Effort-Software Actual 0% 0% 24% 45% 51% 7% 7% 6% 7% 64% 63% 37%

Risks (Low) 0 3 4 4 4 4 4 4 4 3 3 3Risks (Med) 0 0 0 0 0 0 0 0 0 1 1 1Risks (High) 0 0 0 0 0 0 0 0 0 0 0 0

Project PlanningCost/Schedule Revs Planned 0 0 1 0 0 0 0 0 0 0 0 0

Cost/Schedule Revs Actual 1 0 1 0 0 0 0 0 0 0 0 0Effort-Management Planned 10% 10% 10% 10% 10% 10% 10% 10% 10% 10% 10% 10%

Effort-Management Actual 24% 79% 37% 10% 5% 10% 7% 9% 8% 6% 5% 5%Software Functionality

Requirements Planned 8.1 16.2 24.3 32.4 40.5 55.75 71 86.25 97.0 107.8Requirements Actual 0 0 19 28 51 51 51 51 57 61 142 157

Software QualityFSW Defect Count 0 0 0 0 0 0 0 0 0 0 0 2

non-FSW Defect Count 0 0 0 0 0 0 0 0 0 0 0 0Inspections Planned 0 0 0 0 0 0 1 0 0 1 0 0

Inspections Actual 0 0 0 0 0 0 0 0 0 0 0 0Effort-Quality Planned 0 0 0 0 0 0 0.2 0 0 0.2 0 0

Effort-Quality Actual 0 0 0 0 0 0 0 0 0 0 0 0Configuration Management

VDD Reviews Planned 0 0 0 0 0 0 1 0 0 1 0 0VDD Reviews Actual 0 0 0 0 0 0 0 0 0 0 0 0

CM Meetings Planned 0 0 0 0 0 0 0 0 0 0 0 0CM Meetings Actual 0 0 0 0 0 0 0 0 0 0 0 0

Requirements ManagementRequirements Changes 0 0 2 0 1 0 12 0 31 17 52 0

Effort-Engineering 24% 0% 3% 0% 0% 3% 5% 12% 29% 17% 5% 9%

Page 61: 1 PFP QSR, 4/19/2011 Particles and Fields Package Quarterly Status Review (QSR) April 19, 2011 Dave Curtis, PFP PM.

61PFP QSR, 4/19/2011

Margin Chart

Apr-10 May-10 Jun-10 Jul-10 Aug-10 Sep-10 Oct-10 Nov-10 Dec-10 Jan-11 Feb-11 Mar-11DCB

Spec A D E E E E F G H I I JPROM SIZE 32 32 32 32 32 32 32 32 32 32 32 32

EEPROM SIZE 256 256 256 256 256 256 256 256 256 256 256 256FLASH TABLES 512 512 512 512 512 512 512 512 512 512 512 512

RAM SIZE 3072 3072 3072 3072 3072 3072 3072 3072 3072 3072 3072 3072CPU Cycles/sec 16777216 16777216 16777216 16777216 16777216 16777216 16777216 16777216 16777216 16777216 16777216 16777216CPU Cycles/int 65536 65536 65536 65536 65536 65536 65536 65536 65536 65536 65536 65536

CMD UART bps 57600 57600 57600 57600 57600 57600 57600 57600 57600 57600 57600 57600TM UART bps 57600 57600 57600 57600 57600 57600 57600 57600 57600 57600 57600 57600

FSWVERSION 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 1.0 1.0 1.0

PROM (BOOT) 0.00 0.00 0.00 4.44 7.46 7.46 7.46 7.46 7.46 8.61 12.61 12.61EEPROM (OPx2) 0.00 0.00 0.00 0.03 0.03 0.03 0.03 0.03 0.03 0.03 25.21 25.21

FLASH 0.00 0.00 0.00 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03RAM 0.00 0.00 0.00 6.59 14.80 14.80 14.80 14.80 14.80 14.80 14.80 14.80

CPU Cycles/4s 6710886 6710886 6710886 6710886 6710886 6710886 6710886 6710886 6710886 6710886 6710886 6710886CPU Cycles/Int 6550 6550 6550 6550 6550 6550 6550 6550 6550 6550 6550 6550

CMD UART% 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000TLM UART% 27000 27000 27000 27000 27000 27000 27000 27000 27000 27000 27000 27000

MARGINS 50% 50% 50% 49% 48% 48% 47% 46% 45% 44% 43% 43%PROM (BOOT) 620% 329% 329% 329% 329% 329% 272% 154% 154%

EEPROM (OPx2) 819100% 819100% 819100% 819100% 819100% 819100% 819100% 915% 915%FLASH 1638300% 1638300% 1638300% 1638300% 1638300% 1638300% 1638300% 1638300% 1638300%

RAM 46517% 20656% 20656% 20656% 20656% 20656% 20656% 20656% 20656%CPU Cycles/4s 150% 150% 150% 150% 150% 150% 150% 150% 150% 150% 150% 150%CPU Cycles/Int 901% 901% 901% 901% 901% 901% 901% 901% 901% 901% 901% 901%

CMD UART% 5660% 5660% 5660% 5660% 5660% 5660% 5660% 5660% 5660% 5660% 5660% 5660%TLM UART% 113% 113% 113% 113% 113% 113% 113% 113% 113% 113% 113% 113%

Page 62: 1 PFP QSR, 4/19/2011 Particles and Fields Package Quarterly Status Review (QSR) April 19, 2011 Dave Curtis, PFP PM.

62PFP QSR, 4/19/2011

Fever Chart

1. MAG delivered a completely new version of software requirements, conflicting with implemented software.

LegendGreat. Ahead of ScheduleConcern about somethingProblems!

BOOT Apr-10 May-10 Jun-10 Jul-10 Aug-10 Sep-10 Oct-10 Nov-10 Dec-10 Jan-11 Feb-11 Feb-11RequirementsSpecificationsSoftware DevelopmentTesting

OPERATIONAL Apr-10 May-10 Jun-10 Jul-10 Aug-10 Sep-10 Oct-10 Nov-10 Nov-10 Jan-11 Feb-11 Feb-11RequirementsSpecificationsSoftware DevelopmentTesting