Permeability and Seepage
N. Sivakugan
Duration = 17 minutes
![Page 2: 1 Permeability and Seepage N. Sivakugan Duration = 17 minutes.](https://reader035.fdocuments.us/reader035/viewer/2022081801/56649e715503460f94b707b4/html5/thumbnails/2.jpg)
2SIVA
Copyright©2001
What is permeability?A measure of how easily a fluid (e.g., water)
can pass through a porous medium (e.g., soils)
Loose soil
- easy to flow
- high permeability
Dense soil
- difficult to flow
- low permeability
water
![Page 3: 1 Permeability and Seepage N. Sivakugan Duration = 17 minutes.](https://reader035.fdocuments.us/reader035/viewer/2022081801/56649e715503460f94b707b4/html5/thumbnails/3.jpg)
3SIVA
Copyright©2001
Bernoulli’s Equation
1. Kinetic energy
datum
z
fluid particle
The energy of a fluid particle is made of:
2. Strain energy
3. Potential energy
- due to velocity
- due to pressure
- due to elevation (z) with respect to a datum
![Page 4: 1 Permeability and Seepage N. Sivakugan Duration = 17 minutes.](https://reader035.fdocuments.us/reader035/viewer/2022081801/56649e715503460f94b707b4/html5/thumbnails/4.jpg)
4SIVA
Copyright©2001
Bernoulli’s Equation
Total head =
datum
z
fluid particle
Expressing energy in unit of length:
Velocity head
+
Pressure head
+
Elevation head
![Page 5: 1 Permeability and Seepage N. Sivakugan Duration = 17 minutes.](https://reader035.fdocuments.us/reader035/viewer/2022081801/56649e715503460f94b707b4/html5/thumbnails/5.jpg)
5SIVA
Copyright©2001
Bernoulli’s Equation
Total head =
datum
z
fluid particle
For flow through soils, velocity (and thus velocity head) is very small. Therefore,
Velocity head
+
Pressure head
+
Elevation head
0
Total head = Pressure head + Elevation head
![Page 6: 1 Permeability and Seepage N. Sivakugan Duration = 17 minutes.](https://reader035.fdocuments.us/reader035/viewer/2022081801/56649e715503460f94b707b4/html5/thumbnails/6.jpg)
6SIVA
Copyright©2001
Some NotesIf flow is from A to B, total head is higher at
A than at B.
water
A B
Energy is dissipated in overcoming the soil resistance and hence is the head loss.
![Page 7: 1 Permeability and Seepage N. Sivakugan Duration = 17 minutes.](https://reader035.fdocuments.us/reader035/viewer/2022081801/56649e715503460f94b707b4/html5/thumbnails/7.jpg)
7SIVA
Copyright©2001
Some Notes
Pressure head = pore water pressure/w
Elevation head = height above the selected datum
At any point within the flow regime:
![Page 8: 1 Permeability and Seepage N. Sivakugan Duration = 17 minutes.](https://reader035.fdocuments.us/reader035/viewer/2022081801/56649e715503460f94b707b4/html5/thumbnails/8.jpg)
8SIVA
Copyright©2001
Some Notes
Hydraulic gradient (i) between A and B is the total head loss per unit length.
water
A BAB
BA
l
THTHi
length AB, along the stream line
![Page 9: 1 Permeability and Seepage N. Sivakugan Duration = 17 minutes.](https://reader035.fdocuments.us/reader035/viewer/2022081801/56649e715503460f94b707b4/html5/thumbnails/9.jpg)
9SIVA
Copyright©2001
Darcy’s LawVelocity (v) of flow is proportional to the hydraulic gradient (i) – Darcy (1856)
v = k i
Permeability
• or hydraulic conductivity
• unit of velocity (cm/s)
![Page 10: 1 Permeability and Seepage N. Sivakugan Duration = 17 minutes.](https://reader035.fdocuments.us/reader035/viewer/2022081801/56649e715503460f94b707b4/html5/thumbnails/10.jpg)
10SIVA
Copyright©2001
Large Earth Dam
SHELL
FOUNDATION
SHELL
CORE
blanket
filter
cutoff
crest
riprap
free board
![Page 11: 1 Permeability and Seepage N. Sivakugan Duration = 17 minutes.](https://reader035.fdocuments.us/reader035/viewer/2022081801/56649e715503460f94b707b4/html5/thumbnails/11.jpg)
11SIVA
Copyright©2001
Permeability Values (cm/s)10-310-6 100
clays gravelssandssilts
CoarseFines
For coarse grain soils, k = f(e or D10)
![Page 12: 1 Permeability and Seepage N. Sivakugan Duration = 17 minutes.](https://reader035.fdocuments.us/reader035/viewer/2022081801/56649e715503460f94b707b4/html5/thumbnails/12.jpg)
12SIVA
Copyright©2001
Stresses due to Flow
X
soil
hw
L
Static Situation (No flow)
zv = whw + satz
u = w (hw + z)
v ' = ' z
At X,
![Page 13: 1 Permeability and Seepage N. Sivakugan Duration = 17 minutes.](https://reader035.fdocuments.us/reader035/viewer/2022081801/56649e715503460f94b707b4/html5/thumbnails/13.jpg)
SIVA
Copyright©2001
Stresses due to FlowDownward Flow
hw
L
flow
X
soil
z
v = whw + satz
w hw + w(L-hL)(z/L)
v ' = ' z + wiz
At X,
hL
u = w hw
u = w (hw+L-hL)
… as for static case
= w hw + w(z-iz)
= w (hw+z) - wiz
Reduction due to flow
Increase due to flow
u =
![Page 14: 1 Permeability and Seepage N. Sivakugan Duration = 17 minutes.](https://reader035.fdocuments.us/reader035/viewer/2022081801/56649e715503460f94b707b4/html5/thumbnails/14.jpg)
14SIVA
Copyright©2001
Stresses due to Flow
flow
Upward Flow
hw
LX
soil
z
v = whw + satz
w hw + w(L+hL)(z/L)
v ' = ' z - wiz
At X,
hL
u = w hw
u = w (hw+L+hL)
… as for static case
= w hw + w(z+iz)
= w (hw+z) + wiz
Increase due to flow
Reduction due to flow
u =
![Page 15: 1 Permeability and Seepage N. Sivakugan Duration = 17 minutes.](https://reader035.fdocuments.us/reader035/viewer/2022081801/56649e715503460f94b707b4/html5/thumbnails/15.jpg)
15SIVA
Copyright©2001
Quick Condition in Granular SoilsDuring upward flow, at X:
v ' = ' z - wiz
flow
hw
LX
soil
z
hL
izw
w '
Critical hydraulic gradient (ic)
If i > ic, the effective stresses is negative.
i.e., no inter-granular contact & thus failure.
- Quick condition
![Page 16: 1 Permeability and Seepage N. Sivakugan Duration = 17 minutes.](https://reader035.fdocuments.us/reader035/viewer/2022081801/56649e715503460f94b707b4/html5/thumbnails/16.jpg)
Seepage Terminology
concrete dam
impervious strata
soil
Stream line is simply the path of a water molecule.
datum
hL
TH = 0TH = hL
From upstream to downstream, total head steadily decreases along the stream line.
![Page 17: 1 Permeability and Seepage N. Sivakugan Duration = 17 minutes.](https://reader035.fdocuments.us/reader035/viewer/2022081801/56649e715503460f94b707b4/html5/thumbnails/17.jpg)
Seepage TerminologyEquipotential line is simply a contour of constant total head.
concrete dam
impervious strata
soil
datum
hL
TH = 0TH = hL
TH=0.8 hL
![Page 18: 1 Permeability and Seepage N. Sivakugan Duration = 17 minutes.](https://reader035.fdocuments.us/reader035/viewer/2022081801/56649e715503460f94b707b4/html5/thumbnails/18.jpg)
FlownetA network of selected stream lines and equipotential lines.
concrete dam
impervious strata
soil
curvilinear square
90º
![Page 19: 1 Permeability and Seepage N. Sivakugan Duration = 17 minutes.](https://reader035.fdocuments.us/reader035/viewer/2022081801/56649e715503460f94b707b4/html5/thumbnails/19.jpg)
Quantity of Seepage (Q)
d
fL N
NkhQ ….per unit length normal to the plane
# of flow channels
# of equipotential drops
impervious strata
concrete dam
hL
head loss from upstream to downstream
![Page 20: 1 Permeability and Seepage N. Sivakugan Duration = 17 minutes.](https://reader035.fdocuments.us/reader035/viewer/2022081801/56649e715503460f94b707b4/html5/thumbnails/20.jpg)
Heads at a Point X
impervious strata
concrete dam
datum
X
z
hL
TH = hL TH = 0
Total head = hL - # of drops from upstream x h
h
Elevation head = -z
Pressure head = Total head – Elevation headd
L
N
h
![Page 21: 1 Permeability and Seepage N. Sivakugan Duration = 17 minutes.](https://reader035.fdocuments.us/reader035/viewer/2022081801/56649e715503460f94b707b4/html5/thumbnails/21.jpg)
Piping in Granular Soils
datumconcrete dam
impervious strata
soil
hL
At the downstream, near the dam,
h = total head dropl
l
hiexit
the exit hydraulic gradient
![Page 22: 1 Permeability and Seepage N. Sivakugan Duration = 17 minutes.](https://reader035.fdocuments.us/reader035/viewer/2022081801/56649e715503460f94b707b4/html5/thumbnails/22.jpg)
Piping in Granular Soils
datumconcrete dam
impervious strata
soil
hL
If iexit exceeds the critical hydraulic gradient (ic), firstly
the soil grains at exit get washed away.
no soil; all water
This phenomenon progresses towards the upstream, forming a free passage of water (“pipe”).
![Page 23: 1 Permeability and Seepage N. Sivakugan Duration = 17 minutes.](https://reader035.fdocuments.us/reader035/viewer/2022081801/56649e715503460f94b707b4/html5/thumbnails/23.jpg)
Piping in Granular SoilsPiping is a very serious problem. It leads to downstream flooding which can result in loss of lives.
concrete dam
impervious strata
soil
Therefore, provide adequate safety factor against piping.
exit
cpiping i
iF
typically 5-6
![Page 24: 1 Permeability and Seepage N. Sivakugan Duration = 17 minutes.](https://reader035.fdocuments.us/reader035/viewer/2022081801/56649e715503460f94b707b4/html5/thumbnails/24.jpg)
24SIVA
Copyright©2001
Piping FailuresBaldwin Hills Dam after it failed by piping in 1963. The failure occurred when a concentrated leak developed along a crack in the embankment, eroding the embankment fill and forming this crevasse. An alarm was raised about four hours before the failure and thousands of people were evacuated from the area below the dam. The flood that resulted when the dam failed and the reservoir was released caused several millions of dollars in damage.
![Page 25: 1 Permeability and Seepage N. Sivakugan Duration = 17 minutes.](https://reader035.fdocuments.us/reader035/viewer/2022081801/56649e715503460f94b707b4/html5/thumbnails/25.jpg)
25SIVA
Copyright©2001
Piping Failures
Fontenelle Dam, USA (1965)
![Page 26: 1 Permeability and Seepage N. Sivakugan Duration = 17 minutes.](https://reader035.fdocuments.us/reader035/viewer/2022081801/56649e715503460f94b707b4/html5/thumbnails/26.jpg)
26SIVA
Copyright©2001
FiltersUsed for:
facilitating drainage preventing fines from being washed away
Used in: earth dams
retaining walls
Filter Materials: granular soils
geotextiless
![Page 27: 1 Permeability and Seepage N. Sivakugan Duration = 17 minutes.](https://reader035.fdocuments.us/reader035/viewer/2022081801/56649e715503460f94b707b4/html5/thumbnails/27.jpg)
27SIVA
Copyright©2001
Granular Filter DesignTwo major criteria:
(a) Retention Criteria
(b) Permeability Criteria
- to prevent washing out of fines
- to facilitate drainage and thus avoid build-up of pore pressures
Filter grains must not be too coarse
Filter grains must not be too fine
granular filter
![Page 28: 1 Permeability and Seepage N. Sivakugan Duration = 17 minutes.](https://reader035.fdocuments.us/reader035/viewer/2022081801/56649e715503460f94b707b4/html5/thumbnails/28.jpg)
28SIVA
Copyright©2001
Granular Filter DesignRetention criteria:
D15, filter < 5 D85, soil
- after Terzaghi & Peck (1967)
Permeability criteria:
D15, filter > 4 D15, soil
average filter pore size
D15, filter < 20 D15, soil
D50, filter < 25 D50, soil
- after US Navy (1971)
GSD Curves for the soil and filter must be parallel
![Page 29: 1 Permeability and Seepage N. Sivakugan Duration = 17 minutes.](https://reader035.fdocuments.us/reader035/viewer/2022081801/56649e715503460f94b707b4/html5/thumbnails/29.jpg)
Drainage Provisions in Retaining Walls
drain pipe
granular soil
weep hole
geosynthetics