1 Operating the Power Grid: Current Scenario and Challenges Ahead V. K. AGRAWAL General Manager...
-
Upload
gerald-harrell -
Category
Documents
-
view
215 -
download
0
Transcript of 1 Operating the Power Grid: Current Scenario and Challenges Ahead V. K. AGRAWAL General Manager...
![Page 1: 1 Operating the Power Grid: Current Scenario and Challenges Ahead V. K. AGRAWAL General Manager SRLDC, Bangalore 8 th November, 2006.](https://reader035.fdocuments.us/reader035/viewer/2022062519/5697bfd31a28abf838cabf37/html5/thumbnails/1.jpg)
1
Largest sized hydro unit (180 MW at Chamera) in the country
Salient FeaturesNorthern Regional Power System
Welcome
UNUSUAL
GRID OPERATING CONDITIONS
Operating the Power Grid:
Current Scenario and Challenges Ahead
V. K. AGRAWAL
General Manager
SRLDC, Bangalore
8th November, 2006
![Page 2: 1 Operating the Power Grid: Current Scenario and Challenges Ahead V. K. AGRAWAL General Manager SRLDC, Bangalore 8 th November, 2006.](https://reader035.fdocuments.us/reader035/viewer/2022062519/5697bfd31a28abf838cabf37/html5/thumbnails/2.jpg)
2
PRESENTATION OVERVIEW
REGIONAL GRIDS IN INDIA – QUICK FACTS
SOUTHERN REGIONAL GRID – AN OVERVIEW
GRID CONTROL - ISSUES & CARDINAL EVENTS
POWER SECTOR - THRUST AREAS & ISSUES
SR GRID – PROJECTS IN PROGRESS
![Page 3: 1 Operating the Power Grid: Current Scenario and Challenges Ahead V. K. AGRAWAL General Manager SRLDC, Bangalore 8 th November, 2006.](https://reader035.fdocuments.us/reader035/viewer/2022062519/5697bfd31a28abf838cabf37/html5/thumbnails/3.jpg)
3
REGIONAL GRIDS
QUICK FACTS
![Page 4: 1 Operating the Power Grid: Current Scenario and Challenges Ahead V. K. AGRAWAL General Manager SRLDC, Bangalore 8 th November, 2006.](https://reader035.fdocuments.us/reader035/viewer/2022062519/5697bfd31a28abf838cabf37/html5/thumbnails/4.jpg)
4
SOUTHERN REGION
WESTERNREGION
EASTERN REGION
NORTHERN REGION
NORTH-EASTERN REGION
INSTALLED CAPACITY
NORTHERN :- 34,207 MW
EASTERN :- 16,478 MW
SOUTHERN :- 36,921 MW
WESTERN :- 37,100 MW
NORTH-EASTERN :- 2,404 MW
TOTAL 127,110 MW
REGIONAL GRIDS
![Page 5: 1 Operating the Power Grid: Current Scenario and Challenges Ahead V. K. AGRAWAL General Manager SRLDC, Bangalore 8 th November, 2006.](https://reader035.fdocuments.us/reader035/viewer/2022062519/5697bfd31a28abf838cabf37/html5/thumbnails/5.jpg)
5
Inter Regional Links – Current Capacity
2700 MW2700 MW
1200MW1200MW
2000MW2000MW
1200 MW1200 MW
900 MW900 MW33,782 MW
16,680
34,867 MW
36,031 MW
2433
1850 MW1850 MW
1650 MW1650 MW
Present IR Present IR Capacity = Capacity = 11,500 MW11,500 MW
![Page 6: 1 Operating the Power Grid: Current Scenario and Challenges Ahead V. K. AGRAWAL General Manager SRLDC, Bangalore 8 th November, 2006.](https://reader035.fdocuments.us/reader035/viewer/2022062519/5697bfd31a28abf838cabf37/html5/thumbnails/6.jpg)
6
11850 MW
1200 MW6050 MW
5500 MW
1400 MW6150 MW
36,700 MW OF INTER-REGIONAL POWER BY 2012
EASTERN REGION
SOUTHERN REGION
WESTERNREGION
NORTHERN REGION
NORTH-EASTERN REGION
INTER-REGIONAL TRANSFER BY END OF 11th PLAN (2012)
4000 MW
![Page 7: 1 Operating the Power Grid: Current Scenario and Challenges Ahead V. K. AGRAWAL General Manager SRLDC, Bangalore 8 th November, 2006.](https://reader035.fdocuments.us/reader035/viewer/2022062519/5697bfd31a28abf838cabf37/html5/thumbnails/7.jpg)
7
TRANSMISSION VOLTAGE
OWNERSHIP TOTAL
CENTRAL STATE
Circuit Kilometer
+ 500 kV HVDC
4,372 1,504 5,876
765 kV charged at 400 kV
917 409 1,326
400 kV 40,854 22,607 63,461
220 kV 9,220 98,521 107,741
132 kV* 2,152 93,126 95,278
Total 57,515 216,167 273,682
EHV Infrastructure
![Page 8: 1 Operating the Power Grid: Current Scenario and Challenges Ahead V. K. AGRAWAL General Manager SRLDC, Bangalore 8 th November, 2006.](https://reader035.fdocuments.us/reader035/viewer/2022062519/5697bfd31a28abf838cabf37/html5/thumbnails/8.jpg)
8
68 0 72 0 76 0 88 0 92 0 96 080 0 84 0
S S
W W
NN
EE
NE
82.5 0
L
GEO POLITICAL
POWER REGIONS
B’DESH-
SRI
NEPALBHUTAN
INDIAINDIA
J&K
HPPUNJAB
HARIANA
RAJASTHANUP
MP
BIHAR
ORISSA
WBGUJARAT
MAHARASHTRA
KARNATAKA
TAMIL
NADU
AP
ASSAM
MNP
MIZTRP
NG
ME
LAKSHADWEEP
A&N
MYANMAR
SKM
PONDICHERY
DELHI
GOA
DIU
DAMAN
NER NER
LANKA
JKND
CTGR
UTTARANCHAL
![Page 9: 1 Operating the Power Grid: Current Scenario and Challenges Ahead V. K. AGRAWAL General Manager SRLDC, Bangalore 8 th November, 2006.](https://reader035.fdocuments.us/reader035/viewer/2022062519/5697bfd31a28abf838cabf37/html5/thumbnails/9.jpg)
9
Ministry of Power, Govt of India
MOP, State Govt.
Central Sector Companies
• Generating Utilities- NTPC, NHPC, NEEPCO, NPCIL
• Transmission Utility- POWERGRID
• APEX BODY -RLDC
• Finance-PFC
• Rural Electrification- REC
Authorities
CEA
R&D
CPRI, NPTI, PSTI
Mega IPPs
State Sector
• Generation
• Transmission
• DistributionState IPPs
CERC
SERC
Appellate
Tribunal
Trading Co.
Pvt. DISCOM
Indian Power Sector - Institutional Framework
![Page 10: 1 Operating the Power Grid: Current Scenario and Challenges Ahead V. K. AGRAWAL General Manager SRLDC, Bangalore 8 th November, 2006.](https://reader035.fdocuments.us/reader035/viewer/2022062519/5697bfd31a28abf838cabf37/html5/thumbnails/10.jpg)
10
INDIAN POWER SECTOR - HIERARCHICAL SET UP
AND TYPICAL FUNCTIONS
CEA
CENTRAL ELECTRICITY AUTHORITY
UNDER CENTRAL GOVT.,POWER MINISTRY
PLANNING, SPECIFYING TECHNICAL STANDARADS, PROMOTE RESEARCH AND MEASURES FOR ADVANCING THE SKILLS AND ASSISTING & ADVISING THE GOVT
CERC
CENTRAL ELECTRICITY REGULATORY COMMISSION
CENTRAL REGULATOR
CENTRAL GOVT.
RPC
REGIONAL POWER COMMITTEE (FORMERLY REB) – ONE AT EACH REGION
COMMITTEE FOR FACILITATING THE INTRGRATED OPERATION IN THE REGION
CTU
RLDC
REGIONAL LOAD DESPATCH CENTRE –
APEX BODY –
TO ENSURE INTEGRATED OPERATION OF THE SYSTEM IN THE REGION
CGS
CENTRAL GENERATING STATIONS
CENTRAL STATIONS HAVING GENERATION CAPACITY ALLOCATED TO DIFFERENT
STATES ON LONG TERM BASIS
SERC
STATE GOVT.
IPP
CENTRAL TRANSMISSION UTILITY
TO UNDER TAKE TRANSMISSION OF ELECTRICITY THROUGH ISTS AND ITS PLANNING, COORDINATION, DEVELOPMENT AND TO PROVIDE
NON- DISCREMENATORY OPEN ACCESS
CPP
SGCSTU
SLDC
DISCOMS
CONSUMERS
STATE ELECTRICITY REGULATORY COMMISSION
STATE GENERATING STATIONS
OWNED BY GENCO’S/SEB’S
INDEPENDENT POWER PRODUCERS
CAPTIVE POWER PLANTSTATE TRANSMISSION
UTILTY
RESPECTIVE TRANSC’S/SEB
STATE LOAD DESPATCH CENTRE
DISTRIBUTION COMPANIES –
FORMED AFTER UNBUNDLING
![Page 11: 1 Operating the Power Grid: Current Scenario and Challenges Ahead V. K. AGRAWAL General Manager SRLDC, Bangalore 8 th November, 2006.](https://reader035.fdocuments.us/reader035/viewer/2022062519/5697bfd31a28abf838cabf37/html5/thumbnails/11.jpg)
11
ALL INDIA MARKET COMPOSITION
5%9%
3%
46%
37%
State Sector long termPPACentral Sector longterm PPAIPP generation
Short Term Trading
Balancing market
(1,27,110 in 2006) AS on 31-07-06
![Page 12: 1 Operating the Power Grid: Current Scenario and Challenges Ahead V. K. AGRAWAL General Manager SRLDC, Bangalore 8 th November, 2006.](https://reader035.fdocuments.us/reader035/viewer/2022062519/5697bfd31a28abf838cabf37/html5/thumbnails/12.jpg)
12
3310, 3%6158, 5% 32135, 26%
82227, 66%
HydroThermalNuclearWind & Others
Source wise composition of installed capacity in India (1,27,110 in 2006) AS on 31-07-06
![Page 13: 1 Operating the Power Grid: Current Scenario and Challenges Ahead V. K. AGRAWAL General Manager SRLDC, Bangalore 8 th November, 2006.](https://reader035.fdocuments.us/reader035/viewer/2022062519/5697bfd31a28abf838cabf37/html5/thumbnails/13.jpg)
13
ALL INDIA GENERATION COMPOSITION
16.8, (3%)
486.1, (83%)
84.5, (14%)
ThermalHydroNuclear
Total Market Size = 587.4 BU
Total Installed Capacity 1,27,110 MW
![Page 14: 1 Operating the Power Grid: Current Scenario and Challenges Ahead V. K. AGRAWAL General Manager SRLDC, Bangalore 8 th November, 2006.](https://reader035.fdocuments.us/reader035/viewer/2022062519/5697bfd31a28abf838cabf37/html5/thumbnails/14.jpg)
14
Sector wise consumption of electricity in India
22%
29%
5%
35%
6%
3%
IndustryDomesticRailwaysAgricultureCommercialOthers
Total Installed Capacity 1,27,110 MW
![Page 15: 1 Operating the Power Grid: Current Scenario and Challenges Ahead V. K. AGRAWAL General Manager SRLDC, Bangalore 8 th November, 2006.](https://reader035.fdocuments.us/reader035/viewer/2022062519/5697bfd31a28abf838cabf37/html5/thumbnails/15.jpg)
15
SOUTHERN REGIONAL GRID
OVERVIEW
![Page 16: 1 Operating the Power Grid: Current Scenario and Challenges Ahead V. K. AGRAWAL General Manager SRLDC, Bangalore 8 th November, 2006.](https://reader035.fdocuments.us/reader035/viewer/2022062519/5697bfd31a28abf838cabf37/html5/thumbnails/16.jpg)
16
SOUTHERN REGION – GEOGRAPHY
ANDHRA PRADESH
TAMIL NADU
KARNATAKA
KE
RA
LA
POPULATION :- 22.5 CRORES ( 22% OF INDIA)
AREA :- 651 (‘000 SQ KM)(19% OF INDIA)
INSTALLED CAPACITY:- 36,921 MW(29.0%)
WEATHER :- South-west monsoon
North-east monsoon
SEA COAST :- AROUND 4000 KM
![Page 17: 1 Operating the Power Grid: Current Scenario and Challenges Ahead V. K. AGRAWAL General Manager SRLDC, Bangalore 8 th November, 2006.](https://reader035.fdocuments.us/reader035/viewer/2022062519/5697bfd31a28abf838cabf37/html5/thumbnails/17.jpg)
17
SR STATES – POWER SYSTEM STATISTICSANDHRA PRADESH
INSTALLED CAPACITY – 8944 MW
MAX DEMAND MET – 8241 MW
DAILY CONSUMPTION MAX – 171 MU
DAILY CONSUMPTION AVG – 142 MU
CONSUMER PROFILE –
INDS -27%, DOM-22%, COMM-5%, IRRI-39% & OTHERS-7%
KARNATAKA
INSTALLED CAPACITY – 6180 MW
MAX DEMAND MET – 5612 MW
DAILY CONSUMPTION MAX – 125 MU
DAILY CONSUMPTION AVG – 95 MU
CONSUMER PROFILE –
INDS -26%, DOM-19%, COMM-7%, IRRI-39% & OTHERS-9%
KERALA
INSTALLED CAPACITY – 2284 MW
MAX DEMAND MET – 2602 MW
DAILY CONSUMPTION MAX – 41 MU
DAILY CONSUMPTION AVG – 34 MU
CONSUMER PROFILE –
INDS -34%, DOM-44%, COMM-13%, IRRI-2%& OTHERS-7%
TAMIL NADU
INSTALLED CAPACITY – 10015 MW
MAX DEMAND MET – 8371 MW
DAILY CONSUMPTION MAX – 166 MU
DAILY CONSUMPTION AVG – 135 MU
CONSUMER PROFILE –
INDS -39%, DOM-25%, COMM-7%, IRRI-24% & OTHERS-5%
![Page 18: 1 Operating the Power Grid: Current Scenario and Challenges Ahead V. K. AGRAWAL General Manager SRLDC, Bangalore 8 th November, 2006.](https://reader035.fdocuments.us/reader035/viewer/2022062519/5697bfd31a28abf838cabf37/html5/thumbnails/18.jpg)
18
ANDHRA PRADESH
POPULATION :- 7.6 CRORES
AREA :- 275 (‘000 SQ KM)
NO OF CONSUMERS :- 162 LAKHS
PER CAPITA CONS. :- 719 UNITS
MAIN AGRICULTURE CROP :- RICE
CLIMATIC CONDITION :- HOT AND HOT & HUMID
SR STATES – GEOGRAPHYKARNATAKA
POPULATION :- 5.3 CRORES
AREA :- 192 (‘000 SQ KM)
NO OF CONSUMERS :- 105 LAKHS
PER CAPITA CONS. :- 642 UNITS
MAIN AGRICULTURE CROP :- COFFEE & RAGI
CLIMATIC CONDITION :- HOT AND HOT & HUMID
KERALA
POPULATION :- 3.2 CRORES
AREA :- 39 (‘000 SQ KM)
NO OF CONSUMERS :- 61 LAKHS
PER CAPITA CONS. :- 386 UNITS
MAIN AGRICULTURE CROP :- COCONUT & SPICES
CLIMATIC CONDITION :- HUMID
TAMIL NADU
POPULATION :- 6.2 CRORES
AREA :- 130 (‘000 SQ KM)
NO OF CONSUMERS :- 152 LAKHS
PER CAPITA CONS. :- 866 UNITS
MAIN AGRICULTURE CROP :- SUGAR CANE & OIL SEEDS
CLIMATIC CONDITION :- HOT AND HOT & HUMID
![Page 19: 1 Operating the Power Grid: Current Scenario and Challenges Ahead V. K. AGRAWAL General Manager SRLDC, Bangalore 8 th November, 2006.](https://reader035.fdocuments.us/reader035/viewer/2022062519/5697bfd31a28abf838cabf37/html5/thumbnails/19.jpg)
19
INSTALLED CAPACITY IN SRSUMMARY OF INSTALLED CAPACITY(MW)
AS ON 31.07.2006
AGENCY HYDRO THERMAL GAS/DIESEL WIND/OTHERS NUCLEAR TOTAL
ANDHRA PRADESH 3587 2963 272 2 --- 6824
KARNATAKA 3389 1470 128 4 --- 4991
KERALA 1835 --- 235 2 --- 2072
TAMILNADU 2137 2970 423 19 --- 5549
PONDICHERRY --- --- 32 --- --- 32
CENTRAL SECTOR --- 8090 360 --- 880 9330
IPP 278 387 3149 4309 --- 8123
TOTAL
11226 (30%)
15880 (43%)
4599 (13%)
4336 (12%)
880 (2%)
36921 (100%)
![Page 20: 1 Operating the Power Grid: Current Scenario and Challenges Ahead V. K. AGRAWAL General Manager SRLDC, Bangalore 8 th November, 2006.](https://reader035.fdocuments.us/reader035/viewer/2022062519/5697bfd31a28abf838cabf37/html5/thumbnails/20.jpg)
20
11226(30%)
15880(43%)
4337(12%)
880(2%)
4599(13%)
SOURCE-WISE INSTALLED CAPACITY OF SR
All Figures In MW
TOTAL 36,921 MW
HYDRO
THERMAL
WIND/OTHERS NUCLEAR
NAPTHA/GAS/DIESEL
![Page 21: 1 Operating the Power Grid: Current Scenario and Challenges Ahead V. K. AGRAWAL General Manager SRLDC, Bangalore 8 th November, 2006.](https://reader035.fdocuments.us/reader035/viewer/2022062519/5697bfd31a28abf838cabf37/html5/thumbnails/21.jpg)
GENERATING UNITS IN SOUTHERN REGION
A.PKAR
TNKERGENERATORS ABOVE 1000 MW
GENERATORS 500 – 1000 MW
GENERATORS BELOW 500 MW
TYPICAL
GENERATOR
SPREAD
IN SR
UNIT CAPACITY AP KAR KER TN CGS TOTAL
THERMAL (500 MW) 2 8 10
THERMAL
(200-250 MW)10 7 13 15 45
GAS/THERMAL
(100-150 MW)9 2 3 10 24
HYDRO
(>50 MW)27 29 16 15 87
TOTAL 48 38 19 38 165
- HYDRO
- THERMAL
- GAS / NAPTHA
- NUCLEAR
![Page 22: 1 Operating the Power Grid: Current Scenario and Challenges Ahead V. K. AGRAWAL General Manager SRLDC, Bangalore 8 th November, 2006.](https://reader035.fdocuments.us/reader035/viewer/2022062519/5697bfd31a28abf838cabf37/html5/thumbnails/22.jpg)
CPP/IPP PLANTS IN SOUTHERN REGION
A.P
KAR
TNKER
Station Name I/C in MW
Variable Cost (Ps)
TATA ELECTRIC 79.1 390
JINDAL 260 280
THANNEERBAVI 220 500
Station Name I/C in MW
Variable Cost (Ps)
KASARGOD PCL 22 470
BSES 157 560
KUTHUNGAL 21 ---
MANIYAR 12 ---
KAYAMKULAM 360 580
Station Name I/C in MW
Variable Cost (Ps)
HITEC 15
TCPL 63.5
GMR VASAVI 196 444
SAMALPATTY 105 474
ST-CMS 250 161
P P NALLUR 330.5 550
ABAN 113 88
MADURAI POWER 106 456
ARKAY 38
Station Name I/C MW
Variable Cost (Ps)
SIMHADRI 1000 104
BSES 220 168
VEMAGIRI PGL 233
SPECTRUM 208 104
JEGURUPADU EXT.
220
JEGURUPADU 216 102
LANCO 355 125
![Page 23: 1 Operating the Power Grid: Current Scenario and Challenges Ahead V. K. AGRAWAL General Manager SRLDC, Bangalore 8 th November, 2006.](https://reader035.fdocuments.us/reader035/viewer/2022062519/5697bfd31a28abf838cabf37/html5/thumbnails/23.jpg)
23
LOAD 500-1500 MW
LOAD 200-500 MW
TYPICAL
LOAD
SPREAD
IN SR
![Page 24: 1 Operating the Power Grid: Current Scenario and Challenges Ahead V. K. AGRAWAL General Manager SRLDC, Bangalore 8 th November, 2006.](https://reader035.fdocuments.us/reader035/viewer/2022062519/5697bfd31a28abf838cabf37/html5/thumbnails/24.jpg)
KHAMMAM
VIJAYAWADANAGARJUNASAGAR
GAZUWAKA
HYDERABAD
RAICHUR
GOOTY
HOODY
SALEM
UDUMALPET
TRICHUR
MADURAI
TRICHY
MADRAS
NEYVELI
CUDDAPAH
DAVANAGERE
RAMAGUNDAM
BANGALORE
MUNIRABAD
PP
P
P
P
P
P
P
P
P
P
PP
P
KOLAR
63
HOSUR
1
60
P
NELLORE
NELAMANGALA
KURNOOL
KALPAKKA
SIMHADRI
HIRIYUR
TALAGUPPA
MAMIDIPALLY
SRI SAILAM
-- OF NTPC
-- OF ANDHRA PRADESH
-- OF TAMIL NADU
-- OF NLC
-- OF POWERGRID
400KV SUB-STATIONS IN SR
NEYVELI TPS I (EXP)
POWERGRID STATE OTHERS TOTAL
AP 8 9 2 19
KAR 6 5 1 12
KER 2 2
TN 6 1 2 9
TOTAL 22 15 5 42
TRIVENDRUM
NARENDRA
VEMAGIRIGMR
JEGRUPADU EXTN
MEHA BOOB NAGAR
CHITTOOR
-- OF NPC
KAIGA
MYSORE
-- OF KARNATAKA
ALMATHI
![Page 25: 1 Operating the Power Grid: Current Scenario and Challenges Ahead V. K. AGRAWAL General Manager SRLDC, Bangalore 8 th November, 2006.](https://reader035.fdocuments.us/reader035/viewer/2022062519/5697bfd31a28abf838cabf37/html5/thumbnails/25.jpg)
25
TRANSMISSION IN SOUTHERN INDIA
ABOUT 3000 CKM OF 400 KV LINES ADDED IN THE PAST 2 YEARS
VOLTAGE LEVEL AP KAR KER TN CGS TOTAL
400 KV 2680 1616 10905 15201
220/230 KV 10274 7839 2692 6538 366 27709
132/110 KV 12360 6060 3720 10220 32360
TOTAL 25314 15515 6412 16758 11271 75270
![Page 26: 1 Operating the Power Grid: Current Scenario and Challenges Ahead V. K. AGRAWAL General Manager SRLDC, Bangalore 8 th November, 2006.](https://reader035.fdocuments.us/reader035/viewer/2022062519/5697bfd31a28abf838cabf37/html5/thumbnails/26.jpg)
26
10000
12000
14000
16000
18000
20000
22000
24000
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
TYPICAL LOAD CURVE OF SR
WINTER
MONSOON
SUMMER
EVENING PEAK
CONSUMPTION
![Page 27: 1 Operating the Power Grid: Current Scenario and Challenges Ahead V. K. AGRAWAL General Manager SRLDC, Bangalore 8 th November, 2006.](https://reader035.fdocuments.us/reader035/viewer/2022062519/5697bfd31a28abf838cabf37/html5/thumbnails/27.jpg)
27
GRID CONTROL
ISSUES & CARDINAL EVENTS
![Page 28: 1 Operating the Power Grid: Current Scenario and Challenges Ahead V. K. AGRAWAL General Manager SRLDC, Bangalore 8 th November, 2006.](https://reader035.fdocuments.us/reader035/viewer/2022062519/5697bfd31a28abf838cabf37/html5/thumbnails/28.jpg)
28
GRID OPERATION – TYPICAL ISSUES IN PAST
• LOW / HIGH FREQUENCY PROBLEMS
– FREQUENCY EXCURSES TO LOW/HIGH VALUES
• LOW / HIGH VOLTAGE OPERATION
– CRITICALLY LOW VOLTAGES AT LOAD CENTRES
– SUBSTANTIALLY HIGH VOLTAGES AT FAR ENDS
• SYSTEM BROWNOUTS / BLACK OUTS
– SEPERATION OF SYSTEMS / LOSS OF LOAD
• ECONOMIC IN-STABILITY / INCREASED ELECTRICAL LOSSES– UNRELIABLE / INEFFICIENT OPERATION OF EQUIPMENT
![Page 29: 1 Operating the Power Grid: Current Scenario and Challenges Ahead V. K. AGRAWAL General Manager SRLDC, Bangalore 8 th November, 2006.](https://reader035.fdocuments.us/reader035/viewer/2022062519/5697bfd31a28abf838cabf37/html5/thumbnails/29.jpg)
29
GRID OPERATION – PRESENT STATUS
STABILISED SYSTEM FREQUENCY
IMPROVED VOLTAGES
MERIT ORDER OPERATION
INTER REGIONAL EXCHANGES
IMPROVED GRID SECURITY
![Page 30: 1 Operating the Power Grid: Current Scenario and Challenges Ahead V. K. AGRAWAL General Manager SRLDC, Bangalore 8 th November, 2006.](https://reader035.fdocuments.us/reader035/viewer/2022062519/5697bfd31a28abf838cabf37/html5/thumbnails/30.jpg)
30
GRID PRESENT STATUS -- CARDINAL EVENTS
• AVAILABILITY BASED TARIFF
• UNIFIED LOAD DESPATCH SCHEME
• GENERATION ADDITION
• INTERREGIONAL AC / HVDC LINKS
• SHORT TERM OPEN ACCESS
• OPERATIONAL EXELLANCE
ABT UI
ULDC
![Page 31: 1 Operating the Power Grid: Current Scenario and Challenges Ahead V. K. AGRAWAL General Manager SRLDC, Bangalore 8 th November, 2006.](https://reader035.fdocuments.us/reader035/viewer/2022062519/5697bfd31a28abf838cabf37/html5/thumbnails/31.jpg)
31
Components of inter-utility tariff(Pre – ABT Mechanism)
COMPOSITE TARIFF COMPRISING OF :
Fixed charges Interest on loans Depreciation O & M charges Return on equity Interest on Working Capital
Energy charges (fuel cost) Surcharge & other levies
![Page 32: 1 Operating the Power Grid: Current Scenario and Challenges Ahead V. K. AGRAWAL General Manager SRLDC, Bangalore 8 th November, 2006.](https://reader035.fdocuments.us/reader035/viewer/2022062519/5697bfd31a28abf838cabf37/html5/thumbnails/32.jpg)
32
Components under Availability Based Tariff (ABT)
TARIFF CONSISTS OF MAINLY
THREE COMPONENTS :Capacity charges
Energy charges
Unscheduled Interchange (UI)
![Page 33: 1 Operating the Power Grid: Current Scenario and Challenges Ahead V. K. AGRAWAL General Manager SRLDC, Bangalore 8 th November, 2006.](https://reader035.fdocuments.us/reader035/viewer/2022062519/5697bfd31a28abf838cabf37/html5/thumbnails/33.jpg)
33
0
50
100
150
200
250
300
350
400
450
500
550
600
650
48.9 49 49.1 49.2 49.3 49.4 49.5 49.6 49.7 49.8 49.9 50 50.1 50.2 50.3 50.4 50.5 50.6 50.7 50.8 50.9 51
Frequency ----------->
UI ra
te
-----
------
------
>
Below 49.0 Hz UI rate =570 p/u
At 50.0 Hz UI rate =150 p/u
At 49.8 Hz UI rate =210 p/u
Above 50.5 Hz UI rate =0 p/u
UI RATE
Rate of Unscheduled Drawal/InjectionFrequency (Hz) Rate (p/u)
Above 50.5 0
50.0 150
49.8 210
49.0 and below 570
![Page 34: 1 Operating the Power Grid: Current Scenario and Challenges Ahead V. K. AGRAWAL General Manager SRLDC, Bangalore 8 th November, 2006.](https://reader035.fdocuments.us/reader035/viewer/2022062519/5697bfd31a28abf838cabf37/html5/thumbnails/34.jpg)
34
UI - A RATIONAL AND SCIENTIFIC VECTOR
BALANCING MARKET
MERIT ORDER OPERATION
TRANSPARENCY
NEUTRALITY
SIMPLICITY
PRICE SIGNAL EASILY AVAILABLE
NO NEED TO NEGOTIATE ANY PRICE
EASY SETTLEMENT
EASY TO UNDERSTAND AND IMPLEMENT
EASE OF REGULATION
![Page 35: 1 Operating the Power Grid: Current Scenario and Challenges Ahead V. K. AGRAWAL General Manager SRLDC, Bangalore 8 th November, 2006.](https://reader035.fdocuments.us/reader035/viewer/2022062519/5697bfd31a28abf838cabf37/html5/thumbnails/35.jpg)
35RTU RTU RTU
SUB LDC SUB LDC SUB LDC
SLDC SLDC SLDC
ERLDC
WRLDC NRLDC SRLDC
NERLDC
NLDC
32 Nos.
51 Nos.
1160Nos.
Unified Grid OperationUnified Grid Operation
5 Nos.
NationalLevel
RegionalLevel
State HQLevel
Group / Distt Level
Plant / Sub-Station Level
![Page 36: 1 Operating the Power Grid: Current Scenario and Challenges Ahead V. K. AGRAWAL General Manager SRLDC, Bangalore 8 th November, 2006.](https://reader035.fdocuments.us/reader035/viewer/2022062519/5697bfd31a28abf838cabf37/html5/thumbnails/36.jpg)
36
RLDC,Bangalore
KalamasseryHyderabad BangaloreChennai
Cuddapah
Warangal
Vijayawada
Kalam’erry
Kannur
Trivandrum
Chennai
Erode
Madurai
Bangalore
Lingusugur
Hubli
CPCC SCC, Pondy
Hyderabad
Hierarchy of The ULDC Scheme in Southern Region
Andhra Kerala Tamilnadu Karnataka
![Page 37: 1 Operating the Power Grid: Current Scenario and Challenges Ahead V. K. AGRAWAL General Manager SRLDC, Bangalore 8 th November, 2006.](https://reader035.fdocuments.us/reader035/viewer/2022062519/5697bfd31a28abf838cabf37/html5/thumbnails/37.jpg)
37
Southern Region Grid Complexities in Monitoring & Control
Annual Inter-Regional Energy Transfer
≈10,000MU
Transformers (220kV and
above)480 nos.
Installed Capacity
≈36031 MW
Integrated Opn
of Ten Power Utilities
Dynamic Grid
Conditions
Generators –Hydro,
Thermal,Gas/IPP
422 nos.
Transmission
Network 400/220kV
≈ 40700 Ckm
30,000 POINTSActive Power, Reactive
Power,Voltage, Frequency,
TransformerTap Position, Circuit
Breaker Position, Isolator Position etc
Transformation
Capacity ≈45000 MVA
![Page 38: 1 Operating the Power Grid: Current Scenario and Challenges Ahead V. K. AGRAWAL General Manager SRLDC, Bangalore 8 th November, 2006.](https://reader035.fdocuments.us/reader035/viewer/2022062519/5697bfd31a28abf838cabf37/html5/thumbnails/38.jpg)
38
GROWTH OF INSTALLED CAPACITY OF SR
1947
5
1983
0
2030
4
2129
8
2213
3
2298
3
2417
3
2616
3 2850
1
2952
6 3273
3 3603
1
10000
15000
20000
25000
30000
35000
40000
1994-95 1995-96 1996-97 1997-98 1998-99 1999-00 2000-01 2001-02 2002-03 2003-04 2004-05 2005-06
YEARS - - ->
IN MW
![Page 39: 1 Operating the Power Grid: Current Scenario and Challenges Ahead V. K. AGRAWAL General Manager SRLDC, Bangalore 8 th November, 2006.](https://reader035.fdocuments.us/reader035/viewer/2022062519/5697bfd31a28abf838cabf37/html5/thumbnails/39.jpg)
39
KADAMPARAI PUMP OPERATION
-300
-200
-100
0
100
200
300
400
5000:
001:
002:
003:
004:
005:
006:
007:
008:
009:
0010
:00
11:0
012
:00
13:0
014
:00
15:0
016
:00
17:0
018
:00
19:0
020
:00
21:0
022
:00
23:0
00:
00
TIME ---->
IN M
W --
-->
48.50
49.00
49.50
50.00
50.50
51.00
FREQ
UENC
Y IN
HZ
---->
GENERATOR MODE
PUMP PUMP
![Page 40: 1 Operating the Power Grid: Current Scenario and Challenges Ahead V. K. AGRAWAL General Manager SRLDC, Bangalore 8 th November, 2006.](https://reader035.fdocuments.us/reader035/viewer/2022062519/5697bfd31a28abf838cabf37/html5/thumbnails/40.jpg)
40
KADAMPARAI ENERGY GENERATED/PUMPED DURING LAST 5 YEARS (MU)
MONTHS2001-02 2002-03 2003-04 2004-05 * 2005-06
GENERATOR MODE
GENERATOR MODE
GENERATOR MODE
PUMP MODE
GENERATOR MODE
PUMP MODE
GENERATOR MODE
PUMP MODE
APRIL 0.1 3.9 35.0 40.0 26.0 35.0 0.0 2.6
MAY 0.0 1.4 37.0 43.0 41.0 48.0 29.6 45.7
JUNE 1.0 6.4 29.0 45.0 55.0 35.0 45.3 51.2
JULY 27.5 6.9 47.0 49.0 50.0 49.0 79.0 62.3
AUGUST 21.4 8.8 54.0 55.0 55.0 41.0 49.5 25.0
SEPTEMBER 11.0 8.6 36.0 48.0 30.0 25.0 40.8 15.2
OCTOBER 19.5 18.5 26.0 15.0 0.0 0.0 46.9 45.1
NOVEMBER 17.9 16.7 23.0 24.0 0.0 0.0 64.1 59.2
DECEMBER 20.3 20.5 49.0 53.0 0.0 0.0 70.0 62.5
JANUARY 18.4 39.0 44.0 58.0 0.0 0.0 72.0 92.9
FEBRUARY 14.0 39.0 21.0 21.0 0.0 0.0 53.3 55.6
MARCH 5.7 32.0 6.0 18.0 0.0 0.0 30.9 37.9
TOTAL 156.7 201.8 407.0 469.0 257.0 233.0 581.4 555.3
Note: The plant was under shutdown from 16th Sep 2004 to 28th April 05 for dam maintenance works.
![Page 41: 1 Operating the Power Grid: Current Scenario and Challenges Ahead V. K. AGRAWAL General Manager SRLDC, Bangalore 8 th November, 2006.](https://reader035.fdocuments.us/reader035/viewer/2022062519/5697bfd31a28abf838cabf37/html5/thumbnails/41.jpg)
41
KADAMPARAI ENERGY GENERATED/PUMPED DURING LAST 5 YEARS (MU)
157
202
407
257
581
469
233
555
0
100
200
300
400
500
600
700
2001-02 2002-03 2003-04 2004-05 2005-06
Generation Pumped
![Page 42: 1 Operating the Power Grid: Current Scenario and Challenges Ahead V. K. AGRAWAL General Manager SRLDC, Bangalore 8 th November, 2006.](https://reader035.fdocuments.us/reader035/viewer/2022062519/5697bfd31a28abf838cabf37/html5/thumbnails/42.jpg)
42
LOW DEMAND(VALLEYS)
SHARP PEAKS
0000 HRS OF 01 SEP 06
29 AUG 06 30 AUG 06 31 AUG 06
![Page 43: 1 Operating the Power Grid: Current Scenario and Challenges Ahead V. K. AGRAWAL General Manager SRLDC, Bangalore 8 th November, 2006.](https://reader035.fdocuments.us/reader035/viewer/2022062519/5697bfd31a28abf838cabf37/html5/thumbnails/43.jpg)
43
GENERATION vs FREQUENCY FOR
10
30
50
70
90
08
:21
09
:21
10
:21
11
:21
TIME IN HH:MM ----->
MW
---
-->
49.00
49.20
49.40
49.60
49.80
50.00
50.20
50.40
FR
EQ
IN
HZ
---
-->
GENERATING UNITS PARTICIPATION IN PRIMARY RESPONCE
SHARAVATHI -1
FREQ DROP FROM 49.72 HZ TO 49.27 HZ
i.e. ~ 0.45HZ
![Page 44: 1 Operating the Power Grid: Current Scenario and Challenges Ahead V. K. AGRAWAL General Manager SRLDC, Bangalore 8 th November, 2006.](https://reader035.fdocuments.us/reader035/viewer/2022062519/5697bfd31a28abf838cabf37/html5/thumbnails/44.jpg)
44
TRAINING ON ULDC SYSTEMSL NAME OF THE TRAINING FROM TO Participants Man Days
1 CISCO ROUTER & NETWORKING 19-01-2004 24-01-2004 17 102
2 XA-21 USER LEVEL 23-02-2004 28-02-2004 10 60
3 RTNA WORKSHOP 29-03-2004 31-03-2004 14 42
4 AIX OPERATING SYSTEM 17-05-2004 22-05-2004 15 90
5 XA-21 USER LEVEL 21-06-2004 25-06-2004 6 30
6 SYBASE DATABASE ADMIN 22-11-2004 04-12-2004 19 228
7 XA-21 USER LEVEL 21-02-2005 23-02-2005 7 21
8 NMS TRAINING 13-06-2005 18-06-2005 14 84
9 RTU TRAINING 27-02-2006 03-03-2006 14 70
10 JAVA FOR SCADA ENVIRONMENT 24-04-2006 29-04-2006 16 96