1 Operating the Power Grid: Current Scenario and Challenges Ahead V. K. AGRAWAL General Manager...

44
1 Largest sized hydro unit (180 M W at Cham era) in the country SalientFeatures N orthern R egionalPow er System W elcome UNUSUAL G RID OPERATING CO N DITIO N S Operating the Power Grid: Current Scenario and Challenges Ahead V. K. AGRAWAL General Manager SRLDC, Bangalore 8 th November, 2006

Transcript of 1 Operating the Power Grid: Current Scenario and Challenges Ahead V. K. AGRAWAL General Manager...

Page 1: 1 Operating the Power Grid: Current Scenario and Challenges Ahead V. K. AGRAWAL General Manager SRLDC, Bangalore 8 th November, 2006.

1

Largest sized hydro unit (180 MW at Chamera) in the country

Salient FeaturesNorthern Regional Power System

Welcome

UNUSUAL

GRID OPERATING CONDITIONS

Operating the Power Grid:

Current Scenario and Challenges Ahead

V. K. AGRAWAL

General Manager

SRLDC, Bangalore

8th November, 2006

Page 2: 1 Operating the Power Grid: Current Scenario and Challenges Ahead V. K. AGRAWAL General Manager SRLDC, Bangalore 8 th November, 2006.

2

PRESENTATION OVERVIEW

REGIONAL GRIDS IN INDIA – QUICK FACTS

SOUTHERN REGIONAL GRID – AN OVERVIEW

GRID CONTROL - ISSUES & CARDINAL EVENTS

POWER SECTOR - THRUST AREAS & ISSUES

SR GRID – PROJECTS IN PROGRESS

Page 3: 1 Operating the Power Grid: Current Scenario and Challenges Ahead V. K. AGRAWAL General Manager SRLDC, Bangalore 8 th November, 2006.

3

REGIONAL GRIDS

QUICK FACTS

Page 4: 1 Operating the Power Grid: Current Scenario and Challenges Ahead V. K. AGRAWAL General Manager SRLDC, Bangalore 8 th November, 2006.

4

SOUTHERN REGION

WESTERNREGION

EASTERN REGION

NORTHERN REGION

NORTH-EASTERN REGION

INSTALLED CAPACITY

NORTHERN :- 34,207 MW

EASTERN :- 16,478 MW

SOUTHERN :- 36,921 MW

WESTERN :- 37,100 MW

NORTH-EASTERN :- 2,404 MW

TOTAL 127,110 MW

REGIONAL GRIDS

Page 5: 1 Operating the Power Grid: Current Scenario and Challenges Ahead V. K. AGRAWAL General Manager SRLDC, Bangalore 8 th November, 2006.

5

Inter Regional Links – Current Capacity

2700 MW2700 MW

1200MW1200MW

2000MW2000MW

1200 MW1200 MW

900 MW900 MW33,782 MW

16,680

34,867 MW

36,031 MW

2433

1850 MW1850 MW

1650 MW1650 MW

Present IR Present IR Capacity = Capacity = 11,500 MW11,500 MW

Page 6: 1 Operating the Power Grid: Current Scenario and Challenges Ahead V. K. AGRAWAL General Manager SRLDC, Bangalore 8 th November, 2006.

6

11850 MW

1200 MW6050 MW

5500 MW

1400 MW6150 MW

36,700 MW OF INTER-REGIONAL POWER BY 2012

EASTERN REGION

SOUTHERN REGION

WESTERNREGION

NORTHERN REGION

NORTH-EASTERN REGION

INTER-REGIONAL TRANSFER BY END OF 11th PLAN (2012)

4000 MW

Page 7: 1 Operating the Power Grid: Current Scenario and Challenges Ahead V. K. AGRAWAL General Manager SRLDC, Bangalore 8 th November, 2006.

7

TRANSMISSION VOLTAGE

OWNERSHIP TOTAL

CENTRAL STATE

Circuit Kilometer

+ 500 kV HVDC

4,372 1,504 5,876

765 kV charged at 400 kV

917 409 1,326

400 kV 40,854 22,607 63,461

220 kV 9,220 98,521 107,741

132 kV* 2,152 93,126 95,278

Total 57,515 216,167 273,682

EHV Infrastructure

Page 8: 1 Operating the Power Grid: Current Scenario and Challenges Ahead V. K. AGRAWAL General Manager SRLDC, Bangalore 8 th November, 2006.

8

68 0 72 0 76 0 88 0 92 0 96 080 0 84 0

S S

W W

NN

EE

NE

82.5 0

L

GEO POLITICAL

POWER REGIONS

B’DESH-

SRI

NEPALBHUTAN

INDIAINDIA

J&K

HPPUNJAB

HARIANA

RAJASTHANUP

MP

BIHAR

ORISSA

WBGUJARAT

MAHARASHTRA

KARNATAKA

TAMIL

NADU

AP

ASSAM

MNP

MIZTRP

NG

ME

LAKSHADWEEP

A&N

MYANMAR

SKM

PONDICHERY

DELHI

GOA

DIU

DAMAN

NER NER

LANKA

JKND

CTGR

UTTARANCHAL

Page 9: 1 Operating the Power Grid: Current Scenario and Challenges Ahead V. K. AGRAWAL General Manager SRLDC, Bangalore 8 th November, 2006.

9

Ministry of Power, Govt of India

MOP, State Govt.

Central Sector Companies

• Generating Utilities- NTPC, NHPC, NEEPCO, NPCIL

• Transmission Utility- POWERGRID

• APEX BODY -RLDC

• Finance-PFC

• Rural Electrification- REC

Authorities

CEA

R&D

CPRI, NPTI, PSTI

Mega IPPs

State Sector

• Generation

• Transmission

• DistributionState IPPs

CERC

SERC

Appellate

Tribunal

Trading Co.

Pvt. DISCOM

Indian Power Sector - Institutional Framework

Page 10: 1 Operating the Power Grid: Current Scenario and Challenges Ahead V. K. AGRAWAL General Manager SRLDC, Bangalore 8 th November, 2006.

10

INDIAN POWER SECTOR - HIERARCHICAL SET UP

AND TYPICAL FUNCTIONS

CEA

CENTRAL ELECTRICITY AUTHORITY

UNDER CENTRAL GOVT.,POWER MINISTRY

PLANNING, SPECIFYING TECHNICAL STANDARADS, PROMOTE RESEARCH AND MEASURES FOR ADVANCING THE SKILLS AND ASSISTING & ADVISING THE GOVT

CERC

CENTRAL ELECTRICITY REGULATORY COMMISSION

CENTRAL REGULATOR

CENTRAL GOVT.

RPC

REGIONAL POWER COMMITTEE (FORMERLY REB) – ONE AT EACH REGION

COMMITTEE FOR FACILITATING THE INTRGRATED OPERATION IN THE REGION

CTU

RLDC

REGIONAL LOAD DESPATCH CENTRE –

APEX BODY –

TO ENSURE INTEGRATED OPERATION OF THE SYSTEM IN THE REGION

CGS

CENTRAL GENERATING STATIONS

CENTRAL STATIONS HAVING GENERATION CAPACITY ALLOCATED TO DIFFERENT

STATES ON LONG TERM BASIS

SERC

STATE GOVT.

IPP

CENTRAL TRANSMISSION UTILITY

TO UNDER TAKE TRANSMISSION OF ELECTRICITY THROUGH ISTS AND ITS PLANNING, COORDINATION, DEVELOPMENT AND TO PROVIDE

NON- DISCREMENATORY OPEN ACCESS

CPP

SGCSTU

SLDC

DISCOMS

CONSUMERS

STATE ELECTRICITY REGULATORY COMMISSION

STATE GENERATING STATIONS

OWNED BY GENCO’S/SEB’S

INDEPENDENT POWER PRODUCERS

CAPTIVE POWER PLANTSTATE TRANSMISSION

UTILTY

RESPECTIVE TRANSC’S/SEB

STATE LOAD DESPATCH CENTRE

DISTRIBUTION COMPANIES –

FORMED AFTER UNBUNDLING

Page 11: 1 Operating the Power Grid: Current Scenario and Challenges Ahead V. K. AGRAWAL General Manager SRLDC, Bangalore 8 th November, 2006.

11

ALL INDIA MARKET COMPOSITION

5%9%

3%

46%

37%

State Sector long termPPACentral Sector longterm PPAIPP generation

Short Term Trading

Balancing market

(1,27,110 in 2006) AS on 31-07-06

Page 12: 1 Operating the Power Grid: Current Scenario and Challenges Ahead V. K. AGRAWAL General Manager SRLDC, Bangalore 8 th November, 2006.

12

3310, 3%6158, 5% 32135, 26%

82227, 66%

HydroThermalNuclearWind & Others

Source wise composition of installed capacity in India (1,27,110 in 2006) AS on 31-07-06

Page 13: 1 Operating the Power Grid: Current Scenario and Challenges Ahead V. K. AGRAWAL General Manager SRLDC, Bangalore 8 th November, 2006.

13

ALL INDIA GENERATION COMPOSITION

16.8, (3%)

486.1, (83%)

84.5, (14%)

ThermalHydroNuclear

Total Market Size = 587.4 BU

Total Installed Capacity 1,27,110 MW

Page 14: 1 Operating the Power Grid: Current Scenario and Challenges Ahead V. K. AGRAWAL General Manager SRLDC, Bangalore 8 th November, 2006.

14

Sector wise consumption of electricity in India

22%

29%

5%

35%

6%

3%

IndustryDomesticRailwaysAgricultureCommercialOthers

Total Installed Capacity 1,27,110 MW

Page 15: 1 Operating the Power Grid: Current Scenario and Challenges Ahead V. K. AGRAWAL General Manager SRLDC, Bangalore 8 th November, 2006.

15

SOUTHERN REGIONAL GRID

OVERVIEW

Page 16: 1 Operating the Power Grid: Current Scenario and Challenges Ahead V. K. AGRAWAL General Manager SRLDC, Bangalore 8 th November, 2006.

16

SOUTHERN REGION – GEOGRAPHY

ANDHRA PRADESH

TAMIL NADU

KARNATAKA

KE

RA

LA

POPULATION :- 22.5 CRORES ( 22% OF INDIA)

AREA :- 651 (‘000 SQ KM)(19% OF INDIA)

INSTALLED CAPACITY:- 36,921 MW(29.0%)

WEATHER :- South-west monsoon

North-east monsoon

SEA COAST :- AROUND 4000 KM

Page 17: 1 Operating the Power Grid: Current Scenario and Challenges Ahead V. K. AGRAWAL General Manager SRLDC, Bangalore 8 th November, 2006.

17

SR STATES – POWER SYSTEM STATISTICSANDHRA PRADESH

INSTALLED CAPACITY – 8944 MW

MAX DEMAND MET – 8241 MW

DAILY CONSUMPTION MAX – 171 MU

DAILY CONSUMPTION AVG – 142 MU

CONSUMER PROFILE –

INDS -27%, DOM-22%, COMM-5%, IRRI-39% & OTHERS-7%

KARNATAKA

INSTALLED CAPACITY – 6180 MW

MAX DEMAND MET – 5612 MW

DAILY CONSUMPTION MAX – 125 MU

DAILY CONSUMPTION AVG – 95 MU

CONSUMER PROFILE –

INDS -26%, DOM-19%, COMM-7%, IRRI-39% & OTHERS-9%

KERALA

INSTALLED CAPACITY – 2284 MW

MAX DEMAND MET – 2602 MW

DAILY CONSUMPTION MAX – 41 MU

DAILY CONSUMPTION AVG – 34 MU

CONSUMER PROFILE –

INDS -34%, DOM-44%, COMM-13%, IRRI-2%& OTHERS-7%

TAMIL NADU

INSTALLED CAPACITY – 10015 MW

MAX DEMAND MET – 8371 MW

DAILY CONSUMPTION MAX – 166 MU

DAILY CONSUMPTION AVG – 135 MU

CONSUMER PROFILE –

INDS -39%, DOM-25%, COMM-7%, IRRI-24% & OTHERS-5%

Page 18: 1 Operating the Power Grid: Current Scenario and Challenges Ahead V. K. AGRAWAL General Manager SRLDC, Bangalore 8 th November, 2006.

18

ANDHRA PRADESH

POPULATION :- 7.6 CRORES

AREA :- 275 (‘000 SQ KM)

NO OF CONSUMERS :- 162 LAKHS

PER CAPITA CONS. :- 719 UNITS

MAIN AGRICULTURE CROP :- RICE

CLIMATIC CONDITION :- HOT AND HOT & HUMID

SR STATES – GEOGRAPHYKARNATAKA

POPULATION :- 5.3 CRORES

AREA :- 192 (‘000 SQ KM)

NO OF CONSUMERS :- 105 LAKHS

PER CAPITA CONS. :- 642 UNITS

MAIN AGRICULTURE CROP :- COFFEE & RAGI

CLIMATIC CONDITION :- HOT AND HOT & HUMID

KERALA

POPULATION :- 3.2 CRORES

AREA :- 39 (‘000 SQ KM)

NO OF CONSUMERS :- 61 LAKHS

PER CAPITA CONS. :- 386 UNITS

MAIN AGRICULTURE CROP :- COCONUT & SPICES

CLIMATIC CONDITION :- HUMID

TAMIL NADU

POPULATION :- 6.2 CRORES

AREA :- 130 (‘000 SQ KM)

NO OF CONSUMERS :- 152 LAKHS

PER CAPITA CONS. :- 866 UNITS

MAIN AGRICULTURE CROP :- SUGAR CANE & OIL SEEDS

CLIMATIC CONDITION :- HOT AND HOT & HUMID

Page 19: 1 Operating the Power Grid: Current Scenario and Challenges Ahead V. K. AGRAWAL General Manager SRLDC, Bangalore 8 th November, 2006.

19

INSTALLED CAPACITY IN SRSUMMARY OF INSTALLED CAPACITY(MW)

         AS ON 31.07.2006

AGENCY HYDRO THERMAL GAS/DIESEL WIND/OTHERS NUCLEAR TOTAL

ANDHRA PRADESH 3587 2963 272 2 --- 6824

KARNATAKA 3389 1470 128 4 --- 4991

KERALA 1835 --- 235 2 --- 2072

TAMILNADU 2137 2970 423 19 --- 5549

PONDICHERRY --- --- 32 --- --- 32

CENTRAL SECTOR --- 8090 360 --- 880 9330

IPP 278 387 3149 4309 --- 8123

TOTAL

11226 (30%)

15880 (43%)

4599 (13%)

4336 (12%)

880 (2%)

36921 (100%)

Page 20: 1 Operating the Power Grid: Current Scenario and Challenges Ahead V. K. AGRAWAL General Manager SRLDC, Bangalore 8 th November, 2006.

20

11226(30%)

15880(43%)

4337(12%)

880(2%)

4599(13%)

SOURCE-WISE INSTALLED CAPACITY OF SR

All Figures In MW

TOTAL 36,921 MW

HYDRO

THERMAL

WIND/OTHERS NUCLEAR

NAPTHA/GAS/DIESEL

Page 21: 1 Operating the Power Grid: Current Scenario and Challenges Ahead V. K. AGRAWAL General Manager SRLDC, Bangalore 8 th November, 2006.

GENERATING UNITS IN SOUTHERN REGION

A.PKAR

TNKERGENERATORS ABOVE 1000 MW

GENERATORS 500 – 1000 MW

GENERATORS BELOW 500 MW

TYPICAL

GENERATOR

SPREAD

IN SR

UNIT CAPACITY AP KAR KER TN CGS TOTAL

THERMAL (500 MW) 2 8 10

THERMAL

(200-250 MW)10 7 13 15 45

GAS/THERMAL

(100-150 MW)9 2 3 10 24

HYDRO

(>50 MW)27 29 16 15 87

TOTAL 48 38 19 38 165

- HYDRO

- THERMAL

- GAS / NAPTHA

- NUCLEAR

Page 22: 1 Operating the Power Grid: Current Scenario and Challenges Ahead V. K. AGRAWAL General Manager SRLDC, Bangalore 8 th November, 2006.

CPP/IPP PLANTS IN SOUTHERN REGION

A.P

KAR

TNKER

Station Name I/C in MW

Variable Cost (Ps)

TATA ELECTRIC 79.1 390

JINDAL 260 280

THANNEERBAVI 220 500

Station Name I/C in MW

Variable Cost (Ps)

KASARGOD PCL 22 470

BSES 157 560

KUTHUNGAL 21 ---

MANIYAR 12 ---

KAYAMKULAM 360 580

Station Name I/C in MW

Variable Cost (Ps)

HITEC 15

TCPL 63.5

GMR VASAVI 196 444

SAMALPATTY 105 474

ST-CMS 250 161

P P NALLUR 330.5 550

ABAN 113 88

MADURAI POWER 106 456

ARKAY 38

Station Name I/C MW

Variable Cost (Ps)

SIMHADRI 1000 104

BSES 220 168

VEMAGIRI PGL 233

SPECTRUM 208 104

JEGURUPADU EXT.

220

JEGURUPADU 216 102

LANCO 355 125

Page 23: 1 Operating the Power Grid: Current Scenario and Challenges Ahead V. K. AGRAWAL General Manager SRLDC, Bangalore 8 th November, 2006.

23

LOAD 500-1500 MW

LOAD 200-500 MW

TYPICAL

LOAD

SPREAD

IN SR

Page 24: 1 Operating the Power Grid: Current Scenario and Challenges Ahead V. K. AGRAWAL General Manager SRLDC, Bangalore 8 th November, 2006.

KHAMMAM

VIJAYAWADANAGARJUNASAGAR

GAZUWAKA

HYDERABAD

RAICHUR

GOOTY

HOODY

SALEM

UDUMALPET

TRICHUR

MADURAI

TRICHY

MADRAS

NEYVELI

CUDDAPAH

DAVANAGERE

RAMAGUNDAM

BANGALORE

MUNIRABAD

PP

P

P

P

P

P

P

P

P

P

PP

P

KOLAR

63

HOSUR

1

60

P

NELLORE

NELAMANGALA

KURNOOL

KALPAKKA

SIMHADRI

HIRIYUR

TALAGUPPA

MAMIDIPALLY

SRI SAILAM

-- OF NTPC

-- OF ANDHRA PRADESH

-- OF TAMIL NADU

-- OF NLC

-- OF POWERGRID

400KV SUB-STATIONS IN SR

NEYVELI TPS I (EXP)

  POWERGRID STATE OTHERS TOTAL

AP 8 9 2 19

KAR 6 5 1 12

KER 2     2

TN 6  1 2 9

TOTAL 22 15 5 42

TRIVENDRUM

NARENDRA

VEMAGIRIGMR

JEGRUPADU EXTN

MEHA BOOB NAGAR

CHITTOOR

-- OF NPC

KAIGA

MYSORE

-- OF KARNATAKA

ALMATHI

Page 25: 1 Operating the Power Grid: Current Scenario and Challenges Ahead V. K. AGRAWAL General Manager SRLDC, Bangalore 8 th November, 2006.

25

TRANSMISSION IN SOUTHERN INDIA

ABOUT 3000 CKM OF 400 KV LINES ADDED IN THE PAST 2 YEARS

VOLTAGE LEVEL AP KAR KER TN CGS TOTAL

400 KV 2680 1616     10905 15201

220/230 KV 10274 7839 2692 6538 366 27709

132/110 KV 12360 6060 3720 10220   32360

TOTAL 25314 15515 6412 16758 11271 75270

Page 26: 1 Operating the Power Grid: Current Scenario and Challenges Ahead V. K. AGRAWAL General Manager SRLDC, Bangalore 8 th November, 2006.

26

10000

12000

14000

16000

18000

20000

22000

24000

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

TYPICAL LOAD CURVE OF SR

WINTER

MONSOON

SUMMER

EVENING PEAK

CONSUMPTION

Page 27: 1 Operating the Power Grid: Current Scenario and Challenges Ahead V. K. AGRAWAL General Manager SRLDC, Bangalore 8 th November, 2006.

27

GRID CONTROL

ISSUES & CARDINAL EVENTS

Page 28: 1 Operating the Power Grid: Current Scenario and Challenges Ahead V. K. AGRAWAL General Manager SRLDC, Bangalore 8 th November, 2006.

28

GRID OPERATION – TYPICAL ISSUES IN PAST

• LOW / HIGH FREQUENCY PROBLEMS

– FREQUENCY EXCURSES TO LOW/HIGH VALUES

• LOW / HIGH VOLTAGE OPERATION

– CRITICALLY LOW VOLTAGES AT LOAD CENTRES

– SUBSTANTIALLY HIGH VOLTAGES AT FAR ENDS

• SYSTEM BROWNOUTS / BLACK OUTS

– SEPERATION OF SYSTEMS / LOSS OF LOAD

• ECONOMIC IN-STABILITY / INCREASED ELECTRICAL LOSSES– UNRELIABLE / INEFFICIENT OPERATION OF EQUIPMENT

Page 29: 1 Operating the Power Grid: Current Scenario and Challenges Ahead V. K. AGRAWAL General Manager SRLDC, Bangalore 8 th November, 2006.

29

GRID OPERATION – PRESENT STATUS

STABILISED SYSTEM FREQUENCY

IMPROVED VOLTAGES

MERIT ORDER OPERATION

INTER REGIONAL EXCHANGES

IMPROVED GRID SECURITY

Page 30: 1 Operating the Power Grid: Current Scenario and Challenges Ahead V. K. AGRAWAL General Manager SRLDC, Bangalore 8 th November, 2006.

30

GRID PRESENT STATUS -- CARDINAL EVENTS

• AVAILABILITY BASED TARIFF

• UNIFIED LOAD DESPATCH SCHEME

• GENERATION ADDITION

• INTERREGIONAL AC / HVDC LINKS

• SHORT TERM OPEN ACCESS

• OPERATIONAL EXELLANCE

ABT UI

ULDC

Page 31: 1 Operating the Power Grid: Current Scenario and Challenges Ahead V. K. AGRAWAL General Manager SRLDC, Bangalore 8 th November, 2006.

31

Components of inter-utility tariff(Pre – ABT Mechanism)

COMPOSITE TARIFF COMPRISING OF :

Fixed charges Interest on loans Depreciation O & M charges Return on equity Interest on Working Capital

Energy charges (fuel cost) Surcharge & other levies

Page 32: 1 Operating the Power Grid: Current Scenario and Challenges Ahead V. K. AGRAWAL General Manager SRLDC, Bangalore 8 th November, 2006.

32

Components under Availability Based Tariff (ABT)

TARIFF CONSISTS OF MAINLY

THREE COMPONENTS :Capacity charges

Energy charges

Unscheduled Interchange (UI)

Page 33: 1 Operating the Power Grid: Current Scenario and Challenges Ahead V. K. AGRAWAL General Manager SRLDC, Bangalore 8 th November, 2006.

33

0

50

100

150

200

250

300

350

400

450

500

550

600

650

48.9 49 49.1 49.2 49.3 49.4 49.5 49.6 49.7 49.8 49.9 50 50.1 50.2 50.3 50.4 50.5 50.6 50.7 50.8 50.9 51

Frequency ----------->

UI ra

te

-----

------

------

>

Below 49.0 Hz UI rate =570 p/u

At 50.0 Hz UI rate =150 p/u

At 49.8 Hz UI rate =210 p/u

Above 50.5 Hz UI rate =0 p/u

UI RATE

Rate of Unscheduled Drawal/InjectionFrequency (Hz) Rate (p/u)

Above 50.5 0

50.0 150

49.8 210

49.0 and below 570

Page 34: 1 Operating the Power Grid: Current Scenario and Challenges Ahead V. K. AGRAWAL General Manager SRLDC, Bangalore 8 th November, 2006.

34

UI - A RATIONAL AND SCIENTIFIC VECTOR

BALANCING MARKET

MERIT ORDER OPERATION

TRANSPARENCY

NEUTRALITY

SIMPLICITY

PRICE SIGNAL EASILY AVAILABLE

NO NEED TO NEGOTIATE ANY PRICE

EASY SETTLEMENT

EASY TO UNDERSTAND AND IMPLEMENT

EASE OF REGULATION

Page 35: 1 Operating the Power Grid: Current Scenario and Challenges Ahead V. K. AGRAWAL General Manager SRLDC, Bangalore 8 th November, 2006.

35RTU RTU RTU

SUB LDC SUB LDC SUB LDC

SLDC SLDC SLDC

ERLDC

WRLDC NRLDC SRLDC

NERLDC

NLDC

32 Nos.

51 Nos.

1160Nos.

Unified Grid OperationUnified Grid Operation

5 Nos.

NationalLevel

RegionalLevel

State HQLevel

Group / Distt Level

Plant / Sub-Station Level

Page 36: 1 Operating the Power Grid: Current Scenario and Challenges Ahead V. K. AGRAWAL General Manager SRLDC, Bangalore 8 th November, 2006.

36

RLDC,Bangalore

KalamasseryHyderabad BangaloreChennai

Cuddapah

Warangal

Vijayawada

Kalam’erry

Kannur

Trivandrum

Chennai

Erode

Madurai

Bangalore

Lingusugur

Hubli

CPCC SCC, Pondy

Hyderabad

Hierarchy of The ULDC Scheme in Southern Region

Andhra Kerala Tamilnadu Karnataka

Page 37: 1 Operating the Power Grid: Current Scenario and Challenges Ahead V. K. AGRAWAL General Manager SRLDC, Bangalore 8 th November, 2006.

37

Southern Region Grid Complexities in Monitoring & Control

Annual Inter-Regional Energy Transfer

≈10,000MU

Transformers (220kV and

above)480 nos.

Installed Capacity

≈36031 MW

Integrated Opn

of Ten Power Utilities

Dynamic Grid

Conditions

Generators –Hydro,

Thermal,Gas/IPP

422 nos.

Transmission

Network 400/220kV

≈ 40700 Ckm

30,000 POINTSActive Power, Reactive

Power,Voltage, Frequency,

TransformerTap Position, Circuit

Breaker Position, Isolator Position etc

Transformation

Capacity ≈45000 MVA

Page 38: 1 Operating the Power Grid: Current Scenario and Challenges Ahead V. K. AGRAWAL General Manager SRLDC, Bangalore 8 th November, 2006.

38

GROWTH OF INSTALLED CAPACITY OF SR

1947

5

1983

0

2030

4

2129

8

2213

3

2298

3

2417

3

2616

3 2850

1

2952

6 3273

3 3603

1

10000

15000

20000

25000

30000

35000

40000

1994-95 1995-96 1996-97 1997-98 1998-99 1999-00 2000-01 2001-02 2002-03 2003-04 2004-05 2005-06

YEARS - - ->

IN MW

Page 39: 1 Operating the Power Grid: Current Scenario and Challenges Ahead V. K. AGRAWAL General Manager SRLDC, Bangalore 8 th November, 2006.

39

KADAMPARAI PUMP OPERATION

-300

-200

-100

0

100

200

300

400

5000:

001:

002:

003:

004:

005:

006:

007:

008:

009:

0010

:00

11:0

012

:00

13:0

014

:00

15:0

016

:00

17:0

018

:00

19:0

020

:00

21:0

022

:00

23:0

00:

00

TIME ---->

IN M

W --

-->

48.50

49.00

49.50

50.00

50.50

51.00

FREQ

UENC

Y IN

HZ

---->

GENERATOR MODE

PUMP PUMP

Page 40: 1 Operating the Power Grid: Current Scenario and Challenges Ahead V. K. AGRAWAL General Manager SRLDC, Bangalore 8 th November, 2006.

40

KADAMPARAI ENERGY GENERATED/PUMPED DURING LAST 5 YEARS (MU)

MONTHS2001-02 2002-03 2003-04 2004-05 * 2005-06

GENERATOR MODE

GENERATOR MODE

GENERATOR MODE

PUMP MODE

GENERATOR MODE

PUMP MODE

GENERATOR MODE

PUMP MODE

APRIL 0.1 3.9 35.0 40.0 26.0 35.0 0.0 2.6

MAY 0.0 1.4 37.0 43.0 41.0 48.0 29.6 45.7

JUNE 1.0 6.4 29.0 45.0 55.0 35.0 45.3 51.2

JULY 27.5 6.9 47.0 49.0 50.0 49.0 79.0 62.3

AUGUST 21.4 8.8 54.0 55.0 55.0 41.0 49.5 25.0

SEPTEMBER 11.0 8.6 36.0 48.0 30.0 25.0 40.8 15.2

OCTOBER 19.5 18.5 26.0 15.0 0.0 0.0 46.9 45.1

NOVEMBER 17.9 16.7 23.0 24.0 0.0 0.0 64.1 59.2

DECEMBER 20.3 20.5 49.0 53.0 0.0 0.0 70.0 62.5

JANUARY 18.4 39.0 44.0 58.0 0.0 0.0 72.0 92.9

FEBRUARY 14.0 39.0 21.0 21.0 0.0 0.0 53.3 55.6

MARCH 5.7 32.0 6.0 18.0 0.0 0.0 30.9 37.9

TOTAL 156.7 201.8 407.0 469.0 257.0 233.0 581.4 555.3

Note: The plant was under shutdown from 16th Sep 2004 to 28th April 05 for dam maintenance works.

Page 41: 1 Operating the Power Grid: Current Scenario and Challenges Ahead V. K. AGRAWAL General Manager SRLDC, Bangalore 8 th November, 2006.

41

KADAMPARAI ENERGY GENERATED/PUMPED DURING LAST 5 YEARS (MU)

157

202

407

257

581

469

233

555

0

100

200

300

400

500

600

700

2001-02 2002-03 2003-04 2004-05 2005-06

Generation Pumped

Page 42: 1 Operating the Power Grid: Current Scenario and Challenges Ahead V. K. AGRAWAL General Manager SRLDC, Bangalore 8 th November, 2006.

42

LOW DEMAND(VALLEYS)

SHARP PEAKS

0000 HRS OF 01 SEP 06

29 AUG 06 30 AUG 06 31 AUG 06

Page 43: 1 Operating the Power Grid: Current Scenario and Challenges Ahead V. K. AGRAWAL General Manager SRLDC, Bangalore 8 th November, 2006.

43

GENERATION vs FREQUENCY FOR

10

30

50

70

90

08

:21

09

:21

10

:21

11

:21

TIME IN HH:MM ----->

MW

---

-->

49.00

49.20

49.40

49.60

49.80

50.00

50.20

50.40

FR

EQ

IN

HZ

---

-->

GENERATING UNITS PARTICIPATION IN PRIMARY RESPONCE

SHARAVATHI -1

FREQ DROP FROM 49.72 HZ TO 49.27 HZ

i.e. ~ 0.45HZ

Page 44: 1 Operating the Power Grid: Current Scenario and Challenges Ahead V. K. AGRAWAL General Manager SRLDC, Bangalore 8 th November, 2006.

44

TRAINING ON ULDC SYSTEMSL NAME OF THE TRAINING FROM TO Participants Man Days

1 CISCO ROUTER & NETWORKING 19-01-2004 24-01-2004 17 102

2 XA-21 USER LEVEL 23-02-2004 28-02-2004 10 60

3 RTNA WORKSHOP 29-03-2004 31-03-2004 14 42

4 AIX OPERATING SYSTEM 17-05-2004 22-05-2004 15 90

5 XA-21 USER LEVEL 21-06-2004 25-06-2004 6 30

6 SYBASE DATABASE ADMIN 22-11-2004 04-12-2004 19 228

7 XA-21 USER LEVEL 21-02-2005 23-02-2005 7 21

8 NMS TRAINING 13-06-2005 18-06-2005 14 84

9 RTU TRAINING 27-02-2006 03-03-2006 14 70

10 JAVA FOR SCADA ENVIRONMENT 24-04-2006 29-04-2006 16 96