1 Month Lookahead Planned

download 1 Month Lookahead Planned

of 1

Transcript of 1 Month Lookahead Planned

  • 8/12/2019 1 Month Lookahead Planned

    1/1

    Activity ID Activity Name OriginalDuration

    PlannedStart

    PlannedFinish

    ActualStart

    ActualFinish

    TAPL 2

    TAPL 2x31.2 MW COGENERATION POWE 31 27-Feb-14 30-Mar-14

    TAPL.1

    TAPL.1 B OILER UNIT 1 30 27-Feb-14 29-Mar-14

    A1090 Levelling and Compaction of Subgrade 5 27-Feb-14 03-Mar-14

    A1100 Compaction Test 1 03-Mar-14 03-Mar-14

    A1110 Layout for Footings 2 03-Mar-14 04-Mar-14

    A1120 Inpspection of layout by CPL 1 04-Mar-14 04-Mar-14A1130 Preparation & Laying of 150 mm thick Subbase 5 05-Mar-14 09-Mar-14

    A1140 Layout for PCC 1 10-Mar-14 10-Mar-14

    A1150 Lean Concrete C15 3 06-Mar-14 08-Mar-14

    A1160 Layout for reinforcement of footings 3 07-Mar-14 09-Mar-14

    A1161 Preparation & Approval of BBS 5 01-Mar-14 05-Mar-14

    A1170 Cutting & Bending of steel 18 06-Mar-14 24-Mar-14

    A1180 Steel Fixing of Footing & Column Dowels 7 11-Mar-14 17-Mar-14

    A1190 Formwork for footings 8 13-Mar-14 20-Mar-14

    A1200 Inspection of Reinforcement & FW by CPL 15 14-Mar-14 29-Mar-14

    A1210 Pouring of concrete C25 for footings 7 17-Mar-14 24-Mar-14

    A1220 Reinforment for Columns upto plinth 7 18-Mar-14 25-Mar-14

    A1230 Formwork for Columns 8 19-Mar-14 27-Mar-14

    A1240 Concrete pouring of columns upto plinth 8 20-Mar-14 28-Mar-14

    TAPL.2

    TAPL.2 B OILER UNIT 2 26 04-Mar-14 30-Mar-14

    A1560 Levelling and Compaction of Subgrade 5 04-Mar-14 08-Mar-14

    A1570 Compaction Test 1 08-Mar-14 08-Mar-14A1580 Layout for Footings 2 08-Mar-14 09-Mar-14

    A1590 Inpspection of layout by CPL 1 09-Mar-14 09-Mar-14

    A1600 Preparation & Laying of 150 mm thick Subbase 5 10-Mar-14 14-Mar-14

    A1610 Layout for PCC 1 15-Mar-14 15-Mar-14

    A1620 Lean Concrete C15 3 11-Mar-14 13-Mar-14

    A1630 Layout for reinforcement of footings 3 12-Mar-14 14-Mar-14

    A1640 Preparation & Approval of BBS 5 06-Mar-14 10-Mar-14

    A1650 Cutting & Bending of steel 18 11-Mar-14 29-Mar-14

    A1660 Steel Fixing of Footing & Column Dowels 7 16-Mar-14 22-Mar-14

    A1670 Formwork for footings 8 18-Mar-14 26-Mar-14

    A1690 Pouring of concrete C25 for footings 7 22-Mar-14 29-Mar-14

    A1700 Reinforment for Columns upto plinth 7 24-Mar-14 30-Mar-14

    TAPL.3

    TAPL.3 TG MAT & DECK 0

    Feb Mar Apr

    2014

    30-Mar-14, TAPL 2x31.2 MW COGENER I

    29-Mar- 14, TAPL.1 BO ILER UNIT 1

    Levelling and Compaction of Subgrade

    Compaction Test

    Layout for Footings

    Inpspection of layout by CPLPreparation & Laying of 150 mm thick Subbase

    Layout for PCC

    Lean Concrete C15

    Layout for reinforcement of footings

    Preparation & Approval of BBS

    Cutting & Bending of steel

    Steel Fixing of Footing & Column Dowels

    Formwork for footings

    Inspection of Reinforcement & FW by CPL

    Pouring of concrete C25 for footings

    Reinforment for Columns upto plinth

    Formwork for Columns

    Concrete pouring of columns upto plinth

    30-Mar- 14, TAPL.2 BO ILER UNIT 2

    Levelling and Compaction of Subgrade

    Compaction Test

    Layout for Footings

    Inpspection of layout by CPL

    Preparation & Laying of 150 mm thick Subbase

    Layout for PCC

    Lean Concrete C15

    Layout for reinforcement of footings

    Preparation & Approval of BBS

    Cutting & Bending of steel

    Steel Fixing of Footing & Column Dowels

    Formwork for footings

    Pouring of concrete C25 for footings

    Reinforment for Columns upto plinth

    2 x 31.2 MW COGENERATION POWER PLANT

    CHINIOT POWER LIMITED

    TENTATIVE CONSTRUCTION SCHEDULE AS PER BOQ

    Primary Baseline

    Actual Work

    Remaining Wor k

    Critical Remaining Work

    Milestone

    Summary

    Date Revision Checked Approved Engr. Sharjeel Shujaat

    Planning Manager

    Technical Associates (Pvt.) Limited