1 Month Lookahead Planned
Transcript of 1 Month Lookahead Planned
-
8/12/2019 1 Month Lookahead Planned
1/1
Activity ID Activity Name OriginalDuration
PlannedStart
PlannedFinish
ActualStart
ActualFinish
TAPL 2
TAPL 2x31.2 MW COGENERATION POWE 31 27-Feb-14 30-Mar-14
TAPL.1
TAPL.1 B OILER UNIT 1 30 27-Feb-14 29-Mar-14
A1090 Levelling and Compaction of Subgrade 5 27-Feb-14 03-Mar-14
A1100 Compaction Test 1 03-Mar-14 03-Mar-14
A1110 Layout for Footings 2 03-Mar-14 04-Mar-14
A1120 Inpspection of layout by CPL 1 04-Mar-14 04-Mar-14A1130 Preparation & Laying of 150 mm thick Subbase 5 05-Mar-14 09-Mar-14
A1140 Layout for PCC 1 10-Mar-14 10-Mar-14
A1150 Lean Concrete C15 3 06-Mar-14 08-Mar-14
A1160 Layout for reinforcement of footings 3 07-Mar-14 09-Mar-14
A1161 Preparation & Approval of BBS 5 01-Mar-14 05-Mar-14
A1170 Cutting & Bending of steel 18 06-Mar-14 24-Mar-14
A1180 Steel Fixing of Footing & Column Dowels 7 11-Mar-14 17-Mar-14
A1190 Formwork for footings 8 13-Mar-14 20-Mar-14
A1200 Inspection of Reinforcement & FW by CPL 15 14-Mar-14 29-Mar-14
A1210 Pouring of concrete C25 for footings 7 17-Mar-14 24-Mar-14
A1220 Reinforment for Columns upto plinth 7 18-Mar-14 25-Mar-14
A1230 Formwork for Columns 8 19-Mar-14 27-Mar-14
A1240 Concrete pouring of columns upto plinth 8 20-Mar-14 28-Mar-14
TAPL.2
TAPL.2 B OILER UNIT 2 26 04-Mar-14 30-Mar-14
A1560 Levelling and Compaction of Subgrade 5 04-Mar-14 08-Mar-14
A1570 Compaction Test 1 08-Mar-14 08-Mar-14A1580 Layout for Footings 2 08-Mar-14 09-Mar-14
A1590 Inpspection of layout by CPL 1 09-Mar-14 09-Mar-14
A1600 Preparation & Laying of 150 mm thick Subbase 5 10-Mar-14 14-Mar-14
A1610 Layout for PCC 1 15-Mar-14 15-Mar-14
A1620 Lean Concrete C15 3 11-Mar-14 13-Mar-14
A1630 Layout for reinforcement of footings 3 12-Mar-14 14-Mar-14
A1640 Preparation & Approval of BBS 5 06-Mar-14 10-Mar-14
A1650 Cutting & Bending of steel 18 11-Mar-14 29-Mar-14
A1660 Steel Fixing of Footing & Column Dowels 7 16-Mar-14 22-Mar-14
A1670 Formwork for footings 8 18-Mar-14 26-Mar-14
A1690 Pouring of concrete C25 for footings 7 22-Mar-14 29-Mar-14
A1700 Reinforment for Columns upto plinth 7 24-Mar-14 30-Mar-14
TAPL.3
TAPL.3 TG MAT & DECK 0
Feb Mar Apr
2014
30-Mar-14, TAPL 2x31.2 MW COGENER I
29-Mar- 14, TAPL.1 BO ILER UNIT 1
Levelling and Compaction of Subgrade
Compaction Test
Layout for Footings
Inpspection of layout by CPLPreparation & Laying of 150 mm thick Subbase
Layout for PCC
Lean Concrete C15
Layout for reinforcement of footings
Preparation & Approval of BBS
Cutting & Bending of steel
Steel Fixing of Footing & Column Dowels
Formwork for footings
Inspection of Reinforcement & FW by CPL
Pouring of concrete C25 for footings
Reinforment for Columns upto plinth
Formwork for Columns
Concrete pouring of columns upto plinth
30-Mar- 14, TAPL.2 BO ILER UNIT 2
Levelling and Compaction of Subgrade
Compaction Test
Layout for Footings
Inpspection of layout by CPL
Preparation & Laying of 150 mm thick Subbase
Layout for PCC
Lean Concrete C15
Layout for reinforcement of footings
Preparation & Approval of BBS
Cutting & Bending of steel
Steel Fixing of Footing & Column Dowels
Formwork for footings
Pouring of concrete C25 for footings
Reinforment for Columns upto plinth
2 x 31.2 MW COGENERATION POWER PLANT
CHINIOT POWER LIMITED
TENTATIVE CONSTRUCTION SCHEDULE AS PER BOQ
Primary Baseline
Actual Work
Remaining Wor k
Critical Remaining Work
Milestone
Summary
Date Revision Checked Approved Engr. Sharjeel Shujaat
Planning Manager
Technical Associates (Pvt.) Limited