Madrid, 27 th October 2009 11th IG Meeting South Gas Regional Initiative.
1 Madrid, 6 th May 2011 16 th IG Meeting South Gas Regional Initiative.
-
Upload
cory-sherman -
Category
Documents
-
view
218 -
download
0
Transcript of 1 Madrid, 6 th May 2011 16 th IG Meeting South Gas Regional Initiative.
1
Madrid, 6th May 2011
16th IG Meeting
South Gas Regional Initiative
2
16th IG meeting SGRI- Agenda
I. Opening
I.1 Welcome
I.2 Approval of the agenda and minutes from the last meeting (for approval)
II. Latest EU developments and potential impact on the South region
II.1 Discussions on the Gas target model (for information by NRAs)
II.2 Framework guidelines and network codes (for information by NRAs)
III. Tasks from the Action Plan 2011-2012
III.1 CAM harmonisation proposal – Pilot testing of FG CAM in Portugal-Spain
interconnection (for information by TSOs)
III.2 CMP country analysis and harmonisation proposals – Pilot testing of CMP guidelines for
comitology (for information by TSOs)
III.3 Update of the regional infrastructure plan and status of projects from OS 2013 and 2015
(for information by TSOs)
III.4 Harmonisation of cross border tariffs structures between Portugal and Spain (for
information by NRAs)
IV. Organisation and role of Gas Regional Initiatives under ACER coordination (for
information by NRAs)
V. AOB and next meetings
3
I.2. Approval of the agenda and minutes
4
II. Latest EU developments and potential impact
on the South region
5
II.1 Latest EU developmentsDiscussions on the Gas Target Model
• Mandate from the Madrid Forum: develop a target model to help preparing the network codes• Help completing the single market by 2014• Address long term issues, beyond 2014
• Workshops • Vienna, 3 December 2010: opening of work• Bonn, 22 February 2011: options and constraints• Florence, FSR workshop, 11 March 2011: open debate• London, 11 April 2011: ideas
• Call for evidence from stakeholders• 2 consultancy studies
• FSR & Clingendael• LECG
6
II.1 Latest EU developmentsDiscussions on the Gas Target Model
• Consultants focused on technical options to deepen market integration• Connecting markets
• Merger of market areas
• Market coupling
• Focus on the development of wholesale markets and short term efficiency
• According to stakeholders and EERs, it is necessary to• Enlarge the scope: the main issue is to combine short and long term to
ensure competition and security of supply
• Address all the topics discussed in the third package implementation, including CAM
• Clarify the market coupling concept and associated benefits
• CEER paper should propose a « vision » seeking for consensus
7
II.1 Latest EU developmentsDiscussions on the Gas Target Model
• What is missing in a South Region perspective?• LNG and storage have not been addressed per se
• Key for competition and security of supply
• Ensure that storage facilities are filled in during summer
• Promote Europe’s attractiveness for LNG
• Investment • Interconnection development and open seasons
• Concept of investment climate (long term visibility)
• Next steps• Preparation of a background document by CEER
• Conference in Brussels on 28 June 2011
8
II.2 Latest EU developmentsFramework guidelines and network codes
• Dominant topics• Capacity allocations
• Balancing
• Tariffs
• Interoperability
• Lessons from the past processes• Preparing framework guidelines requires more time than foreseen in the
third package
• Identifying all the consequences of the preferred orientations is challenging
• Risk: requesting more harmonization than necessary (and concretely possible)
9
Capacity allocation mechanisms
• Framework guideline• ACER consultation closed on 2 May
• The final version should be sent to the Commission by 3 September 2011
• Fora and workshops showed a large stakeholders’ opposition to the "sunset clause"
• Network code development• ENTSOG work has evidenced new issues regarding the implementation
of the framework guideline
• Bundled products: debate on the number of contracts, invoices and nominations. ERGEG view: a single nomination, at least
• Interruptible products: debate on infinite interruptible. Auctions and alignment on the two sides of the border should not allow infinite interruptible
• Capacity products: ENTSOG promotes quarterly products. The consequences on tariffs and cost recovery must be investigated
10
Balancing
• Framework guideline• ACER consultation ongoing until 12 June 2011
• Final version by October 2011
• Main provisions of the framework guideline• Market based balancing as a target
• Imbalance charges should reflect costs
• TSOs to procure gas in short term wholesale market
• Improve transparency
• Remaining questions• Within day constraints could be different between two adjacent systems
• Consistency with CAM and CMP regarding nomination schedules
11
Tariffs
• ACER/CEER work advancement• Problem identification completed• Development of policy options
• Dominant issues under scrutiny• Cost allocation: no discrimination between domestic and cross border entry or exit
points nor between different categories of users need to find a methodology to properly allocate costs
• Cost recovery: combination of ex-ante nd ex-post mechanisms reserve prices for auctions, regulatory account, commodity charge are debated
• Short term versus long term capacity products: how to calculate reserve prices what reference to costs, relevant reserve price for day-ahead products, seasonal reserve prices for short term products?
• Key questions• Zero reserve price for day-ahead products?• Since auctions are the standard CAM, what happens in the absence of congestion?
12
III. Tasks from the Action Plan 2011-2012
13
III Tasks from the Action Plan 2011-2012Actions and timetable
14
III.1. CAM harmonisation proposal – Pilot testing
of FG CAM in Portugal-Spain interconnection
15
III.1 Tasks from the Action Plan 2011-2012CAM harmonisation - Pilot testing Pt-Sp
(Information by TSOs)
Area of work Responsible
Starting Deadline
CAM harmonisation proposal (CAM pilot testing Sp‐Pt borders)
TSOs Jan. 2011 Jan. 2012
16
III.2. CMP country analysis and harmonisation
proposals – Pilot testing of CMP guidelines for
comitology
17
III.2 Tasks from the Action Plan 2011-2012CMP harmonisation - Pilot testing Fr-Sp
(Information by TSOs)
Area of work Responsible
Starting Deadline
CMP country analysis and harmonisation proposals (pilot testing on comitology CMP guidelines)
TSOs Oct. 2010 May 2011
18
III.3. Update of the regional infrastructure plan
and status of projects from OS 2013 and 2015
19
III.3 Tasks from the Action Plan 2011-2012Update on status of projects from OS 2013 and 2015
• Status of projects received from
• Naturgas (updated at 14 March 2011)
• TIGF (updated at 6 May 2011)
• Enagas (updated at 6 May 2011)
• Missing information
• GRTgaz
20
Infrastructures follow-up16th IG S-GRI
6th May 2011
Index
• OS 2013
• OS 2015
Larrau investments
1.1 Name of the infrastructure: Navarra CSTechnical characteristics 38 MW
1.2 Name of the responsible TSO: Enagás S.A1.3 Additional capacity from existing infrastructure (GWh/day)
1.4 Investment approved by TSO (YES/NO) Yes
Spain-France: 0
France-Spain:Max:100
Min: 50(W) / 40 (S)
2.1 Initial Planning 2.2 Updated forecast
Starting operation date 2009 May-09
Administrative milestones A) Application Date B) Concession Date
3.1 Initial (promoter choice) Apr-2004 May-2005
3.2 Environmental Assessment Jun-2007
3.3 Final (Authorisation for starting construction) Dec-2006 Nov-2007
Current project advance A) In previous review (%) B) Total (%)
4.1 Engineering 100% 100%
4.2 Procurement 100% 100%
4.3 Construction 100% 100%
4.4 Commissioning 100% 100%
Causes of delays (if applied)
COMMISSIONED1
2
3
4
5
Larrau investmentsCOMMISSIONED
1.1 Name of the infrastructure: Pipeline Lemona – HaroTechnical characteristics 92 km / 26"
1.2 Name of the responsible TSO: Enagás S.A1.3 Additional capacity from existing infrastructure (GWh/day)
1.4 Investment approved by TSO (YES/NO) Yes
Spain-France: 0
France-Spain:Max:100
Min: 30(W) / 20 (S)
2.1 Initial Planning 2.2 Updated forecast
Starting operation date 2009 Ago-09
Administrative milestones A) Application Date B) Concession Date
3.1 Initial (promoter choice) Mar-2006 Apr-2006
3.2 Environmental Assessment Sep-2007
3.3 Final (Authorisation for starting construction) May-2006 Dec-2007
Current project advance A) In previous review (%) B) Total (%)
4.1 Engineering 100% 100%
4.2 Procurement 100% 100%
4.3 Construction 100% 100%
4.4 Commissioning 100% 100%
Causes of delays (if applied)
1
2
3
4
5
Larrau investmentsCOMMISSIONED
1.1 Name of the infrastructure: Reinforcement of Haro CSTechnical characteristics 23 MW
1.2 Name of the responsible TSO: Enagás S.A1.3 Additional capacity from existing infrastructure (GWh/day)
1.4 Investment approved by TSO (YES/NO) Yes
Spain-France: 0
France-Spain:Max:100
Min: 30(W) / 20 (S)
2.1 Initial Planning 2.2 Updated forecast
Starting operation date 2009 Ago-09
Administrative milestones A) Application Date B) Concession Date
3.1 Initial (promoter choice) Mar-2006 Jul-2006
3.2 Environmental Assessment Apr-2007
3.3 Final (Authorisation for starting construction) Sep-2006 Dec-2007
Current project advance A) In previous review (%) B) Total (%)
4.1 Engineering 100% 100%
4.2 Procurement 100% 100%
4.3 Construction 100% 100%
4.4 Commissioning 100% 100%
Causes of delays (if applied)
1
2
3
4
5
Larrau investmentsCOMMISSIONED
1.1 Name of the infrastructure: Pipeline Castelnou – Tivisa (loop)Technical characteristics 91 km / 26"
1.2 Name of the responsible TSO: Enagás S.A1.3 Additional capacity from existing infrastructure (GWh/day)
1.4 Investment approved by TSO (YES/NO) YesSpain-France: 30(W) / 50 (S)
France-Spain: 100
2.1 Initial Planning 2.2 Updated forecast
Starting operation date 2009 Sep/Oct-09
Administrative milestones A) Application Date B) Concession Date
3.1 Initial (promoter choice) Mar-2006 Feb-2007
3.2 Environmental Assessment Mar-2007 Apr-2009
3.3 Final (Authorisation for starting construction) Mar-2007 Oct-2009
Current project advance A) In previous review (%) B) Total (%)
4.1 Engineering 100% 100%
4.2 Procurement 100% 100%
4.3 Construction 0% 100%
4.4 Commissioning 0% 100%
Causes of delays (if applied)
1
2
3
4
5
Larrau investmentsCOMMISSIONED
1.1 Name of the infrastructure: Villar de Arnedo CSTechnical characteristics 35 MW
1.2 Name of the responsible TSO: Enagás S.A1.3 Additional capacity from existing infrastructure (GWh/day)
1.4 Investment approved by TSO (YES/NO) YesSpain-France: 110(W) / 100 (S)
France-Spain: 100
2.1 Initial Planning 2.2 Updated forecast
Starting operation date 2010 Feb-11
Administrative milestones A) Application Date B) Concession Date
3.1 Initial (promoter choice) Apr-2006 Feb-2008
3.2 Environmental Assessment Nov-2008
3.3 Final (Authorisation for starting construction) Jul-2008 Mar-2010
Current project advance A) In previous review (%) B) Total (%)
4.1 Engineering 81% 100%
4.2 Procurement 61% 100%
4.3 Construction 0% 100%
4.4 Commissioning 0% 100%
Causes of delays (if applied)
1
2
3
4
5
Larrau investments
1.1 Name of the infrastructure: Pipeline Tivisa – Paterna (loop)Technical characteristics 235 km / 40"
1.2 Name of the responsible TSO: Enagás S.A1.3 Additional capacity from existing infrastructure (GWh/day)
1.4 Investment approved by TSO (YES/NO) YesSpain-France: 30(W) / 50 (S)
France-Spain: 100
2.1 Initial Planning 2.2 Updated forecast
Starting operation date 2009 Apr-12
Administrative milestones A) Application Date B) Concession Date
3.1 Initial (promoter choice) Mar-2006 May-2007
3.2 Environmental Assessment Jun-2007 Jul-2009
3.3 Final (Authorisation for starting construction) Jun-2007 Jan-2011
Current project advance A) In previous review (%) B) Total (%)
4.1 Engineering 100% 100%
4.2 Procurement 97% 98%
4.3 Construction 0% 69%
4.4 Commissioning 0% 0%
Causes of delays (if applied)The pipeline is divided in 3 tranches (i.e North, Central, South). The information of section 4 is related to the North tranche. The South tranche (25%) is also under construction.
1
2
3
4
5
Larrau investments
1.1 Name of the infrastructure: Pipeline Zarza de Tajo - YelaTechnical characteristics 100 km / 30"
1.2 Name of the responsible TSO: Enagás S.A1.3 Additional capacity from existing infrastructure (GWh/day)
1.4 Investment approved by TSO (YES/NO) YesSpain-France: 110(W) / 100 (S)
France-Spain: 100
2.1Initial Planning 2.2 Updated forecast
Starting operation date 2010 Sep-12
Administrative milestones A) Application Date B) Concession Date
3.1 Initial (promoter choice) Apr-2006 Dec-2007
3.2 Environmental Assessment
3.3 Final (Authorisation for starting construction) May-2008
Current project advance A) In previous review (%) B) Total (%)
4.1 Engineering 70% 70%
4.2 Procurement 35% 95%
4.3 Construction 0% 0%
4.4 Commissioning 0% 0%
Causes of delays (if applied)
1
2
3
4
5
Larrau investments
1.1 Name of the infrastructure: Pipeline Yela – Villar de ArnedoTechnical characteristics 251 km / 30"
1.2 Name of the responsible TSO: Enagás S.A1.3 Additional capacity from existing infrastructure (GWh/day)
1.4 Investment approved by TSO (YES/NO) YesSpain-France: 110(W) / 100 (S)
France-Spain: 100
2.1Initial Planning 2.2 Updated forecast
Starting operation date 2010 Dec-12
Administrative milestones A) Application Date B) Concession Date
3.1 Initial (promoter choice) Apr-2006 Jun-2008
3.2 Environmental Assessment Nov-2010
3.3 Final (Authorisation for starting construction) Jul-2008 Dec-2010
Current project advance A) In previous review (%) B) Total (%)
4.1 Engineering 50% 100%
4.2 Procurement 11% 22%
4.3 Construction 0% 0%
4.4 Commissioning 0% 0%
Causes of delays (if applied)
1
2
3
4
5
Larrau investments
• OS 2013
• OS 2015
Biriatou investments
1.1 Name of the infrastructure: CS at the borderTechnical characteristics To be defined
1.2 Name of the responsible TSO: Application made by Enagás S.A for authorisation1.3 Additional capacity from existing infrastructure (GWh/day)
1.4 Investment approved by TSO (YES/NO) YesSpain-France: 60
France-Spain: 0
2.1 Initial Planning 2.2 Updated forecast
Starting operation date 2015 2015
Administrative milestones A) Application Date B) Concession Date
3.1 Initial (promoter choice) Jun-2008
3.2 Environmental Assessment
3.3 Final (Authorisation for starting construction)
Current project advance A) In previous review (%) B) Total (%)
4.1 Engineering 0% 0%
4.2 Procurement 0% 0%
4.3 Construction 0% 0%
4.4 Commissioning 0% 0%
Causes of delays (if applied)
1
2
3
4
5
THANK YOU
6th May 2011
Status of infrastructures at 14 March 2011
Naturgas infrastructuresSummary
Irun Biriatou project TSO Status Mandatory Planning Date of operationBergara Zaldibia NET In operation A - Urgent In operationZaldibia Villabona NET In operation A - Urgent In operationVillabona Irún NET In Operation A - Urgent In operationBilbao Treto NET Environmental impact assesment 04/03/2011 A - Urgent 31.12.2013
CS Irún NET/ENAGASA - FID Arcangues Coudures comunicada TIGFPending TSO selection 01.04.2015
Naturgas infrastructuresBergara - Zaldibia
Interconnection Euskadour
Km 30,367 D(") 26 P(MW)
Winter Summer5 40 10
100%
2.2 Updated forecast (according to real works status)
2.1Initial Planning
A) Application Date B) Concession Date
1.3 Capacity with this infrastructure (GWh/day)
A) In previous review (%) B) Current (%)
01/07/2002
26/12/2001
16/01/2006
21/11/2006
YES
31/07/2008 02/02/2009
26/12/2001
14/03/2011Review date: (dd/mm/yyyy):
Gasoducto Bergara Zaldibia
NATURGAS ENERGIA TRANSPORTE
1.4 Investment approved by TSO (YES/NO)
100%
100%
100%
100%
1.1 Name of the infrastructure:
1.2 Name of the responsible TSO:
Spain-France (Common Value) :France-Spain (Common Value) :
Starting operation date
Technical characteristics:
Administrative milestones
3.1 Initial (promoter choice)
3.2 Environmental Assessment3.3 Final (Authorisation for starting construction)
Project advance
4.1 Engineering
Comments Pipeline in operation
4.2 Procurement
4.3 Construction
4.4 Commissioning
Causes of delays (if applied)
100%
100%
100%
Naturgas infrastructuresZaldibia - Villabona
Interconnection Euskadour
Km 25,389 D(") 26 P(MW)
Winter Summer5 40 10
Administrative milestones
3.1 Initial (promoter choice)
4.2 Procurement
4.3 Construction
4.4 Commissioning
Causes of delays (if applied)
3.2 Environmental Assessment3.3 Final (Authorisation for starting construction)
Project advance
4.1 Engineering
0%
100%
1.4 Investment approved by TSO (YES/NO)
1.1 Name of the infrastructure:
1.2 Name of the responsible TSO:
Spain-France (Common Value) :France-Spain (Common Value) :
Starting operation date 31/03/2009 22/05/2009
26/12/200101/07/2002
100%
14/03/2011Review date: (dd/mm/yyyy):
Gasoducto Zaldibia Villabona
NATURGAS ENERGIA TRANSPORTE
YES
100%
100%
Comments Pipeline in operation
26/12/2001
20/11/200616/01/2006
20/11/2006
100%
90%
Technical characteristics:
100%
2.2 Updated forecast (according to real works status)
2.1Initial Planning
A) Application Date B) Concession Date
1.3 Capacity with this infrastructure (GWh/day)
A) In previous review (%) B) Current (%)
Naturgas infrastructuresVillabona - Irún
Interconnection Euskadour
Km 35,043 D(") 26 P(MW)
Winter Summer5 90 10
100%
2.2 Updated forecast (according to real works status)
2.1Initial Planning
A) Application Date B) Concession Date
1.3 Capacity with this infrastructure (GWh/day)
A) In previous review (%) B) Current (%)
01/07/2002
26/12/2001
08/05/200904/12/2008
08/05/2009
YES
31/03/2010 01/07/2010
26/12/2001
14/03/2011Review date: (dd/mm/yyyy):
Gasoducto Villabona Irun
NATURGAS ENERGIA TRANSPORTE
1.4 Investment approved by TSO (YES/NO)
100%
50%
0%
100%
1.1 Name of the infrastructure:
1.2 Name of the responsible TSO:
Spain-France (Common Value) :France-Spain (Common Value) :
Starting operation date
Technical characteristics:
Administrative milestones
3.1 Initial (promoter choice)
3.2 Environmental Assessment3.3 Final (Authorisation for starting construction)
Project advance
4.1 Engineering
Comments Pipeline in operation
4.2 Procurement
4.3 Construction
4.4 Commissioning
Causes of delays (if applied)
100%
100%
100%
Naturgas infrastructuresBilbao - Treto
Interconnection Euskadour
Km 45.336 D(") 26 P(MW)8.627 12
Winter Summer5 90 10
Review date: (dd/mm/yyyy): 14/03/2011
1.1 Name of the infrastructure: Gasoducto Bilbao TretoTechnical characteristics:
1.2 Name of the responsible TSO: NATURGAS ENERGIA TRANSPORTE1.3 Capacity with this infrastructure (GWh/day)
1.4 Investment approved by TSO (YES/NO)
YESSpain-France (Common Value) :France-Spain (Common Value) :
2.1Initial Planning 2.2 Updated forecast (according to real works status)
Starting operation date 31/03/2010 31/12/2013
Administrative milestones A) Application Date B) Concession Date
3.1 Initial (promoter choice) 23/02/2007 06/11/2006
3.2 Environmental Assessment 23/02/2007 04/03/2011
3.3 Final (Authorisation for starting construction) 23/02/2007 31/12/2013
Project advance A) In previous review (%) B) Current (%)
4.1 Engineering 0% 0%
4.2 Procurement 0% 0%
4.3 Construction 0% 0%
4.4 Commissioning 0% 0%
Causes of delays (if applied)
Comments Pending Authorisation
Status of infrastructures at 6 May 2011
TIGF infrastructuresReversibilité LACAL
Review date :
1.1 Name of the infrastructure :1.2 Name of the TSO :1.3 Additional capacity (GWh/d)
1,4 Total capacity of the infrastructure (GWh/d)
1.4 Possible entry points :1.5 Possible exit points :1.6 Description of the infrastructure :
2.1 Studies start :2.2 Preliminary studies :2.3 Environmental & safety studies :2.4 Decision :2.5 Application for administrative authorization :2.6 Construction start :2.7 Starting operation date :
50 (S) - 30 (W) ENAGAS -> TIGF
06/05/2011
1Project description
LACALTIGF
50 (S) - 30 (W) ENAGAS -> TIGF100 TIGF -> ENAGAS
ENAGAS - GRT Gaz - StorageENAGAS - GRT Gaz - Storage
Modifications Alcay metering station and Mont compression station to reverse the flow of LACAL
pipeline.
2Planning
Date as planned Date as realized2Q 2008 2Q 2008
2 nd half 2008 2Q 2008
2Q - 2010 2Q - 2010
4Q -2010 4Q - 2010
3Comments
TIGF infrastructuresArtère de Guyenne (phase A)
Review date :
1.1 Name of the infrastructure :1.2 Name of the TSO :1.3 Additional capacity (GWh/d)
1,4 Total capacity of the infrastructure (GWh/d)
1.4 Possible entry points :1.5 Possible exit points :1.6 Description of the infrastructure :
2.1 Studies start :2.2 Preliminary studies :2.3 Environmental & safety studies :2.4 Decision :2.5 Application for administrative authorization :2.6 Construction start :2.7 Starting operation date :
70 (S) - 60 (W) GRTgaz -> TIGF
06/05/2011
1Project description
Artère de Guyenne (phase A)TIGF
130 (S) - 180 (W) TIGF -> GRTgaz180 (S) - 150 (W) GRTgaz -> TIGF
230 TIGF -> GRTgazGRTGaz - NATURGAS-ENAGAS - StorageGRTGaz - NATURGAS-ENAGAS - Storage
70 km of pipeline Captieux-Mouliets and 2 compression stations developing 24 MW at Sauveterre and Lussagnet
2Planning
Date as planned Date as realizedQ4 2004Q1 2005
1st half 2005january 2006
(DUP pipe) 2007-03-22september 2007
4Q 2008 (pipe)3Q 2009 (comp. stations)
4Q 2008 (pipe)3Q 2009 (comp. Station)
3Comments
TIGF infrastructuresGirland (Artère de Guyenne - B)
Review date :
1.1 Name of the infrastructure :1.2 Name of the TSO :1.3 Additional capacity (GWh/d)
1,4 Total capacity of the infrastructure (GWh/d)
1.4 Possible entry points :1.5 Possible exit points :1.6 Description of the infrastructure :
2.1 Studies start :2.2 Preliminary studies :2.3 Environmental & safety studies :2.4 Decision :2.5 Application for administrative authorization :2.6 Construction start :2.7 Starting operation date :
195 (S) - 65 (W) GRTgaz -> TIGF
06/05/2011
1Project description
GIRLAND (Artère de Guyenne - B)TIGF
185 (S) - 190 (W) TIGF -> GRTgaz375 (S) - 215 (W) GRTgaz -> TIGF415 (S) - 420 (W) TIGF -> GRTgaz
GRTGaz - NATURGAS-ENAGAS - StorageGRTGaz - NATURGAS-ENAGAS - Storage
57 km of pipeline DN900 (36") Lussagnet - Captieux1 additional compressor (8 MW) at Sauveterre
2Planning Pipe
Date as planned Date as realized2Q 2008 2Q 2008
3Q - 2009 2Q - 20093Q - 2010 3Q - 20101Q - 2010 1Q - 20102Q - 20114Q - 2012
3Q - 2013 (pipe)3Q - 2014 (compressors) (*)
3Comments
(*) This additional compression capacity is not required, for the provision of the capacities OS2013, until Q3/2014.
TIGF infrastructuresArtère du Béarn (Lussagnet - Lacq)
Review date :
1.1 Name of the infrastructure :1.2 Name of the TSO :1.3 Additional capacity (GWh/d)
1,4 Total capacity of the infrastructure (GWh/d)
1.4 Possible entry points :1.5 Possible exit points :1.6 Description of the infrastructure :
2.1 Studies start :2.2 Preliminary studies :2.3 Environmental & safety studies :2.4 Decision of investment:2.5 Application for administrative authorization :2.6 Construction start :2.7 Starting operation date :
115(S) - 135(W) ENAGAS -> TIGF
06/05/2011
1Project description
Artère du Béarn (Pipeline Lussagnet Lacq)TIGF
65 TIGF -> ENAGAS165 ENAGAS -> TIGF165 TIGF -> ENAGASz
GRTgaz - ENAGAS - StorageGRTgaz - ENAGAS - Storage
57 km of pipeline DN800 (32") Lussagnet - Lacq
2Planning
Date as planned Date as realized2Q 2008 2Q 2008
2 nd half 2008 1Q 20092Q - 2009 2Q - 20091Q - 2010 1Q - 20101Q - 2010 1Q - 20103Q - 20114Q - 2012
3Comments
TIGF infrastructuresEuskadour (Arcangues-Coudure)
Review date :
1.1 Name of the infrastructure :1.2 Name of the TSO :1.3 Additional capacity (GWh/d)
1,4 Total capacity of the infrastructure (GWh/d)
1.4 Possible entry points :1.5 Possible exit points :1.6 Description of the infrastructure :
2.1 Studies start :2.2 Preliminary studies :2.3 Environmental & safety studies :2.4 Decision of investment:2.5 Application for administrative authorization :2.6 Construction start :2.7 Starting operation date :
56 (S) - 55(W) NATURGAS -> TIGF
06/05/2011
1Project description
Euskadour (Pipeline Arcangues-Coudure)TIGF
50 (S) 60 (W) TIGF -> NATURGAS60 (*) NATURGAS -> TIGF60 (*) TIGF -> NATURGAS
GRTgaz - NATURGAS - StorageGRTgaz - Storage
95 km DN600 (24") of pipeline Arcangues Coudure
2Planning
Date as planned Date as realized4Q - 2008 4Q - 20084Q - 2010 4Q - 20104Q - 20111Q - 2011 1Q - 20112Q - 20121Q - 20144Q - 2015
3
Comments(*) Physical capacity at the border (Biriatou) could be doubled, depending on agreements with Naturgas/Enagas.
Status of infrastructures
46
III.4. Harmonisation of cross border tariffs
structures between Portugal and Spain
47
III.4 Tasks from the Action Plan 2011-2012Harmonisation of cross border tariffs Pt-Sp
(Information by NRAs - ERSE)
Area of work Responsible
Starting
Deadline
Harmonisation of cross‐border tariffs structures between Portugal and Spain
NRAs 2010 Dec. 2011
48
IV. Organisation and role of Gas Regional
Initiatives under ACER coordination
49
IV. Organisation and role of GRIsRegional Initiatives under ACER coordination
• ACER - CEER Meeting about Regional Initiatives (5th April 2011):
• General Objective: achieve the European Internal Energy Market in 2014
• Main conclusions:
• Regional Initiatives must have concrete, ambitious and realistic roadmaps.
• Governance: a project- oriented approach as a means to achieve a greater
number of goals (with a responsible NRA).
• RI must focus on implementation instead of regulation proposals.
• RI must develop consistent Roadmaps in 2 months.
• ACER may tackle cross border disagreements.
• There is an urgent need to establish the Roadmap until 2014, with clear
goals, responsibilities and deadlines.
50
IV. Organisation and role of GRIsRegional Initiatives under ACER coordination
• Next meeting to be held in Ljubljiana in 2
months. Workplans 2011-2014 must be ready at
that time
• Annual conference on Regional Initiatives in
Ljubljiana in September
51
• Letter from EC to CEER (18/04/11):
• Request to NRAs – under the coordination of Lead Regulators – to contribute to
elaborate a “European Energy Work Plan 2011-2014” by the end of June 2011
• To be sent jointly to the EC and ACER
• Aiming at determining, for each region and pan-European project, the steps
allowing to reach the common goal in 2014
• In particular, regarding implementation of target models for CAM and CMP
• The EC and ACER to use regulatory tools available in case of blocking (Art. 8
of Regulation EC/715/2009)
• A specific event to be organised in Fall 2011 at Commissioner’s level
• New working meeting between EC and CEER in May
IV. Organisation and role of GRIsRegional Initiatives under ACER coordination
52
IV. Organisation and role of GRIsRegional Initiatives under ACER coordination
• Letter from EC to CEER (20/04/11): additional thinking on RI and next steps
• Target resulting from European Council concerning energy: IEM should
be completed in 2014. TSOs and NRAs in cooperation with ACER must
step up their work
• Time to shift “from governance to action”
• Results of Communication on Reg. Initiatives:
• Main tasks: implementation of EU Acquis, regional issues and pilot testing
• Composition: no consensus on changes. Keep existing scheme, although
legislative tools could be used by EC if progress is insufficient
• Governance: in order to involve Member States, EC in favour of a flexible
approach: each Lead Reg. to determine the best way to ensure governance
53
• We need to step up work on implementation through specific projects.
Urgent action is needed
• Update of the Action Plan to meet EC deadline (end of June). Next steps
• Starting from the current Action Plan 2011-2012, draft a Work Plan 2011-2014 for
the South GRI (by NRAs)
• Send draft to operators and stakeholders by the end of May
• Request for comments and suggestions until 15th June
• Final version to be submitted to EC and ACER by the end of June
• Contents for the new Work Plan 2011-2014
• Extend the current Action Plan
• Contents of the current plan are in line already with EC request (CAM, CMP)
• More focus might be needed on implementation of target model and steps for
reaching the Internal Energy Market in 2014
IV. Organisation and role of GRIsNext steps to be taken in the South GRI
54
V. AOB and next meetings
55
V. AOB
56
(Conclusions)
Next meeting (to be defined)
V. Conclusions and next meetingsV. Conclusions and next meetings