1 ISE 491 - Ch. 8 pt. 2 Resource-constrained scheduling: Computer demonstration EMR Project The...

22
1 ISE 491 - Ch. 8 pt. 2 Resource-constrained scheduling: Computer demonstration EMR Project The development of a handheld electronic medical reference guide to be used by emergency medical technicians and paramedics Problem There are only eight design engineers who can be assigned to the project due to a shortage of design engineers and commitments to other projects.

Transcript of 1 ISE 491 - Ch. 8 pt. 2 Resource-constrained scheduling: Computer demonstration EMR Project The...

Page 1: 1 ISE 491 - Ch. 8 pt. 2 Resource-constrained scheduling: Computer demonstration EMR Project  The development of a handheld electronic medical reference.

1ISE 491 - Ch. 8 pt. 2

Resource-constrained scheduling: Computer demonstration

EMR Project The development of a handheld electronic medical reference

guide to be used by emergency medical technicians and paramedics

Problem There are only eight design engineers who can be assigned to

the project due to a shortage of design engineers and commitments to other projects.

Page 2: 1 ISE 491 - Ch. 8 pt. 2 Resource-constrained scheduling: Computer demonstration EMR Project  The development of a handheld electronic medical reference.

2ISE 491 - Ch. 8 pt. 2

Your turn … See the network diagram on pg 245

enter the tasks into MS Project be sure that EMR Project is your top-level task indent all tasks under EMR Project view the network diagram and correct any errors in your plan to move the top-level “EMR Project” block, do the following:

______________________________________________

enter the resources (8 design engineers) as follows:

_________________________________________ enter the resource requirements for each task as

shown in the network diagram first, change “resource leveling” to “manual” as follows:

________________________________________________

Page 3: 1 ISE 491 - Ch. 8 pt. 2 Resource-constrained scheduling: Computer demonstration EMR Project  The development of a handheld electronic medical reference.

3ISE 491 - Ch. 8 pt. 2

EMR project (cont.)

enter the resource requirements for each task as shown in the network diagram

first, change “resource leveling” to “manual” as follows:

________________________________________________ next, assign resources to tasks as follows:

________________________________________________

View the resource graph and resource usage sheet as follows:

__________________________________________ When are the resources overloaded?

Level the resources and see what happens:

___________________________________________

Page 4: 1 ISE 491 - Ch. 8 pt. 2 Resource-constrained scheduling: Computer demonstration EMR Project  The development of a handheld electronic medical reference.

4ISE 491 - Ch. 8 pt. 2

EMR project: network view of schedule before resources leveled

FIGURE 8.6

Page 5: 1 ISE 491 - Ch. 8 pt. 2 Resource-constrained scheduling: Computer demonstration EMR Project  The development of a handheld electronic medical reference.

5ISE 491 - Ch. 8 pt. 2

EMR project before resources added

FIGURE 8.7

Page 6: 1 ISE 491 - Ch. 8 pt. 2 Resource-constrained scheduling: Computer demonstration EMR Project  The development of a handheld electronic medical reference.

6ISE 491 - Ch. 8 pt. 2

EMR project—time constrained resource usage view, January 15–23, 2005

FIGURE 8.8A

Page 7: 1 ISE 491 - Ch. 8 pt. 2 Resource-constrained scheduling: Computer demonstration EMR Project  The development of a handheld electronic medical reference.

7ISE 491 - Ch. 8 pt. 2

Resource loading chart for EMR project, January 15–23, 2005

FIGURE 8.A8B

Page 8: 1 ISE 491 - Ch. 8 pt. 2 Resource-constrained scheduling: Computer demonstration EMR Project  The development of a handheld electronic medical reference.

8ISE 491 - Ch. 8 pt. 2

EMR project network view schedule after resources leveled

FIGURE 8.9

Page 9: 1 ISE 491 - Ch. 8 pt. 2 Resource-constrained scheduling: Computer demonstration EMR Project  The development of a handheld electronic medical reference.

9ISE 491 - Ch. 8 pt. 2

EMR project resources leveled

FIGURE 8.10

Page 10: 1 ISE 491 - Ch. 8 pt. 2 Resource-constrained scheduling: Computer demonstration EMR Project  The development of a handheld electronic medical reference.

10ISE 491 - Ch. 8 pt. 2

The impacts of resource-constrained scheduling Reduces delay but reduces flexibility Increases sensitivity of the network Increases scheduling complexity May make traditional critical path no longer

meaningful Can break sequence of events May cause parallel activities to become

sequential and critical activities with slack to become noncritical

Page 11: 1 ISE 491 - Ch. 8 pt. 2 Resource-constrained scheduling: Computer demonstration EMR Project  The development of a handheld electronic medical reference.

11ISE 491 - Ch. 8 pt. 2

Splitting/multitasking Splitting/Multitasking

A scheduling technique use to get a better project schedule and/or increase resource utilization

Involves interrupting work on an activity to employ the resource on another activity, then returning the resource to finish the interrupted work

Is feasible when startup and shutdown costs are low

Is considered the major reason why projects fail to meet schedule

Page 12: 1 ISE 491 - Ch. 8 pt. 2 Resource-constrained scheduling: Computer demonstration EMR Project  The development of a handheld electronic medical reference.

12ISE 491 - Ch. 8 pt. 2

Splitting/multitasking

FIGURE 8.11

Page 13: 1 ISE 491 - Ch. 8 pt. 2 Resource-constrained scheduling: Computer demonstration EMR Project  The development of a handheld electronic medical reference.

13ISE 491 - Ch. 8 pt. 2

Assigning project work

Factors to consider in assigning work: Don’t always pick the same people for the toughest

assignments. Choose people with an eye to fostering their

development through participation on the project. Pick people with compatible work habits and

personalities but who complement each other. Team-up veterans with new hires to share experience

and socialize newcomers into the organization. Select people who may need to learn work together

on later stages of the project or other projects.

Page 14: 1 ISE 491 - Ch. 8 pt. 2 Resource-constrained scheduling: Computer demonstration EMR Project  The development of a handheld electronic medical reference.

14ISE 491 - Ch. 8 pt. 2

Multiproject resource schedules Multiproject scheduling problems

Overall project slippage Delay on one project creates delays for other projects.

Inefficient resource application The peaks and valleys of resource demands create

scheduling problems and delays for projects.

Resource bottlenecks Shortages of critical resources required for multiple projects

cause delays and schedule extensions.

Page 15: 1 ISE 491 - Ch. 8 pt. 2 Resource-constrained scheduling: Computer demonstration EMR Project  The development of a handheld electronic medical reference.

15ISE 491 - Ch. 8 pt. 2

Multiproject resource schedules Managing multiproject scheduling

Create project offices or departments to oversee the scheduling of resources across projects.

Use a project priority queuing system: first come, first served for resources.

Centralize project management: treat all projects as a part of a “megaproject.”

Outsource projects to reduce the number of projects handled internally.

Page 16: 1 ISE 491 - Ch. 8 pt. 2 Resource-constrained scheduling: Computer demonstration EMR Project  The development of a handheld electronic medical reference.

16ISE 491 - Ch. 8 pt. 2

Creating a time-phased budget

FIGURE 8.12

Page 17: 1 ISE 491 - Ch. 8 pt. 2 Resource-constrained scheduling: Computer demonstration EMR Project  The development of a handheld electronic medical reference.

17ISE 491 - Ch. 8 pt. 2

Creating a time-phased budget (cont’d)

FIGURE 8.13

Page 18: 1 ISE 491 - Ch. 8 pt. 2 Resource-constrained scheduling: Computer demonstration EMR Project  The development of a handheld electronic medical reference.

18ISE 491 - Ch. 8 pt. 2

Creating a time-phased budget (cont’d)

FIGURE 8.14

Page 19: 1 ISE 491 - Ch. 8 pt. 2 Resource-constrained scheduling: Computer demonstration EMR Project  The development of a handheld electronic medical reference.

19ISE 491 - Ch. 8 pt. 2

Creating a time-phased budget (cont’d)

FIGURE 8.15

Page 20: 1 ISE 491 - Ch. 8 pt. 2 Resource-constrained scheduling: Computer demonstration EMR Project  The development of a handheld electronic medical reference.

20ISE 491 - Ch. 8 pt. 2

Creating a time-phased budget (cont’d)

FIGURE 8.16

Page 21: 1 ISE 491 - Ch. 8 pt. 2 Resource-constrained scheduling: Computer demonstration EMR Project  The development of a handheld electronic medical reference.

21ISE 491 - Ch. 8 pt. 2

Monthly Cash Flow Statement

FIGURE 8.17

Page 22: 1 ISE 491 - Ch. 8 pt. 2 Resource-constrained scheduling: Computer demonstration EMR Project  The development of a handheld electronic medical reference.

22ISE 491 - Ch. 8 pt. 2

Resource Usage Table

FIGURE 8.18