1 - INTRODUCTIONenvironmentclearance.nic.in/writereaddata/FormB/EC/EIA...EMP Report For Colour...
Transcript of 1 - INTRODUCTIONenvironmentclearance.nic.in/writereaddata/FormB/EC/EIA...EMP Report For Colour...
EMP Report For Colour Granite Mine of 4.000 Ha, located in Gopalpur (V), M.Turkapally (M), Yadadri District, Telangana State
M/s. SOLIDO ROCKS AND MINERALS PVT. LTD.
Global Enviro Labs, Hyderabad 1
1. INTRODUCTION
1.1 INTRODUCTION
M/s. SOLIDO ROCKS AND MINERALS PVT. LTD., Director: Atin Agarwal applied
a quarry lease for colour granite over an extend of 4.000 Hectares in survey numbers:
227/1 of Gopalpur Village, M.Turkapally Mandal, Yadadri District, TS.
The lease was issued by Director of Mines & Geology, Hyderabad, Vide Proceeding No.
11830/R2-2/2016 dated 19-01-2017. The mining plan was prepared and approved vide
letter No.2788/QP/YDB/2017 Dt: 24.10.2017.
The Lessee is proposes to produce about 10249.20 (max) cum per annum of Colour
Granite. The total cost of the project is Rs. 45 Lakhs only.
Cluster Clarification: The proposal submitting under cluster formation as per
MoEF&CC Notification S.O. No.141 (E) dated 15th
January 2016 and its amendment
Notification S.O. No.2269 (E) dated 1st July 2016.The ADMG,Yadadri-Bhuvanagiri
District issued a cluster clarification letter vide Lr.No.1700/QL/2016 Dt:11.12.2017.as
per the letter with in the 500 mtrs more than 5.00 Hect. extent s mines are there so that
this proposal applying to SEAC.
S.No. Name of the
Lessee Location
Extent In
Hect.
1 Kola Sethna
Sy No. 50/1
Gopalpuram (V)
M.Turkapally (M).
8.00 Hect
M/s. SOLIDO ROCKS AND MINERALS PVT. LTD is conscious of its responsibility
towards the society in minimizing the pollution load due to this proposed activity and
according to Office Memorandum No. -11011/47/2011-IA.II(M), dated.18-05-2012 from
MoEF, GoI, New Delhi for obtaining Environmental Clearance from SEIAA, Telangana
State; the project proponents intends to prepare an Environmental Management Plan for
submission for grant of Environmental Clearance for their proposed 4.000 Hectares.
Colour Granite Mine Lease area.
EMP Report For Colour Granite Mine of 4.000 Ha, located in Gopalpur (V), M.Turkapally (M), Yadadri District, Telangana State
M/s. SOLIDO ROCKS AND MINERALS PVT. LTD.
Global Enviro Labs, Hyderabad 2
Table – 1: SALIENT FEATURES OF THE STUDY AREA
Details of the Study Area
District & State Yadadri, Telangana
Mandal M.Turkapally
Village Gopalpur
Nature of the Area Government Land
Latitude & Longitude
17° 40’41.01” N 78°45’35.25” E
17° 40’42.59” N 78°45’36.78” E
17° 40’45.20” N 78°45’34.99” E
17° 40’45.84” N 78°45’36.80” E
17° 40’48.27” N 78°45’37.14” E
17° 40’48.71” N 78°45’36.33” E
Topo-sheet No: 56 K/10.
17° 40’50.13” N 78°45’37.35” E
17° 40’49.11” N 78°45’40.04” E
17° 40’49.04” N 78°45’42.69” E
17° 40’46.58” N 78°45’40.38” E
17° 40’44.64” N 78°45’42.80” E
17° 40’41.66” N 78°45’41.49” E
17° 40’40.11” N 78°45’40.83” E
General Climatic Conditions
Maximum Temperature 44oC
Minimum Temperature 18 oC
Annual Rainfall 770 mm
Wind Pattern NE - SW
Accessibility
Road Connectivity A BT Road of 01 Km Length is connecting to
the area from Gopalpur Village.
Rail Connectivity The nearest Railway station is located at
Bhuvanagiri at a distance of 32 km from the
applied area
Air Port RGIA-60 Km
Nearest Village Gopalpur Village is located at a distance of 01
m from the applied area.
Nearest City Hyderabad- 70 Km
Historical / Important Places
Archaeologically Important Site Nil within the study area
Historically Important Site Nil within the study area
Sensitive Places Nil within the study area
Sanctuaries / National Parks Nil within the study area
Nearest Forest Gopalpur RF- 15 mtrs,
Kondapuram RF,Vasalamarri
RF,Chinnalakshmi RF-01 Km,Pirlapalli
Rf,Srinivasapuram RF – 4 KM,Karkupatla RF-
01 Km,Somajipalli RF-5.5 Km
Nearest water body Shamirpet Vagu-8.5 Km,Waterpond-50 mtrs
Figure 1 shows the 10 km radius of the study area around the proposed Mine Lease area.
EMP Report For Colour Granite Mine of 4.000 Ha, located in Gopalpur (V), M.Turkapally (M), Yadadri District, Telangana State
M/s. SOLIDO ROCKS AND MINERALS PVT. LTD.
Global Enviro Labs, Hyderabad 3
EMP Report For Colour Granite Mine of 4.000 Ha, located in Gopalpur (V), M.Turkapally (M), Yadadri District, Telangana State
M/s. SOLIDO ROCKS AND MINERALS PVT. LTD.
Global Enviro Labs, Hyderabad 4
2. PROJECT DESCRIPTION
2.1 THE PROJECT
The project of M/s. SOLIDO ROCKS AND MINERALS PVT. LTD deals with the
production 10249.20 (max) cum/Year of Colour Granite in Sy. No 227/1 of Gopalpur
village, M.Turkapally Mandal, Yadadri District of Telangana State. In view of the
shallow nature of the deposit, open cast mining method shall be adopted in a semi
mechanized manner by developing multiple benches.
The applied Quarry lease Area is located on Survey of India Toposheet No.56/K/10 and the area falls
between the 17° 40’40.77” N, 78°45’34.99” E. The quarry lease applied area is located at
1.0 km due South of Gopalpur village and M.Turkapally Mandal Head Quarters is
located at the distance of 06 km due South of the quarry lease applied area.
2.2 NEED FOR THE PROJECT
In order to meet the statutory requirements the lessee intends to obtain Environmental
Clearance from Statutory Authorities.
2.3 TOPOGRAPHY
The quarry lease applied area is located on a low N-S trending barren hill sloping on both
sides rising 13 M above ground level. The area is unfit for agriculture as it is strewned
with boulders.
The area fall partly on the Water Divide Zone. The drainage network is due West and
SW flows of the quarry lease applied area. The area around the applied area are barren
and Dry agricultural lands.
The quarry lease applied area is a part of barren hill raised 13 M above ground level
within the quarry lease applied area with topo relief in East direction. The exposures of
rock outcrops are abundant in N-S. The lowest contour is 581 M and highest contour is
594 M.
EMP Report For Colour Granite Mine of 4.000 Ha, located in Gopalpur (V), M.Turkapally (M), Yadadri District, Telangana State
M/s. SOLIDO ROCKS AND MINERALS PVT. LTD.
Global Enviro Labs, Hyderabad 5
2.4 GEOLOGY
2.4.1 Regional Geology
The quarry lease areas comprise of Granites and Granitic Gneiss of Archean Age. Pink
and Grey Granites, Pink Alkali - Feldspar Granites and Gneissic Grano Diorite – Quartz
Diorite with enclaves of Supra - Crystals like Quartzite, Chlorite Schist, Hornblende -
Biotite Schist etc. constitute the Granitoid – Migmatite complex. These Litho units are
exhibit various geomorphic expressions like Domes, Inselbergs, Castle - Koppies and
Whalebacks and Basic Dykes forms Linear Ridges with moderate Relief.
The geological succession of the area as worked out by GSI (1991) is as follows:
RECENT SOIL / ALLUVIUM
Precambrian
Intrusive
Basic intrusive Dolerite / Porphyritic
Dolerites, Gabbro, Pyroxenite
Aplite / Pink Pegmatite / Quartz Reef /
Quartz Veins. Pink Whitish Fine Grained
Alkali Feldspar Granite/Migmatite-II
Granitoid Migmatite
Pink Coarse Grained Granite /
Migmatite II Meta Pyroxenite, Meta
Dolerite Dyke / Grey Pegmatite
Grey Granite – Granodiorite /
Migmatite I. Gneissic Quartz Diorite –
Tonolite / Granite Units
Supracrustal
(Dharwars)
Amphibolites / Hornblende Schist /
Mica Chlorite Schist / Meta Basite / Meta
Volcanics / Quarzite / Banded Iron
Formations
Pre Cambrian Supra Crustal occurs as linear enclaves in younger granites.
The region of the quarry lease area is belonging to peninsular gneiss of Archaean group.
The Peninuslar Gneissic Complex comprising migmatite gneiss, grey granodiorite,
porphyritic granite and intruded by dolerite and aplite veins.
The Peninsular Gneissic Complex comprises gneiss-migmatite-granite suite of rocks.
They are highly variable in mineralogical composition appearance structure and relative
ages. The individual members have not been distinguished in a major part of the area.
However, granite and migmatite gneiss occupy a large part of the area, while bands of
relatively younger coarse-grained gneissic granite occur in the north eastern part.
EMP Report For Colour Granite Mine of 4.000 Ha, located in Gopalpur (V), M.Turkapally (M), Yadadri District, Telangana State
M/s. SOLIDO ROCKS AND MINERALS PVT. LTD.
Global Enviro Labs, Hyderabad 6
The Karimnagar belt located along the tectonic joitns between the Dharwar belt and
bastra cratons in north eastern part of the state and made up of rocks of high grade
metamorphism, migmatisation and intense deformation. These granites, which are often
porphyritic, are intrusive into the gneissic terrain and contain alkali feldspar space. The
later in parts the colour to the granite which ranges from light to deep pink because of the
massive nature of these intrusive they are mineral for producing large size blocks.
The rock is exposed in the form of cluster of sheet.
2.4.2 Geology of the Area:
Entire quarry lease area is covered with colour granite which is rising up to 13 M above
ground level trending N – S, the strike length of the deposit in the applied area measured
257 M in the area with an average width of 153M.
Three sets of joints are recorded in the formation
1. N – S Vertical
2. E- W Veritcal
3. Horizontal / Sheet Joints
These joints are closely spaced on the surface. On the other hand they are widely spaced
in the depth as noticed in the quarry sections.
Regionally the area constitute a part of Peninsular Gneissic complex of Archaean, and
occupied by Prophyritic granite, white, grey and pink colour alaskitic granite, with
patches of amphibolites, hornblende schist bonded magnetite quartzites as enclaves in
both prophyritic and alaskitic granite.
The major litho units are extensively invaded by younger quartz, pegmatite, epitode,
calcite veins and also by dykes basic rocks.
The porphyritic granite along with intermixing of pink alaskitic granite forming as
mounds, ridges and hillocks in the area; contact of the rocks clearly indicate intrusive
relationship, young alaskites intruded into older porphyritic granite; which is locally
showing poorly developed foliation trending N – E.
The older basic enclaves of amphibolites hornblende schist show signs of metasomatism
in the form of flakes of biotitic. Number of acidic veins like pegmatite, quartz is
EMP Report For Colour Granite Mine of 4.000 Ha, located in Gopalpur (V), M.Turkapally (M), Yadadri District, Telangana State
M/s. SOLIDO ROCKS AND MINERALS PVT. LTD.
Global Enviro Labs, Hyderabad 7
traversing the porphyritic granite trending in NNE – SSW. NE – SW to NNW – SSE to
NW – SE.
COLOUR GRANITE DEPOSIT
Area is characterized by rugged topography with isolated tors and inselbergs intervened
by plain land.
In quarry lease area, porphyroblastic granite occurs as massive exfoliation dome steeply,
sloping in all the direction. It is rising from minimum elevation of MSL 581 Mt to Max
elevation of MSL 594 Mt. It is uniform in mineral assemblage, texture, colour and devoid
of major joints, though few joints present, they are widely spaced with limited lateral
extent, along these joints, large boulders are formed from the domes.
However, due to very coarse grained nature of rock due to K. Feldspar crystals the rock is
prone to weathering. Hence, thick weathered mantle, soil core observed along the western
edges of the rocky outcrops with vegetal cover.
The granite porphyry has attracted the attention of the market by virtue of its pleasing
texture, where the orthoclase porphyries are unfiromly distribute in the form of elongated
or rougly oval shaped prophyroblasts of orthoclase in the mesostasis of quartz,
plagioclase, biotite and hornblend. In fact, the quartz grains with bluish tinge have added
more attraction after polishing.
Details of prospecting/ Mining already Carried Out: No Exploration/quarrying is
carried out in the area as the subject area is applied for grant of quarry lease.
2.5 GEOLOGICAL RESERVES
The quarry lease applied area is a part of barren hill raised 13M above ground level
within the quarry lease applied area with topo relief in East direction. The exposures of
rock out crops are abundant in N-S. The lowest contour is 581 M and highest contour
is 594 M.
The exposed outcrops upto 13M above the ground level and the reserves upto 20 M
below the surface are considered under proved Category of Reserves (upto RL 560 M)
and 20 M below the proved reserves (upto RL 540 M) are considered under Probable
Resources (Plate-III).
EMP Report For Colour Granite Mine of 4.000 Ha, located in Gopalpur (V), M.Turkapally (M), Yadadri District, Telangana State
M/s. SOLIDO ROCKS AND MINERALS PVT. LTD.
Global Enviro Labs, Hyderabad 8
Hence, G1 (Proved) scale category as (111) code & G2 (Probable) scale category as
(122) is calculated.
As per UNFC guidelines the G3 (333) (Possible) category are not considered as they
are not mineable unless proved by exploration.
Saleable Blocks: Even after obtaining the 20% blocks the recovery of sizeable large
blocks would be around 25% and 75% would be marginal blocks by obtaining smaller
sizes.
Blocked up (211): 10,08,812.00 M3
Mineral Resources: (Mineral resources may be estimated purely based on level of
exploration, with reference to the threshold value of minerals declared by IBM)
Level of Exploration Resources in Million M3/Colour Granite
G1-Detailed exploration 0.139
G2-General exploration 0.048
G3-Prospecting -
G4-Reconnaiswsance -
Method of Estimation of Reserves:
As the area is virgin and no exploration is carried out in the area as the lease is yet to be
granted. Hence, the database of the existing quarrying pits around are extrapolated to the
subject area to arrive the profile of the deposit.
The exposed granite deposit is found to be irregular in shape, the volume of the deposit is
computed by Cross Sectional Area method by multiplying the sectional influence.
The cross sections were drawn perpendicular to the strike direction, the cross sectional
area of the individual sections are calculated to arrive at section area, the area thus arrived
is multiplied by the sectional influence of 50 M (average) to arrive the volume of rock
mass.
The Colour Granite is general occurs as massive formation and with joints spaced are
apart on surface and widens in depth, the sizeable blocks of dimensional stones are
anticipated to be obtained. Hence, a conservative recovery of 20% is arrived for Colour
Granite.
The cross section in E-W direction are drawn at equal interval of 50 M. 5 cross sections
A-A1 to E-E1 was drawn.
EMP Report For Colour Granite Mine of 4.000 Ha, located in Gopalpur (V), M.Turkapally (M), Yadadri District, Telangana State
M/s. SOLIDO ROCKS AND MINERALS PVT. LTD.
Global Enviro Labs, Hyderabad 9
a) Total Geological Reserves
TOTAL GEOLOGICAL RESERVES
Sections Category &
UNFC Code
Sectiona
l Area
Sectional
Influence
Volume Recovery of
@ 20%
(M2) (M) (M
3) (M
3)
A – A1 Proved (111) 3.660.00 56.00 204,960.00 40,992.00
Probable (122) 3,185.00 56.00 178,360.00 35,672.00
B - B1 Proved (111) 4,294.00 50.00 214.700.00 42,940.00
Probable (122) 3,078.00 50.00 153.900.00 30,780.00
C – C1 Proved (111) 5,458.00 50.00 272,900.00 54,800.00
Probable (122) 3,728.00 50.00 186.400.00 37,280.00
D – D1 Proved (111) 3,469.00 50.00 173,450.00 34,690.00
Probable (122) 2,265.00 50.00 113,250.00 22,650.00
E – E1 Proved (111) 4,970. 54.00 268,380.00 53,676.00
Probable (122) 3,224.00 54.00 174,096.00 34,819.20
TOTAL RESERVES 1,94,396.00 3,88,079.20
RESERVES IN UNFC CODE
S.No. Category of Reserves UNFC Code Reserves in M3
Reserves in
Million M3
1 Proved 111 11,34,390.00 1,134
2 Probable 122 8,06,006.00 0.808
3 Possible 333 Nil Nil
RESERVES BLOCKED UNDER 7.5 M BUFFER ZONE
Sections Category &
UNFC Code
Sectional
Area
Sectional
Influence
Volume
(M2) (M) (M
3)
A – A1 Proved (111) 260.00 56.00 14,560.00
Probable (122) 208.00 56.00 11,648.00
B - B1 Proved (111) 436.00 50.00 21,800.00
Probable (122) 343.00 50.00 17,150.00
C – C1 Proved (111) 612.00 50.00 30,600.00
Probable (122) 456.00 50.00 22,800.00
D – D1 Proved (111) 478.00 50.00 23,900.00
Probable (122) 478.00 50.00 15,900.00
E – E1 Proved (111) 318.00 54.00 15,768.00
Probable (122) 292.00 54.00 9,882.00
TOTAL RESERVES 1,84,008.00
EMP Report For Colour Granite Mine of 4.000 Ha, located in Gopalpur (V), M.Turkapally (M), Yadadri District, Telangana State
M/s. SOLIDO ROCKS AND MINERALS PVT. LTD.
Global Enviro Labs, Hyderabad 10
RESERVES BLOCKED UNDER SAFETY SLOPES
Sections Category &
UNFC Code
Sectional
Area
Sectional
Influence
Volume
(M2) (M) (M
3)
A – A1 Proved (111) 449.00 56.00 25,144.00
Probable (122) 935.00 56.00 52,360.00
B - B1 Proved (111) 510.00 50.00 25,500.00
Probable (122) 1,307.00 50.00 65,350.00
C – C1 Proved (111) 581.00 50.00 29,050.00
Probable (122) 1,39.00 50.00 67,950.00
D – D1 Proved (111) 734.00 50.00 36,700.00
Probable (122) 1,478.00 50.00 73,900
E – E1 Proved (111) 777.00 54.00 41,580.00
Probable (122) 1,514.00 54.00 81,756.00
TOTAL RESERVES 4,99,290.00
Reserves blocked under Road Safety Barrier Zone:
Sections Category &
UNFC Code
Sectional
Area
Sectional
Influence
Volume
(M2) (M) (M
3)
A – A1 Proved (111) 2,259.00 56.00 1,26,112.00
Probable (122) 2,042.00 56.00 1,14,352.00
TOTAL RESERVES 2,40,464.00
Reserves blocked under Temple Safety Barrier Zone:
Sections Category &
UNFC Code
Sectional
Area
Sectional
Influence
Volume
(M2) (M) (M
3)
E – E1 Proved (111) 925.00 54.00 49,950.00
Probable (122) 650.00 54.00 35,100.00
TOTAL RESERVES 85,050.00
Total Mineable Reserves
RESERVES AVAILABLE FOR MINING
A. Total Geological Proved 11,34,390.00 M3 19,40,396.00 m3
Probable 8,06,006.00 m3
B Reserves Blocked under Proved 1,06,628.00 m3
EMP Report For Colour Granite Mine of 4.000 Ha, located in Gopalpur (V), M.Turkapally (M), Yadadri District, Telangana State
M/s. SOLIDO ROCKS AND MINERALS PVT. LTD.
Global Enviro Labs, Hyderabad 11
7.5 M buffer zone 1,84,008.00 m3
Probable 77,380.00 m3
C. Reserves blocked under
safety slopes
Proved 1,57,974.00 m3 4,99,290.00 M3
Probable 3,41,316.00 m3
D. Reserves blocked under
road safety Barrier Zone
Proved 1,26,112.00 m3 2,40,464.00 m3
Probable 1,14,352.00 m3
E. Reserves blocked under
Temple safety Barrier
Zone
Proved 49,950.00 m3
85,050.00 m3
Probable 35,100.00 m3
D. Total Reserves Blocked
(B+C+D+E)
Proved 4,40,664.00 m3 10,08,812.00 m3
Probable 5,68,148.00 m3
E Reserves available for
quarry (A-(B+C+D+E)
Proved 6,93,726.00 m3 9,31,584.00 m3
Probable 2,37,858.00 m3
Extraction of Market Grade Reserves :
b) Recovery (Proved)
@ 20% Recovery (Proved) = 1,38,745.20 M3Life of the Quarry
= 1,38,745.20 M3 / 8,154.96 M
3
= 17.01 YEARS
c) Recovery (Probable)
@ 20% Recovery (Probable) = 47,571.60 M3
Life of the Quarry = 47,571.60 M3 / 8,154.96 M
3
= 5.83 OR
EMP Report For Colour Granite Mine of 4.000 Ha, located in Gopalpur (V), M.Turkapally (M), Yadadri District, Telangana State
M/s. SOLIDO ROCKS AND MINERALS PVT. LTD.
Global Enviro Labs, Hyderabad 12
d) Life of the Quarry
Proved + Probable = 22.84 or say 23 Years
Economic Marketable Reserves : The Colour Granite is having good export market,
rough blocks free from defects like fractures, joints, shears, Hair Line Cracks,
Segregation Veins, Drastic Colour variation and having 120 up Size (Ganga Saw Size)
are mostly preferred by exporters and international buyers. These area known as
Economic or Market Grade (But in this quarry such sizes rarely found). The size blocks
used for manufacturing of tiles generally recovered from this quarry, which forms nearly
25% recovery of economic grade and 75% of market grade:
TOTAL RESERVES (Proved+Probable) = 1,86,316.80 M3
(a) Economic Grade (Large Blocks) 25% = 46,579.20 M3
(b) Marginal Grade 75% = 1,39,737.60 M3
2.6 MINING
(Open Cast other than fully Mechanized / Semi Mechanized) : The method of
quarrying shall be opencast and Semi-mechanized on single shift basis. Excavations
shall be carried out by Jack Hammer drilling and blasting. Bench height and width will
be maintained at 6m height and 6 m width each respectively with overall slope at 60o.
Excavation and loading shall be carried out with simple excavators of capacity 0.9 to 1.1
m3 bucket capacity. This shall be utilized for developmental work, excavation and
loading into the trucks. Tippers of 10 T capacity shall be utilized for all transportation
purpose.
The Colour Granite in the quarry lease applied area is exposed on the surface with
boulders. Hence, it is proposed to mine the boulders / sheet by open cast, semi-
mechanized methods, by developing the benches of 6 height in and 6 M width. Wire Saw
cutting will be deployed based on the favourable conditions. The development of benches
in the sheet rock will be maintained @ 600
safety slopes.
The separation of blocks from the mother rock will be carried out by drilling and
chiseling with hammers with small pressure after wire saw operations, drilling and
EMP Report For Colour Granite Mine of 4.000 Ha, located in Gopalpur (V), M.Turkapally (M), Yadadri District, Telangana State
M/s. SOLIDO ROCKS AND MINERALS PVT. LTD.
Global Enviro Labs, Hyderabad 13
dousing with excavators will be done by through poclain teeth or with bucket separating
from the mother rock.
The second splitting, dressing of blocks will be done manually or poclain bucket by tam
rock machine with drilling and splitting.
Therefore, mining operations are to be carried out in this area in 2 stages.
1) Development
2) Production
Stage- 1
The removal of weathered and under sized boulders will be cleared in the quarry lease
applied area for the next five years by using excavator.
The sheet that is exposed will be subjected to drilling, with compressors and tam rocks,
chiseling with hammers applying pressure by poclain teeth and splitting from mother
rock.
Rock splitting / Wedging : Thus 20’ x 20’ to 40’ x 20’ to 40’ mass will be separated
from mother rock by drilling the slotter holes on both sides of the mass and a top holes
intersecting these two holes and wiresaw rope is passed through and cutting is done
horizontally and vertically and by this there will be mass opening on all the sides from
the mother mass.
Stage-2
After removal of weathered and under sized boulders.
The large boulders will be subjected to splitting into required sizes of blocks
by using Jack Hammers by drilling series of deep holes at right angles at
regular intervals, later by inserting feather and wedges in these holes and
hammering with sledge hammer will release the blocks.
The boulders will be splitted to the required sizes with drilling and if required
by using chemical compound at the source only. The boulders separated will
be brought to the dressing yard for dressing.
If the boulders, which fit into the required market grade size will be
transformed into cuboids.
EMP Report For Colour Granite Mine of 4.000 Ha, located in Gopalpur (V), M.Turkapally (M), Yadadri District, Telangana State
M/s. SOLIDO ROCKS AND MINERALS PVT. LTD.
Global Enviro Labs, Hyderabad 14
Secondary Splitting: After separation from the mother rock, it is properly checked by
washing with water to identify defects and cracks. Based on this observation, the size is
decided and the blocks are marked and separated by drilling and wedging.
The separated pieces will be examined for defects and lines, then the block or blocks are
marked in clear area and holes are drilled along the line of marking , with the help of
feathers and wedges the waste portions are separated forming a rectangular blocks. Any
bulges will be removed by drilling and wedging making it perfect blocks. A perfect block
is that all the sides shall make with each other 900.
Dressing:
Dressing of dimensional rough blocks for export: Dressing is final phase of mining
operation, wherein the secondary rough blocks are squared into regular perfect
rectangular sizes, thereby avoiding uneven bulge or cavities and other defects.
Jackhammers with compressor, feather end wedges and sledgehammers are equipments
generally used for dressing the block.
Dressing of rough blocks for domestic processing plant: Dressing by means of squaring
and splitting will be done for rough blocks of the size varying between 120 x 90 x 80 to
300 x 200 x190 M.
Description of granite processing plant: The lessee company does not possess processing
plant.
Drilling & Blasting : Drill hole of 6.25 M depth will be drilled in a single row
with spacing of less than 0.3 M and burden of 1.6 M or more shall be maintained
uniformly. This arrangement will yield rock size of 3 M x 2 M Cross section. A
bench height of 6.0 M will be tackled.
Drilling Parameters: Drill Hole Diameter 32 MM up to 9 M Long.
Depth and Inclination of Drill Hole: Generally drilled vertically in an alignment
however in primary cutting in the absence of sheet joints to develop bottom level,
horizontal holes also are drilled.
Explosive Type: Wherever required gunpowder is used for splitting the rock.
EMP Report For Colour Granite Mine of 4.000 Ha, located in Gopalpur (V), M.Turkapally (M), Yadadri District, Telangana State
M/s. SOLIDO ROCKS AND MINERALS PVT. LTD.
Global Enviro Labs, Hyderabad 15
Machinery:
Excavator(Hitachi)200 1 NO
Compressor 300 1 NO
Jack Hammers 3 NO’ s
Tipper 1 NO
2.7 MINERAL PROCESSING
The lessee intends to sell the raw blocks to the processing units in the country and also
export to foreign countries. The lessee does not possess a processing plan at the moment.
2.8 SITE SERVICES
The rest shelter cum office, First aid room, and toilets are constructed in the flat. The roof
is of asbestos sheets covered by hay to keep it cool in summer. A first aid certificate
holder will be the in charge of the first aid room. Protected drinking water will be
provided and stored in earthen pots.
2.9 EMPLOYMENT POTENTIAL
The mining activity will provide the job facilities to the local people. It will have 1 Mines
Manager, skilled & unskilled labour about 28 persons.
EMP Report For Colour Granite Mine of 4.000 Ha, located in Gopalpur (V), M.Turkapally (M), Yadadri District, Telangana State
M/s. SOLIDO ROCKS AND MINERALS PVT. LTD.
Global Enviro Labs, Hyderabad 16
3. EVALUATION OF IMPACTS
3.1 INTRODUCTION
Opencast mining activity causes some adverse impacts on the surround environment
unless proper environmental management plan is adopted. Selecting suitable sites for
mining and adopting the guidelines prescribed by the Ministry of Environment & Forests
(MoEF) and Indian Bureau of Mines (IBM), one can minimize the major possible
impacts.
In this chapter, an attempt has been made to quantify the possible environmental impacts
on various features such as air, water, noise, land, ecology and socio-economies. The
following aspects have been studied to identify the possible impacts while achieving the
total production of 10249.20 (max) Cum/Year of Colour Granite.
The magnitude and significance of the environmental pollution caused by mining
depends on method of mining, scale and concentration of mining activity.
3.2 AIR ENVIRONMENT
The impacts on air environment from a mining activity depend on various factors like
production capacity, machinery involved, operations and maintenance of various
equipments and vehicle. Apart from these, there will be other activities associated viz
transportation of mineral and waste, stocking facilities and dump management within the
mine lease area that may contribute to pollution.
3.2.1 SOURCES OF DUST EMISSION
Mining is carried out by open cast semi mechanized method by using jack hammer
drilling & wire saw cutting and using low explosive blasting. Based on the various
operations involved in the production of minerals, the various emission sources has been
identified as given below.
a. Point soruces
b. Area sources.
c. Line sources.
EMP Report For Colour Granite Mine of 4.000 Ha, located in Gopalpur (V), M.Turkapally (M), Yadadri District, Telangana State
M/s. SOLIDO ROCKS AND MINERALS PVT. LTD.
Global Enviro Labs, Hyderabad 17
Drilling operations of the mine are considered as point sources. Extraction of mineral
from mine, are considered as area sources. Transportation of material from mining
benches to various end points are considered as line sources. The impact of above sources
on air environment is discussed below:
a) Drilling & Blasting
One the boulder is freed by removing the soil and waste rock surrounding it, a series of
holes are drilled by compressed air using Jack Hammer at a regular interval of 15-30 cms
depending on the size of the boulder, the depth of the hole depends on the height of the
boulder and the holes are drilled up to the bottom leaving about a foot at the base. The
holes have to be perfectly straight and vertical so that the vertical split is obtained. Line
drilling machine can be used to drill straight holes. Feather and wedges are inserted into
the holes and hammered continuously applying uniform pressure and the boulder splits
vertically. Similarly dressing is done and the boulder is given a rectangular shape. All the
defects are avoided during the dressing stage. Diamond wire saw may also be employed
to dislodge the block from the parent rock.
Drill hole pattern will be uniform single lined pattern, equidistances holes from 0.33 m to
0.75 m , 4.5 m in depth. Spacing depends upon the size of the boulder, in general it 15
cms from hole to hole for better splitting.
The concentrations due to low explosives blasting will be confined to a maximum
distance of 10 m from the area of blasting. These concentrations will not be emitted
continuously. However presence of personnel near the blasting site during blasting will
be totally avoided. So, the impact of blasting on the air environment will be minimal.
b) Extraction & Loading
Extraction & Loading will be done by a crane and excavator and these activities of mine
operation is contributing to the area source emission and the extent of influence of this
operation is about 100 m2.
EMP Report For Colour Granite Mine of 4.000 Ha, located in Gopalpur (V), M.Turkapally (M), Yadadri District, Telangana State
M/s. SOLIDO ROCKS AND MINERALS PVT. LTD.
Global Enviro Labs, Hyderabad 18
c) Haulage &Transportation
In the operating mine, the dressed blocks from mine face to the consumers is transported
by hired trucks. The trucks will be well maintained so that exhaust smoke does not
contribute abnormal values of noxious gases and unburnt hydrocarbons. The other
sources of air pollution is due to the dust generated during the movement of tippers on the
haul road.
The above sources, which include drilling, low explosives blasting, excavation, haulage
for transport of blocks will contribute to dust pollution in the air.
3.2.2 ANTICIPATED IMPACTS
The impacts envisaged due to mining activity are evaluated based on various factors. The
emission inventory of the pollutants is as follows, the main air pollutant would be dust or
particulate matter generated by handling and transportation of Colour Granite . But the
impact of mining operations on air quality is minimum as mining involved method by
using jackhammer drilling & wire saw cutting & low explosive blasting and as the
production quantity is very less i.e. 40.99 Cum/Day only.
3.2.2.1 Dust Generation and Control
The air pollutant would be dust or particulate matter generated by handling and
transportation of granite blocks. The existing ambient air quality at quarry lease area is
within the limits prescribed by T.S.P.C.B. The envisaged production of minerals is only
40.99 Cum/Day. The dust generated due to mining operations will be controlled by water
sprinkling through water tankers
3.3 NOISE ENVIRONMENT
Noise will be produced at the mine is due to operations of machinery, drilling, blasting,
and movement of vehicles. The noise generated by the mining activity is dissipated
within a small zone around the mine. The present noise levels at quarry lease area are
within the limits prescribed by T.S.P.C.B. There is no major impact of the mining activity
on the vicinity however; pronounced effect of above noise levels will felt only near the
EMP Report For Colour Granite Mine of 4.000 Ha, located in Gopalpur (V), M.Turkapally (M), Yadadri District, Telangana State
M/s. SOLIDO ROCKS AND MINERALS PVT. LTD.
Global Enviro Labs, Hyderabad 19
active working area and on the personnel working in the vicinity. The impact of noise on
the villages is negligible as the villages are located far from the mine site.
3.4 WATER ENVIRONMENT
The Mining activity will be carried out on mound slope will not have any effect on the
ground water and the static water table in this area is below 20 m.
3.4.1 Impact on Surface Water
There are no major streams and rivers, which can get effected by the mining. Hence,
there will be no effect on the surface water.
During the present plan period quarrying will go to depth of 10 meters from the present
level of mining. During the monsoon period, the rainwater, if gets stagnated, will be
drained out. The benches will made with an inward slope to facilitate run off more faster
on to the mine floor. Small bunds, garlands and silting tanks also will be constructed to
minimize inflow muddy water which carry fine material.
3.4.2 Impact on Ground Water
Mining activity will be above the BWL (20 m). Hence, there will be no effect on the
ground water regime.
3.4.3 Impact on Water Quality
Water quality in the buffer zone have indicated that the ground water is free from heavy
metal concentration and this mining activity will not interference on the water quality.
3.4.4 Water Consumption & Wastewater Generation
The water requirement for this proposed mining activity will be 5.5 KLD. Breakup
details are:
Sl. No: Purpose Quantity (KLD)
1 Dust suppression purpose 3.5
2 Domestic purpose 1.0
3 Greenbelt purpose 1.0
Total 5.5
There is no generation & discharge of wastewater from this mine.
EMP Report For Colour Granite Mine of 4.000 Ha, located in Gopalpur (V), M.Turkapally (M), Yadadri District, Telangana State
M/s. SOLIDO ROCKS AND MINERALS PVT. LTD.
Global Enviro Labs, Hyderabad 20
3.5 LAND ENVIRONMENT
Various components of land environment have been identified for study of impact of the
mine operations. Details of the same are given below:
3.5.1 Solid Waste Generation
Removal of weathered rock and the rock waste is the only solid waste that will be
generated from this mine. Some of the material from the waste may be sorted out and
used for making small blocks to be used by the local unit for making tiles. The market for
tiles is good at the moment and they will offer a better substitute for marble in terms of
price and quality. Some rejected and unsorted material may be used in the civil
engineering projects in the vicinity of the area. The waste material can also be crushed
into smaller sizes and can be used as road metal
The waste generated during the five years may be dumped in the zone separately reserved
for dumping within the quarry lease area. The dump will be designed in such that it will
have slopes equal to the angle of repose of such material. Garland drains have to be sunk
along around the leading edge of the dump. A retaining wall will be constructed around
the dump to preventing the slanting of boulders Care will be taken to minimize the waste
generation at the source.
About 40996.80 m3/Year of waste will be generated from this mine. The waste generated
will be dumped temporarily in the NW of the quarry lease area between the grids N
1956135 – 1956195 & E 262465 – 262570 covering an area of 3,438 m3 with an average
height of 6M with 450 slope angle with be formed. A retaining wall will be constructed
around the dump for preventing the slanting of boulder.
3.5.2 Impact on Land use
The mine is located in an area of 4.000 Ha. No forestland is involved.
After the operations cease, the mine spoiled area will be back field. It may not be
possible to complete regain the original topography of the area. During quarrying
whatever solid waste is generated shall be dumped at dumping site inside the Q.L. area.
The mining lease area is not a part of any type of forest. Entire mine lease area is govt.
EMP Report For Colour Granite Mine of 4.000 Ha, located in Gopalpur (V), M.Turkapally (M), Yadadri District, Telangana State
M/s. SOLIDO ROCKS AND MINERALS PVT. LTD.
Global Enviro Labs, Hyderabad 21
land hence all the impact on land use is positive because aesthetic environment will not
be effected, as the mine is located on a plain with some bushes.
Due to opencast mining activities, the landscape will be slightly changed. There
will be no land subsidence as the country is made up of hard rock. The Soil cover in this
mine is almost nil and Agriculture is seen mainly in the plains in the vicinity of the lease
area and the mining will not have any impact on the agricultural pattern. Only few bushes
will be cleared to facilitate mining and other related activities and there are no big
trees, which may have to be cut.
3.5.3 Impact of Ground vibrations
Fragmentation of rock by blasting is an important operation in mining project, where hard
rock occurs. Blasting will be done only when it is absolutely necessary, using low
intensity explosives.
Blasting of the mineral at the proposed mine will be done by using Low-density
chemical explosives like ECM/ CaOH will be used. Sometimes smooth blasting may be
done using silent non-explosive demolishing agents like Acconex.
The ground vibrations caused by blasting will not have any affect as the mining is on a
mound and the vibrations will be minimum and will not be carried too far due to the hard
nature of the rock.
3.6 BIOLOGICAL ENVIRONMENT
There is no adverse impacts are anticipated due to the proposed mining activity on
biological environment. However, with the implementation of the environmental
management measures, there will be improvement in the parameters of biological
environment.
The tree species found with the core zone represent the common type of flora species
along with small shrubs and bushes. Due to mining activities community structure of the
vegetation will not change. Whereas diversity of plant species and food web index of the
area reduced to certain extent.
EMP Report For Colour Granite Mine of 4.000 Ha, located in Gopalpur (V), M.Turkapally (M), Yadadri District, Telangana State
M/s. SOLIDO ROCKS AND MINERALS PVT. LTD.
Global Enviro Labs, Hyderabad 22
However, if the proposed reclamation of the mining area and dumped out area using
proper re-vegetation techniques and development of green belt around the ultimate limit
and roadside there shall be an improvement in the species diversity and food web index
compared to the existing level.
3.7 SOCIO- ECONOMIC ENVIRONMENT
3.7.1 No Rehabilitation
The mine area does not cover any habitation. Hence the mining activity does not involve
any displacement of human settlement. No public buildings, places, monuments etc. exist
within the lease area or in the vicinity. The mining operations will not disturb/ relocate
any village or need resettlement. Thus no adverse impact is anticipated.
3.7.2 Improvement in Socio Economic Status
It will be obvious to assume that the activities of the mining operations have to be
produced some improvements in the socio-economic levels in the study area.
The Lessee will provide employment to local population and it will give preference to the
local people whenever there is requirement of manpower. The proposed mining activities
will provide employment to persons of different skills and trades. The local population is
the largest plausibility among these employees. The employment potential ameliorated
economic conditions of these families directly and provided employment to many other
families indirectly who are involved in business and service oriented activities. This in-
turn will improve the socio-economic conditions of the area.
3.7.3 Occupational Health and Safety
The mine is going to be developed mainly semi mechanized opencast method by using
jackhammer drilling & wire saw cutting & low explosive blasting. No major crushing or
pulverization will be done here. The small-scale mining will not have any ill effects on
the health of labour. Excessive dust and noise are the chief health hazards for the miners.
As already mentioned these causative factors are well within the safety limits and the
proponents will strictly implement the prescribed safety measures. The health of the
workers will be regularly checked and suitable medical facilities should be created on or
close to the site. Highest safety will be ensured in the working conditions of the miners.
EMP Report For Colour Granite Mine of 4.000 Ha, located in Gopalpur (V), M.Turkapally (M), Yadadri District, Telangana State
M/s. SOLIDO ROCKS AND MINERALS PVT. LTD.
Global Enviro Labs, Hyderabad 23
4. ENVIRONMENTAL MANAGEMENT PLAN
4.1 INTRODUCTION
The mining development in the study area needs to intertwined with judicious utilization
natural resources within the limits of permissible assimilative capacity. The assimilative
capacity of the study area is the maximum amount of pollution load that can be
discharged in the environment without affecting the designated use and is governed by
dilution, dispersion and removal due to natural physio-chemical and biological processes.
The Environmental Management Plan (EMP) is required to ensure sustainable
development in the study area.
This chapter covers the genesis of pollution, the principal sources of pollution, the nature
of pollution, the proposed measures required for meeting the prevailing statutory
requirements of gaseous emissions, wastewater discharge characteristics, noise levels etc.
for environmental management purpose in connection with the mining and mining related
activities in the study area.
This section discusses the management plan for mitigation/abatement impacts and
enhancement of beneficial impacts due to mining. The Environmental Management Plan
(EMP) has been designed within the framework of various Indian legislative and
regulatory requirements on environmental and socio-economic aspects.
Environmental Management Plan giving the environmental protection measures at mine
to meet the stipulated norms of IBM/MoEF are as detailed.
4.2 AIR POLLUTION CONTROL MEASURES
The present ambient air quality measurements in the mine area are well within the limits.
Due to the proposed production of 10249.20 (max) Cum/Year of Colour Granite, there
will be marginal increase in dust concentrations.
EMP Report For Colour Granite Mine of 4.000 Ha, located in Gopalpur (V), M.Turkapally (M), Yadadri District, Telangana State
M/s. SOLIDO ROCKS AND MINERALS PVT. LTD.
Global Enviro Labs, Hyderabad 24
Mitigative measures suggested for air pollution control are based on the baseline ambient
air quality monitoring data. From the point of view of maintenance of an acceptable
ambient air quality in the region, it is desirable that air quality should be monitored on a
regular basis to check it vis-à-vis the standards prescribed by CPCB and in cases of non-
compliance appropriate mitigative measures shall be adopted.
The following dust prone areas are identified for adopting proper control measures in the
mine area.
i) Drilling & Wire Saw Cutting & Blasting
ii) Excavation
iii) Transportation
The environmental control measures which will be implemented to control the fugitive
dust released from the proposed production are given below:
Wet drilling system & Dust proof
Optima Wire Saw Cutting (using water reduces dust)
Use of sharp drill bits for drilling holes. The charge concentration of the
explosives will be between 10 – 40 grams per linear meter.
Water sprinkling arrangements such as specially fabricated tankers mounted on
tipper are deployed at mine site to control the fugitive dust generation from the
haulage roads.
Regular grading of haul roads and service roads to clear accumulation of loose
material
The blasted blocks (temporary) are wetted by spraying water
Avoiding blasting during high windy periods, night times and temperature
inversion periods.
Excavation operations are suspended during periods of very strong winds.
Massive afforestation for control of dust
Spraying of water on sub grade stacks
EMP Report For Colour Granite Mine of 4.000 Ha, located in Gopalpur (V), M.Turkapally (M), Yadadri District, Telangana State
M/s. SOLIDO ROCKS AND MINERALS PVT. LTD.
Global Enviro Labs, Hyderabad 25
The vehicles and machinery are kept in well-maintained condition so that
emission of fugitive constituents is minimized.
Plantation of wide leaf trees, creepers, tall grass around working pit, along roads
will help suppress dust.
Tall trees with an average height of 5 m will be developed all along the boundary
of the lease area to minimize the dispersion of the dust from the mining.
Periodical monitoring of air quality to take steps to control the pollutants.
4.2.1 OCCUPATIONAL HEALTH & SAFETY MEASURES
All the precautions would be adopted to prevent dust generation at site and to be
dispersed into the outer environment. However, for the safety of workers at site, engaged
at strategic locations/dust generation points like drilling, loading and unloading points,
etc., dust masks would be provided. Dust masks would prevent inhalation of RSPM
thereby reducing the risk of lung diseases and other respiratory disorders. Regular health
monitoring of workers will be carried out.
4.3 NOISE POLLUTION CONTROL MEASURES
The ambient noise level monitoring is carried out in and around the proposed mine shows
that ambient noise levels are well within the stipulated limits of CPCB.
Noise generation may be for an instant, intermittent or for continuous periods, with low
to high decibels. Periodic inspection and checks of the risk prone areas and equipments
have to be conducted.
To control noise pollution during the proposed mining operations following steps will be
practiced.
The noise generated by the machinery will be reduced by proper lubrication of the
machinery and equipment.
The workers employed should be provided with personal hearing protection
equipment, with earmuffs and earplugs combined, as a protection from the high
noise level generated at the plant site.
EMP Report For Colour Granite Mine of 4.000 Ha, located in Gopalpur (V), M.Turkapally (M), Yadadri District, Telangana State
M/s. SOLIDO ROCKS AND MINERALS PVT. LTD.
Global Enviro Labs, Hyderabad 26
The provision of green barrier along the boundary will further reduce the
propagation of noise level generated.
Limiting time exposure of workers to excessive noise.
Speed of trucks entering or leaving the mine is limited to moderate speed of 25
kmph to prevent undue noise from empty tippers.
Safety in Blasting:
Care should be taken to evacuate the mining area completely at the time of low explosive
blasting operations. The blasting team should be equipped with all personal safety and
precautionary measure. The following safety measures will be given attention while
conducting the blasting operations.
A blasting SIREN should be used at the time of blasting for audio signal.
Before blasting and after blasting, red & green flags should be displayed as visual
signals.
Warning notice boards indicating the time of blasting and NOT TO TRESPASS
are displayed prominently.
4.4 WATER POLLUTION CONTROL MEASURES
The action program for minimizing adverse affects on water regime is to prevent wash-
off of mine water and uncontrolled run-off water during monsoon. Proposed measures for
this are as follows:
Building/extending of retention/toe walls at the foot of the dumps
Construction of Garland drains along the slopes to divert the rainwater course
away from the dumping areas.
Covering of dump slopes with grass plantation to stabilize and prevent erosion.
Plantation of trees along the ridges and slopes.
EMP Report For Colour Granite Mine of 4.000 Ha, located in Gopalpur (V), M.Turkapally (M), Yadadri District, Telangana State
M/s. SOLIDO ROCKS AND MINERALS PVT. LTD.
Global Enviro Labs, Hyderabad 27
4.5 LAND ENVIRONMENT
The Dhanbad declaration on Environmental Management in Mining Industry states “It is
imperative that in order to ensure the continued and sustained progress of the mining
industry in India, the environmental dimensions should be integrated into the planning,
design, development, operation and working practices of quarry on scientific and rational
lines, by the Governments and the industry in a mutually reinforcing manner”. The land
related Environmental Management Plan (EMP) has been presented here under two
sections viz., Soil & Water conservation and Afforestation.
Existing Land use pattern with already rehabilitated area and area matured for
reclamation is tabulated below:
During the first five years 14,248 m2 of the quarry lease applied area will be reduced
by18 M. The mining will after the shape of the present ridge with a large quarry pit.
S.No. Pattern of Utilization Area put on use at
start of plan period
(Ha)
Area degrades
during plan period
(Ha)
1 Quarry pit Nil 1,425
2 Dump Nil 0.344
3 Stock yard Nil 0.108
4 Office & site service Nil (0.021) (with road
safety barrier zone)
5 Roads Nil 0.061
6 Green Belt/plantation Nil (0.075) (with 7.5m
buffer zone)
Total Nil 1.938
Storage and Reuse of Top Soil:
Topsoil removed during clearing of the area for granite extraction shall be stacked
separately to check the erosion of the stacked soil. A retaining wall shall be constructed
all around the topsoil stockyard. Planting of grass and local species etc., are proposed on
the surface of this stack to prevent erosion and to increase the soil nitrogen. As per the
analysis of the soil samples they are found to be basic in nature. During afforestation, it is
recommended to plant fast growing species with good canopy cover and dense leaf
density and some ornamental species to give a good aesthetic look. It is recommended to
EMP Report For Colour Granite Mine of 4.000 Ha, located in Gopalpur (V), M.Turkapally (M), Yadadri District, Telangana State
M/s. SOLIDO ROCKS AND MINERALS PVT. LTD.
Global Enviro Labs, Hyderabad 28
sow neem, mahogany plants as soil and climatic conditions are suitable for the growth of
these plants.
Solid Waste Management
Removal of weathered rock and the rock waste is the only solid waste that will be
generated from this mine. Some of the material from the waste may be sorted out and
used for making small blocks to be used by the local unit for making tiles. The market for
tiles is good at the moment and they will offer a better substitute for marble in terms of
price and quality. Some rejected and unsorted material may be used in the civil
engineering projects in the vicinity of the area. The waste material can also be crushed
into smaller sizes and can be used as road metal
The waste generated during the five years may be dumped in the zone separately reserved
for dumping Within the quarry lease area. The dump will be designed in such that it will
have slopes equal to the angle of repose of such material. Garland drains have to be sunk
along around the leading edge of the dump. A retaining wall will be constructed around
the dump to preventing the slanting of boulders Care will be taken to minimize the waste
generation at the source.
About 40996.80 m3/Year of waste will be generated from this mine. The waste generated
will be dumped temporarily in the NW of the quarry lease area between the grids N
1956135 – 1956195 & E 262465 – 262570 covering an area of 3,438 m3 with an average
height of 6M with 450 slope angle with be formed. A retaining wall will be constructed
around the dump for preventing the slanting of boulder.
Stabilization and vegetation of dumps:
Waste dump yards are proposed in the quarry lease area. The dumps will have angle of
repose so that no creeping of material will occur. The dead end will be subjected to
vegetation by growing grass and bushes. Garland canal is proposed to be dug around the
dump and plantation will be taken up in this site.
Land Restoration/Reclamation:
Land restoration or reclamation of the area is very essential in any mining industry.
Proper measures adopted during restoration will control most of the adverse
EMP Report For Colour Granite Mine of 4.000 Ha, located in Gopalpur (V), M.Turkapally (M), Yadadri District, Telangana State
M/s. SOLIDO ROCKS AND MINERALS PVT. LTD.
Global Enviro Labs, Hyderabad 29
environmental impacts of Quarry and also improve the aesthetic beauty of the area. Due
to the Quarry activities in this area the profile of the ground will change due to formation
of pits. At the end of the Quarry operations, the top soil/mineral rejects will be utilized
for back filling wherever suitable and rehabilitated.
Following steps shall be taken for improving and protecting the environment.
a) Quarry lease area
b) Surrounding the Quarry lease area.
c) Surrounding the statutory buildings
d) On the undisturbed virgin lease area.
Surrounding the Mining area: The dust generated during the quarrying operations will
be carried by wind and will be deposited over the trees and on the adjacent area around
the quarry in the buffer zone. To filter this dust, a green belt of 10m width shall be
developed along the quarry lease area i.e., around ultimate pit limit, this green belt will
also act as sound barrier. In between the tree saplings, grass and bushes shall be grown.
Creation of the green belt around the lease areas shall be undertaken on priority basis and
shall be completed concurrent to Quarry over a 10-year period.
Surrounding the statutory buildings: All around the proposed statutory buildings and
along the road sides trees shall be planted in addition to the existing ones which will
protect the workers from the noise and dust. To plant trees around the statutory buildings,
the topsoil that is going to be mined from the area shall be laid to form a strip of 10-15m
width and 0.5m thickness.
On the undisturbed virgin lease area: The undisturbed virgin lease area shall be
utilized for afforestation purposes by developing the area with local varieties. This work
shall be done after the cessation of Quarry operations.
Afforestation Plan: The lessee proposed for afforestation in the north of the quarry lease
area within the 7.5m buffer zone over an extent of 450.00m2 between the grids N 00-S 50
to E 50- 150 in phased manner during the plan period with Neem plants.
EMP Report For Colour Granite Mine of 4.000 Ha, located in Gopalpur (V), M.Turkapally (M), Yadadri District, Telangana State
M/s. SOLIDO ROCKS AND MINERALS PVT. LTD.
Global Enviro Labs, Hyderabad 30
Year Area (M2) No. of Plants
1st 150.00 150
2nd
150.00 150
3rd
150.00 150
4th
150.00 150
5th
150.00 150
TOTAL 750.00 750
Apart from the green belts and aesthetic plantation for eliminating fugitive emissions and
noise control, all other massive plantation efforts shall be decided and executed with the
assistance and co-operation of the local community. Based on the community needs the
afforestation would mainly aim at:
a) Protection & Development of Natural Vegetation
b) Protection of soil erosion
c) Plantations of fuel wood blocks to meet the energy requirements.
4.6 SOCIO ECONOMIC BENEFITS
There is positive impact on socio-economics of people living in the villages. The villages
in buffer zone depend upon agriculture. Mining operations in the subject area has positive
impact by providing direct and indirect job opportunities. There will be indirect
employment opportunities in transportation of ore to destination.
4.7 POST PROJECT MONITORING
The Lessee will monitor the environmental parameters as per APPCB/IBM/CPCB
guidelines
4.8 IMPLEMENTATION OF EMP & MONITORING PROGRAMME
The environment management plan is detailed on the basis of impact assessment. Control
and mitigation measures for the adverse impacts envisaged. As the major environmental
attributes have been confined to the project area alone, implementations of the proposed
control measures and monitoring thereof will be undertaken on the regional basis. The
Lessee will ensure the implementation of the measures within the mine area and carryout
EMP Report For Colour Granite Mine of 4.000 Ha, located in Gopalpur (V), M.Turkapally (M), Yadadri District, Telangana State
M/s. SOLIDO ROCKS AND MINERALS PVT. LTD.
Global Enviro Labs, Hyderabad 31
efficient monitoring. In order to implement the measures suggested for mitigating the
adverse impacts on the environment, it is suggested to monitor the environmental
parameters regularly.
The details of investments to carryout the regular monitoring and pollution control
measures are given below in table – 2.
Table – 2: Cost of Environmental Protection Measures (in Rs.)
Sl.No Description Item Capital Cost
in Rs.
Reccuring
Cost in Rs. Remarks
1 Air pollution
Nose Marks
1,500.00
1,000.00
Replaceable, and cost
can increase with time
Cloth for drillers
5,000.00
3,500.00 Issued thrice in a year
Gunny bags for
covering the surface
of jackhammer holes
10,000.00
8,000.00 As and when needed
Road wetting and
plant water feeding
20,000.00
80,000.00
Water tanker cost @
three tankers per day
for 8 months
Plantation (Greenbelt)
on road side and
buffer zone plus
maintenance
75,000.00
30,000.00 Re-plant the non-
surviving plants
2 Water
pollution
Construction of
garland drains
70,000.00
25,000.00
Once only (For
manual de-silting)
De-silting operations
15,000.00
5,000.00
Yearly and manual
operations
Construction of check
dams
100,000.00
45,000.00
Once in year, cost
incurred is to buy
sand bags and filling
sand
Construction of
retaining wall for
waste dump
80,000.00
30,000.00
Cost of construction
of wall around the dip
side of the dump.
3 Noise
Pollution
Maintenance of
machinery
10,000.00
8,000.00 Included in main cost
PPE’s like Ear muffs
10,000.00
6,000.00 Once in six months
4
Occupational
Health &
Safety
Providing First aid
and fire
kitsextinguishers
8,000.00
5,000.00
Once in year, replace
by conducting
periodical checkup
EMP Report For Colour Granite Mine of 4.000 Ha, located in Gopalpur (V), M.Turkapally (M), Yadadri District, Telangana State
M/s. SOLIDO ROCKS AND MINERALS PVT. LTD.
Global Enviro Labs, Hyderabad 32
Providing Personal
protective equipments
to all employees
(hand gloves, safety
shoe and helmets)
8,000.00
5,000.00
Included in air
pollution and noise
pollution
Training and
awareness programs
on risk factors during
emergencies by the
experts
10,000.00
5,000.00
Once in six months
and create sign boards
about the risk and
safety precautions
regularly
Periodical medical
checkup and supply
of medicines
15,000.00
5,000.00
Once in a year and
supply of medicines
for every three
months
5 Environmental
monitoring
Ambient air quality
studies – Once in six
months – 3 locations
-
25,000.00
MoEF /NABL
recognized
laboratories
Water quality studies
– Once a year – 3
Locations
-
8,000.00
Noise studies – once
in six months – 3
Locations
-
7,000.00
Vibration studies –
Once in year – 1
location
-
10,000.00
6
CSR
Activities
For providing School
uniform, Books and
health camp etc.
100,000.00
60,000.00
TOTAL 537,500.00 371,500.00
The applicant will adhere to all the terms & conditions laid in respect of safe working
keeping in view of the sustainable Environmental Management and will comply with the
provisions of the Environmental Protection Act-1986, The Mines Act-1952 & Mineral
Conservation & Development Rules-1988 and any other Rules notified from time to time.
EMP Report For Colour Granite Mine of 4.000 Ha, located in Gopalpur (V), M.Turkapally (M), Yadadri District, Telangana State
M/s. SOLIDO ROCKS AND MINERALS PVT. LTD.
Global Enviro Labs, Hyderabad 33
CONCLUSIONS, SUGGESTIONS/RECOMMENDATIONS
The Mining method proposed as per the approved Mining Plan from Dept. of Mines &
Geology is small-scale semi mechanical mining activities without deployment of deep
hole drilling and use of Heavy machinery. The actual method of mining Colour Granite is
by slicing. Based on the appraisal of the existing environmental scenario coupled with
the assessment studies carried out, it is concluded that there is no long term
environmental impact due to the Colour Granite quarry at the lease area.
The particulate matter getting airborne from the mining activity gets dispersed in close
proximity itself and settles down early. The noise levels due to the proposed quarry
activity are also not of a higher order that calls for immediate corrective measures. The
ground water analysis indicates that the sources do not get influx of pollutants from the
quarry activity. There is positive socio-economic front in the surrounding region due to
the proposed mining industry. The practice of afforestation scheme is a step in the right
direction towards achieving ecological balance.
Suggestions/Recommendations
Even though there is no perceptible impact from the quarry activity on the environment of
the region, it is imperative that mitigative measures have got to be implemented on full
scale for creating environmental balance and intern maintain the ecology of the region.
The following suggestions/recommendations merit due consideration in this regard.
As no control over wind can be exercised, the frequency of the dust
suppression measures like constant watering of the haul roads shall be
practiced.
Afforestation as envisaged in the mining plan is to be carried out so that it
not only enhances the green canopy but also stop the spread of dust
particles and air borne pollutants.
Surface water conservation measures and groundwater recharge be given
high priority.