Internal Rate of ReturnInternal Rate of ReturnInternal Rate of ReturnInternal Rate of Return
Internal Rate of Return (IRR):
The interest rate i* at which NPW = 0
Note: This is the same as finding the roots of a polynomial equation. If there is more than one sign change in the net annual cash flows over the life of the project, then there is more than one internal rate of return (root)!
We may find the IRR by either the manual method we used for the bond yield, or we may use the computer to find the roots by either plots or numerical methods
2
IRR ExampleIRR ExampleIRR ExampleIRR ExampleProject A costs $10,000 and will last
for 10 years. Annual, end of year revenues will be $3000, and expenses will be $1000. There is no salvage value.
Project B costs $20,000 and will also last for 10 years. Annual revenues will be $4000 with annual expenses of $1500. Salvage value is $14,500.
What is each project’s IRR?
3Numerical Method Example: IENG 302 IRR.xls
Table Example
i* (P/A, i*, 10) (P/F, i*, 10)
6% 7.3601 .5584
8% 6.7101 .4632
10% 6.1446 .3855
12% 5.6502 .3220
18% 4.4941 .1911
4
-10000
-5000
0
5000
10000
15000
20000
25000
0 5 10 15 20
Interest Rate (%)
Ne
t P
res
en
t W
ort
h (
$)
Project A
Project B
5
Decisions with IRRDecisions with IRRDecisions with IRRDecisions with IRR
When applied to project selection among independent projects – i.e. there are enough funds such that any or all of the projects may be selected – then investing based on IRR is easy:
Select all projects with IRR > MARR!
Note: Make sure that there is only one IRR (root)!
6
Decisions with IRRDecisions with IRRDecisions with IRRDecisions with IRR
When applied to project selection among mutually exclusive projects – i.e. there is not enough money to do them all – IRR can produce the same result as NPW and EAW.
However, incremental analysis MUST be used!
REASON: IRR is a relative measure of project merit
7
Why Must Incremental Why Must Incremental Analysis be Used for Analysis be Used for Competing Projects?Competing Projects?
Why Must Incremental Why Must Incremental Analysis be Used for Analysis be Used for Competing Projects?Competing Projects?
Assume that an MARR of 16% per year is required, and $85 000 is available to invest:
•Project A requires $50 000 upfront to obtain an IRR of 35% per year.
•Project B requires an $85 000 first cost and returns an IRR of 29% per year.
•What could we do with the un-invested money from Project A? ($35 000)
8
Why Must Incremental Why Must Incremental Analysis be Used for Analysis be Used for Competing Projects?Competing Projects?
Why Must Incremental Why Must Incremental Analysis be Used for Analysis be Used for Competing Projects?Competing Projects?
It would be reasonable to invest the remaining $35 000 at the MARR:
•Overall IRRA = 50 000(.35) + 35 000(.16)
85 000 = 27.2% per year
•Project B returns an IRR of 29% per year on ALL the money available to invest.
9
Incremental AnalysisIncremental AnalysisIncremental AnalysisIncremental Analysis
A technique or approach that can be used with NPW, EAW, and later with IRR and Cost/Benefit to determine if an incremental expenditure should be made.
Note: If using NPW or IRR, lifetimes must be equal – so use Least Common Multiple or Study Period!
10
Incremental AnalysisIncremental AnalysisIncremental AnalysisIncremental AnalysisIncremental Analysis can used by
putting the options in the order of increasing initial investment.
Check the feasibility of the first investment.
• If it is feasible, then you consider
the increment to the next level of investment.
• If it is not feasible, then you check the second investment alternative for feasibility, and so on until all options are considered.
11
Incremental AnalysisIncremental AnalysisIncremental AnalysisIncremental Analysis
Incremental Analysis can also be used when you’re
already incurring an expense
(e.g., DSL internet service)
and you are trying to determine if it is a good
decision to spend additional funds
(e.g., satellite or cable?).
12
Steps of the ProcessSteps of the ProcessSteps of the ProcessSteps of the Process1. Order alternatives from lowest to
highest initial investment.
2. Let Alternative A0 (do nothing) be considered the current best.
3. Consider next Alternative ( j = j+ 1)
4. Determine cash flows for “current best” and Alternative j.
5. Determine incremental cash flows between “current best” and Alternative j.
6. Calculate PW, AW, FW, IRR (or Benefit/Cost) of only the incremental cash flows.
13
Steps of the ProcessSteps of the ProcessSteps of the ProcessSteps of the Process7. If incremental investment yields
NPW, EAW, or a NFW > 0*, then the new “current best” becomes Alternative j.
* (B/C ratio > 1, or IRR > MARR)
8. If there are remaining alternatives, go to Step 3.
9. If all alternatives have been considered, select the “current best” alternative as the preferred alternative.
14
i = 18% Net Cash Flows for Alternatives A0 - A3
End of Year, t
A 0 A 1 A 2 A 3
0 $0 $0 -$50,000 -$75,000
1 0 4,500 20,000 20,000
2 0 4,500 20,000 25,000
3 0 4,500 20,000 30,000
4 0 4,500 20,000 35,000
5 0 4,500 20,000 40,000
15
IRR Incremental IRR Incremental AnalysisAnalysis
IRR Incremental IRR Incremental AnalysisAnalysisRank projects from lowest to highest
initial cost
Eliminate any projects with IRR < MARR
Starting from the least expensive project to the next most expensive, justify each incremental investment
• IRR HC-LC < MARR Accept LC Project & Reject HC
Project
• IRR HC-LC = MARR Indifferent
• IRR HC-LC > MARR Reject LC Project & Accept HC
Project