1 Info 1409 Systems Analysis & Design Module Lecture 5 - Feasibility HND Year 1 2008/9 De Montfort...

27
1 Info 1409 Systems Analysis & Design Module Lecture 5 - Feasibility HND Year 1 2008/9 De Montfort University
  • date post

    21-Dec-2015
  • Category

    Documents

  • view

    215
  • download

    0

Transcript of 1 Info 1409 Systems Analysis & Design Module Lecture 5 - Feasibility HND Year 1 2008/9 De Montfort...

Page 1: 1 Info 1409 Systems Analysis & Design Module Lecture 5 - Feasibility HND Year 1 2008/9 De Montfort University.

1

Info 1409 Systems Analysis & Design Module

Lecture 5 - Feasibility

HND Year 12008/9

De Montfort University

Page 2: 1 Info 1409 Systems Analysis & Design Module Lecture 5 - Feasibility HND Year 1 2008/9 De Montfort University.

2

Objectives

The objectives of this lecture are to build on our previous lecture (4) which explained the following 4 topics:

Analyzing the Business Case Systems Requests Users and their requirements

Page 3: 1 Info 1409 Systems Analysis & Design Module Lecture 5 - Feasibility HND Year 1 2008/9 De Montfort University.

3

Preliminary Investigation

This lecture is concerned with the

The Preliminary investigation stage of the S.D.L.C.

This investigation stage follows the system request

It includes a Feasibility study.

Page 4: 1 Info 1409 Systems Analysis & Design Module Lecture 5 - Feasibility HND Year 1 2008/9 De Montfort University.

4

Lecture objectives

By the end of this lecture you will:

Have learned about the types of feasibility that need to be considered

Have examined some of the techniques used in project management

Been introduced to the preliminary investigation model.

Page 5: 1 Info 1409 Systems Analysis & Design Module Lecture 5 - Feasibility HND Year 1 2008/9 De Montfort University.

5

Project Planning The Preliminary investigation is

conducted by the Systems Analyst who follows a series of steps.

Sometimes project management tools are used (e.g. Microsoft Project software)

Page 6: 1 Info 1409 Systems Analysis & Design Module Lecture 5 - Feasibility HND Year 1 2008/9 De Montfort University.

6

                                                                                                                               

Microsoft Project enables a project manager to define project tasks, list activities and participants, plan the sequence of work, estimate project milestone dates, and track all costs.

Fig 2.11 Shelley et al

Page 7: 1 Info 1409 Systems Analysis & Design Module Lecture 5 - Feasibility HND Year 1 2008/9 De Montfort University.

7

Project software

Specialist software also provides a way of documenting the request formally

The following slide shows an example of an on-line request form.

Managers and analysts can then examine this to determine just what is required.

Page 8: 1 Info 1409 Systems Analysis & Design Module Lecture 5 - Feasibility HND Year 1 2008/9 De Montfort University.

8

Example of an on-line request form

Page 9: 1 Info 1409 Systems Analysis & Design Module Lecture 5 - Feasibility HND Year 1 2008/9 De Montfort University.

9

Risk Management

Every IT project involves risks.

A risk is an event which could affect the project negatively

Risk management is the process of identifying, controlling and evaluating risks.

Risk management also involves information handling.

Page 10: 1 Info 1409 Systems Analysis & Design Module Lecture 5 - Feasibility HND Year 1 2008/9 De Montfort University.

10

Evaluation of request

In order to evaluate the system request

Often a group of key managers and users form a systems revue committee

The objective is to use their combined judgment and experience to evaluate the project.

Page 11: 1 Info 1409 Systems Analysis & Design Module Lecture 5 - Feasibility HND Year 1 2008/9 De Montfort University.

11

Feasibility Studies

A system request must pass a series of tests

The results of these tests form the ‘Feasibility study’

The feasibility study will help to decide whether to proceed or not.

Page 12: 1 Info 1409 Systems Analysis & Design Module Lecture 5 - Feasibility HND Year 1 2008/9 De Montfort University.

12

The need for Feasibility studies

Figure 2.13 on the following slide shows that a feasibility study uses 4 main yardsticks to measure a proposal.

(figure 2.12 taken from text book Shelley et al) & student learning tool.

Page 13: 1 Info 1409 Systems Analysis & Design Module Lecture 5 - Feasibility HND Year 1 2008/9 De Montfort University.

13

We will examine each of these in turn in the following slides

Page 14: 1 Info 1409 Systems Analysis & Design Module Lecture 5 - Feasibility HND Year 1 2008/9 De Montfort University.

14

Operational Feasibility

Operational feasibility means that the proposed system will be used effectively after it has been developed.

Questions:Will users have difficulty with the new

system?Will it provide the expected benefits?

Page 15: 1 Info 1409 Systems Analysis & Design Module Lecture 5 - Feasibility HND Year 1 2008/9 De Montfort University.

15

Technical Feasibility

Technical Feasibility refers to the technical resources needed to develop, purchase, install or operate the system.

Questions:

Does the company have the necessary hardware, software and network resources?

Does the company have the needed technical expertise?

Page 16: 1 Info 1409 Systems Analysis & Design Module Lecture 5 - Feasibility HND Year 1 2008/9 De Montfort University.

16

Economic Feasibility

Economic feasibility means that the projected benefits will outweigh the estimated costs of the project.

Questions:What are the tangible benefits?What is the cost of developing/not

developing the system?What are the intangible benefits?

Page 17: 1 Info 1409 Systems Analysis & Design Module Lecture 5 - Feasibility HND Year 1 2008/9 De Montfort University.

17

Schedule Feasibility

Schedule feasibility means that the project can be implemented in an acceptable time.

Questions:Has management established a firm

timetable for the project?Will an accelerated schedule pose any

risks?Might these risks be acceptable?

Page 18: 1 Info 1409 Systems Analysis & Design Module Lecture 5 - Feasibility HND Year 1 2008/9 De Montfort University.

18

Setting Priorities

The work of the systems revue committee includes the following:

Rejecting system requests that are not feasible.

Giving highest priority to projects that provide the greatest benefits.

Setting the priorities.

Page 19: 1 Info 1409 Systems Analysis & Design Module Lecture 5 - Feasibility HND Year 1 2008/9 De Montfort University.

19

Preliminary Investigation Overview

P63 Shelley et al

Page 20: 1 Info 1409 Systems Analysis & Design Module Lecture 5 - Feasibility HND Year 1 2008/9 De Montfort University.

20

Activities time

The first 19 slides describe the process of project management from a system request to the completion of the preliminary investigation.

Working in twos, create a model to show these initial stages. Use rectangles for the stages and list the activities in each.

You only have 5 mins.

Page 21: 1 Info 1409 Systems Analysis & Design Module Lecture 5 - Feasibility HND Year 1 2008/9 De Montfort University.

21

Feedback time:

What stages did you identify?This is your chance to comment or

feedback –Use it!

Page 22: 1 Info 1409 Systems Analysis & Design Module Lecture 5 - Feasibility HND Year 1 2008/9 De Montfort University.

22

Preliminary Investigation planning

Before the Investigation begins the Analyst needs to plan the process.

Planning the investigation involves a number of steps.

Page 23: 1 Info 1409 Systems Analysis & Design Module Lecture 5 - Feasibility HND Year 1 2008/9 De Montfort University.

23P64 Shelley et al

Page 24: 1 Info 1409 Systems Analysis & Design Module Lecture 5 - Feasibility HND Year 1 2008/9 De Montfort University.

24

Completion of stage 1

The investigation is completed when:

The system request has been evaluated Priorities are set A feasibility report has been prepared

and sent to management Management have considered the

available options and made a decision.

Page 25: 1 Info 1409 Systems Analysis & Design Module Lecture 5 - Feasibility HND Year 1 2008/9 De Montfort University.

25

Analysis Activities

The exact procedure for the preliminary investigation depends upon the following:

1. The nature of the request2. the size of the project 3. the degree of urgency

(The activities of the Analyst will be examined in more detail in later Lectures).

Page 26: 1 Info 1409 Systems Analysis & Design Module Lecture 5 - Feasibility HND Year 1 2008/9 De Montfort University.

26

In conclusion

At the end of this lecture you have:

Been introduced to the different types of feasibility

Examined the techniques used in the preliminary investigation stage.

Know what is meant by the preliminary investigation model

Page 27: 1 Info 1409 Systems Analysis & Design Module Lecture 5 - Feasibility HND Year 1 2008/9 De Montfort University.

27

Background reading

(Phase 1)– Chapter 2

Systems Analysis & Design. Shelley Cashman and Rosenblatt

6th/7th EditionThomson Course Technology 2006/7