1 IGCC: Towards zero emissions power plants Francisco García Peña – Engineering R&D Director,...
-
Upload
theodore-daniels -
Category
Documents
-
view
212 -
download
0
Transcript of 1 IGCC: Towards zero emissions power plants Francisco García Peña – Engineering R&D Director,...
1
IGCC: Towards zero emissions power plants
Francisco García Peña – Engineering R&D Director, ELCOGAS, Spain
Conference on Clean Coal and Carbon Capture and Storage Technologies
2nd and 3rd December, 2013 at Trichy (India)
2
Index
1. The ELCOGAS company
2. Puertollano IGCC power plant
3. Future of IGCC technology
4. ELCOGAS R&D investment plan
5. Conclusions
3
Index
1. The ELCOGAS company
2. Puertollano IGCC power plant
3. Future of IGCC technology
4. ELCOGAS R&D investment plan
5. Conclusions
4
ELCOGAS is an Spanish company established in April 1992 to
undertake the planning, construction, management and operation of a 335 MWeISO IGCC
plant located in Puertollano (Spain)
Enel, SpA4,32%
Siemens Project Ventures GmbH
2,53%
Hidrocantábrico Explotación de Centrales SAU
4,32%
Electricité de France
International, S.A.31,48%
Endesa Generación, S.A.
40,99%
Krupp Koppers GmbH0,04%
Iberdrola Generación, S.A.
12,00%
Hidroeléctrica del Cantábrico, S.A.
4,32%
ENCASUR (open cast coal mine)
REPSOL refinery
Puertollano IGCC Plant
The ELCOGAS company
Shareholders
Puertollano
5
Index
1. The ELCOGAS company
2. Puertollano IGCC power plant
3. Future of IGCC technology
4. ELCOGAS R&D investment plan
5. Conclusions
6
Description of the Puertollano IGCC process
G
Flue gas to stack
SteamHeat Recovery Steam
Generator STEAM TURBINE135MWISO
Cooling towerHot combustion gas
Condenser
GAS TURBINE200 MWISO
GGasifier
Slag
Sulfur (recovery of 99.8%)
Quench Gas
O2
Air
Clean
SyngasRaw Gas
Coal - N2
HP Boiler
MP Boiler
Coal PetCoke
Limestone
Fly ash
Claus Gas
HP Steam
MP Steam
Air Separation Unit
N2 O2
Compressed air
Waste N2
TailGas
Waterto treatment
Coalpreparation
FiltrationWater wash
Sulfur removal
Sulfur recovery
G
Flue gas to stack
SteamHeat Recovery Steam
Generator STEAM TURBINE135MWISO
Cooling towerHot combustion gas
Condenser
GAS TURBINE200 MWISO
GGasifier
Slag
Sulfur (recovery of 99.8%)
Quench Gas
O2
Air
Clean
SyngasRaw Gas
Coal - N2
HP Boiler
MP Boiler
Coal PetCoke
Limestone
Fly ash
Claus Gas
HP Steam
MP Steam
Air Separation Unit
N2 O2
Compressed air
Waste N2
TailGas
Waterto treatment
Coalpreparation
FiltrationWater wash
Sulfur removal
Sulfur recovery
Combined cycle
Gasification
ASU
General view of the Puertollano IGCC plant
Fuel preparation
Gasifier
Clean-up of gas
Combined cycleLaboratory and
water treatment
CO2 capture
Air separation unit
7
8
Description of the Puertollano IGCC process
Fuel design values
Syngas composition
Fuel design is a mixture 50/50 of coal/coke which now is 45/55. Moreover some tests with biomass were undertaken (meat bone meal, grape seed meal, olive oil waste).
Real average Design Real average Design
CO (%) 59.26 61.25 CO (%) 59.30 60.51
H2 (%) 21.44 22.33 (%) 21.95 22.08
CO2 (%) 2.84 3.70 2.41 3.87
N2 (%) 13.32 10.50 14.76 12.5
Ar (%) 0.90 1.02 Ar (%) 1.18 1.03
H2S (%) 0.81 1.01 H2S (ppmv) 3 6
COS (%) 0.19 0.17 COS (ppmv) 9 6
HCN (ppmv) 23 38 HCN (ppmv) - 3
RAW GAS CLEAN GAS
H2
N2 (%)
CO2 (%)
COAL PET COKE FUEL MIX(50:50)
Moisture (%w) 11.8 7.00 9.40Ash (%w) 41.10 0.26 20.68C (%w) 36.27 82.21 59.21H (%w) 2.48 3.11 2.80N (%w) 0.81 1.90 1.36O (%w) 6.62 0.02 3.32S (%w) 0.93 5.50 3.21LHV (MJ/kg) 13.10 31.99 22.55
With those fuels at 50:50, the whole plant demonstrated a gross efficiency of 47.2%
and a net efficiency of 42%, under acceptance tests in 2000 year
9
1st 5 years: Learning curve2003: Major overhaul Gas Turbine findings2004 & 2005: Gas turbine main generation transformer isolation fault2006: Gas turbine major overhaul & candle fly ash filters crisis2007 & 2008: ASU WN2 compressor coupling fault and repair MAN TURBO
2010: No operation due to non-profitable electricity price (30-40 days).2011: 100,000 EOH Major Overhaul 2012: 1,498 hours in stand-by due to regulatory restrictions. (3,969 in 2013)
IGCC, NGCC and Total yearly production
9
335
911
1.3
91
1.5
95
1.3
71
1.2
93
1.1
29
1.1
50
1.1
30
1.1
62
1.5
27
1.4
35
1.3
58
1.1
66
74
3
83
6
62
2
32
1
34
3
30
1
45
2
42
1
31
2
25
9
32
7
27
7
26
3
26
5
25
1
0
500
1.000
1.500
2.000
2.500
1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012
year
GW
h
NGCC GWh
IGCC GWh
752
1,171
1,533
1,712
1,938
1,6721,744
1,5501,462
1,3891,489
1,8031,698
1,623
1,417
Operational data: Annual energy production
10ELCOGAS power plant emissions in NGCC & IGCC modes
Natural gas (NGCC)
Coal gas (IGCC)
Natural gas (mg/Nm3 at 6% O2 dry)
250
4
292
294
294
250
13NINI
125
0,46,7
155,3
0
50
100
150
200
250
300
350
SO2 NOx Particles
EEC 88/609EU Directive 2001/80/EECELCOGAS Environmental PermitEU Directive 2010/75/EU DEIELCOGAS 2012 average
Coal gas (mg/Nm3 at 6% O2 dry)
20
650
400
50
200
500
200
5
300
200
111
200,40
100
200
300
400
500
600
700
SO2 NOx Particles
EU Directive 88/609/EECEU Directive 2001/80/EECELCOGAS Environmental PermitEU Directive 2010/75/EECELCOGAS 2012 average
Operational data: Emissions 2012
11
Note: Net energy variable costs (average 2012)
Fuel mode FuelConsume (GJPCS)
Production (GWh)
Heat rate (GJPCS/ GWh)
Fuel cost (€/ GJPCS)
Partial cost (€/ MWh)
Total cost (€/ MWh)
GT Natural gas 59.987 2,891 20.748 10,46 216,98 216,98
NGCC Natural gas 249.495 22,154 11.262 10,46 117,77 117,77NGCC + ASU Natural gas 1.854.675 155,148 11.954 10,46 125,01 125,01
Natural gas 351.147 10.522 10,46 110,03
Coal 67.459 2.021 3,49 7,05
Petocke 195.947 5.871 1,98 11,61
NG auxiliar consumption
257.700 260 10,46 2,71
Coal 2.536.891 2.555 3,49 8,91
Petocke 7.368.734 7.422 1,98 14,67
NGCC+ASU+Gasifier
(by flare)33,373 128,69
IGCC 992,811 26,30
Operational data: Variable costs 2012
12
Index
1. The ELCOGAS company
2. Puertollano IGCC power plant
3. Future of IGCC technology
4. ELCOGAS R&D investment plan
5. Conclusions
• Multi-fuel (coal, biomass, wastes) • Multi-product (H2, electricity, liquid fuels, chemicals)• CO2 capture and storage
Potential demonstrating of new process with synthesis
gas partial flow.
Future of IGCC technology
GASIFICATIONGAS
CLEAN UP
COMBINED
CYCLE
XtLAlternative Fuel &
Chemicals
COAL + BIOMASS + WASTES
CO2
H2 CO + H2O CO2 + H2
H2/CO2 SEPARATION
GASIFICATIONCO2 CAPTURE &
H2PURIFICATION
PROCESS
SECONDARY
PRODUCTION H2:
WATER-GAS REACTIONPREPARATION
CO2
H2
Step 1: Syngas production from Gasification
Fly ash
Char
Cl-
CN-
SH2
COS
CO2
N2 …
Step 3: “Shifting” or water-gas reaction
Step 4: H2 and CO2 separation H2 CO2&
CO + H2O CO2 + H2
Carbon compound + O2 + H2O CO + H2 + Impurities400-1600ºC10-40 bar
Step 2:Conditioning fly ash removal, particles and sulphur comp.
H2 production from fossil fuels involves CO2 generation To talk about “clean” H2 it is required to consider CCS
H2 Production by coal gasificationFuture of IGCC technology
15
Index
1. The ELCOGAS company
2. Puertollano IGCC power plant
3. Future of IGCC technology
4. ELCOGAS R&D investment plan
5. Conclusions
In 2007 a R&D investment plan was elaborated and results are yearly reported to
Spanish authorities for evaluation. Its 6 master research lines are:
ELCOGAS R&D investment plan
PUERTOLLANO IGCC ACTIVITIES: Based on the opportunity that an IGCC plant represents
Can be relevant in:
• climate change mitigation
• energy supply reliability
CO2 emission reduction in utilization of fossil fuels
H2 production by
gasification of fossil fuels
Diversification of raw fuels
and products
Other environment improvements
IGCC process
optimization
Dissemination of
results
• Forum participations. CO2, H2, and sustainability associations and Technological Platforms. European and Spanish. Coordinating working groups in Technological Spanish Platforms.
• Participation in conferences, seminars, congresses.
• Consulting services. Germany, China, Chile
• Attending and promoting technical visits. Generally international visits.
ELCOGAS R&D investment plan Dissemination of results
Oriented to improve availability & costs
Gasifier materials/Syngas corrosion processes
Ceramic filters
Elimination of membrane water leakages at reaction
chamber
Test materials
ELCOGAS R&D investment plan Optimization of IGCC process
Overview of the test rig for mercury and carbonyls analysis
ELCOGAS R&D investment plan Other environmental improvements
• Liquid wastes reduction (Zero Liquid Discharges). Installation of a new liquid waste treatment plant (evaporation – crystallization).
•Improvements in the dry dedusting system.
•Improvements in Sulphur Recovery plant.
In progress several modifications to improve availability and to reduce S emissions.
•Optimization of additives parameters.
Internal research for improve the quality of subproducts
•Emissions reduction during start up and other transitory situations.
Overview of the new ZLD plant
•Project FECUNDUS (RFCS-CT-2010-00009, 2010-2013) Selection of biomass and undertake real co-gasification test (2 and 4 % in weight of biomass) for asset its influence in CO2 capture process.
•Project PIIBE (ESP-CENIT).
To impulse biofuels technologies in Spain. ELCOGAS has coordinated the subproject about biodiesel from gasification by real co-gasification 10% of biomass and syngas characterization (F-T process in laboratory).
•Meat and Bone Meal (MBM) co-gasification test (2001)
•Possibility to install a pilot plant in IGCC of Puertollano to develop process to obtain gasoline / diesel from syngas
•Availability to undertake tests of gasification of different fuels at large scale to help in design of new IGCC plants Biomass yard
ELCOGAS R&D investment plan Diversification of raw fuels and products
Pre-selected biomasses
LOAD DURING 8% ORUJILLO CO-GASIFICATION TEST
0
10
20
30
40
50
60
70
80
90
100
14/0
6/20
09 7
:12
14/0
6/20
09 1
2:00
14/0
6/20
09 1
6:48
14/0
6/20
09 2
1:36
15/0
6/20
09 2
:24
15/0
6/20
09 7
:12
15/0
6/20
09 1
2:00
15/0
6/20
09 1
6:48
15/0
6/20
09 2
1:36
16/0
6/20
09 2
:24
16/0
6/20
09 7
:12
16/0
6/20
09 1
2:00
16/0
6/20
09 1
6:48
16/0
6/20
09 2
1:36
17/0
6/20
09 2
:24
17/0
6/20
09 7
:12
17/0
6/20
09 1
2:00
17/0
6/20
09 1
6:48
17/0
6/20
09 2
1:36
18/0
6/20
09 2
:24
18/0
6/20
09 7
:12
18/0
6/20
09 1
2:00
18/0
6/20
09 1
6:48
18/0
6/20
09 2
1:36
19/0
6/20
09 2
:24
19/0
6/20
09 7
:12
19/0
6/20
09 1
2:00
19/0
6/20
09 1
6:48
19/0
6/20
09 2
1:36
20/0
6/20
09 2
:24
20/0
6/20
09 7
:12
20/0
6/20
09 1
2:00
20/0
6/20
09 1
6:48
%
0
20.000
40.000
60.000
80.000
100.000
120.000
140.000
160.000
180.000
200.000
Nm
3/hCO clean gas (%)
H2 clean gas (%)
% Orujillo
clean gas flow (%)
gasifer load (%)
Battery of Biomass co-gasification tests
Test Month/Year
Biomass type
Biomass dosage
ratio (%wt)Biomass
(t)
Test Duration
(h)
2001
Meat Bone &
Meal 1%-4,5% 93.3 15
2007- 2009
Oil olive waste
(Orujillo)
1 -2 % 1,572.8 800.3
2008 4% 652.1 154
Mar. 2009 6% 395.8 64.4
Jun. 2009 8% 383.9 46
Sept. 2009 10% 656.6 62
Nov - Dec 2011 Oil olive waste
(Orujillo)
2% 218.1 106
Oct - Nov 2012 4% 409.3 153.5
Oct. 2012 Grape Seed Meal
2% 179.3 127
Nov - Dec 2012 4% 425.7 119.5
TOTAL 4,986.9 1,647.7
Critical parameter for biomass selection was the behavior on the ELCOGAS grinding system
Load during 8% olive oil waste co-gasification test
Biomass selection criteria:
Size < 25 mmHumidity < 12 %Price < 150 €/tAvailability in large quantities
ELCOGAS R&D investment plan Diversification of raw fuels and products
Clean H2 production by gasification of fuels
Collaboration in several projects (HYDROSEP (UE-RFCS) and SPHERA (ESP-CENIT)
H2 production optimization using the CO2-H2 Pilot Plant
Possibility to collaborate with The National Center for Hydrogen “CNH2” (SPAIN)
CO2 Emission reduction
IGCC Efficiency Optimization• Analysis of viability to improve efficiency based on Critical Assessment of
Puertollano IGCC design.
• Auxiliary consumption optimization. New revision
• Development of tools to improve efficiency. Supervision on line of main (120) equipment efficiency. Installed and in tests
• Integration optimization. Improvement of controls to adjust heat & mass balances in real operation
And
CO2 capture for CCS with IGCC
ELCOGAS R&D investment plan H2 production and CO2 emission reduction
23
To demonstrate the feasibility of capture of CO2 and production of H2 in an IGCC that uses solid fossil fuels and wastes as main feedstock.
To obtain economic data enough to scale it to the full Puertollano IGCC capacity in synthetic gas production.
TARGETS
Project of pilot plant in an existing IGCC of Puertollano (pre-combustion technology) is part of a Spanish national initiative, “Advanced technologies of CO2 conversion, capture and storage” and it is coordinated with other related projects:
Project # 2 is to explore oxyfuel combustion to be applied in the construction of a pilot plant (20-30 MW) to be built in El Bierzo, NW of Spain. CIUDEN
Project # 3 is to study and regulate geological storage in Spain. IGME
Project # 4 is to study public awareness of CCS technologies. CIEMAT
PARTICIPANTS & BUDGET
ELCOGAS – UCLM – Ciemat – INCAR CSIC 14.5 M€ (initially 18.5 M€)
COORDINATED
PSE-CO2 project
ELCOGAS R&D investment plan – Line CO2
Puertollano IGCC power plant and pilot plant location
PRENFLO Gasifier
Coal preparation
Sulphur Recovery
Combined Cycle
New CO2 capture pilot
plant
ASU
ELCOGAS R&D investment plan – Line CO2
25
COMBINEDCYCLE
COAL + COKE
GASIFICATION
Raw gas FILTRATION
SYSTEM
Syngas
PURIFICATION &
DESULPHURATION
Tail gas1.3 bar
IP STEAM
SHIFTING REACTORS
CO2
CO2 & H2
separation(Chemical, aMDEA)
100 t/d
CO + H2O → CO2 + H2
Raw H2 (80% of purity)
40%
H2 rich gas
37.5 % CO2
50.0 % H2 3.0 % CO
HYDROGENPURIFICATION
(PSA)
Recycle compressor
Pure H2 (2 t/d)
99.99% H2 @ 15 bar
SWEET /SOUR
+H2S (1.44%)
2% 2%
SWEET SOUR
Flow
(Nm3/h)3,610 4,006
P (bar)
19.8 23.6
T (ºC) 126 138
% CO2 60.45 53.72
% H2 21.95 19.57
% H2O 0.29 10.40
% H2S 0 0.70
% COS 0 0.11
CO2 capture & H2 production
Pilot plant
Installation unique in the worldInstallation unique in the world: 14 MWt pre-
combustion technology integrated in an existing IGCC.
3 step process: shifting unit, CO2/H2 separation
by chemical absorption, and H2 purification by
PSA. All technology used is commercialtechnology used is commercial.
100 t/d of CO100 t/d of CO22 are captured and 2 t/d of pure 2 t/d of pure
HH22 are produced
In service since October 2010. Operation is Operation is intermittent,intermittent, linked to official Research projects, collaborations and internal research campaigns.
1,017 hours of operation accumulated.
Cost of construction (equipment & services): 13.5 Million €
No storage is foreseen
Consejería de Educación, Ciencia y Cultura
CO2 stripper
CO2 absorber
PSA adsorbers
WGS reactors
Control room
26
CO2 capture & H2 production
Pilot plant
1) The carbon capture pilot Project has been a success: first of its kind in the
world, >90% capture rate achieved and CO2 capture cost can be <30 €/t
2) Commercial technology at any scale is available: the singularity comes
from “integration in a existing IGCC plant”
3) Tests carried out show room for improvement in operating conditions and
optimization of energy balance.
4) Carbon capture cost estimations come from figures of a real project.
5) From now on, the pilot is being used for internal research
6) But it is also open for international research projects and for other kinds of
collaboration
CO2 capture & H2 production Conclusions
28
With SWEET catalyst
With SOUR catalyst
CO2 capture in IGCC plants
Fuel preparation Gasification
Filtrationand wet scrubbing
Desulphurization and sulphur
recovery
Unit of CO2 capture
Combined cycle
S CO2
Fuelpreparation Gasification
Filtrationand wet
scrubbing
Unit of CO2
captureCombined
cycle
CO2 + H2S
Based on our CO2 capture pilot plant, we have scaled the cost of a CO2 capture unit at scale 1:1 about 350 M€. Approximately, it represents the cost of the desulphurization and sulphur recovery units in an IGCC w/o CO2 capture.
By installing an IGCC with CO2 acid capture to store or use CO2 together with ~1.5% H2S, the investment costs are similar to those w/o CO2 capture. And the only penalty is the
decreasing efficiency: From 42 33% currently
and from 50 44% near future
(1.5%)
CO2 capture & H2 production
Results and learning
29
Index
1. The ELCOGAS company
2. Puertollano IGCC power plant
3. Future of IGCC technology
4. ELCOGAS R&D investment plan
5. Conclusions
Conclusions
IPCC Unless greenhouse gas emissions are cut by 50-80% by 2050 (especially CO2), the impact of global warming can be disastrous.
World energy demand Expect to be doubled by 2050.
We must act fast using a portfolio of solutions
(energy efficiency improvement, renewables
& CCS) to reduce CO2
emissions in the required massive scale
IGCC technology can contribute to this aim because:
Existing IGCC plants are an opportunity to develop cleaner electricity with fossil fuels, so next IGCC generation must learn from them
IGCC is a promising technology with the minimum variable costs and the best environmental performance and it can be adapted to multifuel and polygeneration
Main burden for IGCC technology deployment is high investment requires a long term regulatory frame
30