1 draft NO A WBS J. Cooper NO A Working Group Meeting June 29,2005 Work is the effort of Ron, Dave,...
-
Upload
kathlyn-rogers -
Category
Documents
-
view
216 -
download
0
description
Transcript of 1 draft NO A WBS J. Cooper NO A Working Group Meeting June 29,2005 Work is the effort of Ron, Dave,...
1
draft NOA WBSJ. Cooper
NOA Working Group MeetingJune 29,2005
Work is the effort of Ron, Dave, Bill, Suzanne, Harry, not just me.
2
draft NOA WBS
J. Cooper, Project ManagerR. Ray, Deputy
3
Far Site, 1.1 – 1.7• Starting now with the EAW
process• Major work
• Maybe 2 contractors, maybe 1• RGU complication mostly
applies here• This “outfitting” is tied to the
building• Crucial to proper containment
• Need “Roads & Grounds” during Detector assembly phase
• Safeguards & Security• Under Lab / University
umbrellas except at Far Site• Value at scattered assembly
sites is low, major value is at Far site
• e.g. thinking security fence, video surveillance, gates, ….
$ 7.4 M$ 13.7 M
$ ?
$ ?
$ ~ 3.0 M
~ 19 % of cost + contingency
1.1
1.2
1.3
1.4
1.6
1.7
1.5
$ 6.8 M
4
Strategic Materials, 2.1 – 2.3
• All are large phased procurements• Value management will dictate
competition• e.g. 2 extrusion vendors with 33% each?• Mix vs. buy scintillator?
• All have cost fluctuation problems• $ to Yen• Price of crude oil
• Together they dominate the detector cost + contingency
• therefore the cost risk & contingency• All have a common thread of QA
• Sustained over several years, often done on the same object in several places
• All need to aim for conservative HEP version of “just in time delivery” to the far site
• Delivery from vendors within our cost profile
• Delivery to the sites where the raw materials are needed
• Need to minimize storage
$ 20.0 M
$ 34.8 M
~ 44% of cost + contingency
$ 17.4 M27,000 km
7.5 M gallons,24 kt
374 km, 6 ktStructural, but also light gathering
5
• Near structure identical to Far, so can roll each up
• Except add “fast electronics” task to Near – this is 5 planes only
• Far is now the assembly of 24,000 objects of various kinds
• APDs, TE coolers, ASICs, PC boards• Module factories
– Manifolds and bottom closures• Trigger / DAQ (underestimated?)
– But is a large fraction of the EDIA– Supernova complication?– Slow controls…
• & Final Assembly at Far Site• Block Raiser, Assembly tables• Crew
NOA Detectors3.1 – 3.3
~ 23 % of cost + contingency
$ 3.1 M “no cost”$ 2.8 M
$ 0.4 M
$ 10.1 M
$ 8.1 M
$ 13.5 M
6
Level 4Details in Detector
3.1• One module part is
structural and dear to heart of “Assembly 3.1.5”
• Scintillator Distribution & QA 3.1.5.8 is now the act of filling extrusions, separate from the building distribution task in 1.
7
Details of 3.3 -Simulations
• Why is this in the Project?• Needs structure, leaders• Direct feedback in many
cases to project scope / details
• Could correlate with total mass• May imply design changes• Near Detector details
• E.g. move up slope if LSND confirmed
• Overburden question• Prototype Near, Final Near
• Must carry calibrations to Far• “no cost” since thought to be
all scientist effort• So having this in the project
allows us to track the total scientific effort better
• “DOE liked this for BTeV” ??
8
Project Management 4.
• Project Office - $ 4.7 M• SWF for non-scientists• Travel, computing
• $ 14.1 M of “additional contingency” listed in proposal stashed here
• Expect to farm this out to other WBS elements in resource loaded schedule exercise
• i.e. not for Director’s Review
~ 12 % of cost + contingency
9
draft NOA WBS Comments• Need Near subtasks in Strategic Materials if we
are to roll up a real total for Near• Suzanne notes the Detector roll-up has an
additional level, implies two financial reports….• Add some Level 2 task and make 1,2,4 at Level 2 below that?
10
draft NOA WBS MORE Comments
• Do we want to include the R&D in this “project”?• Want to duplicate structure to track it anyway?• Should start with FY05
• The “$ 165 M” cost does NOT include the R&D– Additional ~ $ 3 M of M&S– Additional ~ $ 3 – 4 M of SWF (crude estimate)– Mike Procario heard these numbers February 28, 2005.– The March 2005 NOA Proposal is consistent with these numbers.
11
draft NOA WBS - Level 1 Managers?
S. Dixon ? R. Ray J. Cooper J. Cooper / S. Pasek / K. Kephart ?
J. Cooper, Project ManagerR. Ray, Deputy
Clearly woulddepend on 3 strong Level 2 managers
12
More structure, not WBS
• PMP usually shows • Project PPD Directorate DOE, line management
• Collaboration with Spokespersons to one side in a separate line– NOA has an Executive Committee
• Project might have a Technical Advisory Committee to the Project Manager
– Composed of Level X managers + a few more?
• So eventually the structure is way more complicated than shown today