Asset Disposal Project
Rebuild Proposal For Mobile Equipment
![Page 2: 1 Asset Disposal Project Rebuild Proposal For Mobile Equipment.](https://reader036.fdocuments.us/reader036/viewer/2022062322/5697bf9d1a28abf838c93a0e/html5/thumbnails/2.jpg)
2
Truck Regeneration
BEFORE …
AFTER……
![Page 3: 1 Asset Disposal Project Rebuild Proposal For Mobile Equipment.](https://reader036.fdocuments.us/reader036/viewer/2022062322/5697bf9d1a28abf838c93a0e/html5/thumbnails/3.jpg)
3
Rebuild Programme
Rebuild Proposal for Mobile Equipment
- Selection of Machines identified for Rebuild Programme
- Proposal from OEMS ie., Sandvik and Atlas Copco
- Rebuild in Ireland prior to shipping
![Page 4: 1 Asset Disposal Project Rebuild Proposal For Mobile Equipment.](https://reader036.fdocuments.us/reader036/viewer/2022062322/5697bf9d1a28abf838c93a0e/html5/thumbnails/4.jpg)
4
Machines identified for Rebuild
OEMMachine Number Machine Model Machine Type Serial Number
Rebuild Cost Vs
New Cost
Machine Value Vs
New Machine
Sandvik 292 Toro 50D Dump Truck T7050362 43% 54%
![Page 5: 1 Asset Disposal Project Rebuild Proposal For Mobile Equipment.](https://reader036.fdocuments.us/reader036/viewer/2022062322/5697bf9d1a28abf838c93a0e/html5/thumbnails/5.jpg)
5
Truck Rebuild Example
Toro 50D Truck
• Typical cost to rebuild is from 45% to 60% of comparable new unit• Timeframe for delivery is also significantly less than typical new
unit delivery timeLeadtime on Rebuild 10/14 Weeks Depending on Rebuild/Repair
SpecLeadtime on New Machines – 27/32 Weeks depending on unit type
• Typical reduction up to 30% of cost per hour to operate and maintain following return to production after completion of rebuild programme.
![Page 6: 1 Asset Disposal Project Rebuild Proposal For Mobile Equipment.](https://reader036.fdocuments.us/reader036/viewer/2022062322/5697bf9d1a28abf838c93a0e/html5/thumbnails/6.jpg)
6
EXAMPLE OF REBUILD
Truck Regeneration - Toro 50D Truck
Frame StructureStrip, Sandblast, Structural Inspection, Repair and Paint
CabinStrip, Sandblast, Re-upholster, Electrical Inspection, Repair and Paint
EngineReconditioned by engine OEM specialist
Powertrain and Driveline ComponentsAll components inspected and reconditioned to OEM specification
HydraulicsAll piping and hosing replaced and all valves repaired/replaced
ElectricsAll electrics built and tested to OEM specification
Quality Control and TestingMachine completed to OEM production unit standard test procedures
![Page 7: 1 Asset Disposal Project Rebuild Proposal For Mobile Equipment.](https://reader036.fdocuments.us/reader036/viewer/2022062322/5697bf9d1a28abf838c93a0e/html5/thumbnails/7.jpg)
7
Key Benefits
KEY BENEFITS• Allows customer to retain proven technology with option to upgrade• Improved machine availability equating to lower cost per tonne• Economical second life repair• Keeps equipment in the field longer
ADDED VALUE (Examples)• Safety Rails• Emission Solutions – DPF Filter• Reverse Cameras• Warranty• Customer specific modifications• Compliance with updated legislative requirements• All OEM safety updates installed
![Page 8: 1 Asset Disposal Project Rebuild Proposal For Mobile Equipment.](https://reader036.fdocuments.us/reader036/viewer/2022062322/5697bf9d1a28abf838c93a0e/html5/thumbnails/8.jpg)
8
Rebuild Programme
Cost Saving to Operations **Rebuilt Machine for 45% - 60% cost of New**
• Detailed Audit Inspection• Disassembly down to bare chassis• Full recondition of major components• Performance Testing• Full Repaint• Weekly inspection by Lisheen Personnel• Specialised Tooling• Fabrication • ISO 9001:2008 Quality Assurance Record• Warranty assured on delivery• Shipping organised with Operation• Commercial agreement direction between buyer and OEM• Weekly Progress Reports and Photographic Progress Log