44 ForecastingForecasting
PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e
PowerPoint slides by Jeff Heyl
![Page 2: 1 4 4 Forecasting PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.](https://reader035.fdocuments.us/reader035/viewer/2022081417/56649cf95503460f949ca5ef/html5/thumbnails/2.jpg)
2
Outline What Is Forecasting?
Forecasting Time Horizons
Forecasting Approaches Overview of Qualitative Methods and Quantitative Methods
Time-Series Forecasting Decomposition of a Time Series Naive Approach
Time-Series Forecasting (cont.) Moving Averages Exponential Smoothing(with trend)
Associative Forecasting Methods: Regression and Correlation
Using Regression Analysis for Forecasting Correlation Coefficients for Regression Lines Multiple-Regression Analysis
![Page 3: 1 4 4 Forecasting PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.](https://reader035.fdocuments.us/reader035/viewer/2022081417/56649cf95503460f949ca5ef/html5/thumbnails/3.jpg)
3
Learning Objectives
When you complete this chapter you should be able to :
1. Understand the three time horizons and which models apply for each use
2. Explain when to use each of the four qualitative models
3. Apply the naive, moving average, and exponential smoothing
4. Compute measures of forecast accuracy
![Page 4: 1 4 4 Forecasting PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.](https://reader035.fdocuments.us/reader035/viewer/2022081417/56649cf95503460f949ca5ef/html5/thumbnails/4.jpg)
4
Forecasting at Disney World
Revenues are derived from people Forecast used to adjust opening times, rides,
shows, staffing levels, and guests admitted Model includes gross domestic product, cross-
exchange rates, arrivals into the USA Survey 1 million park guests, employees, and
travel professionals each year Inputs are airline specials, Federal Reserve
policies, Wall Street trends, vacation/holiday schedules for 3,000 school districts around the world
![Page 5: 1 4 4 Forecasting PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.](https://reader035.fdocuments.us/reader035/viewer/2022081417/56649cf95503460f949ca5ef/html5/thumbnails/5.jpg)
5
Why Forecast?
What are we trying to Forecast?A very well known attribute of a forecast is that
they are always wrong.For example, Snackwell Cookies (1993), But . . .
L. L. BeanTaco BellAMR
Characteristics of ForecastsA forecast is more than a single numberAggregate forecasts are betterThe further in the future, the more inaccuracyForecasts only predict from past events
![Page 6: 1 4 4 Forecasting PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.](https://reader035.fdocuments.us/reader035/viewer/2022081417/56649cf95503460f949ca5ef/html5/thumbnails/6.jpg)
6
Short-range forecast Up to 1 year, generally less than 3 months Purchasing, job scheduling, workforce
levels, job assignments, production levels
Medium-range forecast 3 months to 3 years Sales and production planning, budgeting
Long-range forecast 3+ years New product planning, facility location,
research and development
Forecasting Time Horizons
![Page 7: 1 4 4 Forecasting PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.](https://reader035.fdocuments.us/reader035/viewer/2022081417/56649cf95503460f949ca5ef/html5/thumbnails/7.jpg)
7
Forecasting Approaches
Qualitative Methods Used when situation is vague and little data exist Involves intuition, experience
Quantitative Methods Used when situation is ‘stable’ - historical data exist Involves mathematical techniques
![Page 8: 1 4 4 Forecasting PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.](https://reader035.fdocuments.us/reader035/viewer/2022081417/56649cf95503460f949ca5ef/html5/thumbnails/8.jpg)
8
Overview of Qualitative Methods
1. Jury of executive opinion Pool opinions of high-level experts
2. Delphi method
3. Sales force composite Aggregated estimates from salespersons
4. Consumer Market Survey
![Page 9: 1 4 4 Forecasting PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.](https://reader035.fdocuments.us/reader035/viewer/2022081417/56649cf95503460f949ca5ef/html5/thumbnails/9.jpg)
9
Delphi Method Iterative group
process, continues until consensus is reached
3 types of participants Decision makers Staff Respondents
Staff(Administering
survey)
Decision Makers(Evaluate
responses and make decisions)
Respondents(People who can make valuable
judgments)
![Page 10: 1 4 4 Forecasting PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.](https://reader035.fdocuments.us/reader035/viewer/2022081417/56649cf95503460f949ca5ef/html5/thumbnails/10.jpg)
10
Overview of Quantitative Approaches
1. Naive approach
2. Moving averages
3. Exponential smoothing
4. Trend projection
5. Linear regression
time-series models
associative model
![Page 11: 1 4 4 Forecasting PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.](https://reader035.fdocuments.us/reader035/viewer/2022081417/56649cf95503460f949ca5ef/html5/thumbnails/11.jpg)
11
Set of evenly spaced numerical data
Forecast based only on past values, no other variables important
Components of a Time Series: Trend Seasonal Cyclical Random
Time Series Forecasting
![Page 12: 1 4 4 Forecasting PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.](https://reader035.fdocuments.us/reader035/viewer/2022081417/56649cf95503460f949ca5ef/html5/thumbnails/12.jpg)
12
Components of DemandD
eman
d f
or
pro
du
ct o
r se
rvic
e
| | | |1 2 3 4
Time (years)
Average demand over 4 years
Trend component
Actual demand line
Random variation
Figure 4.1
Seasonal peaks
![Page 13: 1 4 4 Forecasting PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.](https://reader035.fdocuments.us/reader035/viewer/2022081417/56649cf95503460f949ca5ef/html5/thumbnails/13.jpg)
13
Naive Approach
Assumes demand in next period is the same as demand in most recent period e.g., If January sales were 68, then
February sales will be 68
Sometimes cost effective and efficient
Can be good starting point
![Page 14: 1 4 4 Forecasting PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.](https://reader035.fdocuments.us/reader035/viewer/2022081417/56649cf95503460f949ca5ef/html5/thumbnails/14.jpg)
14
MA is a series of arithmetic means Used if little or no trend
Used often for smoothing Provides overall impression of data
over time
Moving Average Method
Moving average =∑ demand in previous n periods
n
![Page 15: 1 4 4 Forecasting PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.](https://reader035.fdocuments.us/reader035/viewer/2022081417/56649cf95503460f949ca5ef/html5/thumbnails/15.jpg)
15
January 10February 12March 13April 16May 19June 23July 26
Actual 3-MonthMonth Shed Sales Moving Average
(12 + 13 + 16)/3 = 13 2/3
(13 + 16 + 19)/3 = 16(16 + 19 + 23)/3 = 19 1/3
Moving Average Example
101213
(10 + 12 + 13)/3 = 11 2/3
![Page 16: 1 4 4 Forecasting PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.](https://reader035.fdocuments.us/reader035/viewer/2022081417/56649cf95503460f949ca5ef/html5/thumbnails/16.jpg)
16
Graph of Moving Average
| | | | | | | | | | | |
J F M A M J J A S O N D
Sh
ed S
ales
30 –28 –26 –24 –22 –20 –18 –16 –14 –12 –10 –
Actual Sales
Moving Average Forecast
![Page 17: 1 4 4 Forecasting PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.](https://reader035.fdocuments.us/reader035/viewer/2022081417/56649cf95503460f949ca5ef/html5/thumbnails/17.jpg)
17
Used when some trend might be present Older data usually less important
Weights based on experience and intuition
Weighted Moving Average
Weightedmoving average =
∑ (weight for period n) x (demand in period n)
∑ weights
![Page 18: 1 4 4 Forecasting PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.](https://reader035.fdocuments.us/reader035/viewer/2022081417/56649cf95503460f949ca5ef/html5/thumbnails/18.jpg)
18
January 10February 12March 13April 16May 19June 23July 26
Actual 3-Month WeightedMonth Shed Sales Moving Average
[(3 x 16) + (2 x 13) + (12)]/6 = 141/3
[(3 x 19) + (2 x 16) + (13)]/6 = 17[(3 x 23) + (2 x 19) + (16)]/6 = 201/2
Weighted Moving Average
101213
[(3 x 13) + (2 x 12) + (10)]/6 = 121/6
Weights Applied Period
3 Last month2 Two months ago1 Three months ago
6 Sum of weights
![Page 19: 1 4 4 Forecasting PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.](https://reader035.fdocuments.us/reader035/viewer/2022081417/56649cf95503460f949ca5ef/html5/thumbnails/19.jpg)
19
Moving Average And Weighted Moving Average
30 –
25 –
20 –
15 –
10 –
5 –
Sa
les
de
man
d
| | | | | | | | | | | |
J F M A M J J A S O N D
Actual sales
Moving average
Weighted moving average
Figure 4.2
![Page 20: 1 4 4 Forecasting PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.](https://reader035.fdocuments.us/reader035/viewer/2022081417/56649cf95503460f949ca5ef/html5/thumbnails/20.jpg)
20
Form of weighted moving average Weights decline exponentially Most recent data weighted most
Requires smoothing constant () Ranges from 0 to 1
Less need for keeping past data
Exponential Smoothing
![Page 21: 1 4 4 Forecasting PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.](https://reader035.fdocuments.us/reader035/viewer/2022081417/56649cf95503460f949ca5ef/html5/thumbnails/21.jpg)
21
Exponential Smoothing
New forecast = Last period’s forecast+ a (Last period’s actual demand
– Last period’s forecast)
Ft = Ft – 1 + a(At – 1 - Ft – 1)
where Ft = new forecast
Ft – 1 = previous forecast
a = smoothing (or weighting) constant (0 ≤ a ≤ 1)
![Page 22: 1 4 4 Forecasting PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.](https://reader035.fdocuments.us/reader035/viewer/2022081417/56649cf95503460f949ca5ef/html5/thumbnails/22.jpg)
22
Exponential Smoothing Example
Predicted demand = 142 Ford MustangsActual demand = 153Smoothing constant a = .20
![Page 23: 1 4 4 Forecasting PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.](https://reader035.fdocuments.us/reader035/viewer/2022081417/56649cf95503460f949ca5ef/html5/thumbnails/23.jpg)
23
Exponential Smoothing Example
Predicted demand = 142 Ford MustangsActual demand = 153Smoothing constant a = .20
New forecast = 142 + .2(153 – 142)
![Page 24: 1 4 4 Forecasting PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.](https://reader035.fdocuments.us/reader035/viewer/2022081417/56649cf95503460f949ca5ef/html5/thumbnails/24.jpg)
24
Exponential Smoothing Example
Predicted demand = 142 Ford MustangsActual demand = 153Smoothing constant a = .20
New forecast = 142 + .2(153 – 142)
= 142 + 2.2
= 144.2 ≈ 144 cars
![Page 25: 1 4 4 Forecasting PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.](https://reader035.fdocuments.us/reader035/viewer/2022081417/56649cf95503460f949ca5ef/html5/thumbnails/25.jpg)
25
Impact of Different
225 –
200 –
175 –
150 –| | | | | | | | |
1 2 3 4 5 6 7 8 9
Quarter
De
ma
nd
a = .1
Actual demand
a = .5
![Page 26: 1 4 4 Forecasting PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.](https://reader035.fdocuments.us/reader035/viewer/2022081417/56649cf95503460f949ca5ef/html5/thumbnails/26.jpg)
26
Impact of Different
225 –
200 –
175 –
150 –| | | | | | | | |
1 2 3 4 5 6 7 8 9
Quarter
De
ma
nd
a = .1
Actual demand
a = .5 Chose high values of when underlying average is likely to change
Choose low values of when underlying average is stable
![Page 27: 1 4 4 Forecasting PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.](https://reader035.fdocuments.us/reader035/viewer/2022081417/56649cf95503460f949ca5ef/html5/thumbnails/27.jpg)
27
Choosing
The objective is to obtain the most accurate forecast no matter the technique
We generally do this by selecting the model that gives us the lowest forecast error
Forecast error = Actual demand - Forecast value
= At - Ft
![Page 28: 1 4 4 Forecasting PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.](https://reader035.fdocuments.us/reader035/viewer/2022081417/56649cf95503460f949ca5ef/html5/thumbnails/28.jpg)
28
Common Measures of Error
• Mean Absolute Deviation (MAD)
• Mean Squared Error (MSE)
• Mean Absolute Percent Error (MAPE)
![Page 29: 1 4 4 Forecasting PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.](https://reader035.fdocuments.us/reader035/viewer/2022081417/56649cf95503460f949ca5ef/html5/thumbnails/29.jpg)
29
Comparison of Forecast Error
Rounded Absolute Rounded AbsoluteActual Forecast Deviation Forecast Deviation
Tonnage with for with forQuarter Unloaded a = .10 a = .10 a = .50 a = .50
1 180 175 5.00 175 5.002 168 175.5 7.50 177.50 9.503 159 174.75 15.75 172.75 13.754 175 173.18 1.82 165.88 9.125 190 173.36 16.64 170.44 19.566 205 175.02 29.98 180.22 24.787 180 178.02 1.98 192.61 12.618 182 178.22 3.78 186.30 4.30
82.45 98.62
![Page 30: 1 4 4 Forecasting PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.](https://reader035.fdocuments.us/reader035/viewer/2022081417/56649cf95503460f949ca5ef/html5/thumbnails/30.jpg)
30
Comparison of Forecast Error
Rounded Absolute Rounded AbsoluteActual Forecast Deviation Forecast Deviation
Tonnage with for with forQuarter Unloaded a = .10 a = .10 a = .50 a = .50
1 180 175 5.00 175 5.002 168 175.5 7.50 177.50 9.503 159 174.75 15.75 172.75 13.754 175 173.18 1.82 165.88 9.125 190 173.36 16.64 170.44 19.566 205 175.02 29.98 180.22 24.787 180 178.02 1.98 192.61 12.618 182 178.22 3.78 186.30 4.30
82.45 98.62
MAD =∑ |deviations|
n
= 82.45/8 = 10.31
For a = .10
= 98.62/8 = 12.33
For a = .50
![Page 31: 1 4 4 Forecasting PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.](https://reader035.fdocuments.us/reader035/viewer/2022081417/56649cf95503460f949ca5ef/html5/thumbnails/31.jpg)
31
Comparison of Forecast Error
Rounded Absolute Rounded AbsoluteActual Forecast Deviation Forecast Deviation
Tonnage with for with forQuarter Unloaded a = .10 a = .10 a = .50 a = .50
1 180 175 5.00 175 5.002 168 175.5 7.50 177.50 9.503 159 174.75 15.75 172.75 13.754 175 173.18 1.82 165.88 9.125 190 173.36 16.64 170.44 19.566 205 175.02 29.98 180.22 24.787 180 178.02 1.98 192.61 12.618 182 178.22 3.78 186.30 4.30
82.45 98.62MAD 10.31 12.33
= 1,526.54/8 = 190.82
For a = .10
= 1,561.91/8 = 195.24
For a = .50
MSE =∑ (forecast errors)2
n
![Page 32: 1 4 4 Forecasting PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.](https://reader035.fdocuments.us/reader035/viewer/2022081417/56649cf95503460f949ca5ef/html5/thumbnails/32.jpg)
32
Comparison of Forecast Error
Rounded Absolute Rounded AbsoluteActual Forecast Deviation Forecast Deviation
Tonnage with for with forQuarter Unloaded a = .10 a = .10 a = .50 a = .50
1 180 175 5.00 175 5.002 168 175.5 7.50 177.50 9.503 159 174.75 15.75 172.75 13.754 175 173.18 1.82 165.88 9.125 190 173.36 16.64 170.44 19.566 205 175.02 29.98 180.22 24.787 180 178.02 1.98 192.61 12.618 182 178.22 3.78 186.30 4.30
82.45 98.62MAD 10.31 12.33MSE 190.82 195.24
= 44.75/8 = 5.59%
For a = .10
= 54.05/8 = 6.76%
For a = .50
MAPE =∑100|deviationi|/actuali
n
n
i = 1
![Page 33: 1 4 4 Forecasting PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.](https://reader035.fdocuments.us/reader035/viewer/2022081417/56649cf95503460f949ca5ef/html5/thumbnails/33.jpg)
33
Comparison of Forecast Error
Rounded Absolute Rounded AbsoluteActual Forecast Deviation Forecast Deviation
Tonnage with for with forQuarter Unloaded a = .10 a = .10 a = .50 a = .50
1 180 175 5.00 175 5.002 168 175.5 7.50 177.50 9.503 159 174.75 15.75 172.75 13.754 175 173.18 1.82 165.88 9.125 190 173.36 16.64 170.44 19.566 205 175.02 29.98 180.22 24.787 180 178.02 1.98 192.61 12.618 182 178.22 3.78 186.30 4.30
82.45 98.62MAD 10.31 12.33MSE 190.82 195.24MAPE 5.59% 6.76%
![Page 34: 1 4 4 Forecasting PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.](https://reader035.fdocuments.us/reader035/viewer/2022081417/56649cf95503460f949ca5ef/html5/thumbnails/34.jpg)
34© 2011 Pearson Education, Inc. publishing as Prentice Hall
Exponential Smoothing with Trend Adjustment
When a trend is present, exponential smoothing must be modified
Forecast including (FITt) = trend
Exponentially Exponentiallysmoothed (Ft) + smoothed (Tt)forecast trend
![Page 35: 1 4 4 Forecasting PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.](https://reader035.fdocuments.us/reader035/viewer/2022081417/56649cf95503460f949ca5ef/html5/thumbnails/35.jpg)
35© 2011 Pearson Education, Inc. publishing as Prentice Hall
Exponential Smoothing with Trend Adjustment
Ft = a(At - 1) + (1 - a)(Ft - 1 + Tt - 1)
Tt = b(Ft - Ft - 1) + (1 - b)Tt - 1
Step 1: Compute Ft
Step 2: Compute Tt
Step 3: Calculate the forecast FITt = Ft + Tt
![Page 36: 1 4 4 Forecasting PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.](https://reader035.fdocuments.us/reader035/viewer/2022081417/56649cf95503460f949ca5ef/html5/thumbnails/36.jpg)
36© 2011 Pearson Education, Inc. publishing as Prentice Hall
Exponential Smoothing with Trend Adjustment Example
ForecastActual Smoothed Smoothed Including
Month(t) Demand (At) Forecast, Ft Trend, Tt Trend, FITt
1 12 11 2 13.002 173 204 195 246 217 318 289 36
10
Table 4.1
![Page 37: 1 4 4 Forecasting PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.](https://reader035.fdocuments.us/reader035/viewer/2022081417/56649cf95503460f949ca5ef/html5/thumbnails/37.jpg)
37© 2011 Pearson Education, Inc. publishing as Prentice Hall
Exponential Smoothing with Trend Adjustment Example
ForecastActual Smoothed Smoothed Including
Month(t) Demand (At) Forecast, Ft Trend, Tt Trend, FITt
1 12 11 2 13.002 173 204 195 246 217 318 289 36
10
Table 4.1
F2 = aA1 + (1 - a)(F1 + T1)
F2 = (.2)(12) + (1 - .2)(11 + 2)
= 2.4 + 10.4 = 12.8 units
Step 1: Forecast for Month 2
![Page 38: 1 4 4 Forecasting PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.](https://reader035.fdocuments.us/reader035/viewer/2022081417/56649cf95503460f949ca5ef/html5/thumbnails/38.jpg)
38© 2011 Pearson Education, Inc. publishing as Prentice Hall
Exponential Smoothing with Trend Adjustment Example
ForecastActual Smoothed Smoothed Including
Month(t) Demand (At) Forecast, Ft Trend, Tt Trend, FITt
1 12 11 2 13.002 17 12.803 204 195 246 217 318 289 36
10
Table 4.1
T2 = b(F2 - F1) + (1 - b)T1
T2 = (.4)(12.8 - 11) + (1 - .4)(2)
= .72 + 1.2 = 1.92 units
Step 2: Trend for Month 2
![Page 39: 1 4 4 Forecasting PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.](https://reader035.fdocuments.us/reader035/viewer/2022081417/56649cf95503460f949ca5ef/html5/thumbnails/39.jpg)
39© 2011 Pearson Education, Inc. publishing as Prentice Hall
Exponential Smoothing with Trend Adjustment Example
ForecastActual Smoothed Smoothed Including
Month(t) Demand (At) Forecast, Ft Trend, Tt Trend, FITt
1 12 11 2 13.002 17 12.80 1.923 204 195 246 217 318 289 36
10
Table 4.1
FIT2 = F2 + T2
FIT2 = 12.8 + 1.92
= 14.72 units
Step 3: Calculate FIT for Month 2
![Page 40: 1 4 4 Forecasting PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.](https://reader035.fdocuments.us/reader035/viewer/2022081417/56649cf95503460f949ca5ef/html5/thumbnails/40.jpg)
40© 2011 Pearson Education, Inc. publishing as Prentice Hall
Exponential Smoothing with Trend Adjustment Example
ForecastActual Smoothed Smoothed Including
Month(t) Demand (At) Forecast, Ft Trend, Tt Trend, FITt
1 12 11 2 13.002 17 12.80 1.92 14.723 204 195 246 217 318 289 36
10
Table 4.1
15.18 2.10 17.2817.82 2.32 20.1419.91 2.23 22.1422.51 2.38 24.8924.11 2.07 26.1827.14 2.45 29.5929.28 2.32 31.6032.48 2.68 35.16
![Page 41: 1 4 4 Forecasting PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.](https://reader035.fdocuments.us/reader035/viewer/2022081417/56649cf95503460f949ca5ef/html5/thumbnails/41.jpg)
41© 2011 Pearson Education, Inc. publishing as Prentice Hall
Exponential Smoothing with Trend Adjustment Example
Figure 4.3
| | | | | | | | |
1 2 3 4 5 6 7 8 9
Time (month)
Pro
du
ct d
eman
d
35 –
30 –
25 –
20 –
15 –
10 –
5 –
0 –
Actual demand (At)
Forecast including trend (FITt)with = .2 and = .4
![Page 42: 1 4 4 Forecasting PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.](https://reader035.fdocuments.us/reader035/viewer/2022081417/56649cf95503460f949ca5ef/html5/thumbnails/42.jpg)
42
Associative Forecasting
Used when changes in one or more independent variables can be used to predict
the changes in the dependent variable
Most common technique is linear regression analysis
We apply this technique just as we did in the time series example
![Page 43: 1 4 4 Forecasting PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.](https://reader035.fdocuments.us/reader035/viewer/2022081417/56649cf95503460f949ca5ef/html5/thumbnails/43.jpg)
43
Associative ForecastingForecasting an outcome based on predictor variables using the least squares technique
y = a + bx^
where y = computed value of the variable to be predicted (dependent variable)a = y-axis interceptb = slope of the regression linex = the independent variable though to predict the value of the dependent variable
^
![Page 44: 1 4 4 Forecasting PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.](https://reader035.fdocuments.us/reader035/viewer/2022081417/56649cf95503460f949ca5ef/html5/thumbnails/44.jpg)
44
Least Squares Method
Time period
Va
lue
s o
f D
ep
end
en
t V
ari
able
Figure 4.4
Deviation1
(error)
Deviation5
Deviation7
Deviation2
Deviation6
Deviation4
Deviation3
Actual observation (y-value)
Trend line, y = a + bx^
![Page 45: 1 4 4 Forecasting PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.](https://reader035.fdocuments.us/reader035/viewer/2022081417/56649cf95503460f949ca5ef/html5/thumbnails/45.jpg)
45
Associative Forecasting Example
Sales Area Payroll($ millions), y ($ billions), x
2.0 13.0 32.5 42.0 22.0 13.5 7
4.0 –
3.0 –
2.0 –
1.0 –
| | | | | | |0 1 2 3 4 5 6 7
Sal
es
Area payroll
![Page 46: 1 4 4 Forecasting PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.](https://reader035.fdocuments.us/reader035/viewer/2022081417/56649cf95503460f949ca5ef/html5/thumbnails/46.jpg)
46
Associative Forecasting Example
y = 1.75 + .25x^ Sales = 1.75 + .25(payroll)
If payroll next year is estimated to be $6 billion, then:
Sales = 1.75 + .25(6)Sales = $3,250,000
4.0 –
3.0 –
2.0 –
1.0 –
| | | | | | |0 1 2 3 4 5 6 7
No
del
’s s
ales
Area payroll
3.25
![Page 47: 1 4 4 Forecasting PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.](https://reader035.fdocuments.us/reader035/viewer/2022081417/56649cf95503460f949ca5ef/html5/thumbnails/47.jpg)
47
How strong is the linear relationship between the variables?
Coefficient of correlation r measures degree of association
Values range from -1 to +1
Coefficient of Determination r2
the % change in y predicted by the change in x Values range from 0 to 1
For example, when r = .901 r2 = .81
Correlation
![Page 48: 1 4 4 Forecasting PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.](https://reader035.fdocuments.us/reader035/viewer/2022081417/56649cf95503460f949ca5ef/html5/thumbnails/48.jpg)
48
Correlation Coefficient
y
x(a) Perfect positive
correlation: r = +1
y
x(b) Positive correlation:
0 < r < 1
y
x(c) No correlation:
r = 0
y
x(d) Perfect negative
correlation: r = -1
![Page 49: 1 4 4 Forecasting PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.](https://reader035.fdocuments.us/reader035/viewer/2022081417/56649cf95503460f949ca5ef/html5/thumbnails/49.jpg)
49
Multiple Regression Analysis
If more than one independent variable is to be used in the model, linear regression can be
extended to multiple regression to accommodate several independent variables
y = a + b1x1 + b2x2 …^
Computationally, this is quite complex and generally done on the
computer
![Page 50: 1 4 4 Forecasting PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.](https://reader035.fdocuments.us/reader035/viewer/2022081417/56649cf95503460f949ca5ef/html5/thumbnails/50.jpg)
50
Multiple Regression Analysis
y = 1.80 + .30x1 - 5.0x2^
In the Nodel example, including interest rates in the model gives the new equation:
An improved correlation coefficient of r = .96 means this model does a better job of predicting the change in construction sales
Sales = 1.80 + .30(6) - 5.0(.12) = 3.00Sales = $3,000,000
![Page 51: 1 4 4 Forecasting PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.](https://reader035.fdocuments.us/reader035/viewer/2022081417/56649cf95503460f949ca5ef/html5/thumbnails/51.jpg)
51
Forecasting in the Service Sector
Presents unusual challenges Special need for short term records Needs differ greatly as function of
industry and product Holidays and other calendar events Unusual events
![Page 52: 1 4 4 Forecasting PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.](https://reader035.fdocuments.us/reader035/viewer/2022081417/56649cf95503460f949ca5ef/html5/thumbnails/52.jpg)
52
Fast Food Restaurant Forecast
20% –
15% –
10% –
5% –
11-12 1-2 3-4 5-6 7-8 9-1012-1 2-3 4-5 6-7 8-9 10-11
(Lunchtime) (Dinnertime)Hour of day
Per
cen
tag
e o
f sa
les
Figure 4.12
![Page 53: 1 4 4 Forecasting PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.](https://reader035.fdocuments.us/reader035/viewer/2022081417/56649cf95503460f949ca5ef/html5/thumbnails/53.jpg)
53
FedEx Call Center Forecast
Figure 4.12
12% –
10% –
8% –
6% –
4% –
2% –
0% –
Hour of dayA.M. P.M.
2 4 6 8 10 12 2 4 6 8 10 12
![Page 54: 1 4 4 Forecasting PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.](https://reader035.fdocuments.us/reader035/viewer/2022081417/56649cf95503460f949ca5ef/html5/thumbnails/54.jpg)
54
In-Class Problems from the Lecture Guide Practice Problems
Problem 1:Auto sales at Carmen’s Chevrolet are shown below. Develop a 3-week moving average.
Week Auto Sales
1 82 103 94 115 106 137 -
![Page 55: 1 4 4 Forecasting PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.](https://reader035.fdocuments.us/reader035/viewer/2022081417/56649cf95503460f949ca5ef/html5/thumbnails/55.jpg)
55
In-Class Problems from the Lecture Guide Practice Problems
Problem 2:Carmen’s decides to forecast auto sales by weighting the three weeks as follows:
Weights Applied
Period
3 Last week
2 Two weeks ago
1 Three weeks ago
6 Total
![Page 56: 1 4 4 Forecasting PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.](https://reader035.fdocuments.us/reader035/viewer/2022081417/56649cf95503460f949ca5ef/html5/thumbnails/56.jpg)
56
In-Class Problems from the Lecture Guide Practice Problems
Problem 3:A firm uses simple exponential smoothing with α=0.1 to forecast demand. The forecast for the week of January 1 was 500 units whereas the actual demand turned out to be 450 units. Calculate the demand forecast for the week of January 8.
![Page 57: 1 4 4 Forecasting PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.](https://reader035.fdocuments.us/reader035/viewer/2022081417/56649cf95503460f949ca5ef/html5/thumbnails/57.jpg)
57
In-Class Problems from the Lecture Guide Practice Problems
Problem 4:Exponential smoothing is used to forecast automobile battery sales. Two value of α are examined α = 0.8 and α=0.5. Evaluate the accuracy of each smoothing constant. Which is preferable? (Assume the forecast for January was 22 batteries.) Actual sales are given below:
Month Actual Battery Sales
Forecast
January 20 22
February 21
March 15
April 14
May 13
June 16