onstruction activity still rising but material costs and ...
1 3. M ODELING U NCERTAINTY IN C ONSTRUCTION Objective: To develop an understanding of the impact of...
-
Upload
jocelin-flowers -
Category
Documents
-
view
212 -
download
0
Transcript of 1 3. M ODELING U NCERTAINTY IN C ONSTRUCTION Objective: To develop an understanding of the impact of...
1
3. MODELING UNCERTAINTY IN
CONSTRUCTIONObjective:
To develop an understanding of the impact of uncertainty on the performance of a project, and to introduce planning tools for handling uncertainty:
Summary:3.1 Uncertainty in Construction
3.2 Deterministic Analysis
3.4 PERT Network Analysis and Modeling Uncertainty
3.5 CPM Network Analysis using Monte Carlo Sampling
2
3.1 UNCERTAINTY IN
CONSTRUCTION
Uncertainty in construction can occur in many places:– productivity;– environmental conditions; – supply of information;– availability of labor; etc...
3
This lack of knowledge makes it difficult to accurately estimate:– project costs;– project duration;
In turn, this complicates management tasks such as the following:– determining an appropriate bid;– budgetary control;– comparison of the cost or time efficiency of alternative
construction methods.
4
Uncertainty is a lack of knowledge about the likely outcome or requirement of some aspect of a project:– can reduce uncertainty by analyzing the situation in
more detail, however, this is limited:• limited theory defining cause-effect relationships between
key project variables;• performance of computing hardware and software;• limited resources available to undertake the study, such as
money, time and expertise.
5
3.2 DETERMINISTIC ANALAYSIS
Usually, uncertainty is ignored, and a deterministic stand is adopted:– two major problems:
• no indication as to whether actual performance will vary much from expected performance;
• leads to optimistic bias in performance assessment.
Will discuss these points in turn:
6
Probability Density
ProjectDuration
Figure 1: Different Degrees of Certainty about Expected Project Duration
Likely variation fromexpected durationis small
Likely variation fromexpected durationis large
Both cases have thesame expectedduration
95% probabilities
The greater uncertainty means more likely extend beyond completion deadline
PlannedCompletiondate
7Figure 2: Simple Network with Uncertain Activity Durations
‘a’
‘c’
‘b’
‘d’ ‘e’
1 day
5 days10 days
5 days10 days
3 days 5 days10 days15 days20 days
Observed durations from past projects
Second Major Problem: optimistic bias.
8
If use deterministic analysis:– ‘b’ takes 7.5 days (mean)– ‘c’ takes 7.5 days (mean)– thus the duration between ‘a’ and ‘d’ = 7.5 days
In reality, there are four possible outcomes:
ActivityActivity ActivityActivity Duration betweenDuration between‘‘b’b’ ‘c’‘c’ ‘a’ and ‘d’‘a’ and ‘d’
5 days 5 days 5 days
5 days 10 days 10 days
10 days 5 days 10 days
10 days 10 days 10 days
Therefore, on average it will take (5+10+10+10)/4 = 8.75 days
9
3.4 PERT NETWORK ANALYSIS
AND MODELING UNCERTAINTY
PERT (Program Evaluation and Review Technique):– a method (similar to deterministic CPM)
developed to take account of uncertainty; – quite popular in construction;– it includes an incorrect assumption that
makes it only slightly more useful than the deterministic approach.
10
‘a’
‘b’
‘c’
‘d’
Each activity has three durations associated with it:
10
most likelyduration
5
optimisticduration
(<=0.05p)
15
pessimisticduration
(<=0.95p)
9 10 11
7 9 10
1 2 3
11
Project duration only takes uncertainty into account along the critical path:
‘a’
‘b’
‘c’
‘d’9 10 11
7 9 10
1 2 35 10 15
• The calculated project duration is therefore the same as in deterministic analysis
duration = 22 days
• The calculated variance in the project duration is also under estimated
12
Probability Density
ProjectDuration
PERT derivedproject durationdistribution
Actual project duration distribution(broader)
Deterministic & PERTexpected project duration
Actual expected project duration (longer)
13
3.5 CPM NETWORK ANALYSIS
USING MONTE CARLO SAMPLING
Monte Carlo based CPM– a method where a random sample of
possible outcomes are considered; – increasing popularity in construction;– its accuracy increases with an increase in
the number of samples considered– will accurately estimate expected duration
and variance.
14
activity
d1 d2
• Consider a project where each activity has just two possible durations, d1 and d2.
Number of Activities
Number of Possible Outcomes
Time for a Computerto Process all Possibilities
1 2 0.002 m secs
10 1024 1.024 secs
25 33,554,432 9.32 hours
50 1.12 x 1015 35,678 years
100 1.27 x 1030 4.02 x 1019 years>>> age of universe
• Clearly, evaluating all possible outcomes is not feasible!• So just select a random sample of possible outcomes.• The most popular way of selecting the samples is Monte
Carlo sampling
15
‘a’
‘b’
‘c’
‘d’
Each activity will have some distribution of possible durations, for example:
• Normal distribution with a mean and standard deviation;• Discrete distribution; many others...
12
meanduration
1.5
standarddeviation
19 1.1
21 2.2
18 1.7
16
The approach recognizes that different paths could be critical in different samples:
• Consequently, the estimate of project duration is accurate;• Also, the estimate of variance in project duration is accurate;• We have additional information:
- probabilities of activities becoming critical (critical indices);- probability distributions for amounts of float on each activity;
17
Probability Density
ProjectDuration
Monte CarloProject DurationDistribution(say 100 + samples)
Actual project duration distribution