1 2014 System Operator Conference Simulator Drill Orientation 2014 System Operator Conferences...

download 1 2014 System Operator Conference Simulator Drill Orientation 2014 System Operator Conferences Charlotte NC & Franklin TN SERC/SOS Facilitator Team.

If you can't read please download the document

Transcript of 1 2014 System Operator Conference Simulator Drill Orientation 2014 System Operator Conferences...

  • Slide 1
  • 1 2014 System Operator Conference Simulator Drill Orientation 2014 System Operator Conferences Charlotte NC & Franklin TN SERC/SOS Facilitator Team
  • Slide 2
  • 2014 System Operator Conference 2 2014 System Operator Conference EMERGENCY DRILLS The Simulated POWER SYSTEM Finist Energy Interconnection Operator Training Simulator (OTS) by FINIST
  • Slide 3
  • 2014 System Operator Conference 3 Learning Objective At the conclusion of this training session, you should be able to: Review the configuration of the simulated FINIST ENERGY interconnection, including: Finist Balancing Authority (BA), neighboring BAs, and the rest of the Interconnection total generating capacity and power plants peak demand transmission voltage levels reactive control equipment
  • Slide 4
  • 2014 System Operator Conference 4 Learning Objective State the basic features of OTS Finist user interface including: Start/stop/pause the simulator (from Facilitator interface only) Display frequency/ACE/total load Display system one-lines and station details Determine location of generating plants, substations and loads from symbols on the one-lines Determine overloads or out-of-range voltages from color coding on the one-lines Change generation, AGC control mode, interchange schedules Change status of circuit breakers; switch in/out equipment Recognize abnormal/emergency events from simulator displays
  • Slide 5
  • 2014 System Operator Conference 5 Outline of Topics THE POWER SYSTEM Host Balancing Authority is FINIST ENERGY where all the action takes place. Neighboring Balancing Authorities: BA1, BA2, BA3 Large interconnection Generating capacity and peak demand in each area One-line overview of system List of power plants and types, voltage control equipment, flowgates
  • Slide 6
  • 2014 System Operator Conference 6 Outline of Topics, continued THE SIMULATOR Accessing and manipulating the simulator Working with displays Working with system one-lines Monitoring system parameters Implementing operator control actions Recognizing when an event has taken place
  • Slide 7
  • 2014 System Operator Conference 7 The FINIST INTERCONNECTION
  • Slide 8
  • 2014 System Operator Conference 8 Balancing Area 3 Finist Energy Balancing Area 2 Balancing Area 1 Interconnection 500 kV 230 kV
  • Slide 9
  • 2014 System Operator Conference 9 Peak Load & Generating Capacity FINIST ENERGY (Host BA) Peak: 4,685 MW (includes 85 MW auxiliaries) Gen Capacity: 3,325 MW BA-1 Peak: 3,200 MW Gen Capacity: 3,600 MW BA-2 Peak: 3,200 MW Gen Capacity: 3,700 MW BA-3 Peak: 3,100 MW Gen Capacity: 4,200 MW INTERCONNECTION Peak: 81,500 MW (79,500 MW + 2,000 MW non-conforming load) Gen Capacity: 90,000 MW
  • Slide 10
  • 2014 System Operator Conference 10 Features of Finist Energy System voltage levels are 500 kV, 230 kV, 138 kV Load is connected via circuit breakers off 10 kV busses on station single lines System equipment includes: 33 Generators at 7 Plants Hydro Plant Nuclear Plant 6 Synchronous Condensers 2 Reactors Capacitor bank Static Var Compensators Phase Shifting Transformers
  • Slide 11
  • 2014 System Operator Conference 11 Squares are generators Circles are substations FINIST ENERGY LEGEND
  • Slide 12
  • 2014 System Operator Conference 12 FINIST Energy One-Line NUC Hydro
  • Slide 13
  • 2014 System Operator Conference 13 7 Power Plants 33 units
  • Slide 14
  • 2014 System Operator Conference 14 FINIST Energy One-Line
  • Slide 15
  • 2014 System Operator Conference 15 Finist Voltage Control Equipment Synch. Cond., Capacit ors, Reactor s, SVC
  • Slide 16
  • 2014 System Operator Conference 16 FINIST Energy One-Line
  • Slide 17
  • 2014 System Operator Conference 17 Finist Flowgates
  • Slide 18
  • 2014 System Operator Conference 18 INTERACTING WITH FINIST Operating Training Simulator
  • Slide 19
  • 2014 System Operator Conference 19 Interface to the OTS (Operators Workplace) Icon you will see on the computers desktop Your Facilitator Team will start the OTS and initiate all events. You may be instructed to open the OWP icon to begin the drill, or OWP may already be open on your laptop. Make sure the clock in the upper right is running!
  • Slide 20
  • 2014 System Operator Conference 20 Interface to the OTS (Operators Workplace) Start by opening the diagrams!
  • Slide 21
  • 2014 System Operator Conference 21 Basic Diagrams (Simplified)
  • Slide 22
  • 2014 System Operator Conference 22 Finist Energy (Overview)
  • Slide 23
  • 2014 System Operator Conference 23 Station Diagrams (Simplified) Expand to see list of stations
  • Slide 24
  • 2014 System Operator Conference 24 230kV Deer (Simplified) 24
  • Slide 25
  • 2014 System Operator Conference 25 Station Diagrams (Detailed)
  • Slide 26
  • 2014 System Operator Conference 26 Detailed 230 kV Deer (Detailed)
  • Slide 27
  • 2014 System Operator Conference 27 Voltage, Flow, Frequency MW MVAR
  • Slide 28
  • 2014 System Operator Conference 28 Voltage Monitor On Overview
  • Slide 29
  • 2014 System Operator Conference 29 Voltage Monitor Screen
  • Slide 30
  • 2014 System Operator Conference 30 MVA Monitor On Overview
  • Slide 31
  • 2014 System Operator Conference 31 MVA Monitor Screen
  • Slide 32
  • 2014 System Operator Conference 32 Current Monitor on Overview
  • Slide 33
  • 2014 System Operator Conference 33 Load Management Display
  • Slide 34
  • 2014 System Operator Conference 34 Neighboring Areas (w/ Interchange) 34
  • Slide 35
  • 2014 System Operator Conference 35 Reactive Devices
  • Slide 36
  • 2014 System Operator Conference 36 Generation Controls
  • Slide 37
  • 2014 System Operator Conference 37 Generation Controls
  • Slide 38
  • 2014 System Operator Conference 38 AGC Modes Generation costs may be changed at any time and this may make AGC use another station If regulating station goes offline, the next lowest generator cost station becomes the regulating unit
  • Slide 39
  • 2014 System Operator Conference 39 AGC Modes A generator can be in the following active generation modes: AGC automatic generation control - ACE control Droop initial mode, follows generation schedule LFC load frequency control, frequency regulation Manual fixed active generation value (manually entered) Offline generator is offline
  • Slide 40
  • 2014 System Operator Conference 40 Generator Auxiliaries Generator auxiliaries located on station one-line diagrams and Generation Control Display. Auxiliaries must be energized for generator to start and generator will trip if auxiliaries are de- energized. Can start generator without auxiliaries with blackstart option.
  • Slide 41
  • 2014 System Operator Conference 41 Capacitor Bank Control 1 23 4
  • Slide 42
  • 2014 System Operator Conference 42 Shunt Reactor Control
  • Slide 43
  • 2014 System Operator Conference 43 Static Var Compensator Control 1 23 4
  • Slide 44
  • 2014 System Operator Conference 44 Synchronous Condenser Control 123 2A 3A 4A4A 1A1A
  • Slide 45
  • 2014 System Operator Conference 45 Transformer Tap Control 1 2 3 4
  • Slide 46
  • 2014 System Operator Conference 46 Generator Control 3 2 4 1
  • Slide 47
  • 2014 System Operator Conference 47 Generator MVAR Control 1234
  • Slide 48
  • 2014 System Operator Conference 48 Generator Plant Control 23 1 4
  • Slide 49
  • 2014 System Operator Conference 49 Load Shedding 1
  • Slide 50
  • 2014 System Operator Conference 50 Load Shedding 2 23 4 1
  • Slide 51
  • 2014 System Operator Conference 51 MVAR Load Adjustment 12 3 4
  • Slide 52
  • 2014 System Operator Conference 52 Starting Generators To start a generator it needs to be connected to at least one load. This load may or may not be its own auxiliaries Started generator immediately generates power equal to the load but no more than 5% of maximum generation Load Frequency Generation The generator works for the first 20 seconds despite frequency and voltage conditions to allow operator to match island load and generation
  • Slide 53
  • 2014 System Operator Conference 53 Alarms Panel Filter by severity Fix panel position Stay-on-top of other windows Is invoked from Operators Workplace toolbar Events can be sorted by date or by level of severity
  • Slide 54
  • 2014 System Operator Conference 54 Summary This has been an introduction to the Finist OTS designed to get you started, including : Start/Stop/Pause from Facilitators interface only (Note: NO Undo button!) How to display station & system maps What the color codes and symbols mean How to monitor: MW, MVAR, current, frequency, interchange, load How to control: Gen. units, AGC modes, interchange, reactive reserves (caps, reactors, synch. condensers, SVCs), transformer taps, load adjustments
  • Slide 55
  • 2014 System Operator Conference 55 OTS Finist DEMO Now lets demonstrate! BEGIN DEMO
  • Slide 56
  • 2014 System Operator Conference 56 Questions?