MSC-TF Section Meeting Vertical Stations: 2010 Activity 1

Transcript of 1. 2 LHC consolidation: tests completed in 2010 Projects completed in 2010 Test facility...

Page 1: 1. 2 LHC consolidation: tests completed in 2010 Projects completed in 2010 Test facility consolidation Where are we now? Planning Foreseen Activities.

1

MSC-TF Section Meeting

Vertical Stations:2010 Activity

Page 2: 1. 2 LHC consolidation: tests completed in 2010 Projects completed in 2010 Test facility consolidation Where are we now? Planning Foreseen Activities.

2

Contents LHC consolidation: tests completed in 2010

Projects completed in 2010

Test facility consolidation

Where are we now?

Planning

Foreseen Activities for 2011

Page 3: 1. 2 LHC consolidation: tests completed in 2010 Projects completed in 2010 Test facility consolidation Where are we now? Planning Foreseen Activities.

3

LHC consolidation: tests completed in 2010 600A and 14kA connections : 2 sessions with screwed and crimped 600A

connection 1 test with 14kA screwed connections.

Pray-Hand: 3 tests ,12000 cycles up to 9kA, without kapton belt 2000 cycles up to3kA and 12000cycles up to 6kA

Factor was1.5 on current, 2.25 on forces and about 10 on lifetime No resistance degradation after cycling.

Diode: one session with thermal dependence and 4sessions of 4 diodes.

Copper Bar: A 4 cm defect was introduced in a 5m long copper bar

of cross section 20X10mm, to estimate the current carrying capacity of copper

in case of a default in a bus bar.

We were able to regulate at different stables temperatures (24k, 13k, 40k,…).

Defect machined out of the bar

Page 4: 1. 2 LHC consolidation: tests completed in 2010 Projects completed in 2010 Test facility consolidation Where are we now? Planning Foreseen Activities.

4

Projects completed in 2010KIT Wiggler: 5 tests during the year. the goal was to ramp up to 175A, but only 156A have been reached.

TQS03: 3 tests – Aging with 1000 cycles up to11kA with a quench after each 150 cycles. - Loss measurements: electrically and by cryogenic measurements

of the dissipated power. - Magnetic measurements.

Russian Wiggler: one test with shielding (max current 120A).

HFM: SMC Component qualification at cold, test with dummy and real coils, powering one coil at 7784A.

MgB2: -5 tests of cables and wires samples during the year.

-2 bending tests with different radius.

HIE Isolde: Nb3Sn 2 tests of both impregnated and ceramic solenoids

Page 5: 1. 2 LHC consolidation: tests completed in 2010 Projects completed in 2010 Test facility consolidation Where are we now? Planning Foreseen Activities.

5

Test facility Consolidation

Cryostat 1 ( aux)

Cryostat 2 (diode + CL)

Cryostat 3 ( FRESCA 2)

Cryostat 4 ( LONG)

Feed Box x SCL and FCM

Switch

Cryo Racks DAQ Racks DAQ Racks

Cryo Control

VERTICAL test benches &

Supercritical helium test station

Page 6: 1. 2 LHC consolidation: tests completed in 2010 Projects completed in 2010 Test facility consolidation Where are we now? Planning Foreseen Activities.

6

Civil engineering started in March 2010

Dismounting Block 4 started on 15th of October 2010

Test facility Consolidation

Status in October 2010

Page 7: 1. 2 LHC consolidation: tests completed in 2010 Projects completed in 2010 Test facility consolidation Where are we now? Planning Foreseen Activities.

7

Where are we now? Vertical station in SM18

First test expected March 2010

Bat 892-bloc4

Should be empty end of 2010

Page 8: 1. 2 LHC consolidation: tests completed in 2010 Projects completed in 2010 Test facility consolidation Where are we now? Planning Foreseen Activities.

8

Déménagement bloc41 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 5 6 7 8

Fonctionnement bloc4 :

Avec 20KA, switch, barres cuivreAvec boite à vannes (possibilité tests avec PS 2KA et 600A)

Fonctionnement SM18

Génie Civil (4 puits) + 3 semaines Séchage

Obturation Puits, mise en sécurité

Plateforme

Fabrication Daniel P.

Pose plateforme + 2 potences (pour retour chaud + cables controles) Daniel P. Potences + modification DanielInstallation salle de contrôle Daniel P.

Installation électriques

Installation armoire secteur triphasée (support ?) + raccordement Nuno D. Raccordement NunoPose chemin de cables sous PF Jean-Claude G.Pose chemin de cables en périphérique de la PF NunoDistribution des prises secteurs + alimentations racks ?? +20KA Nuno

Tirage câbles Nuno ????

Mise en place racks electriques Mickael K. Julien H.

Installation cryogénie

Pose tuyauterie cryo (retour chaud, ballon, pompage …) ou Vladislav B., Patrick V. (TF)Raccordement rack cryo ST long Vladislav B., Patrick V. (TF)

Démontage et installation boite a vannes + raccordement electrique ?????? Vladislav B., Patrick V.

Alimentation et câbles de puissance

Démontage au bloc4 câbles de puissance (Alimentation, switch..) Jean-Claude G.Alimentation 20KA (Démontage, installation et révision) Hugues T., Patrick V. Switch thyristor + mécanique (Démontage, installation et révision) Knud D., Patrick V. Démontage au bloc4 et pose Barres de cuivre pour distribution 20KA Patric FredInstallation câbles de puissance (Alim., switch, PS-->B.barres + switch) Jean-Claude G.

Eau déminéralisée de refroidissement Frank Franck M.Alimentation 600A Hugues T., Patrick V. (TF)

Tourelles

Démontage tourelle ST Longue et installation Patrick Fred

Installation et cablage racks

Plc cryo.(cablage armoire, programmation, cablage extérieur)? Marco P., Christian G., Jerome F., FredPlc alimentations(cablage armoire, programmation, cablage extérieur)? David, Christian G., Jerome F., Michael K.

Système d'acquisition PXI (cablage)? Gaelle D., Frederic F.Rack alimentation chaufferette Michael K., Jerome F.

Supervision cryo. Marco P., Christian G. (TF)

Fonctionnement Station- Longue

Déplacement et installation cryostat Patrick V. (TF) et cryo.Rack cryo (raccordement) avec cryostat Patrick V. (TF)

Rack détection quenches (cablage)+ matrice de sécurité(cablage) Christian G., Michael K., Jerome F.(TF)Rack mesures magnétique (cablage) Guy D., Frederic F.Rack Plc automate (Raccordement et mise au point) Marco P, Christian G., Jerome F., Michael K. (TF)Rack acquisition PXI (Raccordement, cablage) Gaelle D., Frederic F.Rack instrumentation (Temp., Pression, chauffage…) Michael K., Christian G.Installation câbles de puissance (B.barres--> Leads + support) Jean-Claude G., Patrick V.

Fonctionnement SC-Link

CryoRack lecture (potentiels, températures)

Rack Plc automateCâbles puissance 13KA + supportModification et Installation Feedbox

semaine semaine semaine semaine semaine semaine semaine semaine semaine semaine semaine semaine mars-11 avr-11 mai-11sept-10 oct-10 nov-10 déc-10 janv-11 févr-11juin-10 juil-10 août-10

Page 9: 1. 2 LHC consolidation: tests completed in 2010 Projects completed in 2010 Test facility consolidation Where are we now? Planning Foreseen Activities.

9

Foreseen activities for2011 HQ: in March or April @1,9K

SMC: From march for 4 models with several cool downs, 3months

Diodes: 4 runs of 4 diodes starting in August

HIE Isolde solenoids: starting in July

Wiggler for Clic: starting in July

SC Link and FCM from May and for 5 weeks