CES, MBE, GLEReplace ACM soffit – CT/CMPL
SMSGLE, MBE, CES
Replace Stage Rigging and Lighting (ACM wiring)
CMPL
CHS and SMSBrick masonry improvements for
serviceability - CT
Proposed Priority Capital Maintenance ProjectsPhase I 2015/16
BES, GLE, MBE,CES and SMS
Replace select electric panels
CHS Electronic school sign
SMSReplace gym floor and
bleachers
SMS and FBEReplace bathroom partitions
FBE, CHS and HAEOverlay/re-pave asphalt parking
lots and drives
Cambria, TechnologyPave/overlay asphalt parking lots
Proposed Priority Capital Maintenance ProjectsPhase II 2015/16
BES and CPSReplace select A/C Units
CHSReplace Auditorium Moveable
Partitions
HAE, BEL MPR- Replace flooring
Technology Building - Replace windows
Montgomery CentralReplace windows-
lower building
Beeks, FBE, GLE Improve Security Fencing
CHSReplace lockers
Proposed Priority Capital Maintenance ProjectsPhase II 2015/16
GLE, FBE, HAEReplace concrete sidewalks
EMHS Electronic school sign
CHSReplace air handling units,
C9, B3, A9
CHS, SMSReplace ceiling tileGLE
Paved play area
Proposed Priority Capital Maintenance ProjectsPhase III 2015/16
Replace Mobile Units
(~14 units >/= 18 years old)