1 1 Project Planning & Estimating – Are we there yet? Deb Smith Mayo Clinic, Enterprise Portfolio...
-
Upload
bernadette-sims -
Category
Documents
-
view
215 -
download
0
Transcript of 1 1 Project Planning & Estimating – Are we there yet? Deb Smith Mayo Clinic, Enterprise Portfolio...
11
Project Planning & Estimating –Are we there yet?
Deb SmithMayo Clinic, Enterprise Portfolio Management Office (EPMO)
2
Introduction• Education
• MS in Project Mgmt from SMU of MN October 2006
• Undergrad in Electrical & Computer Engineering from University of Michigan
• Employment/Experience
• Mayo Clinic Enterprise Portfolio Management Office, Sr. Project Consultant
• Adjunct Professor Saint Mary’s University MS Project Mgmt since 2006
• Project/Portfolio Manager 8 yrs (Mayo)
• IT Project Manager 15 yrs (IBM & Mayo)
• PMI Certified PMP 25 February 2002
3
Discussion Overview
• Project Life Cycle
• Estimating Projects
• What Makes Projects Different
• “Adjust the use and rigor”
• Questions and Comments
4
What is a project?• Organized set of work efforts.
• Progressively elaborated
• Limited by time and resources
• Have a defined beginning and ending
Project – “a temporary endeavor undertaken tocreate a unique product, service, or result.” PMBOK® Guide
Project – “a temporary endeavor undertaken tocreate a unique product, service, or result.” PMBOK® Guide
5
What is a Project?• It is a temporary endeavor with specific start and end
dates that can answer “yes” to one or more of the following questions:
• Does the activity require independent approval? • Does the activity require specific funding and have separate
budget? (e.g. Capital and/or operational expenses)• Is there a specific team focused on this activity outside of
normal operations?• Can this activity be implemented independently of other
activities?• Does this activity require more than 20 person hours? (this
may be of IT Infrastructure and/or combined resource effort - still working this out)
Mayo Enterprise Standard
6
Project Life Cycle Stages/Process Groups• Initiating — when a project is proposed, planned at a
high level, and key participants commit to it in broad terms
• Planning — starts after the initial commitment, includes detailed planning, and ends when all stakeholders accept the entire detailed plan
• Executing — includes authorizing, executing, monitoring, and controlling work until the customer accepts the project deliverables
• Closing — all activities after customer acceptance to ensure project is completed, lessons are learned, resources are reassigned, and contributions are recognized.
Mo
nit
or
and
Co
ntr
ol
Planning
7
Project Life Cycle Stages
Project Manager
8
Start Developing the Project Plan
Who, What, When, Where, & HowWho, What, When, Where, & How
Questions DocumentationWhat is to be done? Scope definition document
Why should we do it? Business case or rationale
How should we do it? Strategy & Work Breakdown Structure (WBS)
In what sequence? Network Diagram
Where should work be done? Organizational Breakdown Structure (OBS)
When should work be done? Schedule Plan
Who should do the work? Resource Utilization Plan
How much will it cost? Cost Plan or Budget Plan
How do we judge process? Milestone Plan or Earned Value (EV) Plan
9
Mayo Enterprise Standard
10
Project Management
1111
Estimating Projects
12
How to Estimate• Have the right people make the estimate
• Use history and experience as guide
• The smaller the unit of work being estimated the better the estimate
• Bottom-up approach best – most costly
• Effort-based activities may be compressed by adding staff • The “mythical man month”
• Some people tend to estimate optimistically. Keep in mind:• Actual productive time (~ 80%)• Learning curves/Rework• Competing priorities and dependencies not available on time
(Document the assumptions and approach) • Emergencies/illness/Vacation
• Do not pad the numbers
13
10 Tips for Increasing Estimating Accuracy
1. Create and use planning documents2. Identify assumptions and constraints 3. Simplify 4. Prioritize deliverables5. Use complexity factor 6. Manage “iron triangle” 7. Track actuals8. Modify plans/forecasting9. Use lessons learned10.Use more than one method to arrive at an
estimate
COST
Quality
TIMESCOPE
14
Ensure success of each team member• Consider partial time allocation
• Determine collision or collaboration points
• Develop efficient ways to organize and perform the work
1515
What Makes Projects Different?
16
What Makes Projects Different?
• Projects vs. operations
• Large or Small
• Complex or Simple
• Process Improvement or Product Development
• Waterfall or Iterative Approach
17
Projects vs. OperationsQ: When is maintenance a project?
A: When it is a temporary endeavor that delivers a unique product, service, or result.
18
Size and Complexity
19
Product or Process Improvement
20
Waterfall vs. Iterative
Plan Driven Adaptive
21
Agile Project Management• Organize the project into short iterations
• Only plan in detail for nearby tasks.
• PM emphasis is moved from planning to execution
2222
Adjust the Use and Rigor
23
Project Mgmt Plan - How
• Scope Mgmt Plan
• Schedule Mgmt Plan
• Cost Mgmt Plan
• Quality Mgmt Plan
• Staffing/Resource Mgmt Plan
• Communication Mgmt Plan
• Risk Mgmt Plan
24
How much is too much?• What is your ratio of documentation to
deliverables?
• What is the percentage of time spent on planning vs. execution?
• How many different groups/organizations must be coordinated?
• Has this been done before?
• Are there critical resource constraints?
• What documentation do you need to get funding?
25
Minimum Required Formal Documents• Project Charter
• Work Breakdown Structure (WBS)
• Communication Plan
• Risk Identification and Owners
• Status Report
26
27
Plan the work!
Work the plan!
NET: Failing to plan is planning to fail
28
Questions, Comments, Suggestions