1 · 1'-2" min. 3'-8" max. see eo-13794 for roof thickness. construction standards eo-8007 revision...
Transcript of 1 · 1'-2" min. 3'-8" max. see eo-13794 for roof thickness. construction standards eo-8007 revision...
Approvers: Attard, Jason S 08/17/2017
••
•
•
•
•
App
rove
rs: A
ttard
, Jas
on S
08/
17/2
017
7"
7'-1
"
4 10
3
(MAXIMUM EARTH COVER 3'-8")
34,700 #
6,300 #
NS0111537
NS0111532
NS0111533
CAST IRON FRAME TYPE (Q-8-7)
CAST IRON COVER TYPE (Q-8-S)
DUCTILE IRON VENTED COVER TYPE "Q8" GRATE
GRADING BLOCKS OR COLLARS
CEMENT MORTAR
CABLE STANCHIONS - TWO SLOTS
PRECAST CONCRETE WEDGE ITEM 6
17
AS REQ'D.8
AS REQ'D.9
1010
411
EO-9359-C 003-5915
345796 003-9487
EO-10321-B
EO-100,167 003-0802
EO-9210-C 003-0387
EO-5299-B
DISTRIBUTION ENGINEERING DEPT.
7/27/17
R. VENTURA 16
16
FILL WITH SIKA GROUT 212 OR
APPROVED EQUAL ALL AROUND.
INSTALLATION SPECIFICATIONS:
• IN ROCK EXCAVATIONS INSTALL MANHOLE ON 3" SAND CUSHION.
• FILL LIFTING POCKETS IN FLOOR AND 1" GAP BETWEEN FLOOR AND WALLS
WITH SIKA GROUT 212 OR APPROVED EQUAL (ITEM 12); FILL LIFTING HOLES ON
WALLS AND UNUSED OPENINGS WITH ITEM 9 (CEMENT MORTAR).
• SET ROOF SLAB CENTERED ON TOP OF WALL WITH CEMENT MORTAR (ITEM 9).
BUILD COLLAR TO OBTAIN GRADE AND SET CASTING AS PER EO-1092.
• USE APPROPRIATE METHOD SHOWN ON EO-10321-B TO OBTAIN GRADE.
PACK WITH SIKA
GROUT 212 OR
APPROVED EQUAL
AND FORCE WEDGE
IN PLACE.
• UPDATED DIMENSIONS,
BILL OF MATERIALS,
STOCK NUMBERS,
APPROXIMATE WEIGHTS
& INSTALLATION
SPECIFICATION.
• ADDED SECTION X-X,
VENTED COVER
REQUIREMENT & ITEM
12.
• REMOVED REF. DWG.
EO-8394-D AND METHOD
A&B ON ITEM 3.
D.E. 7/27/17
SECTION X-X
X
X
GROUT (SIKA GROUT 212)AS REQ'D12
12
10
1
2
"
1'-2" MIN.
3'-8" MAX.
SEE EO-13794 FOR ROOF THICKNESS
CONSTRUCTION STANDARDS EO-8007 REVISION 24 MANUAL NO.11 OCTOBER 2003
1
CONSOLIDATED EDISON CO. OF NEW YORK, INC.
4 IRVING PLACE NEW YORK, NY 10003
DISTRIBUTION ENGINEERING DEPARTMENT SUBSTATION & EQUIPMENT SECTION
SPECIFICATION EO-8007 REVISION 24
OCTOBER 2003
INSTALLATION OF PRECAST CONCRETE CONDUIT
FILE: CONSTRUCTION STANDARDS FIELD MANUAL NO. 11 FIELD MANUAL NO. 17
CONSTRUCTION STANDARDS EO-8007 REVISION 24 MANUAL NO.11 OCTOBER 2003
2
TABLE OF CONTENTS PARAGRAPH DESCRIPTION PAGE 1.0 SCOPE 3 2.0 APPLICATION 3 3.0 GENERAL 3 4.0 DEFINITIONS 3 5.0 MATERIAL 3 6.0 TRENCH PREPARATION 4 7.0 INSTALLATION 5 8.0 BACKFILL 6 9.0 INSPECTION AND ACCEPTANCE 6 10.0 REPLACEMENT 7 11.0 PULLING LINES 7 12.0 PLUGS 7 13.0 REFERENCE STANDARDS 7 14.0 ATTACHMENTS
CONSTRUCTION STANDARDS EO-8007 REVISION 24 MANUAL NO.11 OCTOBER 2003
3
INSTALLATION OF PRECAST CONCRETE CONDUIT 1.0 SCOPE This specification describes the method for installing precast concrete conduit. 2.0 APPLICATION This specification applies to all Con Edison districts. 3.0 GENERAL
This specification provides for the installation of underground precast concrete conduit suitable for the housing of electric cable. These conduits shall be used and installed by Company forces and contractor personnel for new work and for replacement of conduit.
4.0 DEFINITIONS
4.1 Bend - Any change in the direction of the conduit center-line in the horizontal,
vertical or any intermediate plane is to be considered as a bend if the change in direction is greater than 5°.
4.2 Offset - Any displacement of the conduit center-line parallel to itself is to be
considered an offset.
4.3 Dip - A dip is a double offset, the second of which returns the conduit center-line to its original alignment.
5.0 MATERIAL
5.1 Straight Sections - The conduit material shall be in accordance with Con Edison specification EO-1042. The conduit shall be of a square external cross section and shall have a concentric bore and dimensions as per drawing EO-7875-D.
CONSTRUCTION STANDARDS EO-8007 REVISION 24 MANUAL NO.11 OCTOBER 2003
4
5.0 MATERIAL (Cont'd)
5.2 Bends - Bends shall have a concentric bore and square external cross section along their entire lengths and dimensions as specified on drawing EO-9489-C. The 20 foot radius bends shall be used for primary cables. When field conditions prevent the use of 20 foot radius bends, 10 foot radius bonds may be substituted. The use of 5 foot radius bends shall be restricted to service or mains cables, or primary cable from a street trench to a sidewalk transformer vault. The 3 foot radius bends shall be limited to use on intervault ties.
5.3 Split Conduit - When a conduit is field split for installation around existing cable,
either singly or in banks of conduit, it shall be secured as shown on drawing EO-9138-C. Two clamps or straps shall be used per conduit length. When clamps are used, the bolt of the clamp shall be faced in a direction so as not to interfere with any adjacent conduit. Stainless steel ties (EO-100,612) can be used as alternates to the clamps. The maximum length of a split conduit run shall be 75 feet.
5.4 Couplings - The conduits, which are double male end types, are joined with a force
fit plastic coupling as per EO-1179. The plastic coupling, when used for split conduit, shall be cut and wrapped around the ends.
6.0 TRENCH PREPARATION
6.1 Excavation of the Trench - The trench shall be excavated so as to provide a nominal cover of 24" over the highest conduit. The bottom of the trench shall be graded smooth and tamped to minimize initial settlement and to avoid "point" support of conduits. All stones projecting into the trench bottom shall be removed, and the voids backfilled before conduits are placed. Where streets are not to final grade, the cover shall be measured from the final grade, or the existing grade, whichever provides the deeper trench. If due to subsurface conditions the cover is less than 20", the duct shall be protected by 3/8" steel plates the same width as the trench. Adjacent plates shall overlap by two inches. Where possible, provide a 4" layer of clean, well-tamped backfill (Type 3/8" as per EO-8085) between the plate and the top of the duct bank. Trench widths shall be in accordance with EO-7907-D.
CONSTRUCTION STANDARDS EO-8007 REVISION 24 MANUAL NO.11 OCTOBER 2003
5
6.0 TRENCH PREPARATION (Cont'd)
6.2 Rock Protection - In rock excavations, the conduits shall be bedded as per the procedure in Con Edison specification EO-1181.
7.0 INSTALLATION
7.1 Material Inspection - Prior to installation, an inspection of the general conduit condition shall be made by the installing party, whether it be Company forces or contractor personnel. The inspection will include a random check of sections with a mandrel.
7.2 Alignment - The conduit shall be laid in as straight an alignment as possible
maintaining concentric bore and flush joints to permit smooth, easy pulling of cable without damage. A maximum permissible offset of 3 inches in any 4 foot of length will be accepted. Standard precast concrete bends shall be used in all cases where greater changes in alignment are necessary. Double male end joints shall have the plastic couplings forced on snugly to provide a tight seal. All bends shall be laid so that they are tangent at the point of joining. Care shall be exercised to prevent the introduction of foreign material.
7.3 Formation - The conduits shall be laid in the trench in the recommended formation,
specified on drawings EO-7326-B, EO-5571-B and EO-7907-D and as directed by specific layouts. When two or more conduits are installed in a duct bank, the joints must be staggered a minimum of 4 inches, both in the horizontal and vertical directions. When changes in the formation of a bank of conduits within a duct run are necessary, the transition shall be accomplished in as straight an alignment as possible, maintaining continuous earth support under the conduits.
Where specified, gas mains and precast concrete conduits shall be installed in a common trench with clearances as shown on EO-5571-B.
CONSTRUCTION STANDARDS EO-8007 REVISION 24 MANUAL NO.11 OCTOBER 2003
6
7.0 INSTALLATION (Cont'd)
7.4 Construction of Dips and Offset - An offset in any plane of more than 4.6" is to be made by means of 20 foot radius bends. A maximum of three, 20' radius, 5.625° precast bends are used to change the direction of the duct line, followed by a number of tangent sections of conduit to obtain the required distance of offset and three 20' radius, 5.625° precast bends to return the duct line to a direction parallel to its original direction. Drawing EO-9706-C shows the method of making duct deviations for dips and offsets. The approximate values of the offset and required horizontal distance from the start of the offset to the point of maximum deviation are given for a few possible combinations.
7.4.1 An offset of 4.6" or less may be made by cocking the straight sections of
conduit. However, the misalignment of each 4' conduit section is to be limited to 3" as measured at the outer end of the section being installed and at right angles to the projected center-line of the previous section of conduit.
7.5 Points of Entry - Bell end conduits (EO-9799-D) shall be used as the terminal
conduit sections for smooth, precise entry into the manhole wall and carefully cement-grouted into position, as indicated on Drawing EO-9508-C.
7.6 Closing - Closing a section of conduits with double male type ends shall be
accomplished by the use of adapters. Each adapter has a female end which shall be with a section of straight PVC or fiberglass not longer than 1 foot in length and of the same nominal diameter as the conduit in the run. The PVC or fiberglass conduit shall be encased with a concrete protective coating at least two inches thick.
8.0 BACKFILL - The material, procedure, and testing shall be as described in Con Edison
Specification EO-1181. 9.0 INSPECTION AND ACCEPTANCE
9.1 Specification EO-1063 gives the procedures to be followed and the requirements to be met for acceptance of the conduit system.
9.2 Any method used to clean the conduit must be accomplished in a manner that will
not damage the smooth bore. Any damaged conduit must be replaced with new conduit.
CONSTRUCTION STANDARDS EO-8007 REVISION 24 MANUAL NO.11 OCTOBER 2003
7
10.0 REPLACEMENT
10.1 Vacant Duct - Repairs to conduits shall not be permitted. All individual damaged or impaired lengths of conduit shall be removed and replaced with new conduit meeting specification requirements.
10.2 Loaded Duct - Replacement of conduits which are removed from around existing
cables shall be accomplished with precast concrete conduit, field split. Couplings for the field split conduit shall be cut and installed as stated on paragraph 5.4. PVC snap together split conduit as replacement conduit shall be limited to primary cable and it shall be concrete encased.
10.3 Adapting - Joining precast concrete conduit with conduits of other diameters or
material is not recommended. In exceptional cases where this cannot be avoided, use concrete adapters, as per EO-1042, for this transition.
11.0 PULLING LINES – Pulling line installation is described in Con Edison specification EO-
1063. 12.0 PLUGS - Duct ends that do not terminate in manholes or service boxes shall be closed
with duct plugs as shown on drawing EO-10864-D. Plugs should be installed at the end of each day's work to prevent entry of foreign material.
13.0 REFERENCE STANDARDS
EO-1042 ------------"Precast Concrete Conduit" EO-1063-------------"Preparation of Conduit for Cable Installation"
EO-1179 ------------"Couplings Used with Precast Concrete Conduits"
EO-1181 ------------"General Specification for Backfilling of Trench and Small Openings"
EO-4410-C ---------"Mandrel for Clearing Ducts"
EO-5571-B ----------"Typical Installation One, Two or Four Duct, Electric Subway with 2" to 12" Gas Main in Common Trench"
EO-7326-B ----------"Conduit Formations-4" and 5" I.D."
CONSTRUCTION STANDARDS EO-8007 REVISION 24 MANUAL NO.11 OCTOBER 2003
8
EO-7875-D ----------"Precast Concrete Duct with thick Male Ends" 13.0 REFERENCE SPECIFICATIONS (Cont'd)
EO-7907-D ----------"Trench Excavation for Precast Concrete Ducts"
EO-8085 ------------"General Backfill and Bedding Material for Excavation"
EO-9138-C ----------"Clamp for Precast Concrete Ducts"
EO-9489-C ----------"Precast Concrete Conduit Bends Thick Male Ends"
EO-9508-C ----------"Entrances and Recesses in Manhole, Distribution Box, and Vault Walls"
EO-9799-D ----------"Precast Concrete Conduit Bell End with Thick Male End
EO-10,864-D --------"Molded Plastic Plug for Conduit"
EO-16734-B ---------"Test Mandrel for 4 inch and 5 Inch Conduits"
EO-100,612 ---------"Purchase Recommendation for Stainless Steel Ties for Field Split
Precast Concrete Ducts"
CONSTRUCTION STANDARDS EO-8007 REVISION 24 MANUAL NO.11 OCTOBER 2003
9
14.0 ATTACHMENTS EO-9706-C ----------"Typical Arrangement of Precast Concrete Conduit Showing Permissible Offsets"
Edward A. Bertolini (Signature on File) Edward A. Bertolini Section Manager Distribution Substation and Equipment Distribution Engineering
R. Raebiger REVISION FILE Revised paragraph for allowable cable bends Construction Standards and paragraph for Loaded Duct. Revised Manual No. 3 – Section 37 document formatting. Field Manual No. 11 – Section 2 Field Manual No. 17 – Section 2
FILING INFORMATION: CONSTRUCTION STANDARDS, MANUAL 3, SECTION 1 Paper copies of procedures and instructions are uncontrolled and therefore may be outdated. Please consult Distribution Engineering Intranet Site Distribution Engineering or http://distribution, for the current version prior to use.
CONSOLIDATED EDISON COMPANY OF NEW YORK, INC.
4 IRVING PLACE NEW YORK, N.Y. 10003
DISTRIBUTION ENGINEERING DEPARTMENT STRUCTURES AND TOOLS
SPECIFICATION EO-8008 REVISION 2
NOVEMBER 2013
INSTALLATION OF FIBERGLASS UTILITY CONDUIT FOR UNDER BRIDGE APPLICATIONS
Specification Revision Rev. Date Effective Date Copyright Information Page 2 of 6 EO-8008 Rev 2 Nov 2013 November 22, 2013 © 2004-2013 Consolidated Edison Co. of New York, Inc. FILING INFORMATION: CONSTRUCTION STANDARDS, MANUAL 3, SECTION 1 Paper copies of procedures and instructions are uncontrolled and therefore may be outdated. Please consult Distribution Engineering Intranet Site Distribution Engineering or http://distribution, for the current version prior to use.
TABLE OF CONTENTS 1.0 SCOPE .................................................................................................................. 3 2.0 DISTRICTS APPLICABLE .................................................................................... 3 3.0 DEFINITIONS ........................................................................................................ 3 4.0 GENERAL REQUIREMENTS ............................................................................... 3 5.0 JOINT CONNECTIONS ........................................................................................ 4 6.0 ANCHOR/SUPPORT REQUIREMENTS ............................................................... 4 7.0 EXPANSION JOINT REQUIREMENTS ................................................................ 5 8.0 ABUTMENT PENETRATION REQUIREMENTS .................................................. 5
Specification Revision Rev. Date Effective Date Copyright Information Page 3 of 6 EO-8008 Rev 2 Nov 2013 November 22, 2013 © 2004-2013 Consolidated Edison Co. of New York, Inc. FILING INFORMATION: CONSTRUCTION STANDARDS, MANUAL 3, SECTION 1 Paper copies of procedures and instructions are uncontrolled and therefore may be outdated. Please consult Distribution Engineering Intranet Site Distribution Engineering or http://distribution, for the current version prior to use.
INSTALLATION OF FIBERGLASS UTILITY CONDUIT FOR UNDER BRIDGE APPLICATIONS
1.0 SCOPE
This specification applies to the installation of heavy wall and extra heavy wall fiberglass conduits to house primary, phase-grouped cables for under bridge applications.
2.0 DISTRICTS APPLICABLE
This specification is applicable to Consolidated Edison Company of New York, Inc.’s entire service area.
3.0 DEFINITIONS
• The term “Con Edison” as used in this specification refers to the Consolidated Edison Company of New York, Inc.
• The term “Con Edison Engineer” as used in this specification refers to the project engineer.
• The term “Con Edison Construction Representative” as used in this specification refers to the Construction Manager, Contract Construction Manager or their authorized representative
4.0 GENERAL REQUIREMENTS
Conduit used will meet or exceed the requirements within NEMA TC14, latest edition. These conduit types are approved for use, in sizes up to 6” nominal I.D.:
• Type HW Conduit - Heavy Wall • Type XW Conduit - Extra Heavy Wall (“Bullet Resistant”)
Type HW and Type XW conduit products from these manufactures are approved:
• Champion Fiberglass • United Fiberglass of America
Manufacturer’s recommended solvents/adhesives may be used after approval from Con Edison’s EH&S Department. A standard “grid” type under bridge conduit support system manufactured by United Fiberglass of America may be used. Similar custom “grid” designs are acceptable with a Con Edison Engineer’s review and approval.
Specification Revision Rev. Date Effective Date Copyright Information Page 4 of 6 EO-8008 Rev 2 Nov 2013 November 22, 2013 © 2004-2013 Consolidated Edison Co. of New York, Inc. FILING INFORMATION: CONSTRUCTION STANDARDS, MANUAL 3, SECTION 1 Paper copies of procedures and instructions are uncontrolled and therefore may be outdated. Please consult Distribution Engineering Intranet Site Distribution Engineering or http://distribution, for the current version prior to use.
Auxiliary support members and attachments to bridge structural members shall be reviewed and approved by a Con Edison Engineer. All new steel added to bridge shall be finished per Con Edison Specification CE-SS-3400-9900. Local municipal and DOT approval may be required for any new or modified supporting structures that will be attached to existing bridges or other public structures. Users are to secure necessary approvals prior to installation.
5.0 JOINT CONNECTIONS
Each length of conduit shall be supplied with an integral wound tapered bell on one end and a tapered spigot on the other end. All fittings, adapter, expansion joints, and bends shall be fabricated of the same filament wound material as the conduits. All joints shall use manufacturer approved adhesive and application procedures. Pullout strength of all joints shall meet or exceed the axial pull requirements of NEMA TC14, latest edition, “Joint Separation”.
6.0 ANCHOR/SUPPORT REQUIREMENTS
The span between supports shall comply with the conduit manufacturer’s loading specifications, based on the heaviest primary cable used within the Con Edison system. All supports are to be mounted to existing bridge structural members using galvanized fasteners (HDG per ASTM A123 or A153). Welding to bridge structural members is not permitted. The use of anchoring systems, such as concrete expansion bolts mounted to the underside of the bridge deck, is not permitted. The support configuration and bracing system shall be designed for appropriate dead loads, live loads, wind loads, and axial sliding friction loads from thermal expansion/contraction, and also due to cable pulling operation. Cable pulling loads shall be calculated as per EO-1090. Configurations of supports are to be selected as to minimize bending at the mounting hardware and interface with the bridge structural member. All support design configurations shall be submitted to Con Edison Engineer for review and approval.
Specification Revision Rev. Date Effective Date Copyright Information Page 5 of 6 EO-8008 Rev 2 Nov 2013 November 22, 2013 © 2004-2013 Consolidated Edison Co. of New York, Inc. FILING INFORMATION: CONSTRUCTION STANDARDS, MANUAL 3, SECTION 1 Paper copies of procedures and instructions are uncontrolled and therefore may be outdated. Please consult Distribution Engineering Intranet Site Distribution Engineering or http://distribution, for the current version prior to use.
7.0 EXPANSION JOINT REQUIREMENTS
For bridges with spans between 200 feet and 400 feet, two expansion joints are required. One located at the center of each half section of the bridge. For bridges with spans greater than 400 feet, expansion joints are to be placed at no more than 100 feet from each bridge abutment. Additional expansion joints shall be equally spaced at every 200 feet. Expansion joints shall be guided by supports on both sides of the expansion joint. The location for these supports shall not be more than six feet away from the center of the expansion joint and not less than one foot away from the expansion joint. Axial anchors (split stop rings) shall be used to guide the expansion/contraction of the conduits in the desired direction of movement. At time of installation, the male end shall be located at the mid-point of the expansion joint. At least four inches of the conduit shall be inside the expansion joint at the time of installation. A minimum stroke distance (i.e. remaining travel distance before expansion joint bottoms out) of 6 inch shall be maintained at time of installation. On conduit runs that are pitched, the orientation of the expansion joint assembly shall be installed in the direction that will minimize the potential for water infiltration from run-off that may flow outside along the conduit runs. Expansion joints and supports are to be braced to prevent large displacements at the time of the cable pull. Support configuration to be reviewed by Con Edison construction Representative prior to pulling of cables.
8.0 ABUTMENT PENETRATION REQUIREMENTS
The abutment penetration shall be constructed of steel conduits. Installation shall follow EO-8014. Steel conduits shall be spaced with a minimum of 2 inches of separation. The steel conduit penetration shall have a minimum clearance of 4 inches from rebar and structural steel. The installation of concrete ducts to the penetration shall follow EO-1042. The interface between the steel penetration and the fiberglass conduit shall use threaded connections. The finished joints are to be sealed.
Specification Revision Rev. Date Effective Date Copyright Information Page 6 of 6 EO-8008 Rev 2 Nov 2013 November 22, 2013 © 2004-2013 Consolidated Edison Co. of New York, Inc. FILING INFORMATION: CONSTRUCTION STANDARDS, MANUAL 3, SECTION 1 Paper copies of procedures and instructions are uncontrolled and therefore may be outdated. Please consult Distribution Engineering Intranet Site Distribution Engineering or http://distribution, for the current version prior to use.
Mohsen Shaaker (Signature on File) Mohsen Shaaker Manager Distribution Engineering
Alexander Chia
REVISION No. 2 Edited Sections 6.0 and 7.0.
FILE: CONSTRUCTION STANDARDS MANUAL 3, SECTION 1
Copyright Information ©1978-2011 Consolidated Edison Co. of New York, Inc.
Paper copies of procedures and instructions are uncontrolled and therefore may be outdated. Please consult Distribution Engineering Intranet Site Distribution Engineering or http://distribution for the current version prior to use.
Page1/18
CONSOLIDATED EDISON COMPANY OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY 10003
DISTRIBUTION ENGINEERING TOOLS AND STRUCTURES SPECIFICATION EO – 1008 REVISION 14
APRIL, 2011
EFFECTIVE DATE APRIL 18, 2011
PLAIN AND REINFORCED CONCRETE
FILE: PURCHASE AND TEST MANUAL NO. 6, SECTION 7
TARGET AUDIENCE DISTRIBUTION ENGINEERING
REGIONAL ENGINEERING
NESC REFERENCE SECTION 32
Specification Revision Rev Date Effective Date
Copyright Information Page 2/18
EO – 1008 Rev 14 April 2011 04/18/2011 ©2007-2011 Consolidated Edison Co. of New York, Inc. Filing Information Purchase and Test Manual No. 6 Section 7 Paper copies of procedures and instructions are uncontrolled and therefore may be outdated. Please consult Distribution Engineering Intranet Site Distribution Engineering or http://distribution, for the current version prior to use.
TABLE OF CONTENTS
1.0 PURPOSE ..................................................................................................................... 3 2.0 APPLICATION .............................................................................................................. 3 3.0 GENERAL REQUIRMENT ............................................................................................ 3
3.1 GENERAL WORK REQUIREMENT ................................................................... 3 3.2 ITEMS OF WORK .............................................................................................. 3 3.3 WORK BY OTHERS ........................................................................................... 3 3.4 REFERENCE SPECIFICATIONS ....................................................................... 3 3.5 QUALITY CONTROL .......................................................................................... 6 3.6 REJECTION OF CONCRETE ............................................................................ 7
4.0 MATERIAL AND PRODUCT SPECIFICATONS ........................................................... 7 4.1 GENERAL .......................................................................................................... 7 4.2 CEMENT ............................................................................................................ 8 4.3 AGGREGATES .................................................................................................. 8 4.4 WATER .............................................................................................................. 8 4.5 ADMIXTURES .................................................................................................... 8 4.6 STEEL REINFORCEMENT ................................................................................ 9 4.7 CLASSIFICATION OF CONCRETE ................................................................. 10 4.8 CURING MATERIALS ...................................................................................... 10 4.9 FORMS AND FORM-TIES ............................................................................... 11 4.10 FORM OIL (PARTING AGENT) ........................................................................ 11 4.11 CONCRETE PROPORTIONS AND CONSISTENCY ....................................... 12
5.0 CONCRETE MIXING, PLACING, CURING, TESTING ............................................... 13 5.1 MIXING CONCRETE ........................................................................................ 13 5.2 PREPARATION OF EQUIPMENT AND CONVEY, PLACE OF DEPOSIT ....... 13 5.3 CONCRETE TESTS ......................................................................................... 15 5.4 COLD WEATHER REQUIREMENTS ............................................................... 15 5.5 HOT WEATHER REQUIREMENTS ................................................................. 16 5.6 CONSOLIDATION ............................................................................................ 17 5.7 CONCRETE FINISHES .................................................................................... 17
6.0 RIGHT TO INSPECT AND IDENTIFY ALL CONCRETE WORK ................................ 17 7.0 DESIGN CHANGES MUST OBTAIN APPROVAL ...................................................... 17
Specification Revision Rev Date Effective Date
Copyright Information Page 3/18
EO – 1008 Rev 14 April 2011 04/18/2011 ©2007-2011 Consolidated Edison Co. of New York, Inc. Filing Information Purchase and Test Manual No. 6 Section 7 Paper copies of procedures and instructions are uncontrolled and therefore may be outdated. Please consult Distribution Engineering Intranet Site Distribution Engineering or http://distribution, for the current version prior to use.
1.0
This specification covers the furnishing of all labor, materials, equipment, tools, services and all other items necessary for the complete and approved installation of all precast, cast-in-place plain and reinforced concrete work, which includes ready mixed, job-site mixed, and plant-mixed concrete, as indicated on the contract drawings and/or specified herein.
PURPOSE
2.0
This specification applies to the Con Edison electrical distribution system. APPLICATION
3.0
GENERAL REQUIRMENT
3.1 Concrete shall consist of portland cement, fine and coarse aggregates, admixtures and clean water thoroughly mixed in quantities as specified by the latest edition and latest addenda of ACI, ASTM standards, Engineering Documents, NYC or local building codes, and the rules concerning safety & health from OSHA and EPA. Completed mix must obtain the required concrete strength as outlined in this specification.
General Work Requirement
3.2
The specific items of work are outlined in the "Project Specifications and Contract Drawings".
Items of Work
3.3 Work by Others
3.3.1 Controlled Inspection. 3.3.2 Inspection and Testing of Concrete.
3.4 Reference Specifications
The work covered by this specification shall conform to the latest edition and latest addenda thereto of the following standards and specifications:
3.4.1 ACI — American Concrete Institute
117 Standard Specifications for Tolerances for Concrete
Construction and Materials 237R Self-Consolidating Concrete 304R Guide for Measuring, Mixing, Transporting and Placing
Concrete
Specification Revision Rev Date Effective Date
Copyright Information Page 4/18
EO – 1008 Rev 14 April 2011 04/18/2011 ©2007-2011 Consolidated Edison Co. of New York, Inc. Filing Information Purchase and Test Manual No. 6 Section 7 Paper copies of procedures and instructions are uncontrolled and therefore may be outdated. Please consult Distribution Engineering Intranet Site Distribution Engineering or http://distribution, for the current version prior to use.
305R Hot Weather Concreting 306.1 Standard Specification for Cold Weather Concreting 306R Cold Weather Concreting 308R Guide to Curing Concrete 309R Guide for Consolidation of Concrete 318 Building Code Requirements for Reinforced Concrete
3.4.2 ASTM — American Society for Testing and Materials
A185 Standard Specification for Steel Welded Wire Reinforcement,
Plain, for Concrete A615 Standard Specification for Deformed and Plain Carbon Steel Bars for Concrete Reinforcement A775 Standard Specification for Epoxy-Coated Steel Reinforcing Bars C31 Standard Practice for Making and Curing Concrete Test
Specimens in the Field C33 Standard Specification for Concrete Aggregates C39 Standard Test Method for Compressive Strength of Cylindrical
Concrete Specimens C94 Standard Specification for Ready-Mixed Concrete C143 Standard Test Method for Slump of Hydraulic Cement
Concrete C150 Standard Specification for Portland Cement C172 Standard Practice for Sampling Freshly Mixed Concrete C260 Standard Specification for Air-Entraining Admixtures for
Concrete C309 Standard Specification for Liquid Membrane-Forming
Compounds for Curing Concrete
Specification Revision Rev Date Effective Date
Copyright Information Page 5/18
EO – 1008 Rev 14 April 2011 04/18/2011 ©2007-2011 Consolidated Edison Co. of New York, Inc. Filing Information Purchase and Test Manual No. 6 Section 7 Paper copies of procedures and instructions are uncontrolled and therefore may be outdated. Please consult Distribution Engineering Intranet Site Distribution Engineering or http://distribution, for the current version prior to use.
C494 Standard Specification for Chemical Admixtures for Concrete C618 Standard Specification for Coal Fly Ash and Raw or Calcined
Natural Pozzolan for Use in Concrete C989 Standard Specification for Granulated Blast-Furnace Slag for
Use in Concrete and Mortars C1602 Standard Specification for Mixing Water Used in the Production
of Hydraulic Cement Concrete
3.4.3 EO — Engineering Documents / Specifications
a EO-1125 — Specification for Field-Mixed Concrete in Small Batches. b EO-5228 — Specification for Fabrication of Precast Concrete
Distribution Structures. c EO-100167 — Purchase Recommendation for Packaged, Dry,
Combined Materials for Mortar and Concrete. d EO-1007 — Specification for Membrane Method of Waterproofing for
Electrical Distribution Structures. e EO-100285 — Purchase Recommendation for Plain and Reinforced
Concrete. f EO-100642 — Purchase Recommendation for Membrane
Waterproofing Systems for Electrical Distribution Structures. g EO-100271 — Purchase Recommendation for Rapid Setting Concrete
Dry Gravel Mix. 3.4.4 Approved Product List by EH&S
EH&S approved product list for use of admixtures in concrete. See CRS-Chemical Reporting System at https://intapps7.coned.com/crsv/webform1.aspx and EO-100285.
3.4.5 Building Codes
Building Codes of the City and State of New York including Westchester County and other Municipalities as applicable.
Specification Revision Rev Date Effective Date
Copyright Information Page 6/18
EO – 1008 Rev 14 April 2011 04/18/2011 ©2007-2011 Consolidated Edison Co. of New York, Inc. Filing Information Purchase and Test Manual No. 6 Section 7 Paper copies of procedures and instructions are uncontrolled and therefore may be outdated. Please consult Distribution Engineering Intranet Site Distribution Engineering or http://distribution, for the current version prior to use.
3.4.6 Occupational Safety and Health Administration (OSHA)
a 29 CFR 1910 — Occupational Safety and Health Standards. b 29 CFR 1926 — Safety and Health Regulations for Construction
3.4.7 New York City, DOT Requirements
Standard Highway Specifications, New York City Department of Transportation.
3.5 Quality Control
3.5.1 Concrete Strength Tests
a Minimum Strength All concrete shall have minimum 28 days strength as specified in the project specification and contract drawings, unless noted otherwise.
b Investigation of Low Strength Test Results,
If any strength test (see ACI 318-08, section 5.6.2.4 and 5.6.3) of laboratory-cured cylinders falls below fc’ by more than the value given in ACI 318-08, section 5.6.3.3. then tests and structural analysis shall be taken as per ACI 318-08, section 5.6.5 at the contractor’s expense.
3.5.2 Special Inspection and Concrete Testing
Concrete shall be controlled in accordance with the requirements of Building Codes of the City and State of New York including Westchester County and other local Municipalities, as well as NYC Buildings Bulletin 2009-026. Special inspection and concrete testing shall be performed by the special inspection agency and concrete testing laboratory accepted by New York City Building Department.
3.5.3 Frequency of Testing
Samples for strength tests of concrete placed for manholes or any other load bearing structures shall be taken once a day or one for each structural element. i.e. floor slab, wall and roof slab, respectively. At the time fresh concrete is sampled to fabricate specimens for strength tests, the slump and air content tests and temperature of concrete shall be performed.
Specification Revision Rev Date Effective Date
Copyright Information Page 7/18
EO – 1008 Rev 14 April 2011 04/18/2011 ©2007-2011 Consolidated Edison Co. of New York, Inc. Filing Information Purchase and Test Manual No. 6 Section 7 Paper copies of procedures and instructions are uncontrolled and therefore may be outdated. Please consult Distribution Engineering Intranet Site Distribution Engineering or http://distribution, for the current version prior to use.
3.5.4 Concrete Testing Laboratory All compressive strength tests of concrete, tests on cement, aggregates, slump and air content shall be done for Con Edison by an independent licensed concrete testing laboratory, see section 3.5.2.
3.5.5 Report Requirement
Special inspection agency, see section 3.5.2, shall keep records of inspections for a period of 6 years to conform to the provisions of sections BC 1704, BC 1903 and BC 1905 of the Building Codes of the State and City of New York and NYC Buildings Bulletin 2009-026. The agency shall submit to Con Edison Construction Management one hard copy and one electronic copy for them to keep in the project folder.
3.6 Rejection of Concrete
Final acceptance by Con Edison of all concrete work done by the contractor shall be predicated on meeting the job specific requirements, contract document and accepted ACI industry standards. The acceptance parameters include but are not limited to: compressive strength, mix design, slump, air entrainments, rebar placement and size. Additionally, the acceptance is contingent upon the finished condition of the concrete including general condition and no unacceptable evidence of honey combing, cracking, air bubbles or spalling. Con Edison reserves the right to assign an independent agency to conduct further investigation which may include nondestructive tests and strength tests of cores for those concrete strength tests that failed to meet specifications and any suspected defective concrete. If the results of subsequent physical testing or analytical modeling, stated in 3.5.1 to 3.5.4, reveals that the contactor placed concrete is defective and unacceptable, all costs for this investigative work shall be at the contractor’s expense and the concrete in dispute shall be removed, replaced and tested until the strength and quality meet the requirements in this specification, at the contractor’s expense.
4.0 MATERIAL AND PRODUCT SPECIFICATONS
4.1 General
4.1.1 Products and manufacturers listed in section 3.4.3 and 3.4.4 are all subject to compliance with the applicable codes and standard requirements.
Specification Revision Rev Date Effective Date
Copyright Information Page 8/18
EO – 1008 Rev 14 April 2011 04/18/2011 ©2007-2011 Consolidated Edison Co. of New York, Inc. Filing Information Purchase and Test Manual No. 6 Section 7 Paper copies of procedures and instructions are uncontrolled and therefore may be outdated. Please consult Distribution Engineering Intranet Site Distribution Engineering or http://distribution, for the current version prior to use.
4.2 Cement
4.2.1 Cement used in the concrete mix shall be Portland cement and shall conform to ASTM C150.
4.2.2 Cements of a special nature for specific purposes shall conform to the
specifications of latest edition of ASTM and ACI 318, and shall be submitted to Con Edison Construction Management (CM) for approval prior to the finalization of contract/construction drawings.
4.2.3 Neither fly ash nor slag is allowed to be used in concrete.
4.3 Aggregates
4.3.1 Fine aggregate shall be natural sand conforming to ASTM C33, Section
6.1 4.3.2 Coarse aggregate shall be crushed stone conforming to size number 67
in accordance with ASTM C33, Table 2, unless otherwise indicated.
4.3.3 Coarse aggregates for sidewalk slabs shall be grits which shall pass a sieve having 3/8 inch square openings and not less than 90% shall be retained on a No. 4 sieve.
4.4 Water Water used in mixing concrete shall conform to ASTM C1602.
4.5 Admixtures
4.5.1 Admixtures listed in EO-100285 shall be added to the concrete as
specified in contract drawings and/or the detailed project specification and strictly follow the manufacturer’s recommendations. Admixtures shall be added only through calibrated dispensing devices. Dispensers shall be inspected and certified as to accuracy by the manufacturer of the admixture. Descriptions of admixtures, and data indicating quantities intended for use, shall be submitted to Construction Management and Distribution Engineering Tools and Structures Engineer for approval.
4.5.2 An air-entraining admixture shall be added to the mix for all concrete.
Air-entraining admixtures shall conform to ASTM C260. Air-entraining admixtures shall be added to the concrete mixtures immediately before or during mixing.
Specification Revision Rev Date Effective Date
Copyright Information Page 9/18
EO – 1008 Rev 14 April 2011 04/18/2011 ©2007-2011 Consolidated Edison Co. of New York, Inc. Filing Information Purchase and Test Manual No. 6 Section 7 Paper copies of procedures and instructions are uncontrolled and therefore may be outdated. Please consult Distribution Engineering Intranet Site Distribution Engineering or http://distribution, for the current version prior to use.
4.6 Steel Reinforcement
4.6.1 All reinforcement and accessories shall be free of loose rust, loose
scale, grease, oil, and other coatings or foreign substances that would reduce the bonding qualities.
4.6.2 Bars
a Bar reinforcement, sizes No. 3 through No. 8 inclusive, shall be deformed, new billet steel bars conforming to ASTM A615, Grade 60, as indicated on the applicable drawings. Reinforcing bars shall be epoxy coated for all underground and wet structures in accordance with ASTM A775. Epoxy coating damaged as a result of handling or cutting of reinforcing bars shall be field coated with epoxy patching material conforming to ASTM A775.
b Each bar shall be branded in the deforming process to identify the
manufacturer, size, type and grade of steel. 4.6.3 Welded Wire Fabric
Welded wire fabric shall be epoxy-coated in accordance with ASTM A884. The size or sizes indicated on the drawings, shall conform to ASTM A185. Epoxy coating damaged as a result of handling or cutting of fabric members shall be field coated with epoxy patching material conforming to ASTM A775.
4.6.4 Tie Wire
Tie wire for securing reinforcement in place shall be 16 gauge or heavier, black annealed plastic-coated wire.
4.6.5 Bar Supports
a Bar supports shall be standardized and non-corrosive wire bar
supports conforming to the material specifications of the Manual of Standard Practice of the CRSI and contract drawings. Bar supports shall be sufficient in number and strength to properly carry the reinforcing bars and normal construction loads supported thereon.
b Precast concrete blocks, plain or provided with embedded coated tie
wires, and dowel blocks, conforming to the Manual of Standard Practice of the CRSI shall be used to support bars in footings and slabs on ground.
Specification Revision Rev Date Effective Date
Copyright Information Page 10/18
EO – 1008 Rev 14 April 2011 04/18/2011 ©2007-2011 Consolidated Edison Co. of New York, Inc. Filing Information Purchase and Test Manual No. 6 Section 7 Paper copies of procedures and instructions are uncontrolled and therefore may be outdated. Please consult Distribution Engineering Intranet Site Distribution Engineering or http://distribution, for the current version prior to use.
4.7 Classification of Concrete
4.7.1 Concrete shall be furnished in accordance with the following Consolidated Edison (Con Edison) classifications:
Con Edison Company
Classification Type of Structures
Min. 28-Day Compression Strength, Psi
Class I
Watertight Structures:
Cast-in-Place, Precast and Self Consolidated Concrete (SCC) or Special Structures
5,000
Class II
Non- Watertight Structures
4,500
Others
Duct Banks, Sidewalks and
General Use
3,500
4.8 Curing Materials
4.8.1 Waterproof paper for curing concrete shall conform to ASTM C171. 4.8.2 Membrane forming compounds for curing concrete shall conform to
ASTM C309. 4.8.3 Polyethylene sheet used for curing concrete shall conform to the
moisture retention requirements of ASTM C171. Polyethylene sheet shall be free of visible defects, uniform in appearance, and not less than 0.004 inches thick.
4.8.4 Polyethylene-coated waterproof paper for curing concrete shall conform
to the moisture retention requirements of ASTM C171. The polyethylene coating shall have a minimum thickness of 0.002 inches, and shall be permanently bonded to the waterproof paper.
Specification Revision Rev Date Effective Date
Copyright Information Page 11/18
EO – 1008 Rev 14 April 2011 04/18/2011 ©2007-2011 Consolidated Edison Co. of New York, Inc. Filing Information Purchase and Test Manual No. 6 Section 7 Paper copies of procedures and instructions are uncontrolled and therefore may be outdated. Please consult Distribution Engineering Intranet Site Distribution Engineering or http://distribution, for the current version prior to use.
4.9 Forms and Form-Ties
4.9.1 For underground construction that requires Class I or II concrete structure with watertight treatment, fiberglass form tie system made by RJD Industrial, INC. or approved equal shall be used. No timber or wood forms shall be constructed. No other form tie or snap tie is allowed for watertight concrete construction.
4.9.2 For above ground construction that requires Class I or II non-watertight
concrete structure, steel, timber or wood forms may be constructed. Metal forms shall conform to ACI 347 and Section BC 1906 of the Building Code of the City of New York or other local municipal building codes. The materials used shall produce or facilitate obtaining the specified surface finish of the concrete.
4.9.3 All form ties shall have removable or snap-off ends and shall be fixed or
adjustable in length. The portion of the tie remaining in the concrete after the removal of the exterior parts shall not project beyond the surface of the concrete and shall be at least one inch back from any surface that will be exposed to view. Plug both ends of the form tie opening with non-shrink cement grout with minimum thickness of one inch.
4.9.4 Unexposed Concrete Surfaces No. 2 common or better lumber, or any material specified for exposed surfaces shall be used.
4.9.5 Exposed Concrete Surfaces Plywood or metal forms in accordance with the following requirements shall be used:
a Plywood shall be APA Structural I Plyform, mill-oiled not less than 5-
ply and at least 1/2 inch thick.
b Metal used for forms shall comply with the American Iron and Steel Institute requirements for light gauge, cold-formed steel. Metal forms shall produce surfaces equal to those provided by wood forms.
4.10 Form Oil (Parting Agent)
4.10.1 A colorless mineral oil, free of kerosene shall be used. Flash point shall be not less than 300oF, determined in accordance with ASTM D 92. Freezing point shall be less than -20°F.
Specification Revision Rev Date Effective Date
Copyright Information Page 12/18
EO – 1008 Rev 14 April 2011 04/18/2011 ©2007-2011 Consolidated Edison Co. of New York, Inc. Filing Information Purchase and Test Manual No. 6 Section 7 Paper copies of procedures and instructions are uncontrolled and therefore may be outdated. Please consult Distribution Engineering Intranet Site Distribution Engineering or http://distribution, for the current version prior to use.
4.10.2 The Contractor shall verify with the admixture manufacturer that the form oil used is compatible with the admixtures included in the concrete mix. The Contractor shall notify the Construction Management in writing that such verification has been made.
4.10.3 Avoid dropping oil on the reinforcement bars or any exposed concrete
surface.
4.11 Concrete Proportions and Consistency
4.11.1 Concrete material shall be mixed in such proportions as to achieve the specified compressive strength at the age of twenty-eight days. The contractor shall be responsible for the proper concrete design mix in accordance with sections 4.1 to 4.5.
4.11.2 Concrete mix proportioning shall produce concrete with slump and air content designed to minimize bleeding and segregation.
4.11.3 Slump for all concrete that does not contain a super-plasticizer
admixture shall be a minimum of 4 inches and a maximum of 6 inches unless noted otherwise.
4.11.4 Unless noted otherwise, normal weight concrete structure for vaults and
manholes subject to freezing- and-thawing exposures shall be assigned to Exposure Class F2 (severe exposure) of ACI 318-08 and air-entrained with air content of (6 +/- 1.5) %.
4.11.5 The water / cement ratio for concrete subject to special exposure
conditions shall meet the requirements of section BC 1904 of the New York City Building Code or other applicable municipal local codes.
4.11.6 If the contractor intends to use self-consolidating concrete, (SCC),
polyarboxylate based high-range water-reducer (HRWA) shall be used and meet the requirements of ASTM C-494/C, Type F or G and ACI 237. The contractor shall submit the design concrete mix with the admixture to Construction Management and Distribution Engineering Tools and Structures Engineer for review and comments prior to placing the order of SCC.
Specification Revision Rev Date Effective Date
Copyright Information Page 13/18
EO – 1008 Rev 14 April 2011 04/18/2011 ©2007-2011 Consolidated Edison Co. of New York, Inc. Filing Information Purchase and Test Manual No. 6 Section 7 Paper copies of procedures and instructions are uncontrolled and therefore may be outdated. Please consult Distribution Engineering Intranet Site Distribution Engineering or http://distribution, for the current version prior to use.
4.11.7 The slump of the concrete shall remain the same throughout the period required to unload the truck or mixer. Discharge of the contents shall be completed within 1-1/2 hours, after the introduction of mixing water to the cement and aggregates or the introduction of cement to the aggregates. During hot weather, when the temperature is above 80°F., the time limit shall be reduced to 45 minutes.
4.11.8 For all concrete, air-entrainment shall be accomplished by adding an
air-entraining agent to the mix, in accordance with paragraph 4.5. 4.11.9 The source of supply for the fine or coarse aggregate shall not be
changed during the course of the job. If the contractor wishes to change the source of supply for aggregates, the contractor must submit redesign concrete mix using the new source supply to Construction Management and Distribution Engineering Tools and Structures Engineer for review and approval.
4.11.10 The Contractor shall submit design mix to Construction Management
and Distribution Engineering Tools and Structures Engineer for review and acceptance, a minimum of three weeks prior to the concrete mix being used for this project. The mixes as specified and filed with Construction Management shall not be adjusted except as specified herein, without the approval of the Construction Management and Distribution Engineering Tools and Structures Engineer. The Contractor shall submit to the Con Edison Construction Representative 2 copies of the concrete mix as accepted by Construction Management.
5.0 CONCRETE MIXING, PLACING, CURING, TESTING
5.1 Mixing Concrete
5.1.1 All concrete shall be mixed thoroughly and uniformly in accordance with ACI 318 section 5.8.
5.1.2 After mixing of materials has been completed, the use of additional
water to make the mixture more workable will not be allowed. Concrete that has attained initial set shall not be placed, nor shall it be retempered or re-mixed in any way for use.
5.2 Preparation of Equipment and Convey, Place of Deposit
5.2.1 Preparation of equipment and place of deposit of concrete shall be done in accordance with ACI 304R and ACI 318 section 5.9 and 5.10.
Specification Revision Rev Date Effective Date
Copyright Information Page 14/18
EO – 1008 Rev 14 April 2011 04/18/2011 ©2007-2011 Consolidated Edison Co. of New York, Inc. Filing Information Purchase and Test Manual No. 6 Section 7 Paper copies of procedures and instructions are uncontrolled and therefore may be outdated. Please consult Distribution Engineering Intranet Site Distribution Engineering or http://distribution, for the current version prior to use.
5.2.2 Concrete shall not be placed until all reinforcement and embedded
items, including pipes, conduits, frames, cut-outs, recess and shelf angles, anchor bolts, inserts, sleeves and other items that are called for on the drawings to be placed in the concrete, have been set in position.
5.2.3 The Construction Management Inspector shall timely arrange for the
special inspection agency to inspect formwork for rigidity of supports, and reinforcing for correct placement and alignment. The special inspection agency will file with the Construction Management attestation that this inspection has been made.
5.2.4 Concrete shall not be allowed to drop freely more than 5 feet and shall
be deposited in forms in a manner to avoid inclined construction joints. 5.2.5 When a continuous pour of concrete is being made, deliveries of mixed
concrete shall be made at the place of deposit at intervals not exceeding one-half hour. Concrete shall be deposited continuously, or in layers of such thickness that no concrete will be deposited on concrete which has hardened sufficiently to cause the formation of seams or planes of weakness within the section.
5.2.6 Tops of rough slabs shall be brought to the level indicated on the
drawings within a tolerance of plus or minus 1/4 inch.
5.2.7 All concrete shall be thoroughly compacted in accordance with section 5.6, immediately after placing, and shall be thoroughly worked around the reinforcement, embedded fixtures, and into the corners of the forms.
5.2.8 Chute Placement
a Concrete may be conveyed by approved chutes. The chute shall be
metal or metal-lined wood with sections set at approximately the same slope to assure a continuous uniform flow throughout the length of the chute without segregation or loss of the materials.
b Aluminum shall not be used for construction of metal chutes or for
lining of wooden chutes. c The chute shall be thoroughly cleaned before and after each run.
Waste material and flushing water shall be discharged outside the forms.
Specification Revision Rev Date Effective Date
Copyright Information Page 15/18
EO – 1008 Rev 14 April 2011 04/18/2011 ©2007-2011 Consolidated Edison Co. of New York, Inc. Filing Information Purchase and Test Manual No. 6 Section 7 Paper copies of procedures and instructions are uncontrolled and therefore may be outdated. Please consult Distribution Engineering Intranet Site Distribution Engineering or http://distribution, for the current version prior to use.
5.2.9 Pump Placement
a Pump placement of concrete shall be in accordance with ACI 304.2R, Placing Concrete by Pumping Methods.
b Where it is proposed by the Contractor to convey or place concrete
by pumping, a description of the proposed pumping system, equipment, and procedures to be used shall be submitted by the Contractor, for information only, to the Con Edison Construction Management include output of system in cubic yards per hour, and pump range in feet, horizontally and vertically.
c In addition, the concrete mix shall contain a super-plasticizer
admixture with air-entraining agent providing air content stated in section 4.11.4. Mix shall have adequate lubricating characteristics, including low mix-to-line-surface friction and low internal friction within the mix. Adjustments in mix design necessary to ensure efficiency of operation, including satisfactory pumping rates with smooth even flow shall be made by the Contractor at his expense and at no additional cost to Con Edison.
d Aluminum pipelines shall not be used when placing concrete by
pumping.
5.3 Concrete Tests 5.3.1 Construction Management shall coordinate and arrange for the
Concrete Testing Laboratory described in section 3.5, to perform all required tests including slump and compression tests to determine the strength classifications of the adjusted design mixes.
5.3.2 During construction, test samples of the concrete mix shall be taken at the hose discharge point by the Testing Laboratory Representative. Test samples used to determine slump and strength requirements shall be taken at the receiving hopper of the pump.
5.4 Cold Weather Requirements
5.4.1 Adequate equipment shall be provided for heating the concrete materials and protecting the concrete during freezing or near freezing weather. The contractor shall conform to the cold weather requirements of ACI 318-08, section 5.12, ACI 306R and ACI 306.1 unless otherwise designated.
Specification Revision Rev Date Effective Date
Copyright Information Page 16/18
EO – 1008 Rev 14 April 2011 04/18/2011 ©2007-2011 Consolidated Edison Co. of New York, Inc. Filing Information Purchase and Test Manual No. 6 Section 7 Paper copies of procedures and instructions are uncontrolled and therefore may be outdated. Please consult Distribution Engineering Intranet Site Distribution Engineering or http://distribution, for the current version prior to use.
5.4.2 If at any time during the progress of the work the surrounding air
temperature is 40°F or less, or within 24 hours is expected to drop that low, the water, the aggregate or both should be heated so that the temperature of the concrete when placed is not less than 50°F nor more than 70°F.
5.4.3 Concrete shall not be placed when the outside temperature is below 32°
F, unless the work is protected and heat is supplied to raise the ambient temperature to 50° F. During cold weather, the surface of freshly poured concrete shall be suitably protected to prevent the surface from dropping below 50 °F for a period of seven days for normal Portland cement concrete, and for a period of three days for high-early strength cement concrete.
5.4.4 In no event shall concrete be deposited on a frozen subgrade, nor shall
frozen materials be used in the concrete. Salt, chemicals, or other foreign materials shall not be mixed with the concrete to prevent freezing or to accelerate its setting. Any concrete damaged by freezing shall be removed and replaced at the expense of the Contractor.
5.5 Hot Weather Requirements
5.5.1 Whenever the temperature of the surrounding air exceeds 85°F, freshly poured concrete shall be protected to prevent rapid drying and to avoid high temperatures. The Contractor shall conform to the requirements of ACI 305R and ACI 318-08 section 5.13.
5.5.2 Newly placed concrete shall be maintained at a surface temperature not
exceeding 75°F during the curing period. 5.5.3 Any concrete damaged by accelerated evaporation shall be removed
and replaced at the expense of the Contractor. 5.5.4 When the ambient temperature exceeds 65°F, a retarding admixture, as
specified in section 4.5 Admixtures, shall be added to the 5000-psi concrete mix.
Specification Revision Rev Date Effective Date
Copyright Information Page 17/18
EO – 1008 Rev 14 April 2011 04/18/2011 ©2007-2011 Consolidated Edison Co. of New York, Inc. Filing Information Purchase and Test Manual No. 6 Section 7 Paper copies of procedures and instructions are uncontrolled and therefore may be outdated. Please consult Distribution Engineering Intranet Site Distribution Engineering or http://distribution, for the current version prior to use.
5.6 Consolidation Procedures for consolidation of concrete shall comply with the requirements of ACI 309R. Concrete shall be placed in layers not over 18 inches deep. Each layer shall be consolidated by mechanical internal-vibrating equipment supplemented by hand spading, rodding and tamping as required. Vibrators shall not be used to transport concrete inside forms. Duration of vibration shall be limited to time necessary to produce satisfactory consolidation without causing objectionable segregation. The vibrator shall not be inserted into lower courses that have begun to set.
5.7 Concrete Finishes
Immediately after removal of the forms all fines and loose material shall be removed; honeycombs, voids and holes over 1/2 inch in diameter shall be cut out to solid concrete, thoroughly wetted, brush-coated with neat cement grout, and filled with cement mortar composed of 1 part Portland cement to 2 parts fine aggregate. Mortar shall be finished flush and in the same plane as adjacent surfaces. Undersides of floor slabs and other exposed surfaces of concrete need not be rubbed free of form marks, unless otherwise designated on the drawings.
6.0 RIGHT TO INSPECT AND IDENTIFY ALL CONCRETE WORK
Con Edison reserve the right to inspect and identify all concrete work at the mixing plant and job site, whether field-poured or precast concrete.
7.0 DESIGN CHANGES MUST OBTAIN APPROVAL If there are proposed changes to the design, such changes shall be submitted to Construction Management and Distribution Engineering Tools and Structures Engineer for approval prior to fabrication / construction.
Specification Revision Rev Date Effective Date
Copyright Information Page 18/18
EO – 1008 Rev 14 April 2011 04/18/2011 ©2007-2011 Consolidated Edison Co. of New York, Inc. Filing Information Purchase and Test Manual No. 6 Section 7 Paper copies of procedures and instructions are uncontrolled and therefore may be outdated. Please consult Distribution Engineering Intranet Site Distribution Engineering or http://distribution, for the current version prior to use.
Joseph R. Martin (Signature on File) Joseph R. Martin Manager Tools & Structures Distribution Engineering Jason Liu, P.E. REVISON No. 14 1) Section 1.0 adds precast. Section 3.4.4, removes fly ash / slag and add admixture. 2) Section 3.4.7, deletes ERA requirements and add NYC-DOT codes. Modify section 3.5.2 and 3.5.5. 3) Add 3.4.3 and 3.4.4 in section 4.1.1 and omit section 4.1.2. 4) Add section 4.2.3, No fly ash / slag is allowed. 5) Section 4.5 and 4.11, add Distribution Engineering Tools and Structures Engineer. Revise section 4.5.1, 4.6.2, 4.6.3, 4.6.5. 4.11.1, 4.11.4 and omit section 4.5.3 6) Renumber 4.9.4 and 4.9.5 7) Revise section 4.7.1. Add type of structures for all concrete and revise the concrete strength for Class II and others to meet requirements of ACI 318-08 and NYC-Building Code. 8) Section 4.11.6 adds ACI 237. 9) Add sections 5.0, 6.0 and 7.0
FILE: Purchase and Test Manual No. 6, Section 7
Due for review / revision: 5/2016
Copyright Information 1999-2014 Consolidated Edison Co. of New York, Inc.
Paper copies of procedures and instructions are uncontrolled and therefore may be outdated. Please consult Distribution Engineering Intranet Site Distribution Engineering or http://distribution for the current version prior to use.
Page 1/8
CONSOLIDATED EDISON COMPANY OF NEW YORK, INC.
4 IRVING PLACE NEW YORK, NY 10003
DISTRIBUTION ENGINEERING TOOLS & STRUCTURES
SPECIFICATION EO-1042 REVISION 19
September 2014 EFFECTIVE DATE
October 24, 2014
PRECAST CONCRETE CONDUIT
FILE: PURCHASE AND TEST MANUAL NO. 6
TARGET AUDIENCE
NESC REFERENCE
Specification Revision Rev Date Effective
Date Copyright Information Page
2/8 EO – 1042 19 10/ 2014 10/24/2014 1999-2014 Consolidated Edison Co. of New York,
Inc. Filing Information Purchase and Test Manual No. 6 Paper copies of procedures and instructions are uncontrolled and therefore may be outdated. Please consult Distribution Engineering Intranet Site Distribution Engineering or http://distribution, for the current version prior to use.
TABLE OF CONTENTS 1.0 PURPOSE ............................................................................................................ 3
2.0 APPLICATION ..................................................................................................... 3
3.0 REFERENCES ..................................................................................................... 3
3.1 Standards ................................................................................................... 3 3.2 EO Specifications ...................................................................................... 3
4.0 GENERAL ............................................................................................................ 3
5.0 REQUIREMENTS ................................................................................................. 4
5.1 Materials ..................................................................................................... 4 5.2 Design......................................................................................................... 4 5.3 Manufacture ............................................................................................... 5 5.4 Inspection ................................................................................................... 5 5.5 Testing of Conduit ..................................................................................... 5 5.6 Acceptance ................................................................................................ 7 5.7 Identification .............................................................................................. 7
Specification Revision Rev Date Effective
Date Copyright Information Page
3/8 EO – 1042 19 10/ 2014 10/24/2014 1999-2014 Consolidated Edison Co. of New York,
Inc. Filing Information Purchase and Test Manual No. 6 Paper copies of procedures and instructions are uncontrolled and therefore may be outdated. Please consult Distribution Engineering Intranet Site Distribution Engineering or http://distribution, for the current version prior to use.
1.0 PURPOSE This specification covers precast concrete conduit used for housing electric cable.
2.0 APPLICATION The specification applies to all Con Edison districts.
3.0 REFERENCES
3.1 Standards ASTM C150 – Standard Specification for Portland Cement ASTM C33 – Standard Specification for Concrete Aggregates ASTM C94 – Standard Specification for Ready Mixed Concrete ASTM C1602 – Standard Specification for Mixing Water Used in the
Production of Hydraulic Cement Concrete
3.2 EO Specifications EO-1179 – Couplings Used With Precast Conduit EO-8007 – Installation of Precast Concrete Conduit EO-4410-C – Mandrel for Clearing Ducts EO-6130-C – Flared Conduit for Primary Cable Manhole Entrance EO-7875-D – Precast Concrete Conduit with Thick Male Ends EO-9138-C – Clamp for Precast Concrete Conduit Scored Types EO-9489-C – Precast Concrete Conduit Bends Thick Male Ends EO-9490-D – Plastic Coupling for Precast Concrete Conduit EO-9799-D – Precast Concrete Conduit Bell End with Thick Male End EO-9947-D – Adapter Type 4H-4K, 5H-5K or 6H-6K to Receive Plastic
Coupling and 4”, 5” or 6” Korduct, Steel, or Fiber Conduit EO-9962-D – Adapter Type 5H-4K, 4H-3 ½K, 4H-3K, 4H-2K to Receive
Plastic Coupling and 4”, 3 ½“, 3”, and 2” Korduct, Steel, or Fiber Conduit
EO-11048-D – Adapter Type 4H-4LM; 5H-5LM to Receive Plastic Coupling and 4” or 5” Light Male End Precast Concrete Conduit
EO-11049-D – Adapter Type 4H-4F; 5H-5F to Receive Plastic Coupling and 4” or 5” Female End Precast Concrete Conduit
4.0 GENERAL This specification covers the materials, design, manufacture, testing, inspection, acceptance, and identification of straight and bend sections of precast concrete conduits and adapters.
Specification Revision Rev Date Effective
Date Copyright Information Page
4/8 EO – 1042 19 10/ 2014 10/24/2014 1999-2014 Consolidated Edison Co. of New York,
Inc. Filing Information Purchase and Test Manual No. 6 Paper copies of procedures and instructions are uncontrolled and therefore may be outdated. Please consult Distribution Engineering Intranet Site Distribution Engineering or http://distribution, for the current version prior to use.
5.0 REQUIREMENTS
5.1 Materials 5.1.1 Cement
The cement used shall be Portland Cement. It shall conform to the requirements of ASTM C150, Standard Specification for Portland Cement.
5.1.2 Aggregates Aggregates shall conform to the requirements of ASTM C33, Standard Specification for Concrete Aggregates.
5.1.3 Water The water used in mixing mortar or concrete shall conform to the requirements of ASTM C1602, Standard Specification for Mixing Water Used in the Production of Hydraulic Cement Concrete.
5.1.4 Admixtures No hardening or curing agent shall be used in manufacturing of the conduits and adapters.
5.2 Design 5.2.1 Straight Sections
The conduit shall have of a square external cross-section, a smooth, concentric bore, and dimensions as specified on Drawing EO-7875-D. The longitudinal dimension of the conduit shall be straight and measured along the body of the conduit inclusive of the male ends.
5.2.2 Bends The conduit along its entire length shall have smooth concentric bore, square external cross-section, and dimensions as specified on Drawing EO-9489-C. Dimensions of the conduit bend shall be determined by its radius and central angle.
5.2.3 Adapters Adapters along their entire length shall have a smooth concentric bore, square external cross-section, and dimensions as specified on Drawings EO-9947-D, EO-9962-D, EO-11048-D, and EO-11049-D. They shall be measured along the body of the conduit inclusive of the male ends.
5.2.4 Bell-End Conduit The conduit along its entire length shall have a smooth concentric bore,
Specification Revision Rev Date Effective
Date Copyright Information Page
5/8 EO – 1042 19 10/ 2014 10/24/2014 1999-2014 Consolidated Edison Co. of New York,
Inc. Filing Information Purchase and Test Manual No. 6 Paper copies of procedures and instructions are uncontrolled and therefore may be outdated. Please consult Distribution Engineering Intranet Site Distribution Engineering or http://distribution, for the current version prior to use.
square external cross-section, and dimensions as specified on EO-9799-D. The longitudinal dimension of the conduit shall be straight and measured along the body of the conduit inclusive of the male end. Bell-end conduit shall be furnished for use at manhole entrances. The bell-end shall be installed flush with the inside face of the manhole.
5.2.5 Method of Joining Conduits shall have heavy male-ends which mate with a plastic coupling as indicated on EO-9490-D. They shall be joined with a force fit having sufficient pressure to prevent foreign matter from entering the conduit.
5.3 Manufacture 5.3.1 The conduits, bends, and adapters shall be made to meet the inspection and
test requirements outlined in this specification. The conduits, bends, and adapters shall be air-cured for a 28-day period before delivery. Steam curing may be used upon specific approval by the Distribution Structures Engineer.
5.3.2 Conduit bends and adapters made in a form shall be vibrated during
manufacture so as to produce a dense and smooth product with optimum strength.
5.3.3 The mix shall have low water content in order to produce a no-slump
concrete mortar.
5.4 Inspection 5.4.1 All conduits and adapters shall be free from cracks, broken ends, defects, or
irregularities. The inner surface shall be smooth and free from burrs, blisters, loose sand, or concrete. The finished product shall be free of foreign matter and conform to the dimensions and tolerances shown on the appropriate drawings.
5.4.2 All conduits are subject to inspection at the factory, Company yard, trench, or
other points of delivery by an inspector employed by Con Edison. Conduits that do not conform to this Specification shall be rejected in their entirety.
5.5 Testing of Conduit 5.5.1 Purpose
Con Edison reserves the right to test any or all conduits and adapters for the purpose of determining compliance with this specification.
Specification Revision Rev Date Effective
Date Copyright Information Page
6/8 EO – 1042 19 10/ 2014 10/24/2014 1999-2014 Consolidated Edison Co. of New York,
Inc. Filing Information Purchase and Test Manual No. 6 Paper copies of procedures and instructions are uncontrolled and therefore may be outdated. Please consult Distribution Engineering Intranet Site Distribution Engineering or http://distribution, for the current version prior to use.
5.5.2 Restrictions Specimens that have been used in any one of the strength tests shall not be used for any other test.
5.5.3 Mandrel Test A flexible steel mandrel as shown on Drawing EO-4410-C and of a diameter ¼” less than the nominal bore diameter shall pass freely through each section of the conduit.
5.5.4 Transverse Loading for Straight Sections The 4’ long test specimen shall be placed on two hardwood supports, 2” square by 6” long, placed 42” apart, center to center. The load shall be applied, midway between the supports, on a hardwood bearing block 2” wide 6” long and 1” thick, placed across the conduit. The speed of the cross head of the test machine shall be between 0.06 and 0.08 inches per minute. The minimum breaking load shall be 2,500 pounds for 4” conduit, 3,500 pounds for 5” conduit, and 5,300 pounds for 6” conduits. The Company reserves the right to also test 2’ long straight sections.
5.5.5 Transverse Loading for Bend Sections Conduit bends, 2’ long with 5’, 10’ or 20’ radius shall be placed on supports consisting of 1” diameter rollers, 6” long, located 21” center to center. The load shall be applied on the crown of the duct midway between the supports on a 2” flat plate 6” long, placed across the conduit. The speed of the cross head of the test machine shall be between 0.03 and 0.04 inches per minute. The test breaking load shall exceed 4,800 pounds for 4” conduit, 6,000 pounds for 5” conduits, and 7,200 pounds for 6”conduits.
5.5.6 Compression (Load Crushing) Test The specimen for the compression or load crushing test shall have a nominal length of 12”. Its faces shall be smooth and level with no surface irregularities. The specimen shall then be tested between two flat hardwood blocks in a standard testing machine. The wood blocks shall be 2” thick and the contact surfaces approximately ¼” longer than the surface dimensions of the specimen. If the bottom and top surfaces of the specimen are not smooth and level, then they must be capped parallel with hydrostone or equal to allow for a uniform spread of the test load. The speed of the cross head of the test machine shall be between 0.03 and 0.04 inches per minute. The load shall be increased until the specimen fractures or a drop in load is indicated on the test machine. The breaking load shall exceed 4,800 pounds for 4” conduit, 6,000 pounds for 5” conduit, and 7,200 pounds for 6”conduit sections. The Company reserves the right to also test 2’ and 4’ long conduit
Specification Revision Rev Date Effective
Date Copyright Information Page
7/8 EO – 1042 19 10/ 2014 10/24/2014 1999-2014 Consolidated Edison Co. of New York,
Inc. Filing Information Purchase and Test Manual No. 6 Paper copies of procedures and instructions are uncontrolled and therefore may be outdated. Please consult Distribution Engineering Intranet Site Distribution Engineering or http://distribution, for the current version prior to use.
sections.
5.5.7 Friction Test The test specimen shall be a 4’ straight section placed in a horizontal position. The test shall be performed by measuring the tension required to keep a 2-¼“ standard steel pipe, 2-7/8” O.D., 12” long moving through the conduit at approximately 1 foot per second. The steel pipe shall be uniformly weighted and the edges shall be rounded. The formula for calculation of the coefficient of friction is as follows: F = T/W F = Dry Sliding Coefficient of Friction W= Weight of the Steel Pipe (pounds) T = Force to Move the Steel Pipe (pounds) For this test, two 4’ sections will be selected at random and four tests shall be made with the duct on each of the four sides. A dry sliding coefficient of friction less than 0.4 is required.
5.6 Acceptance Con Edison accepts only conduits which fully meet the requirements of this Specification. A more than 2% failure of a conduit shipment in meeting the requirements of this specification will result in rejection of the entire shipment. All rejected conduits shall be unmistakably identified, removed, and replaced with conduits which meet the requirements of this Specification.
5.7 Identification 5.7.1 Straight Sections
Straight conduits shall be marked with the name of manufacturer and the year of manufacture.
5.7.2 Bend Sections Bends shall be marked with the name of the manufacturer and the type in accordance with Drawing EO-9489-C, latest revision.
5.7.3 Adapters Adapters shall be marked with the name of the manufacturer and the adapter type using ink with font size not less than 2” height to identify each adapter as following:
Specification Revision Rev Date Effective
Date Copyright Information Page
8/8 EO – 1042 19 10/ 2014 10/24/2014 1999-2014 Consolidated Edison Co. of New York,
Inc. Filing Information Purchase and Test Manual No. 6 Paper copies of procedures and instructions are uncontrolled and therefore may be outdated. Please consult Distribution Engineering Intranet Site Distribution Engineering or http://distribution, for the current version prior to use.
Markings Drawing No. Title 4H-4K, 5H-5K, 6H-6K EO-9947-D Adapter Type 4H-4K,5H-5K or 6H-6K to
Receive Plastic Coupling and 4”, 5” or 6” Korduct, Steel, Fiber, FRP, or Sched.40 PVC Conduit
4H-3 ½ K, 4H-3K, 4H-2K, 5H-4K
EO-9962-D Adapter Type 4H-3 ½ K or 4H-3K or 4H-2K or 5H-4K to Receive Plastic Coupling and 4”, 3 ½ “, 3”, and 2” Korduct, Steel, Fiber, FRP, or Sched.40 PVC Conduit
4H-4LM, 5H-5LM EO-11048-D Adapter Type 4H-4LM; 5H-5LM to Receive Plastic Coupling and 4” or 5” Light Male End Precast Concrete Conduit
4H-4F, 5H-5F EO-11049-D Adaptive Type 4H-4F; 5H-5F to Receive Plastic Coupling and 4” or 5” Female End Precast Concrete Conduit
Maged Filtes, P.E. Mohsen Shaaker (Signature on File) Mohsen Shaaker Manager
Tools & Structures Distribution Engineering REVISION 19: Revised: Formatting to comply with EO-1070 Revision 2 Add 6” conduits be as per Staten Island Region request Update of the specifications and standards references Removal of attachments Edit of the pipe size for friction test
FILE: Purchase & Test Manual No. 6 Section 7 – Concrete, Concrete Devices, and Temporary Paving Field Manual #17 Survey, Section 1- General
Due to be Revised 10/2019
Specification Revision Rev Date Effective
Date Copyright Information Page
1/6 EO – 1063 2 08/02/2012 08/02/2012 2005-2012 Consolidated Edison Co. of New York, Inc. Filing Information Construction Standards Manual No. 3, Sect. 16 Paper copies of procedures and instructions are uncontrolled and therefore may be outdated. Please consult Distribution Engineering Intranet Site Distribution Engineering or http://distribution, for the current version prior to use.
CONSOLIDATED EDISON COMPANY OF NEW YORK, INC.
4 IRVING PLACE NEW YORK, NY 10003
DISTRIBUTION ENGINEERING CABLE
SPECIFICATION EO-1063 REVISION 2 August, 2012
EFFECTIVE DATE AUGUST 2, 2012
PREPARATION OF CONDUIT FOR CABLE INSTALLATION
FILE: CONSTRUCTION STANDARDS, MANUAL NO. 3, SECT. 16
TARGET AUDIENCE DISTRIBUTION ENGINEERING REGIONAL ENGINEERING REGIONAL CONSTRUCTION
NESC REFERENCE ALL SECTIONS
Specification Revision Rev Date Effective
Date Copyright Information Page
2/6 EO – 1063 2 08/02/2012 08/02/2012 2005-2012 Consolidated Edison Co. of New York, Inc. Filing Information Construction Standards Manual No. 3, Sect. 16 Paper copies of procedures and instructions are uncontrolled and therefore may be outdated. Please consult Distribution Engineering Intranet Site Distribution Engineering or http://distribution, for the current version prior to use.
TABLE OF CONTENTS
1.0 SCOPE ................................................................................................................. 3
2.0 GENERAL ............................................................................................................ 3
3.0 OPERATION SEQUENCE ................................................................................... 3
3.2 Operations ................................................................................................................... 3 3.3 Duct Rodding .............................................................................................................. 4 3.4 Brushing ....................................................................................................................... 4 3.5 Cleaning ........................................................................................................................ 4 3.6 Mandrel ......................................................................................................................... 5 3.7 Final Actions ............................................................................................................... 5
Specification Revision Rev Date Effective
Date Copyright Information Page
3/6 EO – 1063 2 08/02/2012 08/02/2012 2005-2012 Consolidated Edison Co. of New York, Inc. Filing Information Construction Standards Manual No. 3, Sect. 16 Paper copies of procedures and instructions are uncontrolled and therefore may be outdated. Please consult Distribution Engineering Intranet Site Distribution Engineering or http://distribution, for the current version prior to use.
PREPARATION OF CONDUIT FOR CABLE INSTALLATION
1.0 SCOPE
This specification covers the preparation procedure to be followed prior to the installation of distribution cable in underground conduit systems.
2.0 GENERAL
The operation described herein shall be followed prior to the installation of distribution cable in conduits.
3.0 OPERATION SEQUENCE
3.1 The following sequence of operations shall be employed as specified below 3.1.1 Previously unoccupied conduit Perform operations 3.2 through 3.6
inclusive 3.1.2 Previously occupied conduit Perform operations 3.3 through 3.6
inclusive
3.2 Operations
These operations may be performed by either Company or contractor forces as necessary.
3.2.1 Rod duct 3.2.2 Brush duct
3.2.3 Clean duct
3.2.4 Perform mandrel operation
3.2.5 Install 1/2" steel rope, 9/16” steel rope or 1/4" polypropylene rope
3.2.6 Secure poly rope in structure
Specification Revision Rev Date Effective
Date Copyright Information Page
4/6 EO – 1063 2 08/02/2012 08/02/2012 2005-2012 Consolidated Edison Co. of New York, Inc. Filing Information Construction Standards Manual No. 3, Sect. 16 Paper copies of procedures and instructions are uncontrolled and therefore may be outdated. Please consult Distribution Engineering Intranet Site Distribution Engineering or http://distribution, for the current version prior to use.
3.3 Duct Roddinq
Rodding is performed from the duct entrance in one structure to the corresponding duct exit in the next structure on the conduit run
3.3.1 Rodding serves to:
a. Establish that a clear passage through the conduit exists between adjacent structures.
b. Provides a means of installing various lines to perform subsequent
cleaning, mandreling, and cable pulling operations.
3.3.2 Rodding operations are performed either manually or by means of vehicle mounted power systems. Manual operations utilize continuous long length (600') fiberglass snakes or segmented fiberglass rods.
3.4 Brushing
Brushing is performed to remove any soil or debris that might have entered the duct since it was installed. This could occur during initial backfilling operations or during the service life of the installation as groundwater washes soil through the duct system. While individual deposits of this soil may be minor, it is removed to prevent accumulations at the nose of the cable during installation operations. This pile up may be so severe as to wedge the nose of the cable tight enough to obstruct the duct. The brushing operation will continue to the extent necessary to ensure free passage of the mandrel. All brushing will be performed in the direction of the cable pull.
3.5 Cleaning
When accumulations of soil and debris are such that the rodding device cannot pass from one structure to another, a water jetting operation shall be employed. A source of pressurized water is connected to a hose line that terminates in a nozzle assembly. This nozzle is fed into the conduit to the point of the obstruction by means of a rod or snake. The water supply is then turned on and allowed to impact upon the blockage and wash the accumulated debris away. Once the debris has been removed or softened, the rodding device or snake can be passed through and the conduit cleaned in the normal manner.
Specification Revision Rev Date Effective
Date Copyright Information Page
5/6 EO – 1063 2 08/02/2012 08/02/2012 2005-2012 Consolidated Edison Co. of New York, Inc. Filing Information Construction Standards Manual No. 3, Sect. 16 Paper copies of procedures and instructions are uncontrolled and therefore may be outdated. Please consult Distribution Engineering Intranet Site Distribution Engineering or http://distribution, for the current version prior to use.
3.6 Mandrel
3.6.1 The purpose of the mandrel operation is two fold
a. Establish that a specific size passageway exists from one end of the duct to the other.
b. Establish that the alignment of the duct is such that horizontal and
vertical bends meet the specified minimum radii requirements.
3.6.2 Use of Mandrels
a. The first consideration should be the length of the cable pull. If an extra long pull (greater than 550 feet actual length) is planned, the conduit system must be aligned so that the 20 ft. radius mandrel will pass.
b. After length, the next most important factor is cable size; large
cables require better conduit systems. Large cable in a fairly long pull (300-500 feet) also requires a near perfect system (passing the 20 ft. radius mandrel).
c. Cases where the conduit system is under 300 ft. long and the cable
is large or the system is from 300 to 550 feet long even with small cable require the 10 ft. radius mandrel to pass.
d. Short pulls and small cable only require the passage of the flexible
mandrel.
3.6.3 Care shall be taken to monitor both travel speed and the line tension so as to assure that any obstructions may be noted and that no damage is done to the duct.
3.7 Final Actions
Upon completion of the mandrel operation the following action shall be taken: 3.7.1 If cable pulling operations are to be performed immediately, ½ inch
steel rope or 9/16 inch steel rope pulling line shall be installed in the conduit.
Specification Revision Rev Date Effective
Date Copyright Information Page
6/6 EO – 1063 2 08/02/2012 08/02/2012 2005-2012 Consolidated Edison Co. of New York, Inc. Filing Information Construction Standards Manual No. 3, Sect. 16 Paper copies of procedures and instructions are uncontrolled and therefore may be outdated. Please consult Distribution Engineering Intranet Site Distribution Engineering or http://distribution, for the current version prior to use.
3.7.2 If the cable pulling operations are to be performed at a later time, a ¼ inch polypropylene rope shall be installed in the duct and properly secured in each structure. Duct entrances shall be plugged with polyethylene plugs.
George Murray (Signature on File) George Murray Section Manager, Cable Section Distribution Engineering Department Joseph Watts/ JW REVISION 2: August 2012 Reissued Without Modification
FILE: Engineering Manual No. 4
CONSOLIDATED EDISON COMPANY OF NEW YORK, INC.
4 IRVING PLACE NEW YORK, NY 10003
DISTRIBUTION ENGINEERING DISTRIBUTION EQUIPMENT
SPECIFICATION EO-1092 REVISION 1
OCTOBER 2007 EFFECTIVE DATE
OCTOBER 1, 2007
INSTALLATION OF STEEL FRAMES AND CASTINGS OVER ELECTRIC DISTRIBUTION STRUCTURES
IN ROADWAY OR SIDEWALK
FILE: CONSTRUCTION STANDARDS MANUAL NO. 3
TARGET AUDIENCE REGIONAL CONSTRUCTION NESC REFERENCE NONE
Copyright Information 2006-2007 Consolidated Edison Co. of New York, Inc.
Paper copies of procedures and instructions are uncontrolled and therefore may be outdated. Please consult Distribution Engineering Intranet Site Distribution Engineering or http://distribution for the current version prior to use.
Page 1/10
Specification Revision Rev Date Effective
Date Copyright Information Page
2/10 EO-1092 1 10/01/2007 10/01/2007 2006-2007 Consolidated Edison Co. of New York, Inc. Filing Information Construction Standards Manual No. 3 Paper copies of procedures and instructions are uncontrolled and therefore may be outdated. Please consult Distribution Engineering Intranet Site Distribution Engineering or http://distribution, for the current version prior to use.
TABLE OF CONTENTS 1.0 PURPOSE............................................................................................................ 3
2.0 APPLICATION ..................................................................................................... 3
3.0 REFERENCE SPECIFICATION........................................................................... 3
4.0 GENERAL............................................................................................................ 3
5.0 COLLAR CONSTRUCTION MATERIAL ............................................................. 3
5.1 Material Required to Build And/or Extend Walls................................... 3
5.2 Material Storage and Handling ............................................................... 4
6.0 INSTALLATION PROCEDURE ........................................................................... 4
6.1 New Constructions .................................................................................. 4
6.2 Replacement Construction ..................................................................... 8
Specification Revision Rev Date Effective
Date Copyright Information Page
3/10 EO-1092 1 10/01/2007 10/01/2007 2006-2007 Consolidated Edison Co. of New York, Inc. Filing Information Construction Standards Manual No. 3 Paper copies of procedures and instructions are uncontrolled and therefore may be outdated. Please consult Distribution Engineering Intranet Site Distribution Engineering or http://distribution, for the current version prior to use.
1.0 PURPOSE This specification covers installation procedures for castings and rectangular
steel frames used with underground structures on the electric distribution system. 2.0 APPLICATION This specification applies to all Con Edison districts. 3.0 REFERENCE SPECIFICATION
For a listing of approved, prepackaged cementitious material used to make rapid-setting concrete for installation of frames/castings, see Purchase Recommendation EO-100,271.
4.0 GENERAL Proper field installation of castings and frames over walls, roof slabs, concrete or
masonry collars of electric distribution structures is necessary to ensure: A. Structurally sound installations B. Prevention of settlement cracks in the roadway pavement or sidewalk
surrounding the structure C. Elimination of noise generation that occurs between a loosely-installed
frame/casting and its corresponding cover when exposed to vehicle or pedestrian traffic
5.0 COLLAR CONSTRUCTION MATERIAL
5.1 Material Required To Build Collar And/Or Extend Walls
a. Precast concrete collar sections, masonry grading blocks. b. High-Strength cement mortar (EO-100167) c. Non-Shrink cement grout (Sikagrout 212 or approved equal) d. Rapid-Setting dry, prepackaged concrete gravel mix (EO-100271) e. Epoxy-coated steel reinforcing bars, Grade 60 (ASTM A615 and
Specification Revision Rev Date Effective
Date Copyright Information Page
4/10 EO-1092 1 10/01/2007 10/01/2007 2006-2007 Consolidated Edison Co. of New York, Inc. Filing Information Construction Standards Manual No. 3 Paper copies of procedures and instructions are uncontrolled and therefore may be outdated. Please consult Distribution Engineering Intranet Site Distribution Engineering or http://distribution, for the current version prior to use.
ASTM A775)
5.2 Material Storage and Handling - Prepackaged material, precast concrete collar sections, and masonry concrete or clay units shall be stored in a dry place, on pallets, and protected from freezing and rain. The packaged materials shall be delivered to the job site in the original, closed package, clearly labeled with the manufacturer's name and application instructions.
6.0 INSTALLATION PROCEDURE Follow these steps when installing frames and/or castings: 1) Clean bearing wall or roof slab areas. Repair any spalls or defects visible
on the bearing areas (follow specification EO-5227). 2) Determine depth of collar required. Collar depth is the distance from the
top of the existing wall or roof slab to the bottom of the casting or frame to be installed.
6.1 New Construction
6.1.1 Setting Casting Over a Cable Manhole or Service Box in
Roadway
A. Collar with a maximum depth of 12 inches
1. Follow method 1 or 2 of specification EO-10321-B when precast grading blocks are used to build the collar.
2. Set form around inside surface of casting--which is
already resting on top of the newly built collar--and place rapid-setting concrete up to 2 inches from grade. Pour concrete monolithically with the roadway pavement.
Specification Revision Rev Date Effective
Date Copyright Information Page
5/10 EO-1092 1 10/01/2007 10/01/2007 2006-2007 Consolidated Edison Co. of New York, Inc. Filing Information Construction Standards Manual No. 3 Paper copies of procedures and instructions are uncontrolled and therefore may be outdated. Please consult Distribution Engineering Intranet Site Distribution Engineering or http://distribution, for the current version prior to use.
3. As an alternative to the construction methods of specification EO-10321-B, rapid-setting concrete can be used to build the collar, encasing the casting up to 2 inches from grade.
4. Protect fresh rapid-setting concrete from traffic contact
for at least 6 hours until curing occurs. 5. Turn in job for roadway paving restoration. B. Collar with a depth greater than 12 inches 1. Follow method 3 of specification EO-10321-B when
precast concrete collar sections and/or grading blocks are used (up to 24 inches of depth) to set castings to match grade.
2. Follow methods 4 thru 7 of specification EO-10321-B
when a field-constructed collar (chimney) is required (up to 10 feet of depth).
3. Once the casting has been placed over the collar,
encase it with rapid-setting concrete up to 2 inches from grade.
4. As an alternative to the construction methods of
specification EO-10321-B, rapid-setting concrete can be used to build the collar (chimney), encasing the casting up to 2 inches from grade. Pour concrete monolithically with surrounding roadway pavement.
5. Protect fresh rapid-setting concrete from traffic contact
for at least 6 hours until curing occurs. 6. Turn in job for roadway paving restoration.
6.1.2 Setting Rectangular Steel Frame Over Roadway Transformer manhole, Cable Manhole or Cable Distribution Box
A. Collar with a maximum depth of 12 inches
Specification Revision Rev Date Effective
Date Copyright Information Page
6/10 EO-1092 1 10/01/2007 10/01/2007 2006-2007 Consolidated Edison Co. of New York, Inc. Filing Information Construction Standards Manual No. 3 Paper copies of procedures and instructions are uncontrolled and therefore may be outdated. Please consult Distribution Engineering Intranet Site Distribution Engineering or http://distribution, for the current version prior to use.
1. Set frame (inserting grading blocks through each corner) in place over manhole or service box wall tops to match grade.
2. Set form around the inside perimeter of the wall tops
and base of frame. 3. Prepare rapid-setting concrete as per manufacturer's
recommendations. 4. Pour fresh rapid-setting concrete into the cavity under
and adjacent to the frame and ensure that the base of the frame is completely touching the freshly poured concrete.
5. Continue pouring fresh concrete to encase the outside
frame surface up to 2 inches from grade. Pour concrete monolithically with surrounding roadway pavement.
6. Protect fresh rapid-setting concrete from traffic contact
for at least 6 hours until curing occurs. 7. Turn in job for roadway paving restoration. B. Collar with a depth greater than 12 inches 1. Build the reinforced concrete collar as follows: a. Drill 1" diameter by 6" deep doweling holes at 18"
spacing along the centerline of the top of each wall without damaging any ducts entering the structure.
b. Firmly grout #5 ASTM A-615 grade 60
epoxy-coated reinforcing steel bars (dowels) into the holes with Sikagrout #212 or approved equal.
c. Cut the dowels to a length necessary to maintain a
clearance of 1 inch of concrete cover from the top of the collar. Make sure that all bare rebar areas, including ends, are epoxy coated in the field with patching material meeting ASTM A 775.
Specification Revision Rev Date Effective
Date Copyright Information Page
7/10 EO-1092 1 10/01/2007 10/01/2007 2006-2007 Consolidated Edison Co. of New York, Inc. Filing Information Construction Standards Manual No. 3 Paper copies of procedures and instructions are uncontrolled and therefore may be outdated. Please consult Distribution Engineering Intranet Site Distribution Engineering or http://distribution, for the current version prior to use.
d. Wire tie #5 epoxy-coated reinforcing bars, horizontally placed, to the vertical dowels at 6" spacing to form a vertical grid. Position the horizontal reinforcing bars facing the inside surface of the structure.
e. Once the steel reinforcing bar grid has been
secured in place, then proceed to form up area before rapid-setting concrete is prepared as instructed by the concrete manufacturer.
f. Set frame to match grade and pour fresh concrete
up to 2" from grade. 2. Protect fresh rapid-setting concrete from traffic contact
for at least 6 hours until curing occurs. 3. Turn in job for roadway paving restoration.
6.1.3 Setting of Rectangular Steel Frame Over Sidewalk Transformer Vault or Manhole To Support Prefabricated Concrete Roof Slabs and/or Grating Assemblies:
A. Collar with a Maximum Depth of 12 inches 1. Follow method 2 (Vault) of specification EO-10321-B. 2. Set frame (by inserting grading blocks at each corner)
in place over walls of manhole or vault to match grade. 3. Place properly sized pre-molded elastomeric material to
function as construction joints between the new concrete encasing the outside frame and the existing concrete sidewalk surrounding the vault or manhole.
4. Encase frame with fresh rapid-setting concrete, which
should be finished to simulate the appearance of the surrounding sidewalk concrete surface.
5. Protect fresh rapid-setting concrete from pedestrian
traffic contact for at least 6 hours until curing occurs. B. Collar with a Depth Greater Than 12 inches
Specification Revision Rev Date Effective
Date Copyright Information Page
8/10 EO-1092 1 10/01/2007 10/01/2007 2006-2007 Consolidated Edison Co. of New York, Inc. Filing Information Construction Standards Manual No. 3 Paper copies of procedures and instructions are uncontrolled and therefore may be outdated. Please consult Distribution Engineering Intranet Site Distribution Engineering or http://distribution, for the current version prior to use.
1. Follow steps described in section 6.3.2.B, but substitute
sidewalk for roadway work. 2. Install elastomeric construction joints between existing
and new concrete surfaces before fresh concrete is poured.
3. Protect fresh rapid-setting concrete from pedestrian
traffic contact for at least 6 hours until curing occurs.
6.2 Replacement Construction - Existing casting and/or frame installations may have to be removed and replaced for maintenance, repair, or adjustment to match new street or sidewalk grade changes. Replace these installations as follows:
1) Break out and remove the asphalt paving and concrete base
(roadway) or sidewalk concrete encasing the casting or frame. 2) Remove the casting or frame. 3) Remove any deteriorated, loose concrete, or damaged masonry
grading units from the bearing areas. 4) Make sure that the structural integrity of the walls or roof slab is
sound by following inspection specification EO-10,222. Follow specification EO-5227 to repair any concrete deterioration before the new collar is built.
5) Clean bearing areas and wet them before collar construction starts. 6) Construct the new collar as follows:
A. Setting of Casting Over Cable Manhole or Service Box 1. Collar with a maximum depth of 12 inches a. Follow steps described in section 6.3.1.A. 2. Collar with a depth greater than 12 inches a. Follow steps described in section 6 3 l.B.
Specification Revision Rev Date Effective
Date Copyright Information Page
9/10 EO-1092 1 10/01/2007 10/01/2007 2006-2007 Consolidated Edison Co. of New York, Inc. Filing Information Construction Standards Manual No. 3 Paper copies of procedures and instructions are uncontrolled and therefore may be outdated. Please consult Distribution Engineering Intranet Site Distribution Engineering or http://distribution, for the current version prior to use.
B. Setting of Rectangular Steel Frame Over Roadway Transformer Manhole or Cable Manhole or Cable Distribution Box
1. Collar with a maximum depth of 12 inches a. Follow steps described in section 6.3.2.A. 2. Collar with a depth greater than 12 inches a. Follow steps described in section 6.3.2.B for cable
manhole or service box reconstruction work. b. Follow steps shown on specification EO-15596-A
for transformer manhole roof reconstruction work (Up to 4 feet of depth). If roof/walls reconstruction is deeper than 4 feet, then follow paragraph 2.a in this section.
C. Setting of Rectangular Steel Frame Over Sidewalk
Transformer Vault or Manhole to Support Prefabricated Concrete Roof Slabs and/or Grating Assemblies
1. Collar with a maximum depth of 12 inches a. Follow steps described in section 6.3.3.A. 2. Collar with a depth greater than 12 inches a. Follow steps described in section 6.3.3.B.
Specification Revision Rev Date Effective
Date Copyright Information Page
10/10 EO-1092 1 10/01/2007 10/01/2007 2006-2007 Consolidated Edison Co. of New York, Inc. Filing Information Construction Standards Manual No. 3 Paper copies of procedures and instructions are uncontrolled and therefore may be outdated. Please consult Distribution Engineering Intranet Site Distribution Engineering or http://distribution, for the current version prior to use.
Joseph F. Somma (Signature on File) Joseph F. Somma Department Manager
Distribution Equipment Distribution Engineering Jay Sun REVISION 1: Revised to change format. To be reviewed by 9/2012.
FILE: Construction Standards Manual No. 3, Section 30 - Covers, Frames, and Gratings
Copyright Information 1991-2019 Consolidated Edison Co. of New York, Inc.
Paper copies of procedures and instructions are uncontrolled and therefore may be outdated. Please consult Distribution Engineering Intranet Site Distribution Engineering or http://distribution for the current version prior to use.
Page 1/5
CONSOLIDATED EDISON COMPANY OF NEW YORK, INC. 4 IRVING PLACE
NEW YORK, NY 10003
DISTRIBUTION ENGINEERING
DISTRIBUTION EQUIPMENT AND
OVERHEAD STANDARDS AND PLANNING
SPECIFICATION EO-1100 REVISION 11
July 2019
EFFECTIVE DATE: SEPTEMBER 1, 2019
SEALING OF SERVICE DUCTS, ENTRANCES, AND BUS OPENINGS IN ELECTRICAL DISTRIBUTION STRUCTURES
FILE: CONSTRUCTION STANDARDS MANUAL NO. 3, SECTION NO. 42 CABLE PULLING FIELD MANUAL NO. 3, SECTION NO. 4 TARGET AUDIENCE DISTRIBUTION ENGINEERING
REGIONAL ENGINEERING REGIONAL CONSTRUCTION
NESC REFERENCE SECTION 322
Specification Revision Rev Date Effective Date
Copyright Information Page 2/5
EO-1100 11 July 2019 09/01/2019 1991-2019 Consolidated Edison Co. of New York, Inc. Filing Information Construction Standards Manual No. 3 Paper copies of procedures and instructions are uncontrolled and therefore may be outdated. Please consult Distribution Engineering Intranet Site Distribution Engineering or http://distribution, for the current version prior to use.
TABLE OF CONTENTS 1. PURPOSE ............................................................................................................ 3
2. REGIONS APPLICABLE ..................................................................................... 3
3. SAFETY AND ENVIRONMENTAL GUIDELINES ................................................ 3
4. GENERAL INFORMATION .................................................................................. 3
5. APPLICATION OF DUCT SEALING MATERIAL ................................................ 4
6. SEALING PROCEDURE ……………………………………………………………...4
7. REFERENCE SPECIFICATIONS ........................................................................ 5
Specification Revision Rev Date Effective Date
Copyright Information Page 3/5
EO-1100 11 July 2019 09/01/2019 1991-2019 Consolidated Edison Co. of New York, Inc. Filing Information Construction Standards Manual No. 3 Paper copies of procedures and instructions are uncontrolled and therefore may be outdated. Please consult Distribution Engineering Intranet Site Distribution Engineering or http://distribution, for the current version prior to use.
1.0 PURPOSE
This specification provides guidelines on locations where duct sealing is required, and procedures for duct sealing in order to maintain a water and gas tight seal.
2.0 REGIONS APPLICABLE
All electric operations regions. 3.0 SAFETY AND ENVIRONMENTAL GUIDELINES
3.1. All field personnel handling or installing duct sealing materials shall use all
proper personal protective equipment. Approved hand cleaners shall be used to clean up after work is completed.
3.2. Approved mechanical ventilation shall be used in the structure prior to and during application of foam or compound duct sealing materials. Ventilation is not required during mechanical duct sealing
3.3. Duct sealing within unit substation switchgear requires that the feeder be
de-energized and grounded in accordance with Con Edison’s “General Instructions Governing Work on System Electrical Equipment” handbook.
3.4. Remnants of duct sealing compounds or foams used by Company field
personnel shall not be left in the structure after work is completed. Precautions should be taken to prevent any sealing compound or foam material from adhering to cables or equipment housed in the structure. All duct sealing materials shall be “faced-off” with the wall.
4.0 GENERAL INFORMATION 4.1. Sealing against water and gas penetration is required in service duct(s)
and bus opening(s) in structures housing distribution system electrical equipment. Application of sealing material prevents flooding of equipment, and water, gas penetration into customer's premises and/or service equipment.
4.2. All initial duct sealing required in this specification shall be installed by company personnel. Ducts located within customer premises shall be maintained by the customer.
Specification Revision Rev Date Effective Date
Copyright Information Page 4/5
EO-1100 11 July 2019 09/01/2019 1991-2019 Consolidated Edison Co. of New York, Inc. Filing Information Construction Standards Manual No. 3 Paper copies of procedures and instructions are uncontrolled and therefore may be outdated. Please consult Distribution Engineering Intranet Site Distribution Engineering or http://distribution, for the current version prior to use.
5.0 APPLICATION OF DUCT SEALING MATERIAL
5.1. Type of Sealing Material Used: The choice of the sealing material used
will depend on the water pressure encountered at the particular location. For normal conduit depth, ordinary compounds shall be used. For deeper conduit installations, or heads of water pressure greater than 5 feet, foams or mechanical seals shall be applied according to purchase specification EO-100023.
5.2. Locations to be Sealed: Water and gas tight seals shall be applied at the following locations:
5.2.1. At both ends of all ducts entering transformer manholes or vaults
from a street or private property duct system.
5.2.2. At both ends of ducts between network vaults. Exception: Water and gas tight seals are not required in a duct if the duct length is less than 2 feet, and other means of gas or water migration exist, such as weep holes, floor penetrations, etc.
5.2.3. At both ends of underground service pipes or conduits, including riser pipes connecting to underground services. Exception: Services to outdoor meters do not require duct sealing inside the company structure.
5.2.4. At the ends of all ducts from station manhole to the unit substation
switchgear. Any spare ducts from the station manhole to the unit substation switchgear shall be plugged with a molded plastic plug that properly fits the duct diameter in both the manhole and the switchgear cubicle.
6.0 SEALING PROCEDURE
6.1. Service Ducts and Entrances
All cable and duct surfaces shall be cleaned. Water should not be allowed to flow through the duct while proper curing of the sealing material is achieved. If running water is present, follow steps described in specification EO-6217-C for additional measures. Follow all duct sealing material application steps described in specification EO-6217-C.
Specification Revision Rev Date Effective Date
Copyright Information Page 5/5
EO-1100 11 July 2019 09/01/2019 1991-2019 Consolidated Edison Co. of New York, Inc. Filing Information Construction Standards Manual No. 3 Paper copies of procedures and instructions are uncontrolled and therefore may be outdated. Please consult Distribution Engineering Intranet Site Distribution Engineering or http://distribution, for the current version prior to use.
6.2. Bus Openings
To seal bus openings between vault compartments, the joints between the bus and insulating supports as well as the joints between the supports and the surrounding areas shall be sealed as described in Paragraph 5.2.2.
7.0 REFERENCE SPECIFICATIONS
EO-3584-C Method of Sealing Bare Neutral in Service Cables at Customers
end of Service Duct. EO-6208-C Customers Electrical Service Installation Buildings with
Basements at Property Line Indoor Metering. EO-6210-B Property Line Splice Box Requirements for Buildings Back of
Property Line. EO-6214-C Customers Electric Service Installation in Building with Sub -
sidewalk Space Outside of Property Line Indoor Metering. EO-6217-C Method of Sealing Phase Grouped Service Cable and Conduit. EO-8302-B Primary and Secondary Cable Risers. EO-100023 Purchase Recommendation for Duct Sealing Compounds. Jane Shin (Signature on File) Kevin Oehlmann (Signature on File) Jane Shin, Department Manager Distribution Equipment
Kevin Oehlmann Section Manager Overhead Standards and Planning
J. Attard
O. Chilaka
REVISION NO. 11: Added NECS reference; Revised service duct sealing requirements in Paragraph 5.2; Reorganized sections into “Safety” and “General” paragraphs.
FILE: CONSTRUCTION STANDARDS MANUAL NO. 3, SECTION NO. 42. Field Manual No.3, Cable Pulling Section No. 4 – Sealing of Duct Field Manual No. 5, Vault Installation Section No. 2. Field Manual No. 11 & 12, Subway Construction Section No. 1.
CONSOLIDATED EDISON COMPANY OF NEW YORK, INC.
4 IRVING PLACE NEW YORK, NY 10003
DISTRIBUTION ENGINEERING DISTRIBUTION EQUIPMENT
SPECIFICATION EO-5433 REVISION 1
OCTOBER 2007 EFFECTIVE DATE
OCTOBER 1, 2007
SPECIFICATION FOR FIBERGLASS REINFORCED EPOXY
CONDUITS AND FITTINGS
FILE: PURCHASE AND TEST MANUAL NO. 6
TARGET AUDIENCE PURCHASING DEPAREMENT NESC REFERENCE NONE
Copyright Information 2006-2007 Consolidated Edison Co. of New York, Inc.
Paper copies of procedures and instructions are uncontrolled and therefore may be outdated. Please consult Distribution Engineering Intranet Site Distribution Engineering or http://distribution for the current version prior to use.
Page 1/7
Specification Revision Rev Date Effective
Date Copyright Information Page
2/7 EO-5433 1 10/01/2007 10/01/2007 2006-2007 Consolidated Edison Co. of New York, Inc. Filing Information Application and Design Manual No. 6 Paper copies of procedures and instructions are uncontrolled and therefore may be outdated. Please consult Distribution Engineering Intranet Site Distribution Engineering or http://distribution, for the current version prior to use.
TABLE OF CONTENTS 1.0 PURPOSE............................................................................................................ 3
2.0 APPLICATION ..................................................................................................... 3
3.0 GENERAL............................................................................................................ 3
4.0 SPECIFICATIONS ............................................................................................... 3
5.0 GENERAL REQUIREMENTS .............................................................................. 4
5.1 Material, Application and Dimension ..................................................... 4 5.2 Performance Tests................................................................................... 5
6.0 ACCEPTANCE OF CONDUITS WITH DIMENSIONAL CHECK ......................... 6
7.0 MARKING ............................................................................................................ 6
8.0 CONDUIT SECTIONS.......................................................................................... 6
9.0 ADAPTERS OR COUPLINGS ............................................................................. 6
10.0 JOINING METHODS............................................................................................ 7
1.0
Specification Revision Rev Date Effective
Date Copyright Information Page
3/7 EO-5433 1 10/01/2007 10/01/2007 2006-2007 Consolidated Edison Co. of New York, Inc. Filing Information Application and Design Manual No. 6 Paper copies of procedures and instructions are uncontrolled and therefore may be outdated. Please consult Distribution Engineering Intranet Site Distribution Engineering or http://distribution, for the current version prior to use.
PURPOSE This specification covers fiberglass reinforced epoxy (FRE) conduits and fittings
for the housing of wire and cable. 2.0 APPLICATION This specification applies to all Con Edison districts, electrical substations, and
generating stations. 3.0 GENERAL FRE conduits are to be encased in concrete when used for underground subway.
For applications other than those covered by this specification, contact the Electrical Distribution Engineer.
For installation of FRE conduits in substations and generating stations,
see specification EI-3004.
For installation of FRE conduits on the electrical distribution system, see specification EO-1091.
For a list of approved FRE product manufacturers, see Purchase and Test
Recommendation EO-100,628. 4.0 SPECIFICATIONS FRE conduits and fittings must meet the requirements of the following
specifications: ASTM D-2412 "Test for External Loading Properties of Pipe by
Parallel-Plate Loading" ASTM D-2444 "Test for Impact Resistance of Thermoplastic Pipe and
Fittings by Means of a Tup (Failing Weight)" ASTM D-2996 "Standard Specification for Filament-Wound Reinforced
Thermosetting Resin Pipe" ASTM D-635 "Rate of Burning and/or Extent and Time of Burning of
Self-Supporting Plastics in a Horizontal Position" ASTM E-84 "Surface Burning Characteristics of Building Materials"
Specification Revision Rev Date Effective
Date Copyright Information Page
4/7 EO-5433 1 10/01/2007 10/01/2007 2006-2007 Consolidated Edison Co. of New York, Inc. Filing Information Application and Design Manual No. 6 Paper copies of procedures and instructions are uncontrolled and therefore may be outdated. Please consult Distribution Engineering Intranet Site Distribution Engineering or http://distribution, for the current version prior to use.
NEMA TC14 "Filament-wound Reinforced Thermosetting Resin Conduit
and Fittings" U.L. 651 "Rigid Nonmetallic Electrical Conduit" 5.0 GENERAL REQUIREMENTS
5.1 Material, Application and Dimension
5.1.1 All FRE conduits and fittings shall be made of fiberglass reinforced epoxy material, manufactured using the filament-winding process, capable of meeting all requirements specified in this specification.
5.1.2 All FRE conduits and fittings shall have a glass fiber content of
not less than 60% of the laminate by weight. The epoxy resin shall contain an ultraviolet ray inhibitor required for long term outdoor storage.
5.1.3 The fiberglass epoxy conduits and fittings shall meet or exceed
cell classification RTRP-11AD-0111 as defined in ASTM D-2996.
5.1.4 The conduits and fittings shall be homogeneous throughout and free of visible cracks, holes, surface flaking, foreign inclusions or other defects, and shall be uniform in density and other physical properties. The bore of the conduits and fittings shall be smooth and free of obstructions.
5.1.5 The FRE conduits shall be made of material capable of meeting
or exceeding flammability requirements as specified in U.L 651-Sect. 12, and meeting or exceeding a class 1 fire rating with a ASTM E-84 flame spread rating of less than 25. The conduits shall be self extinguishing when the source of flame is removed as specified in ASTM D-635.
5.1.6 The fiberglass reinforced epoxy conduits shall resist a minimum
heat distortion temperature of 215 degrees Fahrenheit (102 degrees Celsius) when tested as per ASTM D648.
5.1.7 The inside surface of the joining arrangement shall be flush with
the conduit inside diameter.
Specification Revision Rev Date Effective
Date Copyright Information Page
5/7 EO-5433 1 10/01/2007 10/01/2007 2006-2007 Consolidated Edison Co. of New York, Inc. Filing Information Application and Design Manual No. 6 Paper copies of procedures and instructions are uncontrolled and therefore may be outdated. Please consult Distribution Engineering Intranet Site Distribution Engineering or http://distribution, for the current version prior to use.
5.1.8 All dimensions for conduits and fittings used on the electric distribution system shall be Iron Pipe Size (IPS) and shall comply with NEMA specification TC-14A. Tubing size FRE conduits required for installation inside electric generating stations and substations shall comply with NEMA TC-14B. The 2" and 3" conduits shall be type HW (Heavy Wall), and the 4" and 5" conduits shall be type SW (Standard Wall).
5.2 Performance Tests
5.2.1 Conduit Stiffness and Impact Resistance Tests - All Fiberglass
Reinforced Epoxy conduits must be tested as specified by the following ASTM standards (latest revisions). Test values must meet or exceed those shown in this section.
PROPERTY & ASTM
CONDUIT SIZE & TYPE
TEST METHOD 2"-HW 3"-HW 4"-SW 5"-SW
Conduit Stiffness @5% I.D. Deflection 2 ASTM-D-2412* (lbs/in2 )
180
60
40
22
Impact Resistance ASTM--D2444* (ft-lbs)
30
50
50
70
*Test specimens shall be 6 inches long.
5.2.2 Low Temperature Handling Test - The fiberglass conduit shall withstand the impact and bending stresses incidental to transportation, handling, and installation during temperatures down to -4±1°F (-20±1°C). The following low-temperature handling test shall be performed:
One 30 inch specimen shall be cut from sample lengths of each
size of finished conduit. The ends of each specimen shall be smooth and perpendicular to the longitudinal axis of the conduit. The specimens shall be cooled in circulating air for 5 hours to a temperature of -4+1°F (-20+1°C). While still at the low temperature, each specimen shall be dropped onto a concrete floor twice in quick succession from a height of 60 inches. During the first drop, the specimen is to make an angle of approximately
Specification Revision Rev Date Effective
Date Copyright Information Page
6/7 EO-5433 1 10/01/2007 10/01/2007 2006-2007 Consolidated Edison Co. of New York, Inc. Filing Information Application and Design Manual No. 6 Paper copies of procedures and instructions are uncontrolled and therefore may be outdated. Please consult Distribution Engineering Intranet Site Distribution Engineering or http://distribution, for the current version prior to use.
45° with the floor so that one end of it reaches the floor first. During the second drop, the specimen is to fall parallel to the floor. The conduit is unacceptable if it shatters, chips, or cracks.
6.0 ACCEPTANCE OF CONDUITS WITH DIMENSIONAL CHECK Acceptance of conduits, both straight and bend sections, shall be subject to the
following check: The inside diameter at each end shall be measured accurately. One
measurement shall be taken along the horizontal axis and another one along a perpendicular line to the first measurement. The average value of these readings shall be equal to or greater than the minimum inside diameter value shown on NEMA TC14 (latest edition). Outside diameter and wall thickness must also meet those shown on the NEMA specification. The minimum required partial inspection level is 10% per shipment.
7.0 MARKING Each section of conduit and fitting shall be prominently and permanently
identified as indicated on NEMA T (q 1 4 8.0 CONDUIT SECTIONS The sections of straight conduit shall be furnished in 20 foot lengths with either
one standard coupling or one belled end. The conduit shall have a 2", 4" or 5" diameter, as specified, and the radius of bend sections shall be 5'-0", 10'-0", or 20'-0", respectively. For substation or generating station FRE installation, conduits and bends with diameters or radius other than those listed on this specification may be purchased and used if required.
9.0 ADAPTERS OR COUPLINGS All adapters or couplings for use with FRE conduits on the electric distribution
system shall be IPS standard types, and shall be compatible with PVC Schedule 40 pipe sizes, standard fiber conduit, korduct conduit, fiberglass conduit, or other similar conduits installed on the system. If tubing size FRE conduits and fittings are installed inside generating stations and substations, special adapters must be used to join all tubing size FRE conduits to the Iron Pipe Size (IPS) FRE conduit or any other scheduled 40 piping used in underground subway.
10.0
Specification Revision Rev Date Effective
Date Copyright Information Page
7/7 EO-5433 1 10/01/2007 10/01/2007 2006-2007 Consolidated Edison Co. of New York, Inc. Filing Information Application and Design Manual No. 6 Paper copies of procedures and instructions are uncontrolled and therefore may be outdated. Please consult Distribution Engineering Intranet Site Distribution Engineering or http://distribution, for the current version prior to use.
JOINING METHODS Tapered-bell and spigot joint or saw-cut joining systems must be joined with a
two-component, thermosetting adhesive. The adhesive shall meet the requirements of ASTM-02517, and it shall be applied as recommended by the manufacturer. Mechanical joints are also acceptable, if they meet dimensional requirements shown on NEMA TC14.
Christopher G. Jones (Signature on File) Christopher G. Jones Section Manager Distribution Equipment Distribution Engineering Jay Sun INITIAL ISSUE: Revised the Format To be revised by 9/2012.
FILE: Purchase and Test Manual No. 6, Sect. 8 - Conduit, Tubing and Accessories.
Approvers: Attard, Jason S 06/15/2017
•
•
•
Approvers: Gul, Taimur 07/01/2016
Copyright Information 2005-2012 Consolidated Edison Co. of New York, Inc.
Paper copies of procedures and instructions are uncontrolled and therefore may be outdated. Please consult Distribution Engineering Intranet Site Distribution Engineering or http://distribution for the current version prior to use.
Page 1/4
CONSOLIDATED EDISON COMPANY OF NEW YORK, INC.
4 IRVING PLACE NEW YORK, NY 10003
DISTRIBUTION ENGINEERING, CABLE SYSTEMS
SPECIFICATION EO-100023 REVISION 37 APRIL 2012
PURCHASE RECOMMENDATION FOR DUCT SEALING COMPOUNDS
FILE: PURCHASE AND TEST STANDARDS MANUAL NO. 6
TARGET AUDIENCE DISTRIBUTION ENGINEERING REGIONAL ENGINEERING
NESC REFERENCE ALL SECTIONS
Specification Revision Rev Date Effective
Date Copyright Information Page
2/4 EO – 100023 37 4/27/2011 4/2011 2005-2012 Consolidated Edison Co. of New York, Inc. Filing Information Manual No. 6 PURCHASE AND TEST STANDARDS Paper copies of procedures and instructions are uncontrolled and therefore may be outdated. Please consult Distribution Engineering Intranet Site Distribution Engineering or http://distribution, for the current version prior to use.
TABLE OF CONTENTS 1.0 PURPOSE ............................................................................................................ 3 2.0 GENERAL ............................................................................................................ 3 3.0 APPROVED MANUFACTURERS…………………………………………………….3 4.0 PACKAGING ........................................................................................................ 4 5.0 ALTERNATIVE PRODUCTS ............................................................................... 4
Specification Revision Rev Date Effective
Date Copyright Information Page
3/4 EO – 100023 37 4/27/2011 4/2011 2005-2012 Consolidated Edison Co. of New York, Inc. Filing Information Manual No. 6 PURCHASE AND TEST STANDARDS Paper copies of procedures and instructions are uncontrolled and therefore may be outdated. Please consult Distribution Engineering Intranet Site Distribution Engineering or http://distribution, for the current version prior to use.
PURCHASE RECOMMENDATION FOR DUCT SEALING COMPOUNDS
1.0 PURPOSE
This purchase recommendation covers duct sealing compounds used on the underground electric distribution system.
2.0 GENERAL
Duct sealing compounds covered under this specification shall meet the requirements of EO-5089. All duct sealing compounds must be applied as per EO-6217-C.
3.0 APPROVED MANUFACTURERS
3.1 Standard Mastic Type Duct Sealing Compounds (Stock # 631-0072)
The following duct sealing compounds shall be used to seal conduits installed at a depth of 5’-0” or less below grade:
3.1.1 Uniseal SE-411F; Uniseal Inc. 3.1.2 Ducteez 109-S, Ramtec
3.2 Special Duct Sealing Foams
The following special duct sealing foams shall be used to seal conduits installed deeper than 5’-0” below grade, and for sealing ducts entering a 265/460 volt vault installation:
3.2.1 DUO-FILL 400; Todol Products Inc. 3.2.2 3-6548 RTV Silicone Foam – Dow Corning 3.2.3 FST-180-KIT Duct Sealant, American Polywater Corp.
3.2.4 FST-250-KITW Duct Sealant & ETS-2000 Applicator Gun, American Polywater Corporation
3.2.5 Ductolox 419 with Polytet Flame Proof Material, Arjunox Corp.
Specification Revision Rev Date Effective
Date Copyright Information Page
4/4 EO – 100023 37 4/27/2011 4/2011 2005-2012 Consolidated Edison Co. of New York, Inc. Filing Information Manual No. 6 PURCHASE AND TEST STANDARDS Paper copies of procedures and instructions are uncontrolled and therefore may be outdated. Please consult Distribution Engineering Intranet Site Distribution Engineering or http://distribution, for the current version prior to use.
3.2.4 Ductolox 431 with Polytet Flame Proof Material (For use with ducts having active water leaks), Arjunox Corp.
3.3 Quickset Sealing Compound
The following quickset sealing compound shall be used to seal conduits experiencing heavy water flow. 3.3.1 Compound Patching Quickset 1 gal container Class & Stock 000-
0612 4.0 PACKAGING
4.1 Standard mastic type duct sealing compounds shall be packaged in 5 lbs. units.
4.2 Special duct sealing foams shall be made available in a kit. The kit shall
include materials and accessories as described in the stock description.
4.3 Directions for mixing and/or application of the product shall be affixed to the packaging or container. Manufacturer’s identification and date of manufacture, including expiration date, if applicable, shall be printed on each package.
5.0 ALTERNATIVE PRODUCTS
Alternative duct sealing materials may be submitted to the Electrical Distribution Engineer for evaluation. Should such materials be found acceptable, they will be included in the subsequent revisions of this purchase recommendation.
George Murray (Signature on File) George Murray Section Manager, Distribution Cable Systems Distribution Engineering Department Thomas Campbell
Specification Revision Rev Date Effective
Date Copyright Information Page
5/4 EO – 100023 37 4/27/2011 4/2011 2005-2012 Consolidated Edison Co. of New York, Inc. Filing Information Manual No. 6 PURCHASE AND TEST STANDARDS Paper copies of procedures and instructions are uncontrolled and therefore may be outdated. Please consult Distribution Engineering Intranet Site Distribution Engineering or http://distribution, for the current version prior to use.
REVISION 37: Added Ducteez 109-S mastic type duct sealing compound and Ductolox 419 and 431 foam sealants.
FILE: Engineering Manual No. 6 PURCHASE AND TEST STANDARDS
Q4 XI
Consolidated Edison Company of New York, Inc.4 Irving Place, New York, N.Y. 10003
Purchase andTest Page 1Manual No. 6, Sect.12 EO-100,624
JUN 28 1984
PURCHASE RECOMMENDATIONFOR GALVANIZED STEEL RISER GUARDS
1.0 SCOPE - This purchase recommendation covers galvanized steel riser guards to be used as a temporaryrepair measure over corroded or damaged riser pipes.
2.0APPLICATION - This purchase recommendation applies to all Overhead Districts.
3.0 GENERAL - This purchase recommendation gives the specifications for the riser guard. In addition, itlists the vendors approved for purchase.
4.0 MATERIALS - The guards shall be a minimum of 16 gauge mill steel with the following specifications:
4.1 Length - guards shall be 5 foot in length.
4.2 Dimensions - radius of the guard shall be 2-5/8 inches with a side dimension of 4-3/4 inches. Flangesshall be 1 inch wide with 7/16 inch bolt holes for attachment hardware.
4.3 Finish - guards shall be galvanized in accordance with ASTM Des. A - 153
4.4 Hardware - guards shall be supplied with a grounding stud.
5.0 APPROVED VENDORS - The following distributors and their products are approved as listed.VendorsProducts
McGraw Edison DU32P2Reliable Elect.Co.UP-500-5HDAnexterPruzanMcGraw Ed ProductGraybar McGraw Ed ProductFargo UP-828HC
SEE NEXT PAGE FOR SIGNATURE
CONSOLIDATED EDISON COMPANY OF NEW YORK, INC.
4 IRVING PLACE NEW YORK, NY 10003
DISTRIBUTION ENGINEERING DISTRIBUTION EQUIPMENT
SPECIFICATION EO-100628 REVISION 6
OCTOBER 2007 EFFECTIVE DATE
OCTOBER 1, 2007
PURCHASE RECOMMENDATION FOR FIBERGLASS REINFORCED EPOXY
CONDUITS AND FITTINGS
FILE: PURCHASE AND TEST MANUAL NO. 6
TARGET AUDIENCE PURCHASING DEPARTMENT NESC REFERENCE NONE
Copyright Information 2006-2007 Consolidated Edison Co. of New York, Inc.
Paper copies of procedures and instructions are uncontrolled and therefore may be outdated. Please consult Distribution Engineering Intranet Site Distribution Engineering or http://distribution for the current version prior to use.
Page 1/4
Specification Revision Rev Date Effective
Date Copyright Information Page
2/4 EO-100628 6 10/01/2007 10/01/2007 2006-2007 Consolidated Edison Co. of New York, Inc. Filing Information Purchase and Test Manual No. 4 Paper copies of procedures and instructions are uncontrolled and therefore may be outdated. Please consult Distribution Engineering Intranet Site Distribution Engineering or http://distribution, for the current version prior to use.
TABLE OF CONTENTS 1.0 PURPOSE............................................................................................................ 3
2.0 APPLICATION ..................................................................................................... 3
3.0 GENERAL............................................................................................................ 3
4.0 APPROVED MANUFACTURERS........................................................................ 3
5.0 ALTERNATE PRODUCTS AND MANUFACTURERS ........................................ 4
Specification Revision Rev Date Effective
Date Copyright Information Page
3/4 EO-100628 6 10/01/2007 10/01/2007 2006-2007 Consolidated Edison Co. of New York, Inc. Filing Information Purchase and Test Manual No. 4 Paper copies of procedures and instructions are uncontrolled and therefore may be outdated. Please consult Distribution Engineering Intranet Site Distribution Engineering or http://distribution, for the current version prior to use.
1.0 PURPOSE This purchase recommendation covers fiberglass reinforced epoxy (FRE)
conduits and fittings for the housing of wire and cable. 2.0 APPLICATION This purchase recommendation applies to all Con Edison districts, electrical
substations, and generating stations. 3.0 GENERAL FRE conduits are to be encased in concrete when used for underground subway.
For a listing of performance requirements applicable to FRE conduits and fittings, see specification EO-5433.
4.0 APPROVED MANUFACTURERS Products of the following manufacturers are approved for use on the electric
distribution system: Fiberglass Pipe and Conduit Company (FIPCO) A.O. Smith-Inland Inc. FRE Conduit Composites, Inc.(*) Metra Conduit System, Inc. Champion Fiberglass, Inc. United Fiberglass of America, Inc. (*) Approved only for Inside-plant installations. 5.0
Specification Revision Rev Date Effective
Date Copyright Information Page
4/4 EO-100628 6 10/01/2007 10/01/2007 2006-2007 Consolidated Edison Co. of New York, Inc. Filing Information Purchase and Test Manual No. 4 Paper copies of procedures and instructions are uncontrolled and therefore may be outdated. Please consult Distribution Engineering Intranet Site Distribution Engineering or http://distribution, for the current version prior to use.
ALTERNATE PRODUCTS AND MANUFACTURERS
FRE conduits and fittings, other than listed, may be submitted to the Electrical Distribution Engineer for approval. Should such materials be found acceptable, they will be included in following revisions of this purchase recommendation.
Christopher G. Jones (Signature on File) Christopher G. Jones Section Manager Distribution Equipment Distribution Engineering Jay Sun REVISION 6: Revised the Format To be revised by 9/2012.
FILE: Purchase and Test, Manual No. 6, Sect. 8 - Conduit, tubing and Accessories.
”
”
CONSOLIDATED EDISON COMPANY OF NEW YORK, INC. 4 IRVING PLACE
NEW YORK, NEW YORK 10003
Page 1 of 13
Paper copies of the Engineering Operations Manual are uncontrolled and therefore may be outdated. Please verify that you have the current version prior to use by viewing the Central Engineering website (http://ceng/).
ENGINEERING INSTRUCTION
CE-SI-1080
Guidelines for Protecting Existing Underground Transmission Electric Facilities from Nearby Construction Activities
REVISION 01
SEPTEMBER, 2018
Prepared By: Jungmin Lee Hou 9/25/2018
Civil Engineering – Engineer Date
EH&S Review By: Walter Stepien 8/16/2018
EHS Design Engineering Date
Civil Engineering
SME Concurrence By: Mun Lai Wong 9/18/2018
Civil Engineering – Senior Engineer Date
Transmission Operations
SME Concurrence By: Vernon Schaefer 9/19/2018
Transmission Operations – Project Manager Date
Transmission Engineering
SME Concurrence By: Arie Makovoz 9/20/2018
Transmission Operations – Technical Expert Date
Approve By: Tom Villani 9/24/2018
Transmission Engineering – Section Manager Date
Approve By: Michael Nuzzi 8/14/2018
Civil Engineering – Section Manager Date
Effective Date: 9/25/2018
ENGINEERING INSTRUCTION CE-SI-1080, Rev. 01
Guidelines for Protecting Underground Transmission Electric Facilities from Nearby Construction Activities
SEPTEMBER, 2018
Page 2 of 13
Paper copies of the Engineering Operations Manual are uncontrolled and therefore may be outdated. Please verify that you have the current version prior to use by viewing the Central Engineering website (http://ceng/).
TABLE OF CONTENTS
SECTION SUBJECT PAGE
1.0 SCOPE 3
2.0 DEFINITIONS 3
3.0 INSTRUCTIONS 4
4.0 EXHIBITS 11
5.0 REFERENCES 12
ENGINEERING INSTRUCTION CE-SI-1080, Rev. 01
Guidelines for Protecting Underground Transmission Electric Facilities from Nearby Construction Activities
SEPTEMBER, 2018
Page 3 of 13
Paper copies of the Engineering Operations Manual are uncontrolled and therefore may be outdated. Please verify that you have the current version prior to use by viewing the Central Engineering website (http://ceng/).
SECTION I – GENERAL REQUIREMENTS
1.0 SCOPE
The scope of this document is a general guideline for the prevention of damage to high pressure pipes and coating for underground 69, 138 and 345 kV cable systems (electric facilities), caused by construction on (“outside plant”) properties not owned by CECONY. The guideline provides information such as:
a) general instructions and notification requirements prior to any construction activities; b) clearance requirements; c) precautions/protections to be made; and d) special notes during construction activities
The guideline is not applicable for solid dielectric or self-contained oil-filled cables. Specific work plans for these type of Transmission Feeders shall be reviewed with Con Edison for approval.
1.1 APPLICATION
This instruction applies to all Consolidated Edison Company of New York, Inc. (CECONY) organizations and contractors, and outside “third party” organization with oversight responsibility for municipal public improvement contractors and non-municipal contractors, commencing or engaging in underground construction activities associated with excavations, foundations, and demolitions within the vicinity of CECONY’s existing underground transmission system.
2.0 DEFINITIONS
2.1 CECONY refers to Consolidated Edison Company of New York, Inc.
2.2 Contractor is the construction firm hired by the Property Owner or Project Manager to perform the construction services.
2.3 Designated Contact is the contact person identified within the Project Manager Company and the Property Owner who has the responsibility to communicate on all of the planned construction works to be carried out safely.
2.4 Encroachment Area is the area where the ground disturbance occurs within 25 feet on land of the centerline of the Assumed Location of the existing electric facilities.
2.5 Assumed Location is the location of underground facilities determined from the subsurface investigations, such as record drawings or utility mark outs on streets.
2.6 Known Location is the Assumed Location that is visually confirmed from hand dug test holes. Both horizontal and vertical locations of underground facilities shall be field verified at, (a) every proposed crossings, (b) every turn in direction, and (c) a minimum of two locations along a straight run of the existing Transmission Electric Facilities. A use of vacuum excavations is an acceptable means of
ENGINEERING INSTRUCTION CE-SI-1080, Rev. 01
Guidelines for Protecting Underground Transmission Electric Facilities from Nearby Construction Activities
SEPTEMBER, 2018
Page 4 of 13
Paper copies of the Engineering Operations Manual are uncontrolled and therefore may be outdated. Please verify that you have the current version prior to use by viewing the Central Engineering website (http://ceng/).
exposing underground facilities.
2.7 Professional Engineer is the engineer, currently licensed in New York State, hired by the Property Owner or Contractor to perform the engineering/design services.
2.8 Property Owner is the entity that has legal jurisdiction or ownership of the work area or new facility being installed.
2.9 Tolerance Zone is the area in which soil must be removed by non-mechanical means, such as hand excavations methods, to expose subsurface utilities in absence of test pits. It is 2-ft clear distance on both sides of the Assumed Locations and the width of the existing Transmission Electric Facilities.
2.10 Trained Personnel refer to someone who is capable of identifying existing and predictable hazards in the surroundings or working conditions, has authorization to take prompt corrective measures to eliminate the hazards, and is trained and experienced in utility installation and inspection.
2.11 Transmission Electric Facilities refer to underground transmission feeders 69kV and higher and associated circulation piping.
2.12 Wingback is the required longitudinal distance of a pipe to be exposed by excavation in order to achieve the desired relocated position.
3.0 INSTRUCTIONS
3.1 GENERAL INSTRUCTIONS
3.1.1 Follow the requirements outlined in the State of New York Department of Public Service NYCRR 16 Part 753, “Protection of Underground Facilities”.
3.1.2 Perform subsurface investigations and mark-outs prior to planning and performing any work in the Encroachment Area of the underground Transmission Electric Facilities.
3.1.3 Mark-outs of the Assumed Locations of the underground facilities must be refreshed periodically, by the Contractor, to ensure underground facilities locations are always clearly identified over the entire project duration. If at any time the underground facilities marks become illegible, work must be stopped until the locations can be re-identified.
3.1.4 Contractor shall provide proper support of all exposed Transmission Electric Facilities during excavation activities.
3.1.4.1 A work plan, including pipe support design and calculations, shall be submitted to CECONY Engineering for approval, at least two weeks prior to performing any work in the Encroachment Area of the electric facilities. Refer to section 3.4 for pipe support design criteria.
3.1.4.2 For management of excavated soils, refer to section 3.5, “Backfill”.
ENGINEERING INSTRUCTION CE-SI-1080, Rev. 01
Guidelines for Protecting Underground Transmission Electric Facilities from Nearby Construction Activities
SEPTEMBER, 2018
Page 5 of 13
Paper copies of the Engineering Operations Manual are uncontrolled and therefore may be outdated. Please verify that you have the current version prior to use by viewing the Central Engineering website (http://ceng/).
3.1.4.3 CECONY Transmission Operation shall review the work plan on an as-needed basis and shall inspect the work area for pipe support, moving process and coating conditions prior to backfill.
3.1.4.4 The approved work plan shall be obtained by the Contractor prior to commencement of any work.
3.1.5 In absence of test pits, excavation within the Tolerance Zone shall be performed by hand only. Saw-cutting pavements within the Tolerance Zone is allowed with blade depths less than the confirmed asphalt pavement thickness.
3.1.6 For Known Locations, a zone of protection shall be established by shielding the exposed facilities from damage that could result from falling debris, i.e. rocks, concrete, compacted soil, etc. Machine excavation or additional saw-cutting of pavements may then be allowed as directed by CECONY Engineering or CECONY Field Representative.
3.1.7 Maintain clearances and separation distances to the existing Transmission Electric Facilities to the maximum extent possible at all times. Refer to section 3.2 for clearance and separation distance requirements.
3.1.8 Only Trained Personnel should work in the vicinity of exposed underground Transmission Electric Facilities.
3.2 CLEARANCES AND SEPARATION DISTANCE
3.2.1 Existing Transmission Electric Facilities within the Tolerance Zone must be protected in place. In general, a minimum of 3 feet of cover over the electric facilities shall be maintained. When less than 2 feet of cover is authorized because of special conditions, suitable guards shall be placed over pipes as described in CE-TS-3352. Clear distance between the guard and the pipe shall be a minimum of 6 inches. Contractor may be allowed to move the existing Transmission Electric Facilities by following the requirements described in section 3.2.2 and 3.4.4, or the new facilities must be relocated.
3.2.2 Maintain both the following minimum required vertical clearances and horizontal separation distances between existing Transmission Electric Facilities and the new subsurface facilities:
ENGINEERING INSTRUCTION CE-SI-1080, Rev. 01
Guidelines for Protecting Underground Transmission Electric Facilities from Nearby Construction Activities
SEPTEMBER, 2018
Page 6 of 13
Paper copies of the Engineering Operations Manual are uncontrolled and therefore may be outdated. Please verify that you have the current version prior to use by viewing the Central Engineering website (http://ceng/).
Subsurface Facility
Minimum Required Vertical Clearance* to Electric Facilities [ft]
Minimum Required Horizontal
Separation Distance* to Electric Facilities [ft]
Without Protection
With Protection
Without Protection
With Protection
Gas Transmission Facilities ⒶⒷⒸ 1.0 0.5 1.0 0.5
Gas Distribution Facilities ⒶⒷⒸ 1.0 0.5 1.0 0.5
Gas Service FacilitiesⒷⒸ 1.0 0.5 1.0 0.5
Electric Distribution Facilities ⒷⒺ
Duct Bank ≥ 6 Ducts Duct Bank < 6 Ducts
1.0 1.0
*** ***
12.0 6.0
*** ***
Steam Main Ⓑ Pipe Size ≥ 6 inch Pipe Size < 6 inch
2.0 1.5
*** ***
12.0 6.0
*** ***
Liquid Petroleum Pipelines ⒷⒸ 1.0 0.5 1.0 0.5
Water & Sewer Ⓑ ** 2.0 *** 2.0 *** Temporary Construction (e.g. sheeting, shoring, piles, etc.) 2.0 1.0 2.0 1.0
Other Utilities (e.g. telephone, cable, etc.) Ⓓ
1.0 *** 1.0 ***
Permanent Structures (e.g. piles, piers, catch basins, manholes, etc.)
2.0 *** 2.0 ***
∗ If it is not practical to achieve the minimum required clearance or separation distance, it may be further reduced provided that all parties involved agree to the reduction and that suitable protective materials are placed between the electrical and other facilities for the entire length of the reduced clearances.
** If Transmission Electric Facilities pass within 2-ft of water mains or services, Transmission Electric Facilities shall be protected as described in specification CE-TS-3352, Section 1.2.4.
*** As directed by CECONY Field Representative
Ⓐ CECONY Corporate Instruction CI-920-1, “Gas Facilities – Clearances, Encroachments, Interference, and Corrosion”.
Ⓑ CECONY Specification CE-TS-3352, “Specification for the Installation of High Pressure Pipe for 69, 138 and 345 kV Cable Systems – Section I General Requirements”.
Ⓒ State of New York Department of Public Service NYCRR 16 Part 101, “Underground Electric Facility Construction”.
Ⓓ 2012 NESC – National Electrical Safety Code, C2-2012, IEEE Standard Association.
Ⓔ CECONY Specification CE-ES-3004, “Construction Specification for the Installation of Underground Fiberglass Reinforced Epoxy (FRE) and Polyvinyl Chloride (PVC) Conduits.
ENGINEERING INSTRUCTION CE-SI-1080, Rev. 01
Guidelines for Protecting Underground Transmission Electric Facilities from Nearby Construction Activities
SEPTEMBER, 2018
Page 7 of 13
Paper copies of the Engineering Operations Manual are uncontrolled and therefore may be outdated. Please verify that you have the current version prior to use by viewing the Central Engineering website (http://ceng/).
3.3 Vibration Monitoring Program
3.3.1 Construction activities that involve blasting and non-blasting activities, including but not limited to pile driving, hydraulic breakers (hoe ram), drilling or boring activities, in the Encroachment Area of the underground facilities having the potential to produce vibration levels that may be susceptible to damaging existing Transmission Electric Facilities shall be monitored.
3.3.2 All blasting and non-blasting activities described in section 3.3.1 must be approved by CECONY Engineering prior to commencing the work and may require a vibration monitoring plan subject to CECONY review and approval. Allow minimum two weeks for CECONY Engineering’s review and approval of a vibration monitoring plan.
3.3.3 The Contractor is required to engage professional engineering services to conduct an existing conditions survey of the Transmission Electric Facilities, and an experienced vibration monitoring Consultant, with minimum 5 years of related experience in New York State, is required to measure peak particle velocities prior to and during construction activities.
3.3.4 The measured vibration level experienced on the Transmission Electrical Facilities shall not exceed 0.5 in/sec. If maximum values are approached, construction activities shall be halted; construction means and methods shall be reevaluated, or an approved alternative construction methodology may be adopted to mitigate excessive vibration.
3.3.5 The vibration monitoring plan shall include, but not be limited to, the following items:
3.3.5.1 Description of the Transmission Electric Facilities to be surveyed;
3.3.5.2 Monitoring equipment;
3.3.5.3 Monitoring device locations;
3.3.5.4 Monitoring frequency;
3.3.5.5 List of personnel to be notified (supplied by CECONY) in the event that vibration approaches the threshold limits.
3.3.6 The Contractor shall maintain a continuous log at the construction site and shall furnish a copy to the CECONY Field Representative upon request. The log shall also include receipts and notices of complaints. CECONY reserves the right to concurrently monitor any construction vibration levels. A preconstruction survey documenting the existing condition of the Transmission Electric Facilities to be monitored shall be conducted by the Contractor.
3.4 Transmission Electric Facility Support Design Criteria
3.4.1 Any and all materials/means used to hang, support, and/or protect the Transmission Electric Facility pipes must maintain the integrity of the pipe
ENGINEERING INSTRUCTION CE-SI-1080, Rev. 01
Guidelines for Protecting Underground Transmission Electric Facilities from Nearby Construction Activities
SEPTEMBER, 2018
Page 8 of 13
Paper copies of the Engineering Operations Manual are uncontrolled and therefore may be outdated. Please verify that you have the current version prior to use by viewing the Central Engineering website (http://ceng/).
coating. Any and all damage to the coating must be reported to the CECONY representative on site; and no backfilling of the pipe can be performed until pipe coating is restored and inspected.
3.4.2 Prior to any Transmission Electric Facility pipe support work that deviates from the CET manual, the Contractor shall submit to CECONY Engineering the following for review and approval:
3.4.2.1 Drawings drawn to scale showing plans, sections and details of pipe support design stamped by a Professional Engineer.
3.4.2.2 Supporting calculations stamped by the Professional Engineer.
3.4.2.3 The design span for Transmission Electric Facility supports shall satisfy the allowable stress and deflection limits in accordance with ASME B31.1 considering both static loads and internal operating pressure. Additional loads due to jacking to move the Transmission Electric Facility pipes shall be accounted for in the support design.
3.4.2.4 Typical Transmission Electric Facility pipe parameters are listed in Exhibit A for calculating design loads for pipe supports.
3.4.2.5 The maximum spacing between supports shall not exceed 10 feet.
3.4.3 Pending a condition assessment of the pipe by CECONY, the Contractor may be allowed to adjust the location and/or elevation of existing Transmission Electric Facility pipes by transitioning the pipes with the minimum required Wingback distances for the required offsets as outline below. Wingback distances were computed for high pressure fluid filled (pipe-type) Transmission Electric Facilities only. Refer to drawing 516411 for schematic guideline on relocation of Transmission Electric Facilities.
Nominal Pipe Size [in]
Minimum Required Wingback [ft]
6” Offset 9” Offset 12” Offset
5 88 108 125
6 98 120 138
7 (TUBE) 97 119 137
8 111 136 157
10 129 158 183
12 147 180 208
3.4.4 A work plan detailing the steps and means of moving the pipe shall be submitted to CECONY Engineering for approval. The plan shall identify the incremental sequence and distances to move the pipe in achieving the final offset, a
ENGINEERING INSTRUCTION CE-SI-1080, Rev. 01
Guidelines for Protecting Underground Transmission Electric Facilities from Nearby Construction Activities
SEPTEMBER, 2018
Page 9 of 13
Paper copies of the Engineering Operations Manual are uncontrolled and therefore may be outdated. Please verify that you have the current version prior to use by viewing the Central Engineering website (http://ceng/).
description of jacks (or other equipment) to move the pipe, their locations and load capacity, and the protective measures that will be employed to not damage the pipe coating.
3.5 Backfill
3.5.1. Prior to backfilling the exposed electric Transmission Electric Facility, CECONY Transmission Operations/Corrosion Control shall be notified to inspect the condition of pipe and repair any areas of corrosion or damaged coating.
3.5.2. Approved material is to be used for backfilling under, adjacent and over the Transmission Electric Facilities pipe as described in specifications EO-8085 (for general backfill) and CE-TS-4074 (for thermal sand) and as depicted on EO-12640-B. 345kV transmission feeders must be backfilled with thermal sand and 69 KV and 138kV transmission feeders must be backfilled with clean sand as described by specifications. Contractor must submit a copy of the gradation analysis and test report to CECONY Engineering for approval.
3.5.3. Reuse of excavated soil may be permitted as approved backfill materials if it conform to the requirements outlined in the Specification, CE-TS-3352, latest revision. Contractor must submit a copy of the gradation analysis and the material must be approved by CECONY prior to its application.
3.5.3.1. For CECONY Contractors, excavated soil must be managed in accordance with the requirements of CECONY GEHSI E05.11 “Management of Excavated Soils on Property Not Owned by the Company”, latest revision. Excavated soil cannot be reused as backfill if it does not meet the requirements of the governing GEHSI.
3.5.4. Approved backfill shall be compacted in maximum 12” lifts in accordance with Specification EO-1181, latest revision, unless otherwise approved by CECONY.
3.5.5. The CECONY Field Representative may require in-place density tests to ensure proper compaction.
3.6. SPECIAL NOTES FOR CONSTRUCTION ACTIVITIES
3.6.1. Each party shall use its best efforts to avoid or minimize, to the maximum extent practicable, any adverse environmental effects associated with the construction activities around subsurface Transmission Electric Facilities.
3.6.2. Perform daily job briefings with all employees before each shift, highlighting the hazards associated with working around Transmission Electric Facility and in excavations, i.e. high voltage electrical hazards, high pressure dielectric fluid or nitrogen gas pressure, coal tar pipe coatings, asbestos coating on pipe, work area protections, traffic, cave-ins, etc.
3.6.2.1. In the event that the Transmission Electric Facility pipe displays disturbed or disbonded asbestos coating, stop the work immediately and contact the CECONY Designated Contact for further directions.
ENGINEERING INSTRUCTION CE-SI-1080, Rev. 01
Guidelines for Protecting Underground Transmission Electric Facilities from Nearby Construction Activities
SEPTEMBER, 2018
Page 10 of 13
Paper copies of the Engineering Operations Manual are uncontrolled and therefore may be outdated. Please verify that you have the current version prior to use by viewing the Central Engineering website (http://ceng/).
3.6.3. Long duration projects must be managed with vigilance to ensure that all employees maintain proper focus regarding the hazards associated with working around the Transmission Electric Facilities.
3.6.4. CECONY shall inspect the exposed Transmission Electric Facility to verify its condition prior to any work being performed. It is Contractor’s responsibility to contact CECONY to schedule this inspection.
3.6.5. Any undermined Transmission Electric Facility ten feet or great in span must be supported with sand bags, nylon slings or other approved methods, taking special care to not damage the pipe coating.
3.7. EMERGENCY ACTION PLAN
3.7.1. In the event of emergency, such as pipe cracks, leaks, or breakage, Contractor must notify the CECONY’s Designated Contact immediately. All work must stop and cannot proceed until the CECONY field representative has inspected the damage and further direction is provided.
ENGINEERING INSTRUCTION CE-SI-1080, Rev. 01
Guidelines for Protecting Underground Transmission Electric Facilities from Nearby Construction Activities
SEPTEMBER, 2018
Page 11 of 13
Paper copies of the Engineering Operations Manual are uncontrolled and therefore may be outdated. Please verify that you have the current version prior to use by viewing the Central Engineering website (http://ceng/).
4.0 EXHIBITS
EXHIBIT A – TYPICAL TRANSMISSION STEEL PIPE/CONDUIT PARAMETERS*
Pipe Size OD t Uniform
Weight Max
Operating Pressure
Design Temperature
[inch] [inch] [plf] [psig] [°F]
5 5.5625 0.258 22 600 140
6 6.6250 0.280 30 600 140
7 (Tube) 7.0000 0.250 49 400 140
8 8.6250 0.250 68 400 140
10 10.7500 0.250 91 400 140
12 12.7500 0.250 109 400 140
∗ Transmission steel pipe parameters described hereon are pipes manufactured in accordance with ASTM A-523 Grade A steel only. For any other materials encountered for during excavation, Contractor shall notify CECONY and request material-specific parameters. Weight includes pipe, cables and oil for 7” pipes and bigger. 5” and 6” pipes are return pipes with no cable inside and the weights include weight of pipe and oil only.
ENGINEERING INSTRUCTION CE-SI-1080, Rev. 01
Guidelines for Protecting Underground Transmission Electric Facilities from Nearby Construction Activities
SEPTEMBER, 2018
Page 12 of 13
Paper copies of the Engineering Operations Manual are uncontrolled and therefore may be outdated. Please verify that you have the current version prior to use by viewing the Central Engineering website (http://ceng/).
5.0 REFERENCES
5.1 State of New York Department of Public Service, 16 NYCRR Part 753 – Protection of Underground Facilities.
5.2 State of New York Department of Public Service, 16 NYCRR Part 101 – Underground Electric Facility Construction.
5.3 New York City Department of Buildings Technical Policy and Procedure Notice #10/88, “Procedures for the Avoidance of Damage to Historic Structures”.
5.4 New York State Department of Transportation, Engineering Instruction, EI-05-044, “Special Specification for Building Condition Survey(s) and Vibration monitoring (Non-Blasting)”
5.5 2012 NESC – National Electrical Safety Code, C2-2012, IEEE Standard Association.
5.6 ASME B31.1-2014 ASME Code for Pressure Piping, B31 – Power Piping.
5.7 ASME BPVC.II.D.C-2015, ASME Boiler & Pressure Vessel Code – Section II Materials – Part D – Properties (Customary).
5.8 CECONY Corporate Instruction CI-920-1 – Gas Facilities – Clearances, Encroachments, Interference, and Corrosion.
5.9 CECONY General Environmental Health and Safety Instructions
GEHSI E05.11 “Management of Excavated Soils on Property Not Owned by the Company”
5.10 Central Engineering Drawings and Specifications
CE-ES-3004, “Construction Specification for the Installation of Underground Fiberglass Reinforced Epoxy (FRE) and Polyvinyl Chloride (PVC) Conduits.
CE-TS-3352, “Specification for the Installation of High Pressure Pipe for 69, 138 and 345 kV Cable Systems – Section I General Requirements”.
CE-TS-4074, “General Purchase Specification for Controlled Thermal Sand Material for High Pressure Pipe Type Cables”.
CE-TS-4197, “General Purchase Specification for Steel Pipe for Electrical Facilities and Casings”.
CE-SS-3400, “Specification for the Installation of Civil Material and Equipment – Section III Detail Standard Specification, Part 2200 – Excavation & Backfilling”.
EO-12640-B, “H.P. Cable and Dielectric Fluid Circulating Pipe Trenching and Backfill”.
Dwg 516411, “Guideline for Permanent Relocation of Feeder Pipes using “Wingback” Method”.
ENGINEERING INSTRUCTION CE-SI-1080, Rev. 01
Guidelines for Protecting Underground Transmission Electric Facilities from Nearby Construction Activities
SEPTEMBER, 2018
Page 13 of 13
Paper copies of the Engineering Operations Manual are uncontrolled and therefore may be outdated. Please verify that you have the current version prior to use by viewing the Central Engineering website (http://ceng/).
5.11 Distribution Engineering Specification
EO-1181, “General Specification For Backfilling Of Trench And Small Openings”
EO-8085, “General Specification for Backfill and Bedding Material for Excavations”.
Field Guide for Working around Electric Transmission Lines
Last Review Aug 2011. Presented at Dielectric Leak Prevention Committee April 2009. Document origination: June 13, 2006.
FEEDER TYPES
HIGH PRESSURE FLUID FILLED (HPFF) FEEDERS
HPFF feeder pipes (“Oil‐o‐static” a trade name) are installed with anywhere from one to eight pipes and may include oil return line(s), and may have cables and dielectric fluid inside. See Figure 1.
Sometimes oil return lines are not located in the same trench or on the same street as the conductors. Refer to the appropriate maps and plates for their exact location. When found in the same trench they are usually located above and offset from the feeder pipes but interference with other utilities may have required them to be installed in between or on the side of the feeder pipes.
SOLID DIELECTRIC (SD) FEEDERS
SD feeders are a newer type of feeder and do not have dielectric fluid in them or oil return lines. SD feeders usually are housed fiber‐reinforced Epoxy (FRE) with concrete around the duct bank, but may also be housed in pipe or concrete duct. See Figure 2 & 3. SD feeders may also be direct buried, especially near/within substations.
GAS FILLED FEEDERS
Some transmission feeders consist of pipes that are filled with nitrogen gas; they are called gas‐filled feeders. Their pipes are similar in construction as the HPFF feeders.
LOW PRESSURE AND MEDIUM PRESSURE
There are low pressure and medium pressure transmission feeders as well which may be installed in ducts, or in some cases, may be direct buried. With these systems, the cable is impregnated with oil as well.
GENERAL INFORMATION
Transmission feeder cables exists at voltages of 69KV, 138KV OR 345KV (“Feeders”). Information on transmission feeders can be found on a Composite maps (by borough/county) or individual feeder maps, conduit plates, and sub‐surface drawings (“10 scales”). Most newly installed HPFF pipes and SD feeders have communication control lines associated with them; the majority of the feeders do not. Detail drawings of Bridge crossing are available through the Public Improvement Engineering Group. Some transmission feeders were installed directly in the concrete on bridge crossings without steel protection plates over them, so caution must be taken working on bridges. The backfill used around electric transmission lines is typically sand (either Type 3/8 or thermal sand).
Coatings on feeder pipes and oil return lines may be coal tar and should always be assumed to contain PCBs and ACM unless tested otherwise.
At some locations, the feeder pipes or duct bank can be installed through a sleeve to pass around or under adjacent facilities. The sleeve will be larger than the pipe running through it. Generally, this sleeve will be bare steel and will be in line with the Code 753 markings.
Transmission manholes almost always have dual openings (i.e. two manhole covers). Transmission manholes also almost always have “gas valve box covers” associated with the manhole, which contain cathodic protection test stations. See Figure 4.
If oil or fluid is in the soil or if the pipe is leaking, notify #9, your supervisor and EH&S immediately (follow GEI 2.01 Spill Reporting). Utilize spill kits as required and once the spill has been properly reported, call Transmission Operations (718) 204‐4488 or 4489 to inspect and repair the leak.
#9 PHONE NUMBERS: Manhattan: 212‐780‐3733 or 3743 Brooklyn/Queens: 718‐802‐5150 or 5151 Staten Island: 718‐390‐6207 or 2267 Bronx: 914‐925‐6205 Westchester: 914‐925‐6221 or 914‐921‐3722
Figure 4: HPFF
Figure 4: FRE
Figure 4: FRE
Figure 4: Test Station
Field Guide for Working around Electric Transmission Lines
Last Review Aug 2011. Presented at Dielectric Leak Prevention Committee April 2009. Document origination: June 13, 2006.
BEFORE EXCAVATING Refer to the most current version of the M&S, Conduit, and C&DO plates as well as the Composite Feeder Maps. The feeder maps are available from Transmission Engineering (212‐460‐2914 or 212‐460‐4189).
Ensure that Code 753 markings have been made. Note – the Transmission Lines will be marked “Oil‐O”, “HPP”, “Trans‐FRE”, or “Trans‐STL.” Renew markings as required throughout duration of excavation activities.
If marks are not accurate or missing, contract the area FPG CCI or PI Operating Supervisor (Staten Island): Manhattan: 917‐939‐7912 Bronx: 347‐234‐0125 Brooklyn: 646‐584‐7333 Queens: 917‐559‐3593 Westchester: 347‐672‐8180 Staten Island: 646‐879‐2729
Hold a field meeting with the excavator before work begins. Supervisors/Mechanics/CR/Inspector must review project limits, methods and procedures to support, protect and maintain Con Edison facilities.
Ensure that the most current facility plates and maps are on site.
SAW CUTTING AND MACHINE USE
NO SAW CUTTING of the pavement is permitted directly crossing over feeders or oil return lines that have been identified in the work area, regardless of whether facility is noted shallow cover or not.
Except for removal of asphalt and concrete base, there shall be no mechanical excavation within the tolerance zone of feeders until the location of the facility and any associated piping has been found. HAND DIG ONLY.
TEST PITS
Hand excavated test pits shall be performed to verify the markouts and location of all critical facilities within the work zone as per Code 753 requirements. In addition, critical facilities within 5’ of a work zone, that crosses and run parallel to the work zone, shall be located before beginning any intended excavation with hand excavated test pits. Test pitting shall also be performed as required, to verify the location of critical facilities for extended trenches and excavations. If test pits are to be used to confirm the exact location of the feeders and associated piping and comply with standard excavating requirements by hand and machine.
FEEDER PIPE INSPECTION
If the feeder pipes are exposed, NOTIFY CORROSION OPERATIONS TO INSPECT THE PIPES. If the coating needs repair or removal, the Corrosion Group will notify Underground Transmission to arrange for Company forces or a contractor to do this work. If for some reason Gas Corrosion cannot respond, notify Transmission Operations directly and they will send someone to do the inspection.
CORROSION OPERATIONS PHONE NUMBERS: 718‐579‐1498 or 718‐579‐1216. Inform them of the Feeder number and location.UNDERGROUND TRANSMISSION PHONE NUMBERS: 718‐204‐4489 or 718‐204‐4488. 24‐hr phone number (718)393‐8999
RESTORATION
When pipes pass within 2’ of a water main/service, a Con Edison approved ½” thick rubber sheet (class & stock #059‐5306) shall be installed between the pipe(s) and the water main/service. There shall be an overlap of 6” between sheets if more than one sheet is required. The rubber sheet(s) shall overhang the water main/service by 18”. The rubber sheet should never be wrapped around the feeder pipe. All backfill around transmission feeder pipes and oil lines MUST conform to company specifications. Refer to Specification EO‐1173‐5 “Specification for Controlled Backfill for HP Cable Pipe Installations” for requirements. For additional information on restoration, please refer to CE‐TS‐3352 (“General Specification for installation of High Pressure Pipe for 69KV, 138KV and 345KV Cable Systems, Section 1 – General Requirements”), which can be found on the Central Engineering Website (http://ceng/ceng).