09 PROJECT PERFORMANCE MGT

download 09 PROJECT PERFORMANCE MGT

of 43

Transcript of 09 PROJECT PERFORMANCE MGT

  • 8/8/2019 09 PROJECT PERFORMANCE MGT

    1/43

    Performance ManagementPerformance Management

    Session 9Session 9

  • 8/8/2019 09 PROJECT PERFORMANCE MGT

    2/43

    The Project CycleThe Project Cycle

  • 8/8/2019 09 PROJECT PERFORMANCE MGT

    3/43

    Performance ManagementPerformance Management

    The Most Basic SystemThe Most Basic System

  • 8/8/2019 09 PROJECT PERFORMANCE MGT

    4/43

    Performance ManagementPerformance Management

    Monitoring Time PerformanceMonitoring Time Performance

  • 8/8/2019 09 PROJECT PERFORMANCE MGT

    5/43

    Performance ManagementPerformance Management

    This Is What It Looks Like In MS ProjectThis Is What It Looks Like In MS Project

  • 8/8/2019 09 PROJECT PERFORMANCE MGT

    6/43

    Performance ManagementPerformance Management

    Monitoring Time PerformanceMonitoring Time Performance

  • 8/8/2019 09 PROJECT PERFORMANCE MGT

    7/43

    PerformancePerformance

    ManagementManagement

    y Looks only at time

    y Does not take into account cost performance

    y While it implies work completed it is based on

    time spent this not verified actual complete

    y What is the value of the work completed?

    CommentComment

    Monitoring Time PerformanceMonitoring Time Performance

  • 8/8/2019 09 PROJECT PERFORMANCE MGT

    8/43

    Performance ManagementPerformance Management

    Monitoring Budget PerformanceMonitoring Budget Performance

    Example you budget 100 hours to assemble bridge

    pillars and at the end of the period you have achieved the 100 hours

    Budget Actual Variance

    100 hours @ R 300 R 100 hours @

    R 300

    R 0

  • 8/8/2019 09 PROJECT PERFORMANCE MGT

    9/43

    Performance ManagementPerformance Management

    Ho do you stay on track?Ho do you stay on track?

    What is a Project Monitoring System

    Examples of Progress Reports

    What is the Project Control Process and why is it useful?

    How do I Monitor Time Performance

    The shortcomings of monitoring Systems

    Earned Value Management

    Integrated Cost/Schedule System

    Project Baselines

  • 8/8/2019 09 PROJECT PERFORMANCE MGT

    10/43

    Performance ManagementPerformance Management

    Time PerformanceTime Performance

    Does not connect duration to resource

    utilization

  • 8/8/2019 09 PROJECT PERFORMANCE MGT

    11/43

    Performance ManagementPerformance Management

    Cost PerformanceCost Performance

    Systems that measure only cost

    variances do not identify resource and

    project cost problems associated with

    falling behind or progressing ahead of

    schedule

  • 8/8/2019 09 PROJECT PERFORMANCE MGT

    12/43

    Performance ManagementPerformance Management

    Ho do you stay on track?Ho do you stay on track?

    What is a Project Monitoring System

    Examples of Progress Reports

    What is the Project Control Process and why is it useful?

    How do I Monitor Time Performance

    The shortcomings of monitoring Systems

    Earned Value Management

    Integrated Cost/Schedule System

    Project Baselines

  • 8/8/2019 09 PROJECT PERFORMANCE MGT

    13/43

    Performance ManagementPerformance Management

    EVAEVA-- What do you need?What do you need?

    Does not connect duration to resource

    utilization

  • 8/8/2019 09 PROJECT PERFORMANCE MGT

    14/43

    Performance ManagementPerformance Management

    EVAEVA-- What do you need?What do you need?

    Does not connect duration to resource

    utilization

  • 8/8/2019 09 PROJECT PERFORMANCE MGT

    15/43

    Performance ManagementPerformance Management

    What is Earned ValueAnalysis (EVA)?What is Earned ValueAnalysis (EVA)?

    Does not connect duration to resource

    utilization

    A project performancemeasurement technique that

    integrates scope, time, and cost

    data.

  • 8/8/2019 09 PROJECT PERFORMANCE MGT

    16/43

    Performance ManagementPerformance Management

    What is Earned ValueAnalysis (EVA)?What is Earned ValueAnalysis (EVA)?

    Does not connect duration to resource

    utilization

    A project performance measurement technique

    that integrates scope, time, and cost data.

    Given a baseline (original plan plus approvedchanges), you can determine how well the

    project is meeting its goals.

    You must enter actual information

    periodically to use EVA.

  • 8/8/2019 09 PROJECT PERFORMANCE MGT

    17/43

    Performance ManagementPerformance Management

    The Planned Value (PV)The Planned Value (PV) -- This is that portion of the approved total costThis is that portion of the approved total costestimate planned to be spent on an activity during a given periodestimate planned to be spent on an activity during a given period

    1000

    900

    800

    700

    600

    500

    400

    300

    200

    100

    1 2 3 4 5 6 7 8 9 10

    PVPV

  • 8/8/2019 09 PROJECT PERFORMANCE MGT

    18/43

    Performance ManagementPerformance Management

    The Planned Value (PV)The Planned Value (PV) -- This is that portion of the approved total costThis is that portion of the approved total costestimate planned to be spent on an activity during a given periodestimate planned to be spent on an activity during a given period

    1000

    900

    800

    700

    600

    500

    400

    300

    200

    100

    1 2 3 4 5 6 7 8 9 10

    PVPV

  • 8/8/2019 09 PROJECT PERFORMANCE MGT

    19/43

    Performance ManagementPerformance Management

    Actual Cost (AC)Actual Cost (AC) --TheThe total coststotal costs incurred in finishing work on anincurred in finishing work on anactivity during a given periodactivity during a given period

    1000

    900

    800

    700

    600

    500

    400

    300

    200

    100

    1 2 3 4 5 6 7 8 9 10

    PVPVACAC

  • 8/8/2019 09 PROJECT PERFORMANCE MGT

    20/43

    Performance ManagementPerformance Management

    Earned Value (EV)Earned Value (EV) -- An estimate of the value of the physical workAn estimate of the value of the physical workactually completedactually completed

    1000

    900

    800

    700

    600

    500

    400

    300

    200

    100

    1 2 3 4 5 6 7 8 9 10

    PVPVACAC EVEV

  • 8/8/2019 09 PROJECT PERFORMANCE MGT

    21/43

    Performance ManagementPerformance Management

    Time NowTime Now An importantconceptAn importantconcept

    1000

    900

    800

    700

    600

    500

    400

    300

    200

    100

    1 2 3 4 5 6 7 8 9 10

    PVPVACAC EVEV

  • 8/8/2019 09 PROJECT PERFORMANCE MGT

    22/43

    Performance ManagementPerformance Management

    Based on this you can calculate:Based on this you can calculate:

    CV Cost Variance

    SV Schedule Variance

    CPICost Performance

    Index

    SPISchedule Performance

    Index

  • 8/8/2019 09 PROJECT PERFORMANCE MGT

    23/43

    Performance ManagementPerformance Management

    Earned ValueEarned Value

    Determine value of work

    completed attime now

    Or percentage times budget

    atcompletion (EV=

    PCxBAC), where PC is

    percentage complete

  • 8/8/2019 09 PROJECT PERFORMANCE MGT

    24/43

    Performance ManagementPerformance Management

    Cost VarianceCost Variance

    Earned Value (EV) minus

    Actual Cost (AC) shows the

    difference between theestimated cost of an activity

    and the actual cost of that

    activity

    EV-AC=CV

  • 8/8/2019 09 PROJECT PERFORMANCE MGT

    25/43

    Performance ManagementPerformance Management

    Cost Performance IndexCost Performance Index

    CPI = EV/AC

    If the CPI < 1 then the project

    is spending more than it isgetting in terms of value

    Corrective action needs to be

    taken else the project will

    make a loss or will run out offunds

  • 8/8/2019 09 PROJECT PERFORMANCE MGT

    26/43

    Performance ManagementPerformance Management

    Schedule VarianceSchedule Variance

    Earned Value (EV) minus

    Planned Value (PV) shows the

    difference between theschedule completion and

    actual completion to date.

    EV-PV=SV

  • 8/8/2019 09 PROJECT PERFORMANCE MGT

    27/43

    Performance ManagementPerformance Management

    Schedule Performance IndexSchedule Performance Index

    SPI = EV/PV

    If the SPI < 1 then the projectis behind schedule

    Corrective action needs to be

    taken to bring up to schedule

  • 8/8/2019 09 PROJECT PERFORMANCE MGT

    28/43

    Performance ManagementPerformance Management

    Estimate at Completion (Estimate at Completion (EACEAC))

    EAC = AC/PC (where PCis Percentage Complete

    atTime Now

  • 8/8/2019 09 PROJECT PERFORMANCE MGT

    29/43

    Performance ManagementPerformance Management

    Estimate to Complete (ETC)Estimate to Complete (ETC)

    ETC = EAC-AC

  • 8/8/2019 09 PROJECT PERFORMANCE MGT

    30/43

    Performance ManagementPerformance Management

    ExampleExample

    WP BAC PV PC EV AC SV CV EAC ETC

    1 9000 9000 100 9000 11000 0 -2000 11000 0

    2 2000 2000 100 2000 2000 0 0 2000 0

    3 10000 6000 50 5000 7000 -1000 -2000 14000 7000

    4 6000 6000 67 3996 4000 -2004 -4 6006 2006

    5 4000 4000 50 2000 2500 -2000 -500 5000 2500

    6 6000 0 0 0 0 0 0 6000 6000

    7 8000 0 0 0 0 0 0 8000 8000

    8 4000 2000 50 2000 1500 0 500 3000 1500

    9 8000 4000 25 2000 3000 -2000 -1000 12000 9000

    10 4000 4000 100 4000 3500 0 500 3500 0

    29996 34500 -7004 -4504 70506 36006

    ExampleExample

  • 8/8/2019 09 PROJECT PERFORMANCE MGT

    31/43

    Performance ManagementPerformance Management

    ExampleExample

    WP BAC PV PC EV AC SV CV EAC ETC

    1 9000 9000 100 9000 11000 0 -2000 11000 0

    2 2000 2000 100 2000 2000 0 0 2000 0

    3 10000 6000 50 5000 7000 -1000 -2000 14000 7000

    4 6000 6000 67 3996 4000 -2004 -4 6006 2006

    5 4000 4000 50 2000 2500 -2000 -500 5000 2500

    6 6000 0 0 0 0 0 0 6000 6000

    7 8000 0 0 0 0 0 0 8000 8000

    8 4000 2000 50 2000 1500 0 500 3000 1500

    9 8000 4000 25 2000 3000 -2000 -1000 12000 9000

    10 4000 4000 100 4000 3500 0 500 3500 0

    29996 34500 -7004 -4504 70506 36006

    ExampleExample

  • 8/8/2019 09 PROJECT PERFORMANCE MGT

    32/43

    Performance ManagementPerformance Management

    Ho do you stay on track?Ho do you stay on track?

    What is a Project Monitoring System

    Examples of Progress Reports

    What is the Project Control Process and why is it useful?

    How do I Monitor Time Performance

    The shortcomings of monitoring Systems

    Earned Value Management

    Integrated Cost/Schedule System

    Project Baselines

  • 8/8/2019 09 PROJECT PERFORMANCE MGT

    33/43

    Performance ManagementPerformance Management

    Dwight EisenhowerDwight Eisenhower

    Plans are useless planning is indispensible

  • 8/8/2019 09 PROJECT PERFORMANCE MGT

    34/43

    Performance ManagementPerformance Management

    When plans changeWhen plans change

    EVA allows experts in the field tochange original baseline durationsand costs because new information

    tells them the original estimates arenotaccurate

    EVA uses actual costs-to-date plus anefficiency index to project final costsin large projects where the originalbudget is unreliable

  • 8/8/2019 09 PROJECT PERFORMANCE MGT

    35/43

    Performance ManagementPerformance Management

    An Integrated SystemAn Integrated System

    System

    Planning

    Control

    WBS

    Network

    Diagram

    Schedule Bar

    Chart

    Monitorand

    Review

    Corrective

    Action

  • 8/8/2019 09 PROJECT PERFORMANCE MGT

    36/43

    Performance ManagementPerformance Management

    An Integrated SystemAn Integrated System

  • 8/8/2019 09 PROJECT PERFORMANCE MGT

    37/43

    Performance ManagementPerformance Management

    Ho do you stay on track?Ho do you stay on track?

    What is a Project Monitoring System

    Examples of Progress Reports

    What is the Project Control Process and why is it useful?

    How do I Monitor Time Performance

    The shortcomings of monitoring Systems

    Earned Value Management

    Integrated Cost/Schedule System

    Project Baselines

  • 8/8/2019 09 PROJECT PERFORMANCE MGT

    38/43

    Performance ManagementPerformance Management

    Baseli e isananchor oint for easuring erfor anceBaseline isananchor oint for easuring erfor ance

  • 8/8/2019 09 PROJECT PERFORMANCE MGT

    39/43

    Performance ManagementPerformance Management

    To change the baselineTo change the baseline change control processchange control process

  • 8/8/2019 09 PROJECT PERFORMANCE MGT

    40/43

    Performance ManagementPerformance Management

    To change the baselineTo change the baseline change control processchange control process

  • 8/8/2019 09 PROJECT PERFORMANCE MGT

    41/43

    Performance ManagementPerformance Management

    To change the baselineTo change the baseline change control processchange control process

  • 8/8/2019 09 PROJECT PERFORMANCE MGT

    42/43

    Performance ManagementPerformance Management

    To change the baselineTo change the baseline change control processchange control process

  • 8/8/2019 09 PROJECT PERFORMANCE MGT

    43/43