National Cement Company. P.S.C Dubai
LOESCHE SYMPOSIUM:
Cost saving as result of conversion from HFO to pulverized coal
Presented by: Eng. Radwan MouakatDüsseldorf, 25.09.2014
National Cement Company P.S.CDubai
Dubai City in year 1976
Dubai City Today
National Cement Co. P.S.C Dubai Works
Today in the heart of Dubai City
National Cement Co. Works in brief
Commissioned wet process in 1978
Converted to dry process in 1987
National Cement Co. Works in brief
Current capacity 4000 tpd
Original heat source was HFO
Conversion to coal firing since 2012
Fuel price from 2004 to 2012 (USD/TON)
Consumption of fuel per ton of clinker
Rising price of heavy oil and gas
Difficult market conditions
Strong impact on production costs
Cost reduction challenge
Decision – cost saving conversion from HFO to pulverized coal
Challenges
For cost saving as result of conversion from HFO to pulverized coal
Selection of the Coal grinding CompanyA Strategic Decision
?
Selection
Coal Grinding Plant Concepts and
Considerations
Concepts and Considerations
Lay-out and operation of coal handling facilities
Safety regulations
Modern fuel efficient kiln types
Drying of coal
Grindability of coal meal fineness
Mill for grinding of coal
Design latest regulations regarding constructions
Processing
Arrangement of coal grinding plant:
There are various factors have to be taken into considerations when arranging a coal grinding plant: Quality of coal
Supply of hot air for drying
Type and numbers of Kiln
Investment cost
Maintenance cost
Reliability
Conditions
Based on evaluation of these matters, decision can be made regarding the following: Direct, semi-direct or indirect firing
Inert or non-inert operation
Ball mill or Vertical Roller Mill
Bag Filter or EP for possible dedusting
Instrumentation & automation of the coal grinding plant
Filters and coal mills silos
Conditions
Coal stacking and storing
Other Safety precautions, the following tips should be considered:
Feeding arrangement, to ensure steady feed of raw coal to the mill.
Horizontal surfaces, where coal may settle. Ducts should have proper inclinations (min. 60° upwards and 45°downwards.)
Gas velocity in ducts (min. 20m/sec.)
Conditions
Mill separator, duct between separator and filter, filter and coal meal silos should be fitted with pressure relief valve, which must open to the outside air, not inside the buildings.
The installations mechanical and electrical equipment to be well maintained for future maintenance.
Buildings and equipment should be kept clean
Common sense: To consider the operation, designed plant which is in accordance with current industrial standards, to reduce risks.
Conditions
Lower energy consumption
Higher drying capacity
Output capacity can easily be varied within a wide range
corresponding to the fuel consumption of the Kilns
Fast feed output response
Accept larger feed sizes up to 80mm
Lower noise level
Requires less building volume
Benefits
Larger quantity of air to be dedusted
Less suitable for abrasive coal. Wear parts are
expensive and replacement causes downtime.
Sensitive to variations in feed rate and feed
quantity
Challenges
A Strategic Decision
Selection of the Coal grinding Company
LOESCHE GmbH
For cost saving as result of conversion from HFO to pulverized coal
Result of selection and evaluation
Beginning in 2012
One Compact System, comprising grinding, drying and classification
Stable running conditions, hence easy to operate
Easy to maintain and reduced specific wear rates
Highly energy efficient
Very flexible grinding system
Why LOESCHE Vertical Roller Mill
Mill Type: LM 28.2 D
Feed Material: Hard Coal
Throughput (design): 40 tph
Product Fineness: 12%R90μm
Drive Capacity: 600 kW
Commissioned:2012
LOESCHE Coal Mill in the City of Dubai
National Cement Co. Coal Mill Building
Numbers represent the year 2007/08
Share Vertical Mills for Coal Grinding
LOESCHE Mill Flow-sheet
Dosing Unit DRW 4.12/2 DRW 4.12/2
Type Rotor weigh feeder Rotor weigh feeder
Material Coal Dust Coal Dust
Capacity 16,2 t/h 17,8 t/h
Application Calciner Main Burner
Commissioning 02.05.2012 02.05.2012
Bulk Density 0,35 – 0,6 t/m3 0,35 – 0,6 t/m3
Distance of Feed Line
70m 123m
Pulverized Coal Dosing
S.NO SPECIFICATIONS UNIT SPECIFICATION YEAR2013
YEAR2014
01 TOTAL MOISTURE % MAX - 8.50 7.58 8.93
02 INHERENT MOISTURE % MAX - 3.50 1.60 1.86
03 GROSS CALORIFIC VALUE Kcal/kg
MIN - 6400 6438.11 6549.72
04 SULPHUR % MAX - 1.00 0.60 0.61
05 ASH CONTENT % MAX - 16.00 15.91 15.01
06 VOLATILE MATTER % MAX - 26.00 28.02 29.00
Raw coal specifications
Coal price for the year 2012
Market prices for coal 2013 & 2014
COAL CONSUMPTION PER TON OF CLINKER FROM JUNE - DEC. 2012
0.115
0.12
0.125
0.13
M. TON
M. TON 0.1241 0.1249 0.1248 0.1211 0.1244 0.1243 0.1277
JAN. FEB. MARC APRIL MAY JUNE JULY AUG. SEPT. OCT. NOV. DEC.
CONSUMPTION OF COAL PER TON OF CLINKER FOR THE YEAR 2013
0.115
0.12
0.125
0.13
0.135
M.TON
M.TON 0.1263 0.1296 0.1281 0.1290 0.1312 0.1326 0.1265 0.1266 0.1225 0.1237 0.1225 0.1229
JAN. FEB. MARC APRIL MAY JUNE JULY AUG. SEPT. OCT. NOV. DEC.
CONSUMPTION OF COAL PER TON OF CLINKER FROM JAN. - JULY 2014
0.12
0.125
0.13
0.135
M.TON
M.TON 0.1255 0.1244 0.1324 0.1283 0.1250 0.1252 0.1252
JAN. FEB. MARC APRIL MAY JUNE JULY AUG. SEPT. OCT. NOV. DEC.
Coal consumption
Alternative fuels
Such fuels as wood chips, sludge, used car tyres or even
house hold garbage ….. etc.
The application of these fuels are becoming more and more
interesting. There is no doubt that in the future the cement
kiln will be used more and more as incineration plant for
disposal of hazardous waste.
In this regard, we are nowadays using carbon dust which is
available in Aluminium industry with reasonable Price ,
also full unit of used car tyres.
Alternative fuels
S.NO SPECIFICATION UNIT YEAR-2013 YEAR-2014
CARBONDUST GRADE-I
CARBONDUST GRADE-II
CARBONDUST GRADE-I
CARBONDUST GRADE-II
01 GROSS CALORIFIC VALUE
Kcal / Kg 7562.26 3586.11 7534.07 4095.51
02 SULPHUR % 1.69 1.07 1.48 1.30
03 ASH CONTENT % 3.01 45.68 2.85 38.23
Carbon Dust Specifications
Alternative fuels
%
Alternative fuels
PERCENTAGE OF COAL AND ALTERNATE FUEL FROM JUNE 2012 TO JULY 2014
94.90 91.45 92.40
5.10 8.55 7.60-5.0010.0015.0020.0025.0030.0035.0040.0045.0050.0055.0060.0065.0070.0075.0080.0085.0090.0095.00100.00
2012 2013 2014
COALALTERNATE FUEL
ENERGY COST IN USD/TON OF CLINKER
-
10.00
20.00
30.00
40.00
50.00
60.00
Series1
Series1 51.70 13.67 13.30 13.16 12.79
FUEL OIL COA L COA L + CA RB ON DUST COA L + TYRESCOA L + CA RB ON DUST +
TYRE
Energy cost
ENERGY COST IN USD/TON OF CLINKER
10.00
11.00
12.00
13.00
14.00
15.00
Series1
Series1 13.67 13.30 13.16 12.79
COAL COAL + CARBON DUST
COAL + TYRES COAL + CARBON DUST + TYRE
Energy cost